NOTICE OF PUBLIC MEETING
BOARD OF DIRECTORS
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
SEPTEMBER 10, 1992
8:30 A.M.
CLARK COUNTY COMMISSION CHAMBERS
225 EAST BRIDGER AVENUE
LAS VEGAS, NEVADA 891 55
FOR ADDITIONAL INFORMATION CONTACT:
VIRGINIA BAX-VALENTINE, P.E., GENERAL MANAGER
301 EAST CLARK AVENUE, SUITE 301
LAS VEGAS NEVADA 89101
455-31 39
POSTED: SEPTEMBER 4, 1992
CITY OF NORTH LAS VEGAS 2200 CIVIC CENTER DRIVE NORTH LAS VEGAS, NV 89030
CLARK COUNTY BRIDGER BUILDING 225 EAST BRIDGER AVENUE LAS VEGAS, NV 89155
CITY OF U S VEGAS CITY HALL 400 EAST STEWART U S VEGAS, NV 89101
REGIONAL FLOOD CONTROL DISTRICT 301 EAST CLARK, SUITE 301 LAS VEGAS, NV 89101 I
' 1 T . 7 f .- T--
AGENDA
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT BOARD OF DIRECTORS SEPTEMBER 10, 1992
1. CALL TO ORDER AND MINUTES
2) ACTION TO APPROVE THE MINUTES OF THE REGULARLY SCHEDULED MEETING OF AUGUST 13, 1992
II. DESIGN AND CONSTRUCTION
3) ACTION TO APPROVE A REQUEST FROM CLARK COUNTY FOR ' CHANGE ORDER NO. 2 FOR THE VAN BUSKIRK CHANNEL
/
4)- VAN BUSKIRK CHANNEL
A) ACTION TO ACCEPT A PRESENTATION BY CLARK COUNTY FOR THE VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS - DETENTION BASIN SITE "C"
B) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE INTERLOCAL CONTRACT FOR CONSTRUCTION OF
DETENTION BASIN SITE "C" THE VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS -
5) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN 1 THE INTERLOCAL CONTRACT FOR DESIGN OF THE CHEYENNE
CHANNEL - BUFFALO DRIVE TO THE GOWAN SOUTH DETENTION BASIN
6) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN / THE SEVENTH SUPPLEMENTAL INTERLOCAL CONTRACT FOR THE
HEMENWAY VALLEY WASH IMPROVEMENTS
7 ) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE SECOND SUPPLEMENTAL INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE GOWAN DETENTION SYSTEM
RFCD Board Agenda Page 2 September 10, 1992
8 ) ACTION TO APPROVE A REQUEST FROM THE CITY OF NORTH LAS VEGAS FOR CHANGE ORDER NO. 1 FOR THE LAS VEGAS WASH
9) ACTION TO APPROVE A REQUEST BY CLARK COUNTY FOR A VARIANCE FROM THE UNIFORM REGULATIONS FOR THE CONTROL
LAUGHLIN, NEVADA OF DRAINAGE - ELEVATION REQUIREMENT AT 3699 CATALINA,
111. ADMINISTRATION
10) REVlEW/DISCUSSION AND POSSIBLE ACTION TO APPROVE AMENDMENTS TO THE POLICIES AND PROCEDURES MANUAL - 1992
11) RECEIVE A REPORT REGARDING PROJECTS ON WHICH AESTHETIC ENHANCEMENTS MAY BE REQUIRED AND DIRECT STAFF AS DEEMED APPROPRIATE
12) DISCUSSION AND POSSIBLE ACTION TO AUTHORIZE THE GENERAL MANAGER TO DIRECT THE DISTRICT ATTORNEY’S OFFICE TO REPRESENT THE REGIONAL FLOOD CONTROL DISTRICT IN MATTERS RELATED TO THE KERN RIVER GAS PIPELINE
13) ACTION TO ACCEPT THE PROJECT STATUS REPORTS
14) ACTION TO ACCEPT THE FINANCIAL REPORTS
15) CITIZENS PARTICIPATION No action can be taken on any matter discussed under this item, although the Board can direct that it be placed on a future agenda
MINUTES CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
BOARD OF DIRECTORS AUGUST 13, 1992
MEETING NOTICES: Public Notices of the meeting were posted August 7, 1992, by Jon Downer of the Regional Flood Control District in the following locations: Las Vegas City Hall, North Las Vegas City Hall, Clark County Bridger Building, and the Clark County Regional Flood Control District offices.
Public Notices of the meeting were also mailed on August 6, 1992 to the cities of Boulder City, Henderson, Laughlin, and Mesquite for posting on community notice boards.
MEMBERS PRESENT: Michael R. Harris, Chairman, City of Henderson Thalia Dondero, Vice-chairman, Clark County Iris Bletsch, City of Boulder City Bruce Woodbury, Clark County Jan Laverty Jones, City of Las Vegas Tom R. Leavitt, City of Mesquite Theron Goynes, City of North Las Vegas
MEMBERS EXCUSED: Scott Higginson, City of Las Vegas
STAFF: Virginia Valentine, General Manager Gale Wm. Fraser II, Assistant General Manager Deanna Lefko, Management Analyst I Chris Figgins, Deputy District Attorney Timothy E. Sutko, Senior Hydrologist Dennis Johnson, Manager, Business & Finance Catherine Razor, Project Administration Coordinator Chrisell Anderson-Jones, Word Processor
INTERESTED PARTIES: Martin Manning, Clark County Public Works Mark Teepan, City of Las Vegas Public Works Ken Gilbreth, VTN Nevada
Board Minutes August 13, 1992 Page 2
1. CALL TO ORDER AND MINUTES
The meeting was called to order at 8:34 a.m.
Commissioner Dondero moved to approve the agenda. There being' no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
2) ACTION TO APPROVE THE MINUTES OF THE REGULARLY SCHEDULED MEETING OF JULY 9. 1992
Commissioner Dondero moved to approve the minutes. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
111. PLANNING
3) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN A CONTRACT WITH JAMES M. MONTGOMERY ENGINEERS, INC. FOR PREPARATION QF THE MOAPA VALLEY MASTER PLAN UPDATE
Ms. Valentine stated that staff negotiated a professional services contract in the amount of $1 20,000 with James M. Montgomery Engineers, Inc. to prepare a routine Master Plan update for the Moapa Valley. The contract was reviewed by the District Attorney's office and staff recommended approval.
Councilman Goynes moved for approval. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
At the request of the District Attorney, this item was ratified later in the meeting with Commissioner Woodbury and Mayor Jones being present,
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 3
4) ACTION TO APPROVE AND AUTt 4ORIZE THF CHAIRMAN TO SIGN A SUPPLEMENTAL AGREEMENT WITH DAMES & MOORE FOR PREPARATION OF ENVIRONMENTAL ASSESSMENTS FOR THE FLOOD CONTROL FACILITIES JDENTlFlED FOR GOODSPRINGS AND SFARCHI ,IGHT. NEVADA
Ms. Valentine explained that staff had negotiated an amendment to the original contract to provide Environmental Assessments that would not require additional funding. The cost for these services is 575,897; however, they will be provided without increasing approved funding under the existing contract. The District Attorney has reviewed the amendment and staff recommended approval.
Councilman Goynes moved for approval. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
5) ACTION TO APPROVE A REQUEST BY CLARK COUNTY FOR A VARIANCE FROM THE UNIFORM REGULATIONS FOR THE CONTROL OF DRAINAGE FOR 3699 CATALINA, LAUGHLIN. NEVADA
Chairman Harris said that he understood this item is to be continued to the next regular meeting. Ms. Valentine stated that staff requests the item be held pending receipt of additional information from Clark County Public Works on the specifics of the variance requested.
Commissioner Dondero moved that this item be held for consideration at the next regular meeting. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
111. DESIGN AND CONSTRUCTION
Ms. Valentine said that without a two-thirds vote (six members), the Board would not be able to take action to approve interlocal contracts. She suggested that consideration of items #6 through #8C be postponed until the expected arrival of another Board Member.
Board Minutes August 13, 1992 Page 4
6) ACTION TO APPROVE AND AUTHOqllE THE CHAIRMAN TO SIGN THE FIRST SUPPLEMENTAL INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE GOWAN PETENTION SYSTFM
(Item held for consideration later in the meeting.)
7 ) BUFFALO CHANNEL - SUMMERLIN PARKWAY TO VEGAS DRIVE
A) ACTION TO ACCEPT A PRESENTATION FROM THE CITY OF LAS VEGAS ON THE BUFFALO CHANNEL - SUMMERLIN PARKWAY TO VEGAS DRIVE
(Presentation held for later in the meeting.)
B) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO-SIGN THE INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE BUFFALO CHANNEL - SUMMERLIN PARKWAY TO VEGAS DRIVE
(Item held for consideration later in the meeting.)
8 ) MEADOWS - ALTA STORM DRAIN
A) ACTION TO ACCEPT A PRESENTATION FROM THE CITY OF LAS VEGAS ON THE MEADOWS - ALTA STORM DRAIN (MEADOWS - PHASE V STORM DRAIN)
(Presentation held for later in the meeting.)
B) ACTION TO APPROVE A REQUEST FROM THE CITY OF LAS VEGAS TO RE-PRIORITIZE PROJECTS ON THE DISTRICT’S 10-YEAR PLAN AND THE FISCAL YEAR 1992/93 PROJECT LIST
(Item held for consideration later in the meeting.)
C) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE MEADOWS - ALTA STORM DRAIN (MEADOWS - PHASE V STORM DRAIN)
(Item held for consideration later in the meeting.)
Board Minutes August 13, 1992 Page 5
9) ACTION TO APPROVF A RFQUEST FROM THE CITY OF LAS VEGAS TO RE- PRIORITIZE PROJECTS ON THE DISTRICT'S 1 O-YEAR PLAN AND THE FISCAL YEAR 1992/93 PROJECT LIST (FREEWAY CHANNEL - SAHARA AVENUE TO IVANHOE WAY)
Ms. Valentine stated that a significant savings will be realized if the portion of the channel which lies under Sahara Avenue is constructed before the Interchange is built. Staff recommended approval of the re-prioritization of this project.
Councilman Bletsch moved for approval. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
10) LOGAN WASH CHANNEL
A) ADOPTION OF CLARK COUNTY'S RECOMMENDATION TO APPROVE A RIGHT-OF-WAY ACQUISITION NEGOTIATED SETTLEMENT FOR THE LOGAN WASH CHANNEL Generally located in the S 1 /2 of the SE 1/4 of Section 27, Township 15S, Range 67E. Proposed settlement is dedicated right-of-way exchange for modifying the plans for the project. Parcel No. 690-800-001. Owner: Carson Wayne Newton
Ms. Valentine stated that as a part of the settlement negotiated for the right-of-way acquisition, a construction change was made to the project. Staff recommends approval of the negotiated settlement and the change order to facilitate the settlement.
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: . 5 AYES - 0 NAYS
B) ACTION TO APPROVE A REQUEST FROM CLARK COUNTY FOR CHANGE ORDER NO. 1 FOR THE LOGAN WASH CHANNEL
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 6
Councilman Bletsch asked if the Special Technical Advisory Committee had met and discussed this item. Ms. Valentine said that the Special Technical Advisory Committee had met and recommended approval of both items A & B. She modified staff's recommendation for approval to be subject to approval of the interlocal contract (item 1 OC). Chairman Harris acknowledged staff's modified recommendation.
. 'e
C) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE FIRST SUPPLEMENTAL INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE LOGAN WASH CHANNEL, MOAPA VALLEY
(This item was held for consideration later in the meeting.)
11) VAN BUSKIRK CHANNEL
A) ACTION TO ACCEPT A RECOMMENDATION FROM CLARK COUNTY FOR AWARD OF BID FOR THE VAN BUSKIRK CHANNEL PHASE 111 PROJECT
Ms. Valentine stated that staff recommends acceptance of the County's recommendation for Award of Bid to Professional Contracting, Inc. in the amount of $778,060.
Commissioner Dondero motioned for approval. There being no further discussion, the motion carried.
VOTE: 5 AYES - 0 NAYS
(Commissioner Woodbury arrived 8:40 a.m.).
It is hereby noted that with Commissioner Woodbury's arrival, the required f Board members were present to authorize approval of interlocal
B) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE FIRST SUPPLEMENTAL INTERLOCAL CONTRACT FOR DESIGN OF THE VAN BUSKIRK CHANNEL IMPROVEMENTS
Chairman Harris motioned for approval. There being no further discussion, the motion carried.
VOTE: 6 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 7
6) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE FIRST SUPPLEMENTAL INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE GOWAN DETENTION SYSTEM
Ms. Valentine stated that staff recommends approval of the City of Las Vegas' request for a first supplement interlocal contract which reduces the funding due to favorable bids. The return of $3.4 million to the Bond Fund (444) will be available for reappropriation.
Councilman Bletsch moved for approval. There being no further discussion, the motion carried.
VOTE: 6 AYES - 0 NAYS
7 ) BUFFALO CHANNEL - SUMMERLIN PARKWAY TO VEGAS DRIVE
A) ACTION TO ACCEPT A PRESENTATION FROM THE CITY OF LAS VEGAS ON THE BUFFALO CHANNEL - SUMMERLIN PARKWAY TO VEGAS DRIVE
Ken Gilbreth, VTN Nevada (engineering consultant for this project), gave the presentation. Commissioner Dondero stated, for clarification, that only the box culvert over the Washington area is going to be open channel through Vegas Drive. Mr. Gilbreth concurred.
B) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE BUFFALO CHANNEL - SUMMERLIN PARKWAY TO VEGAS DRIVE
Ms. Valentine stated that staff recommends approval.
Commissioner Woodbury moved to accept the presentation and approve the interlocal contract. There being no further discussion, the motion carried.
VOTE: 6 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 8
8) MEADOWS - ALTA STORM DRAIN t
A) ACTION TO ACCEPT A PRESENTATION FROM THE CITY OF LAS VEGAS ON THE MEADOWS - ALTA STORM DRAIN (MEADOWS - PHASE V STORM DRAIN)
Mark Teepan from the City of Las Vegas gave the presentation. Councilman Bletsch asked if this phase had not yet been constructed due to a lack of funding. Mr. Teepan explained that Part A and Part B, depicted in the exhibit as being the upper and lower ends, were constructed before funding ran out, and the contractor can piggyback construction of Part C, giving the appearance of a continuation of the same project.
B) ACTION TO APPROVE A REQUEST FROM THE CITY OF LAS VEGAS TO RE-PRIORITIZE PROJECTS ON THE DISTRICT'S 10-YEAR PLAN AND THE FISCAL YEAR 1992/93 PROJECT LIST
Ms. Valentine stated that staff recommends approval of the re-prioritization of the project. This action will reduce project costs and eliminate costs associated with ripping up the street, if constructed at a later date.
Councilman Bletsch moved to accept the presentation and approve re-prioritization. There being no further discussion, the motion carried.
VOTE: 6 AYES- 0 NAYS
C) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE MEADOWS - ALTA STORM DRAIN (MEADOWS - PHASE V STORM DRAIN)
Chairman Harris moved for approval. There being to further discussion, the motion carried.
VOTE: 6 AYES - 0 NAYS
(Mayor Jones arrived at 8:47 a.m.)
Ms. Valentine advised the Board that the District Attorney requested a ion of items #3 and #4 since seven members of the Board were now
Board Minutes August 13, 1992 Page 9
10) LOGAN WASH CHANNEL
C) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE FIRST SUPPLEMENTAL INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE LOGAN WASH CHANNEL, MOAPA VALLEY
Ms. Valentine stated that staff recommends approval.
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
12) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE FIRST SUPPLEMENTAL INTERLOCAL CONTRACT FOR CONSTRUCTION OF THE UNION PACIFIC RAILROAD CHANNEL
Ms. Valentine stated that staff recommends approval of the first supplemental interlocal contract to fund additional work on the Union Pacific Railroad Channel. This action does not increase funding approved in the original interlocal contract.
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
13) ACTION TO APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE FOURTH SUPPLEMENTAL INTERLOCAL CONTRACT FOR THE LAS VEGAS WASH BETWEEN CRAIG ROAD.AND CIVIC CENTER DRIVE
Ms. Valentine stated that staff recommended approval of the request to fund additional expenses incurred during construction, to facilitate final payments, and to close out the project.
Councilman Goynes moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 10
14) ACTION TO APPROVE A REQUEST FROM THE CITY OF BOULDER CITY FOR
[MPROVEMENTS y N R N .
Ms. Valentine stated staff recommends approval of the change -order. The net increase to the construction contract is 8149,970.37 and includes adjustments for utility conflicts and rock excavation.
Councilman Bletsch moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
15) ACTION TO APPROVE A REQUFST FROM THE CITY OF LAS V m S FOR CONTRACT MODIFICATION NO. 1 ON THF WASHINGTON AVENUE C0NVEYANC;r SYSTEM - SANDHILL ROAD OUTFALL STRUCTURE
Ms. Valentine said the contract modification will decrease the interlocal in the amount of $30,976 and staff recommends approval.
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
IV. ADMINISTRATION
16) J3lSCUSSlON AND POSSIBLF ACTION TO AUTHORIZE THE GENERAL MANAGER TO SUBMIT A BILL DRAFT REQUFST
Ms. Valentine said that at the request of the Board at the July -9 meeting, staff prepared a Bill Draft Request. She explained that if submitted and passed, this legislation will allow an entity to proceed with a project after approval by the District and the entity in which any or all of the project is located. The District Attorney's office has reviewed the language.
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 11
17) ACTION TO APPROVE AN AMENDMENT TO SECTION 34.030 (c) OF THE UNIFORM EGULATIONS FOR THE CONTROL OF DRAINAGE,
Ms. Valentine stated the Uniform Regulations for the Control of Drainage include a passage that requires finished grade contours on grading plans. Local consultants were opposed to this requirement. The consultants contended that the information could be conveyed correctly without the additional cost of adding finished contours.
Ms. Valentine further explained that the proposed amendment would provide consultants with the option of utilizing sufficient spot elevations or finished grade contours on grading plans. The amendment was reviewed by the District Attorney’s office, and staff recommended approval.
Councilman Bletsch moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
18) plSCUSSlON AND POSSIBLE ACTION TO APPROVE AN AMENDMENT TO SECTION 6.1 (f) OF THE DISTRICT’S POI ,lClES AND PROCEDURES
Ms. Valentine said that at the direction of the Board, staff had drafted an amendment to the Policies and Procedures Manual which would clarify the manner in which requests for landscaping and aesthetic enhancements are made. Specifically, that at the time an entity requested funding for landscaping or aesthetic enhancement, specific plans, cost estimates, and scope of work would be detailed in the interlocal contract.
Chairman Harris said that while he personally does not support the idea, the Board needs more information concerning the specifics surrounding the funds being requested for landscaping and aesthetic enhancements.
Commissioner Dondero suggested that the District and the entity building the project contribute equally in funding aesthetic enhancements. By incorporating a’”matching funds” policy, all entities would be able to receive District funds for projects requiring landscaping and aesthetic enhancements.
Councilman Bletsch reiterated the issues involved with approving landscaping and aesthetic enhancements as part of a flood control project, and the importance of minimizing this type of funding altogether.
.. .* - - r -
Board Minutes August 13, 1992 Page 12
.~ ‘k
Ms. Valentine explained the purpose of this policy is to provide the Board with detailed information at the time a request for funding is presented, enabling the Board to make that decision at the onset of a project.
Councilman Leavitt inquired if staff had analyzed upcoming projects to determine which may fit this criteria. Ms. Valentine said that an analysis had not been made, but that staff would provide the Board with a report on the review of aesthetic enhancement costs associated with upcoming projects. ‘With that information, an item would be presented to discuss Commissioner Dondero‘s suggestion of “matching funds.”
Chairman Harris said that the proposed language change will provide the Board with better information concerning what is specifically being requested. Meanwhile, he requested a more in-depth look into the issue of funding landscaping and aesthetic enhancements.
Councilman Bletsch moved for approval of the proposed language for landscaping and aesthetic enhancement of projects, and requested an investigation of and a report on the methodology of funding these expenses, There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
19) ACTION TO ACCEPT THE FOURTH QUARTER STATUS REPORTS FOR FY 1991 /92 ANNUAL MAINTENANCE WORK PROGRAMS IN CLARK COUNTY AND THE CITIES OF BOULDER CITY, HENDERSON, LAS VEGAS, MESQUITE, AND NORTH LAS VEGAS
Ms. Valentine stated these are the final Quarter reports for FY 91/92. Staff is in the process sf closing out those maintenance work plans which had not been committed, and carrying them over to FY 1992/93 plans. Chairman Harris requested that all entities complete their close outs and move into the current FY 1992/93 budget.
Chairman Harris moved for approval. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
Board Minutes August 13, 1992 Page 13
20) ACTION TO ACCEPT THE PROJECT STATUS REPORTS
Ms. Valentine stated there are 28 projects complete to date, 10 currently under construction, and about 23 in design or awaiting start of construction. She cited the significant milestones reached during the month of July in project completions and starts. Ms. Catherine Razor gave a brief overview of the status of the projects.
Chairman Harris moved to accept the Project Status Reports. There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
Ms. Valentine stated that the project delay reports indicated those projects which were experiencing delays since the previous quarter. She noted that the delays were primarily due to circumstances outside of the District's control, such as weather and right-of-way negotiations. Ms. Valentine said that since the tabulation of the report, two projects had already been completed, Pittman Wash Channel Phase 2 and Town Wash Detention Basin.
Chairman Harris requested that the Board be made aware of any projects which may be experiencing insurmountable problems causing delays. He said there may be a need to re-prioritize such projects and return approved funding for reallocation in the interim.
Commissioner Dondero inquired about the Winnick Avenue delay, noted due to coordination with Imperial Palace. Martin Manning, Clark County Public Works Director, explained that because of the owners' concerns with disturbance under the hotel, hydraulic modeling had been requested. He said there is a need to safely capture and convey a large quantity of flowing water to the Flamingo Wash. At this time, they were at a 90 percent level of design completion.
Chairman Harris asked if the District had an alert system in place which would allow the Imperial Palace enough time to move parked vehicles in the event of a storm. Ms. Valentine assured the Board that the District works very closely with the management of the Imperial Palace. In addition to placing a number of rain gauges in the area and constant communications during an event, the District may give them direct access to the flood warning system.
Board Minutes August 13, 1992 Page 14
Commissioner Dondero inquired about the intake capabilities of the design and Councilman Bletsch noted concern about washed-away vehicles. Mr. Manning explained that the project is being designed to handle the forceful stormwaters experienced in that area, and to keep the water and debris contained and off the street.
Chairman Harris noted there was no action on this item, it was informational only.
22) ACTION TO ACCEPT THE FlNANClAl REPORTS
Ms. Valentine said the usual monthly Financial Reports were in order for approval. Chairman Harris asked for an explanation concerning Clark County's withdrawal of approximately $616,678 District Funds. Ms. Valentine explained that in monthly payments by the County for interest earned, it appeared an overpayment accrued in Fund 286. To correct the undetected windfall, the County deducted the overpayment from Fund 286. She added that the current fund balances were such so as not to affect any of the actions taken by the Board at this meeting, and that next month's financials would reflect the fund's change.
Commissioner Dondero moved for acceptance. There being. no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
23) ACTION TO ACCEPT THE FINAL ACCOUNTING REPORT AND THE PROJECT CLOSE OUTS
Ms. Valentine said that 6 project close outs will return 8228,876,87 to Fund 286 for future allocations on new projects.
Chairman Harris moved for acceptance of the report and close outs. .There being no further discussion, the motion carried.
VOTE: 7 AYES - 0 NAYS
24) N
There was none.
Board Minutes August 13, 1992 Page 15
ADJOURNMENT
There being no further business, Chairman Harris adjourned the meeting at 9:12 a.m.
Respectfully submitted,
VIffiUhIA VALENTINE, P.E. GENERAL MANAGERKHIEF ENGINEER
Attest: 1992
MICHAEL R. HARRIS CHAIRMAN
r~ T
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJECT:
VAN BUSKIRK CHANNEL OUTFALL - CHANGE ORDER NUMBER 2
~~~~ ~
(CLA.03.B.90)
RECOMMENDATION SUMMARY
STAFF: Approve.
TECHNICAL C 0 M " E E : Approve.
CITIZENS COMMITTEE: Approve.
RFCD AGENDA
Date: 9110192
CLARK COUNTY
REGIONAL FU)OD CONTROL DISTRICT
AGENDA I” ._ ‘k
SuBJErn.
VAN BUSKIRK CHANNEL OUTFALL
I PETITIONER M. J. MANNING, DIRECTOR OF PUBLIC WORKS
RECOMMENDATION OF PETITIONER
THAT THE REGIONAL FLOOD CONTROL DISTRICT APPROVE CHANGE ORDER NUMBER 2 TO THE CONTRACT TO CONSTRUCT THE VAN BUSKIRK CHANNEL OUTFALL, BID NO. 2554-91.
FISCAL IMPACX Current interlocal contract funding is sufficient to cover change order number 2 in the amount of $85,209.21.
BACKGROUND:
This Change Order represents an adjustment of bid quantities to reflect actual quantities used in the amount of $62,200.81. Also included is a change in scope of work required at a junction structure for an increase of $24,438.40, and a credit of $1,130.00 for’a reduction in the size of manholes.
The work and associated cost have been reviewed by the Consultant and Public Works staff and are felt to be equitable.
TM: AGE- RFCD AGE- I”&M# 6A
D8te: 9/10/92 D8ta 0 8 / 2 7 / 9 2 ITEM# 3
~~~~
M‘J J. BLIC WORKS
MJM:GC:slh
Regional Flood Control District AGENDA ITEM DEVEIBPMENT
Staff Discussion: [ Date: 8/19/92
VAN BUSKIRK CHANNEL OUTFALL - CHANGE ORDER NUMBER 2 (CLA.03.B.m)
Clark County has negotiated a change order for the Van Buskirk Channel project. The change order represents an adjustment of bid quantities to reflect as-built quantities and includes extra work required at a junction structure. The net increase to the construction contract for Change Order Number 2 is $85,209.21. Current interlocal corrtract funding is sufficient to cover the increase.
Staff Recommendation:
Approve.
Discussion By Technical Advisory Committee I AGENDA # 6A Date: 8/27/92
Recommendation:
Approve.
Discussion By Citizens Advisory Committee I AGENDA # 6A Date: 8/31/92
Recommendation:
Approve.
CLARK COUNTY MMRTMENT OF PUBLIC WDRKS
PAOJECT NO. F900711 SHEET I . O F 2 CONWXl NO. 2554-91 DATE - - PROJECT NAME Van Buskirk Channel Out fa l l
Ig Contri Construction. , oontractor. You are hereby directed to make the herein doacribe changes fran the plans a n d . specifications, oz do the follawing described wark not included in the plans and opecifhtiars on this amtract.
Qwge requested Public Works
(1) Esthte of increases and/or decreases In amtract item at contract prices: Final Ouantity Accounting $62,200.81 .
Cred i t Manhole Size Reduction 10 EA 8 $113/EA S[1,130.00~ Remove and Replace Structure 0 Flamingo $24,438.40
,008.40
Original Oontract Sum . . . . . . . . . . . . . . . . . . . . . . . . . . . $199898.678.Q0. Net change by previously authorized cbnge Orders . . . . . . . . . . . . . $ 1 m 0 " mtal cost this Change Orfkr (increase) (decrease). . . . . . . . . . . . . $ 85-1 Net contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3.097.041.21 /
We, the undersigned Oontractmr, ha& given careful consideration to the changeprCsQ=dandhere$yagree,if this proposal is agprwed, that vn9 ,
w i l l provide all equiplwt, furnish al l materials, except as my otherrtfse be noted above, and perfom all aelxices necessary for the work atnm specified, and will accept as full paytent therefore the prices shum aboue..
of this pRopoad dwge,
1 be'all&&. days extension or of
CT ENGINEER
I' I i I 1
I I I I I
I
I I
I I I I I I I
I
c ?-
c
eUG-19-92
WE
D L4:17
I
1
P. b
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJECT:
VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS - PROJECT PRESENTATION (CLA.03.D.91)
RECOMMENDATION SUMMARY
STAFF: Accept the presentation.
TECHNICAL COMMITTEE: Accept the presentation.
CITIZENS COMMITTEE: Accept the presentation.
RFCD AGENDA ITEM# 4A
CLARK COUNTY
REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM .-
I VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS
PETITIONER M. J. MANNING, DIRECTOR OF PUBLIC WORKS
RECOMMENDATION OF PETITIONER:
THAT THE REGIONAL FLOOD CONTROL DISTRICT RECEIVE A PRESENTA- TION ON VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS BETWEEN THE INTERSECTIONS OF UNIVERSITY/MCLEOD AND HARMON/HARRISON, INCLUDING DETENTION BASIN utCtu.
FISCAL IMPACT: None
BACKGROUND:
The Regional Flood Control District has provided funding for the design of the Van Buskirk Channel Phase IV segment. The design is nearing completion and Clark County Public Works is prepared to make a presentation on the proposed improvements to the District.
MJM:WCB:slh
Regional Flood Control District AGENDA I T M DEVEIOPHENT
I
Staff Discussion: I Date: 8/19/92
VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS - PROJECT PRESENTATION (CLA.03.D.91)
In accordance with District Policies and Procedures and NRS 543.580, Clark County will make a presentation on the Van Buskirk Channel Phase N Improvements located between McLeod Drive and Harmon Avenue.
The presentation will also be made at the Citizens Advisory Committee meeting on August 31, 1992, at 3:30 p.m.
Staff Recommendation:
Accept the presentation.
~~~~ ~
Discussion By Technical Advisory Committee 1 AGENDA # 6B Date: 8/27/92
Recommendation:
Accept the presentation.
~~
Discussion By Citizens Advisory Committee I AGENDA # 6B Date: 8/31/92
Recommendation:
Accept the presentation.
PROJECT PRESENTATION
VAN BUSKIRU CHANNEL - PHASE N IMPROVEMENTS
In accordance w i t h the requirements o f NRS Chapter 543.580, we are now proposing t o proceed with Van Buskirk Channel Phase N Improvements which l i e between the intersections of University Avenue/McLeod Drive and Harmon Avenue/Harrison Drive, including Detention Basin " C t l ; fur ther ident i f i ed on accompanying Exhibits A, 8, and C which d e p i c t the overall phasing, Phase N limits, and neighborhood channel routing. Design Plans are 90% complete and have been reviewed b y County and Flood Control District s t a f f s .
These Phase N Improvements are identif ied on the Regional Flood Control District's 1991 Las Vegas Valley Master Plan Update a s Faci l i ty Nos. 0212, 0237, and 0238. I t i s a prioritized project scheduled f o r F a l l , 1992 construction a t an estimated cost of $1,072,000 for. construction and construction engineering. Funding w i l l be accomplished by 1991 flood control bonds w i t h a l l work t o be completed within 150 calendar days from construction s t a r t , subsequent t o an es t ima ted 11 /17 /92 b i d award.
Ac tual work consis ts o f s tart ing a t the two 9' x 5 ' Phase 111 reinforced concrete boxes a t the southwest corner of University Avenue/McLeod Drive (Exhibit * P ) by joining the boxes w i t h a rectangular reinforced concrete channel. This rectangular configuration continues upstream along University Avenue westerly incorporating an l l - f o o t channel bottom t o a point where it turns south between existing blockwalls a s a 12-foot wide rectangular channel t o Detention Basin r r C t l .
A unique feature of Detention Basin clC'l i s t h a t the channel continues a s a rectangular 8-foot wide concrete channel diagonally across the basin. This segment i s designed t o pass 650 c. f . s . while allowing any excess to sp i l l -o f f on e i ther side; t h u s functioning a s a "peaking" basin d u r i n g a 100-year return storm drain event. Spill-over i s accomplished 'by setting freeboard height t o t h e 650 c . f . s . flow and allowing stormwater flow over the sides onto gabion splashblocks . The bas in w i l l drain by means o f two 18-inch f l a p valves a f t e r channel flow subsides.
A direct b e n e f i t o f this construction w i l l be t o remove 100-year return storm flooding from single-family residences along Bunker Circle, Campus Circle, McLeod Drive, Zane Circle, and Van Buskirk Circle where approximately 50 houses could s u f f e r varying e f fec t s o f flooding. I f we consider t h a t flood losses may approach $2O,OOO per residence on the average; then approximately $1,000,000 would be saved per event by the proposed construction, not to mention eliminating the propensity for injury or loss o f l i f e during flood events.
ENGINEERING COST ESTIMATE: 90% SUBMITTAL
B I D SCHEDULE BASE B I D
I T E M APPROX. U N I T B I D NUMBER I T E M D E S C R I P T I O N Q T Y . U N I T P R I C E T O T A L
109.01 CONSTRUCTION CONFLICTS AND A D D I T I O N A L WORK 1 L S $30,000 $ 30,000.00
109.02
200.01
202.01
203.01
302.01
302.02
402.01
502.01
502.02
502.03
603.01
609.01
609.02
613.01
613.02
TEMPORARY FLOOD CONTROL 1 L S
M O B I L I Z A T I O N 1 L S
REMOVE STRUCTURES & OBSTRUCTIONS 1 LS
BASIN EXCAVATION 19,107 CY
TYPE I 1 AGGREGATE BASE (ROADWAY) 226 TON
TYPE I AGGREGATE BASE (ROADWAY) 508 TON
PLANTMIX BITUMINOUS SURFACE 283 TON
PNEUMATICALLY PLACED REINFORCED CONCRETE CHANNEL OR CAST I N PLACE REINFORCED CONCRETE CHANNEL 1 L S
12 ' X 6 ' PRECAST REINFORCED CONCRETE BOX 130 LF
CMU WALL 240 LF
24" DO.ol REINFORCED CONCRETE P I P E 66 LF
TYPE "C" DROP I N L E T L=12' D=5' 2 EA
TYPE "C" DROP I N L E T L=12' D=4' 2 EA
24" "L" TYPE CURB & GUTTER 204 LF
CONCRETE SIDEWALK 1,020 SF
$JOAJQ $ca-oD-aacr $ 20,000 $ 20,000.00
$180 .OOO $ 180,000.00
$ 3 $ 57,321.00
8 10 $ 2,260.00
$ 10 5,080.00
$ 35 $ 9,905.00
613.03 CONCRETE VALLEY GUTTER 534 S F $ 6 $ 3,XM-QQ
616.01 6 ' C H A I N L I N K FENCE 365 LF $ in $ 3,-
616.02 12 ' X 6 ' DOUBLE SWING GATE 3 EA $ 300 $ g n n m
623.01 250 W H.P.S. STREET LIGHT 1 EA $ 2.000 $ 2.000.00
624.01 TRAFFIC CONTROL 150 CAL DAYS $ 175 $ 26,250.00
661.01 GABION FOR OVERFLOW/EROSION PROTECTION 250 CY $ 85 $ 21,250.0Q
661.02 GABION RETAINING WALL 1,740 CY $ 10Q $ 174.-
.. '*
TOTAL $ 932,064.00
EXHIBIT "'A"
LEGEND L
m a m a a m
PROPOSED DETENTION BASIN SITE
PROPOSED CHANNEL/CULVERT ALIGNMENT
r' #*
I
L i
PHASE
.VAN BUSKIRK CHANNEL FLOOD CONTROL FACILITIES
- VANBUSK 9/28/90 Kn
. . . .
EXHIBIT "8"
LEGEND
PROPOSED DETENTION BASIN SITE - PROPOSED CHANNEL/CULVERT ALIGNMENT
FLAMINGO ROAD
ROCHELLE AVENUE
___t ARMON AVENUE
W
VAN BUSKIRK CHANNEL FLOOD CONTROL FACILITIES
VANBUSK 9/28/90 K l L
-e- SCALE 1'=80' EXHIsrT'C"
L CURVE TABLE DESC. D E LTA RADIUS LENGTH TANGENT CHORD
c1 88- 14-09 60.00 92.40 58.18 83.54 c10 34-09-42 50.00 29.8 1 15.36 29.37
---
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
RECOMMENDATION SUMMARY
STAFF: Approve subject to acceptance of the project presentation.
TECHNICAL COMMI'ITEE: Approve.
CITIZENS COMMITTEE: Approve.
RFCD AGENDA ITEM #4B Date: 9/10/92
CLARK COUNTY
REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUEJEKX
VAN BUSKIRK CHANNEL PHASE IV IMPROVEMENTS
I PEnTIONER M. J. MANNING, DIRECTOR OF PUBLIC WORKS
RECOMMENDATION OF PETITIONER
THAT THE REGIONAL FLOOD CONTROL DISTRICT APPROVE AND AUTHORIZE THE CHAIRMAN TO SIGN THE INTERLOCAL CONTRACT FOR CONSTRUCTION AND CONSTRUCTION ENGINEERING OF THE VAN BUSKIRK CHANNEL IV IMPROVEMENTS BETWEEN THE INTERSECTIONS OF UNIVERSITY/MCLEOD AND HARMON/HARRISON, INCLUDING DETENTION BASIN "C" .
FISCAL IMPACE $1,072,000.00 Total funded by Regional Flood Control
District (Fund 444).
BACKGROUND:
On January 9, 1992 an Interlocal Contract was entered into between Clark County and the Regional Flood Control District for preliminary engineering, engineering design and right-of-way engineering of the Van Buskirk Channel system improvements.
Ninety percent engineering design has been completed for this improvement. Therefore it is desirable to proceed with construction and construction engineering. This project phase will be constructed within existing right- of -way.
(Jd. J. MANNIN DIRECTOR OF WORKS MJM:WCB:slh
Regional Flood Control District AGENDA ITEX
I
Staff Discussion: Date: 8/19/92
VAN BUSKIRK CHANNEL PHASE IV - INTERLOCAL CONTRACT (CLA.03.G.92)
Clark County has submitted a request for an Interlocal Contract for construction and construction engineering of the Van Buskirk Channel Phase IV Improvements. The amount requested is $1,072,000. All right-of-way has been obtained and 90 percent plans and specifications have been submitted to the District. The Van Buskirk Channel is programmed on the Bond Project List. Funding is available from the Bond Fund (Fund 444).
Staff Recommendation:
Approve subject to acceptance of the project presentation.
Discussion By Technical Advisory Committee
Recommendat ion:
Approve.
Discussion By Citizens Advisory Committee AGENDA # 6C Date: 8/31/92
Approve.
INTERLOCAL CONTRACT VAN BUSKIRK CHANNEL
THIS INTERLOCAL CONTRACT made and entered into as of the day of , 1992 by and between the Clark County- Regional Flood Control District, hereinafter referred to as.,- "DISTRICT, and County of Clark hereinafter referred to as llCOUNTYtt.
-
W I T N E S S E T H
WHEREAS, pursuant to Chapter 543 of the Nevada Revised Statutes, the DISTRICT may approve a project to design and construct flood control improvements, and;
WHEREAS, the flood control improvements proposed herein are the same as those identified in the Master Plan Update, Structures No. VBCH 0212, 0237, and 0238 hereinafter referred to as ttPROJECTst; and
WHEREAS, the PROJECT is identified and shown on the attached Exhibit ltAtt; and
WHEREAS, the PROJECT has been approved by the DISTRICT on its annual project priority list; and
WHEREAS, the PROJECT has regional flood control significance and is located in the same hydrographic area as the Las Vegas Valley.
NOW, THEREFORE, in consideration of the covenants, conditions, contracts, and promises of the parties hereto, the DISTRICT and the COUNTY agree to the following:
SECTION I - SCOPE OF THE PROJECT This INTERLOCAL CONTRACT applies to construction and
construction engineering of improvements associated with the Van Buskirk Channel between the intersections of University/McLeod and Harmon/Harrison, including Detention Basin rrC**. The basic improvements shall consist of flood water control facilities including a detention basin, pipes, channels, channel structures, channel access and other appurtenances as may be necessary to control flood waters. The improvements shall be funded through DISTRICT funds as herein described. The PROJECT is further identified and shown on the attached Exhibit rtA1t.
Page 1 , VANBUSKIRK/WCB/7-21-92
SECTION I1 - PROJECT COSTS The DISTRICT agrees to fund PROJECT costs within the limits
specified below:
1. The contract administration, construction engineering, inspection, testing, and survey shall not exceed $75,000.
2. The cost of construction shall not exceed $997,000.
3. The total cost of this CONTRACT shall not exceed $1,072,000 which includes all the items described in paragraphs one and two above.
A written request must be made to the DISTRICT and a supplemental interlocal contract approved to increase any of the amounts noted above prior to payment of any addition funds.
SECTION I11 - GENERAL 1. The title sheet of both the plans and the specifications shall
show the Regional Flood Control District of Clark County as the funding agency.
2. The award of bid for the PROJECT shall occur no later than December 15, 1992. The COUNTY will take all reasonable steps possible to avoid delays in the construction of District funded projects. Project delays more than four months, as measured from the award date, may be subject to a formal review by both the Technical Advisory Committee and the District Board of Directors. At the review, the COUNTY will have an opportunity to present information relative to the delays, measures taken to avoid the delays and the likelihood of those delays continuing. The Board will make a determination, in view of the delays and limited available funding, whether project funding should continue. In the case that the Board chooses to discontinue funding, the Board may cancel any Interlocal Contract(s) associated with the PROJECT and discontinue funding for the remainder of the PROJECT. Funding already spent or appropriated by the COUNTY will not be required to be refunded to the District. PROJECT funding can be reconsidered at anytime when the COUNTY can demonstrate that the PROJECT can proceed on an acceptable schedule.
3. The COUNTY will comply with the Local Purchasing Act, Chapter 332 of the Nevada Revised Statutes.
4. The COUNTY, its employees, and representatives shall at all times comply with all. applicable laws, ordinances, statutes, rules, and regulations in effect at the time work is performed on the PROJECT.
5. The COUNTY will require appropriate financial security for the construction of the PROJECT.
6. The COUNTY shall provide all impacted entities and the DISTRICT with the opportunity to provide the COUNTY with input relative to the following processes: scope of services development; consultant selection; design, construction and maintenance review; and monitoring of the effectiveness and impacts of facilities on flood flows.
7. Applicable portions of the current editions of the Policies and Procedures, the Hydrologic Criteria and Drainage Design Manual, and Uniform Regulations for the Control of Drainage adopted by the DISTRICT will apply in developing this PROJECT unless specifically superseded by this CONTRACT.
8. Purchases of right-of-way in excess of that actually needed for construction will not be allowed unless a comparison between the cost of excess acquisition and needed acquisition including damages, indicates that benefits from such a transaction would result. Title to residual property will be vested in the name of the COUNTY. Revenues derived from the sale of these properties, less the cost of the sale of these properties, will be forwarded to the DISTRICT.
9. Administrative settlements and acceptance of counter offers involving right-of-way may only be made following a review and approval by the DISTRICT. .
10. The DISTRICT will make payment to the COUNTY, its contractor or its consultant , each month for project costs as outlined in SECTION I1 - PROJECT COSTS. Invoices must identify and allocate all costs to the categories noted below:
Page 3
a. Right-of -Way 1. Design & Surveying 2 . Appraisals, negotiations, land acquisition, legal
fees, escrow stamps, recording fees, etc. b. Predesign Engineering (all work prior to design,
c. Design Engineering d. Construction (all work after award of construction
e. Flood Insurance Rate Map amendments or revisions
excluding right-of-way)
contract)
11. Accurate documentation of all work performed and payments made will be maintained by the COUNTY for a period of three(3) years in hard copy form after final project approval and payment. Following the three year period, the COUNTY, shall keep records for permanent storage in original form or in microfilm/fiche media.
12. The DISTRICT reserves the right to review and/or audit all records pertaining to all projects both during and after project completion.
13. The COUNTY will be responsible for any loss, damage, liability, cost or expense caused by the actions or inactions of its employees, consultants, contractors or agents arising under this Contract and hereby holds the DISTRICT harmless therefrom.
14. Any costs found to be improperly allocated to this PROJECT will be refunded by the COUNTY to the DISTRICT.
.
. .
Page 4
- .. -
15. The items covered in SECTION I1 - PROJECT COSTS must be completed to the satisfaction of the DISTRICT prior to July 1, 1993. The DISTRICT may, at any time thereafter, grant extensions or terminate this CONTRACT after thirty (30) days notice.
Date of District Action: REGIONAL FLOOD CONTROL DISTRICT
BY : MICHAEL R. HARRIS, Chairman
ATTEST:
DEANNA LEFKO, Secretary
Approved as to Form:
BY: CHRISTOPHER FIGGINS, Deputy District Attorney
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Date of Commission Action: COUNTY OF CLARK
BY : JAY BINGHAM, Chairman
ATTEST:
LORETTA BOWMAN, County Clerk
f:\usere\judy\agr\vnbskv.ic Page 5
EXHIBIT "A"
. . . .
VAN BUSKIRK CHANNEL FLOOD CONTROL FACILITIES
VANBUSK 9/28/90 KTL
. .
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJECT:
CHEYENNE CHANNEL FROM BUFFALO DRIVE TO GOWAN DETENTION BASINS - INTERLOCAL CONTRACT (LAS.13.A.92)
RECOMMENDATION SUMMARY
STAFF: Approve.
TECHNICAL COMMITTEE: Approve.
CITIZENS COMMITTEE: Approve.
RFCD AGENDA lTEM#5 Dak 9/10/92
CLARK COUNTY
REGIONAL FLOOD CONTROL DISTRICT
BGFNDA ITEM
SUBJECT:
THE GOWAN SOUTH DETENTION BASIN INTERLOCAL CONTRACT FOR DESIGN OF THE CHEYENNE CHANNEL - BUFFALO DRIVE TO
PETITIONER:
CITY OF LAS VEGAS
RECOMMENDATION OF PETITIONER: That the board approve the Interlocal Contract.
FISCAL IMPACT:
Design and Right-of-way Engineering $67,000
BACKGROUND:
Th is I n te r l oca l Con t rac t app l i es t o a1 1 costs for design and r ight-of-way engineering t o p l a c e i n serv ice the Cheyenne Channel - B u f f a l o D r i v e t o t h e 6owan South Detention Basin. The basic improvements s h a l l c o n s i s t o f f l oodwa te r f ac i l i t i es i nc lud ing p ip ing and i n l e t systems, channels, embankments, replacement o f a pre-fabricated arch bridge and other appurtenances as may be necessary to con t ro l f loodwaters . The City i s p resen t l y s ta r t i ng des ign o f t h i s P ro jec t and i s seek ing fund ing fo r th is work.
TAC AGENDA RFCD AGENDA ITEM# 7 ITEM# 5
Richard D. Goecke, D i r e c t o r Department o f Publ ic Works
Regional Flood Control District AGENDA ITEM DEVEIDPHENT
Staff Discussion: Date: 81 19/92
CHEYENNE CHANNEL FROM BUFFALO DRNE TO GOWAN DETENTION BASINS - INTERLOCAL CONTRACT (LAS. 13.A.92)
The City of Las Vegas has submitted a request for an Interlocal Contract to fund the design and right-of-way engineering of the Cheyenne Channel from Buffalo Drive to the Gowan Detention Basin. Staff understands that a library is proposed adjacent to the project. Also, that the City of Las Vegas has had discussions with the library district to coordinate the design effort with them. The library district will assist in funding construction of the project once the design is completed. The amount requested for the Cheyenne Channel project is $67,000. The project is identified on the FY 92/93 Project List and pay-as-you-go funds (Fund 443) axe available.
Staff Recommendation:
Approve.
Discussion By Technical Advisory Committee I AGENDA # 7 Date: 8/27/92
Recommendation:
Approve.
Discussion By Citizens Advisory Committee LEY # 7 Date: 8/31/92
Recommendation:
Approve.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
INTERLOCAL CONTRACT FOR DESIGN OF THE
CHEYENNE CHANNEL - BUFFALO DRIVE TO THE GOWAN SOUTH DETENTION BASIN
THIS INTERLOCAL CONTRACT, made and en tered in to as o f t h e day o f
, 1992 by and between the Clark County Regional Flood Control
D i s t r i c t , h e r e i n a f t e r r e f e r r e d t o as "DISTRICT" and City of Las Vegas, a
mun ic ipa l corpora t ion , here ina f te r re fe r red to as the "CITY".
W I T N E S S E T H
WHEREAS, pursuant t o Chapter 543 o f t h e Nevada Revised Statutes, the
DISTRICT may approve a p ro jec t t o des ign and cons t ruc t f lood con t ro l
improvements; and
WHEREAS, t h e p r o j e c t i s a r e g i o n a l f a c i l i t y d e s c r i b e d i n t h e Master Plan
w i th t he f o l l ow ing s t ruc tu re numbers: GOSO 0051 and GOO2 0000 here ina f te r
r e f e r r e d t o as "PROJECT"; and
WHEREAS, the PROJECT i s i d e n t i f i e d and shown on the a t tached Exhib i t "A";
and
WHEREAS, the PROJECT i s a P r i o r i t y P r o j e c t approved by the DISTRICT Board
of D i rec to rs on the 92-93 Pro jec t L i s t ; and
WHEREAS, the PROJECT has reg iona l f lood con t ro l s ign i f i cance and i s l o c a t e d
i n the same hydrographic area as Clark County, the City o f Henderson, the City
o f Las Vegas and the City o f N o r t h Las Vegas; and
WHEREAS, the CITY i s presen t l y s ta r t i ng des ign o f t h i s PROJECT and i s
seek ing fund ing fo r th is work.
. . .
1
1
2
-3
4
5
6
7
8
9
10
1, 1
--
13
14
15
16
17
18
19
20
21
22
23
NOW, THEREFORE, in consideration of the covenants, conditions, agreements
and promises o f the parties hereto, the DISTRICT authorizes the CITY to proceed
with the PROJECT as it is mutually understood and agreed as follows:
SECTION I - SCOPE OF PROJECT
This INTERLOCAL CONTRACT appl ies to all costs for design and right-of-way
engineering to place in service the Cheyenne Channel - Buffalo Drive to the Gowan South Detention Basin. The basic improvements shall consist of floodwater
facilities including piping and inlet systems, channels, embankments, replacement
of a pre-fabricated arch bridge and other appurtenances as may be necessary to
control floodwaters. The improvements shall be funded through DISTRICT funds as
herein described. This PROJECT is further identified and shown on the attached
Exhibit "A".
SECTION I1 - PROJECT COSTS The DISTRICT agrees to provide funding for PROJECT costs and shall not
exceed the limits specified below:
1. Design and right-of-way engineering shall not exceed $67,000.
A written request must be made to the DISTRICT and a supplemental
inter1 oca1 contract approved to increase any of the amounts noted above prior to
payment of any additional funds.
SECTION I1 I - GENERAL 1. The DISTRICT shall be shown on the title sheet of both the plans and
specifications as the funding agency.
2. The award of bid for this PROJECT shall occur no later than December
2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
3.
4.
5.
31, 1993. The CITY will take a1 1 reasonable steps possible to.
avoid delays i n the cons t ruc t i on o f DISTRICT-funded pro jec ts .
PROJECT delays more than four months, as measured from the award
date, may be s u b j e c t t o a formal review by both the Technical
Advisory Committee and the DISTRICT Board o f D i r e c t o r s . A t the
review, the CITY will have an oppor tun i ty to p resent in fo rmat ion
r e l a t i v e t o t h e d e l a y s , measures taken to avo id the de lays and the
1 i kel i hood o f those delays continuing. The Board wi 11 make a
determination, i n view o f the de lays and l im i ted ava i lab le fund ing ,
whether PROJECT funding should continue. I n the case t h a t t h e Board
chooses to d iscont inue funding, the Board may cancel any I n t e r l o c a l
Contract (s) assoc iated wi th the PROJECT and d iscont inue funding for
the remainder o f the PROJECT. Funding already spent or appropriated
by the CITY will not be r e q u i r e d t o be refunded t o t h e DISTRICT.
Pro ject funding can be reconsidered at any t ime when the CITY can
demonstrate t h a t t h e PROJECT can proceed on an acceptable schedule.
The CITY will comply with the Local Purchasing Act, Chapter 332 o f
the Nevada Revised Statutes.
The CITY, i t s employees and rep resen ta t i ves sha l l a t a l l t imes
comply w i t h a l l a p p l i c a b l e laws, ordinances, statutes, rules and
regu la t ions in e f f e c t a t t h e t i m e work i s performed on the PROJECT.
The CITY will requ i re app rop r ia te f i nanc ia l secu r i t y f o r PROJECT
const ruct ion.
3
1
2
3
4
5
6
7
8
9
10
11
-
13
14
15
16
17
18
19
20
21
22
23
6. The CITY sha l l p rov ide a l l impacted en t i t ies and the DISTRICT w i t h
the oppor tun i ty to prov ide the CITY w i t h i n p u t r e l a t i v e t o t h e
fol lowing processes: scope of services development; consul tant
select ion; design, construction and maintenance review; and
moni tor ing o f the e f fect iveness and impacts o f f a c i l i t i e s on f l o o d
f 1 ows . 7. Any and a l l a p p l i c a b l e p o r t i o n s o f t h e c u r r e n t e d i t i o n s o f t h e
DISTRICT’s Po l i c ies and Procedures, the Hydro log ic Cr i te r ia and
Drainage Manual and the Uni form Regulat ions for Control of Drainage
PROJECT unless adopted by the DISTRICT will apply i n deve lop ing th is
s p e c i f i c a l l y superseded by the In ter loca l Contract .
8 . Purchases o f r i g h t - o f - w a y i n excess o f t h a t a c t u a l l y needed f o r
const ruct ion will not be allowed unless a comparison between the
c o s t o f excess acqu is i t i on and needed acqu is i t ion , inc lud ing
damages, ind icates that benef i ts f rom such a t ransact ion would
r e s u l t . T i t l e t o r e s i d u a l p r o p e r t y will be vested i n t h e name o f
the CITY. Revenues derived from the sale of these propert ies, less
the cost o f the sa le o f these proper t ies, will be forwarded t o t h e
DISTRICT.
9. Administrat ive sett lements and acceptance of counter o f f e r s
involv ing r ight-of-way may only be made fo l l ow ing a review approval
by the DISTRICT.
10. The DISTRICT will make payment t o t h e CITY, i t s c o n t r a c t o r o r i t s
4
1
2
3
4
5
6
7
a 9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
consultant each month for project costs as out1 ined in SECTION I1 - PROJECT COSTS. Invoices must identify and allocate all costs to the
categories noted below:
a. Right-of-Way
1. Design and Surveying
2. Appraisals, negotiations, land acquisition, legal fees,
escrow stamps, recording fees, etc.
b. Pre-design Engineering (all work prior to design, excluding
right-of-way)
c. Design Engineering
11. Accurate documentation of all work performed and payments made will
be maintained by the CITY for a period of three (3) years in hard
copy form after final projects approval and payment. Following the
three-year period, the CITY shall keep records for permanent storage
in original form or in microfilm/fiche media.
12. The DISTRICT reserves the right to review and/or audit all records
pertaining to all PROJECTS both during and after PROJECT completion.
13. The CITY will be responsible for any loss, damage, 1 iabil ity, cost
or expense caused by the actions or inactions of its employees,
consultants, contractors or agents arising under this Contract and
hereby holds the DISTRICT harmless therefrom.
14. Any costs found to be improperly allocated to this PROJECT will be
refunded by the CITY to the DISTRICT.
5
1
2
3
4
5
6
7
8
9
10
11
-
13
14
15
16
17
18
19
20
21
22
23
15. The CITY, as the administer ing agency, will provide the DISTRICT
16.
17.
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
wi th t he i n fo rma t ion requ i red i n NRS 543.580 and sha l l p resent tha t
i n fo rma t ion o ra l l y t o t he C i t i zens ’ Adv i so ry Committee, Technical
Advisory Committee and the Board o f D i rec to rs .
The items covered i n SECTION I 1 - PROJECT COSTS must be completed t o
t h e s a t i s f a c t i o n o f t h e DISTRICT p r i o r t o December 31, 1994. The
DISTRICT may, a t any t i m e thereaf ter , grant extens ions or terminate
t h i s C o n t r a c t a f t e r t h i r t y (30) days no t ice and may r e q u i r e a l l sums
advanced t o t h e CITY be repaid.
The CITY a t i t s own d i sc re t i on may use the se rv i ces o f a consul tant
fo r the comple t ion o f work i d e n t i f i e d i n SECTION I - SCOPE OF
PROJECT and the DISTRICT will not be a p a r t y t o such an agreement.
However, the use o f any consul tant will n o t e n t i t l e CITY t o
addi t ional funds beyond t h a t s p e c i f i e d i n SECTION I1 - PROJECT COSTS
as hereinabove set forth.
6
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
18. The CITY will provide the DISTRICT wi th pre l iminary p lans, 1
spec i f i ca t i ons and cost est imates for review and comments.
I N WITNESS WHEREOF, t h i s I n t e r l o c a l C o n t r a c t i s hereby executed as o f t h e
d a t e f i r s t s e t f o r t h above.
DATE OF DISTRICT ACTION:
ATTEST:
DEANNA LEFKO, SECRETARY
APPROVED AS TO LEGALITY AND FORM:
CHRISTOPHER FIGGINS
DEPUTY DISTRICT ATTORNEY
DATE OF COUNCIL ACTION:
ATTEST:
KATHLEEN TIGHE, C ITY CLERK
. . .
. . .
. . . P:\AGREE\CHEVCHAN.DES
REGIONAL FLOOD CONTROL DISTRICT
BY:
MICHAEL R. HARRIS, CHAIRMAN
CITY OF LAS VEGAS
BY :
JAN LAVERTY JONES, MAYOR
7
CLARK COUNTY 'REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBTECT:
HEMENWAY VALLEY FLOOD CONTROL IMPROVEMENTS - SEVENTH SUPPLEMENTAL INTERLOCAL CONTRACT (BOU.Ol.A.87)
RECOMMENDATION SUMMARY
STAFF: Approve.
TECHNICAL COMMITTEE: Approve.
CITIZENS COMMI?TEE: Approve.
RFCD AGENDA
Date: 9110192
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJECT: Seventh Supplemental lnterlocal Agreement for Hemenway Valley Wash Improvements
PETITIONER: City of Boulder City.
RECOMMENDATION: That the Regional Flood Control District (RFCD) approve and authorize the Chairman to sign the Seventh Supplemental lnterlocal Agreement for the design, construction, material testing and surveying of the Hemenway Valley Wash Improvements.
FISCAL IMPACT:
Current Interlocal Agreements $5,356,000 This request Total
$1 60,000 $5,516,000
BACKGROUND: The low bid for the Hemenway Valley Flood Control Project was $5,389,904.35, and with related engineering & construction administration-inspection,the project funding was $5,666,000 plus $250,000 from Boulder City/NDOT (See Page 2 attached)
Respectfully submitted,
TAC AGENDA ITEM # 8
Boulder City, Nevada Page 1 of 2 12-Aug-92
Page 2 Seventh Supplemental interlocal Agreement Hemenway Valley Wash Agenda Item
Through the Fifth and Sixth Supplemental Agreements, District funding has been reduced from $5,666,000 to $5,356,000. Contract Change Orders 1 and 2 have also reduced the construction and survey cost from $5,389,904.25 to $5,079,970.37.
The Seventh Supplemental Agreement will address two areas of the project:
a. Our original estimate was that contract administration, testing and inspection could be completed for $180,000 or 4% of construction; but based on expenses for the first six months, these services are estimated to be $297,000 or 6% of the construction cost, an increase of $107.000 and represents increased efforts by the City in coordination of the project.
b. The City had proposed to complete the gabion basket construction using Division of Forestry and prison labor; however, the Nevada Labor Commission believes,at the present time, that this violated several State Statues. To complete this construction at the contract bid price will require $53,000 of additional funding.
Boulder City is requesting additional funding in the amount of $160,000. After authorization of additional funding, appropriate purchase orders or contract change orders will allocate these additional funds.
Regional Flood Control District AGENDA ITEM DEWEIDPHENT
Staff Discussion: Date: 8/ 19/92
HEMENWAY VALLEY FLOOD CONTROL IMPROVEMENTS - SEVENTH SUPPLEMENTAL INTERLOCAL CONTRACT (BOU.Ol.A.87)
The City of Boulder City has requested an additional $16O,O00 for the Hemenway Valley Flood' IC Control Improvement project. The amount requested will cover additional costs incurred for increased efforts in construction engineering and for construction of gabion baskets. The Seventh Supplemental Interlocal Contract totals $5,516,000 which includes the requested increase of $160,000. Funding is available from pay-as-you-go funds (Fund 443).
Staff Recommendation: ~~~
Approve.
Discussion By Technical Advisory Committee I AGENDA # 8 Date: 8/27/92
Recommendation:
Approve.
Discussion By Citizens Advisory Committee I AGENDA # 8 Date: 8/31/92
Recommendation:
Approve.
F M H S U P P M F N T M Hemenway Valley Wash Floodway
THIS AGREEMENT, made and entered into this day of . 1992, by and between the City of Boulder City, a political
subdivision, hereinafter referred to as "CITY", the Clark County Regional Flood Control District, hereinafter referred to as "DISTRICT", and the County of Clark, hereinafter referred to as "COUNTY".
WlTNESSETH
Statutes, a Master Plan project to design, perform construction inspection and construct flood control improvements for the Hemenway Wash Floodway, hereinafter collectively referred to as PROJECT, shown on the attached Exhibit "A", being located wholly within the incorporated area of the CITY, and within a hydrographic area common to the COUNTY, has been approved by the DISTRICT.
WHEREAS, pursuant to Chapter 543 of the Nevada Revised
WHEREAS, pursuant thereto, an Interlocal Agreement was entered into on the 3rd day of November, 1987, between the CITY, the DISTRICT and the COUNTY; and
WHEREAS, on the 13th day of September, 1990, a First Supplemental Interlocal Agreement was entered into between the CITY, the DISTRICT, and the COUNTY; and
WHEREAS, on the 2nd day of April, 1991, a Second Supplemental Interlocal Agreement was entered into between the CITY, the DISTRICT, and the COUNTY; and
WHEREAS, on the 12th day of September, 1991, a Third Supplemental lnterlocal Agreement was entered into between the CITY, the DISTRICT, and the COUNTY; and
WHEREAS, on the 26th day of November, 1991, a Fourth Supplemental Interlocal Agreement was entered into between the CITY, the DISTRICT, and the COUNTY; and
Hemenway Valley Wash floodway
WHEREAS, on the 13th day of February, 1992, a Fifth Supplemental Interlocal Agreement was entered into between the CITY, the DISTRICT, and the COUNTY; and
WHEREAS, on the 1 l t h day of June 1992, a Sixth Supplemental lnterlocal Agreement was entered into between the City, the District and the County; and
WHEREAS, it is desired to further supplement the aforementioned agreements to clarify the intent thereof and adjust funding for construction, material testing and surveying.
NOW, THEREFORE, in consideration of the premises and the terms contained herein, the parties agree to modify the lnterlocal Agreement as follows:
1. Section I 1 - Project Costs as previously amended on September 13, 1990, April 2, 1991, September 12, 1991, November 26, 1991 and June 11, 1992, is deleted in its entirety and the following is inserted in lieu thereof: The DISTRICT agrees to provide funding for project costs within the limits specified below:
1. The engineering and design shall not exceed $336,000. 2. Construction administration including material testing shall
3. The construction including survey, shall not exceed
4. The total cost of this DNTERLOCAL AGREEMENT shall not exceed
not exceed $287,000.00
$4,893,000.00
$5.5lS.QD0.00. A written request must be made to the DISTRICT and a supplemental agreement approved to increase any of the amounts noted above prior to payment of any additional funds.
2. The remainder of the original Interlocal Agreement shall remain unchanged.
2
Hemenway Valley Wash Floodway
ATTEST: CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
BY; DEANNA LEFKO, Secretary MICHAEL HARRIS, Chairman
Date of Board Action
Approved as to Legality and Form:
By: CHRISTOPHER FIGGINS, Deputy District Attorney
ATTEST: CITY OF BOULDER CITY
BY; VICKI G. BERGDALE, City Clerk ERIC L. LUNDGAARD, Mayor
Date of Council Action:
ATTEST: CLARK COUNTY BOARD OF COMMISSIONERS
BY; LORETTA BOWMAN, County Clerk JAY BINGHAM, Chairman
Date of Commission Action:
3
- . - -
IMPROYLMENTS
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM L
SUBJECT:
GOWAN DETENTION SYSTEM - SECOND SUPPLEMENTAL INTERLOCAL CONTRACT (LAS.03.C.91)
RECOMMENDATION SUMMARY
STAFF: To be given at the meeting.
TECHNICAL COMMI'ITEE: Consider at the Special Technical Advisory Committee meeting on September 10, 1992 at 8:lO a.m.
SPEC. TAC RFCD AGENDA ITEM #1 ITEM #7'
CLARK COUNTY
REGIONAL FLOOD CONTROL DISTRICT
~ ~~
SUBJECT: Second Supplemental Interlocal Contract for the Construction of the Gowan Detention System PETITIONER: City of Las Vegas
RECOMMENDATION OF PETITIONER: That the Board approve the Second Supplemental Interlocal Contract.
FISCAL IMPACT: None. (Modi f i cation of Project cost requested). BACKGROUND: It is anticipated that on August 31 construction crews will begin work on the Gowan Detention Basins (Gowan Road and Buffalo Drive) near Eisenberg and Kahre Elementary School s haul ing some 1.2 mi 1 1 ion cubic yards of soi 1 to a facility at Cheyenne Avenue and Buffalo Drive. Heavy machinery will be traveling along Buffalo Drive approximately every 50 seconds from 6:OO a.m. to 4:OO p.m. daily and will continue to do this for the next 180 days. In regard to this situation, student safety is of paramount concern.
City Public Works staff have been working with School District Transportation Department staff to determine the need for busing to and from the above two elementary schools the approximately 400 students who live in this area . It is the City’s position that busing these students is the safest way to get them t o and from school in a manner that would not subject them to the heavy construction traffic in the area. From a safety standpoint, we are of the opinion there is no other alternative.
On August 19 the City was officially notified by the School District that buses would not be provided to transport these students due to budget eoastralnts which have been placed upon the School District during this fiscal year. Therefore, the burden of cost for transporting these students 1 ies with the City. Mr. Matt Wallace of the School District Transportation Department advised the City that five buses would be necessary to transport approximately 400 students. Based on information obtained from Hr. Wallace this translates to: 5 buses x $40/day x 129 school days = $25,800. City staff would increase this amount to $30,000 in order to allow for any unforeseen circumstances that would extend the period of busing beyond the original 180 days. The City requests reimbursement for these costs be retroactive to the date this busing is first provided by the School District regarding thi s Project .
Richard D. Goecke, Director Department o f Pub1 ic Works
SPECIAL
ITEM# 1 ITEM# 7
1
2
3
4
5
6
7
8
9
10
1.1.
& -
13
14
15
16
17
18
19
20
21
22
23
SECOND SUPPLEMENTAL INTERLOCAL CONTRACT FOR THE
CONSTRUCTION OF THE GOWAN DETENTION SYSTEM
THIS SECOND SUPPLEMENTAL INTERLOCAL CONTRACT made and en tered in to as of
t h i s day o f , 1992, by and between the C la rk County
Reg iona l F lood Cont ro l D is t r i c t , here ina f te r re fe r red to as the "DISTRICT" and
the City o f Las Vegas, a mun ic ipa l corpora t ion , here ina f te r re fe r red to as the
"CITY 'I.
W I T N E S S E T H
WHEREAS, an Inter local Contract dated November 14, 1991 was en tered in to
between the DISTRICT and the CITY fo r the cons t ruc t ion o f F lood Cont ro l
Improvements described i n t h e DISTRICT Master Plan Update o f t h e Las Vegas
Valley, August, 1991 as F a c i l i t y Nos. GON00000, GON00008, and GOSOOOOO, GOS00051.
A Supplemental In ter loca l Contract was subsequently approved by the Board o f
D i rec to rs on August 13, 1992 adjust ing the amount a l lowed for the const ruct ion
o f t h i s PROJECT as a r e s u l t o f a low b id award o f $6,267,723.86; and
WHEREAS, the CITY requests supplementing t h i s I n t e r l o c a l C o n t r a c t t o
p rov ide fo r the cos t o f bus ing s tudents res id ing in the PROJECT area (the area
bounded by US95 and Bu f fa lo and Cheyenne and Alexander plus the Desert Shores
development) t o Kahre Elementary School and Eisenberg Elementary School f o r t h e i r
safety and well being during the construction period of approximately 180 days.
NOW, THEREFORE, i n cons ide ra t i on o f the covenants, condit ions, agreements,
and promises o f the par t ies hereto, the DISTRICT author izes the CITY t o proceed
w i th t he PROJECT as i t i s mutually understood and agreed as fo l lows:
1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
1. SECTION I 1 - PROJECTS COSTS i s r e v i s e d t o read:
The DISTRICT agrees to p rov ide f und ing f o r t he PROJECT w i t h i n t h e l i m i t s -
spec i f i ed below:
1.
2.
3.
4.
5.
Const ruc t ion a t a c o s t n o t t o exceed $6,970,000.
Busing a t a c o s t n o t t o exceed $30,000. Costs incur red p r io r
to execut ion da te o f t h i s c o n t r a c t wi 11 be reimbursed.
Construct ion engineer ing a t a cos t no t t o exceed $500,000.
Tota l PROJECT cos t sha l l no t exceed $7,500,000.
A wr i t ten request must be made t o t h e DISTRICT and a
Supplemental In te r loca l Cont rac t approved to i nc rease any
amounts noted above p r i o r t o t h e payment o f any add i t iona l
funds . The remainder o f the o r ig ina l In te r loca l Cont rac t da ted November 14, 1991
and the Supplemental In ter loca l Contract dated August 13, 1992 shal l remain
unchanged.
I N WITNESS WHEREOF, t h i s SECOND SUPPLEMENTAL INTERLOCAL CONTRACT i s hereby
executed as o f t h e d a t e f i r s t above set for th .
DATE OF COUNCIL ACTION: CITY OF LAS VEGAS
BY :
ATTEST : JAN LAVERTY JONES, MAYOR
KATHLEEN TIGHE, CITY CLERK
. . .
2
1
2
3
4
5
6
7
8
9
10
11
..-
13
14
15
16
17
18
19
20
21
22
23
ACT ION :
ATTEST :
DEANNA LEFKO, SECRETARY
APPROVED AS TO LEGALITY AND FORM:
~~~~~~~~ ~~ ~ ~~~~~~ ~
CHRISTOPHER D. FIGGINS
DEPUTY D I S T R I C T ATTORNEY
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . .
. . . P:\Agr*e\GDBCONST.25
REGIONAL FLOOD CONTROL D I S T R I C T
BY:
MICHAEL R. HARRIS, CHAIRMAN
3
GOWAN DETENTION BASIN PHASE 1 NUMBER 3
INDEX l. GOWAN SOUTH DETENTION
BASIN, W400 AC-f.7
2. 72w RCP, L-2690
3. GOWAN NOYTH DETENTION BASIN, Vp900 AC-FT
4. 8' X 8' RCB; d Lm440'
5. 66- RCP, L-210'
A
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJECT:
LAS VEGAS WASH BETWEEN CRAIG ROAD AND C M C CENTER DRIVE - CHANGE ORDER NUMBER 1 (NLV.Ol.B.87)
RECOMMENDATION SUMMARY
STAFF: Approve.
TECHNICAL COMMITTEE: Approve.
CITIZENS COMMI'ITEE: Approve.
RFCD AGENDA
Date: 9110192
CLARK COUNTY
REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJE-. Change Order No. 1-Asbuilt for the Las Vegas Wash between Craig Road and Civic Center Drive, AKA the King Charles Diversion Channel
P ~ O N E R : Gary W. Holler, P.E., Director of Public Works City of North Las Vegas
RECOMMENDATION OF PETITIONER:
It is recommended that the Clark County Regional Flood Control District Board approve the Change Order.
FISCAL IMPACT: The current Interlocal Contract funding is sufficient to cover Change Order No. 1 in the amount of $14,539.89.
BACKGROUND:
Change Order No. 1-Asbuilt has been prepared which increases the cost of construction by $14,539.89, due to additional costs experienced in the course of construction of this project. This change order amounts to 0.80% of the approved contract.
Respectfully submitted,
AG-148
Regional Flood Control District AGENDA ITEM DEVEIXlPWENT
I Staff Discussion: Date: 8/ 19/92
LAS VEGAS WASH BETWEEN CRAIG ROAD AND C M C CENTER DRIVE - CHANGE ORDER NUMBER 1 (NLV.Ol.B.87)
The City of North L a s Vegas has negotiated a change order for the Las Vegas Wash project between Craig Road and Civic Center Drive (aka King Charles Diversion Channel Project). The change order represents conflicts experienced during the construction of the project as itemized on Pay Estimate No. 9, included in the backup. The net increase to the construction contract for Change Order Number 1 is $14,539.89. Current i n t e r l d contract funding is sufficient to cover the increase.
Discussion By Technical Advisory Committee
Discussion By Citizens Advisory Committee
CITY OF NORTH IAS MOAS ENGINEERING DIVISION
CONTRACT CHANGE ORDER NUMBER 1 - ASBUILT
PROJECT: King Charles Diversion Channel, Ph. II CONTRACTOR: Max Riggs ConstNctlon
This Change Order reflects the asbulh project costs based upon actual measured quantities of constructed items.
The folk
I==
E P-
~ 11. 10.
P-
ring are the actual increases and/or decreases in c d:
x mtract items at contracl
&-Bulk Change &-
Net
644.00
0 201 .00 0 137.00
0 158.00
0
1,022.00 0
2,281 .00 0
1,187.00 3
1,200.00
0 1 .00 0 1 .00 0 1 .w
0 1 .oo 0 1 .00 0
4,500.00 0
1.97 0.97
40,OOO. 00 0
1.00 0
t prlces8 . DiffWWlCe
$0.00.
$0.00
$0.00 $0.00
$0.00
$0.00
We, the undersigned contractor, have given c a r e f u l consideration to the changes proposed and hereby agree, If this proposal is approved, that wo provided all equipment, furnished all materiak, except as may otherwise be noted above, and performed a l l senrices necesary for the work specified, and will accept as fu l l payment therefor the prices shown.
W Accepted by:
(Date)
i
i
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA I"
SUBJECT:
VARIANCE REQUEST FOR LOT 71 OF LAUGHLIN ESTATES UNIT 1
STAFF:
RECOMMENDATION SUMMARY
Approve subject to the property owner signing a hold harmless waiver, releasing the District and Clark County from any flooding liability.
TECHNICAL COMMI'ITEE: Follow staffs recommendation.
CITIZENS COMMITTEE: Follow staffs recommendation.
RFCD AGENDA ITEM19 Date: 9/10/92
CLARK COUNTY
REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM . 'e
VARIANCE LOT 71 - LAUGHLIN ESTATES UNIT 1
PETITIONER M. J. MANNING, DIRECTOR OF PUBLIC WORKS
RECOMMENDATION OF PETITIONER I THAT THE REGIONAL FLOOD CONTROL DISTRICT APPROVE A VARIANCE FOR THE ELEVATION REQUIREMENT ON LOT 71 IN LAUGHLIN ESTATES UNIT 1, 3699 CATALINA, LAUGHLIN, NEVADA.
I
FISCAL IMPACT: None
BACKGROUND:
Lot 71 in Laughlin Estates Unit 1 located in the Unnamed Wash flood hazard area; designated as an A0 zone depth of flooding 1 foot on the Flood Insurance Rate Map. Many lots in Laughlin Estates Unit 1 were built upon prior to the adoption of the current Uniform Regulations for the Control of Drainage. In order to build a home on Lot 71, the owner is required to fill Lot 71 to an elevation significantly higher than the adjacent lots. The higher lot would not be consistent with the existing homes in the neighborhood.
Clark County has a created a Special Improvement District and the Regional Flood Control District has provided funding for the construction of flood improvements to remove the Laughlin Estates from the flood hazard designated area.
W J . WORKS
MJM:DC: s l h
RFCD Agenda Page 2
On the basis of the proposed flood control improvements, the Federal Emergency Management Agency has issued a conditional letter of map revision for this area. Advertisements for construction bids for the Unnamed Wash flood control facilities will occur in August, 1992 and construction should begin in November, 1992. On this basis, a variance of the higher elevation requirement would be practical and consistent with existing structures in Laughlin Estates.
Specifically, this will request a variance from Section 10.100 ( B ) ( l ) ( A ) of the Uniform Regulations for the Control of Drainage, which requires that the lowest floor be elevated to 18 inches above the 100-year flood depth. The proposed finished floor will be elevated 9 inches above the 100-year flood depth. Therefore,.the proposed finished floor will be elevated 21 inches above the highest adjacent grade.
Regional Flood Control District
AGENDA ITEM DEVELOPMENT I Continued Staff Discussion: I Date: 8/5/92
~~
VARIANCE REQUEST FOR LOT 71 OF LAUGHLIN ESTATES UNIT 1
The information submitted by Clark County is insufficient to evaluate the request as stated above.
I Staff Recommendation:
Resubmit with more information to evaluate the request.
Discussion By Special Technical Advisory Committee
Clark County was requested to resubmit the item with further information.
l2r-L # 2 Date: 8/13/92
Recommendation:
Hold for next regular Technical Advisory Committee meeting in August.
Discussion By Board of Directors
Recommendation:
Hold for next regular meeting.
Regional Flood Control District AGENDA ITEM DEVELOPWENT
Staff Discussion:
VARIANCE R E Q m T FOR LOT 71 OF LAUGHLIN ESTATES UNIT 1
This item was held from the August 13, 1992 Special Technical Advisory Committee meeting pending submittal of additional information from Clark County and advice from legal council on the variance request. Clark County has clarified the variance request on the agenda item.
Clark County has requested a variance from Section 10.100 (B) (1) (a) of the "Uniform Regulations for the Control of Drainage" for Lot 71 of Laughlin Estates Unit 1. Section 10.100 (€3) (1) (a) of the Regulations states:
"New construction and substantial improvement of any residential structure shall have the lowest floor elevated to a minimum of eighteen inches(l8") above the base flood elevation. If the base flood elevation is specified as a depth, it is to be measured from the 'highest adjacent grade.' "
Highest adjacent grade is defined in Section 8 of the Regulations as:
". . . the highest natural elevation of the ground surface prior to construction next to the proposed walls of the structure."
Clark County requests that the lowest floor be elevated to nine inches (9") above the base flood elevation instead of the eighteen inches (18") as stated in the Regulations. Staff understands that the property is located in a Special Flood Hazard Area labeled "Zone A 0 (Depth 1; Velocity 5 FPS)" on Panel 32003 2015B of the September 29, 1989, Clark County, Nevada, Flood Insurance Rate Map (FIRM).
The basis for the variance request is as follows:
1. The fill required by the Regulations would make this property significantly higher then adjacent lots.
2. The Federal Emergency Management Agency (FEMA) has issued a Conditional Letter of Map Revision (CLOMR) for the Unnamed Wash Flood Control improvements.
3. Clark County has created a Special Improvement District and the Regional Flood Control District has provided funding for construction of the Unnamed Wash Project.
4. Clark County expects to advertise for construction of the Unnamed Wash Improvement Project in August, 1992 and construction is anticipated to begin in November 1992. The construction of the project will remove Laughlin Estates from the Special Flood Hazard Area.
continued I
AGENDA ITEM DEVELOPMENT Regional Flood Control District
Continued Staff Discussion: Date: 9/ 1/92
VARIANCE REQUEST FOR LOT 71 OF LAUGHLIN ESTATES UNIT 1
Staff comments on the variance request:
1. FEMA has issued a CLOMR which is a letter of belief that once the project is built that
.a
the FIRM would be revised to remove the Special Flood Hazard Area in Laughlin Estates; however, the FIRM is not officially revised by FEMA until the project is constructed and supporting documentation is provided to FEMA for final review.
2. FEMA’s minimum requirement is to elevate the lowest floor at or above the base flood elevation. The Regulations are more stringent due to the hydrologic and hydraulic conditions found in Clark County and arid regions.
3. Staff takes no exceptions to the request, inasmuch as construction of the Unnamed Wash Project will begin shortly, and when completed, will provide flood protection to this area; and the variance request still meets FEMA’s minimum requirements.
I Staff Recommendation:
Approve subject to property owner executing a release and waiver (in agenda backup) which holds the District and Clark County harmless from any flooding that may occur on the owner’s
I Discussion By Technical Advisory Committee 1 AGENDA # 10 Date: 8/27/92
Recommendation:
Follow staff‘s recommendation.
Discussion By Citizens Advisory Committee AGENDA # 10 Date: 8/31/92
I Recommendation:
Follow staff‘s recommendation.
F.2
RELEASE AND WAIVER EXECUTED on ?
1992, by and #
hereinafter referred to as RELEASOR, owner(6) of property
generally described a6 Lot 71 of Laughlin Estates Unit 1 and more
specifically described in Exhibit A attached hereto and by this
reference incorporated herein, to the County of Clark and the
Clark County Regional Flood Control District, their officers,
employees, agents and representatives hereinafter referred to as
RELEASEES.
IN CONSIDERATION of the RELEASEES granting of a variance
from Section 10(B) (1) ( A ) of the Uniform Regulations for the
Control of Drainage, which requires that the lowest floor be
elevated to eighteen (18) inches above the hundred year flood
depth, to allow RELEASOR to have a finished f loor elevation of
only nine (9 ) inches above t h e hundred year flood depth, RELEASOR
hereby assumes all risk in connection with any flooding which may
occur on RELEASOR'S property. RELEASOR further agrees to release
and hold harmless RELEASEES from all claims, demands and causes
of action, present and future, known or unknown, including any
and all c.laims and causes of action for damages for personal
injury, death or property which may occur as a result of any
flooding or potential flooding on RELEASOR'S property.
IN EXECUTING this Release, RELEASOR acknowledges that
RELEASOR'S property is located in an area designated as a Special
1
Flood Hazard Area labeled "Zone A 0 (Depth 1; Velocity 5 FPS)" on
Panel 32003 2015B of the September 29, 1989, Clark County, Nevada
Flood Insurance Rate Map (FIRm), and that building on said
property may create an inherently dangerous situation should
flooding occur in the area, and with reapect to RELEASEE,
RELEASOR assumes a l l risks, known or unknown, associated with
flooding which may occur on RELEASOR'S premises.
.. 'e
RELEASOR FVRTHER WARRANTS that this Release is executed
without reliance on any statement, representation or action by
RELEASEES.
RELEASOR WARRANTS that he or she is of lawful age and
legally competent to sign this Release; that he or she has fully
informed himself or herself of the contents of the Release by
reading it before signing it; that the terms hereby are
contractual and not merely recitals and that this document has
been signed upon his or her own free will.
RELEASOR agrees that this document will be recorded in the
Clark County Recorder's Office and that this Release is binding
upon RELEASOR, his or her heirs, estates, executors,
administrators, representatives and assigns.
IT WITNESS WHERE I have executed this Release at
, on the day and year first above written.
RELEASOR
RELEASOR
2
STATE OF NEVADA, 1
COUNTY OF CLARK, 1 ) 66:
On this day of 1992, before me
, Notary Public, personally appeared I personally known to me to be the
person whose name is subscribed to this instrument, and
acknowledge that he/she executed it.
(Notary’s Signature)
3
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM
SUBJECT:
POLICIES AND PROCEDURES MANUAL - 1992 ANNUAL UPDATE
RECOMMENDATION SUMMARY
STAFF: Review/discuss and approve the amendment to Section 16.0 - Facility Maintenance
TECHNICAL COMMIlTEE: Follow staff's recommendation
CITIZENS COMMITIEE: Follow staff's recommendation
ITEM# 10
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
SUBJECT:
POLICIES AND PROCEDURES MANUAL - 1992 ANNUAL UPDATE
I VIRGINIA VALENTINE, P.E., GENERAL MANAGEIUCHIEF ENGINEER I RECOMMENDATION OF PETITIONER:
REVIEW/DISCUSSION AND POSSIBLE ACTION TO APPROVE AMENDMENTS TO THE POLICIES AND PROCEDURES MANUAL
FISCAL IMPACT:
None.
BACKGROUND:
The District’s Policies and Procedures Manual, Section 18.0, provides that the policies and procedures will be reviewed in August of each year. The last amendment to the manual was adopted by the Board in February 1992. This was due to the lengthy process involved with coordinating and preparing the changes.
At the direction of the Board, staff has prepared language to amend the Policies and Procedures in Section 16.0 Facility Maintenance as follows:
Maintenance of flood control facilities identified on the Master Plan will be performed in accordance with the Clark County Regional Flood Control District Operations and Maintenance Manual. Entities are required to submit interlocal contracts annually for maintenance funding with an annual maintenance work plan and a maintenance schedule by facility as exhibits to the funding contract. mese schedules must spec@ the estimuted dokrs plrznned for each f a c m by UCti*.
The entity is also responsible for preparing the agenda item to be presented to the District Board. The finalized annual maintenance wonk plans must be presented to the Dsstrict Board in June of each year so that iffirndbg is available and authorized, those maintenance wonk plans can begin on July I of the new fiscal year.
Quartedy status reports must be submitted by the entities to the District on the fonn pmvided for that purpose. (See Exhibit F.) TIrese status reports must
TAC AGENDA
Date: 9110192 Date: 8/27/92 ITEMX10 ITEM13 RFCD AGENDA
. report the work completed on each faciUy by activ&. TIre report is to be in pmgmss dollars, not in expended dollars. The teporting quruters are as follows:
1st Quarter - July thmugh September 2nd Quarter - October thmugh December 3nl Quarter - January thmugh March 4th Quafler - Apd thmugh June
TIre Quartedy status mprts am due in the Wrict ofice 30 days q/terthe close of the Quarter.
M e r the Annual Maintenance Work PSan is appmved by the Boanl, it is the msponsibil& of each entity to mquest, in wdting, the District -to open up purchase oniers for work to be paid by the M&t. Reimbursement for maintenance services will edy be made in compliance with the Policies and Procedures munual and the annual interlocal contract.
Respectfully submitted,
..
Vikidia Valentine, P.E. Gen'kral Managerkhief Engineer
TAC AGENDA ITEM#3
RFCD AGENDA
Dak 9/10/92 Date: 8/27/92 ITEM#lO
Regional Flood Control District AGENDA ITEM DEVELOPMENT
Staff Discussion: Date: 9/ 1 /92 r
POLICIES AND PROCEDURES MANUAL - 1992 ANNUAL UPDATE
The agenda item shows the changes staff has proposed to Section 16.0 - Facility Maintenance. The Citizens Advisory Committee requested a change in Section 4.7 - Project Status, which they subsequently withdrew.
Staff Recommendation:
Reviewldiscussion and possible action to approve the amendment to Section 16.0 - Facility Maintenance.
I
Discussion by Technical Advisory Committee: AGENDA # 3 Date: 8/27/92
The Technical Advisory Committee discussed the changes as proposed by staff and the Citizens Advisory Committee. They voted unanimously to recommend approval of Section 16.0 - Facility Maintenance only, excluding the request by the Citizens Advisory Committee to amend that portion related to project delays.
Recommendation:
Approve amendment to the Policies and Procedures, Section 16.0 - Facility Maintenance.
Discussion by Citiaem Advisory C ~ W t t m : AGENDA # 3 Date: 8/31/92
After further review and discussion, the Citizens Advisory Committee voted unanimously to withdraw their request to amend the Policies and Procedures Manual, Section 4.7 - Project Status.
Recommendation:
I Follow the staff's recommendation. I
EXHIBIT F REGIONAL FLOOD CONTROL DISTRICT
MAINTENANCE WORK PROGRAM STATUS REPORT /
Entity: Dateprepared:
Project: FORCE
ACCOUNT/ APPROVED .AMENDED SCHEDULED WORK PLAN WORK PLAN PERCENT COMPLETION
WORK TO BE COMPLETED DURING CURRENT QUARTER:
' .'K TO BE COMPLETED DURING NEXT QUARTER:
Consubnt/Contractor:
Project Manager: Phone Number: . . * - - T - - . I I - T - T T '
- --.-r---
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM .e
SUF3JECT:
DETENTION BASIN LANDSCAPING
STAFF:
RECOMMENDATION SUMMARY
Receive report and direct staff.
RFCD AGENDA ITEMU 11 Dak 9110192
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
AGENDA ITEM SUBJECT:
DETENTION BASIN LANDSCAPING
PETITIONER:
VIRGINIA BAX-VALENTINE, P.E., GENERAL MANAGER/CHIEF ENGINEER
RECOMMENDATION OF PETITIONER:
THAT THE BOARD RECEIVE THE REPORT AND DIRECT STAFF AS DEEMED APPROPRIATE
FISCAL IMPACT:
None.
BACKGROUND:
At the August 13, 1992 Board meeting it was requested that staff develop landscaping cost estimates for the detention basins proposed on the Ten Year Construction Program. The review included an examination of aerial photos to determine the presence of development adjacent to the basins. Based on existing use, predictions were made regarding the likelihood of development occurring adjacent to the basins within the next ten years. Considering this information and estimated embankment lengths, cost estimates were prepared for landscaping the proposed detention basins using the landscape costs for the Oakey Detention Basin as a basis.
There are 14 detention basins proposed on the Ten Year Construction Program for which funding may conceivably be requested. That estimated cost is approximately $3,630,000. The 14 projects include the Gowan Detention Basins and the Oakey Detention Basin with landscaping costs at $410,000 and $200,000, respectively. The backup includes a list of detention basins on the Ten Year Construction Program and am estimate of Pmdmping costs for each.
Rcspectrully submitted,
'3 /
TAC AGENDA ITEM# 11 ITEM # RFCD AGENDA
Date. 9/10/92 Date.
AGENDA ITEM DEVELOPMENT Regional Flood Control District
Staff Discussion: DETENTION BASIN LANDSCAPING
I Date: 9/02/92
At the August 13, 1992 Board meeting it was requested that staff develop landscaping cost estimates for the detention basins proposed on the Ten Year Construction Program. Staff has developed landscaping cost estimates which take into account an estimate of embankment length and if development adjacent to the basins is existing or expected.
Staff Recommendation:
Receive report and direct staff as deemed appropriate.
Discussion By
Recommendation:
Discussion By
Recommendation:
Page 1
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
SUBJECT:
KERN RIVER GAS PIPELINE
I VIRGINIA VALENTINE, P.E., GENERAL MANAGWCHIEF ENGINEER
RECOMMENDATION OF PETITIONER:
THAT THE BOARD AUTHORIZE THE GENERAL MANAGER TO DIRECT THE DISTRICT ATTORNEY’S OFFICE TO REPRESENT THE REGIONAL FLOOD CONTROL DISTRICT IN MATIERS RELATED TO THE KERN RIVER GAS PIPELINE.
FISCAL IMPACT:
None.
BACKGROUND:
In September 1989, the Kern River Gas Company filed condemnation proceedings against Clark County, the City of Las Vegas, and the City of North Las Vegas for the purpose of obtaining the necessary property in order to place its 36-inch high pressure gas line. Subsequently, the United States District Court granted Kern River the right to occupy the entities’ road rights-of- way.
Recently, the County’s damage experts, Brechler & Bell Consulting Engineers, submitted a report which indicated that there are eleven (1 1) future flood control facilities that are in conflict with Kern River’s gas pipeline. Total damages to the Clark County Regional Flood Control District’s facilities resulting from the pipeline are estimated above $60O,oOO. A trial on the issues relating to damages is set for later this month (September 1992).
Staff requests that the Board authorize the General Manager to direct the District Attorney’s Office to appear on behalf of the Regional Flood Control District in order to plead and defend the property and interest of the District, should this matter proceed to trial.
Vir%& Bdx-Val&tine, P.E. - - -
G e n a ManagerlChief Engineer
TAC AGENDA RFCD AGENDA lTEMX12 Date: 9110192
SEP 81 ’92 16:17 P. 2
MEMORANDUM REX BELL
OFFICE OF THE DJSTRICT ATTORNEY -- ClVJL DIVISION DISI’WCT All#RNEY
TO: VIRGINIA BAX-VALENTINE, General Manager/Chicf Engineer
FROM: CHIUSTOPHER D. FIGGMS, Deputy District Attorney a? SUBJECT: Kern River Gas Pipeline
DATE: September 1,1992
In September, 1989, the Kern River Gas Company filed condemnation proceedings against Clark County, the City of Las Vegas and the City of North Las Vcgas for the purpose of obtaining the necessary property in order to place its 36-inch high prtssurc: gas line. Subsequently, the United States District Court granted K m River the right to occupy the entities’ fddd rights-of-way.
Recently, the County’s damage experts, Beckler & Bell Consulting Engineers, submitted a report which indicated that there are 1 1 future Flood Control facilities that are in conflict with Kern River’s gas pipeline, Total damages to the Clark County Regional Flood Control District’s facilities resulting from the pipeline is estimated above $6OO,OOO,OO. A trial on the issues relating to damages is s e t for later this month.
NRS 37.080 provides as follows:
All persons in occupation of, or having or claiming an interest in, any of the properly described in the complaint, or in the damages for the taking thereof, though not namd, may appcar, plead and defend, each in rcspcct to his own property or interest, or that claimed by him, in like manner as if named in the complaint.
Staff requests that the Board authorize the District Attorney’s Office to appear on behalf of the Regional Fld Control District in order to pltad and defend the property and interest of the District should this matter proceed to trial,
:gs
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
SUBJECT:
PROJECT STATUS REPORTS
PETITIONER:
VIRGINIA BAX-VALENTINE, P.E., GENERAL MANAGERKHIEF ENGINEER
RECOMMENDATION OF PETITIONER:
THAT THE BOARD ACCEPT THE REPORTS
FISCAL IMPACT:
None.
BACKGROUND:
The following Projects Status Reports for the month of August 1992 are submitted for your review:
92/93 PROJECT LIST AND BOND PROJECTS
a) Project Charts b) Project Summary Sheets c) Clark County d) City of L a s Vegas e) City of Boulder City f ) City of Henderson g) City of North Las Vegas
OTHER PROJECTS OF INTEREST a) Clark County - Hiko Springs Remapping b) City of Las Vegas - Gowan North Channel c) Henderson - Pittman Wash Phase II d) Regional Flood Control District
Respectfully submitted,
TAC AGENDA
Date: ITEM#^^ ITEM # RFCD AGENDA
Date: 9/10/92
Catherine A. Razor U.- Project Administration Coordinator
CLARK COUNTY PROJECT STATUS CHART AS OF 813 1 I92
DUCK CREEK BRIDGES
E RANGE WASH DETENTION BASIN
FLAMINGO BRIDGE @ PALOS VERBC
FLAMINGO BRIDGE @ PARADISE
WINNICK AVE IMPROV
RAWHIDE CHANNEL IMPROVEMENTS Annie Oaklsy to Palm Mtn Vista, Pecos, Sandhill
SLOAN CHANNEL
TROPICANA DETENTION BASIN
VAN BUSKIRK SYSTEM
VAN BUSKIRK RIGHT-OF-WAY I I I
I I
X
CLARK COUNTY - OUTLYING PROJECT STATUS CHART AS OF 8/31/92
BUNKERVILLE CHANNEL
GOODSPRINGS
HlKO SPRINGS
LOGAN WASH - Area 1
Area 2
MUDDY RIVER WEST LEVEE
NELSON FLOOD CONTROL
SEARCHLIGHT FLOOD CONTROL
UNNAMED WASH
1992 1993 1994
Jul Aug !Sap Oct NW Doc Jan Fob M n Apr May Jun Jul Aug Sop Oct Nov Doc Jan Fob I I
IOl l lHOLD I I
!
CITY OF LAS VEGAS PROJECTSTATUSCHART AS OF 8/31/92
ALTA STORM DRAIN (Meadow V)
ANGEL PARK DB EXPANSION
BUFFALO CHANNEUDoe-Westcliff9
BUFFALO CH(Summerlii-Vega$)
BUFFALO CH(Westcliff-Summerlin~
CHEYENNE CHANNEL
CAREYllAKE MEAD DET. BASIN
GOWANlCAM 10 & LONE MTN
GOWAN DETENTION BASIN
GOWAN OUTFALL
OAKEY BL DET BASIN SYSTEM
OAKEY COLLECTION SYSTEM
RAMPART STORM DRAIN
WASHINGTON AVE. SYSTEM DESIGN
WASHINGTON AVE. ROW
WASHlNGTONlSANDHlLL OUTLET
WASHINGTONISANDHILL-VIRGIL CONSTRUCTION
PROJECTSTATUSCHART AS OF 8/31 I92
BOULDER CITY HEMENWAY WASH
HENDERSON C-1 CHANNEL SYSTEM
PllTMAN WASH - PHASE 111
SUNSET DETENTION BASIN
UPRR CHANNEL
MESQUITE TOWN WASH DET. BASIN
NORTH LAS VEGAS GOWAN OUTFALLPHASE I
KYLE CANYON DET. BASIN
NLV DETENTION BASIN-OUTLET
UPPER LV WASH DET BASIN
WEST RANGE WASH DIKE
DISTRICT SUMMARY SHEET AS 0
I I I IDONE IDONE I ON HOLD I IAdvisorv Board and envir reauirements Goodsprings Flood Control I I I I I 11 add'l month delay due to environmental Improvements
construction delayed 1 month to find Logan Wash Div X1- Moapa
reschedule pending resolution of SI0 funding Hiko Springs Channel-LaugMin requirements 12/93 9/93 d+ 1 9/92 d + 2 NOW 8303,000
Logan Wash Div. 12 - Moapa DONE DONE NOW
County continues consideration of Master Nelson Hood Control Improvements
right-of-way delay due to numerous property Muddy Rirer West Levee - Moapa 09/92
8800,000 diswsal araa within BLM determined aree 02/93 12/92 d + l DONE DONE
NOW owners. Droiect on hold. ON HOLD
Seerchlight flood Control
,lm~rovemants 8346,000 NOW 9/92 d + 2
groiect -1- Shading indicate* "-4 funded
9/93 d+2 12/92 d + 2 DONE DONE 84,100,000 $4.1 00,000 Jauahlin . ' :
Unnanmd Wash Improvement/ - 12/93 09/93
Plan scauisition DroDosd 1 edd'l month delay due to anvir raauirments end riaht-of-wav easements
~~
d + indicates cumulative delay in months since 6130/92
REGIONAL FLOOD CONTROL SCHEDULE CHANGE FROM DISTRICT SUMMARY SHEET AS PREVIOUS MONTH
-3-
II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT II ENTITY: CLARK COUNTY PUBLIC WORKS DATE PLZEPARED: Q8/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: PUCK CREEK BRIDGES AT TOMIYASU AND PACHUCA
DESCRIPTION: NEW BRIDGES OVER DUCK CREEK AT PACHUCA AND TOMIYASU
PERCENT COMPLETE: - 4% ESTIMATED COST OF PROJECT: S645,OOO.OO
SCHEDULE FOR COMPLETION: (DATES )
DESIGN >0/01/92
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN 12/01/92
~~~~~
CONSTRUCTION START ~~
01/01/93
CONSTRUCTION COMPLETE ~ ~~
06/01/93
CONSULTANT/PROJECT W A G E R : HEFNER
CONSTRUCTION PRIbdE CONTRACTOR:
DELAYS OR PROBLEMS AREAS: DETERMINED RIGHT-OF-WAY RESERACH REQUIRED ON TOMIYASU.
WORK COMPLETED DURING CURRENT MONTH: COMPLETED SUPPLEMENTAL HYDRAULIC ANALYSIS. BEGAN FINAL DESIGN.
WORK TO BE COMPLETED DURING NEXT MONTH: CONTINUE FINAL DESIGN.
-..
PROJECT W A G E R : PlND PHONE #: 455-8339
I . .
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEOJ PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: EAST RANGE WASH DETENTION FACILITY
DESCRIPTION: DETENTION BASIN AND 0UTLET.CHANNEL FACILITIES
PERCENT COMPLETE: ESTIMATED COST OF PROJECT: S9.387.500.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN 12/03/92
R/W CLgARAETCES
ENVIR CLEARANCES
BIDS OPEN 01/07/93
CONSTRUCTION START 01/20/93
CONSTRUCTION COMPLETE 01/28/94
CONSULTANT/PROJECT MANAGER: DOYLE ENGINEERING CORP.
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS: BCC APPROVED PESC CONTRACT 03/17/92.
WORK COMPLETED DURING CURRENT MONTH: COMPLETED PRE-DESIGN AND GEOTECHNICAL. MET WITH GENERAL GRIFFITH. BASE COMMANDER, ON 08/21/92.
~ ~~~-
WORK TO BE COMPLETED DURING NEXT MONTH: COMPLETE REVIEW OF DRAFT PRE-DESIGN WITH USAF. AIR FORCE ACCEPTS DRAFT DESIGN CONCEPT - ARRANGE MEETING WITH GENERAL GRIFFITH, BASE COMMANDER.
PROJECT MANAGER: BRANDT PHONE IC: 455-7707
-5-
. REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT L
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: &UGUST 31 PROJECT: FLAMINGO WASH - BRIDGE AT PALOS VERDES STREET DESCRIPTION: DESIGN AND CONSTRUCT ROAD CROSSING TO ACCOMMODATE 100-YEAR
STORM. DESIGN & CONTRACT ADMINISTRATION.
PERCENT COMPLETE: 100% ESTIMATED COST OF PROJECT: $450.000.00
DESIGN
SCHEDULE FOR COMPLETION: (DATES)
03/24/91
R/W CLEARANCES
ENVIR CLEARAETCES 91/01/91
BIDS OPEN 05/01/91
CONSTRUCTION START 07/08/91
CONSTRUCTION COMPLETE 07/19/92 ~ ~ ~~~~ ~
CONSULTANT/PROJECT MANAGER: =A
CONSTRUCTION PRIME CONTRACTOR: RIGGS
DELAYS OR PROBLEMS AREAS: UNDERGROUND WATER AND TELEPHONE CONFLICTS. RAINS HAVE CAUSED PROJECT TO BE DELAYED.
WORK COMPLETED DURING CURRENT MONTH: WORKING ON CLOSE-OUT DOCUMENTS.
PROJECT MANAGER: FOSTER PHONE #: 455-8334
-6-
- - - - r ' 1 1 T ' T
. II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT II ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31 PROJECT: FLAMINGO WASH - BRIDGE AT PARADISE ROAD DESCRIPTION: CONSTRUCT BRIDGE TO ACCOMMODATE 100 YEAR STORM EVENT.
DESIGN & CONTRACT ADMINISTRATION.
PERCENT COMPLETE: 100% ESTIMATED COST OF PROJECT: $750,000. O Q
DESIGN
SCHEDULE FOR COMPLETION; (DATES )
93/24/91
R/W CLEARANCES
KNVIR CLEARANCES
BIDS OPEN 05/01/91
CONSTRUCTION START 07/08/91
CONSTRUCTION COMPLETE 07/19/92
CONSULTANT/PROJECT W A G E R : MEA
CONSTRUCTION PRIME CONTRACTOR: RIGGS
PROJECT W A G E R : FOSTER PHONE #: 455-8334
-7-
II RBGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTIW: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REXIEW PERIOD FROM: JLUGUST 1 TO: AUGUST 31
PROJECT: FLAMINGO WASH AT WINNICK AVENUE
DESCRIPTION: COLLECT FLAMINGO WASH AND DISCHARGE AT KOVAL
PERCENT COMPLETE: fi E S T I M A m COST OF PROJECT: ~4.300.000.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN 09/30/92
R/W CLEARAEJCES
ENVIR CLEARANCES
BIDS OPEN J.1/30/92
CONSTRUCTION START >2/30/92
CONSTRUCTION COMPLETE 06/30/93
CONSULTANT/PROJ'ECT WOTAGER: F.C. WALLACE
CONSTRUCTION PRIME CONTRACTOR:
PELAYS OR PROBLEMS AREAS: INVESTIGATION OF A WORKING HYDRAULIC MODEL.
WORK TO BE COMPLETED DURING NEXT MONTH: PROCEED WITH WORKING MODEL.
'I
PROJECT W A G E R : BAND PHONg #: 455-8339
-8-
. - - -- - 'T - ' I 1
ll REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT II ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REWIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: RAWHIDE CHANNEL IMPROVEMENTS PHASE I - ANNIE OAKLEY TO PALM DESCRIPTION: COMPLETE REMAINING RAWHIDE CHANNEL IMPROVEMENTS
PERCENT COMPLETE: 99% ESTIMATED COST OF PROJECT: $3.000.000.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN 02/28/92
R/W CLEARANCES
ENVIR CLEARANCES ~~
BIDS OPEN 04/02/92
CONSTRUCTION START 05/11/92
CONSTRUCTION COMPLETE
CONSULTANT/PROJECT MANAGER:
CONSTRUCTION PRIME CONTRACTOR: MEADOW VALLEY CONTRACTORS
DELAYS OR PROBLEMS AREAS:
JVORK COMPLETED DURING CURRENT MONTH; CONTRACTOR COMPLETED CHANNEL LINING. SUBSTANTIAL COMPLETION ON 08/18/92. PERFORMED PUNCH LIST WALK-THROUGH ON 08/20/92.
FORK TO BE COMPLETED DURING NEXT MONTH: CONTRACTOR TO COMPLETE PUNCH LIST WORK.
PROJECT MANAGER: WONDRA PHONE #: 455-7707
-9-
II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT II ENTITY: CLARK COUNTY PUBLIC WORKS DATE PRBPARBD: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 3 1
PROJZCT: RAWHIDE CHANNEL IMPROVEMENTS PHASE I1 - CROSSINGS DESCRIPTION: PECOS. SANDHILL. MTN VISTA - COMPLETE REMAINING PROJECT
COMPONENTS
PERCENT COMPLETE: 2 ESTIMATED COST OF PROJECT: $ 3 . 0 0 0 . 0 0 0 . 0 0
DESIGN
SCHEDULE FOR COMPLETION: (DATES )
06/30/92
BIDS OPEN 98 /27 /92 ~ ~~~ ~~
CONSTRUCTION START J0/01/92
CONSTRUCTION COMPLETE 03/30/93
CONSULTANT/PROJECT MANAGER:
CONSTRUCTION PRIME CONTRACTOR:
II POTHOLE AND SURVEY AND COORDINATION WITH SOUTHWEST GAS.
WORK COMPLETED IN RENT MONTH: 11 ADVERTISED ON OiK7/:2% HELD PRE-BID ON 08/27/92 . BEGAN DESIGN ON
II NEXT PHASE OF RA~~JHIDE CHANNEL CROSSINGS AT TOMIY;ASU ELEMENTARY SCHOOL, ANNIE OAKLEY DRIVE, PEARL STREET, AND MCLEOD DR. (PHASE 111).
WORK TO BE COMPLETED DURING NEXT MONTH: CONTINUE DESIGN ON NEXT PHASE AND PREPARE SCHEDULE FOR ADVERTISING. OPEN RAWHIDE CHANNEL CROSSINGS PHASE I1 BIDS ON 09/11/92 AND HOLD RFCD AWARD ON 09 /24 /92 .
A .
PROJECT MANAGER: DTANESE PHONE #: 455-8309
-10-
PROJECT STATUS REPORT
DESCRIPTION: ROCHELLE/HILDEBRAND TO PECOS-MCLEOD & VIKING - ALSO DETENTION BASIN E
PERCENT COMPLETE: e%. ESTIMATED COST OF PROJECT: $3.500.000.00
DESIGN
SCHEDULE FOR COMPLETION: (DATES )
11/09/92
R/# CLEARANCES
EXVIR CLEARANCES
BIDS OPEN 12/16/92
CONSTRUCTION START 02/15/93
CONSTRUCTION COMPLETE 09/01/93
~ ~~~ ~~~~
CONSULTANT/PROJECT W A G E R : SEA
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS:
WORK COMPLETED DURING CURRENT MONTH: REVIEWED PRE-DESIGN.
WORK TO BE COMPLETED DURING NEXT MONTH; CONTINUE DESIGN.
\
PROJECT MANAGER: BRANDT PHONE #: 455-7707
-11-
II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT II ENTITY: CLARK COUNTY PUBLIC WORKS DATE P61EPAREDt 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: PUGUST 31
PROJECT: VAN BUSKIRK CHANNEL - SYSTEM IMPROVEMENTS (PHASE 111) DESCRIPTION: FLOOD CONTROL FACILITIES - ROCHELLE TO UNIVERSITY/MCLEOD.
PERCENT COMPLETE: 8% ESTIMATEI) COST OF PROJECT: $922.000.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN 06/08/92
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN 0 8 / 0 5 / 9 2
CONSTRUCTION START 10/19/92
CONSTRUCTION COMPLETE 02/19/93
CONSULTANT/PROJEET W A G E R : MEA
CONSTRUCTION PRIME CONTRACTOR: PROGRESSIVE CONTRACTOR
DELAYS OR PROBLEMS AREAS:
WORK COMPLETED DURING CURRENT MONTH; PROJECT AWARDED ON 08/18/92 TO PROGRESSIVE CONTRACTORS.
WORK TO BE COMPLETED DURING NEXT MONTH: BEGIN CONSTRUCTION.
PROJECT MANAGER: CEDERBURG. G. PHONE #: 455-7742
-12-
.. ._ ~- - 'T -
~~
REGIONAL
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: Q8/30/92
-1- PERIOD FROM: AUGUST 1 TO: ,?LUGUST 31
PROJECT: VAN BUSKIRK CHANNEL - SYSTEM IMPROVEMENTS (PHASE IV) DESCRIPTION: FLOOD CONTROL FACILITIES & DETENTION BASIN C BETWEEN
MCLEOD/UNIVERSITY & KARMON/HARRISON INTERSECTIONS
PERCENT C-LETE: 65% ESTIMATED COST OF PROjECT: S1.072.000.00
SCHEDULE FOR COMPLETION; (DATES )
DESIGN 99/08/92
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN 30/08/92
CONSTRUCTION START 12/28/92
CONSTRUCTION COXPLETE 94/30/93
CONSULTANT/PROjECT W A G E R : DELTA ENGINEERING
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS.
V TIED TO BASIN C OUTFALL. SPECIAL SOILS INVESTIGAT~ON ON BASIN c DUE TO HIGH WATER TABLE. PHASE
WORK COMPLETED DURING CURRENT MONTH: COMPLETED FINAL REVIEW OF 100% PLANS.
WORK TO BE COMPLETED DURING NEXT MONTH: ADVERTISE ON 09/10/92.
PROJECT MANAGER: BRANDT PHONS #: 455-7707
-13-
ll REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PRgPARED: 08/30/92
REVIEW PERIOD FROM: FUGUST 1 TO: PUGUST 31 PROJECT: VAN BUSKIRK CHANNEL - SYSTEM IMPROVEMENTS (PHASE V)
.-
DESCRIPTION: FLOOD CONTROL FACILITIES BETWEEN HARMON/HARRISON JNTERSECTION & TROPICANA AVE.
PERCENT COMPLETE: ESTfMATED COST OF PROJECT: ~1.627.000.00
DESIGN
SCHEDULE FOR COMPLETION; . (DATES)
08/14/92
R/W CLEARANCES
ENVIR CL-CES
BIDS OPEN >0/08/92
CONSTRUCTION START 12/01/92
CONSTRUCTION COMPLETE 04/23/93
CONSULTANT/PROJECT W A G E R : PENTACORE
CONSTRUCTION PRIME CONTRACTOR:
WORK COMPLETED DURING CURRENT MONTH: COMPLETED DESIGN.
WORK TO BE COMPLETED DURING NEXT MONTH: I/ ADVERTISE ON 09/11/92 (AFTER PHASE IV).
PROJECT MANAGER: B W T PHONE #: 455-7707
-14-
.. ._ - - + -
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: VAN BUSKIRK CHANNEL - SYSTEM IMPROVEMENTS (PHASE VI) DESCRIPTION: FLOOD CONTROL FACILITIES - EASTERN/TOMPKINS TO MARYLAND/RENO
& SPENCER - TROPICANA TO RENO AND DETENTION BASIN A
PERCENT COMPLETE: 4% ESTIMATED COST OF PROJECT: $4.870.000.00
SCHEDULE FOR COMPLETION; (DATES )
DESIGN 10/27/92
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN 12/02/92
CONSTRUCTION START 01/14/93 CONSTRUCTION COMPLETE 99/16/93
CONSULTANT/PROJECT MANAGER: JM MONTGOMERY
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS:
WORK COMPLETED DURING CURRENT MONTH: REVIEWED PRE-DESIGN.
PROJECT W A G E R : BRANDT PHONE #: 455-7707
-15-
RBGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PRgPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: VAN BUSKIRK CHANNEL - ROW ACOUISTION DESCRIPTION: APPRAISE AND ACOUIRE ROW FOR DETENTION BASIN SITES.
PERCENT COMPLETE: le%: ESTIMATED COST OF PROJECT: S3.100.000.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN
R/W CLEARANCES 12/30/92
ENVIR CLEARANCES
BIDS OPEN
CONSTRUCTION START
CONSTRUCTION COMPLETE
CONSULTAN!F/PROJECT W A G E R :
CONSTRUCTION PRIME CO-CTOR:
DELAYS OR PROBLEMS AREAS:
FORK COMPLETED DURING CURRENT MONTH: COMMENCED NEGOTIATIONS ON SITE 0.
WORK TO BE COMPLETED DURING NEXT MONTH: CONTINUE NEGOTIATIONS ON SITE 0.
.--. ,
PROJECT W A G E R : LAND PHONE #: 455-8300
r , I -
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: Q8/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: BUNKERVILLE FLOOD CONTROL CHANNEL
DESCRIPTION: CONSTRUCT CONCRETE LINED CHANNEL FROM HIGHWAY THRU TOWN & EARTHEN CHANNEL FROM EDGE OF TOWN TO VIRGIN RIVER. DESIGN ONLY.
PERCENT COMPLETE: 8%. ESTMdATED COST OF PROJECT: $1.714.648.00
DESIGN SCHEDULE FOR COMPLETION;
(DATES)
R/W CLEARANCES 04/15/92
ENVIR CLEARANCES 98/01/93
BIDS OPEN
CONSTRUCTION START
CONSTRUCTION COMPLETE
~~
CONSDLTANT/PROJECT MANAGER: THE MARK GROUP
CONSTRUCTION PRIBSB CONTRACTOR:
DELAYS OR PROBLEMS AREAS: PROJECT ON HOLD DUE TO PROJECT PROTEST BY BUNKERVILLE TAB. PROJECT WILL BE DELAYED DUE TO ENVIRONMENTAL REQUIREMENTS.
WORK COMPLETED DURING CURRENT MONTH: SCHEDULED MEETING WITH KENYON LEAVITT, CHAIRMAN OF BUNKERVILLE TAB.
WORK TO BE COMPLETED DURING NEXT MONTH: COMPLETE PLANS AND SPECIFICATIONS. CLOSE OUT CONTRACT WITH MARK GROUP. MEET WITH BUNKERVILLE TAB TO DISCUSS CURRENTLY DESIGNED 11 PROJECT AND THE REQUESTED FUTURE DETENTION SITE.
PROJECT W A G E R : CATANESE PHOrJE #: 455-8309
-17-
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREP-: 08/30/92
REVIEW PERIOD FROM: &UGUST 1 TO: JAUGUST 31 PROJECT: GOODSPRINGS - FLOOD CONTROL DESCRIPTION: DESIGN AND CONSTRUCT BERM AND CHANNEL ALONG SOUTH SIDE OF
TOWN AND WIDEN CHANNEL ALONG PACIFIC ST. ON NORTH SIDE OF TOWN.
PERCENT COMPLETE: 7 4% ESTIMATED COST OF PROJECT:
DESIGN SCHEDULE FOR COMPLETION:
(DATES )
99/28/92
$99,000.00
R/W CLEARANCES 03/15/92
ENVIR CLEARANCES 08/01/93
BIDS OPEN 08/15/93
CONSTRUCTION START 09/15/92
CONSTRUCTION COMPLETE 12/31/93
CONSULTANT/PROJECT MANAGER: G. C. WALLACE
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS: PROJECT CONSTRUCTION DELAY DUE TO ENVIRONMENTAL REQUIREMENTS. ACQUISITION OF ROW WITHIN SAN PEDRO AVE. TO PROPOSED DISCHARGE POINT.
WORK COMPLETED DURING CURRENT MONTH: CONTINUED DESIGN EFFORTS.
WORK TO BE COMPLETED DURING NEXT MONTH: COMPLETE DESIGN.
+
PROJECT W A G E R : CATANESE PRO= #: 455-8309
II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT II IZNTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIm PERIOD FROM: &UGUST 1 TO: JLUGUST 31
PROJECT: LAUGHLIN - HIKO SPRINGS DESCRIPTION: DESIGN FACILITY ON HIKO SPRINGS TO CONTROL 100-yEm FLOWS.
FACILITIES INCLUDE DETENTION BASIN, CHANNEL, AND FIVE BRIDGES.
PERCEWT COMPLETE: 4& ESTIMATED COST OF PROJ’ECT: $19.000.000.00
DESIGN SCHEDULE FOR COMPLETION:
(DATES 1
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN
CONSTRUCTION START
CONSTRUCTION COMPLETE
CONSULTANT/PROJECT MANAGER: BOYLE ENG’G
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS: SCHEDULE IS DEPENDENT ON SID FUNDING,LESS THAN 50% SUPPORT AT PRESENT
WORK TO BE COMPLETED DURING NEXT MONTH: CONTINUE TO SCHEDULE SID STEPS TO DETERMINE ACCEPTANCE LEVEL.
I!
PHONE #: 455-7707 PROJECT MANAGER: BRANDT
-19-
II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
EWCITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: AUGUST 31
PROJECT: MOAPA VALLEY - LOGAN WASH DIVERSION/CHANNEL AREA 1
DESCRIPTION: DESIGN DIVERSION OF LOGAN WASH INTO ANDERSON WASH TO REDUCE PEAK FLOWS.
PERCENT COMPLETE: 8% ESTIWLTED COST OF PROJECT: s690.000.00
SCHEDULE FOR COMPLETION: (DATES 1
DESIGN 08/24/92
R/W CLEARANCES
ENVIR CLgARANCES
BIDS OPEN >0/08/92
CONSTRUCTION START 12/01/92
CONSTRUCTION COMPLETE 02/15/93
CONSULTANT/PROJECT W A G E R : DAMES & MOORE
CONSTRUCTION PRIME CONTRACTOR:
I1 PRE-DETERMINED AREA.
WORK COMPLETED DURING CURRENT MONTH: COMPLETED DESIGN OF DIVERSION BERM AND ROAD.
11 WORK TO BE COMPLETED DURING NEXT MONTH: EXECUTE SUPPLEMENTAL AGREEMENT WITH DAMES & MOORE FOR ADDITIONAL
li DESIGN. NEGOTIATE WITH CONSULTANT.
PROJECT W A G E R : REZABECK PHONE #: 455-8303
-20-
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: &UGUST 1 TO: &UGUST 31
PROJECT: MOAPA VALLEY - LOGAN WASH DIVERSION/CHANNEL AREA 2
DESCRIPTION: INLET STRUCTURE AT UPRR BRIDGE. TWO 10' X 8 ' RCBS, CROSSING AT SR 169 AND OPEN CHANNEL.
PERCENT C-LETE: 8& ESTIMATED COST OF PROJECT:
DESIGN
SCHEDULE FOR COMPLETION: (DATES)
01/03/92
S3.269.540.0Q
R/W CLBAWiNCES 02/15/92
ENVIR CLEARANCES 92/15/92
BIDS OPEW 94/23/92
CONSTRUCTION START
CONSTRUCTION COMPLETE 99/15/92
CONSULTANT/PROJECT W A G E R : PAMES & MOORE
CONSTRUCTION PRIWE CONTRACTOR: MEADOW VALLEY
DELAYS OR PROBLEMS AREAS: NEWTON PROPERTY CAUSING DELAY. NEWTON TO DEDICATE ROW. IN-HOUSE UNDERGROUND DESIGN AND BCC APPROVED $200,000 CHANGE ORDER TO CONSTRUCT 2 10' CAST IN PLACE PIPES INSTEAD OF OPEN CHANNEL.
WORK COMPLETED DURING CURRENT MONTH; NEWTON CHANNEL GOING UNDERGROUND. WROTE NEW LEGAL DESCRIPTION FOR ROW DEDICATION.
WORK TO BE COMPLETED DURING NEXT MONTH: ISSUE NTP.
PROJECT W A G E R : REZABEK PHONE I: 455-8303
-21-
REGIONAL FLOOD CONTROL DISTRICT ~ ~~~~
PROJECT STATUS REPORT
DESCRIPTION: DESIGN EARTH LEVEE ON THE WEST SIDE OF THE RIVER TO CONTAIN 100-YEAR STORM.
PERCENT COMPLETE: 1% ESTIMATED COST OF PROJECT: $2,439,118.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN
CONSTRUCTION START
~ ~~~~
CONSTRUCTION COMPLETE
CONSULTANT/PROJECT MANAGER: THE MARK GROUP
CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREAS: PROJECT SCHEDULE & DATES TO BE REVISED ONCE PROJECT PROBLEMS RESOLVED. ID & ACQUISITION OF ROW & EASEMENTS FROM THE 60 PLUS PROPERTY OWNERS WILL BE EXTREMELY LENGTHY.
WORK COMPLETED DURING CURRENT MONTH: MET DENNIS JOHNSON OF RFCD AND DAVE MALPASS OF MARK GROUP. REVIEWED ROW PLATS AND MAPS AND SENT CORRECTIONS TO MARK GROUP.
WORK TO BE COMPLETED DURING NEXT MONTH: MEET WITH RFCD ON AUGUMENTATION OF SCOPE-OF-WORK.
PROJECT MANAGER: REZABEK PHONE #: 455-8303
-22-
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FRW: AUGUST 1 TO: IAUGUST 31
PROJECT: JVELSON FLOOD CONTROL
DESCRIPTION: DESIGN AND CONSTRUCT DIVERSION BERM UPSTREAM OF ROAD. WIDEN CHANNEL AND DIP,
PERCENT COMPLETE: ESTIMATED COST OF PROJECT: S70.000.00
SCHEDULE FOR COMPLETION: (DATES)
DESIGN
R/W CLgARANCES
ENVIR CLEARANCES
BIDS OPEN
CONSTRUCTION START
CONSTRUCTION COMPLETE
CONSULTANT/PROJECT MANAGER: G C WALLACE
CONSTRUCTION PRIm CONTRACTOR:
DELAYS OR PROBLEMS AREAS: COST OF FACILITIES EXCEEDS BUDGETED AMOUNT. MASTER PLAN UPDATE PROPOSES ACQUIRING PROPERTY IN LIEU OF BUILDING FACILITIES.
WORK COMPLETED DURING CURRENT MONTH:
WORK TO BE COMPLETED DURING NEXT MONTH: MEET WITH RFCD TO DISCUSS COURSE OF ACTION FOR THE RECOMMENDED MASTER PLAN FACILITIES.
PROJECT MANAGER: CATANESE
-23-
PHONE #: 455-8309
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: &UGUST 31 PROJECT: SEARCHLIGHT - DIKE DESCRIPTION: MASTER PLAN STRUCTURES #5014. 5015, 5016 & 5017
PERCENT COXPLETE : 4% ESTIMATED COST OF PROJECT: $172,000.00
SCHEDULE FOR COMPLETION: (DATES )
DESIGN 09/24/92
R/W CLEARANCES
ISNVIR CLEARANCES 08/01/93
BIDS OPEN 07/27/93
CONSTRUCTION START 99/04/93
CONSTRUCTION COMPLETE 32/31/93
CONSULTANT/PROJECT MANAGER: G C WALLACE
CONSTRUCTION PRIME CONTIZACTOR:
WORK COMPLETED DURING CURRENT MONTH: 90% PLAN SUBMITTAL AND REVIEW.
WORK TO BE COMPLETED DURING NEXT MONTH: COMPLETE DESIGN.
PROJECT MANAGER: CATANESE PHONE #: 455-8309
-24-
II REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY: CLARK COUNTY PUBLIC WORKS DATE PREPARED: 08/30/92
REVIEW PERIOD FROM: AUGUST 1 TO: JiUGUST 31 PROJECT: JJAUGHLIN - UNNAMED WASH DESCRIPTION: DESIGN FACILITY ON THE UNAMED WASH TO CONTROL 100-YEAR STORM
FLOWS. FACILITIES INCLUDE CHANNEL. SEDIMENT BASIN AND BRIDGE ON NEEDLES HWY.
PERCENT COXPLETE: 8% ESTIMATED COST OF PROJECT: S8.000.000.00
DESIGN SCHEDULE FOR COMPLETION:
(DATES )
06/15/91
R/W CLEARANCES 12/20/91
ENVIR CLEAWWCES 12/01/91 BIDS OPEN 10/09/92 CONSTRUCTION START 32/15/92
CONSTRUCTION COMPLETE 99/02/93
CONSULTANT/PROJECT MANAGER: SIMONS, LI & ASSOCIATES
CONSTRUCTION PRIME CONTRACTOR:
LAYS OR PROBLEMS AREAS: 11 !iOV. ORDER HEARING ON 06-04-91--64% PROTEST. SECOND TRY AS SID. EPA WANTS MITIGATION PLAN IN PLACE & REVIEWED PRIOR TO 404 PERMIT ISSUANCE. APPROVAL OF 47 ACRES FROM COLORADO RIWR COMM. TO CC.
WORK COMPLETED DURING CURRENT MONTH: 404 PERMIT APPPLICATION PENDING - - USEPA REVIEW RETURNED.
WORK TO BE COMPLETED DURING NEXT M 11 REVIEW FINAL PLANS & SPECS. COE TgZT. MITIGATION NEEDS. SET DESIGN TO REPLACE ONE LEVEE/PROPERTY OWNER REQUEST. II
PROJEXT MANAGER: BUNDT -25-,
PHONE #: 455-7707
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 08/31/92
REVIEW PERIOD FROM : 07/31/92 TO: 08/31/92
PROJECT: Buffalo Channel - Doe to Westcliff
DESCRIPTION: Box culvert imwovements along Buffalo from Doe to Westcliff .-
PERCENT COMPLETE: 20 $6 ESTIMATED COST OF PROJECT 8 6,500,000 DESIGN RTC & CCRFCD
SCHEDULE FOR COMPLETION: (dates)
DESIGN Mav - 1993 RMI CLEARANCE Mav - 1993 ENVIR CLEARANCES Mav - 1993 BIDS OPEN SeDtember - 1993
CONSTRUCTION START DATE October - 1993
CONSTRUCTION COMPLETE October - 1994
CONSULTANTIPROJECT MANAGER: VTN - Nevada/ Ken Gilbreth, PE CONSTRUCTION PRIME CONTRACTOR:-
DELAYS OR PROBLEMS AREA:
,
WORK COMPLETED DURING CURRENT MONTH:
30% design submitted for review.
WORK TO BE COMPLETED DURING NEXT MONTH:
CLV and CCRFCD to review 30% submittal. Design to continue toward the 70% submittal.
PROJECT MANAGER: Dave Nathan, PE PHONE #: 229-6272
WMTAlTOM\DSISTAlL& -26-
REGIONAL FLOOD CONTROL DISTRICT PROJECTSTATUSREPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 0813 1 I92
REVIEW PERIOD FROM : 07/31/92 TO: 08131192
PROJECT: Buffalo Channel (Summerlin to Veaasl DESCRIPTION: Channel or Box Culvert lmorovements alona the Pioneer Alianment from
Summerlin Parkway to Veaas Drive. PERCENT COMPLETE: 93 % ESTIMATED COST OF PROJECT: $~,OOO,OOO
DESIGN SCHEDULE FOR COMPLETION:
(dates)
DESIGN Sentember - 92 RIW CLEARANCE Complete ENVlR CLEARANCES Complete BIDS OPEN October - 92 CONSTRUCTION START DATE November - 92
*
CONSTRUCTION COMPLETE AD^ - 93
CONSULTANTIPROJECT MANAGER: VTN - Nevada1 Ken Gilbreth, PE CONSTRUCTION PRIME CONTRACTOR: NIA
DELAYS OR PROBLEMS AREA:
Coordination with Tennington Ridge subdivision development caused a two week delay in 100% submittal. Conflicts with the channel and proposed sewer line in Pioneer - Washington intersection.
WORK COMPLETED DURING CURRENT MONTH: (Design Phase)
Project presented to CCRFCD and construction funding approved.
WORK COMPLETED DURING CURRENT MONTH: (Design Phase)
Project presented to CCRFCD and construction funding approved.
WORK TO BE COMPLETED DURING NEXT MONTH:
Review 100% submittal and Obtain signatures.
PROJECT MANAGER: Dave Nathan, PE PHONE #: 229-6272
WORK TO BE COMPLETED DURING NEXT MONTH:
Review 100% submittal and Obtain signatures.
PROJECT MANAGER: Dave Nathan, PE PHONE #: 229-6272
WPOATA\TOM\OS\STATLJS -27-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: C i v of Las Veoas DATE PREPARED: 0813 1/92
REVIEW PERIOD FROM : 07131192 TO: 08l31192
PROJECT: Buffalo Channel (Westcliff to Summerlin) DESCRIPTION: Oversizing of RTC Project (Buffalo Interchange)
PERCENT COMPLETE: 35 % ESTIMATED COST OF PROJECT: $ 486,282 CONSTRUCTION CCRFCD PORTION ONLY
SCHEDULE FOR COMPLETION: (dates)
DESIGN Complete RIW CLEARANCE Complete ENVlR CLEARANCES ComDlete BIDS OPEN March - 92 CONSTRUCTION START DATE June - 92
CONSTRUCTION COMPLETE Mav - 93
CONSULTANTIPROJECT MANAGER: GB&L/ George Brizendine, PE CONSTRUCTION PRIME CONTRACTOR: Max Riqgs Construction
DELAYS OR PROBLEMS AREA:
WORK COMPLETED DURING CURRENT MONTH:
Box culvert completed across Westcliff. The entire project is approximately 35% complete. The Box culvert for the Buffalo Channel is approximately 80% complete.
WORK TO BE COMPLETED DURING NEXT MONTH:
Continue placement of the box culvert.
PROJECT MANAGER: Brian Walsh, PE PHONE #: 229-6736
WPDATA\TOM\DS\STATUS -28-
~ - . * -
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 0813 1 I92
REVIEW PERIOD FROM : 07/31/92 TO: 08/31/92
PROJECT: CLW-4 (Phase II)
DESCRIPTION: Carev-Lake Mead Detention Basin at North Las Veaas Aimort
PERCENT COMPLETE: 93 SC ESTIMATED COST OF PROJECT: $4,000,000 CONSTRUCTION
SCHEDULE FOR COMPLETION: (dates)
DESIGN April - 1991 RPN CLEARANCE Mav - 1991 ENVlR CLEARANCES Januarv - 1991 BIDS OPEN SeDtember - 1991 CONSTRUCTION START DATE November - 91
CONSTRUCTION COMPLETE SeDtember - 82
CONSULTANTIPROJECT MANAGER: VTN - NevadalKen Gilbreth, PE
DELAYS OR PROBLEMS AREA:
The contractor has not completed on schedule, liquidated damages started July 3, 1992.
WORK COMPLETED DURING CURRENT MONTH:
Completed the Detention Basin.
WORK TO BE COMPLETED DURING NEXT MONTH:
Walk through scheduled for September 2, 1992. Finalize Project.
PROJECT MANAGER: Joe Christensen. PE PHONE #: 229-221 2
WPDATAITDMIDSISTANS -29-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 0813 1/92
REVIEW PERIOD FROM : 07131192 TO: 08131192
PROJECT: CLVV.3 Gowan North and South Detention Basins DESCRIPTION: Construction of detention basins and 72inch connector pipe.
PERCENT COMPLETE 7 % ESTIMATED COST OF PROJECT $6,300,000 CONSTRUCTION
SCHEDULE FOR COMPLETION: (dates)
DESIGN Complete RIW CLEARANCE Complete ENVlR CLEARANCES Complete BIDS OPEN June - 92 CONSTRUCTION START DATE JUIV - 92
CONSTRUCTION COMPLETE JUIV - 93
CONSULTANTPROJECT MANAGER: Poaaemever Desian GroudLarrv Carroll
DELAYS OR PROBLEMS AREA:
chool buses needed for children to EisenbergIKahre Elementary schools. Haul road will disrupte traffic in CheyenneIBuffalo area.
WORK COMPLETED DURING CURRENT MONTH:
New 8-inch sewer north of Buckskin along Tenaya, new 8-inch sewer along Dalegrove. The 72-inch RCP along Tenaya is nearly complete and the road is open. The bwer north basin is excavated to the subgrade in the berm area.
WORK TO BE COMPLETED DURING NEXT MONTH:
Complete the 72-inch D-50, and the 60-inch RCP along Gowan. Begin hauling from the lower north basin to the south basin berm. Upper north basin grading.
PROJECT MANAGER: Thomas D. Chiatovich, PE PHONE #: 229-6276
WPDATA\TOM\OS\STANS -30-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 08/31 192
REVIEW PERIOD FROM : 07131192 TO: 08131192
PROJECT: CLVV-3 DESCRIPTION: Gowan Detention Basin Outfall
PERCENT COMPLETE: 65 $b ESTIMATED COST OF PROJECT: $4,400,000 CONSTRUCTION
SCHEDULE FOR COMPLETION: (dates)
DESIGN Complete RN CLEARANCE Complete ENVlR CLEARANCES None Needed BIDS OPEN Januarv - 92
CONSTRUCTION START DATE A~ril - 92
CONSTRUCTION COMPLETE Januarv - 93 CONSULTANTIPROJECT MANAGER: Poaclemever Desian GroudLanv Carroll
DELAYS OR PROBLEMS AREA:
WORK COMPLETED DURING CURRENT MONTH:
Placed 8 x 5 RCB up to Shermcrest on Gowan. The section of Gowan Road h m Bradley to Decatw is ready to be repavad.
WORK TO BE COMPLETED DURING NEXT MONTH:
Finish the 18-inch sanitary sewer to Rainbow and start the 8'x 5 RCB from Torrey Pines to Rainbow. Put the asphalt down between Bradley and Decatur.
PROJECT MANAGER: Thomas D. Chiatovich, PE PHONE #: 229-6276
WPDATAITOMIDSISTANS -31-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 0813 1 I92
REVIEW PERIOD FROM : 07131192 TO: 08131192
PROJECT: CLVV - 5 DESCRIPTION: Oakev Boulevard Detention and Convevance . . ' k
PERCENT COMPLETE: 99 96 ESTIMATED COST OF PROJECT $12,000,000 DESIGN
SCHEDULE FOR COMPLETION: (dates)
DESIGN June - 92 R/W CLEARANCE Alianment beina rcauired ENVIR CLEARANCES Under Review BIDS OPEN November - 92 CONSTRUCTION START DATE December - 92
CONSTRUCTION COMPLETE SeDtember - 93
CONSULTANTPROJECT MANAGER: Bovle Enaineering ComIGerald Moleton. PE
DELAYS OR PROBLEMS AREA:
Section 14 modified Environmental Impact Statement was sent to the BLM on June 15, 1992. BLM requested additional information on EarthQuake impacts on the Detention Basin. The project will be bid as soon as BLM approval is obtained.
WORK COMPLETED DURING CURRENT MONTH:
Boyle Engineering has been updating the Bid Documents to include conditions from the residence of the area and the C i y Council. Haul roads and the locations to place the fill on the Community Collage property have been discussed and approved.
WORK TO BE COMPLETED DURING NEXT MONTH:
Complete supplemental agreement for Professional Services to include Construction Administration, landscaping and offsite improvements by Soyle Engineering.
PROJECT MANAGER: Joe Christensen, PE PHONE #: 229-6272
WPDATAITOMIDSISTA~ -32-
. . - -. - _ T -
REGIONAL FLOOD CONTROL DISTRICT PROJECTSTATUSREPORT
ENTITY: Citv of Las Veoas DATE PREPARED: 08/31/92
REVIEW PERIOD FROM : 07/31/92 TO: 08/31 192
PROJECT Ramuart Storm Drain DESCRIPTION: Oversizino of the RTC Ramuart Storm Drain Svstem
PERCENT COMPLETE 12 $6 ESTIMATED COST OF PROJECT $ 9300.000 DESIGN
SCHEDULE FOR COMPLETION: (dates)
DESIGN Mav - 1993 RIW CLEARANCE Mav - 1993 ENVIR CLEARANCES Mav - 1993 BIDS OPEN Auaust - 1993 CONSTRUCTION START DATE Seutember - 1993
CONSTRUCTION COMPLETE November - 1994
CONSULTANTIPROJECT MANAGER: G.C. Wallacel Scott Hummer, PE CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREA:
WORK COMPLETED DURING CURRENT MONTH:
Drainage study in progress.
WORK TO BE COMPLETED DURING NEXT MONTH:
Submit Design Report.
CONSULTANTIPROJECT MANAGER: G.C. Wallacel Scott Hummer, PE CONSTRUCTION PRIME CONTRACTOR:
DELAYS OR PROBLEMS AREA:
WORK COMPLETED DURING CURRENT MONTH:
Drainage study in progress.
WORK TO BE COMPLETED DURING NEXT MONTH:
Submit Design Report.
PROJECT MANAGER: Dave Nathan, PE PHONE #: 229-6272
WPOATAITOMIDStSTATUS -33-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
LNTITY: Ci tv of Las Veaas DATE PREPARED: 08131192
R M E W PERIOD FROM : 07131192 TO: 08130192
PROJECT: Washinaton Avenue Svstem (from Vi i i Street to Lena Street) DESCRIPTION: Triale 12' X 8 RCB
PERCENT COMPLETE 95 SC ESTIMATED COST OF PROJECT $2,437,000 DESIGN
SCHEDULE FOR COMPLETION: (dates)
DESIGN Auaust- 92 RIW CLEARANCE Comdete ENVlR CLEARANCES ComDlete BIDS OPEN Not Scheduled CONSTRUCTION START DATE Not Scheduled
CONSTRUCTION COMPLETE Not Scheduled *
CONSULTANTIPROJECT MANAGER: MEAlLsumal Gubler. PE
DELAYS OR PROBLEMS AREA:
* Construction depends on future funding.
100% Submittal completed.
Review and approve 100% submittal
PROJECT MANAGER: Joe Christensen, PE PHONE #: 229.6272
-34-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 08131192 \
RENEW PERIOD FROM : 07/31/92 TO: 08/31/92
PROJECT: Washinaton Avenue Svstem I Sandhill Outlet DESCRIPTION: TriDle 12’ X 8 RCB from the Las Veaas Wash to Washington Avenue.
PERCENT COMPLETE 99 K ESTIMATED COST OF PROJECT: $1.7001100 CONSTRUCTION
SCHEDULE FOR COMPLETION: (drtot)
DESIGN C m l e t e RIW CLEARANCE Comlete ENNR CLEARANCES Comlete
BIDS OPEN Januarv - 92
CONSli3UCTlON START DATE March - 92
CONSTRUCTION COMPLETE Aumt - 92
CONSULTANTPROJECT MANAGER: MEAlLawnal Gubler. PE -
DELAYS OR PROBLEMS AREA:
WORK COMPLETED DURING CURRENT MONTH.
Walk through and punch list completed.
WORK TO BE COMPLETED DURING NEXT MONTH:
PROJECT MANAGER: Joe Christensen, PE PHONE #: 2298272
WPOATA\TOM\DS\STANS -35-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Citv of Las Veaas DATE PREPARED: 0813 1/92
REVIEW PERIOD FROM : 07131192 TO: 08131192
PROJECT: Washinaton Avenue System (from Sandhill to Viil) DESCRIPTION: Triple 12' X 8' RCB
PERCENT COMPLETE: 89 n ESTIMATED COST OF PROJECT: $2,437,000 DESIGN
SCHEDULE FOR COMPLETION: (dates)
DESIGN Mav - 92 RIW CLEARANCE ComDlete ENVlR CLEARANCES Comdete BIDS OPEN Not Scheduled CONSTRUCTION START DATE Not Scheduled
CONSTRUCTION COMPLETE Not Scheduled
CONSULTANTPROJECT MANAGER: MEAlLaurnal Gubler, PE
DELAYS OR PROBLEMS AREA:
hnding depends on BLM approval of section 14 Envinwwnental Impact Statement for the Oakey Detention Basin
WORK COMPLETED DURING CURRENT MONTH:
On hold waiting for BLM approval.
WORK TO BE COMPLETED DURING NEXT MONTH:
Bid project as soon as BLM accepts EIS for Oakey Detention Basin ( sea delays above). Complete supplemental agreement #2 for professional services for construction administration by MEA.
PROJECT MANAGER: Joe Christensen, PE PHONE #: 229-8212
-36- WPDATAITOYKJSNANT
RECEIVE^ REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT REGIONAL
FLOOD CONTROL DISTR,, ENTIW: Boulder City DATE PREPARED: 9/01/92
REVIEW PERIOD FROM: August 1 - August 31, 1992
PROJECT Hemenway Valley Flood C o n t r o l . 'a
DESCRIPTION: Wide shallow flood plain with control low flow channel and stabilized bank, detension basins, debris basins, outlet works, pipes, channel, dikes, culverts, & other appurtenances.
PERCENT COMPLETE 700h ESTIMATED COST OF PROJECT: $5,666,000.00
scHuxlLEoFooMpLET1oN: (dates)
DESIGN Sep-91
WW CLEARANCES N/A
ENVlR CLEARANCES N/A
BIDS OPEN Oct -9 1
START CONSTRUCTION Jan-92
CONSlRUCTlONcoMpLETE Jan-93
CONSULTANTPROJECTMANAGER: Coe & Van Loo, Paul Hoskins
CONSTRUCTON PRIME CONTRACTOR: Max Riggs Construction Co.
t 1 DELAYS OR PROBLEMS AREAS:
W O R K T O B E C O M P L E T E D D U R I N G ~ ~ Complete missing sections of main channel, Colorado Street and NDOT paths; and both basin spillways.
WORKTO BE COMPLETED DURING NEXTMONTH:
Complete concrete channel bottom & sideslope of upper Trailhead Channel. Start landscape & rail construction.
L J
PROJECT MANAGER: Phillip T. Henry -- PHONE 293-9200
-37-
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
%Nmr City of Henderson DATE Aumst 31. 1992
REVIEW PERIOD: FROM: Aurmst 1. 1992 TO: Aurmst 31. 1992
PROJECT: C-1 Channel System Desip
DESCRIPTION: pesim of 6 miles of concrete channel. 2 miles of piDe. and two detention basins with about 500 AF of storaee,
PERCENT COMPLETE: 30 96 ESTIMATED COST OF PROJECT: $ ~ . O O O
SCHEDULE FOR COMPLETION: (dam)
DESIGN March. 1993
R./W CLEARANCES December. 1992
ENVIR CLEARANCES December. 1992
BIDS OPEN A d . 1993
START CONSTRUCTION Mav. 1993
CONSTRUCIlON COMPLETE November. 1993
CONSULTANT/PROJECT MANAGER: VTNKen Gdbreth
CONSTRUCI'ION PRIME CONTRACTOR: None
DELAYS OR PROBLEM AREAS: None.
. ..
WORK COMPLETED DURING CURRENT MONTH: Held public hearing and reviewed predesign report.
WORK TO BE COMPLETED DURING NEXT MONTH: Finalize pre-design report and select an alternate to begin design.
PROJECT MANAGER: Curt Ch andler PHONE # 565-2329 ..
. .
- *. 3
Y O R D P g R R D A r A \ C l S T form -psr 10/26/90
-38-
. -
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY City of Henderson DATE-st 3 1. 1992
REVIEW PERIOD: FROM:&st 1.1992 TO: Aurmst 31. 1992
PROJECI': Pittman Wash Channel Phase III
DESCRIPTI0N:Concrete lined channel amroximatelv 4500 feet long with a wacitv of 1&,600 cfs. Extends from Duck Creek to SteDhanie Street.
PERCENT COMPLETE: 75 5% ..
ESTIMATED COST OF PROJECI': $3.800.000
SCHEDULE FOR COMPLETION: (dam)
DESIGN Julv 1992
WW CLEARANCES -huBL-
ENVIR CLEARANCES A t 1992
BIDS OPEN Indefinite
START CONSTRUCIION Indefinite
CONSTRUCTION COMPLETE Indefinite
CONSULTANT/PROJECI' MANAGER: PoSmeverLarry Carroll
CONSTRUCTION PRIME CONTRACTOR: None . ..
DELAYS OR PROBLEM AREAS: Construction will be deferred until right-of-way issues can be resolved.
1 WORK COMPLETED DURING CURRENT MONTH: n Meetings held with CCRFCD and Clark County to determine appropriate action. Continue work on design
plans. I WORK TO BE COMPLETED DURING NEXT MONTH:
Receive 90 percent plans from consultant and begin review. . _
PROJECT MANAGER: Curt Chand ler PHONE #: 565-2329 : - . .
C\WORDPERADATA\CCRFCDWPROJST form -psr 10/26/90 e,- :-' ('1 1 . b ~ ! 4 . i I
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY City of Henderson DATE A w t 31. 1992
REVIEW PERIOD: FROM: Aurmst 1. 1992 TO: Aurmst 31. 1992
PROJECT: Sunset Detention Basin - Predesim and Land Acauisition .. .
DESCRIPTION: Predesinn of G52AF detentign basin. inlet. and outlet u a u i s i t i o n of needed rightqf-wav.
PERCENTCOMPLETE: 0 % ESTIMATED COST OF PROJECT: $1.385.000
SCHEDULE FOR COMPLETION: (dates)
DESIGN - WW CLEARANCES Setember. 1993
ENVIR CLEARANCES Undetermined
BIDS OPEN Undetermined
START CONSTRUCIlON Undetermined
. .. CONSTRUCTION COMPLETE Undete rmined
CONSULTANTPROJECT MANAGER: None
CONSTRUCTION PRIME CONTRACTOR: None
DELAYS OR PROBLEM AREAS: 1 None
WORK COMPLETED DURING CURRENT MONTH: Interlocal Contract approved. Preparation of RFQ's c o m p l e t e d .
,WORK TO BE COMPLETED DURING NEXT MONTH: Receive proposals and select a consultant.
PROJECT MANAGER: Saeed Ahmad PHONE #: 565-2432 C\WORDPtiRRDATA\CCDWROlST form -psr 10/26/90
RECEIVED
SEP 1992
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY Citv of Henderson DATE Aurmst 31. 1992
REVIEW PERIOD: FROM:- 1. 1992 TO: t 31. 1992
PROJECT: UPRR Cbannel
DESCRIPTION: 1 Wash . . ..
PERCENT COMPLETE: 20 96 ESTIMATED COST OF PROJECT: $2.300.000.00
SCHEDULE FOR COMPLETION: (dates)
DESIGN
WW CLEARANCES
ComDlete
COmDlete
ENVIR CLEARANCES ComDlete
BIDS OPEN ComDlete
START CONSTRUCTION June. 1992
CONSTRUCTION COMPLETE December. 1992
CONSULTANT/PROJE& MANAGER: G. C. WALLAWCalvin Black
CONSTRUCTION PRIME CONTRACFBR: Max Riggs Construction
DELAYS OR PROBLEM AREAS:
PROJECT MANAGER: Curt Chandler PHONE # 565-2329 M .Ct-,T c ;*=y -aEb,EL LQ,
C \ W O R D ~ A T A \ C C R F C D W l F P R O l ~ form -psr 10/26/90
SEP 2 1992 -41-
m O N U FLOOD CONTSOL DrSTlbacT PROJECT STATUS REPORT
ENTITY: City of North Las Veqas DATE PREP- 08/28/92
REVIEW PERIOD FROM: 08/01/92 rn 08/31/92
PROJECT Gdwan Outfall Structure
DESCRI~TION. Construction of the outfall structure for the Gowan Road Detention Basin system
PERCENTC0"E: 2% ~ T E D c o 6 I O F P R O J E C P $ 11,576,000 construction , 000 eng. L a m .
12,729,000
DESIGN
WWCLEARANCES
ENvIRcLEKRANcEs
Complete
Complete
Complete
BIDS OPEN Complete
April 1991 START WNSTRUClTON
C0NSTRUC"ION COMPLETE lgg2
CONSULTANT/PROJECT MANAGER VTN Nevada/City of North Las Vegas
m u m o N PRIME mmR Las Vegas Pavinq Corporation
DELKYS OR PROBLEM AREAR
WORKC0MPL€TED DURING CURRENT MONTH:
Construction substantially completed.
PROJECT MANAGER: h v r - r.i 1 r,l lnln - PHONE #* a .
-42-
WORK TO BE COMPLETED DURING NEXT MONTH:
Finalize project.
REGIONAL FLOOD CONTROL DISIBICT PROJECT STATUS REPORT
City of North Las Veaas DATE PREPARED: 08/28/92
REVIEW PERIOD FROM: 08/01/92 m 08/31/92
PRojEm Western Tributary to the Las Vegas Wash
DESCRI~TION. Lined channel between Commerce Street and Lone Mountain Road, and channel entrance protection-AKA Stimson Channe:
P&RcENTooMpLfiE: 2 5 % ~ T E D c o 6 I O F P R O J € c r : $ 580,000
EHEDW mR W " X W (-1
DESIGN Complete
WWCLEARANCES N/A
ENvIRcuxRANcEs N/A
BIDS OPEN Complete
START CONSTRUCIION August 1992
= ~ U ~ O N October 1992
CONSULTANT/PROJECT MANAGER VTN Nevada/City of North Las Vegas
~ ~ U ~ O N PRIME a m R Las Veaas Pavinq Cornoration
DELKYS OR PROBLEM AREAS:
-Difficulties in coordination of plans prepared by two different designers and conflict in interpretation of plan details. -Newly discovered ground fissures
W 0 R K ~ " E D DURING CURRENT MON"
No construction work performed.
WORKTO BE COMPLETED DURING NDLT MONTH: . ..
Reconcile all outstanding conflicts, if any. Re-start const- ruction work. Due to difficulty in reconciling issues and ground f issures,project may fall behind schedule up to 4 wks.
PROJECT MANA- PHONE X . - c;
-43-
= O W FLOOD CONTROb DBTRICT PROJECT STATUS REPORT
ENTITE City of North Las Veqas DATE P m m 08/28/92
RFVLEW PERIOD FROM: 08/01/92 To: 08/31/92
PFt0JEm- Kyle Canyon Detention Basin
DESCRI~TION. Desiqn and prepare plans and specifications for detention basin and collection dikes
AMCIN September 1992
WWCLEARAN- November 1992
CLEARANCES November 1992
Blos OPEN September 1993
START CONSTRUCTION November 1993
November 1994
CONSULTANTPROJECT MANAGER VTN Nevada/City of North Las Vegas
CONSTRUCI'ION PRIME CO-R N/A
DELXYSORPROBLEMAREAS:
Possible problem with lO-year old Indian claim on small portion of project.
WORK COMPLETED DURING CURRENT MONTH:
-Completed basin configuration, geotechnical report and outlet structure design. -Completed 70% plan preparation. Project is on schedule.
WORKTO BE COMPLETED DURING NEXT MONTH:
Submit 90% plans for review.
= O m a O O D CONTROb DBTRICT PROJECT STATUS REPORT
ENTITY: Citv of North Las Veqas DATE PREPARED: 08/28/92
REVIEW PERIOD FROM: 08/01/92 To: 08/31/92
PRO= Umer Las Veqas Wash Detention Basin
DESCRI~TION. Construct detention basin and associated facilities in the vicinity of Floyd Lamb State Park
DMGN May 1991
WW-CES November 1991
ENvIRaEmmcEs November 1991
BIDS OPEN March 1992
START CQNSTRUCITON May 1992
CONSTRUCTION^ lgg3
CONSULTANT/PROIECT MRNKGP. Black and Veatch/City of North Las Vegas
~ ~ J S T R U ~ O N p m CONTRACTOR. Granite Construction Company
DEWPS OR PROBLEM AREAS
-Continued damage to tortoise fence by recreation vehicles, daily.
WORK D W G CURRENT MONTH: -85% R.C.B. culvert. -60% complete with pre-wet operation. -60% complete crushing and screening operation for R.C.C. face protection. -70% complete with south leg of dam. -Project is on schedule.
W O R K T O B E C O M P ~ D U R I N G W E X T ~ ~ : -90% complete pre-wet operation. -80% complete crushing and screening operation for R.C.C. face protection. -50% complete spillway construction. -40% complete all dam embankment earthwork. -Begin interception channel and berm.
PROJECT MANAGER: Rv- C i l C l l n r n .. PHONE #* - 6 . I
-45-
~ O N A S J PLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTrIY Citv of North Las Veaas DATE PREP- 08/28/92
REVIEW PERIOD FROM: 08/01/92 To: 08/31/92
PROJECT- West Ranqe Wash Diversion Dike
DEscRIpTIoN. Design and prepare plans and specifications for 5-1/2 mile long dike and appurtenances
PERCENT CO- 9 8 % -TED COST OFPROJEC'P $ 350,000 design phase
SCHEDW FOR W"I0N (-1
DMGN
ww-- ENviRcLEnRuNcEs
Completed
August 1992
June 1992
BIDS OPEN October 1992
START WNSTRUCTION December 1992
CONSTRUCTION COMPLEI'E AuCIUst lgg3
CONSULTANT/PROJE~ MANAGFR Bovle Enqineerinq/City of North Las VegaS
WNSTRUCI'ION PRIME CONTRACTOR
DEIXYS OR PROBLEM AREAS:
BLM staff hesitates to issue a lease/permit until resolution of outstanding mining claim.
WORKcoMpLfiEDDURINC CURRENT MONTH:
Attemptedto obtainmining claim relinquishment from Southern Nevada Paving Co.
Obtain relinquishment.
REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
PERCENT COHPLETE: a EST-TED COST OF PROJECT:
SClHsDULE FOR COMPLETION: (DATES )
DESIGN
S70.000.00
R/W CLEARANCES
BIDS OPEN
CONSTRUCTION START
CONSTRUCTION COMPLETE
CONSULTANT/PROJZCT MIWAGER: BOYLE ENG. CO,
CONSTRUCTION PR- CONTRACTOR:
MORK COMPJaETED DURING CURRENT MONTH: CONCLUDED GATHERING OF INFORMATION FOR FEMA TELE-CONFERENCE MEETING.
WORK TO BE COMPLETED DURING NEXT MONTH: HOLD FEMA TELE-CONFERENCE MEETING.
PROJECT MANAGER: BRANDT PHONE #: 455-7707
-47-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Ci tv of Las b a a s DATE PREPARED: 0813 1192
REMEW PERIOD FROM : 07131192 TO: 07131192
PROJECT: Gowan North Channel (Phase ll Project) DESCRIPTION: Channel to InterceDt and Convev Rows from the Northwest hto the
Gowan North Detention Basin PERCENT COMPLETE: 99 K ESTlMATED COST OF PROJECT $7,490,000
PRE-DESIGN SCHEDULE FOR COMPLETION:
(lhtesl
PRE-DESIGN Essentialhr Comdete R/W CLEARANCE Unknown ENVlR CLEARANCES Unknown BIDS OPEN M 97198 CONSTRUCTION START DATE FY 97198
CONSTRUCTION COMPLETE M 97/98
CONSULTANTIPROJECT MANAGER: Church Enaineerina ITdd Kenner. PE
DELAYS OR PROBLEMS AREA
Master Plan Amendment is planned.
WORK COMPLETED DURING CURRENT MONTH: (fbdesign Phase)
Refinements to the right-of-way drawings to reflect the Kem River gas line a
WORK TO BE COMPLETED DURING NEXT MONTH:
PROJECT MANAGER: Randv Fultz, PE PHONE #: 229-6276
~ A T A & W M S T A T U S '-48- . ._ .- - ~ T - 1 - T ' - T '
- -̂ I
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT STATUS REPORT
ENTITY City of Henderson DATE A w s t 31. 1992-
REVIEW PERIOD: F R 0 M : a s t 1. 1992 TO: Aurmst 3 1. 1992
PROJECI‘: Pittman Wash Channel Phase II
DESCRIPTION: Concrete l i n e d channel amroximatelv 1 mile lone with a caoacitv of 10.600 ds. Extends from Sunset to Santiago.
PERCENT COMPLETE: . 98 R; ESTIMATED COST OF PROJECT: $~OO.OOO
SCHEDULE FOR COMPLETION: ( d m )
DESIGN COmDleted
WW CLEARANCES OrnDleted
ENVIR CLEARANCES QgQpleted
BIDS OPEN OmDleted
START CONSTRUCTION COmDleted
CONSTRUCTION COMPLETE June. 1992
CONSULTANTIPROJECT MANAGER: Black and Veatch/Steve Roberts
CONSTRUCTION PRIME CONTRACTOR: Frehner Construction . ...
DELAYS OR PROBLEM AREAS: II None.
WORK COMPLETED DURING CURRENT MONTH: Project essentially completed.
WORK TO BE COMPLETED DURING NEXT MONTH: Walkthrough of the Project with CCRFCD staf f
PROJECT MANAGER: Curt Chandler PHONE # 565-2329 2 ”
C \ W O R D ~ A T A \ C C R F C D ~ O l S T . .
form -psr 10/26/9b
$213 2 *\::;
-49-
. - . .
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
Entity: REGIONAL FLOOD CONTROl DISTRICT Date Prepared: 09/02/92
Review Period From: 08/17/92 To 08/31 /a
PROJECT aDa Vallev Master Plan Udate
DESCRIPTION: perform a Master Plan UDdate of the MoaDa Vallev which includes the communities of
MoaDa. Gle-ndale w o n .
PERCENT COMPLETE: 2 ESTIMATED COST OF PROJECT: 3 120.000
SCHEDULE FOR COMPLETION: (Dates) Mav 1993
CONSULTANTPROJECT MANAGER: Jam es M. Montaomerv Consultina Enaineers Inc. / Lonnie Rov. P.E.
DELAYS OR PROBLEM AREAS:
None.
WORK COMPLETED DURING CURRENT MONTH:
Issued Notice to Proceed on August 13, 1992, began reconnaissance
WORK TO BE COMPLETED DURING NEXT MONTH:
Complete reconnaissance, review previous reports and plans and begin hydrologic analysis
PROJECT MANAGER: GALE WM.. FRASER. I t . P.E. PHONE #: 455-3139
-50-
-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
Entity: EGIONAI FLOOD CONTROL DISTRICT Date Prepared: 09/02/92
Review Period From: 07/13/92 To 08/31/92
PROJECT: ; i i - - i i '
DESCRIPTION: Produce a centerline alionment. I r" mtlons. rinht-of-wav mam and BLM rioht-of-wav
for the U. S. Armv of Erlpineers TroDiEgna/Flaminoo m e s Proiea
no0 Wash Detention Basin
PERCENT COMPLETE: 20 % ESTIMATED COST OF PROJECT: 3 157,000
SCHEDULE FOR COMPLETION: (Dates) March 1993
CONSULTANTPROJECT MANAGER: E. C. W a Inc. f Calvin Black. P.E.
DELAYS OR PROBLEM AREAS:
WORK COMPLETED DURING CURRENT MONTH:
Finalize reconnaissance, perform record of survey
WORK TO BE COMPLETED DURING NEXT MONTH:
Develop alternative alignments.
PROJECT MANAGER: GALE WM.. FRASER. II. P.E. PHONE #: 455-31 39
-51-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
Entity: REGIONAL FLOOD CONTROL DISTRICT Date P r e p a r e d : 0 9 / 0 2 / 9 2
Review Period From: 07/13/92 To 0813 1 I92
PROJECT -Dicana/Flaminoo Washes (AREA 2) Rioht-of-Wav AcauiSition Plan
DESCRIPTION: B e a centerline alionment. lgpal descrio- rioht-of-way and BLM rioht-of-way
gpplications for the U. S. A n v (;qtps of Emeers TroDiw/Flaminoo Washes Project
-erallv uDstream from the D r w e d TroDicana Wash Detention Basin excludinp Area 1.
PERCENT COMPLETE: 20 % ESTIMATED COST OF PROJECT: $ 150,960
SCHEDULE FOR COMPLETION: (Dates) March 1993
CONSULTANT/PROJECT MANAGER: Church Fnaineerino of Nevada. Inc. / Todd Kenner. P F.
DELAYS OR PROBLEM AREAS:
None.
WORK COMPLETED DURING CURRENT MONTH:
Completed reconnaissance, began development of alignment alternatives
WORK TO BE COMPLETED DURING NEXT MONTH:
Develop alternative alignments.
PROJECT MANAGER: GALE WM.. FRASER. II. P.F PHONE #: 455-31 39
-52-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
Entity: PFGIONAL FLOOD CONTROL DISTRICT Date Prepared: 09 / 01 / 92
Review Period From: 04 / 15 / 92 To 09 / 01 / 92
PROJECT: ; i n I
DESCRIPTION: Flood Insurance Rate MaD DreDaration for the Trodcana Wash to the confluence with the Flaminoo Wash. Base Flood Elevation determination for north. -rat and southern branchemmlmDroxiW
umits determined for minor tributaries.
PERCENT COMPLETE: 75 % ESTIMATED COST OF PROJECT: $ 213.600
SCHEDULE FOR COMPLETION: 01 / 15 / 93
CONSULTANT/PROJECT MANAGER: CH2M Hill / Ted Davis. P.E.
DELAYS FOR PROBLEM AREAS:
Project is on schedule. Special Problem Reports were filed with FEMA regarding discrepancies between break-out flow rates at the U.P.R.R and at 1-1 5 presented in the F.I.S. Hydrology report and flow rates determined by the study contractor by detailed hydraulic methods. Solutions have been reviewed and accepted by FEMA's review contractor.
WORK COMPLETED DURING CURRENT MONTH:
Data collection and field reconnaissance have been completed. Supplemental hydrology has been completed and submitted to FEMA. Topographic mapping and ground control have been completed. Approximate method flood plain delineation has been completed. Detailed hydraulic model was digitized and preliminary runs completed..
WORK TO BE COMPLETED DURING NEXT MONTH: ~~ ~
I Detailed hydraulic model to be completed and submitted to the District for review. Floodways to be determined. Work maps to be drafted. Stream profiles to be prepared.
PROJECT MANAGER: KEVIN EUBANKS. P.E. PHONE t: 455-31 39
-53-
REGIONAL FLOOD CONTROL DISTRICT PROJECT STATUS REPORT
ENTITY: Reqional Flood ControlDATE PREPARED: September 1, 1992 District
PROJECT : FLOOD AWARENESS AND SAFETY
DESCRIPTION:
PERCENT COMPLETE: 90% * .ICSTIHATED COST OF PROJECT: $ 150,000 (COnSUltant on-going fo r staff
SCHEDULE FOR COMPLETION: (date8 )
DESIGN
R/W CLEARANCES
ENVIR CLEARANCES
BIDS OPEN
START CONSTRUCTION
CONSTRUCTION COMPLETE
CONSULTANT/PROJECT MANAGER: Merica, Burch & Dickerson
CONSTRUCTION PRIME CONTRACTOR: -
DELAYS OR PROBLEMS AREAS:
None
WORK COMPLETED DURING CURRENT MONTH:
See attached
WORK TO BE COMPLETED DURING NEXT MONTH:
See attached
PROJECT MANAGER: Cathy Razor PHONE # x 455-3139 -54- form -per 10/26/90
FLOOD AWARENESS & SAFETY STATUS WORK ACCOMPLISHED DURING AUGUST,1992
Billboards Three messages are being used. DONREY showed 24 boards in August for - c- a 75% saturation level. In Septet 16 billboards will be placed for a 50% showing. Work is being performed by MBD with Donrey as a subcontractor.
v On rainy days, Review Journal newspapers are being will be wrapped in bags printed with a flood safety message. 160,OOO will be distributed on each rainy day. The bags were received in August and have beensince utilized. The bag printer had a delay in the shipment of the 2 million bags, originally scheduled for receipt in July. Work was accomplished by MBD and the Review Journal.
Red Rock Vlslto rs Center . . On Saturday, August 22, the District gave a presentation to children ages 6- 12 and parents at the Red Rock Recreation Center. Channel 5's Rusty the Fox made an appearance. The Bureau of Land Management and Fox 5 produced several press releases for the event.
Fox 5 Kids Club "Info-mercials" run 12 times per week through the six-month period of April-September. Rusty the Fox has been available for several of the visits to children. Fox 5 placed our flood awareness message on the cover of the Spring and Autumn editions of the Kids Club Newsletter. RFCD staff has discovered, through the community and school visits, that the vast majority of the young children are familiar with the flood safety messages which are played on the Fox 5 Kids Club.
W ert Storms Can Be Breathtaking" VideQ Channel 10 broadcast the video to public schools over the closed circuit channel at and sf April and is planning another set of broadcasts in September. Channel IQ notifies the teachers about the broadcast through a flyer. RFCO sends letters to each principal asking for their cooperation. RFCD continues to respond to several requests for additional information and for additional copies of the tape. Work is coordinated by RFCD staff, School District and Channel 10.
lorlna Sheet RFCD continues to distribute these to children at public presentations.
us Veaas Sanitation BillingS We are now into our second printing (1 0 0 , O O O each) of a two sided bill stuffer (one side-artwork, second side-flood safety info). Sanitation
-55-
continues to use these flyers with their billings (about 10,000 per month). Assisted by Dennis Moyer, Tom McCaffrey, Mario Garcia and Frank Pearce @ City in obtaining this distribution. Arrangements were made by RFCD staff.
Countv Sanlt- . . They have agreed to use a bill stuffer in their quarterly billings. Arrangements were made by RFCD staff.
jake Mead Recreation Area In August, the rangers were given over 3,000 pieces of literature to be distributed at 11 recreation areas in the park. In addition, the RFCD flash flood video will be shown on a regular basis at the Alan Bible Visitors Center. Coordination was accomplished by RFCD staff and the National Park Rangers.
Brochures RFCD continues to distribute the brochures through a variety of methods.
Skv View Traffic This includes radio spots on Sky View Traffic (1 0-second public service announcements over 18 local radio stations, 2 am, 2 pm/ every other week for twenty-two weeks from mid-April to mid-September). Work by MBD staff with updates to Tom Hawley by RFCD staff.
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
I SUBJECT: FINANCIAL REPORTS
PETITIONER: VIRGINIA VALENTINE. P.E., GENERAL MANAGERKHIEF ENGINEER
I RECOMMENDATION OF PETITIONER: THAT THE BOARD ACCEPT THE REPORTS
FISCAL IMPACT: None .
BACKGROUND: The following Financial Reports for the Month of July 1992. are submitted for your review:
Section DescriDtion Page0
A Fund 286: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-7 Fund Balance Report . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Sales Tax Revenue Report . . . . . . . . . . . . . . . . . . . . . . . . 2
Open Purchase Orders . . . . . . . . . . . . . . . . . . . . . . . . . . 5 ILA Approved . Not yet transferred . . . . . . . . . . . . . . . . . . 6
Monthly Expenditure Report ..................... 3-4
Accounts Payable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 B Fund 330:
Fund Balance Report . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 C Fund 443: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9-28
Fund Balance Report . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Monthly Expenditure Report . . . . . . . . . . . . . . . . . . . 10-1 1 ILA Approved -.Not yet transferred . . . . . . . . . . . . . . . . . 12 Accounts Payable . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Project ExpenseIILA Balance Report . . . . . . . . . . . . . . 14-19 Project Expense Summary ..................... 20-24 Work Maintenance Program Report . . . . . . . . . . . . . . . 25-26 Projects List . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27-28
D Fund 444: ............................... 29-34 Fund Balance Report .......................... 29 Monthly Expenditure Report ..................... 30 Accounts Payable ............................ 31
Bond Projects Funding Status Report . . . . . . . . . . . . . . . . 34 Project ExpenseDLA Balance Report . . . . . . . . . . . . . . 32-33
E Funding Request & Priorities Report/Sum . . . . . . . . . . . 35-39
Respectfully submitted.
. r. Dennis L . Johnson
lTEM # 5
Manager. Business & Finance
. . . . . .
FUND 286 - FUND BALANCE REPORT REGIONAL FLOOD CONTROL DISTRICT JULY 1992
BEGINNING FUND BALANCE AB 494 Funds (Incl Cum Interest) Unused Tax Revenues
TOTAL BALANCE
REVENUES : Sales Tax Interest Earned Sale of Materials Other
TOTAL REVENUES
EXPENSES : Salaries & Benefits Supplies ti Services Professional Services Capital Expenditures Transfer to Fund 443
TOTAL EXPENSES
ENDING FUND BALANCE (FUND 286)
OBLIGATIONS AGAINST FUND BALANCE: P.O. Balances - Prof Serv and Operating Costs ILA's Approved-funds not yet transfered to Fund 443 ILA's Approved- funds not yet transfered back to Fund 286 Bond Fund 330 - Principal & Interest Accrual Accounts Payable
CURRENT FUNDING REQUESTS
PROJECT SCOPE
TOTAL FUND OBLIGATIONS
FUNDS AVAILABLE FOR COMMITMENT
TOTAL REQUESTS FOR FUNDING
BALANCE FILE: FINRPTS\FUND286\FUNDBAL
(59,518) (23,545)
(103 , 289) (599,865)
0
(1,459,655) (7,893,507)
(4,470,653) 228,877
(100)
FISCAL IMPACT
1 o f 3 9 . . - - - T -
SALES TAX REVENUE REPORT REGIONAL FLOOD CONTROL DISTRICT
FISCAL YEAR 1992/1993
DIFFERENCE MONTH SALES 1/4 CENT SALES SALES TAX OVER/(UNDER) CUM REVENUE TAX RECEIVED TAX ESTIMATE REVENUES FROM ESTIMATE FY 92/93
JULY
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
JANUARY
FEBRUARY
MARCH
APRIL
MAY
JUNE
1,919 , 727 ll88O,6OO
1,827,050
1,849,400
1,865,550
1,804,900
1,852 , 950 2,050,800
1,695,300
1,658,800
1,902,125
1,832,900
1,877,861 (41,866)
(1,880,600)
(1,827,050)
(1,849,400)
(1,865,550)
(1,804,900)
(1,852,950)
(2 , 050,800) (1,695,300)
(1,658,800)
(1,902,125)
(1,832,900)
~~ ~
1,877,861
0
0
0
0
0
0
0
0
, o
0
0
~~ ~~
TOTAL: 22 , 140,102 1,877,861 (20,262,241) 1,877,861
FILE: FINRPTS\FUND286\SALESTAX
2 o f 3 9
MONTHLY EXPENDITURE REPORT REGIONAL FLOOD CONTROL DISTRICT FUND 286 MONTH ENDING JULY 1992
SALARIES & BENEFITS: JULY 92 RFCD EMPLOYEES JULY 92 RFCD EMPLOYEES
SUPPLIES & SERVICES:
06.23.92 06.23.92 07.23.92 06.30.92 07.08.92 06.29.92 06.29.92 06.29.92 07.15.92 07.23.92 07.23.92 07.23.92 07.23.92 07.23.92 07.23.92 06.30.92 07.08.92 07.21.92 06.30.92 06.30.92 07.15.92 07.23.92 07.23.92 07.23.92 07.23.92
HOLMAN ' S HOLMAN ' S CC TREASURER ABBOTT TROPHIES CC TREASURER TEACHERS REALTY CORP TEACHERS REALTY CORP TEACHERS REALTY CORP CC TREASURER CENTEL CENTEL CENTEL CELLULAR ATCT ADJUSTING ENTRY XEROX CORP FEDERAL EXPRESS CC TREASURER RESCUE 3 INTERNATIONAL LV REVIEW JOURNAL PRO PROCESS PRO-PROCESS CC TREASURER CC TREASURER CC TREASURER
SALARIES BENEFITS
3550 3550 3550 3550 3550
24463 24463 24463
3550 3550 3550 3550 3550 3550
19037 3550 3550 3550 3550
25974 25974
3550 3550 3550
DEPT OF CONSERVATION & NAT 3550
5000 6000
TOTAL
7010 93818 7010 93959 7010 44109 7030 4398 7110 41848 7120 062992 7120 062992B 7120 0629923 7130 43512 7140 DIRECT BILL 7140 DIRECT BILL 7140 DIRECT BILL 7140 DIRECT BILL 7140 40247 7240 033864104 7250 468817256 7250 42971 7265 072192 7280 052592 7280 14632 7280 14660 7280 44106 7280 42999 7280 42995 7330 071592
45,060.78 14,457.68
59,518.46 --------------
06.10.92 85.45 06.17.92 100.40 07.21.92 11.35 06.29.92 117.50 07.06.92 280.50 06.29.92 7,462.77 06.29.92 160.00 06.29.92 7,822.77 07.09.92 643.00 07.15.92 1,157.94 07.15.92 98.52 07.15.92 124.51 07.15.92 254.27 07.15.92 (21.57) 07.09.92 265.12 06.24.92 30.75 07.01.92 510.14 07.21.92 150.00 05.25.92 105.40 06.25.92 10.00 07.01.92 .65.25 07.15.92 1,482.63 07.15.92 1,155.90 07.15.92 472.12 07.15.92 1,000.00 --------------
23,544.72
MONTHLY EXPENDITURE REPORT REGIONAL FLOOD CONTROL DISTRICT FUND 286 MONTH ENDING JULY 1992
06.25.92 LANDISCOR 06.30.92 WILL & MUYS 06.30.92 DAMES & M O O R E 07.16.92 CC TREASURER 07.16.92 J M MONTGOMERY 07.23.92 DAMES & M O O R E
CAPITAL EXPENDITURES:
NONE THIS PERIOD
TRANSFERS TO FUND 443: MWP-HEN92/93
33138 7210 7002 06.19.92 277.00 10136 7210 062392 06.23.92 1,709 38 76007 7210 001-06317 06.30.92 165.38 3550 7210 37034 07.06.92 35,000.00 16902 7210 NV1799 07.13.92 12,153.44 76007 7210 001-06402 07.17.92 53,984.13 --------------
103,289.33
MWP - HENDERSON FISCAL YEAR 92-93
TOTAL EXPENDITURES/TRANSFERS
599,865.00
762,672.79 lPIIPIPEEEIIIP
FILE: FINRPTS\FUND286\MNTHEXPS
4 o f 39
FUND 286 OPEN PURCHASE ORDERS JULY 1992
WILL & MUYS 7210 10136 JM MONTGOMERY 7210 16902 XEROX 7240 19037 SHOSHONA S 7210 21736 TEACHER'S REALTY 7120 24463 NEVADA PHOTO 7280 28303 MERICA, BURCH & DICKERSON 7210 29184 CIS DAMES & MOORE CH2M HILL TEACHERS REALTY MERCURY BLUEPRINT HANDAR SEARS AHERN RENTERS AC HOUSTON LUMBER TEACHERS REALTY PRO-PROCESS DIGITAL EQUIP CO KAVOURAS, INC HANDAR, INC AVNET COMPUTER U.S. GEOLOGICAL SURVEY G.C. WALLACE, INC CHURCH ENGINEERING CENTEL CELLULAR RALPH JONES DISPLAY MICROSOFT CORP VALCOM VALCOM VALCOM
7210 7210 7210 7120 7280 7240 7060 7120 7030 7120 7030 7240
804017330 8040 8040 7210 7210 7210 7060 7010 7060 8040 7060 8040
31539 76007 33280 41566 33483 34113 34301 34270 34277 34367 34563 34720 35043 35047 34726
PR43753 35530 35531 35463 35541 35499 35449 35142 35496
SARRETT OFFICE FURNITURE 8040 35412 XEROX 7240 35697 HOLMAN'S OF NEVADA 7010 35758 DESERT DECOR 7010 35759 ORACLE CORP 7330 35619
20,000.00 240,000.00 5,241.60 1,500.00 80,964.78
300.00 1501000.00 8, 595.00
744,846.00 270,400.00 92,739.48 2,000.00 3 000.00 250.00 750.00 500.00
93,939.48 750.00 292.00
18,175.00 52 , 834.00 41,067.31 112,500.00 157,000.00 150,960.00
30.00 130.00 297.00 990.81 15.50 353.46 457.00
5,000.00 100.00 400.00
3,135.00
16,543.20 220,109.48 3,059.65 970.00
76, 467.70 265.84
80,401.79 900.00
401,141.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3,456.80 19 , 890.52 2,181.95 530.00
4,497.08 34.16
69,598.21 7,695.00
343,704.86 270,400.00 92,739.48 2,000.00 3,000.00 250.00 750.00 500.00
93,939.48 750.00 292.00
18,175.00 52,834.00 41,067.31 112,500.00 157,000.00 150,960.00
30.00 130.00 297.00 990.81 15.50 353.46 457.00
5,000.00 100.00 400.00
3,135.00
2,259,513.42 799,858.80 1,459,654.62 XXXIIPIPIXP~tt
FILE: FINRPTS\FUND286\PO_BAL
INTERLOCAL AGREEMENTS APPROVED - FUNDS NOT YET TRANSFERED TO FUND 443 REGIONAL FLOOD CONTROL DISTRICT FUND 286
PROJECT AGENDA RFCD BOARD NUMBER ITEM APPRVL DATE
SCOPE FISCAL IMPACT
ILA'S APPROVED IN JUNE: CLA.03.C.90 4C 06.11.92 LAS.OS.D.92 5B 06.11.92 BOU.Ol.A.87 6 06.11.92 LAS92-93 9 06.11.92
ILA'S APPROVED IN JULY: LAS.04.B.90 5 07.09.92 HEN.05.A.92 7 07.09.92 LAS.OZ.D.92 8 07.09.92 LAS.lZ.A.92 9 07.09.92 LAS.03.B.89 10 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92
ILA'S APPROVED IN AUGUST: CLA.03.D.91 118 08.13.92 NLV.Ol.B.87 13 08.13.92 LAS.12.A.92 8C 08.13.92
VAN BUSKIRK CHANNEL ROW - 2ND SUPPL WASHINGTON AVE SANDHILL-VIRGIL (CONST) HEMENWAY WASH 6TH SUPPL MAINT WORK PROGRAM - CITY OF LAS VEGAS
275,000 2,437,000
150,000 588,000
3,450,000 ------------
OAKEY BLVD DET & CONVEYANCE SUPPLEMENT 50,000 SUNSET DETENTION BASIN/COLLECTION SYS & OUTFALL 1,385,000 ANGEL PARK-PECCOLE 1 (RAMPART STORM DESIGN) 65,000 BUFFALO CHANNEL DESIGN (DOE-WESTCLIFF) 93,000 GOWAN OUTFALL & CONVEYANCE SUPPLEMENT 26,000 MAINT WORK PROGRAM FY 92-93 - NORTH LAS VEGAS 50,880 MAINT WORK PROGRAM FY 92-93 - MESQUITE 46,022 MAINT WORK PROGRAM FY 92-93 - BOULDER CITY 85,800 MAINT WORK PROGRAM FY 92-93 - CLARK COUNTY 973,835 MAINT WORK PROGRAM FY 92-93 - HENDERSON 453,170 ----------
3,228, I >
VAN BUSKIRK CHANNEL DESIGN LAS VEGAS WASH CRAIG-CIVIC CENTER ALTA STORM DRAIN CONSTRUCTION
TOTAL TRANSFERS TO FUND 443
INTERLOCAL AGREEMENTS APPROVED - FUNDS NOT YET TRANSFERED BACK TO FUND 286 REGIONAL FLOOD CONTROL DISTRICT FUND 286
PROJECT AGENDA RFCD BOARD NUMBER ITEM APPRVL DATE
SCOPE
200,000 60,000
. 954,800
7,893,507 llDDPIP%IIPI
FISCAL IMPACT
HEN.02.A.89 23 08.13.92 GREEN VALLEY PARKWAY BRIDGE BOU.OZ.A.88 23 -08.13.92 GEORGIA CHANNEL CLA.04.B.89 23 08.13.92 FLAMINGO WASH AT ARVILLE CLA90-91 23 08.13.92 CLARK COUNTY MAINT WORK PLAN FY90-91
152,486
25,181 41,799
9,410
TOTAL TRANSFERS BACK TO FUND 286 228,876
FILE: FINRPTS\FUND286\ILA_PEND
6 of 39
ACCOUNTS PAYABLE FOR JULY 92 REGIONAL FLOOD CONTROL DISTRICT FUND 286
PROCESS VENDOR P . 0 . PROJECT #/ DATE NAME NUMBER EXP CLASS ..........................................................
07.22.92 AC HOUSTON LUMBER 34277 7030 07.23.92 FEDERAL EXPRESS 3550 7250 07.23.92 FEDERAL EXPRESS 3550 7250 07.22.92 MERCURY BLUEPRINT 33483 7280 07.22.92 MERCURY BLUEPRINT 33483 7280
FILE: FINRPTS\FUND286\ACCPAY
INVOICE INVOICE INVOICE NUMBER DATE AMOUNT
001-432516 07.17.92 11.60 470823246 07.15.92 24.50 470207600 07.09.92 48.00 10732-104 07.14.92 3.00 9631-450 07.20.92 13.00 -----------
100. lo =PtaX==IP==
FUND 330 FUND BALANCE REPORT REGIONAL FLOOD CONTROL DISTRICT JULY 31, 1992
BEGINNING FUND BALANCE
REVENUES : INTEREST INCOME
EXPENSES : NONE THIS PERIOD
ENDING FUND BALANCE (FUND 330)
FILE: FINRPTS\FUND33O\FUNDBAL
8 of 39 . . - - _ - . -
36,153
260
260
0
FUND 443 FUND BALANCE REPORT REGIONAL FLOOD CONTROL DISTRICT JULY 1992
BEGINNING FUND BALANCE 24,929,403
REVENUES : TRANSFER IN FROM FUND 286 RETURN OF FUNDS TO FUND 286
599,865
EXPENSES : 9999 - CAPITAL IMPROVEMENT PROGRAM 3560 - MAINTENANCE WORK PROGRAM (2,565,283)
(111,813) ------------ (2,677,096)
ENDING FUND BALANCE (FUND 443)
COMMITTED IMPACTS TO FUND BALANCE: ILA'e APPROVED IN JUNE ILA'e APPROVED IN JULY ILA'e APPROVED IN AUGUST ACCOUNTS PAYABLE
7,891,016 TOTAL COMMITMENTS
PROJECT CLOSE-OUTS - TRANSFER OF FUNDS BACK TO FUND 286: GREEN VALLEY PARKWAY BRIDGE (152,486) GEORGIA AVENUE CHANNEL (9,4101 FLAMINGO WASH BRIDGE AT ARVILLE (25,181) MAINTENANCE WORK PROGRAM - CLARK COUNTY FY90/91 (41,799) ------------
TOTAL TRANSFER OF FUNDS TO FUND 286 (228,877)
COMMITTED FUND BALANCE (FUND 443)
FILE: FINRPTS\FUND443\FUNDBAL
9 of 3 9
MONTHLY EXPENDITURE REPORT REGIONAL FLOOD CONTROL DISTRICT FUND 443 MONTH ENDING JULY 1992
FUND PROCESS VENDOR x DATE NAME
P.0. PROJECT C INVOICE INVOICE INVOICE NUMBER EXP CLASS NUMBER DATE AMOUNT
CAPITAL IMPROVEMENT PROGRAM
443 07.07.92 443 06.30.92 443 06.25.92 443 07.15.92 443 06.25.92 443 06.30.92 443 06.30.92 443 06.30.92 443 07.15.92 443 06.30.92 443 07.15.92 443 07.15.92 443 07.15.92 443 06.25.92 443 07.15.92 443 06.30.92 443 06.30.92 443 06.30.92 443 06.25.92 443 06.30.92 443 07.13.92 443 07.23.92 443 07.23.92 443 07.14.92 443 07.14.92 443 07.23.92 443 07.23.92 443 07.23.92 443 07.23.92 443 07.14.92 443 07.23.92 443 07.23.92 443 07.08.92 443 06.25.92 443 07.14.92 443 06.25.92 443 07.14.92 443 06.25.92 443 07.14.92 443 07.14.92 443 06.25.92 443 06.25.92 443 07.08.92 443 07.08.92 443 07.08.92 443 06.25.92
MAX RIGGS CC TREASURER THE MARK GROUP BLACK & VEATCH BLACK & VEATCH CC TREASURER CC TREASURER CC TREASURER G.C. WALLACE CC TREASURER DELTA ENGINEERING JM MONTGOMERY JM MONTGOMERY PENTACORE ENG SEA INCORP CC TREASURER MAX RIGGS CONST CC TREASURER BOYLE ENG CC TREASURER CITY OF HENDERSON POGGEMEYER POGGEMEYER CITY OF HENDERSON CITY OF HENDERSON CITY OF HENDERSON CITY OF HENDERSON GC WALLACE GC WALLACE CITY OF HENDERSON VTN NEVADA VTN NEVADA CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS
28874 BOU01A87 6 13950 BUNOlA90 40952 12900 BUN01A90 2312 65832 CLA01A87 37339 65832 CLA01A87 036021 12391 CLAO2D90 40949 28143 CLAO2E91 40955 28876 CLAO3B90 40950 28153 CLA03B90 8 28156 CLA03D91 40954 28145 CLA03D91 3598 30697 CLA03D91 NV1745 30697 CLA03D91 NV1771 28155 CLAO3D91 5 29354 CLA03D91 LV-18760 23856 CLA04C90 22635 CLA04C90 28875 CLA05A91 30698 CLA06A91 28883 CLA06A91 65831 HEN01A87 19837 HENOlA87 19837 HEN01A87 16821 HENOlC90 16821 HENOlC90
14 HEN03A91 14 HEN03A91
26077 HEN03A91 26077 HEN03A91 31270 HEN04A91 31268 HEN04A91 31268 HEN04A91 67139 LASO2A87
5 LAS02B91 5 LASO2891 5 LAS02B91 4 LAS02C91 4 LAS02C91
16819 LAS03B89 3 LAS03B89 3 LAS03B89 3 LAS03B89
16819 LAS03B89 3 LAS03B89
30081 LAS04C91 13505 LAS08A89
40951 9
40956 3
40953 13431 7155 7156
013499 013432 013429 013428 032092 052292 013433
3 2
8052 7895 8078 7977 8079 7896 8062 8067 7994 7964 8055 8055 8056 7978
06.26.92 06.23.92 05.17.92 06.22.92 06.09.92 06.23.92 06.23.92 06.23.92 06.24.92 06.23.92 06.30.92 04.30.92 06.26.92 06.10.92 06.23.92 06.23.92 06.24.92 06.23.92 06.11.92 06.23.92 06.25.92 06.15.92 06.15.92 07.08.92 06.25.92 06.25.92 06.25.92 03.20.92 05.22.92 06.25.92 07.01.92 06.01.92 06.25.92 05.14.92 07.09.92 06.18.92 07.09.92 05.14.92 06.30.92 06.30.92 06.22.92 06.05.92 06.25.92 06.25.92 06.25.91 06.18.92
733,355.86 454.97
5,750.00 116.45
1,692.08 140.46
4,241.93 2,046.49 13,442.74 2,959.86 3,720.80 14,886.09 33, 922.38 27,787.28 4,305.43 9,877.’ 22 , 362. 3,428.6cl 28,032.23
351.45 1,014.45
‘10,718.12 11,911.93 4,100.00 48,095.62 4,072.67 2,326.32 25,753.00 7,924.00 6,214.79
109,086.39 69,036.10
621.26 685.97
9,097.06 937.77 78.08 711.17 193.55
16,846.30 678,480.00 28,320.00
562.57 1,374.” 1,496. 1,258.b.
10 o f 39
MONTHLY EXPENDITURE REPORT REGIONAL FLOOD CONTROL DISTRICT FUND 443 MONTH ENDING JULY 1992
FUND PROCESS VENDOR # DATE NAME
P.O. PROJECT # INVOICE INVOICE INVOICE NUMBER EXP CLASS NUMBER DATE AMOUNT
443 07.14.92 443 06.25.92 443 06.25.92 443 07.15.92 443 06.25.92 443 07.08.92 443 07.14.92 443 06.30.92 443 07.14.92 443 06.25.92 443 07.14.92 443 06.30.92 443 07.14.92 443 07.14.92 443 07.14.92 443 07.14.92 443 06.30.92
CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CITY OF LAS VEGAS CH2M HILL CITY OF NO LAS VEGAS CITY OF NO. LAS VEGAS CITY OF NO LAS VEGAS CITY OF NO. LAS VEGAS CITY OF NO LAS VEGAS CITY OF NO LAS VEGAS CITY OF NO LAS VEGAS CITY OF NO LAS VEGAS CC TREASURER
WORK MAINTENANCE PROGRAM EXPENDITURES
443 06.29.92 443 06.29.92 443 07.15.92 443 07.23.92 443 07.23.92 443 07.23.92 443 07.23.92 443 07.14.92
BOULDER CITY BOULDER CONSTRUCTION HELENA CHEMICAL CO CASHMAN EQUIPMENT CO VTN NEVADA VTN NEVADA CITY OF LAS VEGAS CITY OF NO LAS VEGAS
CONTRACTOR RETENTION INTEREST PAYMENTS:
443 07.31.92 443 07.31.92 443 07.31.92 443 07.31.92 443 07.31.92 443 07.31.92 443 07.31.92 443 07.31.92
MAX RIGGS CONSTRUCTION MAX RIGGS CONSTRUCTION MAX RIGGS CONSTRUCTION MEADOW VALLEY CONSTRUC SUPERIOR GUNITE WHEELER CONSTRUCTION CONTRI CONSTRUCTION LAS VEGAS PAVING
FILE: FINRPTS\FUND443\MNEXPRPT
13505 LAS08A89 13505 LAS08A91 19839 LAS09A89 29349 LAS09B91 29349 LAS09B91 30080 LASlOA91 30080 LASlOA91 7548 MESOlB89 14553 NLV01B87 14553 NLV01B87 23137 NLV03C91 23137 NLVO3C91 3213 NLV04A89 3213 NLV04A89 26070 NLV06A91 26070 NLV06A91 74274 SEA01A88
08063 7974 7979 8065 7980 8054
08068 204726 AR2 180 AR2143 AR2173 -2159 AR2175 AR2167 -2168 AR2170 40948
06.30.92 06.12.92 06.18.92 06.30.92 06.18.92 06.25.92 06.30.92 04.24.92 07.10.92 06.17.92 07.09.92 06.23.92 07.09.92 07.18.92 07.18.92 07.09.92 06.23.92
51,680.08 369,031.25
1,216.01 36,811.04
361.21 24,027.38 15,038.68 2,740.03 1,283.47 905.36 409.94
11,866.62 2,304.37 11,012.50 63,103.96 1,400.61
81.90
2,547,066.64 --------------
22919 BOU91-92 30078 CLA90-91 30007 CLA91-92
28 HEN91-92 26 HEN91-92 26 HEN91-92
28880 LAS91-92 28144 NLV91-92
9999 9999 9999 9999 9999 9999 9999 9999
2 06.22.92 19,647.93 RET REL 06.12.92 30,686.83 408147 06.19.92 3,530.40 JUNE92 07.14.92 16,615.00
2 07.01.92 3,738.86 1 06.01.92 3,253.79
8097 07.14.92 25,062.32 AR2166 07.07.92 9,278.00
111,813.13 --------------
8050 CJP606 8050 CJP606 8050 CJP606 8050 CJP606 8050 CJP606 8050 CJP606 8050 CJP606 8050 CJP606
07.31.92 280.65 07.31.92 932.63 07.31.92 657.53 07.31.92 503.27 07.31.92 2,706.79 07.31.92 4,025.86 07.31.92 514.52 07.31.92 8,594.95
18,216.20 --------------
TOTAL EXPENDITURES 2,677,095.97 I~~XIIIIIXXIIP
11 of 3 9 -
INTERLOCAL AGREEMENTS APPROVED - FUNDS NOT YET TRANSFERED REGIONAL FLOOD CONTROL DISTRICT - FUND 443 JULY 1992
ILA'S APPROVED IN JUNE: CLA.03.C.90 4C 06.11.92 LAS.09.D.92 5B 06.11.92 BOU.Ol.A.87 6 06.11.92 LAS92-93 9 06.11.92
ILA'S APPROVED IN JULY:
HEN.05.A.92 7 07.09.92 LAS.OZ.D.92 8 07.09.92 LAS.12.A.92 9 07.09.92 LAS.03.B.89 10 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92 MWP FY92/93 12 07.09.92
LAS.04.B.90 5 07.09.92
ILA'S APPROVED IN AUGUST: CLA.03.D.91 llB 08.13.92 NLV.Ol.B.87 13 08.13.92 LAS.12.A.92 8C 08.13.92
VAN BUSKIRK CHANNEL ROW - 2ND SUPPL 275,000 WASHINGTON AVE SANDHILL-VIRGIL (CONST) 2,437,000 HEMENWAY WASH 6TH SUPPL 150,000 MAINT WORK PROGRAM - CITY OF LAS VEGAS 588,000
3,450,000 -----------
OAKEY BLVD DET C CONVEYANCE SUPPLEMENT 50,000 SUNSET DETENTION BASIN/COLLECTION SYS & OUTFALL 1,385,000 ANGEL PARK-PECCOLE 1 (RAMPART STORM DESIGN) BUFFALO CHANNEL DESIGN (DOE-WESTCLIFF) GOWAN OUTFALL 61 CONVEYANCE SUPPLEMENT MAINT WORK PROGRAM FY 92-93 - NORTH LAS VEGAS MAINT WORK PROGRAM FY 92-93 - MESQUITE MAINT WORK PROGRAM FY 92-93 - BOULDER CITY MAINT WORK PROGRAM FY 92-93 - CLARK COUNTY MAINT WORK PROGRAM FY 92-93 - HENDERSON
VAN BUSKIRK CHANNEL DESIGN LAS VEGAS WASH CRAIG-CIVIC CENTER ALTA STORM DRAIN CONSTRUCTION
65,000 93,000 26,000 50,880 46,022 85,800 973,835 453,170 ----------
3,228,70'
200,000 60,000
954,800
1,214,800 --i--------
TOTAL TRANSFERS TO FUND 443 7,893,507 OtPIIPIIrPt
INTERLOCAL AGREEMENTS APPROVED - FUNDS NOT YET TRANSFERED BACK TO FUND 286 REGIONAL FLOOD CONTROL DISTRICT FUND 286
PROJECT AGENDA RFCD BOARD SCOPE NUMBER
FISCAL ITEM APPRVL DATE IMPACT ...........................................................................................
HEN.OZ.A.89 23 08.13.92 GREEN VALLEY PARKWAY BRIDGE 152,486 BOU.OZ.A.88 23 08.13.92 GEORGIA CHANNEL 9,410 CLA.04.B.89 23 08.13.92 FLAMINGO WASH AT ARVILLE CLA90-91
25,181 23 08.33.92 CLARK COUNTY MAINT WORK PLAN FY90-91 41,799
TOTAL TRANSFERS BACK TO FUND 286 228,876 ----------- IPlltll=DIt
FILE: FINRPTS\FUND443\1LA_PEND
1 2 of 3 9
ACCOUNTS PAYABLE FOR JULY 1992 REGIONAL FLOOD CONTROL DISTRICT FUND 443
PROCESS DATE
VENDOR P . 0 . PROJECT INVOICE INVOICE INVOICE NAME NUMBER t NUMBER DATE AMOUNT
07.15.92 07.15.92 07.15.92 07.15.92 07.15.92
SHERWIN-WILLIAMS SHERWIN-WILLIAMS SHERWIN-WILLIAMS SHERWIN-WILLIAMS SHERWIN-WILLIAMS
FILE: FINRPTS\FUND443\ACCPAY
32241 XWP-CLA 4449-4 06.10.92 970.65 32241 XWP-CLA 5410-5 06.26.92 15.56 32241 MWP-CLA 5277-8 06.25.92 271.01 32241 MWP-CLA 5372-7 06.26.92 946.08 32241 MWP-CLA 6958 06.30.92 287.60 --------------
2,490.90 aPIPllatPtPIPt
13 of 39
PROJECT EXPENSE/INTERLOUL AGREEMENT BALANCE REWRT FUND 443 CLARK COUNTY REGIONAL FLOOD CONTROL DISTRlCT
CLA.Ol.A.87 Upper Flamingo Wash 7,713,000.00 668,155.00 Detention Basin 58.000.01 8 Outfal l
CLA.OZ.D.90 Rawhide Channel Eastern t o Topaz
121499.00 2; 000.00 1,212,536.30
406,?32.45 157,984.00
427.500.00
1,265,000.00 93,150.00
907,322.80 77,000.00
1,077,472.80 _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
CLA.OZ.E.91 Rawhide Channel M c L d t o Mtn. Vista
180,000.00 65,000. 00 610.00
65,610.00 ----- - - - - - - - - - - -
CLA.03.B.90 Van Buskirk Channel
Outfal l
CLA.03.C.90 Van Buskirk Channel Right-of-way
CLA.03.D.91 Van Buskirk System
Rochelle t o Twain Spencer t o Rochelle
3,760,000.00 80,141 -25 49,293.00 18,000.00
151,081.00 277.44
3,011,832.00
3,310,624.69 - - - - - - - - - - - - - - - -
3.575,000.00 . ------ 10,850.00
130,505.20
1.253.878.50 1,115,000.00
650,000.00 15,000.00
50.000.00 77,250.00
Black 8 Veatch C.C. Treasurer Timothy Morse National T i t l e Stewart T i t l e
Nevade T i t l e Lauyers T i t l e
Uheeler Const. Clerk of C o u r t
G.C. Wallace Clark County Meed.Vly. Con.
Clark County Sui f t
Clark County Clark County Converse Cons. Suift Blprtg. G.C. Wallace Contri Const.
Clark Comty K.E. Lent, Stewart T i t l e Clerk of Court Land T i t l e o f NV Nevade T i t l e
Clark County Delta Engineering MEA
1,808.53 650,168.93 17,986.07 0.00 35,345.16 22,654.85 0.00 12,499.00 0.00
0.00 2,000.00
0.00 1,212,536.30 0.00
0.00 157,984.00 0.00 0.00
0 .oo 0.00
406,732.45 427,500.00
0.00
0.00 4,078,476.85 0.00
66,472.15
6,983,242.69 107,113.07 _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
0.00 140.46
0.00
4,241.93 0.00
2,046.49 0.00
0.00
13,442.74 0.00
0.00
0.00 0.00 0.00 0.00 0.00 0.00
3,720.80 2,959.86
0.00
85,493.05 7,656.95 65,660.10
849,092.18 58,230.62 11,339.90
17,264.119 47,135.11 234.00 375.10
46,631 -84 80,111.25 P.O. CLOSED OUT
2,661.16 18,000.00
271.44 0.00 0.00
86,422.22 64,658.18 2,922,836.51 88,995.49
13,746.83 1,253.17 10.a50.00 0.00 .------ ._._
130,505.20 0.00 1,115,000.00 0.00 1,253,878.50 0.00
632,321 .OO 0.00
39.666.80 5,463.88 9,536.12
37,583.20 34,434.42 15,565.58
1 4 o t ...J
PROJECT EXPENSE/INTERLOCAL AGREEMENT BALANCE REPQRT
CLARK CUJNTY REGIONAL FLOOD COWTROL DISTRICT FUND 443
Pentacore
SEA JM Montgomery
S w i f t
27,787.28 48,808.47 4,305.43
0.00
0.00
0.00
22,362.65 0.00
9,877.36 0.00
3,428.60 0.00
28,032.23 351.45
5,750.00 0.00
454.97 0 .00
0.00 0.00
0.00 0.00 0.00 0.00
85,309.46 55.000.14 170,999.86
13,190.54
140,905.97 171 .00
L Upstrean Section 226.000.00 98,500.00
i75i265.00 171 -00
34 359.03 0.00
Tab Contractors 0.00 61,906.00 CLA.04.A.89 Flamingo Uash Bridge at Eastern Avenue
61,900.00 61,900.00
CLA.04.C.90 Flamingo Uash Bridges a t Paradise L Palm Verde
1,702,000.00 186.82
1,345,638.15 216,620.00
80,000.00 55,672.50
1,698,117.47
145,000.00 139,860.00 5,140.00
145,000.00
480,000.00 31,000.00 449,000.00
480,000.00
- - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - -
Clark County MEA Max Riggs
Donrey Outdoor Adv Clark C m t y
193,182.74 186.82
1.294.129.34
0-00 23.437126 51,508.81 54.585.26 25i414.74
55,672.50 0.00
CLA.05.A.91 Duck Creek Bridge? Clark County Hefner Eng 33,523.61
3,570.13 106,336.39 1,569.87
Taniyasu L Pachuca
Detention Basin Fac i l i t ies
CLA.06.A.91 Range Uash 60,871.02
1,874.W 388,122.98 29,126.00 Clark County
Boylc Eng
OUTLYING AREAS:
BUN.O1 A.90 Bmkcrvi l l c Ch-1 (aka UirwLnill Uash)
1w,250.w 9,400.00 7.029.42 129.50
33,750.00 0.00
2,970.58 0.00
541,000.00 143.000.00
10.000.00 9,400.00
The Mark Group Appraisal Serv. Clark County Legal Process Sew
GSP.Ol.A.86 Goodsprings Flood Control lnprwemmts
5,205.16 0.00 32,980.00
7,794.64 w,000.00 32.980.00 13,000.00 Clark County
G.C. Uallace
Clark County Review Journal Simons L i 6 Assoc Acquisition S c i m
13,879.06 106.W
314,174.07 21,600.00
120.94 0.00
8.883.86
LAU.0l.A.69 Laughlin Unnamed Uash
0 . 00, > I
i
1 5 o f 39 1
PROJECT EXPENSE/INTERLOCAL AGREEMENT BALANCE REWRT FUND 443 CLARK COUNTY REGIWAL FLOOD COUTROL DISTRICT
LAU.02.A.89 Laughlin Hiko Springs
370,000.00 106.04 4,143.96 47,750.00 31a.ooo.00
R e v i e w Journal Clark County Simons, L i Boyle Engineers
0.00
0.00 0.00
0.00
0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
106.04 1,407.34
315,730.06 47,750.00
0.00 0.00
4,025.58 43.00 15a.5a.w
10,535.55
209,960.00 106.04
58,560.00 300.00
4,938.00 600.00
2,736.62 0.00
2,269.94 0.00
LAU.OZ.B.92
mM.Ol.B.89
mM.OZ.A.89
Laughlin Hiko Springs - Remap
Clark County Boyle Eng a.ooo.00
1,500.00
Moapa Valley Muddy River West Levee
200,000.00 10,000.00
180,000.00 43.00
Clark County Review Journal The Mark G r o y ,
5,974.42 0.00
21,416.91
Hoep. Valley Logan Wash (aka Bmson Wash)
Clark County
Danes 6 Moore Revieu Journal
Appraisal Serv. Clerk of the Court UPRR Nevada T i t l e Co.
29,398.41 0.00 0.00 0.00 0.00 0.00 0.oq
mM.02.B.92 Hoar# Valley-logan Wash (Construction)
Greiner, Inc. 0.00 0.00 23a,OOO.00
NEL.Ol.A.88
SEA.01 .A.=
Nelson Flood Control luprwcnmts
Control Inprovcnrnts Searchlight Flood
70,000.00 12,000.00 Clark County 0.00 2,961.95 9.03a.05
Clark County G.C. Wallace
a1 -90 7,452.35 14,847.65 0.00 0.00 35,500.00
CITY OF BOULDER CITY:
BOU.Ol.A.87 Hememay Wash 4,489,000.00 94'938.84 765.00
25,769.25 1~,33a.00
0.00 94,938.84 0.00 765 -00
0.00 0-00
J.H.Montgornery E.G. Radig Coe 6 Van Loo C/Boulder C i ty
....
0.00 177,227.59 9,110141 0.00 25,769.25 0.00
PROJECT EXPENSE/INTERLOUL AGREEMENT BALANCE REPORT
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT FUND 443
C I T Y OF HENDERSON:
HEN.Ol.A.87 P i t - Uash Chamel 937,000.00 562,225.00
240,000.00 9,775.00
C/Henderson
Poggeyer T r a m p
1,014.45 285,479.78 0.00
276,745.22 9,775.00
22,630.05 0.00
200,501.46 39,498.54
HEN.Ol.C.90 P i t t m Uash Channel 3,000,000.00 142,471.00 2,729,375.00
125,154.00 3,000.00
C/Henderson
Black L Veatch Superior Gunite
Nevada Labor Ccan
52,195.62 90,820.77 51,650.23 0.00 2,303,130.60 426,244.40 0.00 120.054.63 5.099.37 0.00 3;000.00 0.00
33,677.00 w,050.00 6,398.99
0.00 6,398.99 18,601 -01
HEN.03.A.91
HEN.04.A.91
HEN.05.A.92
UPRR Channel 150,o0O.00 99,050.00 25.000.00
G.C. Uallace C/Henderson
178,122.49 6,214.19
202,424.26 6,214.m 53,785.21
337,575.74 C - 1 Chamel System C/Henderson
VTN Nevada
Sunset Det Basin/ Collection L Outfal l
0.00 0.00 0 .oo
C I T Y OF LAS VEGAS:
LAS.Ol.A.87 Angel Park Detention Basin Outflow Structure
400,300.00 45,432.15 354,867.85
G.C. Uallace C/Las Vegas
0.00 45,432.15 0.00 346,114.26
0.00 8,753.59
LAS.OZ.A.87 Buffalo Chamel (aka Angel Park/Gouan Detention Basin)
4,535,965.00 217,211.95 4,314,753.05
4,000.00
G.C. Uallace C/Las Vegas Kennedy/Jenks
0.00 212,211.95 621 -26 3,824,369.32
5,000.00 490,Uu.TJ
0.00 4,000.00 0.00
i
1 7 o f 39
PROJECT EXPENSE/INTERLOCAL AGREEMENT BALANCE REPORT
CLARK COUNTY REGIOllAL FLOOD CONTROL DISTRICT FUND 443
LAS.OZ.B.91 Buffalo C h m l Srnrrrlin t o Vegas Dr. (aka Angel Park/Gowan Detention Basin)
LAS.OZ.C.91 Buffalo Chamel Ves tc l i f f to Sunrrrlin
(aka Angel Park/Gouan Detention Basin)
LAS.02.D.92 Buffalo Chamcl Design Doc-Vestcliff
LAS.03.B.89 Gowan Detention Basins 8 Outfal l
LAS.04.B.90 Oakey Blvd. System
LAS.04.C.92 Oakey Blvd. System Decatur Crossing
LAS.08.A.89 Carey Avcnuc/Lakt Uead
LAS.09.A.89 Uashington Avcnuc
Detention & C o r n . System
System
LAS.09.B.91 Uashington Avenue System Ssndhill t o Bruce
LAS.W.D.92 Vashimton A v e System Construction
LAS.lO.A.91 Gowan Worth Channel
588,898.00 588,898.00 C/Las vegas
93,000.00 0.00
5,401,000.00 4,703,774.00 C/Las Vegas
694,040.00 Poggemeyer
5,397,814.00 - - - - - - - - - - - - - - - -
562,000.00 471,665.00 Boyle Engr. 90,355.00 C/Las Vegas - - - - - - - - - - - - - - - -
562,000.00
35,000.00 35,000.00 C/Las Vegas
6,750,000.00 6,750,000.00 C/Las Vegas
542,000.00 292,000.00 M.E.A. 35,000.00 C/Las Vegas - - - - - - - - - - - - - - - - 327,000.00
471,000.00 471,000.00 C/Las Vegas
2,437,000.00 0.00
100,000.00 100,000.00 C/Las Vegas
1119.25 789.25 588,108.7s
0.00 0.00 0.00
0.00 668,726.00 725,776.65 805,768.43 3,898,005.57
25,314.00
0.00 464,121.6s 7,523.35 0.00 39,015.4s 51,339.55
1,496.90 35,000.00 CLOSE0
421,970.20 5,153,510.71 1,596,489.29
0.00 1,216.01
290,481.81 1,518.19 21,768.89 13,231.11
37,172.25 58,120.81 412,879.19
0.00 0.00 0.00
39,066.06 73,866.28 26,133.72
1 8 of
PROJECT EXPENSE/INTERLOCAL AGREEMENT BALANCE REPORT FUND 443 CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
LAS.ll.A.92 Angel Park Peccole 1 Ranpart STorn Drain
C I T Y OF MESQUITE:
MES.Ol.B.89 T o m Wash Det. Basin
C I T Y OF NORTH LAS VEGAS:
NLV.Ol.B.87 L.V. Wash/Craig to Civ ic Ctr. (aka King Charles
NLV.03.A.M West Range Wash 4 Detention Basin
NLV.03.C.91 West Range Wash Diversion Dike
NLV.04.A.W Govan Detention Basins Outfall Structure
NLV.05.A.89 Upper L.V. Wash Detention Basin
NLV.06.A.91 Kyle Canyon Detention Basin
65,000.00 0.00 0.00 0.00 0.00
2,740.03 0.00
592,785.13 30,875.00 19,125.00
17,214.87
2,380,600.00 645,088.00 C/N.Las Vegas 2,188.83 0.00 1.672.314.68
632,617.08 63.197.32 12,470.92
1,735,512.00 Max Riggs - - - - - - - - - - - - - - - - . .
2,380,600.00
360,000.00 360,000 .OO C/N . Las Vegas 0.00 307,986.25 52,015.75
350,000.00 350,000.00 C/N.Las Vegas 12.276.56 162,792.7s 187,207.25
13,420,000.00 1,366,OOO.00 C/N.Las Vegas 13,316.87 11,685,198.00 LV Paving
13,051,198.00
968,094.54 0.00 10,941,763.29
397,905.46 743,434.71 _ _ _ _ - - - - - _ - - - - - _
1,650,000.00 1,650,000.00 C/N;Las Vegas 0.00 1,545,142.56 54,1157.64
450,000.00 450,000.00 C/N.Las Veges 64,504.57 205,676.20 244,323.80
!
i 1 19 of 39
PROJECT EXPENSE SUMMARY FUND 443 CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT NUMBER
PROJECT NAME
INTERLOCAL INTERLOCAL INTERLOCAL AGREEMENT AGREEMENT AGREEMENT GRAND TOTAL AMOUNT
AMOUNT EXPIRATION DATE EXPENDED DATE REMAINING
CLARK COUNTY: CLA.Ol.A.87 U per Flamingo Wash
getention Basin SI Outfall
CLA.OZ.D.90 Rawhide Channel Eastern to Topaz
CLA.02.E.91 Rawhide Channel Mcleod to Mtn. Vista
Jul 9, 1987 Sept . 14, 1989 Dec. 13, 1990 Apr. 11, 1991
TOTAL
July 12, 1990 Oct. 11, 1990
TOTAL Oct. 10, 1991
440,000.00 July 31, 1992 6,983,242.69 729,757.31 2,081,000.00 5.819.000.00 i627;OOO.OO) ---------------
7,713,000.00
100,000.00 Dec. 31, 1991 1,000,245.33 264,754.67 1,165,000.00
1,265,000.00 ---------------
180,000.00 July 1, 1992 17 8 499 79 162,500.21
CLA.03.B.90 Van Buskirk Channel June 14, 1990 300,000.00 Apr. 17, 1992 38154,309.26 605,690.74 Outfall Aua. 8. 1991 3.460.000.00
CLA.03.C.90 Van Buskirk Channel Oct. 11, 1990 2,000,000.00 Jan. 31, 1992 3,156,301.53 418,698.47 Right-of-way Aug. 8, 1991 1,300,000.00
Jun 11, 1992 275,000.00 TOTAL 3,575,000.00
--------------- cLA.03.D.91 Van Buskirk Channel Se t. 12, 1991
Spencer to Rochelle Ocg. 10, 1991 Maryland at Reno; Tropicana at S ncer; Between Rochelc €4 Twain
CLA.04.A.89 Flamingo Waeh Bridge Sept. 14, 1989 at Eastern Avenue
CLA.04.C.90 Flamingo Waeh Brdge. July 12, 1990 at Paradise and July 12, 1990 Palos Verde Aprll 11, 1991
June 13, 1991 TOTAL
360,000.00 July 1, 1992 290,000.00 July 1, 1992
61,900.00 Dec. 31, 1990 0.00 61,900.00
750,000.00 Dec. 31, 1991 1,568,586.14 133,413.86 450,000.00 300,000.00 202,000.00 ---------------
1,702,000.00
CLA.05.A.91 Duck Creek Channel Sept. 12, 1991 100,000.00 Oct 1, 1992 37,093.74 107 , 906.26
PROJECT EXPENSE SUMMARY FUND 443 CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
CLA.06.A.91 Ran e Wash Defent ion Basin Facilities
OUTLYING AREAS: BUN.Ol.A.90 Bunkerville Channel
(aka Windmill Wash)
GSP.Ol.A.88 Goodsprin s Flood Control Improvements
LAU.Ol.A.89 Laughlin 4 Unnamed Wash
LAU.02.A.89 Lau hlin Hi& springs
LAU.OZ.B.92 Laughlin Hrko Springs Remap
MOA.Ol.B.89 Moa a Valley Mugdy River West Levee
MOA.02.A.89 Moapa Valley 4 Lo an Wash
(aza Benson Wash)
4
MOA.02.B.92 Moapa Valle Logan Was): Constructlon
NEL.Ol.A.88 Nelson Flood Control I
April 09, 1992 45,000.00
145,000.00 ---------------
Nov. 14, 1991 480,000.00 July 1, 1992
April 11, 1991 June 14, 1990 250,000.00 Dec. 31, 1991
291,000.00 TOTAL 541,000.00
--------------- June 9, 1988 99,000.00 Dec. 31, 1989
Sept. 14, 1989 350,000.00 Dec. 31, 1990
Nov. 9, 1989 370,000.00 Dec. 31, 1990
Feb. 13, 1992 9,500.00 July 1, 1993
Hay 11, 1989 200,000.00 Dec. 31, 1990
June 13, 1991 Sept . 14, 1989 173,000.00 Dec. 31, 1991 Sept 12, 1991 90,000.00
77,000.00
TOTAL 340,000.00 ---------------
Feb. 13, 1992 4,216,000.00 July 1, 1993
July 14, 1988 70,000.00 Dec. 31, 1989
62,751.02 417,248.98
125,808.92 415,191.08
5,205.16 93,794.84
352,643.02 (2,643.02)
364,993.44 5,006.56
0.00 9,500.00
162,651.67 37,348.33
284,999.59 55,000.41
0.00 4,216,000.00
2,961.95 67,038.05 a
2 1 o f 39
PROJECT EXPENSE SUMMARY CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT FUND 443
SEA.Ol.A.88 Searchlight Flood
CITY OF BOULDER CITY: BOU.Ol.A.87 Hemenway Wash
Control Improvements
CITY OF HENDERSON: HEN.Ol.A.87 Pittman Wash Channel
HEN.Ol.C.90 Pittman Wash Channel
HEN.03.A.91 UPRR Channel
HEN.04.A.91 C-1 Channel System
HE1.05.A.92 Sunset Det Basin Collection 6i Outfala
Apr. 14, 1988 172,000.00 Dec. 31, 1989 7,452.35 164,547.65
Oct. 8, 1987 205,000.00 July 1, 1988 Sept. 13, 1990
2,130,381.48 2,358,618.52 70,000.00
Mar. 14, 1991 4,064,000.00 July 9, 1992 150,000.00
TOTAL 4,489,000.00 ---------------
Au a 13, 1987 522,000.00 March 31, 1992 495,756.24 441,243.76 Fe%. 14, 1991 315,000.00 Feb. 13, 1992 100,000.00
Sept. 13, 1990 3,000,000.00 Jan. 31, 1992 2,517,006.00 482,994.00
Sept. 12, 1991 150,000.00 July 1, 1992 105,448.99 44,551.01 Sept. 12, 1991 600,000.00 July 1, 1992 208,639.05 391,360.95 July 9, 1992 1,385,000.00 0.00 1,385,000.00
CITY OF LAS VEGAS:
LAS.Ol.A.87 Angel Park Detention July 9, 1987 2,700.00 Jan. 1, 1991 Basin Structure Jan. 12, 1989 147,300.00
July 13, 1989 250,300.00
391,546.41 8,753.59
- --------------- TOTAL 400,300.00
(aka Angel Park/Gowan Jan. 15 , 1989 1,672 , 700.00 Dec. 14, 1989 3,019,365.00
TOTAL , 4,535,965.00
LAS.02.A.87 Buffalo Channel July 9 1987 94,200.00 Jan. 1, 1991 4,040,581.27 495,383.73 Detentlon Basin) July 13, 1989 (250,300.00)
--------------- LAS.02.B.91 Buffalo Channel Sept. 12, 1991 110,000.00 Jan. 31, 1994 10,720.80 119,279.20
2 2 of d 9
6E 30 EZ
Y
00'000'LE0'Z 00'000'LE~'Z Z66'1 '6 ATnS 00 '0
'18'02'1 '8s
OL'OSZ'Z'1E
61'6L8'2TV
Of '60L'6ZZ
'16'0'60'SW
68'Y'60'SU'I I
I
6Z'680'96S*'1
a3sm
TL'O'1S'tST'S
00'000'SE
68'Y'80'Sll?
'16'3'00'SU'I
06'Z98'8S Ot'LE'1'EOS 06'0'00 SU'I
I
OO'SZ9'LS r66r 'or -730 OO'OOO'OOL'S i66j 'Sf aunr
00*000'0s9 00'000'SL 066T 'ET '7daS
686T '6 'AoN LS'SOS'9Z6'f
OO'OOO'E6
68'0'fO'Sm
z6'a'zo'sU'I
SL'80'1'88S SZ'68L K6'3'ZO'SU'I
PROJECT EXPENSE SUMMARY CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT FUND 443
PROJECT NUMBER
PROJECT NAME
INTERLOCAL INTERLOCAL INTERLOCAL AGREEMENT AGREEMENT AGREEMENT GRAND TOTAL AMOUNT
DATE AMOUNT EXPIRATION DATE EXPENDED REMAINING
System Construction
LAS.lO.A.91 G w a n North Channel LAS.ll.A.92 An el Park-Peccole 1
CITY OF mSQUITE:
MES.Ol.B.89 Town Wash Detention
&impart Storm Drain
Basin
CITY OF NORTH LAS VEGAS: NLV.Ol.B.87 L.V. Wash/Craig to
Civic Center (aka King Charlee Diversion Channel)
NLV.03.A.88 West Range Wash Detention Basin
NLV.03.C.91 West Range Wash Diversion Dike
NLV.04.A.89 G w a n Detention Basins Outfall Structure
NLV.05.A.89 U per LV Wash getention Basin
NLV.06.A.91 K le Canyon getention Basin
Sept. 12, 1991 100,000.00 Jan. 31, 1992 73,866.28 26,133.72
July 9, 1992 65,000.00 0.00 65 , 000.00
July 13, 1989 480,000.00 Dec. 1, 1991 623,660.13 36,339.87 Mar. 14, 1991 180,000.00 Dec. 1, 1991
TOTAL 660,000.00 ---------------
Au 3, 1987 1,000,000.00 July 31, 1993 2,304,931.76 75,668.24 Jus, 14, 1988 no net chan e Sep . 14, 1989 500 , 000.80 June 14. 1990 880,600.00
Apr. 14, 1988 360,000.00 May 1, 1991 307,984.25 52,015.75
June 13, 1991 350,000.00 July 1, 1992 162,792.75 187,207.25
May 11, 1989 480,000.00 July 1, 1994 11,909,857.83 1,510,142.17 Mar. 14. 1991 (3.046.000.00) Nov 8 1990 15,986,000.00
Sept. 14, 1989 650,000.00 Dec. 31, 1991 1,595,142.36 54,857.64 Mar. 14. 1991 1,000,000.00 ---------------
TOTAL 1,650,000.00
Sept. 12, 1991 450,000.00 Dec. 31, 1992 205,676.20 244,323.80
WORK MAINTENANCE PROGRAM FY 92-93 FUND 443 REGIONAL FLOOD CONTROL DISTRICT
ENTITY AMOUNT ILA P.O.
NUMBER
Page 1 of 2 AS OF 08/14/92
P.O. CURRENT TOTAL AMOUNT EXPENDITURE EXPENDED BALANCE BALANCE
ILA P.O.
CLARK COUNTY 973,835.00
LAS VEGAS 588,000.00
NORTH LAS VEGAS 50,880.00
HENDERSON 453,170.00
MESQUITE 46,021.50
BOULDER CITY 85 , 800.00
i TOTAL MWP
973,835.00
1 i
i
2 5 of 39
WORK MAINTENANCE PROGRAM FY 91-92 FUND 443 REGIONAL FLOOD CONTROL DISTRICT
ENTITY ILA P.O. P.O. CURRENT TOTAL P.O. ILA
AMOUNT EXPENDITURE EXPENDED AMOUNT NUMBER BALANCE BALANCE
Page 2 of 2 AS OF 08/14/92
CLARK COUNTY 525,000.00 30742 30007 30008 32242 32258 32241 22919
LAS VEGAS
NORTH LAS VEGAS
HENDERSON
75 14 9 6 3 2
314
-------- , 000.00 ,431.40 ,450.00 ,000.00 , 102.00 ,500.00 , 582.64
3,530.40 14,434.30 0.00 0.00 75,000.00 502,060.70 0.00 8.505.00 9 5 00 42:90) 0.00 0.00 0.00 0.00
0.00 0.00
6,000.00 3,102.00
0.00 0.00 314,582.64
2 , 500.00
320,000.00 28880 320,000.00 25,062.32 25,062.32 294,937.68 294,937.68
54,985.00 28144 54,985.00 9,278.00 47,572.00 7,413.00 7,413.00
293,363.00 24 100 , 000.00 0 0.00 ioo,ooo.oo 293,363.00 25 26
126,440.00 0 0.00 126,440.00 27 16,000.00
7,000.00 6,992.65 0.00
0.00 7,000.00 0.00 16,000.00
28 20,000.00 16,615.00 0.00 20,000.00 -------------- 269,440.00
TOTAL MWP 1,332,778.20 1,903,427.28 81,126.30 138,326.08 1,070,595.16 1,194,452.12 PLIPPP=IPLPPI
TOTAL EXPENDITURES THIS PERIOD 81,126.30 t=t===ttttt=
FILE: FINRPTS\FUND443\WMPFDEAI,
26 of . .
REGIONAL FLOOO COWTROL DISTRICT CAPITAL IMPROVEMENT PROJECTS "PAY AS YOU GO" FUNDS (FUND 443) AS OF JUNE 1992
CLARK COUNTY: UPPER FLAMINGO UASH DETENTION BASIN a OUTFALL
RAUHIDE CHANNEL MCLEOD TO MTN. VISTA a PALM RAUHIDE CHANNEL EASTERN TO TOPAZ
VAN BUSKIRK CHANNEL OUTFALL (FLAMINGO RD-FLAMINGO UASH) VAN BUSKIRK CHANNEL RIGHT-OF-UAY (DET. S I T E E ) VAN BUSKIRK CHANNEL SPENCER-ROCHELLE-TUAIN 0 UPSTREAM VAN BUSKIRK CHANNEL PHASE I V IMPROVEMENTS FLAMINGO UASH BRIDGE AT EASTERN AVENUE FLAMINGO UASH BRIDGE AT ARVILLE FLAMINGO UASH BRIDGES AT PARADISE AN0 PALOS VERDE DUCK CREEK BRIDGES AT TOHIYASU P LA CASITA RANGE UASH DETENTION BASIN FACILITIES
OUTLYING AREAS: LAUGHLIN - UNNAMED UASH LAUGHLIN - HIKO SPRINGS LAUGHLIN - HIKO SPRINGS REMAP BUNKERVILLE CHANNELCAM UlNDMlLL UASH) M A P A VALLEY - HUDOY RIVER UEST LEVEE WOAPA VALLEY - LOGAN UASH ( A M BENSON UASH) WOAPA VALLEY - LOGAN UASH CHANNEL GOOOSPRINGS FLOOD CONTROL IMPROVEMENTS NELSON FLOOO CONTROL IMPROVEMENTS SEARCHLIGHT FLOOD CONTROL IMPROVEMENTS
CITY OF HENDERSON: PITTUAN UASH CHANNEL (PHASE 111) PITTHAN UASH CHANNEL (CONSTRUCTION-PHASE I ) GREEN VALLEY PARKUAY BRIDGE UPRR CHANNEL C - 1 CHANNEL SYSTEM SUNSET DETENTION BASIWICOLLECTION SYSTEM a OUTFALL
CITY OF LAS VEGAS: ANGEL PARK DETENTION BASIN STRUCTURE ( C L W - 1 ) ANGEL PARK/GWAN COWVEYANCE (AKA BUFF CHNL C L W - 2 ) ANGEL PK/GOUAN D E I BSN(BUF CHL)SU"ERLIN-VEGAS OR ANGEL PK/GOUAN D E 1 BSN(BUF CHL)UESTCLlFF-SUUMERLIN BUFFALO CHANNEL DESIGN ( DOE-UESTCLIFF )
W A N OUTFALL AND CONVEYANCE SYSTEM OAKEY BLVD DETENTION 8 CONVEYANCE SYSTEM OAKEY BLVD DETENTION P CONVEYANCE (DECATUR X- ING) CAREY AVENUE/LAKE HEAD D E 1 P CONVEYANCE SYSTEM
CLA.Ol.A.87 7,713,000 CLA.OZ.D.90 1,265,000 CLA.OZ.E.91 180,000 CLA.03.B.90 3,760,000 CLA.03.C.90 3,575,000 CLA.03.D.91 850,000 CLA.03.G.92 1,072,000 CLA.04.A.89 61,900 CLA.04.B.89 294,819 CLA.04.C.90 1,702,000 CLA.05.A.91 145,000 CLA.06.A.91 480,000 ----.---------
20,026,719
LAU.Ol.A.89 350,000 LAU.OZ.A.89 370,000 LAU.OZ.B.92 9,500 BUN.Ol.A.90 541,000 wOA.Ol.B.89 200,000 HOA.OZ.A.89 340,000 HOA.OZ.B.92 4,216,000 GSP.Ol.A.88 99,000 NEL.01.A.88 70,000 SEA.Ol.A.88 172,000 ----.-------.-
6,367,500
HEN.01 A.87 937, DO0 HEN.01.C.90 3,000,000 HEN.02.A.89 1,128,514 HEN.03.A.91 150,000 HEN.04.A.91 600,000 HEN.05.A.92 1,385,000 ------.----.--
LAS.01.A.87 LAS.OZ.A.87 LAS.02.B.91 LAS.OZ.C.91 LAS.OZ.D.92 LAS.03.B.89 LAS.04.B.90 LAS.04.C.91 LAS.08.A.89
7,200,514
400,300 4,535,965
130,000 588,898 93,000
5,401,000 562,000 35,000
6,7SO,OOO
REGIONAL FLOOO CONTROL DISTRICT CAPITAL IMPROVEMENT PROJECTS "PAY AS YOU GO" FUNDS (FUND 443) AS OF JUNE 1992
PROJECT NAME __________________________I_____________-------------. UASHINGTON AVE CONVEYANCE SYSTEM ( C L W - 9 ) UASHINGTON AM SYSTEM - SANDHILL TO BRUCE UASHINGTON AVE SYSTEM - CONSTRUCTION GOVAN NORTH CHANNEL ANGEL PARK-PECCOLE 1 [RAMPART STORM DESIGN) ALTA STORM DRAIN CHEYENNE CHANNEL - BUFFALO DR TO GOUAN S. D E 1 B A S I N
C I T Y OF MESOUITE: T W N UAStI DETENTION BASIN (DSG)
CITY OF NORTH LAS VEGAS: L V UASH CRAIG-CIV IC CENTER(AKA K ING CHARLES D I V ) EAST RANGE UASH DETENTION BASIN VEST RANGE UASH DIVERSION DIKE GOVAN DETENTION BASINS OUTFALL (STIMSON EXTENSION) UPPER LAS VEGAS UASH DETENTION BASIN (DSND P ROW) KYLE CANYON DETENTION BASIN
BOULDER CITY: HEMENUAY UASH GEORGIA AVENUE CHANNEL
CURRENT I L A SUPPLEMENTS PROJECT # VALUE OR NEU I L A ' S
I - - _ - - - - - _ _ - _ _ _ _ _ _ _ _ - - - - - - - . - - - - - - - - - - - - - - - -
LAS.W.A.89 542,000 LAS.W.B.91 471,000 LAS.W.D.92 2,437,000 LAS.lO.A.91 100,000 LAS.l l .A.92 65,000 LAS.12.A.92 954,800 LAS.13.A.92 67,000 .-------------
23,065,963
NLV.Ol.B.87 NLV.03.A.88 NLV.03.C.91 NLV.04.A.89 NLV.05.A.89 NLV.06.A.91
2,380,600 360,000 350,000
13,420,000 1,650,000
450,000
18,610,600
BOU.Ol.A.87 4,489,000 160,000 BOU.0Z.A.88 613,590
- - * - - - - - - - - - - -
5,102,590
FILE: FINRPTS\FUND443\PROJECT
2 8 of 39
FUND 444 - FUND BALANCE REPORT REGIONAL FLOOD CONTROL DISTRICT JULY 1992
BEGINNING FUND BALANCE
REVENUES : 3550 - INTEREST EARNED 9999 - INTEREST EARNED
EXPENSES : EXPENSES IN MARCH
ENDING FUND BALANCE (FUND 444)
CURRENT OBLIGATIONS AGAINST BOND FUNDS
ACCOUNTS PAYABLE BALANCE REMAINING ON PROJECT FUNDED TO DATE
UNOBLIGATED BOND FUNDS
CURRENT FUNDING REQUESTS
ENTITY SCOPE
75,936,466
FISCAL IMPACT
BALANCE 28,604,580 llllPIIPPIPPP
FILE: FINRPTS\FUND444\FUNDBAL
2 9 of 39
MONTHLY EXPENDITURE REPORT REGIONAL FLOOD CONTROL DISTRICT FUND 444 MONTH ENDING JULY 1992
07.23.92 CITY OF BOULDER CITY 07.08.92 COE & VAN LOO 07.15.92 KLEINFELDER 07.21.92 MEADOW VALLEY CONTRACTORS 07.16.92 FREHNER CONSTRUCTION 07.13.92 CITY OF HENDERSON 07.08.92 CITY OF LAS VEGAS 06.25.92 CITY OF LAS VEGAS 06.25.92 CITY OF LAS VEGAS 07.15.92 CITY OF LAS VEGAS 07.23.92 CH2M HILL 06.30.92 CH2M HILL 06.30.92 CH2M HILL 06.30.92 CH2M HILL 06.30.92 PROGRESSIVE CONTRACTING 06.25.92 CITY OF NO. LAS VEGAS 07.14.92 CITY OF NO LAS VEGAS 06.30.92 CITY OF NO. LAS VEGAS 07.21.92 GRANITE CONSTRUCTION
30696 28872
2 31052 28879
3 30079 29351 29351 29351 28870 28870 28870 28870 29034 30741 30741 30741 31267
BOU01A87 BOU01A87 CLA02F92 CLAO2F92 HENOlD91 HEN03B92 LAS03C91 LAso9c91 LAso9c91 LAso9c91 MES01A89 MES01B89 MES01B89 MESOlB89 MES01B89 NLV05B89 NLV05B91 NLV05B92 NLV05B92
5828 39320 314025
2 7
13430 8053 7993 7981 8066
206733 204736 204727 204728
7 AR2139
AR2176 AR2 160
2
02.04.92 06.15.92 06.12.92 05.27.92 07.13.92 06.25.92 06.25.91 06.22.92 06.18.92 06.30.92 06.15.92 05.22.92 04.24.92 04.30.92 06.24.92 06.12.92 07.09.92 06.25.92 07.08.92
28,188.91 19,836.55 6,045.00
209,564.10 372,123.80
181.15 5,228.67
336,379.70 2,733.48 26,865.95 57,872.08 69,449.21 17 , 606.54 103,734.23 417,138.68 3,806.10 1,278.38 16,604.29 132,652.ao -------------
1,827,289.62
FILE: FINRPTS\FUND444\MNTHEXPS
ACCOUNTS PAYABLE FOR JULY 1992 REGIONAL FLOOD CONTROL DISTRICT FUND 444
31 of 3 9
PROJECT EXPENSE/INTE-AL AGREEMENT BALANCE REPORT FUND 444 CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
CLA.02.F.91 RAWHIDE CHANNEL 02.13.92 07.09.92
CLA.OJ.E.92 VAN BUSKIRK SYSTEM 06.11.92 (ROCHELLE-MCCLOUD)
CLA.03.F.92 VAN BUSKIRK CHANNEL 07.09.92 (PHASE V IMPROVEMENTS)
BOULDER CITY :
1,391,000 03.31.93 594,485
218,287 1,767,198
921,800 07.01.93 0 921,800
1,627,000 07.01.93
BOU.Ol.A.87 Hemenway Wash 11.14.91 BOU.Ol.A.87 Hemenway Wash
1,327,000 12.01.92 02.13.92 (460,000) ---------------
HENDERSON : 867,000
0 1,627,000
668,999 198,001
HEN.Ol.D.91 Pittman Waah Chnl 11.14.91 2,520,000 07.31.92 1,792,862 727,138 HEN.03.B.91 UPRR Channel 03.12.92 2,600,000 01.31.93 181 2,599,819 LAS VEGAS:
Phase 11
LAS.03.C.91 Gowan Detention 11.14.91 10,900,000 03.31.94 25,452 10,874,548 Basin
LAS.04.D.92 Oakey Blvd Detention 05.09.92 9,519,200 11.01.94 Basm
0 9,519,200
LAS.09.C.91 Washington Ave. 11.14.91 1,700,000 07.01.94 System - Sandhill Outfall
527,332 1,172,668
MESQUITE: MES.Ol.B.89 Town Wash 11.14.91
Detention Basin 04.09.92 5,448,304 07.01.93 2,770,578 1,366,926 (1,310,800) 4,137,504
---------------
, a
PROJECT EXPENSE/INTERLOCAL AGREEMENT BALANCE REPORT FUND 444 CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT
PROJECT NUMBER
PROJECT NAME
INTERLOCAL INTERLOCAL INTERLOCAL AGREEMENT AGREEMENT AGREEMENT
GRAND
DATE AMOUNT EXPIRATION EXPENDED REMAINING TOTAL AMOUNT
NLV.OS.B.92 Up r Las Vegas Wash 01.09.92 12,900,000 07.30.93 Degntion Basin
192,255 8,757,745 (3,950,000)
OUTLYING AREAS :
7 7 I , ? 7f-l
BONO PROJECTS FUNO 444 OBLIGATIONS
AS OF 19-Aw-92
CLARK COUNTY EAST RANGE UASH DETENTION BASIN RAUHIDE CHANNEL IMPROVEMENTS RAUHIDE CHANNEL ANNIE OAKEY-PALM VAN BUSKIRK SYSTEM IMPROWENTS VAN BUSKIRK SYSTEM
CLARK COUNTY OUTLYING AREAS UNNAMED UASH - LAUGHLIN
C I T Y OF LAS VEGAS BUFFALO CHANNEL (SUCWERLIN PKUY)
GOWAN DETENTION BASINS
OAKEY ELVD. DETENTION BASIN UASHINTON AVE/SANDHILL OUTFALL
C I T Y OF HENDERSON C-1 CHANNEL SYSTEM PITTHAN UASH CHANNEL -PHASE 2 PITTHAN UASH CHANNEL -PHASE 3 UPRR CHANNEL
C I T Y OF BOULDER C I T Y HEHENUAY UASH
C I T Y OF MESQUITE T W N UASH DETENTION BASIN
C I T Y OF NORTH LAS VEGAS
UPPER LAS VEGAS UASH DE1 BASIN
WEST RANGE UASH DIVERSION DIKE
CLA.06.A.91 CLA.0Z.F.92 CLA.OZ.F.92 CLA.03.D.91 CLA.03.E.92 CLA.03.F.92
LAU.Ol.E.92
LAS.OZ.E.91 LAS.02.E.92 LAS.03.C.91 LAS.03.C.91 LAS.04.0.92 LAS.OP.C.91
HEN.04.A.91 HEN.Ol.O.91 HEN.Ol.A.87 HEN.03.E.92
BOU.Ol.A.87
llES.Ol.E.89
NLV.05.B.92
NLV.03.A.88
a,62o,ooo a,62o,ooo 2,820,000 1,391,000 02/13/92
594,485 834,515 07/09/92 7,070,200 7,070,200
921,800 921,800 0 06/11/92 0 1,627,000 (1,627,000) 07/09/92
4,100,000 4,100,000 0 03/12/92
1,500,000 1,500,000 2,245,500 (2,245,500) 08.13.92
10,240,000 10,900,000 (660,000) 11/14/91 (3,400,000) 2,740,000 08.13.92
7,970,000 9,519,200 (1,549,200) 05/09/92 1,700,000 1,700,000 0 11/14/91
6,000,000 6,000,000 3,470,000 2,520,000 950,000 11/14/91 3,162,200 3,162,200 2,300,000 2,600,000 (300,000) 03/12/92
0 1,327,000 11/14/91 (460,000) (867,000) 02/13/92
5,448,304 5,448,304 D 11/14/91 (1,310,800) 1,310,800 04/09/92
12,800,000 12,900,000 (100,000) 01/9/92 (3,950,000) 3,950,000 05/09/92
4,000,000 4,000,000
3 4 of 3 9 .. _ * - - -
i
FUNDING REQUESTS AND PRIORITIES REPORT (FY 92/93) 27-Aug-92
I file:GWf:m:\excel\funpri93.xls
Requests Comments/ Bond FY 92/93 Entity Amount Project Description Received
Funding Priority Numbers
#
13-Aug-92 93-4B CLV $2,245,500 Buffalo Channel; Summerlin to Vegas Dr. 14-Jul 9 1 3-Aug-92 93-38 CLV ($3,400,000) Gowan Detention Basins - 1 st Suppl. 14-Jul 8
9-JuI-92 93-28 CC $1,627,000 Van Buskirk Phase V 9-Jun 7 9-Jul-92 93-5 CLV $26,000 Gowan Detention Basins - 7th Suppl. 9-Jun 6 9-JuI-92 93-4 CLV $93,000 Buffalo Ch. (Westcliff - Doe) 9-Jun 5 9-JuI-92 93-3 CLV $65,000 Rampart Storm Drain 9-Jun 4 9-JuI-92 93-2 HEND $1,385,000 Sunset Detention Basin 9-Jun 3 9-Jut-92 93- 1 B CC $594,485 Rawhide Channel - 1st Suppl. 9-Jun 2 9-JuI-92 93-1 CLV $50,000 Oakey Detention System - 2nd Suppl. 9-Jun 1
Approval Date List List Date
16 1 1 -Aug Cheyenne Channel $67,000 -CLV 93-1 1 17 17-Aug Hemenway Wash - 7th Suppl. $1 60,000 BC 93- 1 2 18 24-Aug Gowan Detention Basins - 2nd Suppl. $0 CLV 93-68 .
I I I NOTES: a - resubmit or hold funding request
b - Mwter Wan Amendment required c - environmental clearances required d - right-of-way required e - engineering study required f - project presentation required g - Policies & Procedures not followed
I
35 of 39
i
FY 92/93 PROJECT LIST - FUNDING REQUEST SUMMARY THROUGH 8/19/92
Program
I I Funding I Amount
[under constructionl
Oakey Datantion Basin and Collection System
[begin basin &I outfall constJconst. part of collection sys.1
Deeign funddlpart of oonrt. on
$50,000 $50,000 Lone Mountain Detention Basin
[predesignl $50,000 $50,000 CAM-10 Detention Basin (West Centennial)
Icomprete predesignl
Predesign funded Gowan Merth Ch. (Lone Mountain - CAM-10 Det. Basin)
[complete pradesignl
Predesign funded Gowan North Channel (Detention Basin - Lone Mountain) $95,000 $93,000 0 188,000 [const. north of Wstcliff/design south of Westcliff]
Part of design 81 conet. funded buffalo Channel (Veges Dr - Charleston)
,[ROW acquisition] $270,000 $270,000 'Washington Avo Ch. Parallel Drain to F St.
[complete design] Design funded 'flashington Avo. Ch. - Reach 3 (Mojave Rd - 24th St)
[complete design] Design funded Weshington Avo. Ch. - Reach 2 (Honolulu - Mojave Rd)
,[const. from Las Vegas Wash to Virgil Street]
Des. fundedfiunding accelerated Washington Ave. Ch. - Reach 1 (LV Wash - Honolulu)
[design Rampart storm drain] $0 $65,000 $65,000 Peccole Ranch Outfalls (Rampart Storm Drain)
[complete channel from Buffalo to basinlupgrade bridges] $841,000 $67,000 8 908,000 Cheyenne Channel
[complete expansion] $100,000 $100,000 Angel Park Detention Basin Expansion ($26,000 $26,000 [begin constructionl
Funded Gowan Detention Basins
[under constructionl Funded Gowan Outfall Structure (Decatur - Tenaya Way)
Bond Liet [begin constructionl
DrsiOn fundedlconst. on Oakey Detention Basin Outfall $1,049,200 $50,000 Bond List $1,099,200
IMeadows Phase V, Aka Drive Storm Drain (Falcon to I I I Jones) [constructionl 1-15 Freeway Channel (Sahara to Ivanhoe) [NDOT
$0 $954,800 $954,800
oversizing constructionl I $600,000 I $0
93,029,200 Lao Vogae FY 92/93 Total : I $4,285,000 I $1,255,800 $600,000
FY 92/93 PROJECT LIST - FUNDING REQUEST SUMMARY THROUGH 8/19/92 N.:rn:\uo.l\(v92-OS.xh
Program Funding Amoun? I I
UPRR Channel Funded
[under construction]
Lower C-1 Channel (Lake Mead Dr. - Drake St.) Design fundedlconst. on Bond
[complete designlconstruction to begin1 List
Sunset Det. Basin, Collection Sys. & Outfall (incl. ROW) $1,385,000 $1,385,000 $0 Ipredesign & ROW acquisition of basin1
Mission Hills Det. Basin & Collection System (incl. ROW) Design part fundadlpart of
[complete designlconstruction to begin] const. on Bond List
Pittman Wash (Sunset - UPRR) & Pittman Park Det. Basin Design fundedlchennel const.
[channel under constructionlcomplete basin predesignl funded
Pittman Wash (Duck Creek - Stephanie St) Design funded
Confluence Detention Basin (incl. ROW) Design fundedlconstruction
[complete designlbegin construction] on Bond List
Upper Las Vegas Wash Interception BermlChannal Funded
[under construction]
Upper Las Vegas Wash Detention Basin Funded
[under constructionl
North Las Vegas Datantion Basin (outlet modifications) $30,000 $30,000
[construct modifications]
West Range Wash Diversion Dike Design fundedlpart of const.
[begin constructionl on Bond List 8 1,200,000 8 1,200,000
Sloan Channel (Les Vegas Wash - Confluence Det. Basin) $800,000 $800,o0O [design]
Kyle Canyon Detention Basin (incl. ROW) Design funded
[complete dasignlROW acquisition1 $100,000 $100.000
Las Vegas Wash (Craig to Civic) ,[complete
construction] $00,000 $60,000 $0 North Las Voges FY 92/93 Total : I $2,190,000 $60,000 82,130,000
37 o f 3 9 _. _. - - f . -
FY 92/93 PROJECT LIST - FUNDING REQUEST SUMMARY THROUGH 8/19/92
Program
Funding Amount Facilitv DaacriDtion Amount Promrammad
1 West Levee - Muddy River IDesign funded
BOND PROJECT LIST - FUNDING REQUEST SUMMARY THROUGH 8/14/92
file:GWF:m:\excel\sum bd.xls
I I TOTAL OF I FUNDING I PROGRAM I
MESQUITE Town Wash Detention Basin $5,448,304 I $4,137,504 $1,310,800
TOTAL - MESQUITE i::-ij::~.:i::~:,:!:,::~.:.:.:.:.::::ij::~::.:::.:::,i:~ii::::::::J::j:
BOULDER CITY (no projects) $0 I $0 Hemenway Wash - 4th Suppl. $1 ,?