nsf: astro 2020 · – conduct senior review of ast portfolio prior to mid-decadal. ast portfolio...

44
NSF: Astro 2020 Ralph Gaume Saul Gonzalez Vladimir Papitashvili

Upload: others

Post on 10-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF: Astro 2020

Ralph GaumeSaul Gonzalez

Vladimir Papitashvili

Page 2: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Outline• NSF Goals for Astro2020

• Notional NSF Budgets: Construction and Operations

• Highlights of AST Response to Astro2010

• Highlights of AST Program Status

• PHY Perspective

• OPP Perspective

• Science, Big Ideas, Summary

July 15, 2019 NSF: Astro2020 2

Page 3: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF Goals for Astro2020

July 15, 2019 NSF: Astro2020

Page 4: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF Goals for Astro2020

• Astro2020 will be most effective if it is aspirational, inspirational, and transformative.

• Astro2020 will be most effective if it is based on community consensus science priorities.

• The agencies are the customers. Astro2020 will be conducted independently of the customer, but must provide recommendations, clear priorities, and actionable advice to the customer.

July 15, 2019 NSF: Astro2020 4

Page 5: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF Goals for Astro2020• NSF wants to know:

– What are science priorities for next decade?– What projects address these priorities?– Which projects are ready to go now and later?

When?– What are costs, risks, development needs of

projects?– What is the priority order for these projects?– What budgets are needed to support the

priorities, and are they realistic?

July 15, 2019 NSF: Astro2020 5

Page 6: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF Goals for Astro2020• NSF wants to know (continued):

– How does the current NSF portfolio address priorities?– What is the state of the profession?

• Recommendations for the agencies.– Division specific:

• AST: Decision rules for MSIP.• PHY: Welcome recommendations on promising

Technology R&D for next gen. facilities

• Let NSF sweat implementation details.– One NSF Astronomy/Astrophysics program

• Provide clear priorities with explanatory decision rules leading to the priorities.

July 15, 2019 NSF: Astro2020 6

Page 7: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Notional NSF Budgets: Construction and Operations

July 15, 2019 NSF: Astro2020

Page 8: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

July 15, 2019 NSF: Astro2020

-

$100

$200

$300

$400

$500

$600

$700

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Mill

ion

$

Fiscal Year

Notional (Ambitious) Future NSF MREFC Account Profile

Horizon (est)

NEON DKIST

LSST

RCRVAIMS

LHC

Mid-scale (est)

LCC (est)

8

Page 9: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF Operations and Maintenance• NSB: Study of O & M costs for NSF Facilities May 2018

• Recommendation 1: NSB and the NSF Director should continue to enhance agency-level ownership of the facility portfolio through processes that elevate strategic and budgetary decision-making.– …a scientifically robust Foundation-wide strategy that is both

transparent and fiscally responsible is critical.– Planning horizons that are longer than the current 5-year

projections required by statute could inform this strategy. The Department of Energy’s Office of Science has found notable success using a 10-year planning model.

– While NSB does not believe that it is necessary to establish a central O&M account at this time, greater flexibility in use of the MREFC account would enhance visibility and agency-level ownership.

July 15, 2019 NSF: Astro2020 9

Page 10: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

July 15, 2019 NSF: Astro2020

-

$500

$1,000

$1,500

$2,000

$2,500

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Mill

ion

$

Fiscal Year

Notional (Ambitious) Total NSF Facility + Mid-scale Funding

R&RA (All NSF O&M + small mid-scale)

MREFC (from previous chart)

10

Page 11: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Highlights of NSF Response to Astro2010

July 15, 2019 NSF: Astro2020

Page 12: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Astro2010: Recommendations for new large projects

• Priority 1: LSST– In construction phase, operations ramp began in FY 2019,

beginning 10-yr survey in FY2023.

July 15, 2019 NSF: Astro2020 12

Page 13: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

LSST Current Construction Site

July 15, 2019 NSF: Astro2020

On budget and on schedule for full operations in FY 2023.

13

Page 14: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Astro2010: Recommendations for new large projects

• Priority 1: LSST– In construction phase, operations ramp began in FY 2019,

beginning operations in FY2023.

• Priority 2: Initiate MSIP, reach annual budget of $40M/yr– Constrained budget and priority choices led to $15-$20M/yr

in alternate year solicitations during mid-decade– FY 18 appropriation allowed $25M/yr– MSRI-1 and 2 hold the potential for further AST support– MSIP will be continued as well as MSRI, potential for MSRI

to replace MSIP in future years. Decision rules for MSIP?

• Other large project priorities not addressed due to budgetary constraints. (CTA team was instructed to apply to MSIP.)

July 15, 2019 NSF: Astro2020 14

Page 15: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Astro2010: Medium project and other

• Medium Project:– CCAT a wide field-of-view 25m telescope to be

constructed near ALMA.– Astro2020 estimated total construction cost at $140M.– Astro2020 recommended NSF share of construction $37M.– Astro2020 recommended $7.5M/year NSF share of

operations.– Funding was insufficient for to address CCAT, CCAT team

instructed to apply to MSIP.• Other:

– Conduct mid-decadal progress study on Astro2010 recommendations. NWNH: A Midterm Assessment.

– Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012).

July 15, 2019 NSF: Astro2020 15

Page 16: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Astro2010: Recommendations for AST core program• ATI – 50% increase over $10M/yr.

– Budgetary limitations reduced to ~$8M every other year.

• AAG – increase to $54M/yr.– Dipped to $42M in FY13, recovered to $51M in FY18.

• Gemini augmentation - gain increased share for slight increase in budget.– That was essentially the outcome of the UK withdrawal.

• TSIP – increase from $2-3M/yr to $5M/yr.– TSIP program discontinued; subsumed in MSIP as

recommended by Portfolio Review.

• Theory and Computation Networks – fund at $2.5M/yr.– Joint solicitation with NASA, one round funded, then folded

into AAG due to funding constraints.– Several programs jointly funded with CISE.– HDR Big Idea is latest agency-level commitment.

July 15, 2019 NSF: Astro2020 16

Page 17: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Highlights of AST Program Status

July 15, 2019 NSF: Astro2020

Page 18: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

AAG

AAPF

ATI

CAREER

MRI

REU

ALMA

Arecibo

NRAO

Gemini

NOAO

LSST

NSO

GBO

MSIP

Individual Investigators

Mid-scale Facilities

AST Division Programs

Technology/Instrumentation

Research

Education and

Special Programs

July 15, 2019 NSF: Astro2020 18

*

*

**NSF Wide

Presenter
Presentation Notes
Overview of AST programs. Color coding: Research support in green, facilities in blue. AAG main research grants program; CAREER (NSF-wide) and AAPF – early career programs. [“Success rates” in recent years.] MRI – NSF-wide – single, general use instrument MSIP – bridges gap between small-scale facilities and large instruments Facilities: radio – optical, some are undergoing divestment. [Later: Where does laboratory astrophysics fit in?]
Page 19: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF and AST Support for Workforce• NSF has provided leadership in ensuring the research and

learning environments its supports are free from harassment.– Awardee organizations must notify NSF of findings, determinations,

admin leave and/or action for funded PIs and CoPIs.

• NSF recognizes the need to promote a diverse and inclusive workforce in our quest to promote the progress of science.

• NSF and AST: AAPF, CAREER, INCLUDES, RUI, REU sites, GRFP, HBCU, EPSCoR, Educ. and Special Pgms, facility awardee’s programs

July 15, 2019 NSF: Astro2020 19

Page 20: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Forefront Facilities Radio-Millimeter-Submillimeter Atacama Large Millimeter-Submillimeter Array Jansky Very Large Array Very Long Baseline Array Green Bank Observatory Arecibo Observatory

Optical/Infrared Gemini 8-m North and South (+Subaru exchange) Blanco 4-m SOAR 4.2-m WIYN 3.5-m Community access to SMARTS, LBT, CHARA, LCO, AAT

Solar GONG, SOLIS, DKIST

July 15, 2019 NSF: Astro2020 20

Page 21: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

DKIST Telescope

July 15, 2019

• Telescope optics in place, M1 & M2 aligned.• Current challenges largely with instrument

completion and delivery, as well as data policy.• Commissioning of thermal control loops also a

significant task.• Still on schedule and within budget contingency.

NSF: Astro2020 21

Page 22: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

AST Facility Transition Summary

July 15, 2019 NSF: Astro2020

Telescope Status

KPNO 2.1m Caltech-led consortium operating for FY 2016-2020.

Mayall 4m DESI; NSF to DOE; NSF/DOE MOA for operations .

WIYN 3.5m NOAO share to NASA-NSF Exoplanet Observational Research Program; NSF/NASA MOU in place; NASA instrument under development.

GBO Separation from NRAO in FY 2017; Collaborations in place for operations; MOA for new partner; more new partners desired.

LBO/VLBA Reintegrated into NRAO; MOA with US Navy in place for 50%.

McMath-Pierce Funding for utilization as science outreach center.

GONG/SOLIS GONG refurbishment; Interagency Agreement with NOAA signed to share GONG operations costs. SOLIS moved from Kitt Peak to Big Bear.

Sacramento Pk. Initial NSF and State funding for consortium led by NMSU; NSO to provide continuing site support; NSB approval for ROD.

Arecibo UCF new operator, plans to increase funding share from UCF partners; hurricane recovery funding being deployed; staffing challenges.

SOAR AAAC subcommittee recommended continuing renewal

22

Page 23: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

FY 2018 Budget (AST) Very good outcome in the end for AST – total $307M,

compared to FY17 actual of $252M.

Much of the increase went to one-time specific projects (some dependent on FY19 availability of funds to complete): MSIP, for total funding close to aspirations in NWNH

Multi-messenger astrophysics grants

Major upgrade to Gemini N Adaptive Optics system in service of time domain follow-up, stellar populations studies

Early funding of DKIST operations for timely completion of data center, supplement for Level 2 data products.

Initial funding of LSST operations ramp for three years.

July 15, 2019 NSF: Astro2020 23

Page 24: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

50.448.0

45.1

29.5

45.1

29.324.9

31.227.6 26.7

31.234.3

38.1 36.8

28.8 28.524.4 23.9

20.7

36.3

22.419.9

14.8 15.4 16.718.6 18.8 19.3

22.3

Proposal Funding Rate, %

16.2 17.0 18.2 17.1 20.2 18.6 17.5 19.3 19.7 18.8 20.9 22.729.4 32.4 30.7 34.0

38.9 41.5 42.1

79.6

49.4 48.144.5 42.4 43.7

48.4 48.5 48.7 50.9

AAG Budget, $M

July 15, 2019 NSF: Astro2020

Page 25: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF FY 2019 Budget Enacted appropriation increases R&RA by 3%. MREFC line re-incorporates Antarctic infrastructure; DKIST (final

year, Ops begin June 2020) and LSST at requested levels. NSF’s bill was not under consideration for passage before the

end of FY 18, so operations after October 1, 2018 were under a Continuing Resolution until Dec 21st.

Major 35-day shutdown challenge for NSF was maintaining flow of funds to facilities awardees, particularly those with Chilean labor contracts. OMB allowed cash draws for previously allocated funding, unlike the 2013 shutdown.

FY 20 President’s Budget Request public last winter. Now preparing FY 2021 PBR for release in early CY 2020.

FY 2019 Directorate and Divisional allocations being executed (spend plan approved by Congress in June 2019). FY 2019 is not yet over, so will not discuss details of FY 2019 budget.

July 15, 2019 NSF: Astro2020 25

Page 26: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF Division of Physics Perspective

Page 27: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Division of Physics –2019 - Programs

July 15, 2019 NSF: Astro2020

Particle Astrophysics; IceCube

Physics at the Information Frontier Q

Midscale Instrumentation

Atomic, Molecular, & Optical Physics

Plasma Physics

Integrative Activities in Physics(REU Sites, MRI, CAREER, BP org)

Elementary Particle Physics; LHC

Gravitational Physics; LIGO, AdvLIGO

Nuclear Physics; NSCL

Theoretical Physics(AMO, Nuclear, EPP, AC)

Physics of Living Systems

Physics Frontiers Centers

Quantum Information Science

27

Page 28: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Division of Physics –2019 - Programs

July 15, 2019 NSF: Astro2020

Particle Astrophysics; IceCube

Physics at the Information Frontier Q

Midscale Instrumentation

Atomic, Molecular, & Optical Physics

Plasma Physics

Integrative Activities in Physics(REU Sites, MRI, CAREER, BP org)

Elementary Particle Physics; LHC

Gravitational Physics; LIGO, AdvLIGO

Nuclear Physics; NSCL

Theoretical Physics(AMO, Nuclear, EPP, AC)

Physics of Living Systems

Physics Frontiers Centers

Quantum Information Science

*

*

*

**

*

* Program with relevance to Astro2020

28

Page 29: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Facilities in the Physics Division

July 15, 2019 NSF: Astro2020

Laser Interferometer GravitationalWave Observatory (LIGO)

National SuperconductingCyclotron Laboratory (NSCL)

ATLAS and CMS Detectors atLarge Hadron Collider (LHC)

IceCube (joint with OPP)

29

Page 30: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Current Status of PHY Facilities

July 15, 2019 NSF: Astro2020

LIGOO3 Run Started April 1; A+ Upgrade

underway

NSCLTransfer to FRIB (DOE) in 2021 Progressing Smoothly

LHCPlanning for MREFC High-Luminosity Upgrade

Underway ($150 M);IRIS Award to Address Computational Challenges

IceCubeUpgrade Underway

(joint with OPP) Photos courtesy of facilities, resp.

30

Page 31: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Physics Division Budgets

July 15, 2019 NSF: Astro2020

0

50

100

150

200

250

300

350

FY 2015 FY 2016 FY 2017 FY 2018

$ m

illion

/ FY

Individual Investigator Centers O&M Infrastructure Other

Individual Investigators

Centers

O&M

Infrastructure

31

Page 32: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Astrophysics-related Programs in PHY

July 15, 2019 NSF: Astro2020

0

20

40

60

80

100

120

FY 2015 FY 2016 FY 2017 FY 2018

$ m

illion

/ FY

Individual Investigator Centers O&M Infrastructure

Individual Investigators

Centers

O&M

Infrastructure

32

Page 33: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

South Pole

Palmer

McMurdo

NSFDenver ASC

Port Hueneme

U.S. Antarctic Program

July 15, 2019 NSF: Astro2020 33

Page 34: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

USAP Logistics System

Continental System(Military/Commercial)

Peninsula System(Commercial)

Challenges:Global Scale Supply ChainsAging Infrastructure/Assets Fuel DependencyPower LimitationsIcebreaker Requirements

July 15, 2019 NSF: Astro2020 34

Page 35: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF/Office of Polar ProgramsAntarctic Sciences and Logistics

Instrumentation and Facilities

Glaciology

OceanAtmosphere Earth sciences

Integrated System Science

Organisms andEcosystems

Astrophysics $9.0M & Geospace $2.5M

Infrastructure and Logistical Support

Annual budget

~$4 per each science dollar

July 15, 2019 NSF: Astro2020 35

Page 36: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

DSL

SPT

BICEP

QUaD

MAPO

IceCube Neutrino Observatory ($272M, NSF/MREFC project, 2002-2010) O&M $7M/year (GEO/OPP & MPS/PHY)

Since 2002, total NSF investments in IceCube science ~$120M

Mid-scale ICNO Upgrade $23M funded in 2018 plus ~$5M for logistical support

High-energy cosmic neutrinos (100 TeV– 1 PeV) are detected and one source is pinpointed (Science, 2013; 2018)

Community plans IceCube Gen2 in 2020s

Neutrino Astrophysics at South Pole

A New Windows on the Universe Multimessenger Astrophysics

July 15, 2019 NSF: Astro2020 36

Page 37: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

South Pole Telescope

BICEP Array of telescopes

Since 2002, total NSF investments in Antarctic Cosmology ~$100M

Community plans CMB-S4 program in 2020s

10m South Pole sub-mm Telescope:Origin and Early History of the Universe CMB E & B modes polarization

BICEP small aperture telescopes: Imprints of Primordial Gravitational Waves in CMB polarization

Cosmology and CMB Research at South Pole

A workhorse of the Antarctic: LC-130

All cargo to South Pole is delivered by this aircraft!

July 15, 2019 NSF: Astro2020 37

Page 38: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Science, Big Ideas, Summary

July 15, 2019 NSF: Astro2020

Page 39: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

NSF’s 10 “Big Ideas” for Future Investment

July 15, 2019 NSF: Astro2020 39

RESEARCH IDEASWindows on the Universe:The Era of Multi-messenger Astrophysics

The Quantum Leap:Leading the Next Quantum Revolution

Navigating the New Arctic

Understanding the Rules of Life:Predicting Phenotype

PROCESS IDEASMid-scale Research Infrastructure

Growing Convergence Research at NSF

NSF 2026

NSF INCLUDES: Enhancing STEM through Diversity and Inclusion

Harnessing Data for 21st Century Science and Engineering

Work at theHuman-TechnologyFrontier: Shaping the Future

Page 40: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

The Era of Multi-MessengerAstrophysics (MMA)

Focus Areas: • Enhancing and accelerating the theoretical, computational, and

observational activities within the scientific community • Building dedicated midscale experiments and instrumentation• Exploiting current facilities and developing the next generation of

observatories

Artist’s illustration of

binary neutron star merger

Goal: To build the capabilities and accelerate the synergyand interoperability of the three messengers, realizing integrated, multi-messenger explorations of the universe

ElectromagneticWaves

High-energy Particles

Gravitational Waves

July 15, 2019 NSF: Astro2020 40

Presenter
Presentation Notes
Credit: National Science Foundation/LIGO/Sonoma State University/A. Simonnet (https://www.nsf.gov/news/news_summ.jsp?cntn_id=297414) Context for image: As an example of the promise of MMA, the binary neutron star merger GW170817 was detected in 2017 by LIGO, Virgo and 70 EM observatories. This was the first detection of gravitational waves from a binary NS merger. Analysis of the combination of GW and EM detections determined that half of all elements heavier than Fe are produced in ns-ns mergers.
Page 41: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Highlight: LIGO

July 15, 2019 NSF: Astro2020 41

First Direct detection of Gravitational Waves

2017 Nobel PrizeSeptember 14, 2015 at 5:51 a.m. Eastern Daylight Time

“LIGO scientists estimate that the black holes for this event were about 29 and 36 times the mass of the sun, and the event took place 1.3 billion years ago. About 3 times the mass of the sun was converted into gravitational waves in a fraction of a second”

(B. P. Abbott et al. (LIGO and Virgo Scientific Collaborations, Phys. Rev. Lett. 116, 061102 (2016) )

[Press Release]

Page 42: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

IceCube 170922290 TeV

Gamma rays energy spectrum 80-400 GeV

Flaring blazar within 0.1o

Fermi-LAT gamma-ray space telescope

MAGIC - Major Atmospheric Gamma Imaging Cherenkov Telescopes (La Palma)

NSF Press Release 18-050 (July 12, 2018)Neutrino observation points to one source of high-energy cosmic rays (Science, 2018)

# 4 in Top 10 stories of 2018 by http://www.sciencenews.org

July 15, 2019 NSF: Astro2020 42

Page 43: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Image of M87 from Event Horizon Telescope

• NSF (AST) invested some $28M in EHT research over the last two decades, including hardware and algorithm development as well as theoretical modeling (PIRE grant for international collaboration).

• ALMA observations were critical for closing phase; South Pole telescope provided critical baselines.

• Doeleman et al. team with 8 telescope VLBI at 1.3 mm.

• Black hole shadow with inferred angular gravitational radius of 3.4±0.4μas.

• Assumed distance yields M=(6.5±0.7)x109M⊙

• Crescent brightness distribution consistent with Kerr Black Hole.

July 15, 2019 NSF: Astro2020

Page 44: NSF: Astro 2020 · – Conduct Senior Review of AST portfolio prior to mid-decadal. AST Portfolio Review (2012). July 15, 2019 NSF: Astro2020 15. Astro2010: Recommendations for AST

Summary

• Astro2020 will be most effective if it is aspirational, inspirational, and transformative.

• Astro2020 will be most effective if it is based on community consensus science priorities.

• Let NSF sweat implementation details.

• Provide clear priorities with explanatory decision rules leading to the priorities.

July 15, 2019 NSF: Astro2020 44