nitrogen rejection unit design options
TRANSCRIPT
Nitrogen Rejection Unit Design Options
©2019 ConocoPhillips CompanyOptimized Cascade® is a registered trademark of ConocoPhillips Company
in the United States and certain countries
ConocoPhillips LNG Engineering & Operations
2
ManagerFilippo Meacci
LNG Conceptual Process Engineering Supervisor
LNG Operations SupervisorLNG Process Engr. & Tech. Support Supervisor
Engineering FellowWes Qualls
Principal Process Engineer
Principal Process Engineer
Staff Process Engineer
Staff Process Engineer
Staff Process Engineer
Staff Process Engineer
Principal Process Engineer
Staff Process EngineerStaff Process Engineer
Senior Process Engineer
Presentation Overview
3
What is a Nitrogen Rejection Unit (NRU)? When is an NRU Required? Where in the LNG Process is the NRU? Key Points Options
Warm NRU Cold NRU Refluxed Third Column
Nitrogen Rejection Unit – Key Points
What is an NRU A Nitrogen Rejection Unit (NRU) Separates and Vents Nitrogen (N2) to the Atmosphere, While
Returning Recovered Hydrocarbon Streams to the Main Liquefaction Process or Routing to Fuel Two to Three Fractionation Columns are Combined With two or More Multi-Pass Brazed
Aluminum Heat Exchangers, Usually Within a Cold Box. The Atmosphere Contains About 78 mol% N2
When do You Need and NRU An NRU is Typically Required When Feed N2 Concentrations Exceed the Amount that can be
Rejected to Fuel. Higher Fuel Gas Requirements Results in Greater Ability to Displace N2. Typically if Feed Gas Contains >1.5 mol% N2 (Downstream of Acid Gas Removal Unit),
Depending on Fuel Requirements
Where do You Place an NRU Typically Located on the End Flash of Competing LNG Technologies Integrated into the Methane Refrigeration System for the Optimized Cascade Process
4
Cryogenic NRU Processes are Highly Heat Integrated
NRUs Within LNG Facilities are Typically Cryogenic Auto-refrigeration Processes.The Pressure Reduction of each Successive Column Bottoms Liquids Results in Lower
Temperatures, Which is Then Used to Condense the Successive Column Feed Streams.
Typical N2 Vent Purity Specifications for Methane (C1) are ≤1 mol%.Options to Reduce C1 in the Vent Include Additional NRU Equipment or Thermal or Catalytic
OxidationThe N2 Vent May be Further Processed to Recover Helium
Typical LNG Products Specifications for N2 are ≤1 mol%Typical Optimized Cascade Project LNG N2 Concentrations are Lower than 0.5 mol%.
5
Nitrogen Rejection Unit – Key Points
NRU Options Within Optimized Cascade LNG Process
6
Warm NRU High Efficiency No Dedicated Rotating Equipment for Feed or Product Streams Required
• Third Column Bottoms Pump Optional Less Heat Integration With Main Liquefaction Facility
• Ability to Bolt On at Later Date (Future N2 Case)
Cold NRU Higher Efficiency Higher Stability No Dedicated Rotating Equipment for Feed or Product Streams Required
• Third Column Bottoms Pump Optional Faster Controls Response More Heat Integration With Main Facility
• Rapid Startup Times• Responds Quickly to Changes in Feed N2
Option Available for All Stainless Steel Exchangers Refluxed Third Column
Strict Restrictions on C1 in N2 Vent
Auto-Refrigeration Provides Natural Process Feedback
With Feedback, NRU Feed Disturbances Can Result in Even Greater NRU Feed Disturbances
Variations in Temperature, Pressure, Concentration & Flow Should be Avoided if Possible
Auto-Refrigeration Processes are Time Consuming to Cooldown and Startup
7
The Key to Successful NRU Design is Understanding & Mastering Feedback
8
Variable NRU Feed Conditions Result in: Variable Vapor/Liquid Flows to HS Column Variable HS Column Levels
Variable HS Column Levels Results In: Variable HS Column Bottoms Liquid Flow Variable Condensing Duty For HS Column Feed Variable Flow Rates to IS Column Variable IS Column Levels
Variable IS Column Levels Result in: Variable IS Column Bottoms Liquid Flow Variable Condensing Duty for IS Column Feed Variable Flow Rates to LS Column Variable LS Column Levels
Variable LS Column Levels Result in: Variable LS Column Bottoms Liquid Flow Variable Condensing Duty for LS Column Feed Variable N2 Vent Flow & Composition
Traditional Warm NRU Feedback Cycles – Typical for Industry
Mastering Feedback
9
Process Design Details Correctly Identify Stream Flow Regimes Layout Equipment to Avoid Slug Flow (Especially Riser Slugging) Include Sufficient Vessel Residence Time
Instrumentation & Controls Design Details Select Proper Control Valve Trim for Application Include Temperature, Pressure & Flow Indication for Controls Philosophy Select the Most Sensitive Locations for Temperature Control Include Sufficient Piping Straight-Run Distances for Equipment & Flowmeters Feed Forward Decouple Controls to Minimize Feedback Disturbances
Optimized Cascade Cold NRU Approach
Cold NRU Design
11
US Patent 9,335,091 B2
Heat Integration with Main Liquefaction Plant to Avoid Auto-refrigeration Feedback
Cold NRU – Key Design Principles External Refrigerant From Main Liquefaction Unit Used to Condense HS Column Feed
Traditional NRUs Condense Feed with Recycled Column Bottoms Liquid. Feedback (Auto-refrigeration)
External Heat Source From Main Liquefaction Facility Used to Reboil HS Column Traditional Warm NRUs Utilize the NRU Feed to Provide HS Column Heat Duty
Condensed HS Column Reboiler Heat Duty Stream Routed to Main Liquefaction Plant The Heat Duty Stream Utilized Would Normally be Condensed & Routed to LNG Regardless Reboiler Duty Does Not Require Additional Process Heat Removal
HS Column Bottoms Liquids Routed to Main Liquefaction Plant With Little Pressure Loss Traditionally Bottoms Liquids are Flashed to a Lower Pressure to Utilize the Lower Temperatures as Feed Condensing Duty Traditionally the Liquids Flashed to Lower Pressures Requires Vaporization, Superheating, Compression & Recondensing
External Refrigeration & Heat Duty Provides Direct and Rapid Controls Response Condensing Duty for Traditional Warm NRUs Incurs Feedback Delay
External Refrigeration & Heat Duty Provides Better Control of the HS Column Overhead Composition Anchoring the Overhead Composition Minimizes Feedback Disturbances For Remaining Downstream Columns
12
13
Variable NRU Feed Conditions DO NOT Result in: Variable Vapor/Liquid Flows to HS Column Variable HS Column Levels
STABLE HS Column Levels Results In: Variable HS Column Bottoms Liquid Flow STABLE Flow Rates to IS Column
Variable IS Column Levels Result in: Variable IS Column Bottoms Liquid Flow Variable Condensing Duty for IS Column Feed Variable Flow Rates to LS Column Variable LS Column Levels
Variable LS Column Levels Result in: Variable LS Column Bottoms Liquid Flow Variable Condensing Duty for LS Column Feed Variable N2 Vent Flow & Composition
NRU High Stage (HS), Interstage (IS) & Low Stage (LS) Feedback Cycles
HS Column Adjusts to Fix Composition to IS and LS Columns to Minimize LS Column Feedback
Summary Pros & Cons of Cold NRU
Pros Faster & Easier to Cool Down
Feed to NRU is Already Cold Cool Down as Quickly as LNG Facility
More Stable, Flexible & Reliable Downstream Column Feedback Eliminated Faster & More Direct Controls ResponseAbility to Anchor HS Column OH CompositionOne Multi-pass Exchanger EliminatedAllows for all Stainless Steel Equipment
Higher Thermal Efficiency Feed to NRU Already Cold Some Liquid Products Dumped to LNG Rather Than
Re-vaporized and Recycled
Cons Additional Equipment Required
External Feed Condenser External Bottoms Reboiler
Additional Integration With LNG Facility Less Conducive to Later Bolt-on Approach Than
Warm NRU Design (Future N2 Case)Higher Cost – Additional Equipment Equipment & Piping Layout and Hydraulics With
Remaining Facility Requires More Design Attention to Detail
Nitrogen Rejection Unit Design – Simplified Decision Chart
15
Nitrogen Rejection Unit Options
Little Nitrogen Moderate Nitrogen
Stable Concentration
Significant Nitrogen
Reject to Fuel
Warm or Cold NRU
Cold NRU
Variable Concentration
Cold NRU
Future Nitrogen Case
Warm NRU
Optional Refluxed Third NRU Column Designs Available for Both Warm And Cold NRUs for Improved Vent Purity Control
Licensed Optimized Cascade Process – Warm & Cold NRUs
16
Kenai LNG1.5 MTPA, 1969
Corpus Christi LNG13.5 MTPA, 2018
Atlantic LNG14.8 MTPA, 1999-2005
Egypt LNG7.2 MTPA, 2005
Darwin LNG3.7 MTPA, 2006
Equatorial Guinea LNG3.7 MTPA, 2007
Angola LNG5.2 MTPA LNG, 20131.7 MTPA NGL
Queensland Curtis LNG8.5 MTPA, 2014 -2015
Gladstone LNG7.8 MTPA, 2015
Wheatstone LNG8.9 MTPA, 2017 -2018
Australia Pacific LNG9.0 MTPA, 2015 - 2016
Sabine Pass LNG22.5 MTPA, 2015 -2018
Warm NRUCold NRU
Conclusions
17
NRU Options Available for Wide Range of Compositions No Rotating Equipment on Feed or Product Streams
• Bottoms Pump on Third Column Optional Warm NRU Option
• Small Amounts of N2
• Future N2 Cases (Bolt-On Solution) Cold NRU
• Moderate to Large Amounts of N2 From Outset of Design Refluxed NRU Options
• Strict N2 Vent Purity Requirements
Stable Operation (All Options) Through Design Attention to Detail
• Equipment• Piping• Controls
N2 Vent Purity Requirements Achieved
Discussion