no_14_tkd_interim_report_fo
DESCRIPTION
http://tk-development.com/Files/Billeder/Issuu/Interim%20reports/2006_07/No_14_TKD_Interim_report_for_the_first_six_months_2006.pdfTRANSCRIPT
Interim report for the first six months 2006/07
TK Development A/S
Announcement No. 14/2006
CVR 24256782
2/36 Interim report for the first six month 2006/07 for TK Development A/S
Contents
Summary 3
Company information 6
Consolidated financial highlights and key katios 7
Management’s review 8
First six months of the 2006/07 financial year 8
Outlook 18
Project portfolio 20
Project portfolio status 20
TKD Nordeuropa 22
Euro Mall Holding 26
TK Development, the Parent Company 28
Investment properties 29
Statement by the Executuve Board and Supervisory Board 30
Consolidated financial statements 31
Income statement 31
Balance sheet 32
Statement of changes in equity 34
Cash flow statement 35
Segment information 36
Interim report for the first six month 2006/07 for TK Development A/S 3/36
During the first six months of the 2006/07 financial year,
TK Development recorded a profit of DKK 2.5 million
after tax and minority interests against DKK -11.7 mil-
lion in the first half of 2005/06.
Management considers the performance for the period
to be acceptable.
Consolidated equity amounted to DKK 1,011.8 million
at 31 July 2006, corresponding to a solvency ratio of
22.9 % based on a balance sheet total of DKK 4,422.3
million at 31 July 2006.
The profit estimate for the 2006/07 financial year has
been revised upwards to about DKK 240 million after
tax and minority interests, compared to the previously
published profit forecast of DKK 200 million.
TKD Nordeuropa-continued strengthening of the project portfolio
During the first six months of the 2006/07 financial year,
TKD Nordeuropa recorded a profit of DKK 7.4 million after
tax. The profit after tax for the first half of 2005/06 amounted
to DKK 12.7 million. Management considers the perform-
ance for the period to be acceptable.
During the period under review, TKD Nordeuropa continued
to focus on improving the quality of its project portfolio and
also sold a number of projects developed and completed in
previous financial years. Further, TKD Nordeuropa developed,
sold and handed over a number of minor projects during the
period under review.
•
•
•
•
Project developments
Entré shopping centre, Malmö, Sweden
Since the balance sheet date, the project has been sold
to CGI – Commerz Grundbesitz Investmentgesellschaft
mbH on the basis of a rate of return of 6 %. The price is
expected to total about SEK 1.5 billion, and the sale is
based on forward funding.
Galerija Azur, Riga, Latvia
This is the Group’s first shopping centre project in the
Baltic States. Construction is completed, and the shop-
ping centre opened on 24 August 2006. The centre has
been sold to Meinl European Land Ltd., and all premises
have been fully let.
Euro Mall Holding-highly satisfactory performance
Euro Mall Holding continued the positive development from
the year before, realizing a profit after tax of DKK 110.6 mil-
lion in the first six months of 2006/07. The profit after tax for
the first half of 2005/06 amounted to DKK 114.7 million.
Management considers the performance for the period to be
highly satisfactory.
Euro Mall Holding’s earnings during the period were gener-
ated from fee income on sold development projects and sites.
In addition, continuing price increases in Central Europe gave
rise to a positive DKK 89.5 million revaluation of Euro Mall
Holding’s investment properties before tax and minority in-
terests.
Euro Mall Holding recorded satisfactory development in its
project portfolio during the period under review.
•
•
Summary
Summary
4/36 Interim report for the first six month 2006/07 for TK Development A/S
Project developments
Galeria Biala, Bialystok, Poland
This project is being developed in a joint venture with
Meinl European Land Ltd. Construction has been initi-
ated, and the shopping centre is expected to be com-
pleted in autumn 2007. The current occupancy rate is
about 80 %.
The Plejada shopping centre, Sosnowiec, Poland
Since the balance sheet date, this shopping centre has
been sold to a company owned by the UK property in-
vestment company St. Martins Property Corporation
Limited based on a rate of return for the investor of 6.75
%. In addition, TK Development is developing an ex-
tension to the centre, also sold to an investor at a 6.75 %
rate of return based on forward funding. Construction
start is scheduled for autumn 2006.
Targówek Retail Park, Warsaw, Poland
This project consists of a 24,100 m² retail park for which
a building permit has been obtained. The current occu-
pancy rate exceeds 75 %. A letter of intent for sale of the
project to an investor has been signed, based on forward
funding.
Prague Outlet Center, Prague, Czech Republic
This project consists of the development of a 25,000 m²
factory outlet centre. An agreement regarding the sale of
25 % of the project was made during the period under
review. A local plan has been obtained for the project.
•
•
•
•
Summary
TK Development, the Parent Company
The half-year results for this part of the Group total DKK
-115.5 million after tax and minority interests, of which DKK
-22.2 million is attributable to minority interests. Manage-
ment considers the performance for the period to be unsat-
isfactory.
During the period under review, the Group sold its project in
St. Petersburg, Russia.
Writedown of the receivable from the Field’s project
Management’s reassessment of the outstanding selling price
receivable resulted in a further writedown of DKK 110.0 mil-
lion before tax in the first half of 2006/07. This reassessment
may still be subject to uncertainty.
Revaluation of the Group’s German investment properties
During the period under review, the Group revalued its Ger-
man investment properties upwards by DKK 2.8 million be-
fore tax and minority interests.
Project developments
Słoneczne Centrum Handlowe, Szczecin, Poland
This 4,500 m² shopping centre has been sold to a UK
investor after the balance sheet date.
•
Interim report for the first six month 2006/07 for TK Development A/S 5/36
31 Jan. 05 31 Jan. 06 31 July 06Gross project portfolio (DKK m.) 2,843 2,862 3,077Forward funding (DKK m.) 191 638 981Carrying amount of project portfolio (DKK m.) 2,652 2,224 2,096
Development potential in ’000 m²:Projects sold (’000 m²) 242 289 270Other projects (’000 m²) 778 720 791Total project portfolio (’000 m²) 1,020 1,009 1,061
Number of projects 90 90 96
Summary
Project portfolio
The earnings potential of the Group’s Project portfolio re-
mains satisfactory high.
Senior Vice President charged by the Polish po-lice
In June 2006, the Senior Vice President in charge of the
Group’s Polish branch office was detained, taken into custody
and charged by the Polish police with irregularities related
to obtaining regulatory approval (zoning permission) for the
Polish Galeria Biala shopping centre project in Bialystok.
The charge has been upheld, and the Senior Vice President
continues to be detained.
Charges brought by the public prosecutor for serious economic crimes
In the autumn of 2005, TK Development A/S and six in-
dividuals were charged by the public prosecutor for serious
economic crimes with fraudulent income recognition and
price manipulation concerning periods covering the 2000/01,
2001/02, 2002/03 and 2003/04 financial years, and in June
2006 another 13 projects were added to the charge. Manage-
ment still considers that the charges are based on misconcep-
tions concerning the Group’s accounting policies.
The issues covered by the charge do not affect the Company’s
current financial position.
Outlook
The profit estimate for the 2006/07 financial year has been
revised upwards to about DKK 240 million after tax and mi-
nority interests, compared to the previously published profit
forecast of DKK 200 million.
The revised profit estimate is underpinned by the profit gen-
erated in the first half of 2006/07, the expected completion
during the second half of 2006/07 of a number of projects in
progress that have already been sold, and the ongoing nego-
tiations regarding the sale of some of the Group’s completed
projects.
TKD Nordeuropa still expects to report a profit after tax of
around DKK 120 million. For more details, please refer to
stock exchange announcement no. 7/2006 for TKD Nordeu-
ropa A/S, dated today.
This interim report is available on the TK Development
Group’s website, www.tk-development.dk.
Further information regarding the 2006/07 interim report is
available from Frede Clausen, President and CEO, tel. +45 88
96 10 10.
The most important elements related to the Group’s project portfolio are shown below.
6/36 Interim report for the first six month 2006/07 for TK Development A/S
Company information
TK Development A/SCVR 24256782
ISIN code 0010258995Municipality of registered office: Aalborg
www.tk-development.dke-mail: [email protected]
Tel: (+45) 8896 1010
Euro Mall Holding A/S
CVR 20114800
TKD Nordeuropa A/S
CVR 26681006
Supervisory board Poul LauritsenTorsten Erik RasmussenPer Søndergaard PedersenKurt DaellJesper Jarlbæk
Executive boardFrede Clausen
Robert Andersen
AalborgVestre Havnepromenade 7
DK-9000 AaborgTel: (+45) 8896 1010
KøbenhavnArne Jacobsens Allé 16, 3. t.v.
DK-2300 København STel: (+45) 3336 0170
Warszawaul. Mszczonowska 2
PL-02-337 WarszawaTel: (+48) 22 572 2910
PragKarolinská 650/1CZ-186 00 Prag 8
Tel: (+420 2) 8401 1010
BerlinAhornstraße 16D-14163 Berlin
Tel: (+49) 30 802 10 21
VilniusA. Gostauto 40
LT-01112 VilniusTel: (+370) 5231 2222
HelsinkiKorkeavuorenkatu 34FIN-00 130 HelsinkiTel: (+358) 9 2284 81
StockholmGamla Brogatan 36-38S-101 27 Stockholm
Tel: (+46) 8 751 37 30
RigaLacplesa 20a
LV-1010 RigaTel: (+371) 7 821 811
100 %80 %
Interim report for the first six month 2006/07 for TK Development A/S 7/36
Consolidated financial highlights and key ratios
Consolidated financial high-lights and key katios
Financial highlights and key ratios
(DKK million.) Half-year 2005/06
Half-year 2006/07
Financial highlights:Net revenue 630.0 437.1Value adjustment. investment properties 93.7 92.3Gross profit/loss 143.0 157.9Profit/loss from ordinary activities before financing 70.7 82.8Financing, etc. -85.7 -76.8Profit/loss before tax -15.0 6.0Consolidated profit/loss 12.3 24.7Shareholders’ share of profit/loss for the year -11.7 2.5
Balance sheet total 4,836.8 4,422.3Property, plant and equipment 721.0 877.7of which investment properties 693.2 853.6Total project portfolio 2,563.6 2,131.7Equity excl. minority interests 289.7 900.9Equity 350.3 1,011.8Total capital resources* 1,128.8 1,507.7
Cash flows from operating activities** 352.4 149.1Net interest-bearing debt, end of year 3,252.2 2,406.7
Key ratios:Return on equity (ROE)*** -7.8 % 0.5 %Earnings before interest and tax (EBIT margin) 11.2 % 18.9 %Solvency ratio (based on equity) 7.2 % 22.9 %Solvency ratio (based on capital resources) 23.3 % 34.1 %Equity value (nom. DKK 20) 20.7 32.1Earnings per share (EPS-D) of nom. DKK 20 -0.8 0.1Dividend (in DKK per share) 0.0 0.0Listed price of shares (nom. DKK 20) 57 62
Key ratios adjusted for the issue of convertible bonds:Return on equity (ROE)*** -7.8% 0.8%Solvency ratio (based on equity) 7.2% 23.9%Solvency ratio (based on capital resources) 23.3% 35.0%Equity value (nom. DKK 20) 20.7 33.3Earnings per share (EPS-D) of nom. DKK 20 -0.8 0.1
The calculation of key ratios was based on the guidelines issued by the Danish Society of Financial Analysts. Basis for calculating solvency ratio: equity at year-end/liabilities at year-end.
*) According to IFRS. total capital resources include minority interests.
**) Calculated as cash flows from operating activities, corrected for increase/decrease in credit institutions.
***) Annualized.
8/36 Interim report for the first six month 2006/07 for TK Development A/S
Management’s review
First six months of the 2006/07 financial year
During the first six months of the 2006/07 financial year, TK
Development A/S recorded a profit of DKK 2.5 million after
tax and minority interests, which Management considers ac-
ceptable.
Income statement
Net revenue
The revenue for the first half of 2006/07 totalled DKK 437.1
million. Total revenue for the same period the year before
amounted to DKK 630.0 million.
The breakdown of net revenue by geographical segment is as
follows: 78.7 % in Northern Europe and 21.3 % in Central
Europe. Net revenue breaks down on the following business
segments: 82.4 % on the retail segment, 1.2 % on the office
segment and 16.4 % on mixed-segment projects.
Gross margin
The gross margin for the first half of 2006/07 amounted to
DKK 157.9 million, against DKK 143.0 million in the first
half of 2005/06. The gross margin was affected by a posi-
tive revaluation of the Group’s investment properties in the
amount of DKK 92.3 million as a consequence of improved
letting activity and a continued positive market development
in Central Europe, resulting in declining return requirements.
In addition, the gross margin was affected by a DKK 110.0
million writedown on the Group’s outstanding selling price
receivable for the Field’s project.
Staff costs and other external expenses
Staff costs and other external expenses amounted to DKK
70.1 million for the first half of 2006/07, the same level as the
first half of 2005/06.
Staff costs totalled DKK 47.8 million in the first half of
2006/07, thus up 12.7 % on the first half of 2005/06. The
number of employees in the Group increased from 190 at 31
July 2005 to 212 at 31 January 2006, and to 231 during the
period ended 31 July 2006. This increase is partly attribut-
able to new recruitments in Euro Mall Centre Management
(EMCM). The staff costs associated with these recruitments
are fully reimbursed by the owners of the shopping centres
managed by EMCM. In addition, new employees were re-
cruited for the strong reinforcement of the Group’s project
development activities. Moreover, compared to the first half
of 2005/06, staff costs were augmented by the costs of the
warrants scheme set up at the end of 2005.
Other external expenses totalled DKK 22.3 million against
DKK 25.7 million in the first half of 2005/06. In the pe-
riod under review, other external expenses were affected by
the reimbursement of costs defrayed in previous years. After
adjustment for this reimbursement, other external expenses
remained at the same level as in the comparable period in
2005/06.
Financing, etc.
In the first half of 2006/07, net financing expenses of DKK
76.8 million were recorded. This is a reduction of about
10 % compared to the first half of 2005/06. Financing ex-
penses were positively impacted by the rights issue that TK
Development A/S carried out in the 2005/06 financial year,
with the payment of net proceeds to TK Development A/S of
DKK 540.1 million at end-January 2006.
Tax on net profit or loss for the period
Estimated tax on the profit for the period constitutes a posi-
tive amount of DKK 18.7 million, which should be viewed
in light of the fact that a major part of the Group’s earnings
in Central Europe were realized as tax-free capital gains in the
interim financial statements.
Management’s review
Interim report for the first six month 2006/07 for TK Development A/S 9/36
Management’s review
Profit after tax
The Group’s profit after tax amounted to DKK 24.7 million,
and the shareholders’ share of the profit after tax amounted to
DKK 2.5 million.
Balance sheet
The Group’s balance sheet total amounted to DKK 4,422.3
million at 31 July 2006, a decline of DKK 414.5 million, or
8.6 %, compared to 31 July 2005. The balance sheet total at
31 July 2006 was DKK 316.8 million lower than at 31 Janu-
ary 2006, a 6.7 % decrease.
Assets
Goodwill
Goodwill totalled DKK 29.1 million at 31 July 2006. The
carrying amount of goodwill has been subjected to an im-
pairment test. This impairment test has not given rise to any
writedown.
Investment properties
The Group’s investment properties are valued on the basis of a
discounted cash-flow model, where future cash flows are dis-
counted to net present value on the basis of a given rate of
return.
The valuation of the Group’s German investment properties at
31 July 2006 was based on a rate of return of 6 %. A positive
revaluation of DKK 2.8 million was made for these properties
during the period under review.
As a consequence of the improved letting situation for the
Group’s investment properties and sustained positive market
development in Central Europe, which led to declining re-
turn requirements, Management made a DKK 89.5 million
revaluation of the Group’s investment properties in the Czech
Republic and Poland, thus affecting the profit for the period
before tax and minority interests. The revaluation is based on
a rate of return of 7.0 % for Czech investment properties,
where the valuation at 31 January 2006 was based on a rate of
return of 8.0 %. The return requirement for the Group’s in-
vestment property in Poland declined from 7.5 % at 31 Janu-
ary 2006 to 6.75 %, corresponding to the return requirement
agreed when the property was sold; see the description below.
At 31 July 2006, the total value of the Group’s investment
properties constituted DKK 853.6 million, of which DKK
622.4 million relates to the Central European investment
properties in Euro Mall Holding, and DKK 231.2 million
relates to the German investment properties.
Deferred tax asset
The deferred tax asset in the balance sheet amounted to DKK
294.3 million at 31 July 2006, up DKK 25.0 million from 31
January 2006. Based on existing budgets and profit forecasts
for a five-year period, Management made a specific assessment
of the valuation of the deferred tax asset. Thus, Management
expects, within the next few years, to be able to utilize the tax
losses underlying the deferred tax asset.
Project portfolio
The total project portfolio declined by DKK 431.9 million,
from DKK 2,563.7 million at 31 July 2005 to DKK 2,131.7
million at 31 July 2006. At 31 January 2006, the project
portfolio amounted to DKK 2,260.4 million. This decline is
attributable to the growing use of forward funding for sold
projects. Moreover, in the first half of 2006/07, the Group
sold and handed over several completed projects that had been
part of its portfolio for some time.
Total prepayments based on forward-funding agreements
amounted to DKK 980.7 million at 31 July 2006 against
DKK 638.1 million at 31 January 2006, equal to an increase
of 53.7 %. At 31 July 2005, prepayments based on forward
10/36 Interim report for the first six month 2006/07 for TK Development A/S
Management’s review
funding amounted to DKK 449.9 million.
For a more detailed description of the Group’s project port-
folio, reference is made to the separate section on page 20 in
this interim report.
Receivables
Total receivables amounted to DKK 682.3 million, equal to
a DKK 121.5 million reduction compared to 31 July 2005
and a DKK 264.0 million reduction compared to 31 Janu-
ary 2006. This reduction was triggered mainly by a decline in
trade receivables.
Cash and cash equivalents
Cash and cash equivalents declined from DKK 363.8 million
at 31 January 2006 to DKK 323.6 million at 31 July 2006.
This decline is attributable to a reduction of the Group’s net
interest-bearing debt.
Liabilities and equity
Equity
Consolidated equity totalled DKK 1,011.8 million at 31 July
2006, of which DKK 110.9 million is attributable to minority
interests. At 31 January 2006, consolidated equity amounted
to DKK 986.7 million, of which DKK 87.6 million was at-
tributable to minority interests.
The increase in equity is largely attributable to the profit gen-
erated for the period.
Total capital resources amounted to DKK 1,507.7 million at
31 July 2006, equal to a solvency ratio of 34.1 %. Based on
equity alone, the solvency ratio is 22.9 %.
Long-term liabilities
The Group’s long-term liabilities represented DKK 302.7 mil-
lion at 31 July 2006, a DKK 247.1 million reduction from 31
January 2006. As a result of the sale of the Group’s investment
property in Sosnowiec, Poland (see detailed description be-
low), the pertinent liabilities were transferred from long-term
to short-term liabilities.
Short-term liabilities
Short-term liabilities declined by DKK 94.8 million from
31 January 2006 to DKK 3,107.8 million at 31 July 2006.
This decline is due to a combination of a DKK 48.3 million
increase in payables to credit institutions and a DKK 143.2
million reduction of trade payables and other debt.
Financial liabilities have been offset against trade receivables
and tied-up cash and cash equivalents, to the extent that the
Company has a right of setoff and also intends or is contrac-
tually obliged to realize assets and liabilities at the same time.
The amount offset against trade receivables totals DKK 89.6
million, and the amount offset against tied-up cash and cash
equivalents totals DKK 83.4 million, a total of DKK 173.0
million.
Cash flow statement
The cash flow statement shows positive cash flows from oper-
ating activities of DKK 206.1 million and negative cash flows
from financing activities of DKK 245.8 million. In the period
under review, the Group substantially reduced trade payables
and other debt.
DKK millionFirst 6
months 2006/07
2005/06 2004/05
Cashflows from operations *) 149.1 506.1 1,507.5
Net interest-bearing debt, end of period 2,406.7 2,577.9 3,603.7
*) Determined as cash flows from operating activities adjusted for changes in credit institutions
Interim report for the first six month 2006/07 for TK Development A/S 11/36
Management’s review
TKD Nordeuropa
During the first six months of the 2006/07 financial year,
TKD Nordeuropa recorded a profit of DKK 7.4 million after
tax. The profit after tax for the first half of 2005/06 amounted
to DKK 12.7 million. The gross margin amounted to DKK
84.2 million, against DKK 81.7 million in the same period
the year before. Management considers the performance for
the period to be acceptable.
TKD Nordeuropa continued to focus on improving the qual-
ity of its project portfolio during the period under review. In
addition, the half-year period saw the sale of projects devel-
oped and completed in previous financial years, including
commercial property for CMC at Vandtårnsvej in Copenha-
gen and the untenanted Daells retail premises in Copenhagen.
Further, TKD Nordeuropa developed, sold and handed over a
number of minor projects in the first half of the year.
Major projects contributing to the profit for the period in-
clude the following:
CMC, Vandtårnsvej, Denmark
Through a 50/50 owned development company, TK Develop-
ment and Nordkranen A/S have sold this property of about
8,300 m2, tenanted by CMC Biopharmaceuticals A/S. The
investor is a Luxemburg fund consisting of institutional inves-
tors and managed by Aberdeen Property Investors. The total
selling price amounts to DKK 182.0 million.
Daells, Copenhagen, Denmark
The untenanted retail premises in the converted building
housing the former Daells Varehus department store were
sold and handed over to a private investor during the period
under review.
AaB College, Hadsundvej, Aalborg, Denmark
Part of the area at Hadsundvej, Aalborg, has been sold to Aal-
borg Boldspilklub A/S, for the purpose of developing a sports
college with course and conference facilities as well as accom-
modation for students. The total project area will cover about
15,000 m2, to be handed over in phases. The first phase of
6,610 m2 has been handed over to AaB, thus contributing
positively to the profit for the period.
Barkarby, Sweden
In July 2006, the first of four phases in total was handed over
to the investor. The first phase covers about 4,000 m2, and the
premises have been let to Jula and Färgtema. The investor buy-
ing the total project is the German investment fund Commerz
Grundbesitz Spezialfondsgesellschaft mbH.
Kristianstad, Sweden
This project consists of a 3,100 m² retail park. The first phase,
which has been let to Intersport, was completed and handed
over to a private investor during the period under review. The
last phase was handed over to a private investor in September
2006, and the premises have been let to Pay C.
Galerija Azur, Riga, Latvia
The Group’s first shopping centre project in Riga, Latvia, cov-
ers about 20,500 m2 and has been sold to Meinl European
Land Ltd. based on forward funding. The Group will receive
fee income, to be invoiced and settled on a continuous basis.
The fee income earned during the period under review has
been recognized in the profit for the period. The shopping
centre was completed after the balance sheet date and opened
on 24 August 2006. All centre premises have been fully let.
Project developments
Entré shopping centre, Malmö, Sweden
Since the balance sheet date, TKD Nordeuropa has sold the
Entré shopping centre project in Malmö to CGI – Commerz
/
12/36 Interim report for the first six month 2006/07 for TK Development A/S
CMC, Vandtårnsvej, Denmark. Daells, Copenhagen, Denmark.
Barkarby, Sweden
Management’s review
Shoppingcenter Entré, Malmö, Sweden
Galerija Azur, Riga, Latvia
/
Interim report for the first six month 2006/07 for TK Development A/S 13/36
Grundbesitz Investmentgesellschaft mbH. The agreed selling
price reflects a return requirement of 6 %, based on forward
funding, and is expected to total about SEK 1.5 billion. TKD
Nordeuropa has entered into a turnkey contract with Skanska
for construction of the centre. The necessary regulatory ap-
provals have been obtained, construction has started and the
occupancy rate exceeds 50 %. The centre is scheduled to open
in the autumn of 2008. Moreover, during the period under re-
view, TKD Nordeuropa bought its joint venture partner out,
thus increasing its interest in the project to 100 %.
Storegade, Esbjerg, Denmark
This project consists of a 2,500 m² retail park, and lease
agreements have been concluded with Arca and Bileksperten.
The planning basis for the project has been approved, and
construction is expected to start at the beginning of 2007,
with handing-over scheduled for autumn 2007. The project
has been sold on the basis of forward funding.
Århus Syd, Denmark
In Århus, the Group is preparing construction of a 5,400 m²
retail park. The project will consist of two phases, the first
covering about 2,500 m². An approval in principle has been
obtained for the first phase, and construction is expected to
start at the beginning of 2007, with handing-over scheduled
for autumn 2007. The total project has been sold on the basis
of forward funding.
Tammisto Retail Park, Helsinki, Finland
In Tammisto, Finland, the Group commenced construction
of a 5,000 m2 retail park, whose tenants include TOYS”R”US.
Completion is scheduled for spring 2007. The project has
been sold to a private investor based on forward funding.
Further major project developments and a more detailed de-
scription of the Group’s largest projects appear from the sec-
tion on the project portfolio.
The development potential of the total project portfolio repre-
sents about 188,000 m² for sold projects and 466,000 m² for
other projects, a total of 654,000 m².
Euro Mall Holding
Euro Mall Holding continued the positive development from
the year before, realizing a profit after tax of DKK 110.6 mil-
lion in the first half of 2006/07. The profit after tax for the
first half of 2005/06 amounted to DKK 114.7 million.
The gross margin amounted to DKK 169.4 million, against
DKK 178.2 million in the same period the year before. Euro
Mall Holding recorded satisfactory development in its project
portfolio during the period under review.
Management considers the profit for the period to be highly
satisfactory.
Major projects contributing to the profit for the period in-
clude the following:
Šestka, Prague, Czech Republic
The Group’s Šestka shopping centre project, covering 26,500
m², has been sold to Europolis based on forward funding.
Construction has started, and the centre is expected to open
in November 2006. The Group will receive fee income, to be
invoiced and settled on a continuous basis. The fee income al-
ready earned has been recognized in the profit for the period.
Galeria Biala, Bialystok, Poland
This project covers a total of about 46,000 m2 and will com-
prise an 11,000 m2 hypermarket, about 90 specialty stores
and leisure facilities. The project is being developed in a joint
venture with the Central European investment company
Meinl European Land Ltd. The current occupancy rate is
about 80 %. Euro Mall Holding obtained a building permit
Management’s review
14/36 Interim report for the first six month 2006/07 for TK Development A/S
for the project in September 2006. Construction has been ini-
tiated and is expected to be completed in autumn 2007.
Sale of land, Wroclaw, Poland
The Group sold its development site in Wroclaw, Poland, to a
Polish investor in the first half of 2006/07.
Revaluation of the Group’s Central European investment
properties
The Group’s investment properties in Central Europe consist
of a shopping centre in Sosnowiec, Poland, and the Group’s
20 % ownership interests in three shopping centres in the
Czech Republic, situated in Hradec Králové, Ostrava and
Olomouc, respectively.
The total value of the Group’s Central European investment
properties amounted to DKK 622.4 million at 31 July 2006.
As a consequence of the improved letting situation for the
Group’s investment properties and sustained positive market
development in Central Europe, which led to declining return
requirements, Management made a positive DKK 89.5 mil-
lion revaluation of the Group’s investment properties in the
Czech Republic and Poland before tax and minority interests.
The Group’s investment property in Sosnowiec, Poland, ac-
counts for about DKK 30 million of this amount. The re-
valuation is based on a rate of return of 7.0 % for the Czech
investment properties, where the valuation at 31 January 2006
was based on a rate of return of 8.0 %. The return require-
ment for the Group’s investment property in Poland declined
from 7.5 % at 31 January 2006 to 6.75 %, corresponding to
the return requirement agreed when the property was sold; see
the description below.
Project developments
Plejada shopping centre, Sosnowiec, Poland
In September 2006, TK Development made an agreement to
sell the Plejada shopping centre in the Polish town Sosnowiec
to St. Martins Europe BV, the Netherlands, owned by the UK
property investment company St. Martins Property Corpora-
tion Limited; see stock exchange announcement no. 11/2006.
The selling price is based on a rate of return for the investor of
6.75 %. As part of the sales agreement, it has been agreed that
TK Development’s subsidiary Euro Mall Holding is to begin
constructing a 5,000 m² extension of the centre in autumn
2006. The extension will accommodate about 19 new spe-
cialty and brand stores. The completion and opening of the
centre are scheduled for mid-2007.
Targówek Retail Park, Warsaw, Poland
Euro Mall Holding has obtained a building permit for this
project, which comprises a 24,100 m2 retail park situated at
the Targówek shopping centre. The current occupancy rate
exceeds 75 %. A letter of intent for sale of the project to an in-
vestor has been signed, based on forward funding. Construc-
tion start is scheduled for autumn 2006.
Prague Outlet Centre, Prague, Czech Republic
This project consists of the development of a factory outlet
centre of about 25,000 m2. During the period under review,
an agreement for the sale of 25 % of the project was made,
and a local plan has been obtained for the project. Euro Mall
Holding expects a building permit to be issued at the end of
2006.
Further major project developments and a more detailed de-
scription of the Group’s largest projects appear from the sec-
tion on the project portfolio.
At 31 July 2006, the development potential of the project
Management’s review
Interim report for the first six month 2006/07 for TK Development A/S 15/36
portfolio represented 73,000 m² for sold projects and 305,000
m² for other projects, a total of 378,000 m².
Euro Mall Centre Management
The business areas of Euro Mall Centre Management
(EMCM) comprise shopping centre management and associ-
ated services in the Czech Republic, Slovakia, Poland and the
Baltic States. In the first half of 2006/07, EMCM increased
its activity level and today manages a total of 17 shopping
centres. The management activities comprise shopping cen-
tre premises of about 416,000 m2 and approximately 1,200
tenancies.
TK Development, the Parent Company
TK Development, the Parent Company, is a holding company
for TKD Nordeuropa and Euro Mall Holding. Moreover, this
part of the Group owns the receivable from the Field’s project,
the projects in Germany and Russia and a few other assets.
The half-year results for this part of the Group total DKK
–115.5 million after tax and minority interests, of which
DKK -22.2 million is attributable to minority interests. Man-
agement considers the performance for the period to be un-
satisfactory.
Writedown of the receivable from the Field’s project
The Group sold its stake in the Field’s project to the Steen
& Strøm Group on 1 December 2004, receiving an amount
of DKK 1.1 billion as payment on account. The outstanding
selling price will be determined on 1 March 2007, based on
the performance of the centre. The crucial element will be
the rent payments received in the period from March 2006
through February 2007, including the revenue-driven rent
obtainable in addition to the agreed-upon minimum rent
from the individual tenants Based on the available data
regarding centre operations, Management’s reassessment of
the outstanding selling price receivable resulted in a further
writedown of DKK 110.0 million in the first half of 2006/07,
with a corresponding impact on pre-tax results. Thus, as the
outstanding selling price will be determined as at 1 March
2007, and will be based in part on the revenue-driven rent
received, the valuation of the outstanding selling price
receivable may still be subject to uncertainty.
Revaluation of the Group’s German investment properties
The Group’s investment properties in Germany consist of
commercial and residential rental properties, all situated
on the outskirts of Berlin, apart from a property located in
Lüdenscheid. The value of these properties aggregated DKK
231.3 million at 31 July 2006. A positive revaluation of DKK
2.8 million before tax and minority interests was made in the
first half of 2006/07.
The revaluation is based on a 6 % rate of return, calculated on
the basis of a discounted cash-flow model. In the period under
review, satisfactory net rent payments were received for these
properties, which are almost fully let and generate a positive
cash flow.
Current assets
The project portfolio of current assets in TK Development,
the Parent Company, principally comprises building land in
Germany, residential units in Russia and a minor shopping
centre in Szczecin, Poland.
Germany
During the period under review, TK Development sold the
remaining 18 holiday units on the island of Usedom in north-
ern Germany. After the sale of these holiday units, the Group’s
project portfolio in Germany consists of four development
sites, and negotiations about the sale of one of these sites are
Management’s review
16/36 Interim report for the first six month 2006/07 for TK Development A/S
Targówek Retail Park, Warsaw, Poland. Shoppingcenter Plejada, Sosnowiec, Poland.
Management’s review
Prague Outlet Center, Prague, Czech Republic
Šestka, Prague, Czech Republic. Galeria Biala, Bialystok, Poland.
Interim report for the first six month 2006/07 for TK Development A/S 17/36
currently ongoing.
Russia
The Group’s housing project close to the Summer Palace in
St. Petersburg was sold to a Swedish investor during the pe-
riod under review. Following this sale, the project portfolio
in Russia consists of a residential project in Moscow with 11
detached houses in Scandinavian style.
Poland
The Group has held the shopping centre in Szczecin, Poland,
for a number of years. The 4,500 m² property, now almost
fully let, was sold to a UK investor after the balance sheet
date.
Lawsuits
For some years now, the Group has been involved in a dispute
with the Polish Government regarding incorrect VAT declara-
tion, the consequence of which was the erroneous payment of
a major VAT amount to the Polish authorities. The District
Administrative Court in Poland found for the Group in its
decision of 9 November 2005, ordering the authorities to re-
pay the amount to the Group. The amount was repaid during
the period under review.
In addition, experts’ opinions have been commissioned for a
few of the Group’s projects, but they are not expected to ma-
terially affect the Group’s earnings, neither individually nor
collectively.
Financial targets
To provide for sufficient future financial resources, TK Devel-
opment has adopted liquidity targets for the subgroups with
active projects, TKD Nordeuropa and Euro Mall Holding. In
addition, Management has adopted a solvency target for the
Group corresponding to a solvency ratio of 25 % based on
total capital resources. Liquidity targets and a group solvency
ratio of not less than 21 % based on the total capital resources
are also used as covenants in respect of the Group’s bankers
providing operating credit facilities. Moreover, covenants are
used vis-à-vis the holders of bonds in TK Development A/S
and TKD Nordeuropa A/S.
Throughout the period under review, the Group complied
with its liquidity targets and covenants, in relation to both
banks and holders of bonds.
With a solvency ratio of 34.1 % based on total capital re-
sources and a solvency ratio of 22.9 % based on equity alone,
the Group has also met the solvency target adopted.
Another of Management’s previously adopted targets was to
reduce the balance sheet total to a figure below DKK 4.5 bil-
lion. With a balance sheet total of DKK 4,422.3 million at 31
July 2006, this target has also been met.
Post-balance sheet events
No major events other than those mentioned in the Manage-
ment’s review have occurred after the balance sheet date.
Senior Vice President charged by the Polish po-lice
In June 2006, the Senior Vice President in charge of the
Group’s Polish branch office was detained, taken into custody
and charged by the Polish police with irregularities related
to obtaining regulatory approval (zoning permission) for the
Polish Galeria Biala shopping centre project in Bialystok.
Management’s review
18/36 Interim report for the first six month 2006/07 for TK Development A/S
The Polish court in Bialystok had not previously found grounds
for extending the period of detention, which prompted expec-
tations that the Senior Vice President would be released; see
stock exchange announcement no. 10/2006.
The Polish prosecution service appealed against the court or-
der, and after a hearing the court decided to uphold the charge
and extend the period of detention; see stock exchange an-
nouncement no. 13/2006.
Group Management has been unable to find any irregularities
in connection with the project in Bialystok, for which a build-
ing permit has been issued and constructed initiated.
Group Management still finds it incomprehensible that the
Senior Vice President could be involved in any irregularities,
and Management therefore continues its efforts to have the
Senior Vice President released from detention.
Charges brought by the public prosecutor for serious economic crimes
Based on information published in stock exchange announce-
ment no. 19/2005, no. 20/2005 and the prospectus of 30
December 2005 as well as other information, the public pros-
ecutor for serious economic crimes has charged TK Develop-
ment A/S and six individuals with fraudulent income recog-
nition and price manipulation concerning periods covering
the 2000/01 to 2003/04 financial years. The charge from the
autumn of 2005 covers 16 projects.
On 14 June 2006, the charge against TK Development A/S
and the six individuals was supplemented. The charge still con-
cerns fraudulent income recognition and price manipulation
and still relates to periods covering the 2000/01 to 2003/04
financial years. The charge was supplemented in June 2006
because several of the alleged offences would otherwise have
become statute-barred shortly. The charge now covers an ad-
ditional 13 projects located in Denmark and Central Europe.
The police suspect that there was no basis for recognizing in-
come at the times in question, and that income could thus not
be recognized according to applicable accounting principles or
the accounting policies disclosed by TK Development A/S.
Management still considers that the charges are based on
misconceptions concerning the Group’s accounting policies.
Reference is also made to stock exchange announcement no.
3/2006.
The issues covered by the charge do not affect the Company’s
current financial position.
Outlook
Management has revised the profit estimate for the 2006/07
financial year upwards to about DKK 240 million after tax
and minority interests, compared to the previously published
profit forecast of DKK 200 million.
The revised profit estimate is underpinned by the profit gen-
erated in the first half of 2006/07, the expected completion
during the second half of 2006/07 of a number of projects in
progress that have already been sold, and the ongoing nego-
tiations regarding the sale of some of the Group’s completed
projects.
The Group also expects the operation of Euro Mall Holding’s
activities to proceed completely satisfactorily. Northern Eu-
ropean activities, under TKD Nordeuropa, are progressing
according to plan. TKD Nordeuropa still expects to report a
profit after tax of around DKK 120 million. For more details,
please refer to stock exchange announcement no. 7/2006 for
TKD Nordeuropa A/S, dated today.
Management’s review
Interim report for the first six month 2006/07 for TK Development A/S 19/36
Viewed in isolation, the remaining activities in TK Devel-
opment A/S, the Parent Company, are expected to have a
negative impact on the performance for the 2006/07 finan-
cial year, primarily due to the writedown regarding Field’s.
Despite this impact, Management has revised the previously
announced profit estimate upwards to about DKK 240 mil-
lion; see above.
Management’s review
20/36 Interim report for the first six month 2006/07 for TK Development A/S
Projects at 31 July 2006 TKD Nordeuropa *)
Euro Mall Holding
TK DevelopmentParent Company *) Group, total
(DKK million) (DKK million) (DKK million) (DKK million) Percentage of totalSoldCompleted 110 0 85 195 9.3 %In progress 395 34 0 429 20.5 %Not initiated 33 0 0 33 1.6 %Total 538 34 85 657 31.4 %
UnsoldCompleted 405 0 60 465 22.2 %In progress 255 0 0 255 12.2 %Not initiated 197 483 39 719 34.4 %Total 857 483 99 1,439 66.6 %
Total project portfolio 1,395 517 184 2,096 100.0 %*) Adjusted for intercompany eliminations.
Projects at 31 July 2006 TKD Nordeuropa Euro Mall Holding
TK Development Parent Company Group, total
m² ('000) m² ('000) m² ('000) m² ('000) Percentage of totalSoldCompleted 12 0 9 21 2.0 %In progress 127 73 0 200 18.9 %Not initiated 49 0 0 49 4.6 %Total 188 73 9 270 25.5 %
UnsoldCompleted 33 0 6 39 3.7 %In progress 82 0 0 82 7.7 %Not initiated 351 305 14 670 63.1 %Total 466 305 20 791 74.5 %
Total project portfolio 654 378 29 1,061 100.0
Project portfolio status
The Group’s project portfolio comprised 1,061,000 m² at 31
July 2006, of which projects sold account for 270,000 m²
and the remaining projects for 791,000 m². The remaining
projects are distributed on 466,000 m² in TKD Nordeuropa,
305,000 m² in Euro Mall Holding and 20,000 m² in the Par-
ent Company, TK Development A/S. At 31 January 2006,
The table below shows the square metres of the project portfolio broken down in the same manner as in the table above.
Project portfolio
Project portfolio
the Group’s project portfolio represented a total floor space
of 1,009,000 m2.
The table below shows the distribution of the carrying amount
of the projects in the portfolio at 31 July 2006, for the Com-
pany and the two subgroups. The projects are divided into
sold and unsold at 31 July 2006 and sub-divided into com-
pleted, in progress and not initiated.
Interim report for the first six month 2006/07 for TK Development A/S 21/36
DKK million 31 Jan. 2005 31 Jan. 2006 31 July 2006
SoldCompleted 126 185 195In progress 97 350 429Not initiated 337 78 40
Total 560 613 664
UnsoldCompleted 1,037 643 465In progress 242 88 255Not initiated 813 880 719
Total 2,092 1,611 1,439
Total project portfolio 2,652 2,224 2,096
Number of projects 90 90 96
Forward funding 191 638 981In % of gross carrying amount of sold projects 25.4 % 51.0 % 59.6 %
m² (’000) 31 Jan. 2005 31 Jan. 2006 31 July 2006
SoldCompleted 14 21 21In progress 98 188 200Not initiated 130 80 49
Total 242 289 270
UnsoldCompleted 83 58 39In progress 51 30 82Not initiated 644 632 670
Total 778 720 791
Total project portfolio 1,020 1,009 1,061
The development at group level is outlined below:
The Company has succeeded in reducing the carrying amount of the project portfolio by means of forward funding. At 31 July 2006, forward funding represented 59.9 % of the gross carrying amount of sold projects.
Development in the Group’s project portfolio in square metres:
Project portfolio
22/36 Interim report for the first six month 2006/07 for TK Development A/S
Project portfolio
TKD Nordeuropa
TKD Nordeuropa recorded satisfactory development in its
project portfolio in the first half of 2006/07.
In addition, TKD Nordeuropa has developed and sold a
number of projects, including some properties held by the
Group for a long-term period. At the same time, a number
of new projects have been added to the portfolio, which now
comprises a total of 60 projects, and this level has remained
unchanged for the past two to three years. At 31 July 2006, the
development potential of the portfolio represented 188,000
m² for sold projects and 466,000 m² for other projects, a total
of 654,000 m².
Projects with a project value of more than DKK 50 million
The table below shows the projects that either represent or
are expected to represent a project value exceeding DKK 50
million. The carrying amounts of the projects listed below ac-
counted for more than 95 % of the total carrying amount of
the project portfolio of TKD Nordeuropa at 31 July 2006.
Based on an assessment of materiality, the table below does
not include the projects that either represent or are expected
to represent a project value of less than DKK 50 million. In
terms of carrying amount, TKD Nordeuropa’s five largest
projects represented a total of DKK 1,076 million at 31 July
2006.
Project name City/town SegmentFloor space (m²)
TKD’s ownership
interest
Construction start/Expected
construction start
Opening/ Expected opening
DenmarkDaells Varehus, retail section Copenhagen Retail 2,600 100 % Early 2002 Mid-2003Kennedy Arcade, retail section Aalborg Retail 30,000 100 % Mid-2002 Early 2004Ringsted factory outlet Ringsted Retail 12,000 50 % Autumn 2006 Autumn 2007Corporate headquarters, KMD Aalborg Office 26,000 50 % 1) End-2004 End-2006Selma Lagerløfsvej Aalborg Office 11,200 50 % Early 2007 Early 2007
Østre Teglgade Copenhagen Office /residential 24,000 100 % 2) 2007 2008
Amerika Plads, underground car park Copenhagen Underground car park 30,000 50 % 2004 As sections are completed
Spinderiet Valby Mixed 40,000 100 % Early 2005 Autumn 2007Ejby Industrivej Copenhagen Mixed 10,000 100 % Early 2008 End-2008Vandtårnsvej Copenhagen Mixed 18,000 50 % Mid-2007 As units are completedHadsundvej Aalborg Mixed 24,800 100 % Early 2007 As units are completedAaB College Aalborg Mixed 8,850 100 % Mid-2006 Mid-2007Østre Havn Aalborg Mixed 81,000 50 % 2) As units are
completed As units are completedAmerika Plads, lot C Copenhagen Mixed 11,500 50 % Mid-2007 Mid-2008Amerika Plads, lot A Copenhagen Mixed 13,000 50 % Mid-2007 Mid-2008SwedenEntré shopping centre Malmö Mixed 39,500 100 % Mid-2006 Autumn 2008Karlstad Retail Park Karlstad Retail 30,000 100 % Early 2007 End-2007Barkarby Retail Park Barkarby Retail 19,350 100 % Mid-2005 Phases 2 + 3: Autumn 2007
Phase 4: Early 2008FinlandVantaa – Phase II Vantaa Retail 11,650 100 % Mid-2006 End-2006Lohja Lohja Retail 4,800 100 % Early 2007 Early 2008Tammisto Tammisto Retail 5,000 100 % Mid-2006 Spring 2007Tammerfors – Phase II Tammerfors Retail 5,300 100 % Early 2007 Early 2008Baltic countriesGalerija Azur Riga Retail 20,500 24 % 3) Mid-2005 August 2006Milgravja Street Riga Retail 21,000 100 % Early 2007 End-2007
TKD Nordeuropa, total floor space approx. 500,0001) TKD Nordeuropa’s share of profit on development amounts to 80 % 3) TKD Nordeuropa’s share of profit on development amounts to 90 % 2) TKD Nordeuropa’s share of profit on development amounts to 70 %
Interim report for the first six month 2006/07 for TK Development A/S 23/36
Project portfolio
Projects with a project value of more than DKK 100 million
The key projects of the project portfolio are listed below. Each
project represented a project value in excess of DKK 100 mil-
lion at 31 July 2006.
Spinderiet, Valby, Denmark
The centre is a multi-functional shopping and metropolitan
centre of 40,000 m², encompassing about 17,000 m² of retail
and restaurant facilities, about 4,500 m² of office premises,
about 6,500 m² of leisure facilities, 12,000 m² of housing
facilities and about 550 parking spaces. Construction com-
menced in the spring of 2005, and the project is scheduled for
handing-over to the investor in autumn 2007. The project,
excl. housing, has been sold to Dades, a property investment
company. The housing part, which will consist of 2,500 m²
of rental housing and 9,500 m² of owner-occupied housing,
has been sold to DVB and a private investor, respectively. At
present, the occupancy rate is 81 % for the part that has been
sold to Dades, which is currently not sufficient to meet the
terms for a sale of the project to Dades. Management expects
the terms to be fulfilled by the opening date.
Corporate headquarters for KMD – Stuhrs Brygge, Aalborg,
Denmark
At the former Aalborg Shipyard, the Company is building
26,000 m² of corporate headquarters for KMD (Kommune-
data). The project has been sold to KMD based on forward
funding and is expected to be handed over at the end of 2006
according to schedule. The project forms part of a future
business and residential park at Stuhrs Brygge of more than
100,000 m², for which TKD Nordeuropa regularly buys land
for developing new projects.
Kennedy Arcade, Aalborg, Denmark
This multi-functional centre in Aalborg, housing a traffic ter-
minal, a cinema, offices and a shopping centre, was completed
and opened on 21 March 2004. Of the 34,500 m² of space
in the centre, the cinema covers 4,500 m². The office section
covers 13,100 m², and some of the premises have been let to
the Social and Health Services, NT, Artros - Aalborg Priva-
thospital A/S and Finanshuset Farsø. The tenants renting the
remaining premises, mainly consisting of the retail section, in-
clude the Dreisler Group. At present, the Arcade is being con-
verted to offer more, smaller tenancies, and various initiatives,
including better signage, are being introduced to sharpen the
centre profile. Letting has proceeded satisfactorily, and only
a few tenancies remain vacant. Sales negotiations regarding
both the office section and the retail section are ongoing.
Entré shopping centre, Malmö, Sweden
The centre will be developed as a multi-functional project of
39,500 m², of which 25,000 m² has been allocated for retail
stores, 10,700 m² for restaurants, cinema, fitness and bowling
facilities, 1,100 m² for offices and 2,700 m² for residential
accommodation. In addition, the centre will have common
areas and underground parking facilities with 900 spaces.
Regulatory approval has been obtained for the project, and
the necessary properties and land required for the project have
been bought. The occupancy rate is just above 50 %. The an-
chor tenants include Hennes & Mauritz, Lindex, Hemköp,
Intersport and Svensk Film och Sats. A turnkey contract has
been concluded with Skanska regarding construction of the
centre, which is expected to open in autumn 2008. Since the
balance sheet date, the project has been sold to CGI – Com-
merz Grundbesitz Investmentgesellschaft mbH on the basis
of a rate of return of 6 % p.a. The selling price is expected to
amount to about SEK 1.5 billion. The sale is based on a for-
ward-funding agreement, and thus payment will be made by
instalments as construction is completed. Moreover, during
the period under review, the Group bought its joint venture
partner out, thus increasing its interest in the project to 100
%.
24/36 Interim report for the first six month 2006/07 for TK Development A/S
Barkarby, Stockholm, Sweden
This project consists of a retail park that will cover 21,350 m²,
distributed on eight to ten stores, when fully developed. Con-
struction will be phased in step with letting. The first phase
of 4,000 m² has been fully let, sold and handed over. The
construction of the second and third phases of 6,300 m² and
7,150 m², which have been fully let, started in autumn 2005
and at end-2005, respectively. Both phases are expected to be
handed over to the investor in autumn 2006. The fourth and
last phase is expected to be completed and handed over to the
investor at the beginning of 2008. The total project has been
sold to the German investment fund Commerz Grundbesitz
Spezialfondsgesellschaft mbH on the basis of forward fund-
ing.
Vantaa – Phase II, Helsinki, Finland
Fully developed, Vantaa Retail Park will cover a total area of
about 25,000 m². Phase I of the retail park of 13,000 m²,
which is fully let, was sold in a previous financial year. Phase
II of the retail park has been sold and, when fully developed,
will cover 11,650 m². A lease agreement has been concluded
for about 4,000 m2 of the remaining 5,000 m2 that may be
built under the option to build. The tenant is EVE Megastore,
a Finnish company selling health and beauty products and
associated services. Construction has started and is scheduled
for completion at the end of 2006.
Galerija Azur, Riga, Latvia
The Group’s first project in the Baltic Region consists of the
20,500 m² Galerija Azur shopping centre. The centre opened
on 24 August 2006 and includes a hypermarket operated by
RIMI, which is owned by ICA and KESKO. The centre has
been sold to Meinl European Land Ltd. on the basis of for-
ward funding. The centre premises have been fully let and are
expected to be handed over to an investor shortly.
Projects with a current project value of less than DKK 100 million, but an expected sales value in excess of DKK 100 million
Listed below are some other large projects that have been initi-
ated or are expected to be initiated over the next few years. At
31 July 2006, they each represented a project value of less than
DKK 100 million in the project portfolio, but are expected to
have a sales value of more than DKK 100 million.
Amerika Plads, Copenhagen, Denmark
Kommanditaktieselskabet Danlink Udvikling (DLU), which
is owned 50/50 by the Port of Copenhagen and TKD Nor-
deuropa, owns three projects at Amerika Plads: Lot A, lot C
and underground parking facilities, which have not been sold.
A building complex with about 13,000 m² of office space is to
be built on lot A, and a building complex with about 11,500
m² of commercial and residential space on lot C. Construc-
tion will take place as the space is let. Part of the underground
car park in the Amerika Plads area has been built, and is oper-
ated by Europark.
Factory outlet, Ringsted, Denmark
TKD Nordeuropa has entered into a 50/50 joint venture
agreement with Miller Developments, an experienced factory
outlet developer, concerning the development of a new fac-
tory outlet on the site owned in Ringsted. This project consists
of a 12,000 m² factory outlet centre as well as restaurant facili-
ties and about 1,000 parking spaces. This will be the first ma-
jor factory outlet centre project in Denmark, and the letting
process is underway. Construction work commenced in au-
tumn 2006, with completion scheduled for autumn 2007. Af-
ter start-up and maturing, the centre is expected to be sold.
Hadsundvej, Aalborg, Denmark
KMD is planning to move to new corporate headquarters
at Stuhrs Brygge in Aalborg at the end of 2006, and in this
Project portfolio
Interim report for the first six month 2006/07 for TK Development A/S 25/36
Project portfolio
connection TKD Nordeuropa will take over the company’s
existing headquarters property at Hadsundvej in Aalborg. The
site is located close to the city centre and the university. The
project area covers 24,800 m², and the planned project will
consist of residential and office space, with construction ex-
pected to start at the beginning of 2007. The development
of residential and office premises will be phased in step with
letting or sale.
AaB College, Aalborg, Denmark
Part of the area at Hadsundvej, Aalborg, has been sold to Aal-
borg Boldspilklub A/S, for the purpose of developing a sports
college with course and conference facilities as well as accom-
modation for students. The project, covering about 15,000
m², will be handed over in stages. The first phase of 6,610
has been handed over, and the second phase is scheduled for
handing-over in mid-2007.
Østre Teglgade, Copenhagen, Denmark
This project area covers 24,000 m² attractively located at Tegl-
holmen. Owned by TKD Nordeuropa, the land is well-suited
for a housing or office project. Construction may be phased in
step with letting and/or sale. At present, it is being attempted
to change the current zoning status and obtain regulatory ap-
proval for constructing residential property on the site.
Karlstad, Sweden
In Karlstad, regulatory approval has been obtained to build a
retail park in a new commercial district with direct motorway
access. TKD Nordeuropa has an option to buy the land. The
project area covers 30,000 m², and construction of the project
will be phased in step with letting. The first leases have been
signed, and construction is scheduled to commence at the be-
ginning of 2007. Now that the regulatory approval is in place,
letting activities have been intensified. The project has been
sold to an intermediary on the basis of forward funding.
26/36 Interim report for the first six month 2006/07 for TK Development A/S
Project name City/town Segment Floor space (m²)
TKD’s ownership
interest
Construction start/Expected
construction startOpening/ Expected
opening
Czech RepublicŠestka Shopping Centre Prague Retail 26,500 24 % 1) End-2005 November 2006Prague Airport Ruzyne II Prague Retail 13,000 100 % 2009 2010Prague Outlet Center Prague Retail 25,000 100 % Early 2007 1st phase: End-2007Ostrava Retail Park Ostrava Retail 10,300 100 % Early 2007 End-2007Ostrava – extension Ostrava Retail 3,500 100 % Early 2007 End-2007Liberec Retail Park Liberec Retail 18,500 100 % Mid-2007 Early 2008PolandGaleria Biala Bialystok Retail 46,000 24 % 2) Autumn 2006 Autumn 2007Targówek Retail Park Warsaw Retail 24,100 100 % Autumn 2006 Mid-2007Bytom Retail Park Bytom Retail 25,800 100 % Mid-2007 As units are completedTivoli Residential Park, Targówek Warsaw Residential/
Service 25,300 100 % Autumn 2006 As units are completed
Poznan Warta Poznan Retail/Residential 50,000 100 % End-2007 As units are completed
Reduta III Warsaw Mixed 9,800 100 % Mid-2007 As units are completedSosnowiec – extension Sosnowiec Retail 5,000 100 % End-2006 Mid-2007
Euro Mall Holding total floor space approx. 280,0001) Euro Mall Holding´s share of profit on development amounts to 100%2) Euro Mall Holding´s share of profit on development amounts to 50%
Project portfolio
Euro Mall Holding
Euro Mall Holding recorded satisfactory development in its
project portfolio in the first half of 2006/07.
At 31 July 2006, the development potential of the portfolio
represented 73,000 m² for sold projects and 305,000 m² for
other projects/project opportunities, a total of 378,000 m².
Investment properties are described in a separate section on
page 29.
Projects with a project value of more than DKK 50 million
The table below shows the projects that either represent or
are expected to represent a project value exceeding DKK 50
million. The carrying amounts of the projects listed below ac-
counted for more than 90 % of the total carrying amount of
the project portfolio of Euro Mall Holding at 31 July 2006.
Based on an assessment of materiality, the table below does
not include the projects that either represent or are expected
to represent a project value of less than DKK 50 million. In
terms of carrying amount, Euro Mall Holding’s five largest
projects represented a total of DKK 397 million at 31 July
2006.
Interim report for the first six month 2006/07 for TK Development A/S 27/36
Projects with a project value of more than DKK 100 million
The key projects of the project portfolio are listed below. Each
project represented a project value in excess of DKK 100 mil-
lion at 31 July 2006.
Šestka, Prague, Czech Republic
Euro Mall Holding has entered into an agreement to sell and
develop the Šestka shopping centre in Prague. The shopping
centre will cover 26,500 m², and the 10,400 m² hypermar-
ket has been let to Hypernova, owned by Dutch hypermarket
operator Royal Ahold. The remaining part of the centre will
consist of about 100 stores. The Šestka shopping centre will
be built on land owned by Euro Mall Holding in the Prague 6
district, one of the largest and most attractive residential areas
in Prague, with more than 100,000 inhabitants. The buyer
is Europolis, an Austrian investment company investing in
the Eastern and Central European property markets. For-
ward funding has been agreed for the project as construction
progresses. The current occupancy rate is 90 %. Construction
started at the end of 2005, the shopping centre being sched-
uled to open in November 2006.
Prague Outlet Centre, Prague, Czech Republic
On Euro Mall Holding’s centrally located land, Best Plot in
Prague, preparations are underway for a factory outlet centre
of approximately 25,000 m2. The project is being developed
in a joint venture with an international collaboration partner
with factory outlet experience. A local plan has been obtained
for the project, and a building permit is expected to be is-
sued at the end of 2006. The first phase will consist of about
18,000 m2, and construction is expected to start at the begin-
ning of 2007, with the opening scheduled for end-2007. An
agreement regarding the sale of 25 % of the project was made
during the period under review.
Targówek Retail Park, Warsaw, Poland
The retail park, which will be constructed on Euro Mall Hold-
ing’s land at the Targówek shopping centre, will have a total
floor space of 24,100 m² when fully developed. A building
permit has been obtained for the project, and the current oc-
cupancy rate is 77 %. A letter of intent for sale of the project
to an investor has been signed, based on forward funding.
Construction is scheduled to commence in autumn 2006.
Projects with a current project value of less than DKK 100 million, but an expected sales value in excess of DKK 100 million
Listed below are some other large projects that have been initi-
ated or are expected to be initiated over the next few years. At
31 July 2006, they each represented a project value of less than
DKK 100 million in the project portfolio, but are expected to
have a sales value of more than DKK 100 million.
Ostrava Retail Park, Czech Republic
The retail park will be built on Euro Mall Holding’s site at
the Futurum shopping centre in Ostrava. The site includes an
option to build 10,300 m². Letting efforts are ongoing, and
tenants have committed themselves to renting about 70 %.
Construction will start once a satisfactory occupancy rate has
been obtained, based on binding lease agreements.
Liberec Retail Park, Czech Republic
This project consists of an 18,500 m² retail park. The project
will be built in phases, the first covering about 11,500 m².
Letting has started, and an application has been submitted
for an approval in principle. Construction is expected to start
mid-2007, with handing-over scheduled for the beginning of
2008.
Galeria Biala, Bialystok, Poland
An agreement has been reached with Meinl European Land
Ltd. regarding the development of a shopping and leisure
Project portfolio
28/36 Interim report for the first six month 2006/07 for TK Development A/S
Project portfolio
centre in Bialystok in Poland. Meinl has acquired the neces-
sary sites and obtained the necessary regulatory approvals. The
continued development and construction of the centre will be
managed by Euro Mall Holding and funded by Meinl Euro-
pean Land Ltd. Covering 46,000 m², the shopping centre will
comprise a hypermarket, about 90 specialty stores and leisure
facilities. Construction of the shopping centre started in Sep-
tember 2006. The current occupancy rate is 80 %.
Bytom Retail Park, Poland
The retail park will be constructed on Euro Mall Holding’s
site at the Plejada shopping centre in Bytom, which offers a
central location in the Katowice region. The site includes an
option to build 25,800 m². Construction of the project will
be phased in step with letting. Letting efforts are ongoing, and
construction will be started as space is let.
Tivoli Residential Park, Targówek, Warsaw, Poland
Euro Mall Holding is planning to develop a housing project
on its land in the Targówek area in Warsaw. When fully de-
veloped, the multi-phase project will consist of 300 residen-
tial units and ground-floor premises for service trades. The
project is expected to be sold as owner-occupied residential
units. Construction is expected to start in autumn 2006. The
advance sale of the owner-occupied units has started.
Reduta III, Warsaw Poland
Euro Mall Holding owns a site adjacent to the Reduta shop-
ping centre in Warsaw. In 2003, a building was erected and
sold and subsequently let to the French sporting goods chain
Decathlon. A 9,800 m² office property is being planned, with
construction to begin upon completion of the letting proc-
ess.
TK Development, the Parent Company
TK Development owns the receivable from the Field’s project,
the projects in Germany and Russia and a few other projects.
The letting of TK Development’s projects in Russia and Ger-
many proceeded satisfactorily during the period under re-
view.
Projects
The project portfolio of current assets in TK Development,
the Parent Company, principally comprises building land in
Germany, residential units in Russia and a minor shopping
centre in Szczecin, Poland.
Germany
During the period under review, TK Development sold the
remaining 18 holiday units on the island of Usedom in north-
ern Germany. After the sale of these holiday units, the Group’s
project portfolio in Germany consists of four development
sites, and negotiations about the sale of one of these sites are
currently ongoing.
Russia
The Group’s housing project close to the Summer Palace in
St. Petersburg was sold to a Swedish investor during the pe-
riod under review. Following this sale, the project portfolio
in Russia consists of a residential project in Moscow with 11
detached houses in Scandinavian style.
Poland
The Group has owned a shopping centre in Szczecin, Poland,
for a number of years. The centre has a floor space of about
4,500 m² and has almost been fully let. In September 2006,
the project was sold to a UK investor.
The investment properties of TK Development, the Parent
Interim report for the first six month 2006/07 for TK Development A/S 29/36
Company, are described in the section below.
Investment properties
The Group’s investment properties are included in the balance
sheet under property, plant and equipment. Investment prop-
erties are measured at fair value on the basis of a discounted
cash-flow model, where future cash flows are discounted to
net present value on the basis of a given rate of return. At 31
July 2006, the Group’s investment properties stood at DKK
853.6 million.
Central Europe
Euro Mall Holding’s investment properties were recognized at
DKK 622.4 million at 31 July 2006 based on a rate of return
of 7.0 % p.a. for the Czech investment properties, calculated
on the basis of a discounted cash-flow model. As mentioned
above, the Group has sold its investment property in Poland
after the balance sheet date. The return requirement for the
Group’s Polish investment property is based on the selling
price, corresponding to a return of 6.75 %.
Germany
The Group has five investment properties in Germany owned
by TK Development A/S, of which a combined commercial
and residential property is located in Lüdenscheid in the west-
ern part of the country, whereas the four remaining properties
are residential rental properties on the outskirts of Berlin.
In the first half of 2006/07, the letting situation was satisfac-
tory. The properties are almost fully let and generate a positive
cash flow.
The investment properties were recognized at DKK 231.2
million at 31 July 2006 based on a rate of return of 6.0 % p.a.,
calculated on the basis of a discounted cash-flow model.
Project name City/town Segment Floor space * (m²)
TKD’s ownership
interestOpening
Czech RepublicFuturum Shopping Centre Ostrava Retail 23,600 20 % 1) May 2000Futurum Multifunctional Centre Hradec Králové Retail 18,300 20 % 1) Nov. 2000Haná Shopping Centre Olomouc Retail 10,100 20 % 1) Sept. 2002PolandShopping Centre Plejada Sosnowiec Retail 21,200 100 % Nov. 2001
Total floor space, Central Europe 73,200
Germany Lüdenscheid/Berlin Residential/ Mixed 26,000 100 % 1996-1998
Total floor space, investment properties 99,200* Floor space denotes the floor space owned by TK Development, including common areas.1) GE/Heitman is to receive a preferred return, after which TK is to receive a preferred return. Subsequently profit is to be shared 50/50.
Project portfolio
Below is a list of the Group’s investment properties.
30/36 Interim report for the first six month 2006/07 for TK Development A/S
The Supervisory Board and the Executive Board have to-
day considered and adopted the interim report for the pe-
riod 1 February 2006 - 31 July 2006 for TK Development
A/S. The interim report, which has not been audited, is
presented in compliance with the recognition and measure-
ment requirements of the International Financial Reporting
Standards (IFRS), and in accordance with Danish disclosure
Statement by the Executuve Board and Supervisory Board
Aalborg 26 September, 2006
EXECUTIVE BOARD
SUPERVISORY BOARD
Frede Clausen Robert Andersen
Poul Lauritsen Torsten Erik Rasmussen
Kurt Daell Per Søndergaard Pedersen
Jesper Jarlbæk
Statement by the Executive Board and Supervisory Board
requirements for half-year interim reports prepared by listed
companies. We consider the accounting policies applied to be
appropriate, and, in our opinion, the interim report gives a
true and fair view of the Group’s assets, liabilities, equity and
financial position, as well as the results of the Group’s activi-
ties and cash flows.
Interim report for the first six month 2006/07 for TK Development A/S 31/36
Income statement
Consolidated financial state-ments
Income statement
All amounts in DKKm GroupHalf-year 2006/07
Half-year 2005/06
Net revenue 437.1 630.0External direct project costs -371.5 -580.7Value adjustment of investment properties. net 92.3 93.7
Gross profit/loss 157.9 143.0
Other external expenses -22.3 25.7Staff costs -47.8 42.4
Total -70.1 68.1
Profit/loss from ordinary activities before financing, depreciation and amortization 87.8 74.9
Depreciation. amortization and writedowns of long-term assets -5.0 4.2
Profit/loss from ordinary activities before financing 82.8 70.7
Income from investments in associates 0.1 0.2Income from investments in group enterprises -0.1 -0.1Financial income 39.1 56.6Financial expenses -115.9 -142.4
Total -76.8 -85.7
Profit/loss before tax 6.0 -15.0
Tax on profit/loss for the year -18.7 -27.3
Profit/loss for the year 24.7 12.3
Allocated as followsShareholders of TK Development A/S 2.5 -11.7Minority interests 22.2 24.0
24.7 12.3
Earnings per share in DKKEarnings per share (EPS) of nom, DKK 20 0.1 -0.8Diluted earnings per share (EPS-D) of nom. DKK 20 0,1 -0,8
32/36 Interim report for the first six month 2006/07 for TK Development A/S
Balance sheet
Balance sheet
All amounts in DKKm Group31.07.06 31.01.06 31.07.05
ASSETSLong-term assets
Goodwill 29.1 29.1 29.1Intangible assets 29.1 29.1 29.1
Investment properties 853.6 761.6 693.2Other fixtures and fittings. tools and equipment 24.1 25.6 27.8Property. plant and equipment 877.7 787.2 721.0
Investments in group enterprises 1.8 1.9 2.1Investments in associates 23.6 23.6 23.6Other securities and investments 50.2 53.4 23.0Deferred tax assets 294.3 269.3 271.2Other long-term assets 369.9 348.2 319.9
Total long-term assets 1,276.7 1,164.5 1,070.0
Short-term assets
Projects in progress or completed 2,131.7 2,260.4 2,563.6
Trade receivables 371.2 594.8 443.0Receivables from associates 116.2 101.7 98.6Other receivables 188.7 241.1 253.6Prepayments 6.2 8.7 8.6Total receivables 682.3 946.3 803.8
Securities 8.0 4.1 4.0Cash and cash equivalents 323.6 363.8 395.4Total short-term assets 3,145.6 3,574.6 3,766.8
ASSETS 4,422.3 4,739.1 4,836.8
Interim report for the first six month 2006/07 for TK Development A/S 33/36
Balance sheet
All amounts in DKKm Group31.07.06 31.01.06 31.07.05
LIABILITIES AND EQUITYEquityShare capital 560.9 560.9 280.4Reserve for adjustment to fair value 257.8 165.5 102.1Reserve for foreign-exchange adjustments 9.7 13.2 -5.5Retained earnings 72.5 159.5 -87.3Shareholders’ share of equity 900.9 899.1 289.7
Minority interests 110.9 87.6 60.6
Total equity 1,011.8 986.7 350.3
Short- and long-term liabilities
Subordinated loan capital 0.0 12.4 12.4Subordinated bond loan 0.0 0.0 766.2Credit institutions 227.1 457.4 461.3Provisions 37.5 38.3 0.0Instrument of indebtedness 0.0 3.1 18.0Deferred tax liabilities 38.1 38.6 63.1Total long-term liabilities 302.7 549.8 1,321.0
Subordinated bond loan 495.9 494.4 0.0Credit institutions 2,181.9 2,133.6 2,515.5Trade payables 220.5 277.9 301.1Prepayments received from customers 35.8 35.5 91.3Corporate income tax 25.8 36.5 30.0Provisions 9.6 25.1 52.7Other debt 131.3 190.0 167.5Deferred income 7.0 9.6 7.4Total short-term liabilities 3,107.8 3,202.6 3,165.5
Total short- and long-term liabilities 3,410.5 3,752.4 4,486.5
TOTAL LIABILITIES AND EQUITY 4,422.3 4,739.1 4,836.8
34/36 Interim report for the first six month 2006/07 for TK Development A/S
Statement of changes in equity
Statement of changes in equity
Equity
The share capital of TK Devlopment A/S is not divided into classes of shares and consists of 28,043,810 shares of DKK 20 each. (nom, DKK 560,876,200)
All amounts in DKKm Group31.07.06 31.01.06 31.07.05
Share capitalShare capital beginning of the year 560.9 280.4 280.4Capital increase 0.0 280.5 0.0
Total share capital 560.9 560.9 280.4
Reserve for adjustments to fair valueReserve for adjustments to fair value. beginning of the year 165.5 8.4 8.4Result for the period 92.3 157.1 93.7
Total reserve for adjustments to fair value 257.8 165.5 102.1
Reserve for foreign exch, adjustmentsReserve for foreign exch, Adjustments. beginning of the year 13.2 3.6 3.6Foreign-exchange adjustment. foreign operations -3.5 12.1 -8.1Tax on changes in equity for the year 0.0 -2.5 -1.0
Total reserve for foreign exch, adjustments 9.7 13.2 -5.5
Retained earningsRetainde earnings. beginning of ther year 159.5 18.4 18.4Profit/loss for the year -89.7 -119.1 -105.7Share-based remuneration (warrants) 1.1 0.2 0.0Capital increase 0.0 280.4 0.0Cost of capital increase 0.0 -20.8 0.0Sale of own shares or subscription rightd in connection with captial increase 1.6 0.4 0.0
Total retained earnings 72.5 159.5 -87.3
Total 900.9 899.1 289.7
Minority interestsMinority interests beginning of the year 87.6 32.9 32.9Disposals for the year 0.2 0.0 0.0Result for the period 22.2 50.5 24.0Foreign-exchange adjustment. foreign operations 0.8 1.5 3.7Share-based remuneration (warrants) 0.1 0.0 0.0Capital increase 0.0 2.7 0.0
Total minority interests 110.9 87.6 60.6
Total equity 1,011.8 986.7 350.3
Interim report for the first six month 2006/07 for TK Development A/S 35/36
Cash flow statement
Cash flow statement
All amounts in DKKm GroupHalf-year 2006/07
Half-year2005/06
Profit/loss before financing 82.8 70.7Adjustments for non-cash items Value adjustments. investment properties -92.4 -93.7 Depreciation and amortization 5.0 4.5 Provisions -16.3 1.6 Market-value adjustments 1.0 -8.6Increase/decrease in investments in projects, etc. 120.5 289.4Increase/decrease in receivables 271.3 307.5Increase/decrease in credit institutions 57.0 -521.2Increase/decrease in payables and other debt -114.9 -86.9
Cash flows from operating activities before net financials and tax 314.1 -36.7
Interest paid, etc. -121.9 -104.3Interest received, etc. 28.5 24.1Corporate income tax paid -14.6 -15.4
Cash flows from operating activities 206.1 -132.3
Investments in equipment. fixtures and fittings, net -2.7 -1.9Investment in leasehold improvements -0.1 -0.1Purchase of securities and investments 0.0 0.4Sale of own shares 2.8 0.0
Cash flows from investing activities 0.0 -1.6
Increase/decrease in subordinated loan capital -12.4 -1.4Increase/decrease in long-term financing -233.4 -3.1
Cash flows from financing activities -245.8 -4.4
Cash flows for the year -39.7 -138.3Cash and cash equivalents, beginning of year 363.8 533.9Market-value adjustment of cash and cash equivalents -0.5 -0.2Cash and cash equivalents at year-end 323.6 395.4
Cash and cash equivalents include temporary deposits related to the sale of the Group’s projects. as well as other cash and cash equivalents to which the Group does not have a full right of disposal. a total of DKK 191,3 million.
The figures in the cash flow statement cannot be inferred from the Consolidated Financial Statements alone.
36/36 Interim report for the first six month 2006/07 for TK Development A/S
Segment information
Segment information
All amounts in DKKm Group
Northern Europe
Central Europe Unallocated Total
Primary segment 2006/07
Net revenue 348.8 93.2 0.0 437.0
Value adjustment of investment properties, net 2.8 89.5 0.0 92.3
Profit/loss, associates 0.1 0.0 0.0 0.1
Profit/loss from ordinary activities before financing -64.5 147.3 0.0 82.8
Investments in associates 23.6 0.0 0.0 23.6
Segment assets 2,752.5 1,388.2 281.6 4,422.3
Segment liabilities 2,784.7 555.1 70.6 3,410.4
Capital expenditure 3.4 0.0 0.0 3.4
Depreciation and amortization 3.9 1.1 0.0 5.0
Other major non-cash costs 107.0 0.4 0.0 107.4
All amounts in DKKm Group
Northern Europe
Central Europe Unallocated Total
Primary segment 2005/06
Net revenue 348.1 281.9 0.0 630.0
Value adjustment of investment properties, net 0.0 93.7 0.0 93.7
Profit/loss, associates 0.2 0.0 0.0 0.2
Profit/loss from ordinary activities before financing -75.5 146.2 0.0 70.7
Investments in associates 23.6 0.0 0.0 23.6
Segment assets 3,150.7 1,406.5 279.6 4,836.8
Segment liabilities 3,818.0 574.4 94.1 4,486.5
Capital expenditure 2.4 1.8 0.0 4.2
Depreciation and amortization 3.5 0.7 0.0 4.2
Other major non-cash costs 101.3 0.1 0.0 101.4
All amounts in DKKm GroupRetail Office Segment
mix Unallocated TotalSecondary segment 2006/07
Net revenue 360.0 5.3 71.7 0.0 437.0
Segment assets 1,000.6 524.5 1,184.8 1,712.4 4,422.3
Capital expenditure 0.0 0.0 0.0 3.4 3.4
Secondary segment 2005/06
Net revenue 388.9 102.0 139.1 0.0 630.0
Segment assets 1,665.5 455.2 1,139.5 1,576.6 4,836.8
Capital expenditure 0.0 0.0 0.0 4.2 4.2