non_compliance_notice2.pdf

2
 Date : 1. ISSUED TO 2. NCN NO:  Name of Contractor: INSTRUMENTATION INC. 2. DESCRIPTION OF NCN: 3. REFERENCE OF NCN See attached files.  NCN Issued by: Signature and Date: J.A.Aguilar/S.L.Sebuc 4. ACTION TAKEN ( PROPOSED CORRECTIVE MEASURE BY CONTRACTOR ) 5. APPROVAL OF CORRECTIVE MEASURES Remarks: 6. CQC TEAM REVIEW AND CLOSE OUT > OP-C-078-0  D.M Consunji, Inc. Re- Inspected by: Signature and Date: Designer / Consultant Operations a. b. Engineering c. CQC d. e. Owner 15 MW CALAPAN BUNKER FIRED POWER PLANT D.M. CONSUNJI, INC. NON COMPLIANCE NOTICE 05-Dec-14 The delivered level switches on site, esp. the devices with type: X5AA8 132R 04G1, X5AA8 132R 04G3, and X5AA8 141R 04G2E268 does not match the flange stub out of the tanks. Because of this, the subcontractor's work for the installation of level instruments on tanks were delayed and the reinstallation and fabrication/procurement of correct flanges will incur additional costs to DMCI.

Upload: jemersonaguilar

Post on 03-Nov-2015

6 views

Category:

Documents


0 download

TRANSCRIPT

  • Date :

    1. ISSUED TO 2. NCN NO:

    Name of Contractor: INSTRUMENTATION INC.

    2. DESCRIPTION OF NCN: 3. REFERENCE OF NCN

    See attached files.

    NCN Issued by: Signature and Date:

    J.A.Aguilar/S.L.Sebuc

    4. ACTION TAKEN ( PROPOSED CORRECTIVE MEASURE BY CONTRACTOR )

    5. APPROVAL OF CORRECTIVE MEASURES Remarks:

    6. CQC TEAM REVIEW AND CLOSE OUT

    >

    OP-C-078-0

    D.M Consunji, Inc.

    Re- Inspected by: Signature and Date:

    Designer /

    Consultant

    Operationsa.

    b. Engineering

    c. CQC

    d.

    e. Owner

    15 MW CALAPAN BUNKER FIRED POWER PLANT

    D.M. CONSUNJI, INC.

    NON COMPLIANCE NOTICE

    05-Dec-14

    The delivered level switches on site, esp. the devices

    with type: X5AA8 132R 04G1, X5AA8 132R 04G3,

    and X5AA8 141R 04G2E268 does not match the

    flange stub out of the tanks. Because of this, the

    subcontractor's work for the installation of level

    instruments on tanks were delayed and the

    reinstallation and fabrication/procurement of correct

    flanges will incur additional costs to DMCI.