![Page 1: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/1.jpg)
Recommendation to the Superintendent
Presented by the Building Future Task ForceNovember 18, 2019
![Page 2: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/2.jpg)
THE TASK FORCE
Parents Community Members D34 Staff
Beth Conlon Angie Khuyag Jill Brickman Marvin Lutz Katie Dahmer
Sven Dahlquist Monica Luna Mandy Chiarieri Nancy Morgan Kevin Dorken
Vanessa De la Cruz Shiva Mohsenzadeh Cathy Cunningham Pastor Chris Neptun Melissa Feiger
Jane Devine Michael Moylan Richard Kreutzfeld John Nicolau Erik Friedman
Dana Doffin Betsy Nelson Jackie Lutz Daniel Toy Karen Hitzeman
Edith Figueroa Nima Onchig Jason Kaiz
Brandy Isaac Scott Southwood Community Partners Alison Keller
Alex Kamilewicz Jancey Straseske Karen Coan Nanette Ross-Meridith
Steve Toomey Craig Solomon Katie Siegel
![Page 3: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/3.jpg)
The Process
![Page 4: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/4.jpg)
Meeting #1
August 6, 2019 | Springman Middle School
● District bus tour, tour of Springman & Westbrook● History of referenda in D34● Current state of District 34● Overview of facilities
○ Facility assessment and space utilization studies○ Proposed solutions
● Financial considerations, CFAC recommendations● Understanding the community engagement process
![Page 5: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/5.jpg)
Meeting #2
August 22, 2019 | Lyon Elementary School
● Tour of Lyon (oldest D34 school)● More in-depth look at facility needs and possible solutions● Considerations of full-day kindergarten● How environment impacts education ● Table discussions on environment, FDK, tax impact● Task Force input guided community engagement sessions
![Page 6: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/6.jpg)
Regular Updates Provided
Email updates on:
● Community & staff engagement sessions● Schematic design● Financing● Preview of mailers/video, surveys, polls
![Page 7: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/7.jpg)
Meeting #3
November 12, 2019 | Attea Middle School
● Review updates on schematic design, financing, tax impact● Recap community engagement, survey and polling ● Small group discussions● Large group consensus
Recommendation & Considerations
![Page 8: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/8.jpg)
The Data
![Page 9: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/9.jpg)
Community Engagement
● 4 community meetings, approximately 150 attendees● 3 staff engagement sessions● Feedback during Q&A, gallery conversations● Presentation posted online and promoted for entire
community● Polco online
![Page 10: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/10.jpg)
Polco Online: Early Data
107 Informed Respondents (attended sessions or reviewed video/presentation/materials)
● Schools Are Important: ○ 87% reported that schools were one of the top two
reasons they moved to Glenview○ 92% said that maintaining quality schools is important
● Trust: 86% believe that the District is a good steward of tax resources
● 70% on FDK: 50% strongly support / 20% support
![Page 11: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/11.jpg)
Mail Survey
1,620 Responses (11% response)Qualitative - Not Scientific
● Modest Awareness of Proposal: 53% are aware● Soft Support Overall: 50% definitely/probably support
proposal● District Grade: 62% gave the District a grade of A or B● Trust/Confidence: 55% are confident in responsibility
for taxpayer money
![Page 12: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/12.jpg)
Mail Survey
● Tax Sensitivity: 61% are extremely/very concerned about the estimated tax impact of $139M proposal
● Priority of Funding:
![Page 13: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/13.jpg)
Phone/Email Poll236 Likely Voters
Scientific Poll +/- 6.38% margin of error
54% probably/definitely yes for $139M (full) proposal
Likely Yes:
● 77% of Democrats likely yes● 37% Republicans likely yes● 38% Independents likely yes
![Page 14: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/14.jpg)
Phone/Email Poll
Support of Full Proposal
● Women 18-54: 67%● Voters with Children in D34
Schools: 63%
![Page 15: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/15.jpg)
Phone/Email Poll
Funding Priorities / Support of Full-Day Kindergarten
![Page 16: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/16.jpg)
Phone/Email Poll
Support Decreases After Tax Impact Information
![Page 17: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/17.jpg)
Key Influencers● There’s support at $139M - but it’s soft support (54%)
○ Key demographics soft support (Parents, 63%)● Election Timing
○ March has more favorable voters, no competing tax● High Trust in District ● High Tax sensitivity● “We listened” sends the right message, respects voters
We can’t give voters everything they want with what they’re willing to pay
![Page 18: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/18.jpg)
The Options
![Page 19: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/19.jpg)
Full Plan
Includes all work at all buildings
(Facility Assessment & Priority 1 work)
Full PlanSource of Funds Amount
Referendum Debt $139,000,000
Operations & Maintenance $1,200,000
Non-Referendum Debt $9,380,000
Fund Balance (10%) $16,311,998
TOTAL PROJECT COST $165,891,998
Tax Impact (per 10K of tax bill) $576.87
![Page 20: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/20.jpg)
Repairs and Renovations Only
Does not address enough of the critical needs
Repairs & Classroom Renovations OnlySource of Funds Amount
Referendum Debt $54,220,000
Operations & Maintenance $1,200,000
Non-Referendum Debt $9,380,000
Fund Balance (10%) $7,200,000
TOTAL PROJECT COST $72,000,000
Referendum Debt Reduction ($84.8M)
Tax Impact (per 10K of tax bill) $228.00
![Page 21: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/21.jpg)
Eliminate Springman Renovation
Not an option:
● Springman is functionally obsolete
● Perpetuates inequities
Eliminate Springman RenovationSource of Funds Amount
Referendum Debt $96,700,000
Operations & Maintenance $1,200,000
Non-Referendum Debt $9,380,000
Fund Balance (10%) $12,100,000
TOTAL PROJECT COST $120,380,000
Referendum Debt Reduction ($41.3M)
Tax Impact (per 10K of tax bill) $410.00
![Page 22: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/22.jpg)
No Full-Day Kindergarten
Not a big enough decrease in tax impact
No Full Day KindergartenSource of Funds Amount
Referendum Debt $126,400,000
Operations & Maintenance $1,200,000
Non-Referendum Debt $9,380,000
Fund Balance (10%) $14,900,000
TOTAL PROJECT COST $151,880,000
Referendum Debt Reduction ($12.6M)
Tax Impact (per 10K of tax bill) $530.00
![Page 23: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/23.jpg)
The Recommendation
![Page 24: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/24.jpg)
Clear ConsensusIncludes:
● All work at Springman● All classrooms renovated● Facility assessment work● No additions● No work to
Admin Building
Consider This:
● Move below $100M
No Additional Space & No FDKSource of Funds Amount
Referendum Debt $101,372,798
Operations & Maintenance $1,200,000
Non-Referendum Debt $9,380,000
Fund Balance (10%) $12,439,200
TOTAL PROJECT COST $124,391,998
Referendum Debt Reduction ($37.5M)
Tax Impact (per 10K of tax bill) $426.00
![Page 25: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/25.jpg)
Why?
This Solution Can Pass● Every classroom. Every building. Every Student.
○ Learning Spaces Updates ○ Visible, tangible solution○ Honoring teachers’ wishes, student needs
● Springman: Addresses inequity and functionality● Aligns with District 34’s Strategic Plan● Recognizes voter reality:
○ High tax sensitivity○ Soft support of full $139M ○ Weak support of FDK
![Page 26: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/26.jpg)
Additional Considerations
● Wording of ballot question● Information campaign: District● Advocacy campaign: Community
![Page 27: November 18, 2019 Presented by the Building Future Task Forcef… · Tour of Lyon (oldest D34 school) More in-depth look at facility needs and possible solutions Considerations of](https://reader034.vdocuments.us/reader034/viewer/2022051921/600ec3e7fbc7e41ef95ed548/html5/thumbnails/27.jpg)
Thank You!