Page 1: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following
Page 2: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 1 Revision: A1 December 2014

CONTENT Page

1 GENERAL 5

2 REFERENCE 8

3 MATERIALS 8

4 RESOURCES TO BE USED 8

4.1 Equipment to be used 8

4.2 Nominated Sub-Contractor 8

5 CONSTRUCTION PROCEDURE 9

5.0 Design 9

5.1 Survey Work 10

5.2 Earthwork for Roadways 10

5.2.1 Clearing 11

5.2.2 Topsoil Removal 11

5.2.3 Excavation 11

5.2.4 Subgrade Preparation 12

5.2.5 Embankment 12

5.3 Pavement 13

5.3.1 Subbase Course 13

5.4 Drainage 13

5.4.1 Pipe Culvert 14

5.4.2 Open Ditch 14

5.5 Incidentals 15

5.5.1 Traffic Sign 15

5.5.2 Slope Protection 15

6 SAFETY CONTROL 15

7 QUALITY ASSURANCE 16

Page 3: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 2 Revision: A1 December 2014

PART 2: SITE SPECIFIC ENVIRONMENTAL & SOCIAL MANAGEMENT & MONITORING PLAN

8 SITE SPECIFIC ENVIRONMENTAL & SOCIAL MANAGEMENT & MONITORING 18

8.1 Introduction 18

8.2 Environmental and Social Pre-Construction Description 19

8.3 Sub-Plan Detail for Access Road T3 - Environment 23

8.4 Sub-Plan Detail for Access Road T3 -Social 24

8.5 Chance Find Procedures 26

9 APPENDIX 27

9.1 Organization of Road Work (Road T3)

9.2 Construction Schedule (Road T3)

9.3 Working Drawings (Road T3)

9.4 Emergency Action Plan

9.5 Resource (Road T3)

9.6 Procurement Schedule (Road T3)

9.7 Inspection and Test Plan

9.8 Environmental Management Active Table

9.9 Layout Plan for RCC Plant and T3 Road

10.0 Original Layout Plan of T3 Road

Page 4: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 3 Revision: A1 December 2014

REVISION STATUS

Rev. No. Description Issue Date Remarks

A1

1st Submission for Owner review

Dec 24, 2014

For Owner’s review

Page 5: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 4 Revision: A1 December 2014

PART 1

DETAILED WORKS PROGRAM

(DWP)

Page 6: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 5 Revision: A1 December 2014

1. GENERAL

First of all, the access roads are divided as the following table and the method statement for

each road will be proposed separately. This detailed works program (Document No.NNP1-MS-

RW038) as volume 5 focuses on the T3 temporary access road. It standardizes construction

procedures and material application for the road.

The original plan for T3 road as shown on Appendix 10.0 is purposely intended for plant road in

which considering the actual condition and effective access on RCC Plant we made the New

Layout Plan for T3 road refer to Appendix 9.9 in which compose of 3 parts ; the T3-A

(L=315.70m ), T3-B (L=125m) and T3-C (L=109.3m).The total length of T3 Road is 550m with

both side had open ditches for the diversion of water during rainy season.

Working Drawing of Road T3 will be submitted and after the approval the work will start

meanwhile, the Design is planned in accordance with “Design Policy” separately submitted on

the Contractor letter NNP1-PCL-00126 dated 20th February 2014.

Table-1 Division of Access Road

No. Road Number and Name Length (km) Remark

Vol. 1 A (STA. 0+000 to 21+200) 21.2 Permanent

Vol. 2 P1 (to dam top) 9.32 Permanent

Vol. 3 P2 (to powerhouse) 1.84 Permanent

Vol. 4 T1 & T2 (haul road) 1.58 Temporary

Vol. 5 T3 (RCC &CVC plant road) 0.55 Temporary

Vol. 6-1 T4 (upstream approach road

0+000km to 0+400km) 0.4 Temporary

Vol. 6-2 T4 (upstream approach road

0+400km to tunnel inlet) 1.54 Temporary

Vol. 6-3 T4 (tunnel inlet to upper

stream coffer dam) 0.557 Temporary

Vol. 7 T5 (temporary access road) 3.88 Temporary

Vol. 8 T6 (jetty road) 0.20 Temporary

Vol. 9 T7 (haul road to dam top) 1.54 Temporary

Vol.10-1 T8 (soil disposal road)

(STA. 0+000~1+600km) 1.60 Temporary

Vol.10-2 T8 (soil disposal road)

(STA.1+600~3+080km) 1.48 Temporary

Vol.11 T9 (haul road to quarry) 1.00 Temporary

Vol.12-1 T10 (haul road) 1.01 Temporary

Vol.12-2 T11(haul road) 0.67 Temporary

Vol.13 T12 (temporary road) 0.72 Temporary

Vol.14 T13 (temporary road) 0.52 Temporary

Page 7: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 6 Revision: A1 December 2014

Vol.15 J (JICA road) from T1 to X 7.27 Rehabilitation

The plan view and typical cross section drawing is shown in below.

Figure-1

Plan View

Figure-2 Cutting and filling section

Page 8: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 7 Revision: A1 December 2014

The major quantities for the construction of the T3 temporary road are shown in table below. The

scope of works of the construction work of the T3 temporary road is to secure the accessibility

during the temporary use period including a daily maintenance. Thus the quantities shown in table

below will be changed depending on actual site condition and work volume for the road

maintenance during the temporary operation.

Table-2 Quantities of T3 construction

No. Description Quantity Unit Remark

1 Sub base course 1,155.00 m3

2 Open ditch 1,100.00 m

3 Installation of pipe culvert 2 location

Current site photographs are shown in below.

T3-A (STA 0+315.70)

T3-B (STA 0+000) T3-C (STA 0+109.3m)

T3-A (STA 0+000)

Page 9: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 8 Revision: A1 December 2014

Figure-3 Photographs before construction of Road T3

2. REFERENCE

Referenced Specifications:

- Earthwork : TS 2.2, 2.3, 8.2

- Pavement (Subbase Course) : TS 8.3

- Drainage : TS 8.6, 9.3

- Incidentals : TS 9.4, 9.8, 9.9

3. MATERIAL

The T3 road is temporary road, therefore, materials to be used are temporary use only.

The specification of materials and test method is attached in Appendix 9.7.

Table-3 Material list

No. Description Use for

1 Crushing Aggregate Sub base Course

2 Reinforced Concrete Pipe Pipe Culvert

3 Sign Plate & Post Traffic Sign

4. RESOURCES TO BE USED

4.1 Equipment and tool

Table-4 Equipment and tool list

No. Equipment / Tool Capacity Nos. Purpose

1 Excavator 0.7~1.0 m3 2 Excavation

2 Dump Truck 15 cu.m. 3 Disposal / Hauling

3 Bulldozer 13 ton 1 Spreading Material

4 Vibratory Roller 10 ton 2 Subbase Compaction

5 Water Truck 16,000 Liter 1 Subbase Compaction

6 Road Grader 4 m wide blade 1 Grading/Spreading

4.2 Nominated Subcontractor and Manpower distribution

Nominated Subcontractor: “Meuang Van Development Co., Ltd.”.

Page 10: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 9 Revision: A1 December 2014

The subcontractor Meuang Van Development Co., Ltd is nominated, concerning not only

price/rate but also following items, totally.

1) Technical competence

2) Financially stable

3) Administrative competence

4) Past project experience and reference

5) Ability to meet schedule

6) Quality and skill of work

7) Capacity (equipment, staff, worker) and organization

8) Ability to meet safety and environment requirements

And then, the evaluation for subcontractor will be done and recorded.

Manpower distribution for this work is planned as below.

Table-5 Manpower list

No. Manpower Nos. Purpose

1 Engineer 1 Site Management

2 Foreman 2 Work Management

3 Equipment Operator 11 Operation of Equipment

4 Skilled Worker 3 Assist operator, compaction, installation of pipe

5 Common worker 3 Assist Skilled worker

6 Mechanic 1 Maintenance of equipment

7 Surveyor 2 Survey

5 CONSTRUCTION PROCEDURES

5.0 Design and Work Procedure

The temporary road T3 is planned and will be constructed based on the “Design Policy” as

separately submitted on the Contractor letter NNP1-PCL-00126 dated 20th February 2014.

The procedure of construction is shown below.

Page 11: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 10 Revision: A1 December 2014

5.1 Survey Work

Figure-3 Conceptual drawing of survey

Firstly temporary benchmarks for elevation and coordinate are established at

approximately 100m intervals.

Secondly, the centerline of the road alignment is identified on site with offset pegging

considering the design alignment. After completion of the centerline survey, the cross

section survey is carried out by minimum 20~25m intervals. And then, based on cross

section survey results, embankment and excavation area can be identified on site.

In case the original design alignment will not be suitable for the actual site condition, the

design alignment will be modified and corrected inside the designated area by the Owner.

Survey instruments shall be calibrated in accordance with the section 5.3.3 testing

equipment and facilities of the Quality Assurance Program (Document No. NNP1-PRG-

DrQAP-A3) in the NNP1-PCL-00086, dated 16th Jan. 2014.

5.2 Earthwork for Roadways

5.2.1 Clearing

Figure-4 Conceptual drawing of clearing

1) Before clearing works, the working area for T3 road will be shown by marking.

Work area shall be clearly pegged and shall be confirmed and approved by the

Owner.

Page 12: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 11 Revision: A1 December 2014

2) Clearing shall consist of the removal and disposal of trees, stumps, logs, bush,

undergrowth, grass, crops and loose vegetable matter above a ground level.

When unsuitable materials stay under a ground level, it will be removed and

replaced with suitable materials.

3) Basically it is confirmed that commercial timber along the T3 temporary road

has been already cleared by the Lao government. If commercial timber is found

on site, the branch shall be trimmed, and the timber trees shall be cut into a

suitable size and stored in the vicinity of the site and it will be informed to the

Owner.

4) Prior clearing, wooden pegging which shows the clearance area will be

installed after inspection by the Owner on the clearance area.

5.2.2 Topsoil Removal

1) Basically, the topsoil including stumps and roots shall be removed and

disposed. Any suitable topsoil which is free from roots and vegetable matter

shall be stockpiled at the specified area and used for planting and/or

embankment. The specified area is to be informed to the Owner.

2) It seems that stumps are not deep and long considering the actual site

conditions, thus all of them can be basically removed and replaced with

suitable material. In case that it is difficult to remove all, its countermeasure

will be discussed with the Owner.

3) Removed topsoil which is suitable material for the construction will be stored at

suitable area along the road where it is distinguished in order to prevent mixing

with unsuitable soil.

4) Keeping clearance to the minimum area is required for the proposed project

activity. The extent of vegetation clearance at each site shall be surveyed and

clearly marked prior to the commencement of clearing. In case that the

existing paddy field is within project area, the ridge of paddy field is to be sifted

and irrigation canal shall be diverted.

5) When spoil moves down slope occasionally, the Contractor will make their

best efforts to carefully remove it without disturbing existing vegetation or

natural slope and dispose of it appropriately.

5.2.3 Excavation

Figure-5 Conceptual drawing of excavation

Page 13: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 12 Revision: A1 December 2014

1) Roadway Excavation

The roadway excavation shall be in accordance with the designed alignment,

levels, grades and cross sections. The existing subgrade shall be checked. If

the soft or unsuitable material is found, it shall be removed and removed

portion shall be replaced with suitable embankment materials.

2) Disposal of excavated material

Excavated soil and rock will be stocked at Disposal area No.5 at right bank

side.

5.2.4 Subgrade Preparation

Figure-6 Conceptual drawing of subgrade preparation

1) The subgrade shall be compacted to at least 95% of the maximum dry density

to a depth of 500 mm for material consisting of non-cohesive material and at

least 90% to a depth of 200 mm for natural cohesive material as determined in

accordance with ASTM D1556.

2) The field density test shall be carried out for every 1,000 m2 according to the

progress of work.

3) In case unstable material will be found after an excavation, the unstable material shall

be removed and replaced with the appropriate material.

5.2.5 Embankment

Figure- 7 Conceptual drawing of embankment

Grader

Vibrati

Page 14: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 13 Revision: A1 December 2014

1) The embankment material which is excavated from subgrade preparation work

and slope excavation work shall be complied with specification.

2) The embankment material will be placed and compacted in layers with not

exceeding 200 mm in loose depth for the full width of the cross section to

achieve a density at least 95% of the maximum dry density as determines in

accordance with ASTM D1556. Average of the modified CBR at 95% of

maximum dry density is sufficient for the required design CBR value for

pavement. Please refer Design Statement for Pavement Structure of Road

Works (Document No. NNP2-RW006-A1) in the Contractor letter NNP2-PCL-

00016, dated 8th November 2013.

3) The field density test shall be carried out for each 1,000 m2 or less according

to the progress of work, in each layer until reach to the subbase course layer.

Embankment slope, gradient shall be in accordance with Design policy

separately submitted.

5.3 Pavement

5.3.1 Subbase Course

1) Subbase shall be spread and compacted on the approved subgrade and/or embankment in layer by layer not exceeding 150 mm after compaction. Each layer shall be compacted at least 95% of the maximum dry density as determines in accordance with ASTM D1556.

2) The field density test and the field thickness test shall be arranged one test for

each 1,000 m2 or less according to the progress of work.

3) The surface treatment will be done on the sub-base course for maintenance. Before starting final pavement by others, the top of 100mm of sub-base course shall be repaired in a healthy condition for a part of permanent pavement.

5.4 Drainage

5.4.1 Pipe Culvert

1) The reinforced concrete pipe shall be of the groove and tongue type and shall

in all respects conform to TIS (Thai Industrial Standards) 128 Class 3 or

equivalent. Pipes shall be free of fractures, large or deep cracks, and surface

roughness.

2) Backfilling shall be carried out with material free from rubbish, vegetable

matter or other deleterious material and as indicated on the drawings. Special

care shall be taken to ensure that backfill shall be brought up evenly on both

side of the pipe. Backfill material will be followed to embankment in section

5.2.5.

3) In order to keep proper water flow, the catchment basin will be provided around

inlet of pipe culvert if necessary. Before rainy season, clearing of pipe will be

carried out.

5) The slope at outlet side will be protected by stone to avoid erosion.

Page 15: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 14 Revision: A1 December 2014

4) Culvert maintenance needs to be undertaken to any build-up material blocking

culvert inlet.

Figure-8 Typical Arrangement of Pipe Culvert

5.4.2 Open Ditch

1) There are 2 types of the open ditch, type 1 for open ditch without lining, type 2

for open ditch with lining. Lining open ditch shall be applicable to the steep

longitudinal profile (more than 4.5%) area, if necessary.

2) The ditch shall be constructed proper alignment and size as shown in the

approved drawings.

3) The ditch without lining will be observed during construction period, if drainage

surface seriously damaged by water flow, the ditch surface may be covered by

lining or appropriate countermeasure may be done.

4) Inside of a ditch shall be clearing and repair before rainy season if necessary.

Page 16: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 15 Revision: A1 December 2014

Figure-9 Typical Side Open Ditch (* the dimension is tentative)

5.5 Incidentals

5.5.1 Traffic Sign

1) The road T3 is a temporary road, the traffic sign also will be used only during

construction period (Nov. 2018) after that it will be removed. However, the

posts shall be embedded into concrete base and traffic sign shall be set

vertically with enough strength. The damaged sign board shall be replaced

immediately.

5.5.2 Slope Protection

1) Basically the embankment slope shall be protected by sod grasses to avoid

erosion of slope surface. The suitable grass shall be selected and approved by

the Owner. If necessary, the placing stone will be considered in case of severe

conditions.

2) During the construction period, sod slope shall be carried out proper

maintenance.

6. Safety control

Safety control for site works shall be followed to the Section 6, Appendix 2.3-01 and Appendix

2.3-02 of Safety and Security Program (Document No. NNP1-PRG-SSp-A2) in the Contractor

letter NNP1-PCL-00044, dated 10th December 2013.

Especially, during T3 road works area, the following issues shall be concerned.

1) Accident to third party

・For all staffs and worker, the safety training shall be carried out.

・Warning sign board will be arranged.

2) Striking heavy equipment

・Watch man shall be arranged.

・When equipment parks on site, stopper shall be set.

3) Safety measure for rainy season

・To inform all worker “Mind Your Step” and “Slippery Rock Surface”

Page 17: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 16 Revision: A1 December 2014

・When thunderstorm will come, the worker shall evacuate.

Before commencement work, safety training shall be carried out to relevant staffs and

workers. And the emergency action plan is attached in Appendix 9-4.

The safety control on site is changed, revised and added time by time in accordance with the

occurrence of a dangerous situation and the Owner’s comments.

7. QUALITY ASSURANCE

Quality Assurance shall be followed to the Quality Assurance Program (Document No. NNP1-

PRG-DrQAP-A3) in the NNP1-PCL-00086, dated 16th Jan. 2014.

Material testing during construction will be performed by on-site laboratory. And the proposed

Inspection and Test Plans (ITP) are as shown in the Appendix 9.7.

Since the T3 road is temporary road, regarding the inspection and test, only FDT that is

mentioned in the section 5.2.4 & 5.2.5 will be executed.

On the other hand, the dimensions of As-built will be measured and As-built drawings will be

developed for submission to the Owner.

The inspection and test on site shall be informed of the Owner before the implementation.

Page 18: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 17 Revision: A1 December 2014

Part 2

Site Specific Environmental and Social

Management and Monitoring Plan

(SS-ESMMP)

Access Road T3

Page 19: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 18 Revision: A1 December 2014

8 Site Specific Environmental and Social Management and Monitoring Plan 8.1 Introduction

This Site Specific Plan has been prepared to highlight environmental and social conditions prior

to the beginning of each construction activity and will be used as a tool to ensure the particular

construction activity follows the correct management and mitigation procedures. Sub-Plans will

be used to detail mitigation methods for each of the activities associated with the construction or

excavation works.

The following site specific plan is to detail construction of access road T3, which is further

separated into three part; T3a, T3b and T3c, please refer to Working Drawing for further details.

The roads are within the CVC and RCC plant yards in which the earthworks are almost complete.

The purpose of the roads are to link the CVC and RCC plant yards.

Table 8.1 below shows the referential linkages of documents regarding environmental matters in

the NNP1 Project. The Owners (NNP1) documents use references and information from the

Concession Agreement. This SS ESMMP (Contractor) uses references and information from

Owners EIA/ESMMP and Owners ESMMP-CP.

Table 8.1 List of Main Documents and Approving Authority

Item Hierarchy of Documents Approving Authority

1 Concession Agreement GOL

2 NNP1 EIA/ESMMP GOL

3 ESMMP-CP GOL

4 Contractors EMP NNP1

5 SS ESMMP NNP1

The Contractor documents are; Contractors EMP (Item 4) and SS ESMMP (Item5) which have

used applicable information extracted from the Owners documents which are Concession

Agreement (Item 1), NNP1 EIA/ESMMP (Item 2) and ESMMP-CP (Item 3).

All obligations of the contractor are stated in the Civil Works Contract (CWC) which includes

Schedule 9 (Concession Agreement Pass Through Obligations) and is the only governing

document for the Contractor.

8.2 Environmental and Social Pre-Construction Description

The closest village to the Project site is Ban Hatxaykham, approximately 4km distance by

existing road from the CVC/RCC Plant Yard construction area, there will be no direct impact to

this village.

The area is within an active construction area so no there are no impacts to local vegetated areas or agricultural land.

Page 20: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 19 Revision: A1 December 2014

Table 8.2 below is a pre-construction checklist to identify any major environmental impacts

that may occur during road works. After completion of the checklist the Sub-Plans can be

selected accordingly.

Table 8.2 Environmental Assessment Checklist – For Pre Construction

Site Location Access Road T3 within CVC and RCC Plant Yard

GPS Coordinates

T3-A: X=340658.006 ; Y=2062385.485 ; Z=678.000

T3-B: X=340844.057 ; Y=2062307.533

T3-C: X=340947.416 ; Y=2062240.966

Photo See attached

Date 19th of December, 2014

Estimated Area 3,850 SQ.M.

Prepared By Santi Sayakoummane

Checked By Ray John

Site Description Access road T3 are roads which will connect the CVC and

RCC Plant yards

Project Setting Yes No Description

Will the site require UXO clearance? X

UXO clearance for the CVC and RCC Plant area

has already been carried out during earthworks

and excavation

Is there surface water located in

close proximity to the site? X

T3 is approximately 300m on the left bank of the

Nam Ngiep

Is there a village or community

located in close proximity to the site? X

Closest Village is Ban Hatxaykham approx. 3km

east of the site.

Is the site located in a vegetated

area? X Area has already been cleared during earthworks

Is the site located in agricultural

land? X The site is within an existing construction area

Are there any PCR sites in the area? X

However Buddha statues were found in a cave

opposite the temporary bridge. These have since

been relocated using Chance find Procedures

Is there an existing access road to

the site? X Access to the site can be made from road P1

Can the site be viewed from public

viewpoints? X Can be viewed from road T5

Is the site located within an existing

Construction Area? X Roads are within the CVC and RCC Plant yard

Will the site development require the

construction of a sub-camp, office

and storage? (if yes, provide a list)

X Existing sub-contractor will be responsible for the

construction, with machinery already on site.

Page 21: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 20 Revision: A1 December 2014

Other Comments:

Environmental Impacts Likelihood

(Yes/No)

Mitigation measure to be

Implemented

Will the site development result in

increased dust generation at near-by

villages?

No

No villages in close proximity during

construction, however when

transporting machinery through local

villages speed will be limited to 10km/h

to reduce dust.

Will the site development result in

increased noise generation at near-by

villages?

No No villages in close proximity

Will the site development result in

surface water turbidity? No

There are no main rivers along the

alignment. Construction will be during

the dry season

Will site development result in

changes to drainage patterns? Yes

Open ditches will be constructed to

divert surface

Will the site result in erosion? Yes Road surfaces will have side ditches to

minimize erosion

Will vegetation clearing be required? No All vegetation has been cleared during

earthworks

Will the site be setting up hazardous

components? (storage, workshop) No

All hazardous materials will be stored at

worker camps. Mobile fuel trucks will be

used to refuel machinery

Will the site generate waste? Yes Any access soil will be transported to

spoil disposal areas.

Site closure plan

No plan closure plan is available at this time, one will be provided at a closer date.

Page 22: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 21 Revision: A1 December 2014

Figure 1 Shows the current site condition of the beginning of the alignment at T3-A (STA 0+000)

Figure 2 Shows the current site condition of the end of the alignment at T3-A (STA 0+315.70)

Page 23: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 22 Revision: A1 December 2014

Table 8.3 below identifies the relevant list of Sub Plans required for the construction activities being undertaken in the T3 area. The Sub Plans were selected after a review of the following:

Detailed Works Program

Pre-Construction Assessment (as per Environmental Checklist attached)

NNP1 EIA, ESMMP and ESMMP CP Access Road

Table 8.3 Relevant Sub Plans for T3 Access Road

Sub-Plan Item Environmental Social

SP01 Erosion and Sediment Control X

SP02 Water Availability and Pollution Control X -

SP03 Emission and Dust Control X

SP04 Noise and Vibration X

SP05 Waste Management - -

SP06 Hazardous Material Management X

SP07 Vegetation Clearing -

SP08 Landscaping and Re-vegetation - -

SP09 Protected Area Management - -

SP10 Biodiversity Management - -

SP11 Spoil Disposal -

SP12 Quarry and Construction Layout - -

SP13 Unexploded Ordinance (UXO) Survey and Disposal X -

SP14 Construction of Work Camps - -

SP15 Traffic and Access X

SP16 Training Awareness X

SP17 Project Personal Health Program X

SP18 Public Safety X

SP19 Damage to Property and Facilities X

SP20 Emergency Preparedness X

SP21 Cultural Resource X

Detailed descriptions of Sub Plan content and guiding objectives are found in the relevant sections relating to NNP1 Environmental and Social Management and Monitoring Plan. See Contractors ESMMP-CP Access Roads, Appendix 2.1 “Sub-Plan for Civil Works” An Environmental Management Activity Table, including monitoring method and frequency, for access road T3 can be referred to in Appendix 9.12 of the DWP.

Page 24: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 23 Revision: A1 December 2014

8.3 Sub-Plan Detail for T3 Access Road - Environmental

SP01 Erosion and Sediment Control

The control of erosion and sedimentation will be carried out by side ditches and pipe culverts. Mitigation measures for erosion and sedimentation control of slope will include:

An open ditch will be constructed on both sides of the road T3 to divert and collect surface

run-off.

The location of pipe culverts can be referred to the drawing plan

Speed humps will be installed inside of side ditch at 50m intervals to reduce water velocity

during heavy rain periods, allowing sediment to be trapped within the side ditch.

In the case that overflow from side ditches occur the ditch size will be increased or modified

accordingly.

Silt fencing or similar materials may be used depending on site conditions or during the rainy

season.

Weekly inspection are conducted as part of the Contractors Environmental, Health and Safety procedures, and these will include inspections of side ditch and sediment traps. Any maintenance such as clearing of sediment will be at the inspector’s discretion, with frequency of clearing increasing during heavy rain periods.

SP02 Water Availability and Pollution Control Open ditches will be designed to allow water to be diverted, minimizing the potential for

uncontrolled run-off. By diverting turbid surface water run-off this will allow for maximum

infiltration.

All maintenance of excavation machinery shall be conducted at workshops to avoid any

storage of hazardous materials such as oil and fuels on site. The use of re-fueling trucks will

eliminate the need for any fuel to be stored on site.

If repairs need to be carried out on site, an oil pan needs to be used to collect any oil and

reduce spillage.

Temporary toilet/s will be provided on site and workers instructed to use these facilities.

SP03 Emission and Dust Control

Water spraying vehicle will be provided in active construction sites as necessary.

All vehicles, while parked on site, will be required to have their engines turned off.

All workers on the ground will be required to wear the correct PPE such as safety glasses,

ear plugs, and breathing masks if necessary.

Speed limits will be imposed to 25km/h or less for all vehicles to reduce dust along access

roads.

To avoid spillage, haul trucks must not over fill their load.

Page 25: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 24 Revision: A1 December 2014

SP06 Hazardous Material Management

All fuels for road works machinery and excavators are stored at worker camp sites in

specially designed areas.

Mobile re-fueling trucks will be used to reduce the need for fuels to be stored on site.

Discharge of any fuels or oils into the environment will be prohibited

8.4 Sub-Plan Detail for T3 Access Road - Social

SP04 Noise and Vibration

All construction personnel working within the construction area will be provided with hearing

protection if working in noisy condition, defined as greater than 80dBA.

SP13 Unexploded Ordinance (UXO) Survey and Disposal

UXO survey and disposal has been conducted by NNP1 prior to commencing any type of

Project related survey or construction activity.

If any UXO’s are uncovered during earthworks or construction of road T3, all works will stop

immediately and the Owner (NNP1) will be notified. No works will be allowed to resume

without approval from NNP1.

SP15 Traffic and access

Watchmen on the ground will control local traffic and ensure safety of excavators and earth

moving machines.

Regularly monitoring of traffic conditions will be conducted as part of the routine

Environmental, Health and Safety inspection.

Speed limit shall be 10km/h when passing along Project roads

Installation of notice boards near entrance of work site to inform workers and visitors of local

hazards and blasting schedule.

Haul trucks must not be overloaded with excavated material when being transported to

disposal areas

Page 26: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 25 Revision: A1 December 2014

SP16 Training and Awareness All new employees will be required to complete Induction Training from OC/NNP1 prior to

commencing any work on site.

In this training, the Contractor will highlight site regulation/rule, and safety & environmental

issue.

A register of induction training will be maintained and can be provided to NNP1 on request.

Monthly safety mass meetings and joint inspections will be conducted with all top

management and safety staff, and will cover all relevant health and safety issues on site.

Weekly meetings are also conducted to bring further awareness to environmental health and

safety issues.

SP17 Project Personnel Health Program

Regarding the content of Section 6, Part 1 of the DWP, the tool box meeting will be carried

out weekly and before commencement of any new works.

Health Awareness Training has been be carried out for all personnel in the monthly mass

meeting.

A register for each item above can be provided to NNP1 on request.

First aid kits are available on site, and with site supervisor.

Health and safety posters will be visible around construction site.

SP18 Public Safety

Traffic speed signage and notice boards detailing blasting times, will be installed at central

locations.

Training for drivers on safe driving practices has been carried out.

Barriers will be installed to keep workers and visitors away from hazardous areas such as cliff

edges and blasting sites.

SP19 Damage to Properties and Facilities

There are no properties or facilities in the T3 construction area. However, in the case of

material transportation vehicles passing through each village, vehicles shall be limited to

10km/h and care will be taken as not to damage the properties and surrounding facilities.

The contractor shall immediately repair and/or compensate for any damage if the damage is

caused by the Contractor after discussion with the Owner.

SP20 Emergency Preparedness

Referring to the emergency action plan in Appendix 9.4, the emergency response procedures,

emergency contact numbers and communication and reporting procedures will be clearly

displayed and each staff always carry it.

First aid kits will be prepared at each site accordingly.

Hazardous materials will be stored in the permitted area only and according to the instruction

by the authorities,

Firefighting equipment shall be prepared, including fire extinguishers in excavators.

Page 27: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 26 Revision: A1 December 2014

At each construction site, information on emergency response procedures, emergency

contact numbers and communication and reposting procedures (to be implemented in case

of an emergency situation) will be clearly displayed.

All construction personnel will be trained in basic emergency response procedures including

communication and reposting procedures to be implemented in case of an emergency

situation.

Barriers will be installed as soon as is required to exclude access by non-working staff.

SP21 Cultural Resource

According to the EIA document, a preliminary survey of the Project Area was conducted by the

Lao PDR Department of Museums and Archaeology (DMA) in October of 2007. In September

2013 local villagers informed NNP1 of Buddha images located in caves near the NNP1

Temporary Bridge site. On the 30th November 2013 the images were successfully relocated to

the local Temple at Ban Hat Gniun. The relocation was complemented by traditional Buddhist

ceremonies, which involved Lao department and authorities including; Head of Hat Gnuin Village,

Representative from NNP1, Representative from Bolikhamxay Province, and Representative

from Bolikhan District and RMU.

8.5 Chance Find Procedures

Objectives of Chance Find Procedures are to; (a) minimize impacts to resources from all NNP1

related activities and (b) to ensure that any artifacts uncovered are appropriately recorded,

documented and reported to the appropriate line agencies.

If any fossil or cultural item of significance is found the Contractor will promptly give notice to the

owner. This follows the guidelines stated in the Civil Works Contract “CWC” Clause 4.25

regarding Fossil and Artifacts. The Contractor will work with Owner to ensure safe removal of the

artifacts, as directed by the Owner who will implement Chance Finds Procedures with a variation

order.

Chance Find Procedures mentioned in the Contractors ESMMP-CP Sub-Plan, Appendix 2.1

Sub-Plan for Civil Works, “21: Cultural Resources” also states the following steps will be

implemented in the event that previously unidentified artifacts are identified:

(i) The Contractor shall immediately cease operations where artifacts /archaeological finds

are unearthed and immediately inform NNP1Site Manager.

(ii) The Owner will consult the Head of Village and Culture and Tourism Administration

Office to obtain advice regarding the next steps.

(iii) The contractor to recommence work only after the Culture and Tourism Office has

provided official notification accordingly.

Page 28: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Construction of Access Road T3

NNP1-MS-RW038-A1

OBAYASHI CORPORATION Page 27 Revision: A1 December 2014

9 APPENDIX 27

9.1 Organization of Road Work (Road T3)

9.2 Construction Schedule (Road T3)

9.3 Working Drawings (Road T3)

9.4 Emergency Action Plan

9.5 Resource (Road T3)

9.6 Procurement Schedule (Road T3)

9.7 Inspection and Test Plan

9.8 Environmental Management Active Table

9.9 Layout Plan for RCC Plant and T3 road

10.0 Original Layout Plan of T3 Road

Environmental Management Active Table The Appendix 9.8, working drawing will be

submitted separately.

Page 29: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Appendix 9.1

As of 18th November 2014

Ray John C Senato

Suthasinee Thaebthao

Souaxiong Briatu

(worker supply)

Nguyen Tan Luc

Seiji Nagasaka

Environmental SpecialistSanti Sayakoummane

CONSTRUCTION SECTION

Bounlone Phomphakdy

Hua Tan Tai

Sakda Pongsuk

Tinnawit Sriputthirat

Civil Engineer

Nguyen Duc Tuyen

Hoang Dinh Noi

Huynh Ngoc Quyen

Deputy Construction Manager Deputy Construction ManagerMitsuo Fukatsu Hiroyuki Iyota

Chief Engineer Chief Engineer

Assistant QS Engineer

Construction Manager

Keiji Sasaki

QC Test Helper

Maintenance

Nguyen Huu Tri

To Hoang Anh

Surveyer

Store Keeper

Fuel Controler

Material Control

Nguyen Ngoc Quang Huy

Civil Engineer

Survey

Civil Engineer

Assistant Surveyer Assistant Surveyer

Nguyen Tri Tuc

Phaimany Lounthone

Nguyen Gia Hieu

SupervisorNgo Van Luan

Kittiphas Moonmueang

Wittaya PhuanginSupervisor

Kham Nammavong

(Grouting)

Civil EngineerHoang Hai Duong

Civil Engineer

Dante Bello Anastacio

Chief Engineer

Michael M. Adducul

(Excavation / Diversion)

(Tunnel) (Structure)

(Excavation & Dam Body) (Powerhouse)

Nguyen Hong Minh

Alexander T. Audian

(RCC/CVC Plant)

Pham Hai Duong

Toshihiko Tange Nguyen Ngoc LiemNguyen Ahn Quoc

Chief EngineerChief EngineerVu Minh Duc

(Structure)

ORGANIZATION CHART

Project Manager

Kazuhiko Chabayashi

Issara Burakhorn

Tran Quang Hop

M & E Manager

Main Dam Construction M & E

Chief Engineer M&E Chief Engineer

Ryuichi Miyanohara

Ho Phi Hoang

Bui Xuan Thai

Supervisor

Ho Cong Minh

Anousone Haoonechanh

Supervisor

Assistant

Nguyen Doan Minh Quan

Assistant

Supervisor

SupervisorSupervisor Supervisor

Mechanical Engineer Erectrical EngineerCivil Engineer Civil Engineer

Civil Engineer

Konglor Sotouky

Shopheap NounNgo Thanh Danh Ha Bac Son Nguyen Minh Thien

Le Anh Tu

Civil Engineer

Tran Anh Tuan

Supervisor Supervisor

Civil Engineer

Truong Nguyen Di Khuong

Ananhxay Insiziengmai

Deputy Construction Manager

Construction ManagerTakanobu Ishii

Civil EngineerPhaivan Xayyavong

Chief EngineerHisashi Nagasima

Road T4, T7 ~ T11

Yoshitake Higuchi

Civil EngineerPhanmaha Ekalath

Salurmseng Sayjoumoua

Civil EngineerThinkonenapha Sybounhueang

Road P1, Camp Yard

RCC/CVC Plant

Office Engineer

Sombath Khamtayang

Tomohiro Taguchi

Tran Anh Kiet

QC Assistant

Nguyen Cam Nhung

Assistant

Nguyen Thi Hoang Minh

Nguyen Viet Thu

Quarry /

Aggregate Plant

Chief Engineer

Luong Ngoc Loc Luong Pham Duy

QC EngineerQS Engineer

Chief Contract EngineerChief QC EngineerChief QS Engineer

Public RelationContract assistanatDoc. ControllerTran Anh Tuan

CAD Operator

Diversion Tunnel

Boutsakorn Somphanthabansouk

Loley Xayouthone

Safety & Envi. Officer

Chief Engineer

Vanhxay Sengsavang

ADMINISTRATION SECTION

Admin. Manager

Makoto Harada

Chief Admistrator

SAFETY & ENVIRONMENTAL

Shion Ishiguro

ClinicPurchase/LogisticsAccount/Finance General Affair

Takayuki Kimura

Engineering Manager

Shop Drawing

ENGINEERING SECTION

Deputy Eng. Manager

ContractQuality Control

(Laboratory)Document ControlQuantity Survey

Accountant DoctorPurchaser

Souksamone Souliyamath Chimdavong Thepkhamheuang

Maid

Lao & Foreign Staff House

Nurse

Cook

Somboun Chanthavong

AdministratorSoudsakhone Phomarinh

Khamfong Chanthabouly

Sounthala HinpaseuthDavone Sisuvong

Air Lorwansai

DriverJP Staff House

Admin Clerk

CookThongxay Xayyasan

Khamdy Khamsy

Air KhamAdmin AssistantYeng Leenhiavue

Ningthida Vilamongkhoun

Bounom Thammavong

Manothai Phaxaysisounon

Le Minh Truc

Ho Van Quoc

Cook Assistant

Maid

Account Assistant

Vinut Vongphouthone

Soudsada Khounphanya

Construction ManagerAkio Igarashi

Construction Manager

Trinh Ngoc Viet

Chief Engineer

Civil Engineer

Chief Engineer Chief Engineer

Chief Engineer Chief EngineerSaikham Vanpaseuth

Civil EngineerVo Anh Pha

Nguyen Van Trung

Le Tien Hoa

(OBC Building Works)

Nguyen Binh PhuongKeita Tamura

Civil Engineer

Do Van Khanh

Le Duc Chuyen Jedsada Sanggred

Khaiphone Sengmany

Sergio M. Adducul Jr.

Moneta Khounphachan

Veow Boulikhan

Phouvong Sanyanouvong

Cook AssistantBounpheng Xayyasan

Nguyen Tri Phuong Thanh

Khamhou Bounyavong

Nguyen Ly Kim Ngan

Road A, Road P1

Takeo Tsuchihashi

Deputy Construction Manager

Maintenance

Office MaidBoualay Thamavong

Phomma Phongoudon

Bounphone Sipaserth

Road P2,

Road T1, T2, T13Temporary Brigde

Khonesavanh Keophaserth

Re-reguration Dam / Dyke

Survey Helper

Songpol Janoh

(worker supply) (worker supply)

Survey Helper Survey Helper

Dao Van Nam Tran An Khanh

Surveyer Surveyer

Chief Engineer

Nguyen Ngoc Duan

Nguyen Van Tung

Assistant Surveyer

Office Engineer

Road Work Section

Sub-contractor for T3 Road Construction

Meuang Van Development Co., Ltd.(Refer to the section 4.2 Nominated Subcontractor and Manpower distributionin this method statement)

Page 30: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works program for Construction of Access Road

Appendix 9.2

9.2 Construction and Environmental Mitigation Schedule of T3 Road Construction

27 28 29 30 31 1 2 3 4 5 6 7 8 9 10ConstructionSurvey Work (T3-A, T3-B and T3-C) 6,215.00 m2Pipe Culvert Work 2.00 locationSub-base course Work (T3-A, T3-B and T3-C) 1,155.00 m3Open ditch Work 1,100.00 mEnvironmental MitigationErosion and Sediment ControlNouse and VibrationHazardous Material Management Vegetation ClearingSpoil DisposalTraffic and AccessTraining and AwarenessProject Personnel Health programPublic Safety

Note) 1. In case that the delay is observed, the countermeasure shall be considered immediately.2. Q'ty is estimation. Base on site condition, it will be changed. And the materials for road maintenance is excluded.3. Above schedule is not included the period of maintenance. The maintenance works will be done untill the completion of Re-Regulation Dam works.

SP-15SP-16SP-17SP-18

SP-01SP-04SP-06SP-07SP-11

4

23

December

1

No. Description Q'ty Unit

Page 31: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Access Road

Appendix 9.3

OBAYASHI CORPORATION Revision : A1

Appendix 9.3

Working Drawings

for Road T3 (Temporary Access Road)

Working drawing will be submitted separately.

Page 32: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

Detailed Works Program for Access Road

Appendix 9.4

Rev. A4 As of 23th September 2014

020-5551-4891

Dr. Rie Ogiwara

Mobile : 020-5559-9502

InstructionThaheua Mr. Boonhieng 020-5549-1810

Embassy of JapanMedical Attaché

Person to Take Action Hat Gniun Mr. Phouvieng

Embassy of JapanUrgent Case

Helicopter

020-5977-4434

Hatsaykham Mr. Phonsysong 030-5738-860

Head of Villagers of Relevant Villages

Name of Head Contact No.

Nonsomboun Mr. Touy Inthavong 020-5614-9468Lao Skyway

Tel : 021-512-027

Report (if necessary) Name of Village

Project Manager

Mr. Chabayashi

OBAYASHI Corporation

Overseas Division (Tokyo)

+81-3-5769-1254Hospital (Thai)Bangkok Hospital

Udon Thani

+66-42-343-111Emergency : Mr.Prayoon Thavon( John)

(International Marketing Executive)

Mobile: +66-85-010-6338

Immigration (Lao)Mr.Sykhamxay

Mobile: 020-2343-4666

Hospital (Thai)Bueng Kan Hospital

+66-42-491-161~3 (ext. 295) (24hrs)Emergency :Ms.Sunan Nokthong

(Chief Nurse)

Mobile: +66-86-857-8279

Immigration (Thai)Pol.Lt.Col. Wallop Khunmuan

Mobile: +66-81-616-1100

BoatMr.Mone

Mobile : 020-2233-9943

Report

Deputy Managing Director

Mr. Tsutsui

Emergency Assistance Japan +81-3-3811-8153RMU

Resettlement Management Unit

Deputy Director

Mr. Khamsing Sayphouvong

020-2233-5546 Hospital / Immigration / Embassy / OthersSafety Chief Engineer

Hospital (Lao)Bolikhamxay Provincial Hospital

054-212-154 (8:00 - 16:00)Emergency 24Hrs. Tel : 054-212-099

Construction Manager

(Japanese)Managing Director

Mr. Yamabayashi

Embassy of Japan

021-414-400AmbulanceBolikhamxay Provincial Hospital

054-212-149 (8:00 - 16:00)Emergency 24Hrs. Tel : 020-5508-4966

Administration Manager

Mr. HaradaFire Station

191

Site Engineer

Mr. Ishiguro 020-59-888-217Dept. of Environment

054-790-836

Mr. Dodo 020-22-422-582

Mr. Kimura 020-59-888-204

Mr. Nagasaka 020-59-888-205Pakxan POLICE

054-280-190

054-212-256 Mr. Tsuchihashi 020-59-888-206

Discoverer

Mr. Harada 020-59-888-208EDL

054-280-308

Mr. Ishii 020-59-888-213

Mr. Tsutsui 020-55-566-959Not Only Accident,

Also Environmental Incident/HazardObayashi Corporation

Pakxan Office 054-790-686

Mr. Chabayashi 020-59-888-201

Mr. Yamabayashi 020-59-565-888

Emergency Plan for Nam Ngiep 1 Hydropower ProjectOBAYASHI Corporation

Nam Ngiep 1 Power Company

Pakxan Office 054-280-168

VTE Office 021-265-185

ACCIDENT

INCIDENT

TAKE ACTION- Send injured person to hospital- Urgent countermeasure- Inform and explain to authorities- Record

Page 33: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Temporary Road

Appendix 9.5

9.5 RESOURCES

27 28 29 30 31 1 2 3 4 5 6 7 8 9 10

1 Road T3 Temporary Road ( L= 550M)Excavator 1 1 1 2 2 2 2

(T3-A, T3-B and T3-C) Bulldozer 1 1 1 1 1 1 1 1 1

Road Grader 1 1 1 1 1 1 1 1 1

Vibratory Roller 2 2 2 2 2 2 2 2 2 2 2

Dump Truck 1 1 3 3 3 3 3 3 3 3 3 3 3

Manpower (excl. Operator) 6 6 6 6 6 6 6 6 6 6 6 6 6

Surveyor 2 2

OBAYASHI CORPORATION

December January2014 2015

1

DayItem Location Resource

PartyYear

Month

Page 34: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Access Road

Appendix 9.6

9.6 PROCUREMENT SCHEDULE

Road T3 : Temporary road

1 2 3 4 5

1 RC Pipe Dia. 600-800mm m 70 15

1) T3 Road is temporary road, therefore, the Contractor will check the quantity and quality of delivered materials/

2) In case of permanent road construction, the inspection will be executed base on ITP in Appendix 9.7 when permanent material will be delivered on site.

OBAYASHI CORPORATION Revision : A1

No. Item AmountWorking Month

UnitRemarks

Page 35: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NAM NGIEP 1 HYDROPOWER PROJECT Detailed Works Program for Access Road

Appendix 9.7

S/C OC Own

2 EARTHWORK

Visual Inspection & Survey of Prepared

Subgrade TS 8.2 Visual inspection / survey Accordance with TS 8.2 I I R At Site Prior to placing subbase in each area. Checklist

Compaction TS 8.3.4 ASTM D1556 (AASHTO T191) Accordance with TS 8.3.4 I I R Field Labo.Once prior to commencement;

and then 1time/1,000m2Checklist

Finishing Condition Visual Check Good Practice I I R At Site @ Each Location Checklist

Dimension Measurement As Approved Shop Drawings I I R At Site @ Each Location Checklist

3 PAVEMENT

Receive Subbase Material TS 8.3.4 Visual inspection Accordance with TS 8.3.4 I I R At Site For each delivery. Checklist

Spreading & Compaction Test for

SubbaseTS 8.3.4 ASTM D1556 (AASHTO T191) Accordance with TS 8.3.4 I I R At Site

Once prior to commencement;

and then 1time/1,000m3Checklist

Visual Inspection & Survey of Prepared

Subbase TS 8.3.4 Visual inspection / survey Accordance with TS 8.3.4 I I R At Site Prior to placing per each area Checklist

Legend: S/C: Subcontractor & Supplier Accredited Laboratories:

OC: The Contractor (Obayashi)

Own: The Owner (NNPC)

H: Hold Point

I: Inspection

W: Witness by Owner (optional)

R: Document Review

Note ) For the construction of Road T8, only FDT will be carried out. (Refer to section 5.2.4 & 5.2.5)

3. TBA

Subbase3.1

Name Address

1. TBA

Subgrade2.1

2.2 Excavation

2. TBA

Testing / Inspection

ItemsRemarks

Inspection by

Acceptable CriteriaTesting

LocationDescription (Properties to be tested) Specification Inspection and Test Method

Verifying

DocumentFrequency

9.7 INSPECTION AND TEST PLAN FOR ROAD WORK

Item

OBAYASHI CORPORATIONRevision : A1

Page 36: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NNP1 HYDROPOWER PROJECT Environmental Management Activity Table Access Road T3 Appendix 9.8

OBAYASHI CORPORATION Revision: A1 December 2014

Environmental Management Activity Table for Access Road T3

Sub-plan Item Monitoring

Method

Monitoring

Frequency On-Site Implementation

SP01 Erosion and Sediment

Control Visual

Weekly or Heavy

rain

An open ditch will be constructed on both sides of the road T3 to divert and collect surface run-off.

Speed humps will be installed inside of side ditch at 50m intervals to reduce water velocity during

heavy rain periods, allowing sediment to be trapped within the side ditch.

In the case that overflow from side ditches occur the ditch size will be increased or modified

accordingly.

Silt fencing or similar materials may be used depending on site conditions or during the rainy

season.

SP02 Water Availability and

Pollution Control

Visual

Weekly

Open ditches will be designed to allow water to be diverted, minimizing the potential for uncontrolled

run-off. By diverting turbid surface water run-off this will allow for maximum infiltration.

All maintenance of excavation machinery shall be conducted at workshops to avoid any storage of

hazardous materials such as oil and fuels on site. The use of re-fueling trucks will eliminate the

need for any fuel to be stored on site.

If repairs need to be carried out on site, an oil pan needs to be used to collect any oil and reduce

spillage.

Temporary toilet/s will be provided on site and workers instructed to use these facilities.

SP03 Emission and Dust Control Visual Daily

Water spraying vehicle will be provided in active construction sites as necessary.

All vehicles, while parked on site, will be required to have their engines turned off.

All workers on the ground will be required to wear the correct PPE such as safety glasses, ear

plugs, and breathing masks if necessary.

Speed limits will be imposed to 25km/h or less for all vehicles to reduce dust along access roads.

To avoid spillage, trucks will not over fill their load.

SP04 Noise and Vibration Visual Each time All construction personnel working within the construction area will be provided with hearing

protection if working in noisy condition, defined as greater than 80dBA.

SP06 Hazardous Material

Management Visual Weekly

All fuels for road works machinery and excavators are stored at worker camp sites in specially

designed areas.

Mobile re-fueling trucks will be used to reduce the need for fuels to be stored on site.

Discharge of any fuels or oils into the environment will be prohibited

SP13 Unexploded Ordnance

(UXO) Survey and Disposal Visual Each time

UXO clearance has been carried out within the T3 site by NNP1 before the beginning of any

construction activities.

If any UXO’s are uncovered during earthworks, all works will stop immediately and the Owner

(NNP1) will be notified. No works will be allowed to resume without approval from NNP1.

Page 37: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

NNP1 HYDROPOWER PROJECT Environmental Management Activity Table Access Road T3 Appendix 9.8

OBAYASHI CORPORATION Revision: A1 December 2014

Sub-plan Item Monitoring

Method

Monitoring

Frequency On-Site Implementation

SP15 Traffic and Access Visual Routine

Watchmen on the ground will control local traffic and ensure safety of excavators and earth

moving machines.

Regularly monitoring of traffic conditions will be conducted as part of the routine Environmental,

Health and Safety inspection.

Speed limit shall be 10km/h when passing along Project roads

Installation of notice boards near entrance of work site to inform workers and visitors of local

hazards and blasting schedule.

Haul trucks must not be overloaded with aggregate material

SP16 Training and Awareness Visual / Verbal Routine

All new employees will be required to complete Induction Training from OC/NNP1 prior to

commencing any work on site.

In this training, the Contractor will highlight site regulation/rule, and safety & environmental issue.

A register of induction training will be maintained and can be provided to NNP1 on request.

Monthly safety mass meetings and joint inspections will be conducted with all top management and

safety staff, and will cover all relevant health and safety issues on site.

Weekly meetings are also conducted to bring further awareness to environmental health and safety

issues.

SP17 Project Personnel Health

Program Visual / Verbal Routine

Regarding the content of the Section 6 of the DWP, the tool box meeting will be carried out before

commencement of any works.

Health Awareness Training will be carried out for all personnel in the monthly mass meeting.

First aid kits shall be prepared at site.

SP18 Public Safety Visual / Asking Routine

Traffic speed signage and notice boards detailing blasting times, will be installed at central locations.

Training for drivers on safe driving practices has been carried out.

Barriers will be installed to keep workers and visitors away from hazardous areas such as cliff edges

and blasting sites.

SP19 Damage to Properties and

Facilities Visual Routine

There are no properties or facilities in the T3 construction area. However, in the case of material

transportation vehicles passing through each village, vehicles shall be limited to 10km/h and care

will be taken as not to damage the properties and surrounding facilities.

The contractor shall immediately repair and/or compensate for any damage if the damage is caused

by the Contractor after discussion with the Owner.

SP20 Emergency Preparedness

Visual

Weekly

Referring to the emergency action plan in Appendix 9.1, the emergency response procedures,

emergency contact numbers and communication and reporting procedures will be clearly

displayed at construction area

First aid kit shall be prepared on site and in Sub-Contractor vehicles.

SP21 Cultural Resource Visual Each time

If the Contractor is to find any new physical or cultural resources during T3 construction, the

Contractor shall stop the works and inform the Owner immediately and follow the Chance Find

Procedures.

Page 38: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

3

7

0

0

3720

3740

Open Ditch

outside

Open Ditch

inside

Laboratory

Stone Powder

Granding Machine

178

5~10mm

Aggregate

9

2

5

m

3

10~15mm

Aggregate

7

3

5

m

3

Open Ditch

Both Sides

3

5

8

0

3

6

8

0

EM YARD

2400M2

3

6

0

0

3

6

2

0

3

6

6

0

3

6

4

0

3

5

2

0

3

5

0

0

3

5

6

0

3

5

4

0

HM YARD

5000M2

Road A =

Open Ditch

(both sides)

Open Ditch

(both sides)

Open Ditch

Both Sides

L=315.70M

L=125.00M

L=109.30M

LAYOUT PLAN RCC PLANT AND T3 ROAD

No

REVISIONNo. DESCRIPTION DATE ENGINEER:

CONTRACTOR:

DESIGNED

DRAWN

CHECKED

APPROVED

DRAWING NO.SCALE:

TITLE

NAM NGIEP 1 HYDRO POWER PROJECTNAM NGIEP 1 POWER COMPANYOWNER:

OBAYASHI CORPORATION

TITLE NAME DATE

REVA1

Page 39: NNP1-MS-RW038-A1 - Nam Ngiep 1 Power Company€¦ · NNP1-MS-RW038-A1 OBAYASHI CORPORATION ... 5.4.1 Pipe Culvert 14 ... First of all, the access roads are divided as the following

Road Name Start point Mid point End point

P1 (To Dam Top) A T1, B, A1, E, I, A2, S P

P2 (To Power house) E G, H, W N

T1, T2 (Haul road EL 230 and 250m) I V O

T3 (RCC & CVC plant road) G - D

T4 (Upstream uproach road) P - Q, R

T5 (Temporary access road) B - H

Road Name Start point

T7 (Haul road to dam top) J

T8 (Soil disposal road) F

T9 (Haul road to quarry) F

T10, T11 (Haul road EL 200 and 230m) K

T6 (Jetty road) H

Length

9.32km

1.84km

1.58km

0.55km

3.88km T12 (Temporary Road ) S

1.94km

Mid point End point

U

M

- C

- K

- L

- T2

Length

0.20km

1.54km

3.20km

1.00km

0.72km

1.68km

T13 (Temporary Road ) V - W 0.52km

-

-

JICA Road A T1, B, T2 X 9.25km

NAM NGIEP 1 HYDRO POWER PROJECT

CONTRACTOR:

NAM NGIEP 1 POWER COMPANYOWNER:

OBAYASHI CORPORATION

TITLE:

ORIGINAL LAYOUT FOR T3 ROAD

Appendix 10.0