NIZWA-JIBREEN ROAD, SULTANAT OMAN Facts Project Description The construction of the project consists of the dualization of 12.5 km single road and a new alignment of two carriageways of 19.5 km length. The pavement layers are of 40 mm bituminous wearing course, 60 mm bituminous base course, 250 mm crushed aggregate base course and construction of box and pipe culverts and Irish crossings. The project is located in Ad Dakhliya Region, starts from the end of Rusayl-Nizwa road (Section III) and ends at Jibreen by passing Nizwa and Bahla towns. Quantities: Length of road 32 km Width of road 26.9 m Earthworks 2,149,996 m³ Granular subbase 147,563 m³ Aggregate base course 201,000 m³ Bituminous wearing and base course 144,960 tons Asphalt 59,876 m³ Concrete 21,291 m³ Rip rap 23,482 m³ Gabions 600 m³ Pipe culverts 360 m Safety barriers 68,000 m City/Country Nizwa-Jibreen / Oman Client Ministry of Transport and Communication Contract Value € 22,70 Mio. Construction Period 9/2005 - 1/2010 (52 months) .

Upload: others

Post on 11-Jun-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NIZWA-JIBREEN ROAD, SULTANAT OMAN · 2016. 6. 29. · NIZWA-JIBREEN ROAD, SULTANAT OMAN Facts Project Description The construction of the project consists of the dualization of 12.5

NIZWA-JIBREEN ROAD, SULTANATOMAN

Facts Project DescriptionThe construction of the project consists of the dualization of 12.5 km single road and a newalignment of two carriageways of 19.5 km length. The pavement layers are of 40 mmbituminous wearing course, 60 mm bituminous base course, 250 mm crushed aggregatebase course and construction of box and pipe culverts and Irish crossings.The project is located in Ad Dakhliya Region, starts from the end of Rusayl-Nizwa road(Section III) and ends at Jibreen by passing Nizwa and Bahla towns.

Quantities:Length of road 32 kmWidth of road 26.9 mEarthworks 2,149,996 m³Granular subbase 147,563 m³Aggregate base course 201,000 m³Bituminous wearing andbase course 144,960 tonsAsphalt 59,876 m³Concrete 21,291 m³Rip rap 23,482 m³Gabions 600 m³Pipe culverts 360 mSafety barriers 68,000 m

City/Country

Nizwa-Jibreen / Oman

Client

Ministry of Transport and Communication

Contract Value

€ 22,70 Mio.

Construction Period

9/2005 - 1/2010 (52 months)

.