NORTHEAST FRONTIER RAILWAY (Construction Organization)
RAIL CONNECTIVITY ENHANCEMENT IN NORTH EASTERN STATES
AGARTALA STATION BUILDING
Conversion of entire MG to BG in NE region.
To provide faster connectivity to NE by doubling of railway line from New Jalpaiguri to Lumding. Working out long term strategic requirements of railway network and lay a road map. Avenues for international connectivity particularly to Myanmar, Bangladesh and Nepal.
OTHER GOALS
SN State Capitals Project Target Date Commissioning
1 Arunachal Pradesh
Naharlagun
(Itanagar)
Harmuti -Naharlagun Commissioned
2 Tripura Agartala
LMG - SCL GC Commissioned
Kumarghat-Agartala
Commissioned
3 Manipur Imphal Jiribam - Imphal In Progress
4 Mizoram Aizawl Bhairabi - Sairang (Aizawl) In Progress
5 Nagaland Kohima Dimapur - Zubza (Kohima) In Progress
6 Meghalaya
Shillong
Tetelia - Byrnihat
In Progress
Byrnihat - Shillong In Progress*
7 Sikkim Gangtok (Rangpo)
Sivok - Rangpo In Progress**
BYNIHAT – SHILLONG
Progress of work affected due to obstructions from Khasi Student Union (KSU). NOC for land acquisition is not given so far by Khasi Hills Autonomous District Council (KHADC).
SEVOK - RANGPO Forest Clearance (WB) awaited from MoEF.
Rail Connectivity to Capitals of NE States
With more than 943 km of MG track converted into BG in last 4 years, there are no MG operation in entire NE region at present.
GAUGE CONVERSION
As on 31.3.16, Double line existed only on 166 km on busy section of New Jalpaiguri to Lumding Work on 469 km is in progress and planned for commissioning in phases. 47.89 km was commissioned in 2017-18.
DOUBLING
Plan Head New Line Gauge
Conversion
Doubling Total
Projects in progress (Nos.) 18 5 7 30
Total anticipated Cost (Crore) 64012 14771 10349 89132
Expenditure as on 31.3.2018 (Crore)
24011 14102 496 38609
Balance as on 1.04.2018 (Crore) 40000 668 9853 50521
Budget grant in 2016-17 (Crore)
4430 141 835 5406
National Projects (Nos.) 9 2 - 11
SUMMARY OF ON GOING PROJECTS IN N. E. REGION
Project Head
No.of projects
Total length
Already commissioned
(Nov’16)
Planning for commissioning up to 2020-21
2018-19 2019-20 2020-21
NL 18 1355.80 339.46 192.20 152.89 184.15
GC 5 2197.00 2197.00 - - -
DL 7 512.00 50.00 96.19 102.05 140.52
Total 30 4065 2587 288.39 254.89 324.67
SUMMARY OF ALL ON GOING PROJECTS IN N.E. REGION
0
1000
2000
3000
4000
5000
6000
7000
2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18
NL GC DL
Year NL GC DL Total
2011-12 1015.92 939.11 17.93 1972.96
2012-13 1854.00 617.82 0.82 2472.64
2013-14 1936.00 1635.00 42.14 3613.14
2014-15 2058.00 2089.00 0.96 4147.96
2015-16 3415.00 1487.00 5.58 4907.58
2016-17 4734.00 1118.00 134.28 5986.28
2017-18 3403.00 68.00 116.83 3587.83
Rs.
In C
rs.
EXPENDITURE ON N. E. REGION
(NEW LINES, GAUGE
CONVERSION & DOUBLING)
0
100
200
300
400
500
600
20
11
-12
20
12
-13
20
13
-14
20
14
-15
20
15
-16
20
16
-17
20
17
-18
NL GC DL
0 Km
Year NL GC DL Total
2011-12 58.92 100.58 9.76 68.68
2012-13 0.00 0 0 0
2013-14 0.00 154.66 0 287.24
2014-15 41.75 172.00 10.3 152.99
2015-16 132.05 398.47 8.12 366.47
2016-17 172.00 294.90 17.62 438.10
2017-18 48.14 0 47.87 95.01
COMMISSIONING IN LAST 7 YEARS IN N. E. REGION
19
2.2
9
15
2.8
4
18
4.1
5
96
.19
10
2.0
5 14
0.5
2
0
50
100
150
200
250
300
350
2018-19 2019-20 2020-21
NL GC DL
Km
YEAR NL GC DL TOTAL
2018-19 192.20 0 96.19 288.39
2019-20 152.84 0 102.05 254.89
2020-21 184.15 0 140.52 324.67
COMMISSIONING PLANNED IN NEXT 3
YEARS IN N.E. REGION
17
Plan Head Name of Project Length (Km) Year
NL Dudhnoi – Mendipathar 19.75
NL Harmuti-Naharlagun 21.75
NL Kumarghat - Agartala 109.00
NL Agartala- Santirbajar of Agartala-Sabroom 65.83
GC Rangapar- Harmuti 142.76
GC North Lakhimpur - Murkongselek 153.77
GC Lumding - Badarpur - Silchar and Finger Lines (Assam, Manipur & Tripura) (420.90 Km)
420.90
GC Katakhal – Bhairabi 84.0
MAJOR PROJECTS COMMISSIONED IN LAST 4 YEARS IN N.E. REGION
LAST 4 YEAR ACHIEVEMENTS OF N. F. RAILWAYS IN N. E. REGION
1. All states of NE Region except
Sikkim brought on BG network of Indian Railway.
2. State capitals of Arunachal Pradesh
and Tripura connected to BG.
3. Barak Valley of Assam connected to Major cities of the country
through BG connectivity.
4. Conversion of entire MG network to BG
in N E Region
LAST 4 YEAR ACHIEVEMENTS OF N. F. RAILWAYS IN N. E. REGION
5. Average annual commissioning of BG line in N E Region in last 4 years IS
3.2 times the average annual commissioning in previous
four years.
6. Average annual expenditure of last 4 years is 2.2 times
the average annual expenditure of previous four
years.
7. All the 41 Girders out of launched at Bogibeel
Bridge.
8. About 65 km of tunneling completed in Capital Connectivity /
Gauge Conversion Projects
KATAKHAL-BAIRABI GC PROJECT
FIRST PASSENGER TRAIN FROM SILCHAR TO BHAIRABI (Mizoram) FLAGGED OFF ON 27.5.16 FROM SHILLONG
KUMARGHAT – AGARTALA NEW LINE PROJECT
Ist BG TRAIN CONNECTING DELHI TO AGARTALA FLAGGED OFF ON 31.07.2016
RAIL CUM ROAD BOGIBEEL BRIDGE PROJECT
• Longest (4940 m) rail-cum-road bridge in India.
• All welded steel girders with no riveting, used for the first time in India and maintenance free with reduction in weight by about 20%.
• Designed by RITES India & Ramboll Denmark and proof checked by Anvikar, Germany.
JIRIBAM – TUPUL – IMPHAL NEW LINE PROJECT
N. F. railway is pioneer in tunneling with about 170 km tunneling against various sanctioned works in challenging geological conditions of NE region.
JIRIBAM – TUPUL – IMPHAL NEW LINE PROJECT
• Tunneling by State of Art NATM (New Austrian Tunneling Method) used world wide.
• Cost Effective for hard rock as well as soft rock tunneling.
• Flexible and Speedy Construction for all rock type.
JIRIBAM-IMPHAL NEW LINE PROJECT WORLD’S TALLEST RAIL BRIDGE PIER UNDER
CONSTRUCTION
Br. No. 164 with Pier height of 141m will be the tallest girder rail bridge in the World. (Existing tallest bridge is 139m high, Mala-Rijeka viaduct in Montenegro, Europe)
Montenegro Bridge (139m) Bridge No. 164 (141m )
AGARTALA - SABROOM NEW LINE PROJECT
Ground improvement in weak soil using Pre-fabricated Vertical Drain technique at Udaipur
WE ARE TRYING TO INCORPORATE LOCAL ART AND CULTURE IN OUR STATION
BUILDING DESIGN AND OTHER STRUCTURES.
DEPICTION OF LOCAL ARCHITECTURE & CULTURE
STRATEGIC LINES & STATUS OF FLS
S/NO LINE APPROX. LENGTH (KM) Approximate Cost
of FLS (Crs.)
1 Misamari (Bhalukpong) –Tenga-Tawang
378 (Arunachal Pradesh )
100.73
2 North Lakhimpur-Bame ( Along) –Silapathar
248
(32 Km in Assam & 216 Km in Arunachal Pradesh )
51.30
3 Pasighat-Tezu- Parsuramkund- Rupai
227 (26 Km in Assam & 201 Km in Arunachal
Pradesh) 35.11
Total 3 Strategic lines are proposed in NF Railway.
STRATEGIC LINES & STATUS OF FLS
Misamari (Bhalukpong) Tenga-Tawang:
- Through very difficult hilly terrain
- Initial investigations completed and TOR finalised
- Detailed field investigations in progress.
North Lakhimpur-Bame ( Along) –Silapathar:
- Through very difficult hilly terrain
- Initial investigations completed and TOR finalised.
- Agency under finalisation for detailed field investigations.
C. Pasighat-Tezu- Parsuramkund- Rupai : Project is relatively in easier terrain. Deatiled field survey is in progress. TDC - Dec’18
Present Status
STRATEGIC LINES & STATUS OF FLS
Cost of these surveys is being borne by Ministry of defence. Rs 47.18 Cr has been received from
MOD in August 2016
Regular coordination meetings are held with Eastern Command to
incorporate the defence requirements. Eastern Command
has already nominated co-ordinating officers for each of the
Survey.
Government of Arunachal Pradesh has also nominated the coordinating officer for the survey. The state Government has been requested vide letter dated 26-09-
2016 to advise their requirement.
TYPE Ongoing Surveys
Targets
2018-19 2019-20
New Line RET 12 11 1
PET - - -
FLS 5 4 1
Doubling/ 3rd Line
RET - - -
PET 6 6 -
FLS - - -
Quadrupling FLS 1 - 1
Total 24 21 3
SUMMARY OF ONGOING SURVEYS
2 FLS for doubling and 7 RECT/PET survey for new lines were completed in 2017-18 and reports submitted to Board.
CONNECTIVITY WITH BANGLADESH
i) Sealdah and Dhaka through Gede
Rail connectivity with Bangladesh exists through-
ii) Old Malda and Rohanpur through Singhabad.
iii) Radhikapur and Birol - restoration completed
Additional connectivity is in progress –
i) New line from Agartala to Akhaura ( 15 km ) sanctioned.
ii) Restoration of Haldibari to Chilati in progress
CONNECTIVITY WITH BHUTAN
Kokrajhar (Assam) to Gelephu (Bhutan)-57.70 Km.
Currently no rail link with Bhutan.
Feasibility studies have been carried out for extending Rail Head to Bhutan at 5 locations-
Pathsala (Assam) to Nanglam (Bhutan)-51.15 Km
Rangiya (Assam) to Samdrupjongkhar (Bhutan)-48.04 Km
Banarhat (West Bengal) to Samtse (Bhutan) – 23.15 km
Hasimara (West Bengal) to Phuentsholing (Bhutan) -17.52 Km
5.45 Km falls in Indian Portion & 13.15 Km falls in Nepal
Estimated Cost - Rs. 373.81 Crs. (2016)
Work entrusted to IRCON. Work is in progress. Land acquisition in Indian portion completed
Land acquisition held up in Nepal
Target -Mar’ 2018 ( subject to availability of land in
Nepal).
Jogbani and Biratnagar (18.60 km)-
CONNECTIVITY WITH NEPAL
TRANS ASIAN RAILWAY
Agreement signed on 29 June 2007 and ratified by the President on 13 sept 2007.
Agreement came in to fore on 11 June 2009 – 22 countries signed.
Southern Corridor – Kunming in China to Kapikule in Bulgaria (11462 km) – Passess through China, Thailand, Myanmar, Bangladesh, India, Pakistan, Iran and Turkey
On Eastern side, TAR link enters India at Tamu ( Myanmar) – Moreh (India) and again enters Bangladesh Shabazpur – Gede (India point)
On western side, it enters Pakistan at Attari (India) – Wagah (Pakistan)
MISSING LINKS IN TAR
In India - Missing Link is
Jiribam - Imphal – Moreh-Tamu (Myanmar)
- Jiribam to Imphal new railway line (110 km) work is in
progress .
- Railway has undertaken RECT survey for new BG line from Imphal to
More (111 km). Anticipated cost is Rs 5378 crore.
On Myanmar side -Missing Link is
- Tamu to Kale (135 km). Governments of India & Myanmar have
agreed to co-Operate for preparation of a DPR for establishing the
missing link.
- Further action after approval of MEA.
HINDRANCES
2. Poor road connectivity to work sites.
3 Hilly terrain , no approach road to work sites.
4. Longer monsoon periods, heavy rainfall. Working season limited to only 4-5 months.
5. Weak geology, frequent land slides, unstable hills.
6. Militancy, frequent kidnapping, threatening and demand for ransom.
1. Delay in acquisition of land
DIFFICULT APPROACH TO WORK SITES
Site survey for fixing alignment of tunnel - BAIRABI –SAIRANG NL PROJECT
JIRIBAM – TUPUL – IMPHAL SECTION
हम अपने रास्ते खुद बनाते हैं, मंजिल को अपने क़रीब लाते हैं;
काम मुश्किल है तो क्या हुआ, असम्भव को सम्भव कर जदखाते हैं
Making Service Roads: Any Slip – Fall of 2000 Feet
DELAY IN LAND ACQUISITION(FOREST LAND)
SN PROJECT
AREA IN HECTARE
STATE STATUS
1 Tetelia- Byrnihat
21.307 Ha. Forest Land
Assam i) “In principle approval” received from MoEF on 06.10.2016 with certain observations. Demand for additional compensation complied.
ii) All boundary pillars erected in consultation with Forest Department. Verification done.
iii). All necessary funds/amounts deposited.
Iv) Observations of MoEF complied on 22.11.2016 and final clearance awaited.
DELAY IN LAND ACQUISITION(FOREST LAND)
SN PROJECT AREA IN HECTARE
STATE STATUS
2
Sivok-Rangpo
98.50Ha (Including 8.85 Ha. Mahananda Wild Life Sanctuary Forest Land)
West Bengal
(i) Forest land acquisition in Mahananda Wild life forest of about 8.85 Ha. in West Bengal : Supreme Court has granted NOC and clearance from MoEF is awaited.
(ii) Forest land acquisition in Kurseong (12.34 Ha), Kalimpong (48.83 Ha) and Darjeeling (18.60 Ha) Divisions in West Bengal :-
Ministry of Tribal Affairs (MOTA) has issued instructions, to form Sub divisional level and District level committees by Govt. of West Bengal to resolve the issue.
iii) Normal Forest Land in Sikkim:-
Forest land of 11.88 Ha. falling in Sikkim State has been handed over to N. F. Railway on 18.02.2016.
3
New Maynaguri-Jogighopa
29.855 Ha
Assam i) Proposal cleared by State Board of Wild Life, Assam on 19.09.2015. Clearance from National Board of Wild Life (NBWL), New Delhi is awaited.
ii) Joint survey verification of Forest Land boundary under Dhubri, Parvatjhora and Aie Valley Forest Divisions completed and report submitted to concern DFOs for approval of MoEF/Shillong.
DELAY IN LAND ACQUISITION(PATTA LAND)
SN PROJECT AREA IN HECTARE
STATE STATUS
4 New BG line from Byrnihat to Shillong (108 Km) (National Project)
626 Meghalaya i) Land Plan of 182.386 hectares from 0.00km to 17.14 Kms has been submitted to DC/Ri-bhoi on 16.07.2015 after joint survey with Horticulture, PWD & Forest Departments of State Govt.
ii) There is opposition from Khasi Students Union/Local people. Regular meeting are being conducted with State Govt. officials to sort out security and other issues.
iii) Land acquisition process is held up for non-issuance of NOC by Khasi Hills Autonomous District Council (KHADC).
iv) However matter is being regularly chased /pursued with State authorities and KHADC. Last meeting held by Additional Chief Secretary Meghalaya on 02-09-2016 .
DELAY IN LAND ACQUISITION(PATTA LAND)
SN PROJECT AREA IN HECTARE
STATE STATUS
5 New BG line from Dimapur (Dhansiri)- Kohima ( Zubza)(90 Km) (National Project)
10.50 Assam &
Nagaland
1. Abnormally high land rates given by Karbi Anglong Autonomous Council (KAAC) (Rs. 150/- per Sq ft) have been disagreed by the Railways. Issue is pending for the past six months.
2. Further KAAC informed on 18.11.2016 that the basic rate of land decided at Rs. 75/- per sqft is reasonable. Matter has been brought to the notice of Chief Secretary, Govt. of Assam and further being referred to Railway Board for PMO’s intervention in the matter.
3. The adjacent land in Nagaland across river Dhansiri has
already been made available to this project @ Rs.25 per sq.ft. In fact, highest land rate paid in Nagaland is Rs 60/- per sq. ft, to be increased by 15% for compulsory nature of acquisition
SN
Name Year/ Cost
State Prog Remarks
1 Sibsagar-Jorhat (62 km)
16-17/ 77.50
Assam 80% DE costing Rs.2696 Cr. under finance
vetting from 12.03.18
TDC : Aug 18
2 Tezpur-Silghat (27 km )
16-17/ 31.25
Assam 80% DE costing Rs.2794 Cr. is under finance
vetting from 02.02.18.
TDC : Aug 18
3 Salona-Khumtai (99 km)
16-17/ 123.75
Assam 60% Field survey in progress. Issue of
reserve forest. S&T Estimate recd.
TDC : Oct 18
4 New Jalpaiguri –
Kakrabita (Nepal)
(46Km)
17-18/
57.5
W.B & Nepal 70% Survey complete. Alignment finalized.
Report being prepared
TDC : Aug 18
5 Dimapur - Tizit
(257 km)
16-17/
257
Nagaland 25% LOA issued on 08.12.17. Work started.
TDC : Dec 19
FLS FOR NEW BG LINES
SN
Name Year/ Cost
State Prog. Remarks
Doubling of Saraighat Bridge (7 km)
16-17/ 8.75
Assam 80% Estimate of Rs.1133.40 Cr. DPR
submitted to Board on 26.03.18.
Bongaigaon-Kamakhya via Rangia
(172 km)
16-17/
172.00
Assam 100% DPR submitted to Board on 18.3.17.
Cost 2498.6 Cr. Ruling Gradient 1 in
150
1 Kamakhya-N Guwahati Quadrupling (10.3 km )
16-17/ 12.88
Assam 10% Agency under finalization
TDC : 14 month after award of tender.
FLS FOR DOUBLING/3RD LINES
SN
Name Year/ Cost
State Prog. Remarks
Harmuti - Majuli (Bihpuria)
(38 km) (RETS)
17-18/ 9.50
Assam 100% Report submitted-Jan18
Length – 44.99 km
Est. cost - 2368.51 Cr. ROR – (-) 7.07%
Moirabari - Jagiroad (50 km) (RETS)
16-17/ 7.50
Assam 100% Report submitted-Jan18
Length – 46.28 km
Est. cost - 1093.73 Cr. ROR – (-) 0.90%
Tetelia - Moirabari (Komapur, Boha, Manaha, Barangbari, Bhurbanda, Charaibahi, Mikirbheta, Patekibori)
(80 km) (RETS)
16-17/ 12.00
Assam 100% Report submitted-Jan18
Length – 70.05 km
Est. cost - 1771.60 Cr. ROR – (-) 3.12%
Bongaigaon-Agthori (Barpeta, Hazo, Sarthebari)
(130 km ) (RETS)
16-17/ 19.50
Assam 100% Report submitted-Jan18
Length – 135.60 km
Est. cost - 3336.19 Cr. ROR – (-)
8.18%
1 Rangia – Dekargaon (Benzera, Sipajhar,
Mangaldoi, Kharupetia,
Dalgaon, Orang)
(140 km) (RETS)
16-17/
21.00
Assam 35% LOA issued on 14.01.18. Work started.
TDC : June 18
RETS/PETS FOR NEW BG LINES
SN
Name Year/ Cost (Lakhs)
State Prog. Remarks
2 Gogamukg-Jorhat (Kamlabari, Garmur)
(100 km) (RET)
17-18/ 25.00
Assam 70% Work started after 7 days notice.
Alignment finalized. Report being
prepared
TDC : May’18
3 Lekhapani – Deban (Nampong, New Khamlang)
(75 km ) (RETS)
16-17/ 11.25
Assam &
AP
50% Work in progress.
TDC : June’18
Lekhapani - Kharsang
(25 km) (RETS)
16-17/
3.75
Assam &
AP
100% Report submitted-Jan18
Length – 26.22 km
Est. cost - 993.46 Cr. ROR – (-)
3.51%
Margherita-Deomali
(31 km) (RETS)
16-17/
4.65
Assam &
AP
100% Report submitted-Jan18
Length – 25.97 km
Est. cost - 999.366 Cr. ROR – (-)
7.97%
4 Dumduma - Wakro (Simalguri, Namsai)
(96 km) (RETS)
16-17/
14.40
Assam &
AP
30% LOA issued on 24.11.17. Work in
progress.
TDC: Dec’18
RETS/PETS FOR NEW BG LINES
SN
Name Year/ Cost
State Prog. Remarks
5 Dangri - Roing (60 km) (RETS)
16-17/ 9.00
Assam & AP 40% LOA issued on 24.11.17. Work in
progress.
TDC: Dec’18
6 Tinsukia – Pasighat (Kanubari, Lekhapani, Jairampur, Kharsang, Miao, Tezu, Roing)
(300 km) (RETS)
16-17/ 45.00
Assam & AP 30% LOA issued on 24.11.17. Work to start.
TDC: Dec’18
7 Dhalaibeel - Itakhola - Seijosa (18 km) (RETS)
16-17/ 2.70
Assam & AP 80% Report received, pending for electrical
estimate. Being compiled
TDC : Aug’18
8 Naharkatia - Deomali (20 km) (RETS)
16-17/ 3.00
Assam & AP 70% Alignment finalized, report being
prepared.
TDC : May’18
Dhubri-Mendipathar (Double line bridge over Brahmaputra)
(120 km) (PETS)
15-16/ 46.80
Assam &
Meghalaya
100% Report submitted-Jan18
Length – 79.19 km
Est. cost - 7112 Cr.
ROR – (-) 8.45%
RETS/PETS FOR NEW BG LINES
SN
Name Year/ Cost
State Prog. Remarks
9 Chapermukh-Jowai (Dalimbari, Bhokchang, Rajagaon, Baithalangso, Dongkamukan, Jengkha, Kheroni & Umrangso) (180 km) (RETS)
16-17/ 54.00
Assam &
Meghalay
a
60% LOA issued on 26.09.17
Alignment under finalization.
Work in progress.
TDC : June’18
10 Pencharthal - Dharmanagar (Kailashahar)
(45 km) (RETS)
16-17/ 6.70
Tripura 60% Work in progress. Alignment under
finalization.
TDC : Oct’18
11 Ext. of Dharmanagar-Pencharthal up to Belonia (Khowai, AGTL)
(170 km ) (RETS)
17-18/ 42.50
Tripura 30% LOA issued on 03.11.17. Work in
progress.
TDC : Dec’ 19
12 Chittagong-Belonia
(125 km) (RETS)
12-13/
18.30
Tripura/
Banglades
h
20% Ref. made for TOR and arranging
permission to cross boarder.
RETS/PETS FOR NEW BG LINES
SN
Name Year/ Cost
State Prog. Remarks
1 Lumding-Dibrugarh (Doubling)
(380 km)
16-17/
133.77
Assam 50% LOA issued on 12.07.17. Work in progress.
TDC : Dec’ 18
2 Katihar-Mukaria (Doubling)
(39 km)
17-18/ 19.50
Bihar 80% Report received. Finance observations on
staff qtrs. are being complied
TDC : June’ 18
3 Siliguri-NJP
(Doubling)
(8 km )
17-18/ 4.00
WB 60% Survey in progress
TDC : Aug’18
4 Radhikapur-Barsoi (Doubling)
(52 km)
16-17/ 20.28
WB
Bihar
50% Survey in progress. TDC : Feb’19
5 Malda-Kumedpur-Barsoi (3rd Line)
(56 km)
17-18/ 2.39
WB &
Bihar
50% Survey in progress
TDC – Aug’18
6 Barsoi - NJP (3rd Line)
(145 km)
17-18/ 72.50
WB &
Bihar
50% Survey in progress
TDC – Aug 18
PETS FOR DOUBLING/3RD LINES