ntpc final report

Upload: sumit-garg

Post on 06-Apr-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Ntpc Final Report

    1/27

    SUBMI

    TTED BY:

    PALAK GOYAL

    08BEC232

    E

    CE FINAL YEAR

  • 8/3/2019 Ntpc Final Report

    2/27

    Acknowledgements

    Everything that happens in the world is an

    outcome of interaction of various factor, some of

    which are favorable while others are not. Always

    for a desired result, the number of favorable

    factors is more. This work is NO exception to thisfact. I acknowledge that Ive been fortunate

    enough to get the support, mentally and

    physically in everything that I do.

    First of all I would

    like to thank Shri Anup Roy choudhary (chairman

    NTPC, Korba) who led the entire team for

    functioning of each department in a modernizedand techno-commercial atmosphere to make the

    project touch such peaking performance. I would

    give special thanks to Mr. Bimal Shah (HR) and

    Mr.A.K.Singh (Sr Engg), for giving his very kind

    permission to undergo the training programme

    under the able guidance of NTPC engineers. All

    these people were of immense importanceregarding the knowledge and supports for the

    well furnished equipments.

    I greatly

    acknowledge the help and the mental strength

    provided by my entire family, VIT University and

    friends for encouraging me and providing meknowledge & guidance related with every

    department of NTPC, KORBA.

  • 8/3/2019 Ntpc Final Report

    3/27

    Contents

    1. INTRODUCTION TO NTPC

    2. ABOUT NTPC , KORBA

    3. IMPORTANT ELEMENTS

    COAL SOURCE

    WATER SOURCE

    LAND

    FINANCIAL FACETS

    HUMAN RESOURCE DEVELOPMENT

    ENVIRONMENT PROTECTION

    ASH UTILIZATION

    4. COAL HANDLING PLANT

    GRADING OF COAL

    TURBINE

    COOLING TOWER

    COAL CYCLE

    5. WORKING PRINCIPLE

    6. PRODUCTION OF ELECTRICITY

    7. GENERATOR AND TRANSFORMER

  • 8/3/2019 Ntpc Final Report

    4/27

    8. OIL SYSTEM

    9. GENERATOR PROTECTION

    10. DISTRIBUTION OF ELECTRICITY

    TRANSFORMER

    SWITCHYARD

    CIRCUIT BREAKER

    11. DEMINERAL PLANT

    12. ENVIRONMENT PROTECTION MEASURE

    13. EFFICIENCY

    14. CONCLUSION

    1. INTRODUCTION TO NTPC

    Established in 1975, NTPC the largest power company of

    the country, has been consistently powering the growth of

    India.With an installed capacity of 30,144 MW, it

    contributes 28.6% of the nations power generation. An

    ISO 9001:2000 certified company, it is worlds sixth

    largest thermal power generator and second most efficient

    in capacity utilization.Rated as one of the Best companies

    to work for India it has developed into a multi-location

    and multi-fuel Company over the past three decades. The

    emergence of Korba NTPC as one of the largest power

    station in the country with an installed capacity of 2100

    MW had put NTPC a step ahead in its Endeavour to meet

    the ever-growing demand of electricity in the country.

  • 8/3/2019 Ntpc Final Report

    5/27

    2. ABOUT NTPC- KORBA

    LOCATION:The Korba Project is located on western bank ofHasdeo River at a distance of approx. 10kms from Korba in the

    Korba District of Chhattisgarh.

    INSTALLED CAPACITY:

    Stage 1: Three 200 MW

    Stage 2: Three 500 MW

    Stage 3: One 500 MW (All in operation.)

    BENEFICIARY STATES:

    MADHYA PRADESH, CHHATTISGARH, DAMAN AND DIU,

    MAHARASHTRA, GUJRAT & GOA.

    3.IMPORTANT ELEMENTS:

    A.COAL SOURCE

    The coal is supplied by Gevra Mines of South Eastern Coal

    Fields through a

    34 km long Merry-Go-Round (M.G.R). Railway System. Annualcoal requirement for Stage-1 & 2 is 12 MMT. The average

    calorific value of the coal is approx. 3500 kcal/kg .

    MERRY-GO-ROUND (M.G.R) SYSTEM

    SILOS

  • 8/3/2019 Ntpc Final Report

    6/27

    TRACK HOPPER

    TOTAL TRACK LENGTH: 34.80 KM

    LENGTH OF LOAD LINE: 14.86 KM

    LENGTH OF EMPTY LINE: 19.94 KM

    TRACKHOPPER:-

    When a rake reaches trackhopper,unloading of coal is done

    manually by given a DC supply to each wagon.When a dc

    supply is given to a wagon ,its bottom gate opens and coal is

  • 8/3/2019 Ntpc Final Report

    7/27

    emptied into a trackhopper.Time taken for unloading each

    wagon is 20seconds. There are total 2 trackhoppers though

    only one works all the time . The 2nd trackhopper is used in case

    of failure operation of 1st trackhopper. It has a capacity of 3000

    tons.

    PADDLE FEEDER:-

    It is used to move coal from track hopper to bunker. These are

    situated below trackhopper and when wagon is emptied it cuts

    the coal into size

  • 8/3/2019 Ntpc Final Report

    8/27

    6 mines per unit.There are 3 units of stage 2 with Capacity 500

    MW and coal is taken from 9 mines per unit.

    STACK YARD:-

    Stack yard is the place where coal is stacked & reclaimed if

    needed. Its done by using Staker & Reclaimer. A stack yard

    consists of Bucket wheel and Boom conveyor. Capacity of stack

    yard is 7 ton. Hence, it can be used for 19-20 days.

    B.WATER SOURCE

    The huge requirement of this project is being met by right sideof Hasdeo River and Bango dam on the up-stream of the

    Hasdeo River. The daily water requirement for the station is as

    follows:

    Service Water & Fire water 46,600

    Cu.m/day

    Cooling Water 96,000

    Cu.m/day

    Processing 2,400

    Cu.m/day

    Domestic 10,000

    Cu.m/day

    Others(ash water)- Stage 1 25,000

    Cu.m/day

    Total

    80,000 Cu.m/day

    C.LAND

    The total 4,826 acres of land is required for the

    construction of plant including the land required for stage

    2 Ash Dyke. The detail of land acquired is as follows:

  • 8/3/2019 Ntpc Final Report

    9/27

    Area wise detail of land Land

    (in Acres)

    1. Main Plant and Existing Ash Dyke

    2601

    2. Permanent Township

    447

    3. M.G.R

    517

    4. Link Road

    35

    5. Stage 2 Ash Dyke

    1226

    Total

    4826

    D. FINANCIAL FACETS:

    1. PROJECT COST

    It involves total investment of Rs 1625.25 crores for

    its capacity of 2100 MW.

    2. FINANCIAL ASSISTANCE

    The Foreign Assistance available for this

    project includes:

    Description Unit AMOUNT

  • 8/3/2019 Ntpc Final Report

    10/27

    IDA Credit US $/Million 200.00

    OPEC Credit US $/Million 20.00

    IDACredit(W.Germany)

    US $/Million 316.40

    KFC Credit US $/Million 173.40

    E. HUMAN RESOURCE DEVELOPMENT

    The Human Resources Development has always been

    accorded supreme priority. In the context of NTPCsobjective of operating a highly capitalized industry, special

    emphasis has been laid towards training and development

    of its engineers, supervisors and technicians to keep up

    with the latest technological development in the power

    sector . It has always laid special emphasis on the training

    & development of its employees.

    F.ENVIRONMENTAL PROTECTION

    Realising the need to live with nature in harmony,

    maintenance of ecological balance has always been a

    priority. All the units have been provided with high

    efficiency Electrostatic Precipitation. More than 1.5 Million

    trees have been planted in & around the plant. Liquid

    Waste Treatment plant for treating ash water, Coal

    handling plant Effluents etc have been established.

    G. ASH UTILISATION

    NTPC has been giving top most priority for maximising Ash

    Utilisation. Ash is used for raising the Ash Dyke, issued to

    Cement Industries and for making bricks. Six bricks

    making plants each with a capacity of 10,000 bricks

    /machines/day has been installed inside the plant & is

    given to cooperative society for making bricks. More than

    1 million bricks are produced annually.

  • 8/3/2019 Ntpc Final Report

    11/27

    COAL HANDLING PLANT (C.H.P)Raw materials required for coal handling plant are Coal,

    Oil, Air and Water. Coal is the major source of energy.

    The flowchart representing the generation of electricity

    is shown below:-

    The Capacity of NTPC Thermal Power Plant is 21

    MW.

    Grading of Coal:-

    Serial no. Grade Calories per kg

    1 A >6200 Kcal/kg

    S W I T C H Y

    G E N E R A T O R

    G E N E R A T

    T U R B I N E

    B O I L E R

    P U L V E R I Z

    B U N K E R

    C R U S H E R

    T R A C K H O P

    M G R

    M I N E S

  • 8/3/2019 Ntpc Final Report

    12/27

    2 B 5600-6200 kcal/kg

    3 C 4490-5600 kcal/kg

    4 D 4200-4490 kcal/kg

    5 E 3360-4200 kcal/kg

    6 F 2400-3360 kcal/kg

    7 G 1300-2400 kcal/kg

    TURBINE:-

    It is a form of engine, which requires a suitable working fluid in

    order to function. When fluid flows through it, a part of energy

    is converted into required mechanical energy.Steam & gas

    turbine uses heat energy whereas water turbine uses pressure

    energy. The turbines are used at High Pressure, Medium

    Pressure and Low Pressure.

    COOLING TOWER:

    For 200 MW unit two CT pumps are provided having

    15000 m3/hr discharge capacity and speed of 500 rpm.

    Each Cooling tower has height 30m with 16 induced draft

    fans having 27000 m3/hr flow rate and cooling range up to

    10 oC.

    COAL CYCLE

    C.H.P Plant Bunker Feeder Pulverization millBoiler section

    Feeder: It is an induction motor driven device, which

    determines the Quantity of coal that should enter in the

    pulverize mill.

    Pulverization mill: Pulverization means exposing a

    large surface area to the action of oxygen.

    Working Principle: -

  • 8/3/2019 Ntpc Final Report

    13/27

    The working principle of a steam plant is based on

    Rankine cycle. Steam is the working medium as it is stable.

    A graph plotted between the temperature and the entropy

    would indicate the technical details of the working by the

    rankine cycle.

    PLANT FLOW DIAGRAM

  • 8/3/2019 Ntpc Final Report

    14/27

  • 8/3/2019 Ntpc Final Report

    15/27

    Meanwhile the heat released from the coal has been

    absorbed by the tube on the boiler walls. Inside the tube,

    boiler feed water is transformed by heat into the steam

    at high pressure and temperature.

    The steam super-heated tube passes to the turbine

    where it is discharged through the nozzles on the turbine

    blades. The energy of the steam, striking the blades,

    makes the turbine rotate.

    Coupled to the end of the turbine is the rotor of the

    generator a large cylindrical magnet, so that when the

    turbine rotates the rotor turns with it.

    The rotor is housed inside the stator having heavy coils of

    copper bars in which electricity is produced through the

    movement of the magnetic field created by the rotor. The

    electricity passes from the stator winding to the step-up

    transformer which increases its voltage so that it can be

    transmitted efficiently over the power lines of the grid.

    The steam which has given up its heat energy is changed

    back into water in the condenser so that it is ready for

    reuse. The condenser contains many long cooling tubes.

    The steam passing around the tubes looses the heat and

    is rapidly changed back to water.

    But the two sections of water (i.e. boiler feed water &

    cooling water) must NEVER MIX. The cooling water is

    drawn from the river but the boiler feed water must be

    absolutely pure, far purer than the water we drink.

    To condense the large quantities of steam, huge and

    continuous volume of cooling water is essential. In most of

    the power stations the same water is used over and over

    again. So, the heat which the water extracts from the

    steam in the condenser is removed by pumping the water

    out to the cooling towers.

    The cooling towers are simply concrete shells acting ashuge chimneys creating a draught of air. The water is

    sprayed out at the top of towers and as it falls into the

    pond beneath it is cooled by the upward draught of air.

  • 8/3/2019 Ntpc Final Report

    16/27

    The cold water in the pond is then circulated by pumps to

    the condensers. However, some of the water is drawn

    upwards as vapours by the draught and forms the familiar

    white clouds which emerge from the towers seen

    sometimes.

    Why should one bother to change steam from the turbine back

    into water if it has to be heated up again immediately? The answer lies in the law of physics which states that the

    boiling point of water is related to pressure. The lower the

    pressure, the lower the temperature at which water boils. The

    turbine designer want as low boiling point of water as possible

    because he can only utilize the energy of the steam when the

    steam changes back into water he can get NO more work out of

    it. So a condenser is built, which by rapidly changing the steam

    back into water creates a vacuum. This vacuum results in a

    lower boiling point which will give steam well below 100oC.

    GENERATORS AND TRANSFORMER:

    TURBO GENERATOR

    KVA 247000

    Power factor 0.85

    Stator voltage 15750

    Stator current 9050

    Rotor voltage 310

    Rotor current 2600

    RPM 3000

    Hz 50

    Phase 3

    Connection YY

    Coolant Water (stator)& hydrogen

    (rotor)

    Gas pressure 3.5kg/cm-sq.

  • 8/3/2019 Ntpc Final Report

    17/27

    TWO TYPES OF OIL SYSTEM:

    1.SEAL OIL SYSTEM Hydrogen in the generator is under very

    high pressure. Seal oil is used to seal the gaps so that hydrogendoesnt come out.

    2. LUBRICATION OIL SYSTEM- Pumps are used to circulate

    lubrication-oil inside the generator. Turbine lubrication oil

    system seeks to provide proper lubrication of turbo generator

    bearings.

    GENERATOR PROTECTION

    1.STATOR PROTECTION-The neutral of star connected

    winding is connected to primary of neutral grounding

    transformer, so that earth fault current is limited by over

    voltage relay.

  • 8/3/2019 Ntpc Final Report

    18/27

    STATOR PROTECTION

    2.DIFFERENTIAL PROTECTION- In case of phase-to-phase

    fault, generator is protected by longitudinal differential relay.

    DIFFERENTIAL PROTECTION

    WORKING:

    Under normal conditions or for a fault outside of the protectedzone, current I1 is equal to current I2 . Therefore the currents in

    the current transformers secondaries are also equal, i.e. i1 =

    i2 and no current flows through the current relay.

  • 8/3/2019 Ntpc Final Report

    19/27

    3. ROTOR PROTECTION-The Rotor winding is damaged by

    earth faults or open circuits. The field is biased by a dc voltage,

    which causes current to flow through the relay for an earth

    fault anywhere on the field system. It short circuits the rotor

    winding and therefore, produce an unsymmetrical field systemand unbalance force on the rotor. This causes vibration of the

    rotor and damage to the bearings. So rotor earth fault

    protection is provided to restrict the fault spreading.

    4. OVER SPEED PROTECTION- Mechanically over speed

    device that is usually in the form of centrifugally operated rings

    mounted on the rotor shaft, which fly out and closes the stop

    valves if the speed of the system increases by more than 10%.

    5. OVER VOLTAGE PROTECTION - It is provided with an over

    voltage relay. The relay is usually induction pattern. The relay

    open the main circuit break and the field switch if the over

    voltage persists. It uses just four components: a silicon

    controlled rectifier or SCR, a zener diode, a resistor and a

    capacitor.

    Working :When the zener diode voltage is reached, current

    will flow through the zener and trigger the silicon controlled

    rectifier or thyristor. This will then provide a short circuit to

    ground, thereby protecting the circuitry.

    DISTRIBUTION OF ELECTRICITY:-

    TRANSFORMER

    TYPES:

  • 8/3/2019 Ntpc Final Report

    20/27

    1. GENRATOR TRANSFORMER :- It is a step up

    transformer that gets its primary supply from generator

    and its secondary supplies the switchyard from where it

    is transmitted to grid. This transformer is oil cooled. The

    primary is connected in star and the secondary in deltaform.

    2. STATION TRANSFORMER:-This transformer has almost

    the same rating as the generator transformer. Its primary

    is connected in delta and secondary in star. It is a step

    down transformer.

    3. UNIT AUXILIARY TRANSFORMER:- It is a step down

    transformer. The primary receives from generator andsecondary supplies a 6.6 KV bus. This is oil cooled. These

    are 8 in number.

    4. NEUTRAL GROUNDED TRANSFORMER:- This

    transformer is connected with supply coming out of UAT

    in stage 2. This is used to ground the excess voltage if

    occurs in the secondary of UAT in spite of rated voltage.

    SWITCH YARD

    As we know that electrical energy cant be stored like cells, sowhat we generate should be consumed instantaneously. But as

    the load is not constant therefore, we generate electricity

    according to need i.e. the generation depends upon load. The

  • 8/3/2019 Ntpc Final Report

    21/27

    yard is the place from where the electricity is sent outside. It

    has both outdoor and indoor equipments.

    SINGLE LINE DIAGRAM OF 220KV SWITCH YARD:

    OUTDOOR EQUIPMENTS

    It includes BUS BAR, LIGHTENING ARRESTER, WAVE TRAP,

    BREAKER, CAPACITOR VOLTAGE TRANSFORMER, CORONA

    RING, EARTHING ROD, CURRENT TRANSFORMER, POTENTIAL

    TRANSFORMER and LIGHTENING MASK.

    INDOOR EQUIPMENTS

    It includes RELAYS and CONTROL PANELS.

    CIRCUIT BREAKER:

    Circuit breaker is an arrangement by which we can break the

    circuit or flow of current. A circuit breaker in station serves the

    same purpose as switch but it has many added and complex

    features. The basic construction of any circuit breaker requires

  • 8/3/2019 Ntpc Final Report

    22/27

    the separation of contact in an insulating fluid that serves two

    functions:

    1. It extinguishes the arc drawn between the contacts when

    circuit breaker opens.

    2. It provides adequate insulation between the contacts and

    from each contact to earth.

    The insulating fluids commonly used in circuit breakers are

    Compressed air, Oil which produces hydrogen for arc

    excitation, Ultra high vacuum, Sulphur & hexafluorides.

    LIGHTING ARRESTER:

    It saves the transformer and reactor from over voltage and

    over currents. Used in both primary and secondary of

    transformer and in reactors.

    A meter is provided that indicates:

    1. Green arrester is healthy

    2. Red arrester is defective

    In case of red, we first de-energize the arrester and then do

    the operation.

    AIR BREAK EARTHING SWITCH:

  • 8/3/2019 Ntpc Final Report

    23/27

    The work of this equipment comes into picture when we want

    to shut down the supply for maintenance purpose. This helps to

    neutralize the system from induced voltage from extra high

    voltage. The induced power is up to 2KV.

    BUS BAR:

    Bus bars generally are of high conductive aluminium or copper

    of adequate cross section located in air insulated enclosures &

    segregated from all other components.

    DEMINERAL PLANT

    INTRODUCTION: --Water is required in plant for many

    purposes like formation of steam, removal of ash, safety during

    fire etc. But the water required for the formation of steam

    should be perfectly devoid of minerals because if minerals are

    present in the steam and the steam strike the blades of

    the turbine, then due to high pressure, it produces scars or

    holes on the turbine blades.

    PURIFICATION OF WATER: -

    Water is purified in DM plant through a chain of processes as

    under: --

    Carbon filter Water taken from the river is first sent to

    the carbon filter for the removal of carbon contents in the

    water.

    Strong acid cation exchanger After passing through

    the carbon filter, water is sent to the strong acid cation

    exchanger, which is filled with the concentrated HCL. The

    acid produces anions, which gets combined with the

    cations present in the water.

    Strong base anion exchanger After this the water is

    sent to the strong base anion exchanger, which is filled

    with the concentrated NaOH. The base produces cations,

    which get combined with the anions present in the water.

  • 8/3/2019 Ntpc Final Report

    24/27

    Mixed bed exchanger Now the water is sent to the

    chamber of mixed bed exchanger where the remaining

    ions are removed. This is the last stage of purification.

    ENVIRONMENT PROTECTION MEASURES TAKEN BY

    NTPC:

    1. Electrostatic Precipitators: The ash left behind aftercombustion of coal isArrested in high efficiency Electrostatic Precipitators (ESPs) and

    particulate emission is controlled well within the stipulated

    norms. The ash collected in the ESPs is disposed to Ash Ponds

    in slurry form.

    2.Flue Gas Stacks:Tall Flue Gas Stacks have been provided

    for wide dispersion of the gaseous emissions (SOX, NOX etc)

    into the atmosphere.

    3.Low-NOX Burners: In gas based NTPC power stations, NOx

    emissions are controlled by provision of Low-NOx Burners (dry

    or wet type) and in coal fired stations, by adopting best

    combustion practices.

    4.Neutralisation Pits: Neutralisation pits have been providedin the Water

    Treatment Plant (WTP) for pH correction of the effluents before

    discharge into Effluent Treatment Plant (ETP) for further

    treatment and use.

    5.Coal Settling Pits / Oil Settling Pits: Coal dust and oil are

    removed from the effluents emanating from the Coal Handling

    Plant (CHP), coal yard and Fuel Oil Handling areas before

    discharge into ETP.

    6.DE & DS Systems: Dust Extraction (DE) and DustSuppression (DS) systems have been installed in all coal firedpower stations in NTPC to extract the fugitive dust released inthe Coal Handling Plant (CHP).

    7.Cooling Towers: Cooling Towers have been provided forcooling the hot Condenser cooling water in closed cycle

  • 8/3/2019 Ntpc Final Report

    25/27

    Condenser Cooling Water (CCW) Systems. This helps inreduction of thermal pollution and conservation of fresh water.

    8.Ash Dykes & Ash Disposal Systems: Ash ponds havebeen provided at all coal based stations where Dry Ash

    Disposal System has been provided.Ash in slurry form is discharged into the lagoons where ash

    particles get settled from the slurry and clear effluent water is

    discharged from the ash pond.

    9.Ash Water Recycling System:In the AWRS, the effluentfrom ash pond is circulated back to the station for further ashsluicing to the ash pond. This helps in savings of fresh waterrequirements for transportation of ash from the plant.

    Monitoring and alarm system

    Most of the power plant operational controls are automatic.

    However, at times, manual intervention may be required. Thus,

    the plant is provided with monitors and alarm systems that

    alert the plant operators when certain operating parameters

    are seriously deviating from their normal range.

    Battery supplied emergency lighting and

    communication

    A central battery system consisting oflead acid cell units is

    provided to supply emergency electric power to power plant's

    control systems, communication systems, turbine tube oil

    pumps, and emergency lighting. This is essential for a safe,

    damage-free shutdown of all the units in an emergencysituation.

    Efficiency

    The energy efficiency of a conventional thermal power station

    as a percent of the heating value of the fuel consumed is

    typically 33% to 48%. This efficiency is limited as all heat

    engines are governed by the laws ofthermodynamics. The rest

    of the energy must leave the plant in the form of heat.

    This waste heat can go through a condenserand be disposed of

    with cooling water or in cooling towers.

    http://en.wikipedia.org/wiki/Lead_acid_batteryhttp://en.wikipedia.org/wiki/Heating_valuehttp://en.wikipedia.org/wiki/Thermodynamichttp://en.wikipedia.org/wiki/Waste_heathttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Cooling_waterhttp://en.wikipedia.org/wiki/Cooling_towerhttp://en.wikipedia.org/wiki/Lead_acid_batteryhttp://en.wikipedia.org/wiki/Heating_valuehttp://en.wikipedia.org/wiki/Thermodynamichttp://en.wikipedia.org/wiki/Waste_heathttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Cooling_waterhttp://en.wikipedia.org/wiki/Cooling_tower
  • 8/3/2019 Ntpc Final Report

    26/27

    Conclusion

    On completion of my implant training

    at NATIONAL THERMAL POWER COMPANY, KORBA I have come

    to know about how the basic necessity of our lives i.e.

    electricity is generated. What all processes are needed to

    generate and run the plant on a 24x7 basis.

    NTPC KORBA is one of the plants in

    India to be under highest load factor for the maximum duration

    of time and is operating at highest plant efficiencies. This plant

    is an example in terms of working efficiency and management

    of resources to all other thermal plants in our country. This

    training gave me an opportunity to clear my concepts from

    practical point of view with the availability of machinery of such

    large rating.Driven by its vision to lead, NTPC has charted out

    an ambitious growth plan of becoming a 40,000 MW plus

    company by 2012.

  • 8/3/2019 Ntpc Final Report

    27/27