Page 1: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

NRC LICENSEE CONTROL

CELL TRAINING

1

Jason KozalSenior Emergency Response

Coordinator

Page 2: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PURPOSE

• This training is intended for non-NRC personnel who will act in the role of the NRC during licensee exercises. Therefore, it is important to have a good understanding of:

– NRC responsibilities and response process

– NRC response organization and functions

• Please note that this is not the exact process used by the NRC. There are a lot of other internal and Headquarters interfaces / activities that do not have an immediate or direct impact on licensees.

• Use of fewer or more people on the Mock NRC team may require shifting some duties / responsibilities described in this training.

2

Page 3: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

NRC ROLES & RESPONSIBILITIES

• Monitor and independently assess licensee’s actions and serve as an independent source of information, advice and technical analyses for the State.

• Coordinate Federal response under the National Response Framework Nuclear/Radiological Incident Annex - Federal support for licensee, State, and local stakeholders.for licensee, State, and local stakeholders.

• Support other Federal agencies and keep them informed of the National Response Framework Nuclear/Radiological Incident Annex response.

• Coordinate public information on the National Response Framework Nuclear/Radiological Incident Annex response for the Federal Government.

• Intervene in a limited fashion to direct licensee actions onsite (rare & unusual circumstances).

3

Page 4: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

NOTIFICATIONPROCESS

Event Notification

Headquarters Operations Officer assesses

information, then makes notifications

Regional Duty Officer determines if Regional

Administrator needs to be

4

Headquarters Emergency Officer determines if HQ management needs to be

notified

Administrator needs to be notified. Otherwise,

notifies designated branch chief

Notification to other Federal agencies

Page 5: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

RESPONSE DECISIONS

NRC Response Decision Licensee Actions

Take no further action. Call back when incident is terminated or if conditions degrade.

Activate Regional Incident Response Center / Headquarters Operations Center.

1. Maintain open ENS line (Alert and above).

2. Establish HPN line when requested.

3 Establish security line when requested if securityp 3. Establish security line when requested if security related incident.

4. Brief NRC management on a regular basis.

Dispatch Site Team. 1. Continue items for activated Regional Incident Response Center / Headquarters Operations Center.

2. Interface with team members when they arrive.

5

Page 6: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

RESPONSE TIMING(REAL TIME)

• Response Decision Making / StaffingT0 = Notification timeT0 + 0.5 hours = Decision making must be completedT0 + 1.5 hours = Response centers staffed

• Site Team TravelT1 = Time decision made to dispatch site team1 pT1 + 4 hours = Plane transporting Site Team departs DFWT1 + 6 hours = Site Team arrival time at local airportT1 + 6.5 hours = Site Team departs local airportT1 + 8 hours = Site Team arrives on site

(Site Team will call for briefing through Headquarters approximately 10 –20 miles from the site or from the local airport).

6

Page 7: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TYPICAL EXERCISE TIMING (COMPRESSED)

• 0.0 hours = Initial notification• 0.5 hours = Decision to enter Monitoring• 1.0 hours = NRC regional facilities staffed for Monitoring• 1 5 hours = Decision to enter Activation1.5 hours Decision to enter Activation• 2.0 hours = NRC headquarters facilities staffed for Activation• 2.5 hours = Decision to enter Expanded Activation / Site Team

dispatched• 3.5 hours = Site team at local airport• 4.0 hours = Site team arrives at EOF

- Goal is to have Site Team in place prior to general emergency

7

Page 8: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

NRC INTERNAL INTERFACE

Headquarters Operations Center

8

Regional Incident Response Center

Site Team

Page 9: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

FUNCTIONAL Co-Location

• The NRC Site Team functionally co-locates with the licensee in the Emergency Operations Facility

• The Site Team will arrive at the Emergency Operations Facility and will move to an area to get a quick briefing from licensee (about 15 minutes)

• After the briefing, Site Team members will set up equipment / communications, obtain an individual briefing from licensee counterparts, obtain turnover from NRC Headquarters and Regional Base Team

• Even though the Site Team is onsite and functioning, communication links to NRC Headquarters will continue to operate

9

Page 10: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

NRC SITE TEAM ORGANIZATION

Site Team Director

Deputy Site Team Director

Technical Assessment Branch

Protective Measures Branch

Security / Safeguards Branch

Liaison LeaderPublic Information

Leader

Response Coordination

Branch Leader

State Emergency Operations Center

Public Information Chronology Assessment Branch

LeaderMeasures Branch

LeaderSafeguards Branch

LeaderOperations Center

Liaison

Liaison Technical Briefer

Technical Briefer

News / Media Liaison

gyManager

Info Technology / Telecommunication

s Specialist

Chronology Communicator

Deputy Technical Assessment Branch

Leader

Deputy Protective Measures Branch

LeaderSecurity Specialist

Senior Resident Inspector

Resident Inspector

Technical Assessment

Specialist

Technical Assessment

Communicator

Protective Measures Specialist

Dose Assessor

Protective Measures

Communicator

Security / Safeguards

Communicator

10

Page 11: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

SITE TEAM MANAGEMENT

Site Team Director

11

Deputy Site Team Director

Page 12: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

SITE TEAM DIRECTOR

• Act as the NRC’s Federal On-scene Coordinator for an integrated response under the Nuclear / Radiological Incident Annex of the National Response Framework

AUTHORITIES

Incident Annex of the National Response Framework

• Recommend actions to the licensee.

• Recommend offsite actions.

• Act as primary spokesperson for the Federal response concerning Coordinating Agency issues at the site.

12

Page 13: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TYPICAL AUTHORITIES NOT DELEGATED TO

SITE TEAM

• Issue formal technical orders to the licensee for specific actions.

• Interact with Governors of affected states concerning issues not directly or entirely related to any of the delegated authorities.

• Coordinate with The White House, Congress, Headquarters of other Federal Agencies and international organizations.

13

Page 14: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

FOCUS AREAS:SITE TEAM DIRECTOR

• Manage the NRC’s on-scene response to the incident.

• Set the battle rhythm for NRC’s on-scene response activities.

• Keep the big picture in mind• Keep the big picture in mind.

• Keep in touch with the Liaison Leader for issues / requests involving State, local and other Federal agencies responding to the incident.

• Keep in touch with the Public Information Leader to ensure that the proper media message is being sent out.

• Keep information flowing to and from the Public Information Branch and Liaison Branch.

14

Page 15: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

DEPUTY SITE TEAM DIRECTOR

• Keep the big picture from a technical perspective.

• Ensure that the licensee is taking appropriate actions to terminate the incident

FOCUS AREAS

the incident.

• Ensure that the licensee is taking appropriate actions to mitigate the consequences.

• Ensure that the licensee is making protective action recommendations to State and local officials, as warranted.

• Assist with information sharing between teams.

• Acts for the Site Team Director in their absence.

15

Page 16: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PUBLIC INFORMATION STAFFING

Public Information Leader

Public Information Not typically

16

Technical Briefer

News Media Liaison

yp ystaffed as part of a “Mock” NRC Team

Page 17: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PUBLIC INFORMATION

• The Public Information Branch Leader serves as the on-scene media representative for the NRC.

• The Public Information Technical Briefer listens to the Reactor Safety Counterpart Link (RSCL) to maintain awareness of the current situation and routinely brief the yPublic Information Branch Leader.

• When staffed, the News Media Liaison Officer takes calls / questions from public and media outside of Joint Information Center, performs external research on issues, and prepares the first draft of press releases.

17

Page 18: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PUBLIC INFORMATION

• Participate in press conferences.

• Draft a press release:

– Soon after arrival of Site Team / transfer of authority to Site Team Director

TASKS:

– Upon notification that the Secretary of the Department of Homeland Security has declared an Incident of National Significance

– On a regular basis as the incident progresses

• Transmit draft press releases to the Site Team Director for approval

• NEVER provide protective action “recommendations”

to the media.

18

Page 19: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PUBLIC INFORMATIONCOMMUNICATION LINKS:

19

Page 20: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

LIAISON STAFFING

Liaison Leader

20

State EOC Liaison

Liaison Technical Briefer

Emergency Support Function Liaison

Not typically staffed as part of a “Mock”

NRC Team

Page 21: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

Liaison

• The Liaison Leader keeps the Site Team Director informed regarding offsite activities and interfaces with State, Local and other Federal representatives in the licensee’s Emergency Operations Facility.

• The State Emergency Operations Center Liaison serves as the primary contact point for interfacing with the State officials that are

t it d ti l b i f th Li i L d ti itinot on-site and routinely briefs the Liaison Leader on activities at the State Emergency Operations Center.

• The Liaison Technical Briefer listens to the Reactor Safety Counterpart Link to keep up with the current situation and reports protective action decisions and requests for assistance as they occur.

• Requests for Federal assistance are processed through the Liaison Leader to Headquarters.

21

Page 22: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

Special Advice

• When interfacing with State / Local representatives, be careful that you do not give the impression or imply the Federal agencies will be taking over the response.

• Offer assistance one time and wait for them to request further help. If they say they do not want our assistance, thank them and let them know we will do what we can if they need us. Do not try to force help upon them.to force help upon them.

• Assistance that can be offered includes:– Technical assistance understanding the situation

at the facility– Technical assistance with dose projections– Assistance requesting technical support from

other Federal agencies

Note: The Liaison Branch does not actually provide theassistance; they coordinate getting it.

22

Page 23: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

LIAISON INTERFACE LINKS

Lia

ison Le

ade

rC on tinua llyope n lin e

E m ergency O perations FacilityThe Liaison Bridge may be substituted with a direct telephone call link for the “Mock” NRC Team.

23

R eac to r S a fe tyC ounterpart L ink

S ta te E m ergencyO pe ra tions C ente rL ia ison

L ia ison T echn ica lB rie fe r

Lapt

op c

ompu

ter

S ta te E m ergen cy O pera tio n s C en ter

C ontinua llyope n line

Prin

ter

C o n tinu a llyopen line

N R C N etw o rkD ia l-u p C on ne c tion

L ia iso n B rid g e

C on tinua llyopen line

Page 24: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TECHNICAL ASSESSMENT STAFFING

Deputy Technical Assessm ent B ranch Leader

Technical Assessm ent Branch Leader

24

Technical Assessm entSpecialis t - Senior ResidentInspector

Technical Assessm entSpecialis t - Resident Inspector

Technical Assessm entCom m unicator - RSCL

Technical Assessm entSpecialis t - ReactorO perations

Not typically staffed for “Mock” NRC

team

Page 25: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TYPICAL TECHNICALASSESSMENT TASKS

• Verify the licensee is taking reasonable actions to mitigate / terminate the incident.

• Ensure the licensee has properly classified the incident.

• Perform a core cooling assessment.

• Perform a core damage assessment.

• Determine the most likely release pathway.

• Determine if the release pathway is monitored or filtered.

• Compare assessments with licensee and resolve differences, if necessary.

25

Page 26: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TECHNICAL ASSESSMENT BRIEFING

26

Use a form similar to this to summarize the NRC’s independent technical

assessment

Page 27: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TYPICAL QUESTIONS

– Did all control rods fully insert?– How is the core being cooled (forced flow or natural circulation)?– What is the heat sink (condenser, atmospheric relief,

suppression pool)?– Any unexpected pressure or level transients?– Offsite and emergency power available?

Was there a release or is there an ongoing release?– Was there a release or is there an ongoing release?– Any actuation of emergency core cooling systems?– Any isolations?– Any unexpected complications or anything unusual about the

scram/trip?– What caused the scram / trip?– Does this event require you to enter your emergency plan?

27

Page 28: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

Reactor SafetyCounterpart Link (RSCL)

• The Reactor Safety Counterpart Link (RSCL) is used by the Technical Assessment Branch in parallel with the Emergency Notification System with the licensee.

It i th i th d f h i t h i l• It is the primary method of sharing technical assessment related information between NRC staff located on scene and in NRC response facilities.

• It serves as an information feed for the State Emergency Operations Center Liaison and Public Information Leader.

28

Page 29: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TECHNICAL ASSESSMENT INTERFACE LINKS

ety

k (R

SC

L)

L i c e n s e e E m e r g e n c yO p e r a t io n s F a c i l i t y

L ic e n s e e J o in tIn f o r m a t io n C e n t e r

S t a t e E m e r g e n c yO p e r a t io n s C e n t e r

L ia is o n T e c h n ic a lB r ie fe r

29

Rea

cto

r S

afe

Co

un

terp

art

Lin

kT e c h n ic a l

A s s e s s m e n tC o m m u n ic a to r

Tec

hnic

al

Ass

essm

ent

Spe

cial

ist

T e c h n ic a lA s s e s s m e n t

B r a n c h L e a d e r

Dep

uty

Tec

hnic

al

Ass

essm

ent

Bra

nch

Lead

er

L ic e n s e e T e c h n ic a lS u p p o r t C e n t e r

L ic e n s e e C o n t r o lR o o m / S im u la t o r

R e s id e n t In s p e c to r

S e n io r R e s id e n tIn s p e c to r

P u b l ic I n fo r m a t io nT e c h n ic a l B r ie f e r

Page 30: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PROTECTIVE MEASURES BRANCH STAFFING

P ro te c t iv e M e a s u re s B ra n c h L e a d e r

30

D e p u ty P ro te c t iv e M e a s u re s B ra n c h L e a d e r

D o s e A s s e s s o r

P ro te c t iv e M e a s u re sC o m m u n ic a to r - P M C L

P ro te c t iv e M e a s u re sS p e c ia l is t

Not typically staffed for “Mock” NRC

team

Page 31: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TYPICAL PROTECTIVE MEASURES

• Perform dose projections to develop Federal protective action recommendations, compare with licensee / State projections and try to resolve discrepancies.

• If there is a significant difference between NRC

TASKS:

gprojections and licensee and State projections, inform the Site Team Director and Liaison Leader so they can discuss the situation with licensee and State management.

• Review protective actions for licensee personnel.

• Recommend actions to the Site Team Director to protect NRC on-scene responders.

31

Page 32: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

PROTECTIVE MEASURES

P ro te c tiv e M e a s u re sC o u n te rp a rt L in k

E m e rg e n c y O p e ra t io n s F a c il ity

D e p u ty P ro te c tiv e

P ro te c tive M e a s u re sB ra n c h L e a d e r

INTERFACE LINKS:

32

P ro te c tive M e a s u re sC o m m u n ic a to r - P M C L

D o s e A s s e s s o r

Lapt

op c

om

pute

r

C o n tin u a llyo p e n lin e

Pri

nte

r

C o n t in u a llyo p e n lin eN R C N e tw o rk

D ia l-u p C o n n e c tio n

P ro te c tive M e a s u re sS p e c ia lis t

p yM e a s u re s B ra n c h L e a d e r

Page 33: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

SAFEGUARDS / SECURITY BRANCH

Safeguards / Security Branch Leader

33

Safeguards / Security Communicator

Security SpecialistWhile this position may not always be

staffed (non-security related incidents), the licensee should be prepared to

communicate security related information to the NRC.

Page 34: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

SAFEGUARDS / SECURITY

• Interface with on-scene law enforcement (local, State and Federal)

• Provide technical and protective measures assessment information to on-scene law enforcement

TASKS:

• Review impact of the incident on plant security / compensatory measures

• Review licensee Security response activities

• Recommend actions to Site Team Director to protect NRC on-scene responders.

• Protect / secure classified and sensitive information.

34

Page 35: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

SETTING UP A CONTROLSETTING UP A CONTROL

CELL

Page 36: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

NRC TELEPHONE CELL(DUPLICATES HQ

INTERFACE)Dedicated com m unicator to serveas the "NRC HeadquartersO perations O fficer" and to m aintainan open ENS line with the licensee.

Dedicated com m unicator to serve

These functions will normally be provided by the Region for the dress rehearsal.The licensee may need to be prepared to

36

as the "NRC Health PhysicsNetwork comm unicator" and tom aintain an open HPN line with thelicensee.

Comm unicator to provide injectsfrom NRC Headquarters (e.g., theChairm an, a Com m issioner, etc.)

p pprovide these functions for those times the Region does not provide this support.

Page 37: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

“MOCK” NRC SITE TEAM ORGANIZATION

Site Team Director

Liaison Leader

State EOC Liaison

Liaison Technical Briefer

Public Information Leader

Public InformationTechnical Briefer

37

Deputy Site Team Director

Liaison Technical Briefer

Technical Assessment Branch Leader Protective Measures Branch Leader

Technical AssessmentSpecialist - Senior ResidentInspector

Technical AssessmentSpecialist - Resident Inspector

Technical AssessmentCommunicator - RSCL

Dose Assessor

Security / Safeguards Branch Leader(staffed for security incidents)

Page 38: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

Special Note

• NRC responders will usually have a good “generic” understanding of how facilities operate or specific technical knowledge such as dose assessment. However, with the exception of the Resident Inspectors, most responders will not have extensive knowledge of p , p ga specific site and its procedures.

• Ask questions to clarify information from the licensee. Examples might include:

– What does that acronym mean?

– Where is this in relation to . . . ?

– How do I find . . .?

– Who do I talk to about . . . ?

38

Page 39: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

COORDINATING RESPONSE TO MULTIPLE FACILITIES

• The Senior Resident Inspector / Resident Inspector report to the “control room” when they are “informed” of the situation.

• The Senior Resident Inspector will relocate to the Technical Support Center when it is activated.

• For exercise planning ensure that the Public Information Branch isFor exercise planning, ensure that the Public Information Branch is scheduled to arrive at the licensee’s Joint Information Center around the same time the Site Team arrives at the Emergency Operations Facility.

• For exercise planning, ensure that the State Emergency Operations Center Liaison and Liaison Technical Briefer arrive at the State Emergency Operations Center around the same time the Site Team arrives at the Emergency Operations Facility.

39

Page 40: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

SPECIAL MESSAGE TO NRC CONTROL CELL MEMBERS

The NRC is willing to help licensees in many different ways. At times, NRC participants may appear to be team mates with the licensee. Examples of support that may be provided:

• Obtain technical expertise to help understand the event as it occurs

• Coordinating with other Federal agencies to get enhanced / replacement communications capabilities to the site

• Coordinating with other Federal agencies to get a large diesel• Coordinating with other Federal agencies to get a large diesel generator or other equipment to augment the licensee’s backup power capabilities

While it can be argued that the licensee should be able to perform these functions, there may be extenuating circumstances such as a large disaster around the facility as with a major hurricane or earthquake. Therefore, it may require the resources of the Federal Government to obtain the necessary support.

A key thing to remember is that the NRC’s primary role is to independently assess the licensee’s actions. Therefore, the licensee should take care not to “task” the NRC to perform functions normally performed by the licensee such as core damage assessment, dose assessment, protective action recommendation development, etc.

40

Page 41: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TYPICAL SCENARIOTYPICAL SCENARIO

Page 42: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

INITIAL NOTIFICATION

• The licensee notifies the NRC Headquarters Operations Center of an emergency.

• The Headquarters Operations Officer should start to fill out Form 361 for a “routine” report.

42

Page 43: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

• For an Unusual Event involving minor safety significance, the Headquarters Operations Officer will typically treat this as a “routine” notification. The licensee will be asked to call back if the situation degrades or when they terminate the emergency.

• For an Alert or higher or for an Unusual Event where there are potential safety concerns, the Headquarters Operations Officer will maintain an open line with the licensee (for non-imminent threat

INITIAL ACTIVITIES

p (situations).

• Simulate getting a briefing for NRC management and making a decision to staff NRC response centers.

• Obtain information to fill out Form 361. Generate a list of data needed to continually assess the incident and ask the licensee to provide the data on a 15 minute interval (the interval and data list can be revised as the incident progresses).

43

Page 44: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

STAFFING THE HEALTH PHYSICS NETWORK

• For exercise purposes, ask the licensee to have someone staff the Health Physics Network:– when there is a potential for a release– when a release is occurring– upon dispatch of the Site Team

f ff• The request for the licensee to staff the Health Physics Network is typically made to the Emergency Notification System Communicator.

• A second request may be made to the Resident Inspectors over the Reactor Safety Counterpart Link asking them to give the licensee the message to staff the Health Physics Network.

• Once staffed, continually discuss dose projections and request input information to perform dose projections.

44

Page 45: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

• Notify the licensee of the decision to dispatch a Site Team over the Emergency Notification System along with an estimated time of arrival.

DISPATCH OF THE SITE TEAM

• Notify the Resident Inspectors of the decision to dispatch a Site Team over the Reactor Safety Counterpart Link.

• Obtain facsimile number / e-mail address to send a roster to the licensee containing the names of the people who will be on the Site Team.

45

Page 46: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

ARRIVAL OF THE SITE TEAM AT THE LOCAL

AIRPORT• When the NRC Site Team arrives at a local airport, the

Site Team Director will call into the NRC Headquarters Operations Center to get the current status briefing.

• The Protective Measures Branch Leader will call in and ask to be put on the Health Physics Network to get the current status on access route to the site.

• The licensee telephone cell will perform these calls and quickly brief the “Mock” NRC Site Team prior to reporting to the Emergency Operations Facility.

46

Page 47: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

• Site Team will enter the Emergency Operations Facility at the designated entry point.

• Sign in / obtain dosimetry as called for by the licensee’s procedures.

• The Site Team Director should ask someone to inform the

Arrival at the Emergency Operations Facility

• The Site Team Director should ask someone to inform the Emergency Director that the Site Team has arrived and would like to be briefed on the current status of the event.

• The Site Team Director should ask someone to show the Site Team where they are to go for the briefing.

47

Page 48: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

LICENSEE BRIEFING

• The Site Team will wait no more than 10-15 minutes to be briefed. If the licensee does not respond in this time frame, the Site Team Director will lead the team into the Emergency Operations Facility and begin functional co-location.

• The briefing should not last more than 15 minutes.The briefing should not last more than 15 minutes.

• The briefing should address the following:– Current situation– Concerns / issues / priorities– Repair and Mitigation Actions underway– Protective Action Decisions being implemented– Administrative info (telephone use instructions, telephone

directories, work locations, bathroom location, etc.)

48

Page 49: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

FUNCTIONAL CO-LOCATION

• After the licensee briefing, the Site Team will go into the Emergency Operations Facility and begin to locate their work locations.

• Staff with computers will begin setting up the computers / printers and hooking up to analog telephone lines.

• Staff who will be on “continually open” lines will usually install corded headsets.

• Staff that need to be mobile while on the telephone will usually install cordless telephones if they are permitted in the licensee’s facility.

49

Page 50: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

TURNOVER TO THE SITE TEAM

• Site Team Members will get a short briefing from their licensee counterparts.

• Site Team Members will get a turnover briefing from their• Site Team Members will get a turnover briefing from their Headquarters / Regional counterparts via telephone call.

• When the equipment has been set up and briefings complete, team members should inform the Site Team Director that they are ready to respond.

• The Site Team Director will inform the “Chairman” that the Site Team is ready for turnover.

50

Page 51: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

MANAGEMENT BRIEFINGS

• The “Chairman” will typically want to be briefed by the licensee’s Emergency Director about an hour after the Alert declaration with additional briefings every 2 hours (unless something changes).

• The “Chairman” will want to be briefed by the licensee’s Emergency Director about 30 minutes after going to a Site Area Emergency and General Emergency.

• The “Chairman” will want to talk to the Site Team Director and Emergency Director soon after the Department of Homeland Security declares an Incident of National Significance.

51

Page 52: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

QUESTIONS?

Page 53: NRC LICENSEE ONTROL CELL TRAINING · T1 + 6 hours = Site Team arrival time at local airport T1 + 6.5 hours = Site Team departs local airport T1 + 8 hours = Site Team arrives on site

Jason Kozal

Senior Emergency Response Coordinator

Contact

g y p

USNRC - Headquarters

301.415.6231

[email protected]

53