nvar standard contract form changes - january 2015

23
Matthew Rathbun Chair, 2014 NVAR Standard Forms NVAR Standard Forms Update January 2015 Release

Post on 19-Oct-2014

325 views

Category:

Education


0 download

DESCRIPTION

To see a video summary, visit: http://elitescoop.com/nvarformsupdate2015/ ‎ This year I had the privilege or chairing the NVAR Standard Forms Committee, which is a collection of the some of the brightest Realtors and attorneys that I've ever had the opportunity to work with. We started the year with the opportunity to evaluate not only the standard forms that we use, but why we are structured the way we are.

TRANSCRIPT

Page 1: NVAR Standard Contract Form Changes - January 2015

Matthew Rathbun Chair, 2014 NVAR Standard Forms

NVAR Standard Forms Update

January 2015 Release

Page 2: NVAR Standard Contract Form Changes - January 2015

The Regional Sales Contract is now the Residential Sales Contract.

Jurisdictional Addendum Merged

Page 3: NVAR Standard Contract Form Changes - January 2015

Why The Change? • Obsolete Model • Reduce Length of Contract • Reduce Confusion • Reduce Liability

Page 4: NVAR Standard Contract Form Changes - January 2015

The New Residential Sales

Contract

Page 5: NVAR Standard Contract Form Changes - January 2015

“Offer Date” and “Contract Date”

Page 6: NVAR Standard Contract Form Changes - January 2015

Specified Financing ¶2

Set Dollar Amount

Percentage of Loan Amount

Page 7: NVAR Standard Contract Form Changes - January 2015

Specified and Alternative Financing ¶2 & ¶15

• Buyer may change lender without seller’s permission • To keep the protection of the financing

contingency when changing loan type(Conventional to VA for example): Buyer must get written permission of the seller (with correct addendum)

Page 8: NVAR Standard Contract Form Changes - January 2015

EMD – Do You Have It Or Will It Be Delivered?

3. DEPOSIT Purchaser’s deposit (“Deposit”) in the amount of check and/or $ by note due and payable on shall be held by (“Escrow Agent”). Purchaser has delivered OR will deliver the Deposit by days after Date of Ratification.

Page 9: NVAR Standard Contract Form Changes - January 2015

“Delivery” Simplified ¶6

No more courtesy copies!

Page 10: NVAR Standard Contract Form Changes - January 2015

POA and Condo Delivery ¶8 & ¶9 • Seller (according to regulation) may choose delivery method

of documents from the association • Purchaser must now provide their preferred address for each

method of delivery

Page 11: NVAR Standard Contract Form Changes - January 2015

Access To Property ¶11

Page 12: NVAR Standard Contract Form Changes - January 2015

Wood Destroying Insects ¶ 19

• Changed to match common practice and requirement of many lenders to inspect for more than just termites.

Page 13: NVAR Standard Contract Form Changes - January 2015

Title ¶21

• If Title can’t be delivered at Closing

• Old Language gave 30 Days • New language creates 2 options

• Void Contract • Negotiation Extension

Page 14: NVAR Standard Contract Form Changes - January 2015

Adjustments ¶26 – Fuel in Supply Tanks

• Old language was ambiguous regarding the disposition of fuel in tanks, especially regarding leased tanks.

• New language “Unless otherwise agreed to in writing, any heating or cooking fuels remaining in supply tanks(s) at Settlement will become the property of the Purchaser.”

Page 15: NVAR Standard Contract Form Changes - January 2015

Title Insurance ¶4 and 30(G) and

• Changes to reflect CFPB New Rules

• Purchaser has the choice of getting a quote for the standard or enhanced title insurance coverage.

Page 16: NVAR Standard Contract Form Changes - January 2015

Improvements to Existing Forms

Page 17: NVAR Standard Contract Form Changes - January 2015

Update to Release of Contract and Deposit K1116

• Added language to disclose to Seller and

Purchaser that release of contract between the parties does not

release any liability to the Broker(s).

Page 18: NVAR Standard Contract Form Changes - January 2015

Useful Information About RE Transactions K1297

• Added Language to reflect the COE protected class of Gender Identity

• New paragraph explaining what FIRPTA[Foreign Investment in Real Property Tax Act] is and what duties the parties may have and to seek legal advice

Page 19: NVAR Standard Contract Form Changes - January 2015

Conventional, FHA and VA Contingency Addenda K1339, K1340, K1359

• Deed of Trust Paragraph moved to Price and Specified Financing

• Seven Non-exclusive reasons for Default have been removed

• Seller Subsidy paragraph has been given the simpler name

• Conventional Finance Addendum updated to reflect VA and FHA which compels Purchaser to show written statement in cases of low appraisal.

Page 20: NVAR Standard Contract Form Changes - January 2015

Walk-Through Inspection – K1210

Language added to clarify Broker nor Settlement Agent shall be liable for breach

any repair agreement.

Unless otherwise specified, all repairs are to be performed by a contractor licensed to do the type of work required. Neither Broker nor Settlement Agent shall be liable for any breach of any agreement made by Purchaser and Seller above.

Page 21: NVAR Standard Contract Form Changes - January 2015

(Only One) New Form

Page 22: NVAR Standard Contract Form Changes - January 2015

New Form – K1376

Page 23: NVAR Standard Contract Form Changes - January 2015

Training opportunities have been scheduled across the

region.

For more information go to: go.nvar.com/NewFormChanges