north anna unit 3 hybrid cooling - eprimydocs.epri.com/docs/advancedcooling...epri workshop on...
TRANSCRIPT
PP640.1
North Anna Unit 3 Hybrid Cooling
John D. Waddill, P.E.Dominion Resources, Inc.
EPRI Workshop on Advanced Cooling Technologies
Acknowledgement: Douglas A. Kemp, P.E.
Bechtel Power Corporation
PP640.2
Why the North Anna Site?
SpaceEnvironmentallyacceptableNo superior alternativeOriginally planned for 4 units
PP640.3
PP640.4
Available Water Supply
Net Inflow
369 cfsPre-Operational Evaporation
93 cfs
Minimum Dam Release
40 cfsAvailable Water Supply
236 cfs
Unit 3 Water NeedsOnce Through System
28 cfs
Storage Volume: 25,400 acre-ft (250 ft to 248 ft, msl)
PP640.5
Overview of North Anna Project
ESP application submitted to NRC in 2003 –
2 units at 1520 MWe each
Unit 3 cooling system changed in 2005 from open to closed cycle due to agency and public concerns–
Thermal Discharge–
Lake level and downstream flow impacts
COL application submitted in Nov 2007ESP received in Nov 2007
PP640.6
Cooling Technologies Considered
Closed Cycle Conventional Cooling TowerThermal Issue: SolvedWater Use Issue: Potentially Worse
Combination Wet-Dry Cooling (Hybrid)Thermal Issue: SolvedWater Use Issue: Significantly Reduced
PP640.7
Available Cooling Technologies
*Data from filed ESP and COL Applications
0.00
5.00
10.00
15.00
1 2 3 4 5 6 7 8 9 10
GPM
/ G
ross
MW
Out
put
Reservoir Mechanical Draft Natural DraftNA3
PP640.8
Wet / Dry Cooling Concept – How does it work?
Closed cycle cooling system design
–
Dry Tower and water-conserving Hybrid Tower in series
–
Unit 3’s Circulating Water cooled initially in Dry Towers
–
Circulating Water then passed through Hybrid Towers•
Dry section of Hybrid tower cools incoming Circulating Water and provides warm air for limiting visible plume.
•
Wet section completes the heat rejection using evaporation
PP640.9
Wet / Dry Cooling Concept – How does it work?
Two conceptual operating modes
–
Energy Conservation (EC) –
Dry cooling will be reduced with reliance on hybrid tower for heat removal.
–
Water Conservation (WC) –
Minimum 1/3 heat removal by Dry Tower, balance of heat removal by Hybrid.
PP640.10
Conceptual Flow Path & Cycles
PP640.11
Projected Plant Consumptive Water Use
System Average Water Use (CFS)
28 27.4
19.4
8.4
05
1015202530
Closed CycleReservoir
Hybrid Tower Hybrid Tower& Dry Tower
(EC/WC)
Hybrid Tower& Dry Tower
(WC Only)
PP640.12
Hybrid Cooling
PP640.13
Hybrid Cooling
PP640.14
Look to the Future
PP640.15
Concept Design – How much dry cooling?
Land UseCostPower RequiredPotential impact on turbine performance
PP640.16
Concept Design – How much dry cooling?
Comparison of Dry Cooling Percentages
Percent Dry Cooling Capacity
Approx. Number of
Tower Cells Required
Percent increased land use
(over 33% design)
Approx. Dry Tower Cost, 2005 dollars
Approx. Electrical
Power Required,
MWe33 100 - 51M 15
67 240 350 137M 36
83 336 500 171M 50
PP640.17
Resulting Performance
Bad News –
The system performs best when normally not needed → Cool weather.
Approach temperature has significant impact on dry tower performance/duty.Resulting higher circulating water temperature has consequence of higher turbine backpressure → lower turbine efficiency → lower power output.Remedy?–
More tower cells–
Results in higher hotel loads, land use, cost
PP640.18
Resulting Performance Effect of Ambient Air Temperature on Dry Tower CWT
PP640.19
Resulting Performance
Good News –
When you really need it, the system can perform → Long droughts.
Projected annual average evaporation reduced by more than 30% using EC/WC operation.
Projected annual average evaporation reduced by 70% using WC only.
PP640.20
Resulting Performance
Percent Decrease (Increase) in Average Water Consumption Vs. Once Through Cooling Design
Energy Conservation
Only (EC)
Water Conservation
Only (WC)
Proposed Operating Plan –
EC and WC Dependent on Lake Level
Annual 2 70 30
Winter (9) 90 22
Spring 3 73 11
Summer 5 51 31
Fall 5 71 55Preliminary Data
PP640.21
Resulting Performance
Existing Units
Existing UnitsPlus
Unit 3 with Once Through Design
Existing UnitsPlus
Unit 3 with Hybrid Cooling
5.2% 11.6% 7.0%
Model Prediction for Time Below Lake Low Level Elevation
PP640.22
Lake Level Hydrograph
Open Cycle Cooling
PP640.23
Lake Level Hydrograph
Closed Cycle Cooling
PP640.24
Summary
The North Anna Unit 3 hybrid cooling system:Eliminates thermal impacts to the lakeSignificantly reduces water use from a once through or conventional wet cooling tower system.Minimizes impact on period of time lake is below low levelProvides a balance between environmental stewardship and cost (capital and lost revenue due to reduced plant efficiency/power production)
PP640.25
Questions?