Improving the Quality of Construction, Reducing Costs, and

Facilitating On-time ProjectCompletion

COMMISSIONINGFOR THE NYCSCA

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 2: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 2/30

Airpath expertise in:

HVAC Design

HVAC Testing and Balancing

Building Systems Commissioning

Retro-Commissioning (HVAC Investigations and Studies)

HVAC Design Basis Consulting

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 3: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 3/30

20 Years of Superior TAB,Design, and Commissioning

 New York State Licensed ProfessionalEngineering Firm

 N.E.B.B. Certified Commissioning

 N.E.B.B. Certified Test & Balance

Other Professional membership affiliations: USGBC, ASHRAE, IGSHPA

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 4: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 4/30

ENGINEERING AND STAFF TRAINING 

NEBB Professionals and Supervisors:

Certified annually with up to 24 hours of 

classroom training and seminars related toNEBB disciplines

NEBB Technicians and Balancers:

Certified every 2 years with

mandatory classroom training

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 5: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 5/30

Quality Construction

If you could improve the total quality of your schools

and facilities without extra costs, would you?

How much do Job Site Construction problems cost youin delays ?

Do you see a deviation in actual installation vs. design

specifications? What is the outcome on your costs,schedule, performance and compliance?

What impact does a poorly performing building haveon students and faculty? How readily does thatbecome your problem?

What should the NYCSCA be considering?

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 6: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 6/30

A Trained Eye on Implementation

Do hard deadlines for School openings leave your projects with

gaping holes?!?

Non-Compliance of School HVAC Systems

Months or years of continued costly fixes

Improper installation Unseen or mis-evaluated design issues

Poor air quality

Misdirected HVAC facility operations

Lack of proper perspective and understanding of the finished project

Under the gun…………………$...$$....$$$$

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 7: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 7/30

Overview of the Commissioning

Process

Commissioning is the administrative act of:

Documentation of NYCSCA Performance Requirements

Evaluation and Documentation of Design Basis and

Contract Drawings

Verifying and Documentation of system installation.

Verifying and Documentation of Equipment Start Up

Verifying and Documentation of Functional performance.

Verifying and Documentation of interactions betweensystems and subsystems

Training of Operations and Maintenance.

Commissioning is an Administrative Plan with components customized for

each project to match the requirements of that project.NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 8: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 8/30

Commissioning Scope

Commissioning is a flexible process configured to

match each individual project.

Design parameter Documentation

Plan & Spec. Commissioning Review

Installation Verification (FIV)

Operational Performance Tests (OPT)

Functional Performance Tests (FPT)

As Built Verification

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 9: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 9/30

System Scope

HVAC Systems

Control Systems

Process Systems

Fire & Smoke Controls

Plumbing Systems

Electrical Systems

Security Systems

Integrated Systems

Other Systems

Page 10: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 10/30

Project Types

New Construction Restructuring

Energy Retrofits

I.A.Q. Investigation HVAC Studies

Page 11: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 11/30

Functional Performance

Testing (FPT)6

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Commissioning

Field Coordination• Coordinate Responsibilities

• Coordinate Schedule

Pre-functional Testing

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

1 5

3

4

8

9

• System Performance Testing

Operational Performance

Testing (OPT)• System Start Up Verification

7

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

PRE DESIGN PHASE – DOCUMENT OWNERS PROJ ECT REQUIRMENTS

Page 12: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 12/30

Functional Performance

Testing (FPT)

5

Commissioning

Field Coordination• Coordinate Responsibilities

• Coordinate Schedule

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

4

2

3

7

8

• System Performance Testing

Operational Performance

Testing (OPT)

• System Start Up Verification

6

2

Design Phase• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

1 •Assist Design team in developing documents that are:

•accurately reflecting Owner’s functional needs

•operable, commissionable and maintainable

• clearly communicate to the Contracts their 

obligations to participate in and support the

commissioning process

•DPC process involves:

•Development of the owners design intent

•Commissioning Reviews of Design Documents

•Development of Commissioning Specifications

Design Phase

Commissioning Processes

Page 13: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 13/30

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report Functional Performance

Testing (FPT)

5

Commissioning

Field Coordination• Coordinate Responsibilities

• Coordinate Schedule

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

14

3

4

8

9

• System Performance Testing

Operational Performance

Testing (OPT)

• System Start Up Verification

6

Commissioning Processes

2 •Scope•Schedule

•Check List Format

•Training Format

Commissioning Plan

Page 14: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 14/30

Commissioning Plan

Identify

Parties

• Owner / General Contractor / Sheet Metal Contractor

• Plumbing Contractor / Electrical Contractor / Fire & Safety

• Piping Contractor / Controls Contractor / Other RelevantContractors

Systems

• Mechanical Systems / Domestic Water Systems / Plumbingand Waste / Controls / Fire and Safety

Scope

• Description of all systems being commissioned

• Catalog of all scheduled equipment to be commissioned

Page 15: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 15/30

Commissioning Processes

Example: Plan and Specification Checklist Report Forms

Page 16: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 16/30

6

7

• System Performance Testing

Functional Performance

Testing (FPT)

5

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

15

4 8

Operational Performance

Testing (OPT)

• System Start Up Verification

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

CommissioningField Coordination

•Coordinate Responsibilities

•Coordinate Schedule3

Page 17: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 17/30

Functional Performance

Testing (FPT)

6

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Commissioning

Field Coordination

• Coordinate Responsibilities

• Coordinate ScheduleCommissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

15

37

8

• System Performance Testing

Operational Performance

Testing (OPT)

• System Start Up Verification

6

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

Pre-Functional

Testing (PFT)

•Installation Verification

•Test Verification4

Page 18: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 18/30

Commissioning Processes

• Installation Verification

• Test Verification

Field Installation Verification (FIV) Example Report Forms

Page 19: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 19/30

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Commissioning

Field Coordination

• Coordinate Responsibilities

• Coordinate Schedule

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

1

3

4

8

9

7

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

Functional Performance

Testing (FPT)6•System Performance Testing

5

OperationalPerformance Testing

(OPT)

•System Start Up Verification

Page 20: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 20/30

Commissioning Processes

Example: Operational and Performance Testing Report Forms

Page 21: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 21/30

Functional Performance

Testing (FPT)

6

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Commissioning

Field Coordination

• Coordinate Responsibilities

• Coordinate Schedule

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Post Acceptance Test

• Off Season Test

15

3

4

8

9

• System Performance Testing

Operational Performance

Testing (OPT)

• System Start Up Verification

Facilities Training

•Turn Over Documents

•System Procedures7

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

Page 22: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 22/30

Commissioning Processes

Example: Training Verification Report Form

Page 23: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 23/30

• System Performance Testing

7

Functional Performance

Testing (FPT)

6

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Commissioning

Field Coordination

• Coordinate Responsibilities

• Coordinate Schedule

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Post Acceptance Test

• Off Season Test

Facilities Training

• Turn Over Documents

• System Procedures

15

3

4

Commissioning Report

•Activity Reports

•Check Lists

8

9

Operational Performance

Testing (OPT)

• System Start Up Verification

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

Page 24: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 24/30

Functional Performance

Testing (FPT)

6

Commissioning Processes

Commissioning Plan•Scope

•Schedule

•Check List Format

•Training Format

Commissioning

Field Coordination

• Coordinate Responsibilities

• Coordinate Schedule

Field Installation

Verification (FIV)

• Installation Verification

• Test Verification

Commissioning Report

• Activity Reports

• Check Lists

Facilities Training

• Turn Over Documents

• System Procedures

15

3

4

8

Post Acceptance Test

•Off Season Test9

• System Performance Testing

Operational Performance

Testing (OPT)

• System Start Up Verification

7

2

Design Phase

• Basis of Design Evaluation

• Drawing Evaluation

• Pre-Submittal Report

Page 25: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 25/30

Benefits of Commissioning

Improved Contract Enforcement

Improved Quality of Documentation

Reduced O & M Costs Improved System Performance

Improved School Comfort

Reduced Liability & Warranty Claims

Improved I.A.Q. (Indoor Air Quality) Future Expansion or Renovation Made Easier

Greater Faculty and Student Satisfaction

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 26: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 26/30

Commissioning Costs

100,000 sq. ft. School

$4,000,000 HVAC Design and Construction Costs

Estimated 250 Ton HVAC System

Commissioning Cost

2% - 2.5% of HVAC Construction Cost

$80,000 - $100,000

Traditionally included in HVAC Cost

Final cost will depend on the detail of the scope of work 

Average cost of commissioning is approximately

2 to 3 times the test and balance costs.

COST EXAMPLE

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 27: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 27/30

Minimum Costs of Not Commissioning

First Year Problem Detection and Solutions Operational problems not discovered at start up

30% of one operator 

Second Year Problem Detection and Solutions Operation problems not discovered at start up

15% of one operator 

Out of Warranty Expense Repair of items not discovered during the 1st year 

Early repair due to incorrect operation

Early repair due to incorrect maintenance Energy Inefficiency

Lack of Calibration & Tuning

Lack of Proper Operation

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 28: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 28/30

Implementing Commissioning

Specification –  Commissioning Administrator (Division 13000 or 18000)

 –  Mechanical Commissioning Support Responsibilities (Division 15000) –  Electrical Commissioning Support Responsibilities (Division 16000)

 –  Vendor Commissioning Support Responsibilities (Equipment Division)

Contract with Owner –  Furnished as an Allowance (Preferred way to guarantee quality)

NYCSCA BUILDING SYSTEMS COMMISSIONING

Page 29: NYCSCA_PPT_Commisioning

7/28/2019 NYCSCA_PPT_Commisioning

http://slidepdf.com/reader/full/nycscapptcommisioning 29/30

 “Quality is Value” 

“The Agony of Poor Quality lives

long after the Ecstasy of a Cheap Price.”

NYCSCA BUILDING SYSTEMS COMMISSIONING