Hardscape: March 2 – March 6 - Fill sidewalk conduit with concrete March 9 – March 13 - Remove Pavers from fountain area. - Hand Grade Fountain paver area. - Relay Paver pattern. - Pour concrete edging for pavers. - Painting of neighborhood entry letters – letters to be painted black (Wednesday/Thursday) - Median sign Bowls (shipped from manufacturer, awaiting arrival), Install pending arrival Note: Tower construction plans are under review by Hillsborough County. Upon issuance of permit, tower construction will resume. Landscape & Irrigation: Week of March 16 - Front Entry landscape to begin. - Existing sod in front of North entry monument has been removed for St. Augustine placement. - Fountain area landscape to be completed pending completion of paver repair. Note: Irrigation repairs at new Publix entry to be completed pending installation of curbing.

Upload: others

Post on 25-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Note: Irrigation repairs at new Publix entry to be …...2020/03/11  · Note: Irrigation repairs at new Publix entry to be completed pending installation of curbing. Note: Phase 1

Hardscape: March 2 – March 6

- Fill sidewalk conduit with concrete March 9 – March 13

- Remove Pavers from fountain area. - Hand Grade Fountain paver area. - Relay Paver pattern. - Pour concrete edging for pavers. - Painting of neighborhood entry letters – letters to be painted black (Wednesday/Thursday) - Median sign Bowls (shipped from manufacturer, awaiting arrival), Install pending arrival

Note: Tower construction plans are under review by Hillsborough County. Upon issuance of permit, tower construction will resume.

Landscape & Irrigation: Week of March 16

- Front Entry landscape to begin. - Existing sod in front of North entry monument has been removed for St. Augustine placement. - Fountain area landscape to be completed pending completion of paver repair.

Note: Irrigation repairs at new Publix entry to be completed pending installation of curbing.

Page 2: Note: Irrigation repairs at new Publix entry to be …...2020/03/11  · Note: Irrigation repairs at new Publix entry to be completed pending installation of curbing. Note: Phase 1

Note: Phase 1 Landscape Installation Limit is to location shown on map below.

Note: Phase 2 Landscape Installation Limit is to location shown on map below.

Page 3: Note: Irrigation repairs at new Publix entry to be …...2020/03/11  · Note: Irrigation repairs at new Publix entry to be completed pending installation of curbing. Note: Phase 1

Note: Phase 3 Landscape Installation Limit is to location shown on map below.

Site Photos – 03-10-2020

Pavers at Fountain area are under construction.

Page 4: Note: Irrigation repairs at new Publix entry to be …...2020/03/11  · Note: Irrigation repairs at new Publix entry to be completed pending installation of curbing. Note: Phase 1

Sod in front of North monument has been removed.