nuclear operating company - nuclear regulatory commission · 2015. 12. 23. · nuclear operating...

68
Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas 77483 , July 15, 2009 U7-C-STP-NRC-090074 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 South Texas Project Units 3 and 4 Docket Nos. 52-012 and 52-013 Response to Request for Additional Information Attached are responses to NRC staff questions included in Request for Additional Information (RAI) letter numbers 76 and 89 related to Combined License Application (COLA) Part 2, Tier 2, Section 6.2 and Appendix 3B. Attachments 1, 2, and 3 are responses to the RAI questions listed below. The responses to these RAI questions are supplements to previous responses. These supplemental responses provide all of the information requested in the RAIs. RAI 06.02.01.01.C-1 RAI 06.02.01.01 .C-2 RAI 06.02.01.01 .C-8 There are no commitments in this letter. If you have any questions regarding these responses, please. contact me at (361) 972-7206, or Bill Mookhoek at (361) 972-7274. STI 32503104

Upload: others

Post on 28-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Nuclear Operating Company

South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas 77483 ,

July 15, 2009

U7-C-STP-NRC-090074

U. S. Nuclear Regulatory CommissionAttention: Document Control DeskOne White Flint North11555 Rockville PikeRockville, MD 20852-2738

South Texas ProjectUnits 3 and 4

Docket Nos. 52-012 and 52-013Response to Request for Additional Information

Attached are responses to NRC staff questions included in Request for Additional Information(RAI) letter numbers 76 and 89 related to Combined License Application (COLA) Part 2, Tier 2,Section 6.2 and Appendix 3B.

Attachments 1, 2, and 3 are responses to the RAI questions listed below. The responses to theseRAI questions are supplements to previous responses. These supplemental responses provide allof the information requested in the RAIs.

RAI 06.02.01.01.C-1RAI 06.02.01.01 .C-2RAI 06.02.01.01 .C-8

There are no commitments in this letter.

If you have any questions regarding these responses, please. contact me at (361) 972-7206, orBill Mookhoek at (361) 972-7274.

STI 32503104

Page 2: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

U7-C-STP-NRC-090074Page 2 of 3

I declare under penalty of perjury that the foregoing is true and correct.

Executed on-7,1'

Mark A.McBurnettVice President, Oversight and Regulatory AffairsSouth Texas Project Units 3 & 4

jet

Attachments:

1. Question 06.02.01.01.C-2. Question 06.02.01.01.C-23. Question 06.02.01.01.C-8

Page 3: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

U7-C-STP-NRC-090074Page 3 of 3

cc: w/o attachment except*(paper copy)

Director, Office of New ReactorsU. S. Nuclear Regulatory CommissionOne White Flint North11555 Rockville PikeRockville, MD 20852-2738

Regional Administrator, Region IVU. S. Nuclear Regulatory Commission611 Ryan Plaza Drive, Suite 400Arlington, Texas 76011-8064

Kathy C. Perkins, RN, MBAAssistant CommissionerTexas Department of Health ServicesDivision for Regulatory ServicesP. 0. Box 149347Austin, Texas 78714-9347

Alice Hamilton Rogers, P.E.Inspections Unit ManagerTexas Department of Health ServicesP. 0. Box 149347Austin, Texas 78714-9347

C. M. CanadyCity of AustinElectric Utility Department721 Barton Springs RoadAustin, TX 78704

*Steven P. Frantz, Esquire

A. H. Gutterman, EsquireMorgan, Lewis & Bockius LLP1111 Pennsylvania Ave. NWWashington D.C. 20004

*George F. Wunder*Stacy Joseph

Two White Flint North11545 Rockville PikeRockville, MD 20852

(electronic copy)

*George Wunder* Stacy Joseph

Loren R. PliscoU. S. Nuclear Regulatory Commission

Steve WinnEddy DanielsJoseph KiwakNuclear Innovation North America

Jon C. Wood, EsquireCox Smith Matthews

J. J. NesrstaR. K. TempleKevin PolloL. D. BlaylockCPS Energy

Page 4: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1Page 1 of 36

RAI 06.02.01.01.C-1:

QUESTION:

Section 6.2.1.1.3: The staff found the containment analyses in support of the certified ABWRdesign to be acceptable based on the use of the GESSAR methodology and confirmatorycalculations by the staff. It is the staff s understanding that the applicant plans to replaceGESSAR with the GOTHIC computer program. It is also the staff s understanding thatthe GOTHIC code was adapted to employ models and assumptions outlined in the NEDO-20533 reports. Please, provide:

- GOTHIC input deck/description for the STP ABWR DBA containment analyses,

- detailed description of how the models and assumptions presented in the NEDO-20533reports were incorporated into the GOTHIC model, and

- reference for qualification and/or benchmarking of GOTHIC to be used as an acceptable toolfor performing the STP ABWR DBA containment analysis.

RESPONSE:

1 st Bullet Item:In response to the request of the first bullet in this RAI, the input parameters for the GOTHICpressure/temperature containment model are provided in RAI 06.02.01.01 .C- 1 Table 1, whichwas previously transmitted to NRC in STPNOC Letter U7-C-STP-NRC-090014 dated February19, 2009. The non-proprietary version of this response was transmitted to the NRC in STPNOCLetter U7-C-STP-NRC-090010 also dated February 19, 2009.

2nd Bullet Item:Westinghouse (WEC) has prepared a containment Pressure/Temperature (P/T) report that hasbeen submitted to the NRC in STPNOC Letter U7-STP-NRC-090067 dated June 30, 2009. Thisreport, WCAP-17058, describes the WEC approach for adapting the GOTHIC code to employmodels and assumptions outlined in the ABWR DCD and NEDO-20533. The WCAP provides adetailed comparison of the DCD approach using NEDO-20533 and the WEC method, andevaluates the impact on the analysis results of the few unavoidable modeling differences due tocertain features in the GOTHIC code. The WEC method of analysis is benchmarked against theDCD analysis. The report addresses the modeling updates as described in Part 7 STD DEP 6.2-2of Rev 2 of the STP 3 & 4 COLA.

The- analysis for calculation of pool swell, including pool swell height, velocity, bubble pressureand wetwell airspace pressure which is also affected by the modeling updates described above,

Page 5: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1Page 2 of 36

will be addressed in a separate departure and will be removed from the STD DEP 6.2-2 scope.Details of this departure and analysis are described in the response to RAI 06.02.01.01 .C-6 inAttachment 2 to STPNOC Letter U7-C-STP-NRC-090033. This response will be supplementedon July 31, 2009.

Consistent with this approach, COLA Rev 2 will be revised as follows : (1) Part 7 STD DEP6.2-2 will be revised to describe the updated containment analysis, reference WCAP-17058, andrefer pool swell changes to a new departure for Appendix 3B. Part 7 tables will also be updatedto reflect this change; (2) Technical Specification 3.6.1.1, 3.6.1.2 and 3.6.1.4 Bases will berevised in both Part 2 Chapter 16 and in Part 4 to reflect the revised peak containment pressure,and (3) Part 2 Tier 2 Section 6.2 text, Table 6.2-1 and Figures 6.2-3, 6.2-4, 6.2-6, 6.2-7, 6.2-8,6.2-12, 6.2-13, 6.2-22, 6.2-23, 6.2-24, and 6.2-25 will be revised or deleted as necessary toreflect updated containment temperatures and pressures.

COLA changes described above are provided in the markups in this response. These changeswill also be provided in COLA Rev 3. Changed portions of the COLA Rev 2 are shown withgray highlighting. Note that the markups provided in this response supersede those provided inSTPNOC Letter U7-C-STP-NRC-090033 submitted on April 20, 2009.

3rd Bullet Item:

The qualification and benchmarking of GOTHIC for the ABWR containment P/T analysis isprovided in WCAP-17058, as described above. The benchmarking performed shows closeagreement between the WEC results and the DCD results. In addition, the GOTHIC program isused to calculate pressure and temperature in the containment for the Feedwater Line Break(FWLB) and Main Steam Line Break (MSLB) using the DCD modeling assumptions with theupdates identified in STD DEP 6.2-2. These results are in close agreement with the results fromNEDO-33372 which incorporated the analysis methodology and assumptions from the DCDwith the updates incorporated.

Page 6: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1Page 3 of 36

6.2.1.1.2.1 Drywell

STD DEP 6.2-2

The maximum drywell temperature occurs in the case of a steamline break(469.720 64- 17~3.2 0t)'. Although this exceeds the ABW Rdrywell ~design temperature(1,71. 10C), it only exceeds it by 2.10 'and only for about 2 seconds:. Due tothermal inertia,components in the drywell would not have sufficient tim~e to reach the' design limiittemperature.

The maximum drywell pressure occurs in the case of afeedwater line break (248.-72-4 281.8kPaG). The design pressure for the drywell (309.9 kPaG) includes 4-6%-approximately 22I1d% margin.

6.2.1.1.2.2 Wetwell

STD DEP 6.2-2

The wetwell chamber design pressure is 309.9 kPaG and design temperature is0-3.-9-0 104 0C.

&der normal pl ant operating conditions,; the maximum, suppression pool wate~r andwetwelL airspace temperature is 350C or less. Under blowdo dw

Y~lto. vn rLOCA, the hiitiaf peoo water tempe I aotfre maH~t me tdH tidxeimnHIv6

ý6+[-]'C. The contirnued rele~ase 6f dec~ay- heat after~ the initial blowdown following4 anisolation event or LOCA may.rsl nsprsi.o oltmeaue shg s97. 95C.TThe Residual HeatiRemoval,(RHR)S•j Stem is. avatlable in the Suppresston PooCooling modeto control the pool temperature. Heatis *removed via •lte RHR•heat exchanger(s) to theRetor Building Cooling Water (RCG )Sysivemi andfinally to the ReactrService Water(RSW) System.The R~rRSystem is, described inSubsect ion5. 4.7.

6.2.1.1.3.3 Accident Response Analysis

STD DEP 6.2-2

The containment design pressure and temperature were established based onenveloping the results of this range of analyses a".. diN,; p•erib. d

For the ABWR pressure suppression containment system, the peak containmentpressure following a LOCA is vepy relatively insensitive to variations in the size of theassumed primary system rupture. This is because the peak occurs late in theblowdown and is determined in very large part by the transfer of the noncondensible

Page 7: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1Page 4 of 36

gases from the drywell to the wetwell airspace. This proeess is n.t sign .fean..yinfluen.ed by the siz, of the break. In addition, there is a15%. an approximately*iTO- % margin between the peak calculated value and the containment design pressure thatwill easily accomodate small variations in the calculated maximum value.

yy2:•:."

Tolerances assoc.'niated withq f-brictn an inn s i tagatgi'n . eutintea Ju.4iechpstulaed break areas being.5% greater thani the values presented in this ehapter Based onthe abeve, these as built variationis would .not ivalidate the plat sf. . anal.sis presentedithis ehapter and Chapter 15 ofanalysis.

the RPV nozzles have been taken into account in this

6.2.1.1.3.3.1.1 Assumptions for Short-Term Response Analysis

STD DEP 6.2-2

The response of the Reactor Coolant System and the Containment System during the short-term blowdown period of the accident has been analyzed using the following assumptions:

(1) The initial conditions for the FWLB accident aresueh that syte enr..imax imized and the sys.temmas is minimized maximize the containmentpressure response. That is:

(a) The reactor is operating at 102% of the rated thermal power, whichmaximizes the post-accident decay heat.

(b) The initial suppression pool mass is at the le94ie• ina1 high water level.

(c) The initial wetwell air space volume is at the high water level.

(d) The suppression pool temperature is the operating maximumtemperature value.

(4) The main steam isolationvlat onIva rte( sstgatlosn 0after theaeeidenf. The nfain-steamt isolaýtion galves aM s -t closing at ,Ss'after thýaccident. They are fu, lelosed in the shortestpossible time (at 3.5 s) following elosureinitiation- The turbine stop valves are closed in 0.2 seconds after reactortrip/turbine trip (RT/TT). By assuming rapid closure of these valves, the RP V ismaintained at a high pressure, which maximizes the calculated discharge of high energywater into the drywell.

(5) The vessel depressurization flos' rates are ealeulated using Moedy,?'shomogeneoust equ~iibrium model (W4)fr the eiritieal break glw__frce

62 The vessel, depressurization fPow rates are calulted using ~oody• s

hcmogen~~uilfbiummdel 1HA~o the eitiey h !k flow critic'alfomde(Reference 6.2-2). The break area en the PcPVside for this study is shown in Figure 6.During the invent.o. depletion p.eriod, subeoled blowdown e.eur.s and theeffective break- area at saturated eonditions is mueh less than the aetual area.The detailed eakeulational method is -provided in Referenee 6.2 1.

At J

Page 8: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment IPage 5 of 36

Reaetor vessel internal heat trans-fir is medeled by dividing the vessel aninternals into six metal nodes. A seventh node depends en the fluid(saturated or subeooled liguidb, saturated steam) eovering the node at the

tm.The assumptions include:-

(a The eenteir of gavioy of each node is speeoed as the elevation of thatnode.

(h) AM1SSof water, in systemT -Vinntr (cxc ept for HPGF and feediwater) H

J J J• • 01 "

,n:: .iw In n19 : F404 :rnornv

(c) Initial thermal poewer is 102% of rated p9ower at steady, state conditions.with corr-e',esponding heat balance parameteirs which cor-respond toturbine cont.rol valve constantpressure of 6.75 Mfai.

(d) Pump heat-, fuel relaxation, and metal water, reaction heat are added tothe AWS44A1S 5.1 decay heat curve plus 20% margin.

(e) Initial vessel pressure is 7.31 AMPaAi.

(6) There arF ,v f P 444 ~ c3 ~~CCSse;adth~JH~~~nhithe-AA".i One H1PCIF System?, one RCJC Sstwemf and As,& RH=IRSytma1-r a begin until 36 seconds after a break-, anthen the flow rate is a functioen of the vessel to wetivell difftirential pressure. Rated HPCPFflow is 182 ms/h per system at 8.12 MPaD and 727 mA/h, per sstem at 0.59 MPaD.Rate PAR flow is 954 m3/h at 0.28 AL~aD with shutoff head of 1.55 MWaD. Rated R~flow is 182 m3. . with reactor pressure betA.ee. 8..12 .. G and 1..0.4 .aG, and syemshut.s down at 0.3< n Paf,•, Influence of dhesithe EGGS systems is minimal since thetime interval analyzed for short-term is approximately the same time as theresponse time of associated systems iniections into the RPV.

(8) The witw vell airspace temperature is allowed to exceed the suppression pooltemperature as determined by,, a mass and enertý' balance onte

7Teiic c/arN i ,lmeaueialoetoexceed. the 'suppression pool

ternperatzfrecis deteirmined'b am~a~hss andenergy balance on the airspace.. Net-Used

(9,) Wetwell and drywell wall-atd-vall and structure heat transfer areae ignored.

(10) Actuation of SR Vs is modeled.

(11) Wetwell-to-drywell vacuum breakers ar-e-not medeledde pj4*t 6niii th..... v .......... _t...... are modeled but donot open.

(12) Drywell and wetwell sprays and RHR cooling mode are not modeled.

(13) The dynamie paek99Fessure model is used.Not Used

(14) Initial drywell conditions are 0.107 A•a• , 5o-- ka'-'. 07••Pa-, 5 7,C and 20%relative humidity.

Page 9: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1Page 6 of 36

(15) Initial wetwell airspace conditions are 0.!07 MPa0I6.5kPg %0717MPa, 35°C and100% relative humidity.

(16) The dryell is modeled as a singe node. 411 brealc.flow into the di.. ell ishomog.eneously mixed with the dr..... e!! inventory. . vThe dywell, is modeled cs asmnlenode.A.l//break flow into~ the di-w-ell -is ,h6mog~e~oiýslyt)ii d~vitA the drywell

inenor. Not. Used

(17) Because of the unique . ontainment geometry of the ABWR, the inertatmo..here in the l.wer dryw.ell would not transf- erto te we.. ell util thepeak pressure in tMe dryvell is achieved. Figure 5.2 :5 shows the actual easeand the model assumption. Because the lower drywvell is connec-te1-d to the6dry.vell connecting vent; no gas can escape from the lower drywell untilth..ea*c preSsure o .curs. nIs situat1on can he .. mparea 1o a ÷ o÷.. w11 ....

oeigis excposed to an atmosphere with an inceain prlure. Th4e

the upper- drjý4sell pressure starts decreasing. A eons ervat4ve creditfoer

transfer o50% of the lower dry4...ell cnt.ent. s ito Mhe we...ell was taken) Not Used.

6.2.1.1.3.3.1.2 Assumptions for Long-Term Cooling Analysis

STD DEP 6.2-2

Following the blowdown period, the ECCS discussed in Section 6.3 provides water for

core flooding, containment spray, and long-term decay heat removal. The containmentpressure and temperature response during this period was analyzed using the following

assumptions:

(1~e G 9;; pup H r avilal s-spc d 46-& ubection 6.3.1.1..2 (except on

~'pr~sflerfedii a brken feedw-ater. line, hin easeoef a F"LB. There. r

two HPCF. Systems, one RCIC System, and three:RHR, Systems inrthe ABWR. All T!motor operated pump systems (HPCF and RHR) are assumed ito be availableft-o , Imaximize Pump heat into the'suppression pool Asinglefailure'of one RHR heat

f(2)I Te•ek SII/AzN)S- 51- 1979 decay heat plus 27sigma uncertainty. is used. Fission energ:lfuel relaxation heat, and pumpv•:heat are-included. -,-". , -

(3) ,ke~sppression pool the only m. dell....... ......... a. ail.b.e. in.the..ont.in..nt,ysem-volumne correspondst6 the low' water level:

(4~) Ifi r 10 mnt sthe P.HLR heat. exchager-s ar0 ra ormv

ree 11 e'ation? e~olitig ofthe supeso o1

wth t'i W-W ystem and

u4tim a t ey to t'hi RS W Sy t&M. This is ai '0s~at 6142 9-- t6io, sinc rthe

... od...........to....~....... . 3..2. . .Aer 30, minutes; one RHR heat ekchanqehLs actiated to remove energy via recirculation cooling of the suppression pool and

Page 10: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.c-.1 U7-C-STP-NRC-090074Attachment 1Page 7 of 36

iOie RHR heat exchanýger is activated to'remove energywa dvywel is.p a i theRCW System andultimately to the RSW System.

(6) The •lower dryellflo"ding 6

&eAri~ring 't4bbvo~hKaportioni of breakfioewflows into thlower dyv1!Thiz5 i~45 lower. w~y~~lioig;ill Pr~abayoccur? ait aproimtlyLlto 120 s1eon4l time pe,4tdis notfimodeled. Wittdicrhlhis-from the lower drywell is assumed tob'e mixed with the suppression pool tocalculate the bulk average temperature.

(7,) A1t 70sgd,:h4)wt~sciietap becomnes 418. 7J/g (10'3an Structuralheat sinks aremodeled JD the contairment systemý.

6.2.1.1.3.3.1.4 Long-Term Accident Responses

STD DEP 6.2-2

In order to assess the adequacy of the containment system following the initialblowdown transient, an analysis was made of the long-term temperature and pressureresponse following the accident. The analysis assumptions are those discussed in Subsection6.2.1.1.3.3.1.2:

Te short t-er IIP6-1-, Peak (2268.,7 ,PaG) ef Fi•g•re 6.2 6 is thepeapressueefo rthe whole transient. Figure 6.2-8 shows temperature time histories for the suppression pool,wetwell, and drywell temperatures. The peak pool temperature (999950 C) is reached at

6 seconds • -1.833 hours. jflhisis less than the suppression pool ieinperatur•Ivalue of 1 OO,'C whichis-used in the net positiv6 suction head available 'NPSHMcalculations.

6.2.1.1.3.3.2 Main Steamline Break

STD DEP 6.2-2

Flow from the condenser side of the break continues for 0.5 seconds, at which time the MSIVsbegin to close on high flow signal. A valve stroke time-of 5 4.5 seconds is used for the MSIVclosure. Flow from the condenser side of the break is Ie ramped down to zero between 0.5and - 5 seconds. The effective break area used fr the AML is. shown in Figure 6.2 10. . Moe detaileddsersiptions of the AML break model are provided in thej follwing:

6.2.1.1.3.3.2.1 Assumptions for Short-Term Response Analysis

STD DEP 6.2-2

The response of the reactor coolant system and the containment system during theshort-term blowdown period of the MSLB accident is analyzed using the assumptionslisted in the above subsection and Subsection 6.2.1.1.3.3.1. 1 for the feedwater line

Page 11: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1Page 8 of 36

break, with the.•folwing . xeeptioc. :except feedwater mass flow rate for a MSL breakwas assumed to be 130% NBRfoGr the case where no operator actionis assume•dtocontrol'water levei. Additional cases were4run With feedwater mass flowrate

requlated to control RPV, water eveL or with no feedwater flow based on an assumedloss of, offsite power.

6.2.1.1.3.3.2.3 Short-Term Accident Response

The maximum drywell temperature (-4-" 1,73.2 0C) is predicted to occur for the steamlinebreak. The MSLB with two-phase blowdown starting when the RPVO \wateir level is atorbelo the main steamline nozzle provides the highest peak drywell temperature. The peakdrywell air temperature is 4-9, 173.20 C, Weehich, its ab•0 v-ethe design value of171.1 °C, and is the limiting one as compared to the FWLB peak temperature. As notedin

~etion 6.2.1.1.2;1 hspa acltd rwl temnperature exceeds the ~desivf limiit ~for only2'secondsri The peak drywell pressurefor the MSLB remains below that for the FWLB, whichbecomes the most limiting.

6.-2.2.3.1 Syývs-t-em ~"-dOper~ation andSequence of Events

(4) (--' taznmhfe iit e oanzuttdfc 10 mi4ts4#is~~etQtestin 430.26)6L) 6ntainment cooling is initiated after 3mO inutegs.

6.2.8 References

STD DEP 6.2-2

Page 12: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1Page 9 of 36

Table 6.2-1 Containment Parameters

Design

Parameter

Design

Value

Calculated

Value1

1. Drywell pressure

2. Drywell temperature

3. Wetwell pressure

4. Wetwell temperature

" Gas Space" Suppression pool

309.9 kPaG

171.10 C

309.9 kPaG

9-7.2100 OC

266.7 ka-G240 281.8 kPaG17,4o i7 2°-C...... 6 •173.20C 2

1 •9. 23 kPaG

989_98.6 0C9679q 99.50oc

2Calculated values from ~Ref 6.2-5Calculated dr~vwelIImaximum tempi-ieature exceeds design temp~erature for o~nI&2,seconds. See discussion in Section 6.2.1 .1 .2. 1.

Page 13: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1

B 316 CONTAINMENT SYSTEMS

B 3.6.1.1 Primary Containment

U7-C-STP-NRC-090074Attachment 1

Page 10 of 36

APPLICABLESAFETY ANAL YSES

STD DEP 6.2-2

SURVEILLANCEREQUIREMENTS

STD DEP 16.3-44

The safety design basis for the primary containment is that it mustwithstand the pressures and temperatures of the limiting DBA withoutexceeding the design leakage rate.

The DBA that postulates the maximum release of radioactive materialwithin primary containment is a LOCA. In the analysis of this accident, itis assumed that primary containment is OPERABLE such that release offission products to the environment is controlled by the rate ofprimarycontainment leakage.

Analytical methods and assumptions involving the primary containmentare presented in References 1 and 2. The safety analyses assume anonmechanistic fission product release following a DBA, which forms thebasis for determination of offsite doses. The fission product release is, inturn, based on an assumed leakage rate from the primary containment.OPERABILITY of the primary containment ensures that the leakage rateassumed in the safety analyses is not exceeded.

The maximum allowable leakage rate for the primary containment (La) is0.5% by weight of the containment air per 24 hours at the m, 6ximfUM

calculated peak containment pressure (Pa) of 0.-2-69 M12aG 274,62-428 1. 8) kPaG or 04-f 9 25 7% by weight of the containment air per 24hours at the reduced pressure of Pt of 444-144.8 MP-akPaG (Ref 1).

SR 3.6.1.1.1

Maintaining the primary containment OPERABLE requires compliancewith the visual examinations and leakage rate test requirements of 10CFR 50, Appendix J (Ref 3), as modified by approved exemptions.Failure to meet air lock leakage testing (SR 3.6.1.2.1), resilient sealprimary containment purge valve leakage testing (SR 3.6.1.3.76),] ,mainstea.. islati.n val.e leakage (SR 3.5.1.3.13), or hydrostatically testedvalve leakage (SR 3.6.1.3.4-21_) does not necessarily result in a failure ofthis SR. The impact of the failure to meet these SRs must be evaluatedagainst the Type A, Bi, and C acceptance criteria of 10 CFR 50, AppendixJ. The Frequency is required by 10 CFR 50, Appendix J (Ref 3), asmodified by approved exemptions. Thus, SR 3.0.2 (which allowsFrequency extensions) does not apply.

Page 14: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 11 of 36

STD DEP 16.3-45STD DEP 6.2-2

REFERENCES 1'ýDG Tet-2ýSeiin 6~.2.J WCAP- 1705,8, June 200.R

2. DCD Tier 2, Section 4J4.15.6.

3. 10 CFR 50, Appendix J.

B 3.6 CONTAINMENT SYSTEMS

B 3.6.1.2 Primary Containment Air Locks

STD DEP 6.2-2

APPLICABLESAFETYANALYSES

The DBA that postulates the maximum release of radioactivematerial within primary containment is a LOCA. In the analysis ofthis accident, it is assumed that primary containment is OPERABLE, suchthat release offission products to the environment is controlled by the rateofprimary containment leakage. The primary containment is designed witha maximum allowable leakage rate (La) of 0.5% (excluding MSIV leakage)by weight of the containment air per 24 hours at the calculated maximumpeak containment pressure (Pa) of 0.-269 MPaG 24- 281.8 kPaG (Ref 3).This allowable leakage rate forms the basis for the acceptance criteriaimposed on the SRs associated with the air lock.

B 3.6 CONTAINMENT SYSTEMS

B 3.6.1.4 Drywell Pressure

BASES

The information in this section of the reference ABWR DCD, including all subsections, isincorporated by reference with the following departure.

STD DEP 6.2-2

APPLICABLE SAFETYANALYSES

Primary containment performance is evaluated for the entire

spectrum of break sizes for postulated LOCAs (Ref 1). Among

Page 15: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 12 of 36the inputs to the DBA is the initial primary containment internal pressure(Ref 1). Analyses assume an initial drywell pressure of 5.20x] W3 MPaG.This limitation ensures that the safety analysis remains valid bymaintaining the expected initial conditions and ensures that the peakLOCA drywell internal pressure doesý not exceed the maximum allowableof 0.310 MPaG.

The maximum calculated drywell pressure occurs during &he r-aetbl.wd.wn . hase ef.t/i D.A, wvhieh isq deter-;mik-e•• to be afeedwaterline break. The calculated peak drywell pressure for this limiting event is0._2 40f 21: 281 .8 kPaG (Ref 1).

Page 16: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 13 of 36

Part 7, Section 2.2 Departures from the Generic Technical Specifications

STD DEP 6.2-2, Containment Analysis

Description

This departure updates the containment analysis for the ABWR DCD in twethreareas: (1) the modeling of flow and enthalpy into the drywell for the feedwaterfollowing a FWLB, an4 (2) the modeling of the drywell connecting vents for theFWLB and MSLB•, and (3) the modeling of decavheat. A more detailed description isshown below.

This depaturesals makes th'e' folloWing-chianges (1) it updatesý the suppression poolltemperatu i~timit from the DCD specified value of 97.2'C to a value 6f 100t, and

(2) it revises the assumed elapsed time between the start of •he LOCA and theinitiation of suppressi~on pool cooling .and containmnit spraysfrom 10) minute.ýto 3,0minutes.

In the ABWR DCD for the FWLB, the maximum possible feedwater flow rate wascalculated to be 164% of nuclear boiler rated .(NBR) flow, based on the response ofthe feedwater pumps to an instantaneous loss of discharge pressure. Since theFeedwater Control System would respond to the decreasing reactor pressure vessel(RPV) water level by demanding increased feedwater flow, and there was no FWLBlogic/mitigation in the certified ABWR design, this maximum feedwater flow wasassumed to continue for 120 seconds. This was based on the following assumptions:

(1) All feedwater system flow is assumed to go directly to the drywell.

(2) Flashing in the broken feedwater line was ignored.

(3) Initial feedwater flow was assumed to be 105% NBR.

(4) The feedwater pump discharge flow will coast down as the feedwater systempumps trip due to low suction pressure. During the inventory depletion period,the flow rate is less than 164% because of the highly subcooled blowdown.A feedwater line length of 100 meters was assumed on the feedwater systemside.

Subsequent to certification, analysis for plant-specific ABWRs revealed that theseassumptions were non-conservative.

For the containment analysis, the feedwater system side of the FWLB has been

Page 17: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 14 of 36changed using a revised time variant feedwater mass flow rate and enthalpy directlyto the drywell airspace. The time histories of the mass flow and enthalpy have beendetermined from the predicted characteristics of a typical feedwater system. Theconservatism of the assumed mass flow and enthalpies will be confirmed afterdetailed condensate and feedwater designs are complete. In addition, to provide addedassurance of acceptable results, safety related FWLB mitigation has been added to theSTP 3 & 4 ABWR design which adds safety related instrumentation to sense andconfirm a FWLB based on high differential pressure between feedwater linescoincident with high drywell pressure to trip the condensate pumps (Ref. STD DEPTI 2.4-2). This automated condensate pump trip is not credited in the containientanalysis.

The analysis is further revised to reflect the characteristics of the horizontal ventsconfiguration that had not been modeled in the DCD. The certified DCD model didnot properly simulate the horizontal vent portion of the vent system and incorrectlymodeled the vent clearing time. The revised STP 3 & 4 ABWR containment analysishas been performed using the drywell connecting vent (DCV) loss coefficients andconsidering the horizontal vents. The total DCV loss coefficient is based on asummation of losses.

Further analysis done based on ANSUIANS-5, l(1 e-994), 1 icluIdinthe 27sigmaincertainty. hasdetermined that the decay heat curves used in the DCD based6on best

estimate ANSI/ANS;-5. (1979) were non-conservative for long-term analysis•T oaddress this, the decay heatdicurves used in the revised containment analvsis werei'evisedto reflect the ANSI/ANS-5.4 (1979) with 2-sigma uncertainty included)

The revised containment analysis uses the GOTHIC code and is documented inWCAP-17058. The analysis uses the same ,ssumptions and inputs thmatwere used inthe DCD with conisiderationi ofthe' revised modlii as not~ed above. The reportdescribes all input assumptios baslining of the GTHIC cde esiifts to those usedin e DCD and lal containment time-dependentpessureanrd emeratureiresults. Thereport also evaluates the imp~act on the alyis reSitS'of the few unavoidablemodeling differences due to certain features in the GOTHIC code.

Theimpact of the revised pressure and t t results n pool -swellvelocity andheight described iný AppendiX 3B4is evaluateddin aneW departure which- is STD DEP313-2.

Technical Specification 3.6.1.1, 3.6.1.2, and 3.6.1.4 Bases (Applicable SafetyAnalyses) are changed based upon the containment analysis. These changes showythe peak containment pressure (Pa) from the containment analysis.

Page 18: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 15 of 36

Evaluation Summary

This departure which updates the containment analysis for STP 3 & 4 does not affectTier 1, Tier 2*, or any operational requirements. However, it does affect the Bases forTechnical Specifications 3.6.1.1, 3.6.1.2, gid 3.6.1.4 - and thereforerequires NRC approval.

There is no impact on environmental qualification of equipment due to the higherpredicted drywell temperatures and pressures. The qualification of equipment is basedon the containment design pressures and temperatures. The calculated containmentpressure and temperature for both the FWLB and MSLB remain below the designvalues except for a two- second period W~heni the drVyve11 temperature exceeds' the"des i'gn 'temperature by 2.1VC for the MSLB. Due to thermalinertia, components in thedrywell ~would not have sufficient time to reach the design limit temperature in such ashort time.~

The change in the design suppression pool temperature lmit is to align the li•mit withihe NPSH calculation assumptions to determine that adecuate NPSH exists for theECCS pumps. These calculations represent the limiting' condition for determimngma'imumi-allowable suppression pool temperature. These 'calculatlons use a1suppression pool temperature of 100'C. Therefore,,the allowable design limimtfor thepeak suppression pool temperature is being changed to:'IO 0'C.:

,he; changee in assumed elapsedtime beteen, startof LOCAand initiation ofsuippression p'ool coolhiiiand conitainment sprays fromi 10 niiimtes to 30miniiutes isconservative relative to the D as heat remoival fromthese systems is not crediteduntil later iiithe accidenit sequene.ic jhis als bringsthe assump'ition for operatoraction•into alignment with current safe janaly-sisjoratices.

This departure was evaluated per Section VIII.C.4 of Appendix A to 1OCFR part 52and: I

(1) This exemption is not inconsistent with the Atomic Energy Act or any otherstatute and therefore is authorized by law. The design change and revisedcontainment analysis represents an improvement and therefore will notpresent an undue risk to the public health and safety. The change does notrelate to security and does not otherwise pertain to the common defense andsecurity.

(2) Special circumstance (iv) applies in that this represents a benefit in publichealth and safety. The more a4VncPd"d &mpletc analysisMethodincorporation of these modelin changesiaKwll a the useof an analysis method

Page 19: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C- 1 U7-C-STP-NRC-090074Attachment 1

Page 16 of 36which has been baselined to tie certified DCD analysis method provide a moreaccurate prediction of peak containment conditions post-accident. These resultsshow that the peak containment pressure ABWR and temperature conditionscalculated following an accident based on these improved analyses are belew-thedesigp ei acceptable. The FWLB mitigation, while not specifically credited inthe containment analysis, will provide added assurance that the revisedcontainment analysis results will remain conservative when detailed feedwaterand condensate system design and procurement work is completed.

As discussed above, the change satisfies the exemption criteria per the requirementsin 10 CFR 52 Appendix A Section VIII.C.4.

Page 20: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 17 of 36

10000

9000

8000

7000

6000

5000

" 4000

.2 3000

2000

1000

00 500 1000 1500

Time (sec)

2000

1

Figure 6.2-3 Feedwater Line Break Flow - Feedwater System Side of Break

Page 21: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 18 of 36

.0

0

UN-

eoa

700 -

S430

.200

20 20 ± L1 510

Timie(sec)

70

450

400

- 350 _E

250

200

150_

"' 100

50

0-

0500 1000 150 2000

Time (sec)

Figure 6.2-4 Feedwater Line Break Flow Enthalpy - Feedwater System Side ofBreak

Page 22: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 ,C- 1 U7-C-STP-NRC-090074Attachment 1

Page 19 of 36

:y wure b.2 6 1rrssure Kesvonse ofvYrmanv Containment ior I! cdwater- Lmc lirea

PRI(0

(13

0~

(0U)0~

0

0

(N

0

Time (sec)

Figure 6.2-6a Drywell Pressure Response for Feedwater Line Break

Page 23: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 20 of 36

C PR2

135

a)

0_

0

LOCD

0D

M

Cý)

0~

Time (sec)

,Figure 6.2-6b Wetweli Pressure Response for Feedwater Line Break

Page 24: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1.

Page 21 of 36

c TV1LO -C") I

LL

0._

(D

E

0CO

0CI)

LOC>

0(NJ

0

It

0

-i

I I I I I I I I0 10 20 30 40 50

Time (sec)

figure"6.2ý,;7a Temperature Response of [D l forFeedwater Line Break

Page 25: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 22 of 36

o TL2rv40Cclr

It-

a1)cQ.

Ea)

CCD

C\J

U")

C)

C)LO

C) I I I I I I I I I0 10 20 30 40 50

Time (sec)

,figure 6.2-7b Temiperature Response of Wetweli for Feedwater LineBreak

Page 26: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 23 of 36

Figure 6.2ý ~8 Thftper-atur-e 1'Tip MistofirVfter a Jedwater Lfine Break

Page 27: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1

oTVi

O-

LO

-C,4)LL t0

Ea)

00

00

0

0

U7-C-STP-NRC-090074Attachment 1

Page 24 of 36

J , I I I I I I

40 50

Time (sec)Eigure6.2-g8a:)rywll•:TemperatueTimeST istory.'" After a Feedwater Line Bre-

Page 28: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

-)

Question 06.02.01.01.C-1 l U7-C-STP-NRC-090074Attachment 1

Page 25 of 36Lo cv40CC)]

'0o IF

C"]

U-

Ui()

Ea)

0

to

0to

LOC"]

0 I I I I I i i i I . i C, , * , m I * *

0 10 20 3,0 40 50Xl e3

Time (sac)

Figure. . 2- 8b..Su pp ession _ e...... . .... A.f t r a Feed wvater Line B rea l•

Page 29: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 26 of 36

o TV2OJ

U-

(DC)

E

o

00

o

oý,FC

i i i I . I I I I . . . I I , I I I I , I I

10 20 30 40'

Time (sec)

,Figure 6.2-8c Wew&1 TiT~nperawle -Tlime History Afer-aFccdwater Line Brak-

Page 30: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1 U7-C-STP-NRC-090074Attachment 1

Page 27 of 36

Figur 6,2.2 l>P~sressw e HiF~e 14is for SfL

Page 31: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 28 of 36o PR1(0-

(D

C2.

oIC)

0

0

CD)

0

0

I

. . . .I I . . . .a I . . . . I . .

U 1U 20 40 .5

Time (sec)

Figure 6.2-2aDryweU. Pressure Time History for MSLB

0 PR2

(U

0.

O

LO

O)

O

- I- ..

//

-/

0 'I U 2U 3 ()Time (sec)

40

Figure e Tme History for MSFLB

Page 32: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 29 of 36

I CA 1-5 20 25

Tirise •cI

Page 33: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-1

o TVI0-

U7-C-STP-NRC-090074Attachment I

Page 30 of 36

LL

a,

CL

E(U

OCCO)

OC)

cj

o0

on

C)C-)

CO

T~ \

F1___________________

LO

O0 10 20 30_) 4U 50

Time (sec)

Figure 6.2-13a. Diywell Temperature Time Histlory_4 r MSLB

1C)

CN

cv40C

U-LI_

aI)

Ea)

U-)

LL-)

(0

Xl e3Time (sec)

Figure 6.2-13b Suppression Pool Temperature Time Histor forMSLB

Page 34: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 31 of 36

Fue .6. 2 -2,2 Biirek F" 1-owý x- 6 Rat-e- ano peii Enthalpy for- the. Fced*water Line'BreALFlo Com1ng from thcFdaerStm de N-ot Used

Page 35: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 32 of 36

00

w

0

.-j

-J

CO

5000

4000

3000 _zw

2000

1 L

'1000..

1~gu&6j~~raFlowRae Speifi Bnaap fo- th a-!_Flo crhiigfr-om the RV Sid~

Page 36: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 33 of 36

1.40E+04

1.20E+04

1.OOE+04

I 8.OOE+03

I 6.00E+03

4.00E+03

2.00E+03

O.OOE+000.0 100.0 200.0 300.0 400.0 500.0 600.0

Time (sec)

Figre 6.2-23~a Break f kI\NRte for the IFctdwter Line Break Flov\ coming io h -VS

1400o

12001

1000

800

600_

400_

200_

0 --40.0 100.0 200.0 300.0 400.0 500.0 600.0

Time (sec)

Figure 6.2-23b Break Flow Specific Enthalpy for, the Feedwater Line.Break Flow coming •fromih~e RPV Side

Page 37: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1

C)0

C)

LUI--

0LLw

CaIn

U7-C-STP-NRC-090074Attachment 1

Page 34 of 36

300 4100'

-5000

,-J46000I-

0..

CI

23000-

Lii0_.

r),

1000

FiLgure 0.2-24 Bretak Flowk i-ale Mid kifllikiph'alpkfr thilt lain SStieB~kwt TA A1A+'.> 7D d- +V T+

NzeNA U...,sed

Page 38: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1'

z

w

'0-jU-

w

16

14

12

10

8

6

•2

MSIV CLOSESAT 5.5 SECONDS

TWO-PHASEBLOWDOWNSTARTS

U7-C-STP-NRC-090074Attachment 1

Page 35 of 36

,300. 400:

5ý000

: 00

-7

ý3000I--

zuJ

a.o0

! I-2000

;0

XO(.556

1400 r

1200

1000

z

0LL

8 00

I-

z

w 400U)

-200

1 :2 3 4 5 100 T200 300 40 0

TIME(sFigfe 6.2 J Beaii Flow Rate and speeife ic Enta-,~ 'frt ai'SeAmline bek~t~~p

I hi 1d, trfngaOn c

Page 39: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-1 U7-C-STP-NRC-090074Attachment 1

Page 36 of 36

8000

7000

6000

5000E

4000

o3000U-

2000

1000

0

0.0 100.0 200.0 300.0 400.0 500.0 600.0

Time (sec)

700.0

Flgure 6.2-25a MSLB Short TermBreak low, V ide)

1400

1200

1000____ _

S800

S600 _____ _____ _____

400

200 ____ _

0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0

Time (sec)

fjgure 6.Short MSLBhh Break-Flow Enthalpy ,(RPV Side)

Page 40: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 U7-C-STP-NRC-090074Attachment 2Page 1 of 11

RAI 06.02.01.01.C-2:

OUESTION:

Section 6.2.1.1.3: The staff is preparing an STP ABWR MELCOR model in support ofperforming independent confirmatory analysis. The following information is needed fordevelopment of the MELCOR input file:- reactor vessel: water flow loss coefficient for the following junctions: downcomer to lowerplenum, lower plenum to core channel, lower plenum to core bypass, core channel to steamseparator, steam separators to downcomer,- reactor vessel: elevation of the main feed water spargers,- setpoint value of the Condensate Storage Tank (CST) level at which High Pressure CoreFlooder (HPCF) and Reactor core Isolation Cooling (RCIC) systems suction transfer from theCST to the Suppression Pool (SP),- setpoint value of the SP level at which HPCF and RCIC systems suction transfer from the CSTto the SP,- setpoint value of the reactor vessel pressure at which the low pressure permissive signal isgenerated to open the Low Pressure Core Flooder (LPCF) injection valve,- ADS valves opening sequence after receiving the ADS initiation signal,- a figure showing the feedwater line break flow from the feedwater system side of break(i.e., Figure 6.2-3 in STP COLA, Rev. 2 with the time axis varying from 0.0 to 5 hrs),- a figure showing the feedwater line break flow enthalpy from the feedwater system side ofbreak (i.e., Figure 6.2-4 in STP COLA, Rev. 2 with time axis varying from 0.0 to 5 hrs),- a figure showing the feedwater line break flow from the RPV side of break (i.e., Figure 6.2-23in ABWR DCD with time axis varying from 0.0 to 5 hrs),- a figure showing the feedwater line break flow enthalpy from the RPV side of break (i.e.,Figure 6.2-23 in ABWR DCD with time axis varying from 0.0 to 5 hrs),- a figure showing the main steam line break flow from the RPV side of break (i.e., Figure 6.2-24in ABWR DCD with time axis varying from 0.0 to 5 hrs),- a figure showing the main steam line break flow enthalpy from the RPV side of break (i.e.,Figure 6.2-24 in ABWR DCD with time axis varying from 0.0 to 5 hrs),- a figure showing the main steam line break flow from the piping side of break (0 to 5 hrs),- a figure showing the main steam line break flow enthalpy from the piping side of break (0 to 5hrs),- a figure showing the feedwater flow rate and enthalpy assumed for the MSLB accidentanalysis as described in section 6.2.1 of STP COLA, Rev. 2.

Page 41: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 -U7-C-STP-NRC-090074Attachment 2Page 2 of 11

RESPONSE:

The requested input parameter information (bullets 1-6) was provided to NRC in STP LetterU7-C-STP-NRC-090014 dated February 19, 2009.

The requested figures are provided with this response as follows:

* Figure 1 shows the feedwater line break flow from the feedwater system side of thebreak. As shown in the figure, the feedwater flow terminates at 30 minutes, thus the flowfrom 30 minutes to the requested 5 hour time is zero.

" Figure 2 shows the feedwater line break flow enthalpy from the feedwater system side ofthe break. As shown in Figure 1, the feedwater flow terminates at 30 minutes, thus theflow enthalpy from 30 minutes to the requested 5 hour time is zero.

* Figure 3a shows the short-term feedwater line break flow from the RPV side of the breakfrom 0 to 500 seconds.

0 Figure 3b shows the long-term feedwater line break flow from the RPV side of the breakfrom 500 seconds to 5 hours.

" Figure 4a shows the short-term feedwater line break flow enthalpy from the RPV side ofthe break from 0 to 500 seconds.

" Figure 4b shows the long-term feedwater line break flow enthalpy from the RPV side ofthe break from 500 seconds to 5 hours.

" Figure 5a shows the short-term main steam line break flow from the RPV side of thebreak from 0 to 600 seconds.

* Figure 5b shows the long-term main steam line break flow from the RPV side of thebreak from 600 seconds to 5 hours.

" Figure 6a shows the short-term main steam line break flow enthalpy from the RPV sidefrom 0 to 600 seconds.

* Figure 6b shows the long-term main steam line break flow enthalpy from the RPV sidefrom 600 seconds to 5 hours.

" Figure 7 shows the main steam line break flow from the piping side of the break from 0to 5.6 see, at which time the flow is zero.

" Figure 8 shows the main steam line break flow enthalpy from the piping side of thebreak from 0 to 10 sec, at wvhich time the flow is zero.

* Figure 9 is the feedwater line flow and enthalpy from 0 to 600 sec assumed for theMSLB accident from 0 to 600 sec.

No COLA revision is required as a result of this RAI response.

Page 42: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 U7-C-STP-NRC-090074Attachment 2Page 3 of 11

10000

9000

8000

7000

6000

5000

" 4000o 3000

2000

1000

00 500 1000 1500 2000

Time (sec)

Figure 1 - FWLB Break Flow Rate (Feedwater Side)

Page 43: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 U7-C-STP-NRC-090074Attachment 2Page 4 of 11

450

400

- 350E.2 300

250

_ 200

150C

W 100

50

00 500 1000 1500

Time (sec)

2000

Figure 2 FWLB Enthalpy (Feedwater Side)

Page 44: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-2 U7-C-STP-NRC-090074Attachment 2Page 5 of 11

1.40E•-04

1.20E+04

1.OOE+04

8.OOE+03

6.00E+03

E

.0

'U

ci:

4.00E+03

2.00E+03

O.OOE+00

0.0 100.0 200.0 300.0 400.0 500.0

Time (sec)

600.0

Figure 3a - FWLB Short Term Break Flow Rate (RPV Side)

3500

3000

2500

2000

1500

1000

500

00.0

2000.0 4000.0 6000.0 8000.0 10000.0 12000.0 14000.0 16000.0 18000.0

Time (sec)

Figure 3b FWLB Long Term Break Flow Rate (RPV Side)

Page 45: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-2 U7-C-STP-NRC-090074Attachment 2Page 6 of 11

1400

1200

1000

i 800

M 600

400

200

0

0.0 100.0 200.0 300.0 400.0 500.0

Time (sec)

600.0

Figure 4a - FWLB Short Term Enthalpy (RPV Side)

350

300

250

200

150

100

50

0.0 2000.0 4000.0 6000.0 8000.0 10000.0 12000.0 14000.0 16000.0 18000.0

Time (sec)

Figure 4b FWLB Long Term Enthalpy (RPV Side)

Page 46: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 U7-C-STP-NRC-090074Attachment 2Page 7 of 11

8000

7000

6000

5000E

4000

3000

2000

1000 _____ __________

0

0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0

Time (sec)

Figure 5a - MSLB Short Term Break Flow Rate (RPV side)

5000

4500

4000

-3500

E 3000

22500-

20000

"1500

1000 -

500

0

0.0 2000.0

I .

1*___________ ____________ ____________

I ____ ____ T ____

______ 1 1

4000.0 6000.0 8000.0 10000.0 12000.0 14000.0

Time (sec)

16000.0 18000.0

Figure 5b MSLB Long Term Break Flow Rate (RPV Side)

Page 47: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 U7-C-STP-NRC-090074Attachment 2Page 8 of 11

E

w-

1400

1200

1000

800

600

400

200

0

0.0 100.0 200.0 300.0 400.0 500.0 600.0

Time (sec)

700.0

Figure 6a - MSLB Short Term Enthalpy (RPV side)

1400 [

1200 [100 - - - _ _

800

-•600--

-i 400

- lit

0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Time (sec)

Figure 6b MSLB Long Term Enthalpy (RPV Side)

Page 48: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-2 U7-C-STP-NRC-090074Attachment 2Page 9 of 11

6000

5000

-4000

E

2 3000

u- 2000

1000

0

0.0 2.0 4.0 6.0 8.0 10.0 12.0

U,

Time (sec)

Figure 7 MSLB Break Flow Rate (Piping Side)

Page 49: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2 U7-C-STP-NRC-090074Attachment 2

Page 10of 11

A J•

E.0

I-.

0.'U

Lu

1 400

1200

800 ________

600

400-

200-

0

0.0 2.0 4.0 6.0

Time (sec)

8.0 10.0 12.0

Figure 8 MSLB Enthalpy (Piping Side)

Page 50: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-2

2500

2000

O 1500 .. . .

1000

u.U-

500

U7-C-STP-NRC-090074Attachment 2

Page 11 of 11

2000

ow - - - Enthalpy

1600

7n-- .--.-. - - 1200 >,

LU

800 "

")

400

0

500 6000 100 200 300 400

Time (s)

Figure 9 MSLB Feedwater Flow Rate and Enthalpy

Page 51: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-8 U7-C-STP-NRC-090074Attachment 3Page 1 of 18

RAI 06.02.01.01.C-8

QUESTION:

6.2.1.1.1 Design Basis - Supplement to RAI 06.02.01.01.C-2 : In support of performingindependent confirmatory analysis, the following are requested additional information:

(a) Reactor Pressure Vessel- Core channel flow rate during full power operation- Core bypass flow rate during full power operation- Loss coefficients for steam/water flow through the feedwater sparger and feedwater nozzle- Approximate elevation of the Reactor Internal Pump (RIP) suction- Design details of the core support plate (weight, thickness, diameter and distribution of

holes in the core plate)- Design details of the orificed and peripheral fuel supports (diameter of orifices and weight

and height of the fuel supports)- Length and inside diameter of control rod guide tubes- Dimensions of the control rod (lengths of SS sheathed blades and absorber tubes, thickness

of the blades, diameter of absorber tubes, and number of absorber tubes)- Weights of SS and B4C in each control rod- Weights of Zircaloy-4 and Zircaloy-2 in each fuel assembly- Outside diameter of control rod housing- Design details of the Top Guide (weight, thickness, diameter and distribution of holes in the

core plate)- Dimensions of the main steam line flow restricting nozzle- Loss coefficient for steam/water flow through the main steam line flow restricting nozzle- Discharge coefficient for steam/water flow through the main steam line flow restricting

nozzle

(b) Fuel- Weight of U02 per assembly- Pitch of the fuel assemblies (or spacing between the fuel assemblies)- Length of the fuel channel (Zircaloy-4 canister)- Fuel channel inside dimensions and wall thickness- Bottom elevation of the fuel channel- Length and material of the fuel assembly nose piece- Length of the active fuel- Elevation of the bottom of active fuel (BAF)- Diametrical gap between fuel pellet and cladding- Length of gas plenum- Fuel rod cladding thickness- Fuel rod outside diameter- Pitch of the fuel rods- Fuel pellet density- Fuel pellet diameter

Page 52: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 2 of 18

- Fuel pellet length- Flow area of fully open Main Steam Isolation Valve (MSIV)- Flow resistance of open MSIV- Discharge coefficient of open MSIV

(c) Engineered Safety Features- Flow area of fully open ADS valve- Loss coefficient and discharge coefficient for the fully open ADS valve- Setpoint value of the drywell pressure at which reactor trip occurs- Setpoint value of the main steam line steam flow rate at which reactor trip occurs- Setpoints for the closure of MSIV- Elevations and radial positions of the HPCF, LPCF and RCIC systems suction strainer in

SP- Elevations and radial positions of the SRV line quenchers in the SP- Elevation and radial position of the exit of RCIC turbine steam exhaust line the SP

(d) Feedwater Line Break (FWLB):- A figure showing the containment pressure and temperature response (i.e., Figures 6.2-6

and 6.2-7 in [reference 2] STP COLA with the time axis varying from 0.0 to 30 min)- A decay power curve in Fig. 6.3-11 of [reference 2] STP COLA is normalized with respect

to which power; operating power or 102 % of the operating the operating power?

(e) Main Steam Line Break (MSLB):- A figure showing the containment pressure and temperature response

(i.e., Figures 6.2-12 and 6.2-13 in [reference 2] STP COLA with the time axis varying from0.0 to 30 min)

RESPONSE:

The response to items (a) through (c) were previously transmitted to NRC in STPNOC LetterU7-STP-NRC-090038 on April 29, 2009. Table 1 and Figure 1 were provided as part of thatresponse and are not included here. The response to items (d) and (e) are provided herein.

(d) For the first bullet item, the requested FWLB figures and curves are provided inFigures 2 through 9. The figures provide results for both the short term (0-50 sec)and the long term (0-13.9 hours) analyses.For the second bullet item, the decay power curve in Fig. 6.3-11 is not used in thecontainment analysis but rather is used for the ECCS analysis. Consequently, thenormalized power level for that Figure would not have any bearing on thecontainment analysis results. The decay power curve used for the containmentanalysis is based on 102% power.

(e) The requested MSLB figures are provided in Figures 10 through 17. These figuresprovide results for both the short term and the long term analyses.

There are no revisions to the COLA as a result of this response.

Page 53: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8

o PR1

C -

U7-C-STP-NRC-090074Attachment 3Page 3 of 18

(_3U)

U,)U)L.10.

0

0C)

0M

0

Time (sec)

Figure 2 Time-Dependent FWLB Drywell Pressure (Short Term)

Page 54: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8

oPR1(01-

C)

0-

U7-C-STP-NRC-090074Attachment 3Page 4 of 18

40 50

0.)

(n'I)

0c)

0Cw

N

C

Time (sec)

Figure 3 Time-Dependent FWLB Drywell Pressure (Long Term)

Page 55: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-8

o PR2

C-

U7-C-STP-NRC-090074Attachment 3Page 5 of 18

€0U,

o0

C

C>

C

Time (sec)

Figure 4 Time Dependent FWLB Wetwell Pressure (Short Term)

Page 56: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8

o PR2CO--

0C-

00

CnCL)

0

0Cv)

0

0

U7-C-STP-NRC-090074Attachment 3Page 6 of 18

I I& 340)%3Time (sec)

Figure 5 Time Dependent FWLB Wetwell Pressure (Long Term)

Page 57: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 7 of 18

o TV1

C,)•o

CD0-

LI-

a)

C.

EW,

C)

C()

C)C'\)

0

LO

V_

IC)

C)

C)

LO

IC)

0D

Time (sec)

Figure 6 Time-Dependent FWLB Drywell Temperature (Short Term)

Page 58: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 8 of 18

o TV1U-)

I_

a)

cEE0)

0

0

CY)

0CLC)

to

IC)

CD0O

0_

Ct)

A

0 10 20 30 40)Re3

Time (sec)

Figure 7 Time-Dependent FWLB Drywell Temperature (Long Term)

Page 59: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-8

o TL2

C)

uCO

U-- _CL.

U7-C-STP-NRC-090074Attachment 3Page 9 of 18

0

0)

Time (sec)

Figure 8 Time-D~pendent FWLB Suppression Pool Temperature (Short Term)

Page 60: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 10 of 18

LL

Ea)F--

tOCN

toN-

0

LO

to,5.-

LO

to

c"J

C

to

LO

to

0

cv40C

0Xl e3

Time, (seFc)

Figure 9 Time-Dependent FWLB Suppression Pool Temperature (Long Term)

Page 61: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8

CPR1

CO

U7-C-STP-NRC-090074Attachment 3Page 11 of 18

CutJ)

a-a)

(I)(I)a)L.0~

0

0

C0

C\j

Time (sec)

Figure 10 Time-Dependent MSLB Drywell Pressure (Short Term)

Page 62: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8

PR1( --

U7-C-STP-NRC-090074Attachment 3Page 12 of 18

0.

09~

0'KIT

C~)0

C\-

o

Time (sec)

Figure 11 Time-Dependent MSLB Drywell Pressure (Long Term)

Page 63: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-8 U7-C-STP-NRC-090074Attachment 3Page 13 of 18

PR20CO

0

'0

0

C)

L..

(jD

-1

cL.

0

Time (sec)

Figure 12 Time-Dependent MSLB Wetwell Pressure (Short Term)

Page 64: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 14 of 18

0

C>

O

PR2

Q.

a)a)U.)

0C~)e0

CV)0>

Time (sec)

Figure 13 Time-Dependent MSLB Wetwell Pressure (Long Term)

Page 65: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01 .C-8

c "I'V1

CZ)

_ LOLL 04

U7-C-STP-NRC-090074Attachment 3Page 15 of 18

a,

n

a)

Ea,H

NN

0

Ct)

aO

Time (sec)

Figure 14 Time-Dependent MSLB Drywell Temperature (Short Term)

Page 66: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 16 of 18

T11

U_

(D

Q.EU)

QQ

LC)COJ

(NI0

LD)00

0

0

Xl e3Time (sec)

Figure 15 Time-Dependent MSLB Drywell Temperature (Long Term)

Page 67: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8 U7-C-STP-NRC-090074Attachment 3Page 17 of 18

o TL2

C)

LL

a,

Cu1.~0,0~

U)I-

00

0

C:)

C)"

0 10 20 30 40 50

Time (see)

Figure 16 Time-Dependent MSLB Mixed Mean Suppression Pool Temperature (Short Term)

Page 68: Nuclear Operating Company - Nuclear Regulatory Commission · 2015. 12. 23. · Nuclear Operating Company South Texas Proect Electric Generating Station P0 Box 289 Wadsworth. Texas

Question 06.02.01.01.C-8

o cv40CU-3C\jIr

U7-C-STP-NRC-090074Attachment 3Page 18 of 18

L.

0

Q_

E

CN(N

0

C)

to

C)

N"-C)

Co(N

0 10 20 30 40 50Xl e3

Time (sec)

Figure 17 Time-Dependent MSLB Mixed Mean Suppression Pool Temperature (LongTerm)