NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
0- (0-) FACILITATING WORKS
0A- (0.2) Site Clearance
AItem 0.00
B
Item 0.00
0A-T Total To Elemental Summary 0.00
1- (1-) SUBSTRUCTURE
1A- (1.1) Standard Foundations
C m 0.00
D m 0.00
E m 0.00
F Pad foundations generally Nr 0.00
GItem 0.00
Any other item in connection with
foundations the Contractor wishes
to price - please insert
1A-T Total To Elemental Summary 0.00
Strip foundations; 600 wide
Strip foundations; 450 wide
Extra; removal of obstructions and
contaminated material off site
Excavate, remove surplus excavation;
earthwork support; concrete, formwork and
reinforcement; all as Engineer's Drawing
15409/300
Strip foundations; 750 wide
General site clearance; removing debris,
shrubs bushes and vegetation generally
Removing topsoil; storing on adjacent site in
spoil heaps; location & placing to be agreed
with the Employer
Contract Sum Analysis Page 1
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
1C- (1.2) Lowest Floor Construction
A
m3 0.00
B
m2 0.00
CItem 0.00
D Item 0.00
Any other item in connection with
slab works the Contractor wishes to
price - please insert
1C-T Total To Elemental Summary 0.00
Reinforced concrete floor slab complete;
granular base; damp proof course;
reinforcement; formwork; surface finish;
joints
Excavate, remove surplus excavation;
earthwork support; concrete, formwork and
reinforcement; all as Engineer's Drawing
15409/301 (screed & insulation included
within finishes)
Extra; removal of obstructions and
contaminated material off site
Excavate to reduce levels; storing on
adjacent site in spoil heaps; location &
method to be agreed with the Employer
Extra; forming floor gulley to showers
Contract Sum Analysis Page 2
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
2- (2-) SUPERSTRUCTURE
2A- (2.1) Frame
A columns t 0.00
B beams t 0.00
C
t 0.00
D fittings/fixings and the like t 0.00
E m2 0.00
Fm2 0.00
GItem 0.00
H JJI 300C engineered timber joists m 0.00
J JJI 300D engineered timber joists m 0.00
KFixing noggins at 1000 centres as
roof bearers m2 0.00
L 12 plywood decking m2 0.00
M Item 0.00
Any other item in connection with
structural works the Contractor
wishes to price - please insert
2A-T Total To Elemental Summary 0.00
Sundry fixings straps infill pieces etc
protection to steel frame; exposed
protection to steel frame; hidden; 2 costs
asphaltic compound
Structural steelwork generally; as Engineer's
Drawing 15409/302, 303 & 304
hollow section, angle and channel section;
secondary steelwork, wind posts etc
Structural timbers generally; as Engineer's
Drawing 15409/302, 303 & 304
structural timbers generally; wall plates,
fixing noggins, cantilever frames etc
Contract Sum Analysis Page 3
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
2B- (2.2) Upper Floors
A Not applicable 0 m2 0.00 0.00
2B-T Total To Elemental Summary 0.00
2C- (2.3) Roof
B
m2 0.00
C Edge/junction detail; eaves m 0.00
D Edge/junction detail; abutment m 0.00
E Edge/junction detail; gable m 0.00
Fm 0.00
G
m 0.00
Any other item in connection with
roof finishes the Contractor wishes
to price - please insert
2C-T Total To Elemental Summary 0.00
2D- (2.4) Stairs and Ramps
L Not applicable 0 m2 0.00 0.00
2D-T Total To Elemental Summary 0.00
Rainwater installations; gutters; fittings and
fixings; as specification R10.311
Roof finish, stucco embossed aluminium
standing seam roofing system complete; as
specification H31.110; insulation
Rainwater installations; pipes, flush joint
aluminium; fittings and fixings; as
specification R10.370
Contract Sum Analysis Page 4
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
2E- (2.5) External Walls
A
m 0.00
B
m2 0.00
C
m2 0.00
D
m2 0.00
E Blockwork inner lining to cladding m2 0.00
FItem 0.00
G
m2 0.00
Masonry walls; external leaf; plain insitu
concrete cavity fill; insulation; inner leaf; to
damp proof course level
Masonry walls; facings as specification
F10.110; insulation as specification
P10.240; 200 blockwork inner leaf complete
as specification F10.260; above damp proof
course; inclusive of works to openings;
lintels as Engineer's Drawing 15409/302;
cills, jambs; damp proof courses, cavity
closer & insulation
Cedar cladding; insulation and structural
support; flashings, trims and the like; as
specification K13.110
Masonry walls; facings as specification
F10.110; in attached piers to front elevation
Masonry support generally; Ancon MDCR as
Engineer's Drawing 15409/302
Masonry walls; facings as specification
F10.110; insulation as specification
P10.240; 140 blockwork inner leaf complete
as specification F10.260; above damp proof
course; inclusive of works to openings;
lintels as Engineer's Drawing 15409/302;
cills, jambs; damp proof courses, cavity
closer & insulation
Contract Sum Analysis Page 5
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
(2.5) External Walls (Continued)
A generally; varying widths m2 0.00
B
Item 0.00
Any other item in connection with
external walls the Contractor wishes
to price - please insert
2E-T Total To Elemental Summary 0.00
PPC aluminium portico as door
surround; 3 thick; supports; flashings;
secret fixings; as specification H31.120
Soffit Cladding as Drawing 8201; soffits
complete; suspension system; board; trims
and flashings; battens; as specification
M20.100
Contract Sum Analysis Page 6
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
2F- (2.6) Windows & External Doors
A GFEX - W01, - 08 Nr 0.00
B GFEX - W09 -14 Nr 0.00
C Nr 0.00
D Extra; double doors; GFEX D03 Nr 0.00
E Nr0.00
F Nr 0.00
G Nr 0.00
H
Nr 0.00
Jm 0.00
K Blinds; as specification N10.230 Item 0.00
Any other item in connection with
windows and external doors the
Contractor wishes to price - please
insert
2F-T Total To Elemental Summary 0.00
Windows, louvres and doors; frames,
glazing; ironmongery; sealing at perimeter;
As Architect's Drawing SH-A-0001 and
specification L10.160
Window board; as specification P20.202;
decorations
External door; single doors to rear entrance;
GFEX 04; as specification L20.500
Glazing at high level; 4510 wide; CW-03
Glazing to rear elevation; 4510 wide; CW-01
& 02
Extra; double doors; GFEX D01 & D02
Glazing to front elevation; 3217 wide
Contract Sum Analysis Page 7
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
2G- (2.7) Internal Walls & Partitions
Blockwork; as specifications F10.250 & 260
A Blockwork; 100 thick m2 0.00
B m2 0.00
C m2 0.00
D Blockwork; 140 thickm2 0.00
E m2 0.00
F m2 0.00
GExtra; lintels as Engineer's
drawings 15409/302Item 0.00
H Movement joints Item 0.00
J
m2 0.00
K
m2 0.00
L
m2 0.00
Mm2 0.00
2G-T Total To Elemental Summary 0.00
Blockwork; 140 thick; fair faced one side
Blockwork; 140 thick; fair faced both sides
Blockwork; 100 thick; fair faced both sides
Blockwork; 100 thick; fair faced one side
Any other item in connection with internal
walls the Contractor wishes to price - please
insert
Partitions; wall type 2; as specification
K10.127B; plaster skim as specification
K10.681A
Internal walls; as Architect's Drawing 6301; all trims
fixings and the like
Partitions; IPS panelling; as specification
K32.150
Partitions; wall type 1; as specification
K10.127A; skim coat plaster as specification
K10.681A
Partitions; wall type 3; as specification
K10.156A; plaster skim as specification
K10.681A
Contract Sum Analysis Page 8
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
2H- (2.8) Internal Doors
A GFINT-D001 Nr 0.00
B GFINT-D002 Nr 0.00
C GFINT-D003 Nr 0.00
D GFINT-D004 Nr 0.00
E GFINT-D005 Nr 0.00
F GFINT-D006 Nr 0.00
G GFINT-D007 Nr 0.00
H GFINT-D008 Nr 0.00
J GFINT-D009Nr 0.00
K GFINT-D010Nr 0.00
L GFINT-D011Nr 0.00
M GFINT-D012Nr 0.00
N GFINT-D013Nr 0.00
P GFINT-D014Nr 0.00
Q GFINT-D015Nr 0.00
R GFINT-D016Nr 0.00
S GFINT-D017Nr 0.00
T GFINT-D018Nr 0.00
U GFINT-D019Nr 0.00
V GFINT-D020Nr 0.00
W GFINT-D021Nr 0.00
X GFINT-D022Nr 0.00
Y
Nr 0.00
ZRoller shutter doors to kitchen; as
specification L20.310 Nr 0.00
Doors; frames and architraves, glazing;
ironmongery; as Drawing SH-A-00002; as
specifications L20.430 & L10.150
Sliding folding partitions; to club room;
incorporating single pass door; GFINT-
D023; as specification L20.540
Contract Sum Analysis Page 9
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
(2.8) Internal Doors (Continued)
A GFINT - W25; 910 x 2260 Nr 0.00
B Decorations to doors generally Item 0.00
Any other item in connection with
internal doors the Contractor wishes
to price - please insert
2H-T Total To Elemental Summary 0.00
Windows, louvres and doors; frames,
glazing; ironmongery; sealing at perimeter;
As Architect's Drawing SH-A-0001
Contract Sum Analysis Page 10
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
3- (3-) FINISHINGS
3A- (3.1) Wall Finishes
Am2 0.00
BDecorations to walls; emulsion paint
as specification M60.110 m2 0.00
CDecorations to walls; mopuld
resistant paint as specification
M60.115m2 0.00
D
m2 0.00
Em2 0.00
Any other item in connection with
wall finishes the Contractor wishes
to price - please insert
3A-T Total To Elemental Summary 0.00
Whiterock; as specification N11.420; in
splash backs to kitchen
Two coat plaster work to walls; to blockwork
base; as specification K10.220
Ceramic wall tiles; fixing with adhesive;
grouting and trims as required; showers; as
specification M40.113
Wall finishes as Drawing 8601; complete;
trims, beading
Contract Sum Analysis Page 11
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
3B- (3.2) Floor Finishes
Am2 0.00
Bm2 0.00
Cm2 0.00
Dm2 0.00
E Carpet; as specification M50.130 m2 0.00
F Carpet; as specification M50.140 m2 0.00
G m2 0.00
H m2 0.00
J m2 0.00
K Tile skirtings generally m 0.00
Lm2 0.00
M m2 0.00
N m2 0.00
P m2 0.00
Qm 0.00
3B-T Total To Elemental Summary 0.00
Any other item in connection with floor
finishes the Contractor wishes to price -
please insert
Timber skirtings generally; 75 x 15, as
specification P20.200; decoration
Screed 115 thick; to insulation base;
generally; as specification M10.130
Insulation, 115 thick to ground floor slab;
generally; as specification P10.230
Entrance barrier; external; as specification
M50.170
Floor finishes as Drawing 8401; levelling
screed, trims and accessories as required
Insulation, 115 thick to ground floor slab; in
connection with under floor heating
Screed 115 thick; to insulation base; in
connection with under floor heating
Entrance barrier; internal; as specification
M50.160
Timber flooring; as specification K21.111
Ceramic Tile; as specification M40.110
Ceramic Tile; as specification M40.111
Ceramic Tile; as specification M40.112
Linoleum; as specification M50.150
Contract Sum Analysis Page 12
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
3C- (3.3) Ceiling Finishes
Am2 0.00
Bm2 0.00
Cm2 0.00
Dm2 0.00
Em2 0.00
F Item 0.00
Gm2 0.00
Hm2 0.00
Any other item in connection with
ceiling finishes the Contractor
wishes to price - please insert
3C-T Total To Elemental Summary 0.00
Extra; access, bulkheads, fire barriers
Ceiling finishes as Drawing 8201; ceilings
complete; suspension system; board; trims
battens
Moisture resistant plasterboard Type 2;
flat; as specification 226B
Moisture resistant plasterboard Type 5;
sloping; as specification K13.226E
Standard plasterboard; Type 3; sloping; as
specification K13.226C
Standard plasterboard; Type 4; sloping; as
specification K13.226D
Standard plasterboard; Type 1; flat; as
spoecification K13.226A
Moisture resistant paint to ceilings as
specification M60,115
Emulsion paint to ceilings as specification
M60,110
Contract Sum Analysis Page 13
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
4-
4A- (4.1) Fittings
A Item 0.00
B Item 0.00
CItem 0.00
DNr 0.00
ENr 0.00
FNr 0.00
GNr 0.00
H Mirrors; as specification N10.240 Nr 0.00
J Mirrors; as specification N10.250 Nr 0.00
K base units Nr 0.00
L wall units Nr 0.00
M worktops Nr 0.00
N custom made units Nr 0.00
P oven Nr 0.00
Q Signage - internal Item 0.00
R Signage -external Item 0.00
Signage generally; as specification N14
Kitchen units; as specification N11; battens,
bearers, fixings generally; sealant
Storage units: as specification N10.120
Notice boards; as specification N10.195
Spur shelving to cleaners; as specification
N10.160
Benches to changing rooms; as specification
N10.170
(4-) FITTINGS, FURNISHINGS &
EQUIPMENT
Coat hooks to changing rooms; as
specification N10.210
Baby change unit; as specification N10.220
Lockers to changing rooms; as specification
N10.200
Contract Sum Analysis Page 14
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
(4.1) Fittings (Continued)
A generally Item 0.00
B signage; as Drawing Nr 06302 Item 0.00
Any other item in connection with
fittings the Contractor wishes to
price - please insert
4A-T Total To Elemental Summary 0.00
Fire fighting equipment; as specification
N17; pattresess, fixings and the like
Contract Sum Analysis Page 15
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
5- (5-) SERVICES
5A- (5.1) Sanitary Installations
ANr 0.00
B Wc's; as specification N13.300 Nr 0.00
CNr 0.00
DNr 0.00
ENr 0.00
FNr 0.00
GNr 0.00
HNr 0.00
JNr 0.00
KNr 0.00
LNr 0.00
M Nr 0.00
PNr 0.00
5A-T Total To Elemental Summary 0.00
Cleaner's sink; taps; as specification
N13.330
Any other item in connection with sanitary
fittings the Contractor wishes to price -
please insert
Wash hand basin; taps; as specification
N13.310
Disabled wc area; as specification N13.320
Sanitary towel dispensers; as specification
N13.370
Soap dispensers; as specification N13.380
Disabled shower area; as specification
N13.340
Sink & single drainer as specification
N11.340
Toilet brush holders; as specification
N13.385
Waste bins; as specification N13.390
Showers to officials; as specification
N13.350
Showers to changing rooms; as specification
N13.350
Paper towel dispensers; as specification
N13.360
Contract Sum Analysis Page 16
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
5B- (5.2) Services Equipment
A Item 0.00
5B-T Total To Elemental Summary 0.00
5C- (5.3) Disposal Installations
BItem 0.00
5C-T Total To Elemental Summary 0.00
5D- (5.4) Water Installations
C Cold water installationsItem 0.00
D Hot water installationsItem 0.00
5D-T Total To Elemental Summary 0.00
5E- (5.5) Heat Source
E Boiler Item 0.00
5E-T Total To Elemental Summary 0.00
5F- (5.6) Space Heating & Air Conditioning
FItem 0.00
5F-T Total To Elemental Summary 0.00
5G- (5.7) Ventilation Systems
G Ventilation installations Item 0.00
5G-T Total To Elemental Summary 0.00
Plant room - mechanical installations
Disposal installations; soil waste and
overflow installations complete
Electrical heating complete (screed and
insulation included within floor finishes)
Contract Sum Analysis Page 17
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
5H- (5.8) Electrical Installations
A Item 0.00
BItem 0.00
C Power installations Item 0.00
DItem 0.00
E Lighting installations generally Item 0.00
F Emergency lighting installationsItem 0.00
G External lighting Item 0.00
H Earthing & bonding Item 0.00
5H-T Total To Elemental Summary 0.00
5I- (5.9) Fuel Installations
J Gas installations generally 0 Item 0.00
5I-T Total To Elemental Summary 0.00
5J- (5.10) Lift & Conveyor Installations
K Not applicable Item 0.00
5J-T Total To Elemental Summary 0.00
5K- (5.11) Fire & Lightning Protection
LFire and smoke alarm installations
Item 0.00
M Lightning protection Item 0.00
5K-T Total To Elemental Summary 0.00
Plant room - electrical installations
Mains installations, sub mains and
containment
Supplies in connection with mechanical
equipment
Contract Sum Analysis Page 18
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
5L-
A Data & telecoms installations Item 0.00
B Access control Item 0.00
C Security installations Item 0.00
D CCTV installations Item 0.00
E Control systems Item 0.00
5L-T Total To Elemental Summary 0.00
5M- (5.13) Others generally
FAny other items the contractor
wishes to insert; please list
5M-T Total To Elemental Summary 0.00
5N- (5.14) Builders Work In Connection
Gplumbing and mechanical
installations Item 0.00
H electrical installations Item 0.00
5N-T Total To Elemental Summary 0.00
(5.12) Communications, Security &
Control
Builders work in connection generally
Contract Sum Analysis Page 19
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
5O- (5.15) Sundry Associated Works
Design
Aplumbing and mechanical
installations Item 0.00
B electrical installations Item 0.00
Specific services preliminaries
Cplumbing and mechanical
installations Item 0.00
D electrical installations Item 0.00
Testing and commissioning
Eplumbing and mechanical
installations Item 0.00
F electrical installations Item 0.00
As built information; operating &
maintenance manuals, information
for SBEM & the like
Gplumbing and mechanical
installationsItem 0.00
H electrical installations Item 0.00
5O-T Total To Elemental Summary 0.00
Contract Sum Analysis Page 20
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
A Not applicable Item 0.00
Total To Elemental Summary 0.00
(7-) WORKS TO EXISTING BUILDINGS
(7.1 - 7.6) Works to Existing Buildings
B Not applicable Item 0.00
Total To Elemental Summary 0.00
6- (8-) EXTERNAL BUILDING WORKS
6A- (8.1) Site Preparation Works
CGeneral reduced level excavation
and store on site m3 -
6A-T Total To Elemental Summary 0.00
(6.1) Prefabricated Buildings & Building
Units
(6-) PREFABRICATED BUILDINGS &
BUILDING UNITS
Contract Sum Analysis Page 21
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
6B- (8.2) Roads, Paths, Pavings & Surfacing
Am2 0.00
Bm2 0.00
Cm2 0.00
Dm2 0.00
Em2 0.00
FExtra; removing unsuitable
excavated material from site m3 0.00
GPrecast concrete kerbs and
foundation; ref HB 2 m 0.00
HPrecast concrete kerbs and
foundation; flush kerb m 0.00
JPrecast concrete edgings and
foundation m 0.00
Any other item in connection with
external finishes the Contractor
wishes to price - please insert
6B-T Total To Elemental Summary 0.00
Excavate, remove surplus excavation and
place on adjacent site; earthwork support;
concrete, formwork and reinforcement; sub
base and pavings; all as Engineer's
Drawings 15409/230 & 235
Sett pavings as pedestrian crossover; as
specification Q25.100
Macadam car parking and roads, as
specification Q22.110
Macadam car parking and roads, as
specification Q22.100
Concrete pedestrian pavings; as
specification Q50.130
Natural stone pebble border; as
specification Q25.120
Contract Sum Analysis Page 22
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
6C- (8.3) Soft Landscaping, Planting
ATopsoil; stored on site; preparing for
seeding m2 0.00
B Grass seeding m2 0.00
C Soft planting Item 0.00
6C-T Total To Elemental Summary 0.00
6D- (8.4) Fencing Rails & Walls
D m 0.00
6D-T Total To Elemental Summary 0.00
(8.5) External Features
E Nr 0.00
F Nr 0.00
G Nr 0.00
H Nr 0.00
J Nr 0.00
K Nr 0.00
Total To Elemental Summary 0.00
Cycle stands; as specification Q50.210
Refuse/Mower store; as specification
Q50.215; base, surround
Entrance barrier; as specification Q50.110
Lamp post protector; as specification
Q50.130
Bollards; as specification Q50.120
External benching; as specification Q50.220
Boot cleaning station; as specification
Q50.220
Contract Sum Analysis Page 23
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
(8.6) External Drainage Within the Confines of the Site
Surface water; as Engineer's
Drawing 15409 240 & 260
A 100 pipe m 0.00
B 150 pipe m 0.00
C rainwater pipe connection Nr 0.00
D road gullies Nr 0.00
E rodding point Nr 0.00
F Nr 0.00
G Nr 0.00
H Nr 0.00
J Nr 0.00
Excavate trenches, earthwork support,
filling on completion removing surplus
excavated material, bed and surround,
pipe and fittings
Excavate , earthwork support, filling on
completion removing surplus excavated
material, concrete bed or foundation,
cover and frame
Mini PPIC chambers complete; maximum
depth not exceeding 600
PPIC chambers complete; depth 750 -
1000
PPIC chambers complete; depth 1000 -
1500
Manhole complete; 1200 diameter
chamber maximum depth 1300
Contract Sum Analysis Page 24
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
Foul water; as Engineer's
Drawing 15409 240 & 260
A 100 pipe m 0.00
B svp connection Nr 0.00
C gully to mower store Nr 0.00
Dinternal gully to plant room; as
specification R11.316Nr 0.00
Elinear floor gully to showers;
as specification R11.310m 0.00
F Nr 0.00
G Nr 0.00
H Nr 0.00
Generally
JTesting foul and surface water
drainageItem 0.00
Any other item in connection with
drainage the Contractor wishes to
price - please insert
Total To Elemental Summary 0.00
PPIC chambers complete; depth 750 -
1000
PPIC chambers complete; depth 1000 -
1250
Manhole complete; 1200 diameter
chamber maximum depth 1200
Excavate trenches, earthwork support,
filling on completion removing surplus
excavated material, bed and surround,
pipe and fittings
Excavate , earthwork support, filling on
completion removing surplus excavated
material, concrete bed or foundation,
cover and frame
Contract Sum Analysis Page 25
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
(8.7) External Drainage Outside the Confines of the Site
Surface water; as Engineer's
Drawing 15409 240 & 260
A 225 pipe m 0.00
B outfall Item 0.00
Foul water; as Engineer's
Drawing 15409 240 & 260
C m 0.00
D Nr 0.00
E Nr 0.00
F
Connection to existing manhole
within highway; approx depth to
invert 2500; inserting 150 pipe,
making good
Nr 0.00
Manhole complete; 1200 diameter
chamber maximum depth 2000; in existing
highway
Manhole complete; 1200 diameter
chamber maximum depth 1560; in existing
highway
Excavate trenches, earthwork support,
filling on completion removing surplus
excavated material, bed and surround,
pipe and fittings
Excavate , earthwork support, filling on
completion removing surplus excavated
material, concrete bed or foundation,
cover and frame
Excavate trenches, earthwork support,
filling on completion removing surplus
excavated material, bed and surround,
pipe and fittings; within existing
Excavate , earthwork support, filling on
completion removing surplus excavated
material, concrete bed or foundation,
cover and frame; within existing
highway
150 pipe; within existing highway
Contract Sum Analysis Page 26
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
Generally
ABreaking out existing drainage
pipes, manholes etcItem 0.00
maintaining flow of existing drains
where applicable
BMaking good highway on completion
to satisfaction of local authorityItem 0.00
C Testing and approvals Item 0.00
(8.8) External Services
Incoming services
C water Item 0.00
D electricity Item 0.00
E gas Item 0.00
F telecoms Item 0.00
G Trenches for incoming services Item 0.00
Total To Elemental Summary 0.00
(9-) DESIGN FEES
(9.1 - 9.3 ) Design fees
B
Consultant fees to complete the
design process and carry out all the
post contract works
Please identify each discipline
separately
Total To Elemental Summary 0.00
Contract Sum Analysis Page 27
NORTH HYKEHAM COMMUNITY HUB
2.2 CONTRACT SUM ANALYSIS
2.2.2 Elemental Detailed Costs
Description Qty Unit Rate Total
8- (10-) RISK
8A- (10.1- 10.4) General Risk
DGeneral contingency for all design
risks by the Contractor Item 0.00
Note; A separate contingency will
be held by the Employer for change
controls
8A-T Total To Elemental Summary 0.00
Contract Sum Analysis Page 28