northern burlington county regional school district board
TRANSCRIPT
Northern Burlington County
Regional School District
Board of Education Update
2018 Referendum Projects
August 16, 2021
Projects Status
Current Projects
•5086.3A – Phase 1 - Health and Training Center – 98% Complete
•5086.4 – Phase 2 - Main Addition (New construction)– Substantially Complete
•5086.4 – Phase 2 - Summer 2020 Renovations – Complete
•5086.5 – Phase 3 - 400/500 Connector – Substantially Complete
•5086.5 – Phase 3 – Summer 2021 Renovations – 60% Complete
•5086.6 – Phase 4 - HVAC Renovations – Complete
•5086.7 – Partial Reroofing –Substantially Complete
•5086.8 – Greenhouse – 80% Complete
•5086.9 – Parking Lot / Old Building Demo –
40% Complete
2
Projects Status
Current Projects
• Construction Progress Meetings are held every other Thursday morning and are held in
the new Media Center
• All personnel on site have been instructed to wear masks whenever in proximity to
District Staff
3
Project Summary
Project 5086.3A – Health and Training Center(Five Prime Contractors)
General Construction – Arthur Ogren
HVAC - Driscoll Mechanical
Structural Steel – Southern New Jersey Steel
Plumbing – Annese Mechanical
Electrical – QPI Electric
• Project is 98% complete – Waiting for wood doors and terrazzo
patching (currently underway)
• Interior renovations that are part of this contract are nearly
complete (Classroom renovations and restrooms)
4
Project Photo
Project 5086.3A – Health and Training Center
Exterior View from Baseball Field
5
Project Photo
Project 5086.3A – Health and Training Center
Inside View – Cleaning in Progress
6
Project Summary
Project 5086.4 – Main Connector Addition/Renovations(Five Prime Contractors)
General Construction – Arthur Ogren
Structural Steel – Southern New Jersey Steel
Plumbing – Annese Mechanical
HVAC – Preferred Mechanical
Electric – QPI Electric
• Project is Substantially Complete
• Remaining new construction work to be complete this month (Site, Roof
Metal, Millwork)
7
Project Summary
Project 5086.4 – Main Connector Additions
West Cafeteria Expansion Complete
8
Project Summary
Project 5086.4 – Main Connector Addition
West Cafeteria Expansion
9
Project Summary
Project 5086.4 – Main Connector Addition
West Cafeteria Expansion
10
Project Summary
Project 5086.4 – Main Connector Addition
West Kitchen Expansion
11
Project Photos
Front Entrance of Main Addition Final Metal Work
12
Project Photos
New Media Center
13
Project Photo
North Side of New Media Center
14
Project Photos
Loading Dock at Rear of Main Addition
15
Project Summary
Project 5086.5 – 400/500 Connector Addition(Five Prime Contractors)
General Construction – Arthur Ogren
Structural Steel – Mastercraft Iron
Plumbing – Three G’s Plumbing
Electric – QPI Electric
HVAC - Preferred Mechanical
• Addition is Substantially Complete with minor issues to address
16
Project Summary
Project 5086.5 – Phase 3 (400/500 Connector) Addition
View from West Parking Lot
17
Project Photo
Project 5086.5 – Phase 3 (400/500 Connector) Addition
Finished Choral Room
18
Project Photo
Project 5086.5 – Phase 3 (400/500 Connector) Addition
Early Childhood Development Room
19
Project Summary
Project 5086.5 – Phase 3 – Summer 2021 Renovations
• June 21, 2021 - Summer Renovation Work Began
• August 27, 2021 – Substantial Completion
Scope of Renovations
• Rooms 203, 205, 306, 307, and 308 are complete and have been
turned over to District
• New Guidance Offices have been turned over to the District
20
Project Summary
Project 5086.5 – Phase 3 – Summer 2021 Renovations
• Extensive renovations continue in 100, 200, 300 and 700 Corridor
Classrooms
• 600 Corridor Restrooms (new) are 80% Complete
• HVAC renovations continue in East Cafeteria, Art Room and 700
Classrooms
21
Project Scope
Project 5086.5 – Phase 3 – Summer 2021 Renovations
22
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
700 Wing Renovation
23
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
24
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
25
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
26
Room Turnover Schedule
Project 5086.5 – Phase 3 – Summer 2021 Renovations
27
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
600 Wing Restroom Tile (Old Faculty Room)
28
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
Old Media Center Conversion to Board Offices
29
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
New Air Handler Unit in 500 Building
30
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
Floor Trenches for Science Lab Utilities
31
Project Photo
Project 5086.5 – Phase 3 – Summer 2021 Renovations
New Casework in Room 203
32
Project Summary
Project 5086.6 – HVAC Renovations
HVAC - Preferred Mechanical
• Project is in close-out phase
• Systems are operating well
• Preferred Mechanical has responded quickly to a minimal number of issues
33
Project Summary
Project 5086.7 – Partial Roof Replacement
Contractor - Winchester Roofing
• Project is Substantially Complete
• Contractor has some punch list items to complete and is working with the
HVAC Contractor flashing curbs for new roof top units
34
Project Summary
Project 5086.8 – Greenhouse Project
Contractor – Aliano Brothers
• New Greenhouse is 80% - anticipated completion 9/1/2021
35
Project Summary
Project 5086.8 – Greenhouse Project
36
Project Summary
Project 5086.8 – Greenhouse Project
• Building concrete, masonry, framing and roofing are complete
• Exterior wall glazing is 85% complete
• Mechanical, Plumbing and Electrical rough-in are 50% complete
• Energy curtains are on site for installation
37
Project Summary
Project 5086.9 – Parking Lot and Demolition of Old
Buildings
• Underground gas, sanitary and water lines are complete
• Rainwater piping is being installed
• Concrete curbs are being formed and poured
• Final paving and finishes may be completed
After the start of school
38