IMPROVED SIZE AND EFFORT ESTIMATION MODELS
FOR SOFTWARE MAINTENANCE
by
Vu Nguyen
A Dissertation Presented to the FACULTY OF THE USC GRADUATE SCHOOL
UNIVERSITY OF SOUTHERN CALIFORNIA In Partial Fulfillment of the
Requirements for the Degree DOCTOR OF PHILOSOPHY
(COMPUTER SCIENCE)
December 2010
Copyright 2010 Vu Nguyen
-
ii
DEDICATION
Knh tng ba m,
Nguyn nh Hong, Nguyn Th Thin
You survived and struggled through one of the darkest chapters in the history of Vietnam
to raise and love your children.
-
iii
ACKNOWLEDGEMENTS
I am deeply indebted to my advisor, Dr. Barry Boehm, for his encouragement,
support, and constructive advice. I have learned not only from his deep knowledge and
experience in software engineering but also from his remarkable personality. I would also
like to thank A Winsor Brown who brought me to work on the CodeCount project and
make the tool more useful for the software development community.
I am grateful to Dr. Bert Steece, whom I regard as my unofficial advisor, for his
statistical insights that shape my understanding of statistical analysis applied to this
dissertation work. My thanks also go to other members of my qualifying exam and
defense committees, Dr. Nenad Medvidovi, Dr. Ellis Horowitz, and Dr. Rick Selby.
Their criticism, encouragement, and suggestion effectively helped to shape my work.
I am thankful to my friends and faculty for their constructive feedback on my
work, including Dan Port, Tim Menzies, Jo Ann Lane, Brad Clark, Don Reifer,
Supannika Koolmanojwong, Pongtip Aroonvatanaporn, and Qi Li. Other colleagues Julie
Sanchez of the USC Center for Systems and Software Engineering, Marilyn A Sperka,
Ryan E Pfeiffer, and Michael Lee of the Aerospace Corporation, and Lori Vaughan of
Northrop Grumman also assisted me in various capacities.
This work was made possible with the support for data collection from the
Affiliates of Center for Systems and Software Engineering and two organizations in
Vietnam and Thailand. Especially, Phuong Ngo, Ngoc Do, Phong Nguyen, Long Truong,
-
iv
Ha Ta, Hoai Tang, Tuan Vo, and Phongphan Danphitsanuphan have provided me
tremendous help in collecting historical data from the organizations in Vietnam and
Thailand.
I awe much to the Fulbright Program for financial support during my Masters
program at USC, giving me an opportunity to fulfill my dream of studying abroad and
doing research with remarkable researchers in the software engineering research
community. My cultural and educational experiences in the United States made possible
by the program are priceless.
-
v
TABLE OF CONTENTS
Dedication ........................................................................................................................... ii
Acknowledgements............................................................................................................ iii
List of Tables .................................................................................................................... vii
List of Figures .................................................................................................................... ix
Abbreviations...................................................................................................................... x
Abstract ............................................................................................................................. xii
Chapter 1. Introduction................................................................................................. 1 1.1 The Problem........................................................................................................ 2 1.2 A Solution ........................................................................................................... 2 1.3 Research Hypotheses .......................................................................................... 3 1.4 Definitions........................................................................................................... 6
Chapter 2. Related Work .............................................................................................. 7 2.1 Software Sizing................................................................................................... 7
2.1.1 Code-based Sizing Metrics ......................................................................... 7 2.1.2 Functional Size Measurement (FSM) ....................................................... 10
2.2 Major Cost Estimation Models ......................................................................... 16 2.2.1 SLIM......................................................................................................... 17 2.2.2 SEER-SEM ............................................................................................... 19 2.2.3 PRICE-S.................................................................................................... 22 2.2.4 KnowledgePlan (Checkpoint)................................................................... 24 2.2.5 COCOMO................................................................................................. 25
2.3 Maintenance Cost Estimation Models .............................................................. 30 2.3.1 Phase-Level Models.................................................................................. 30 2.3.2 Release-Level Models............................................................................... 32 2.3.3 Task-Level Models ................................................................................... 36 2.3.4 Summary of Maintenance Estimation Models.......................................... 44
Chapter 3. The Research Approach............................................................................ 46 3.1 The Modeling Methodology ............................................................................. 46 3.2 The Calibration Techniques.............................................................................. 52
3.2.1 Ordinary Least Squares Regression .......................................................... 52 3.2.2 The Bayesian Analysis.............................................................................. 53 3.2.3 A Constrained Multiple Regression Technique........................................ 55
-
vi
3.3 Evaluation Strategies ........................................................................................ 58 3.3.1 Model Accuracy Measures ....................................................................... 58 3.3.2 Cross-Validation ....................................................................................... 60
Chapter 4. the COCOMO II Model for Software Maintenance ................................. 62 4.1 Software Maintenance Sizing Methods ............................................................ 62
4.1.1 The COCOMO II Reuse and Maintenance Models.................................. 64 4.1.2 A Unified Reuse and Maintenance Model................................................ 68
4.2 COCOMO II Effort Model for Software Maintenance..................................... 75
Chapter 5. Research Results ....................................................................................... 80 5.1 The Controlled Experiment Results.................................................................. 80
5.1.1 Description of the Experiment .................................................................. 80 5.1.2 Experiment Results ................................................................................... 84 5.1.3 Limitations of the Experiment .................................................................. 91
5.2 Delphi Survey Results....................................................................................... 92 5.3 Industry Sample Data........................................................................................ 96 5.4 Model Calibrations and Validation................................................................. 104
5.4.1 The Bayesian Calibrated Model.............................................................. 105 5.4.2 The Constrained Regression Calibrated Models..................................... 110 5.4.3 Reduced Parameter Models .................................................................... 114 5.4.4 Local Calibration .................................................................................... 117
5.5 Summary ......................................................................................................... 122
Chapter 6. Contributions and Future Work .............................................................. 123 6.1 Contributions................................................................................................... 123 6.2 Future Work .................................................................................................... 125
Bibliography ................................................................................................................... 129
Appendix A. UFNM and AA Rating Scale .................................................................... 138 Appendix B. Delphi Survey Form .................................................................................. 139 Appendix C. Data Collection Forms............................................................................... 156 Appendix D. The COCOMO II.2000 Parameters Used in the Experiment.................... 158 Appendix E. Histograms for the Cost Drivers ................................................................ 159 Appendix F. Correlation Matrix for Effort, Size, and Cost Drivers ............................... 170
-
vii
LIST OF TABLES
Table 2-1. COCOMO Sizing Models ............................................................................... 27
Table 2-2. COCOMO II Calibrations ............................................................................... 29
Table 2-3. Maintenance Cost Estimation Models............................................................. 42
Table 4-1. Maintenance Models Initial Cost Drivers ...................................................... 76
Table 4-2. Ratings of Personnel Experience Factors (APEX, PLEX, LTEX).................. 77
Table 4-3. Ratings of RELY ............................................................................................. 78
Table 5-1. Summary of results obtained from fitting the models ..................................... 89
Table 5-2. Differences in Productivity Ranges................................................................. 93
Table 5-3. Rating Values for Cost Drivers from Delphi Survey ...................................... 94
Table 5-4. RELY Rating Values Estimated by Experts.................................................... 96
Table 5-5. Maintenance Core Data Attributes .................................................................. 98
Table 5-6. Summary Statistics of 86 Data Points ........................................................... 101
Table 5-7. Differences in Productivity Ranges between Bayesian Calibrated Model and COCOMO II.2000......................................................................................... 105
Table 5-8. Rating Values for Cost Drivers from Bayesian Approach ............................ 107
Table 5-9. Estimation Accuracies Generated by the Bayesian Approach ...................... 109
Table 5-10. Estimation Accuracies of COCOMO II.2000 on the Data Set.................... 110
Table 5-11. Retained Cost Drivers of the Constrained Models ...................................... 111
Table 5-12. Estimation Accuracies of Constrained Approaches .................................... 112
Table 5-13. Estimation Accuracies of Constrained Approaches using LOOC Cross-validation ..................................................................................................... 112
-
viii
Table 5-14. Correlation Matrix for Highly Correlated Cost Drivers .............................. 115
Table 5-15. Estimation Accuracies of Reduced Calibrated Models ............................... 116
Table 5-16. Stratification by Organization ..................................................................... 119
Table 5-17. Stratification by Program ............................................................................ 119
Table 5-18. Stratification by Organization on 45 Releases ............................................ 120
-
ix
LIST OF FIGURES
Figure 3-1. The Modeling Process.................................................................................... 48
Figure 3-2. A Posteriori Bayesian Update in the Presence of Noisy Data RUSE ............ 54
Figure 3-3. Boxplot of mean of PRED(0.3) on the COCOMO II.2000 data set .............. 56
Figure 3-4. Boxplot of mean of PRED(0.3) on the COCOMO 81 data set ...................... 56
Figure 4-1. Types of Code ................................................................................................ 63
Figure 4-2. Nonlinear Reuse Effects................................................................................. 65
Figure 4-3. AAM Curves Reflecting Nonlinear Effects ................................................... 72
Figure 5-1. Effort Distribution.......................................................................................... 85
Figure 5-2. Maintenance Project Collection Range.......................................................... 97
Figure 5-3. Distribution of Equivalent SLOC ................................................................. 101
Figure 5-4. Correlation between PM and EKSLOC ....................................................... 103
Figure 5-5. Correlation between log(PM) and log(EKSLOC)........................................ 103
Figure 5-6. Adjusted Productivity for the 86 Releases ................................................... 104
Figure 5-7. Adjusted Productivity Histogram for the 86 Releases ................................. 104
Figure 5-8. Productivity Ranges Calibrated by the Bayesian Approach ........................ 108
Figure 5-9. Productivity Ranges Generated by CMRE .................................................. 113
Figure 5-10. Distribution of TIME ................................................................................. 116
Figure 5-11. Distribution of STOR................................................................................. 116
-
x
ABBREVIATIONS
COCOMO Constructive Cost Model
COCOMO II Constructive Cost Model version II
CMMI Capability Maturity Model Integration
EM Effort Multiplier
PM Person Month
OLS Ordinary Least Squares
MSE Mean Square Error
MAE Mean Absolute Error
CMSE Constrained Minimum Sum of Square Errors
CMAE Constrained Minimum Sum of Absolute Errors
CMRE Constrained Minimum Sum of Relative Errors
MMRE Mean of Magnitude of Relative Errors
MRE Magnitude of Relative Errors
PRED Prediction level
ICM Incremental Commitment Model
PR Productivity Range
SF Scale Factor
MODEL PARAMETERS Size Parameters AA Assessment and Assimilation
AAF Adaptation Adjustment Factor
AAM Adaptation Adjustment Multiplier
AKSLOC Kilo Source Lines of Code of the Adapted Modules
CM Code Modified
DM Design Modified
EKSLOC Equivalent Kilo Source Lines of Code
-
xi
ESLOC Equivalent Source Lines of Code
IM Integration Modified
KSLOC Kilo Source Lines of Code
RKSLOC Kilo Source Lines of Code of the Reused Modules
SLOC Source Lines of Code
SU Software Understanding
UNFM Programmer Unfamiliarity
Cost Drivers ACAP Analyst Capability
APEX Applications Experience
CPLX Product Complexity
DATA Database Size
DOCU Documentation Match to Life-Cycle Needs
FLEX Development Flexibility
LTEX Language and Tool Experience
PCAP Programmer Capability
PCON Personnel Continuity
PERS Personnel Capability
PLEX Platform Experience
PMAT Equivalent Process Maturity Level
PREC Precedentedness of Application
PREX Personnel Experience
PVOL Platform Volatility
RELY Required Software Reliability
RESL Risk Resolution
SITE Multisite Development
STOR Main Storage Constraint
TEAM Team Cohesion
TIME Execution Time Constraint
TOOL Use of Software Tools
-
xii
ABSTRACT
Accurately estimating the cost of software projects is one of the most desired
capabilities in software development organizations. Accurate cost estimates not only help
the customer make successful investments but also assist the software project manager in
coming up with appropriate plans for the project and making reasonable decisions during
the project execution. Although there have been reports that software maintenance
accounts for the majority of the software total cost, the software estimation research has
focused considerably on new development and much less on maintenance.
In this dissertation, an extension to the well-known model for software estimation,
COCOMO II, is introduced for better determining the size of maintained software and
improving the effort estimation accuracy of software maintenance. While COCOMO II
emphasizes the cost estimation of software development, the extension captures various
characteristics of software maintenance through a number of enhancements to the
COCOMO II size and effort estimation models to support the cost estimation of software
maintenance.
Expert input and an industry data set of eighty completed software maintenance
projects from three software organizations were used to build the model. A number of
models were derived through various calibration approaches, and these models were then
evaluated using the industry data set. The full model, which was derived through the
Bayesian analysis, yields effort estimates within 30% of the actuals 51% of the time,
outperforming the original COCOMO II model when it was used to estimate these
-
xiii
projects by 34%. Further performance improvement was obtained when calibrating the
full model to each individual program, generating effort estimates within 30% of the
actuals 80% of the time.
-
1
Chapter 1. INTRODUCTION
Software maintenance is an important activity in software engineering. Over the
decades, software maintenance costs have been continually reported to account for a
large majority of software costs [Zelkowitz 1979, Boehm 1981, McKee 1984, Boehm
1988, Erlikh 2000]. This fact is not surprising. On the one hand, software environments
and requirements are constantly changing, which lead to new software system upgrades
to keep pace with the changes. On the other hand, the economic benefits of software
reuse have encouraged the software industry to reuse and enhance the existing systems
rather than to build new ones [Boehm 1981, 1999]. Thus, it is crucial for project
managers to estimate and manage the software maintenance costs effectively.
Software cost estimation plays an important role in software engineering practice,
often determining the success or failure of contract negotiation and project execution.
Cost estimations deliverables, such as effort, schedule, and staff requirements are
valuable pieces of information for project formation and execution. They are used as key
inputs for project bidding and proposal, budget and staff allocation, project planning,
progress monitoring and control, etc. Unreasonable and unreliable estimates are a major
cause of project failure, which is evidenced by a CompTIA survey of 1,000 IT
respondents in 2007, finding that two of the three most-cited causes of IT-project failure
are concerned with unrealistic resource estimation [Rosencrance 2007].
Recognizing the importance of software estimation, the software engineering
community has put tremendous effort into developing models in order to help estimators
-
2
generate accurate cost estimates for software projects. In the last three decades, many
software estimation models and methods have been proposed and used, such as
COCOMO, SLIM, SEER-SEM, and Price-S.
1.1 THE PROBLEM
COCOMO is the most popular non-proprietary software estimation model in
literature as well as in industry. The model was built using historical data and
assumptions of software (ab initio) development projects. With a few exceptions, the
models properties (e.g., forms, cost factors and constants) are supposed to be applicable
to estimating the cost of software maintenance. However, inherent differences exist
between software development and maintenance. For example, software maintenance
depends on quality and complexity of the existing architecture, design, source code, and
supporting documentation. The problem is that these differences make the models
properties less relevant in the software maintenance context, resulting in low estimation
accuracies achieved. Unfortunately, there is a lack of empirical studies that evaluate and
extend COCOMO or other models, in order to better estimate the cost of software
maintenance.
1.2 A SOLUTION
Instead of using the COCOMO model that was designed for new development,
what if we build an extension that takes into account characteristics of software
maintenance. Thus, my thesis is
-
3
Improved COCOMO models that allow estimators to better determine the
equivalent size of maintained software and estimate maintenance effort can improve the
accuracy of effort estimation of software maintenance.
The goal of this study is to investigate such models. I will test a number of
hypotheses testing the accuracy of alternative models that predict the effort of software
maintenance projects, the explanatory power of such cost drivers as execution time and
memory constraints, and potential effects on quality attributes as better determinants of
the effort involved in deleting code. Using the industry dataset that I have collected, I will
also evaluate the differences in the effects of the COCOMO cost drivers on the project's
effort between new development and maintenance projects. Finally, COCOMO models
for software maintenance will be introduced and validated using industry data sets.
1.3 RESEARCH HYPOTHESES
The main research question that this study attempts to address, reflecting the
proposed solution, is as follows
Are there extended COCOMO models that allow estimators to better determine the
equivalent size of maintained software and estimate maintenance effort that can improve
the accuracy of effort estimation of software maintenance?
To address this question, I implement the modeling process as described in
Section 3.2. The process involves testing a number of hypotheses. The inclusion of
hypothesis tests in the process helps frame the discussion and analysis of the results
-
4
obtained during the modeling process. This section summarizes the hypotheses to be
tested in this dissertation.
It is clear from prior work discussed in Chapter 2 that there is no common
maintenance size metric used as compared to the size for new development. In software
(ab initio) development, a certain level of consistency is achieved; either SLOC or
Function Point is widely used. In software maintenance, on the other hand, some
maintenance effort estimation models use the sum of SLOC added, modified, and
deleted, others do not include the SLOC deleted. Due to this inconsistency, evidence on
whether the SLOC deleted is a significant predictor of effort is desired. Thus, the
following hypothesis is investigated.
Hypothesis 1: The measure of the SLOC deleted from the modified modules is not
a significant size metric for estimating the effort of software maintenance projects.
This hypothesis was tested through a controlled experiment of student
programmers performing maintenance tasks. The SLOC deleted metric was used as a
predictor of effort in linear regression models, and the significance of the coefficient
estimate of this predictor was tested using the typical 0.05 level of significance.
Software maintenance is different from new software development in many ways.
The software maintenance team works on the system of which the legacy code and
documentation, thus it is constrained by the existing systems requirements, architecture,
design, etc. This characteristic leads to differences in project activities to be performed,
system complexity, personnel necessary skill set, etc. As a result, we expect that the
impact of each cost driver on the effort of software maintenance would be significantly
-
5
different in comparison with the COCOMO II.2000 model. We, therefore, investigate the
following hypothesis.
Hypothesis 2: The productivity ranges of the cost drivers in the COCOMO II
model for maintenance are different from those of the cost drivers in the COCOMO
II.2000 model.
The productivity range specifies the maximum impact of a cost driver on effort. In
other words, it indicates the percentage of effort increase or decrease if the rating of a
cost driver increases the lowest to the highest level. This hypothesis was tested by
performing simple comparisons on the productivity ranges of the cost drivers between the
two models.
Finally, the estimation model must be validated and compared with other
estimation approaches regarding its estimation performance. As the model for
maintenance proposed in this study is an extension of the COCOMO II model, we will
analyze its performance with that of the COCOMO II model and other two
unsophisticated but commonly used approaches including the simple linear regression
and the productivity index.
Hypothesis 3: The COCOMO II model for maintenance outperforms the
COCOMO II.2000 model when estimating the effort of software maintenance projects.
Hypothesis 4: The COCOMO II model for maintenance outperforms the simple
linear regression model and the productivity index estimation method.
-
6
Hypotheses 3 and 4 were tested by comparing the estimation performance of
various models using the estimation accuracy metrics MMRE and PRED.
1.4 DEFINITIONS
This section provides definitions of common terms and phrases referred to
throughout this dissertation. Software maintenance or maintenance is used to refer to the
work of modifying, enhancing, and providing cost-effective support to the existing
software. Software maintenance in this definition has a broader meaning than the IEEE
definition given in [IEEE 1999] as it includes minor and major functional enhancements
and error corrections. As opposed to software maintenance, new (ab initio) development
refers to the work of developing and delivering the new software product.
COCOMO II is used to refer to a set of estimation models that were developed
and released in [Boehm 2000b] as a major extension of COCOMO to distinguish itself
from the version originally created and published in [Boehm 1981]. COCOMO II.2000
refers to the COCOMO II model whose constants and cost driver ratings were released in
[Boehm 2000b]. COCOMO II model for maintenance is used to indicate the sizing
method and effort estimation model for software maintenance.
-
7
Chapter 2. RELATED WORK
Software cost estimation has attracted tremendous attention from the software
engineering research community. A number of studies have been published to address
cost estimation related problems, such as software sizing, software productivity factors,
cost estimation models for software development and maintenance. This chapter presents
a review of software sizing techniques in Section 2.1, major cost estimation models in
Section 2.2, and maintenance cost estimation models in Section 2.3.
2.1 SOFTWARE SIZING
Size is one of the most important attributes of a software product. It is a key
indicator of software cost and time; it is also a base unit to derive other metrics for
software project measurements, such as productivity and defect density. This section
describes the most popular sizing metrics and techniques that have been proposed and
applied in practice. These techniques can be categorized into code-based sizing metrics
and functional size measurements.
2.1.1 CODE-BASED SIZING METRICS
Code-based sizing metrics measure the size or complexity of software using the
programmed source code. Because a significant amount of effort is devoted to
programming, it is believed that an appropriate measure correctly quantifying the code
-
8
can be a perceivable indicator of software cost. Halsteads software length equation based
on programs operands and operators, McCabes Cyclometic Complexity, number of
modules, source lines of code (SLOC) among others have been proposed and used as
code-based sizing metrics. Of these, SLOC is the most popular. It is used as a primary
input by most major cost estimation models, such as SLIM, SEER-SEM, PRICE-S,
COCOMO, and KnowledgePlan (see Section 2.2).
Many different definitions of SLOC exist. SLOC can be the number of physical
lines, the number of physical lines excluding comments and blank lines, or the number of
statements commonly called logical SLOC, etc. To help provide a consistent SLOC
measurement, the SEI published a counting framework that consists of SLOC definitions,
counting rules, and checklists [Park 1992]. Boehm et al. adapted this framework for use
in the COCOMO models [Boehm 2000b]. USCs Center for Systems and Software
Engineering (USC CSSE) has published further detailed counting rules for most of the
major languages along with the CodeCount tool1. In COCOMO, the number of
statements or logical SLOC, is the standard SLOC input. Logical SLOC is less sensitive
to formats and programming styles, but it is dependent on the programming languages
used in the source code [Nguyen 2007].
For software maintenance, the count of added/new, modified, unmodified,
adapted, reused, and deleted SLOC can be used. Software estimation models usually
aggregate these measures in a certain way to derive a single metric commonly called
effective SLOC or equivalent SLOC [Boehm 2000b, SEER-SEM, Jorgensen 1995, Basili 1 http://csse.usc.edu
-
9
1996, De Lucia 2005]. Surprisingly, there is a lack of consensus on how to measure
SLOC for maintenance work. For example, COCOMO, SLIM, and SEER-SEM exclude
the deleted SLOC metric while KnowledgePlan and PRICE-S include this metric in their
size measures. Several maintenance effort estimation models proposed in the literature
use the size metric as the sum of SLOC added, modified, and deleted [Jorgensen 1995,
Basili 1996].
SLOC has been widely accepted for several reasons. It has been shown to be
highly correlated with the software cost; thus, they are relevant inputs for software
estimation models [Boehm 1981, 2000b]. In addition, code-based metrics can be easily
and precisely counted using software tools, eliminating inconsistencies in SLOC counts,
given that the same counting rules are applied. However, the source code is not available
in early project stages, which means that it is difficult to accurately measure SLOC until
the source code is available. Another limitation is that SLOC is dependent on the
programmers skills and programming styles. For example, an experienced programmer
may write fewer lines of code than an inexperienced one for the same purpose, resulting
in a problem called productivity paradox [Jones 2008]. A third limitation is a lack of a
consistent standard for measurements of SLOC. As aforementioned, SLOC could mean
different things, physical lines of code, physical lines of code excluding comments and
blanks, or logical SLOC. There is also no consistent definition of logical SLOC [Nguyen
2007]. The lack of consistency in measuring SLOC can cause low estimation accuracy as
described in [Jeffery 2000]. A forth limitation is that SLOC is technology and language
-
10
dependent. Thus, it is difficult to compare productivity gains of projects of varying
technologies.
2.1.2 FUNCTIONAL SIZE MEASUREMENT (FSM)
Having faced these limitations, Albrecht developed and published the Function
Point Analysis (FPA) method as an alternative to code-based sizing methods [Albrecht
1979]. Albrecht and Gaffney later extended and published the method in [Albrecht and
Gaffney 1983]. The International Function Point Users Group (IFPUG), a non-profit
organization, was later established to maintain and promote the practice. IFPUG has
extended and published several versions of the FPA Counting Practices Manual to
standardize the application of FPA [IFPUG 2004, 1999]. Other significant extensions to
the FPA method have been introduced and widely applied in practice, such as Mark II
FPA [Symons 1988] and COSMIC-FFP [Abran 1998].
2.1.2.1 FUNCTION POINTS ANALYSIS (FPA)
FPA takes into account both static and dynamic aspects of the system. The static
aspect is represented by data stored or accessed by the system, and the dynamic aspect
reflects transactions performed to access and manipulate the data. FPA defines two data
function types (Logical Internal File, External Interface File) and three transaction
function types (External Input, External Output, Query). Function point counts are the
sum of the scores that are assigned to each of the data and the transactional functions.
The score of each of the data and transaction functions is determined by its type and its
-
11
complexity. Function counts are then adjusted by a system complexity factor called Value
Adjustment Factor (VAF) to obtain adjusted function point counts.
The IFPUGs Function Point Counting Practices Manual (CPM) provides
guidelines, rules, and examples for counting function points. The manual specifies three
different types of function point counts for the Development project, the Enhancement
project, and the Application count. The Development project type refers to the count of
functions delivered to the user in the first installation of the new software. The
Enhancement project type refers to function point counts for modifications made to the
preexisting software. And the Application function point count measures the functions
provided to the user by a software product and is referred to as the baseline function point
count. It can be considered the actual function point count of the development project
developing and delivering the system. Thus, the application function point count can be
determined by applying the same process given for the development project if the user
requirements can be obtained from the working software.
In FPA, the enhancement project involves the changes that result in functions
added, modified or deleted from the existing system. The procedure and complexity
scales are the same as those of the development, except that it takes into account changes
in complexity of the modified functions and the overall system characteristics. The
process involves identifying added, modified, deleted functions and determining value
adjustment factors of the system before and after changes.
-
12
The Effective Function Point count (EFP) of the enhancement project is computed
using the formula
EFP = (ADD + CHGA) * VAFA + DEL * VAFB (Eq. 2-1)
Where,
ADD is the unadjusted function point count of added functions.
CHGA is the unadjusted function point count of functions that are obtained by
modifying the preexisting ones. It is important to note that CHGA counts any
function that is modified, regardless of how much the function is changed.
DEL is the unadjusted function point count of deleted functions.
VAFA is the Value Adjustment Factor of the application after the
enhancement project is completed.
VAFB is the Value Adjustment Factor of the preexisting application.
2.1.2.2 MARK II FUNCTION POINT ANALYSIS
In 1988, Symons [1988] proposed Mark II Function Point Analysis (MkII FPA)
as an extension to Albrechts FPA. MkII FPA was later extended and published by the
United Kingdom Software Metrics Association (UKSMA) in the MkII FPA Counting
Practices Manual [UKSMA 1998]. The MkII FPA method is a certified ISO as an
international standard FSM method [ISO 2002].
-
13
MkII FPA measures the functionality of a software system by viewing the
software system as consisting of logical transactions. Each logical transaction is a finest-
grained unit of a self-consistent process that is recognizable by the user. The logical
transaction consists of three constituent parts: input, processing, and output components.
The input and output components contain data element types that are sent across the
application boundary and processed by the processing component. The processing
component handles the input and output by referencing data entity types. Conceptually,
MkII FPAs definitions of data entity types and data element types are similar to those of
ILFs/EIFs and DETs in Albrechts FPA.
The size of the input and output components is the count of data element types,
and the size of the processing component is the count of data entity types. The MkII
function point count, which is referred to as MFI, is determined by computing a weighted
sum of the sizes of the input, processing, and output components of all logical
transactions. That is,
MFI = Wi Ni + WeNe + WoNo (Eq. 2-2)
Where, Wi, We, Wo are the weights of input data element types, data entity types,
and output data element types, respectively; and Ni, Ne, No are the counts of input data
element types, data entity types, and output data element types, respectively. The weights
Wi, We, Wo are calibrated using historical data by relating MFI to the effort required to
develop the respective functions. In the CPM version 1.3.1 [UKSMA 1998], the industry
average weights are as Wi = 0.58, We = 1.66, and Wo = 0.26.
-
14
For sizing the software maintenance work (referred to as changes in CPM
1.3.1), the MkII function point count includes the size of the logical transactions that are
added, changed, or deleted. This involves counting all individual input/output data
element types and data entity types that are added, modified, or deleted. The formula (Eq.
2-2) can be used to calculate the MkII function point count of maintenance work, where
Ni, Ne, No are treated as the counts of input data element types, data entity types, and
output data element types that are added, modified, or deleted.
2.1.2.3 COSMIC FFP
Full Function Point, which is often referred to as FFP 1.0, is a FSM method
proposed by St-Pierre et al. [St-Pierre 1997]. FFP was designed as an extension to IFPUG
FPA to better measure the functional size of real-time software. The method was later
extended and renamed to COSMIC-FFP by the Common Software Measurement
International Consortium (COSMIC). Several extensions have been published, and the
latest version is COSMIC-FFP 2.2 [COSMIC 2003]. COSMIC-FFP has been certificated
as an ISO international standard [ISO 2003].
COSMIC-FFP views the functionality of a software application as consisting of
functional processes, each having sub-processes. There are two types of sub-processes,
data movement type and data manipulation type. COSMIC-FFP does not handle the data
manipulation type separately, but it assumes some association between the two types. It
defines four types of data movement sub-processes, including Entry, Exit, Read, and
Write. An Entry is a movement of the data attributes contained in one data group from
-
15
the outside to the inside of the application boundary; an Exit moves a data group in the
opposite direction to that of the entry; and a Read or a Write refers to a movement of a
data group from or to storage. The COSMIC-FFP measurement method determines the
functional size by measuring the data movement sub-processes, each moving exactly one
data group. That is, the COSMIC-FFP function point count, which is measured in cfsu
(COSMIC Functional Size Unit), is computed by summing all Entries, Exits, Reads, and
Writes. The complexity of the measurement procedure involves identifying application
layers, application boundaries, and data groups that each sub-process handles. Detailed
rules and guidelines for this process are given in the COSMIC-FFP measurement manual
[COSMIC 2003].
In COSMIC-FFP, the functional size of the software maintenance work is the
simple sum of all Entry, Exit, Read, and Write data movement sub-processes whose
functional processes are affected by the change. By this calculation, COSMIC-FFP
assumes that three different types of change to the functionality (add, modify, and delete)
have the same level of complexity (e.g., the size of adding a function is counted the same
as that of modifying or deleting the function). That is, the COSMIC-FFP count for the
maintenance work (Sizecfsu) is computed as
Sizecfsu = Sizeadded + Sizemodified + Sizedeleted (Eq. 2-3)
Where, Sizeadded, Sizemodified, and Sizedeleted are the COSMIC-FFP counts measured
in csfu of the added, modified, and deleted data movements, respectively.
-
16
The above-discussed functional size measurement methods measure the size of
software maintenance consistently in the sense that added, modified, and deleted
functions are all included in the count, and they are assigned the same weight. Thus, the
number of function point counts assigned for a function is a constant regardless of
whether the function is added, modified, or deleted. This calculation also implies that the
effort required to add a function is expected to be the same as the effort to delete or
modify the same function.
2.2 MAJOR COST ESTIMATION MODELS
Many estimation models have been proposed and applied over the years. Instead
of describing them all, this section provides a brief review of major estimation models
that have been developed, continued to be applied, and marketed by respective
developers. These models include SLIM, SEER-SEM, PRICE-S, KnowledgePlan, and
COCOMO. There are several reasons for this selection. First, they represent the core set
of models that was developed in the early 1980s and 1990s. Second, they are still being
investigated and used widely in practice and literature. Their long history of extensions
and adoptions is proof of their robustness and usefulness. Third, these models perform
estimation for a broad range of software development and maintenance activities,
covering a number of phases of software lifecycles such as requirements, architecture,
implementation, testing, and maintenance.
-
17
2.2.1 SLIM
SLIM is one of the most popular cost estimation models that has been in the
market for decades. The model was originally developed in the late 1970s by Larry
Putnam of Quantitative Software Measurement2, and its mathematical formulas and
analysis were published in [Putnam and Myers 1992]. As the model is proprietary, the
subsequent upgrades of the model structures and mathematical formulas are not available
in the public domain.
Generally, the SLIM model assumes that the staffing profile follows a form of
Rayleigh probability distribution of project staff buildup over time. The shapes and sizes
of the Rayleigh curve reflect the project size, manpower buildup index, and other
productivity parameters. The Rayleigh staffing level at time t is presented as
= 22
22)(
dtt
d
tetKtp (Eq. 2-4)
Where K is the total lifecycle effort and td the schedule to the peak of the staffing
curve. The quality 2dt
KD = is considered staffing complexity of the project. The total
lifecycle effort is calculated using the project size S, the technology factor C, and td, and
is defined as
433 1
dtx
CSK = (Eq. 2-5)
2 www.qsm.com
-
18
Boehm et al. note that some assumptions of staffing profile following the
Rayleigh distribution do not always hold in practice [Boehm 2000a]. For example, some
development practices such as maintenance and incremental development may employ a
constant level of staff. In subsequent adjustments, SLIM handles this limitation by
allowing the staffing profile to be adjusted by a staffing curve parameter. There are
multiple project lifecycle phases defined by the model, such as feasibility study,
functional design, main build (development), and maintenance. Each lifecycle phase may
have a different staffing curve parameter. In the main build phase, for example, the
staffing curve parameter can specify the curve as Medium Front Load (for staff peaking
at 40% of the phase), Medium Rear Load (peaking at 80% of the phase), or Rear Load
(peaking at the end of the phase). In the maintenance phase, this parameter specifies a flat
staffing curve.
SLIM views software maintenance as a software lifecycle phase following the
main build or development phase. The maintenance phase may have major
enhancements, minor enhancements, and baseline support including emergency fixes,
help desk support, infrastructure upgrades, operational support, small research projects,
etc. The maintenance phase can be estimated independently with the other phases.
The model uses the effective SLOC as a unit of project size. Function points and
user-defined metrics such as the number of modules, screens, etc. can be used, but they
have to be converted to effective SLOC using a gear factor. SLIM counts new code and
modified code, but it excludes deleted code. Clearly, the model assumes that new code
and modified code have the same influence on the maintenance effort.
-
19
2.2.2 SEER-SEM
SEER-SEM is a commercial and proprietary model developed and marketed by
Galorath, Inc3. This model is an extension of the Jensen model [Jensen 1983] from which
model structures and parameters are extended while sharing the same core formulas. Like
SLIM, the model uses the Rayleigh probability distribution of staffing profile versus time
to determine development effort. The size of the project and other parameters can change
the Rayleigh curve which then gives estimates for effort, time, and peak staff
accordingly.
In SEER-SEM, the traditional Rayleigh staffing level at time t is calculated as
= 22
22)(
dtt
d
tetKtp (Eq. 2-6)
Where K is the total life cycle effort and td the time to the peak of the staffing
curve; these terms are calculated as
2.13
4.0
=
teCS
xDKe
(Eq. 2-7)
4.0
2.0
=
te
ed C
SDt (Eq. 2-8)
Where D is the staffing complexity, Se the effective size, and Cte the effective
technology. Although sharing the same meaning of D with SLIM, SEER-SEM defines D
3 www.galorath.com
-
20
as 3dt
K , which is slightly different from that of SLIM. The derivative of the Rayleigh curve
p(t) at t = 0 is defined as staffing rate, generally measuring the number of people added
to the project per year. The effective technology Cte is an aggregated factor determined by
using a set of technology and environment parameters. The effective size Se is the size of
the project that can be measured in source lines of code (SLOC), function points, or other
units.
In SEER-SEM, the software maintenance cost covers necessary maintenance
activities performed to ensure the operation of the software after its delivery. These
software maintenance activities involve correcting faults, changing the software to new
operating environments, fine-tuning and perfecting the software, and minor
enhancements. They are usually triggered by change requests and software faults that are
found during the operation of the software. SEER-SEM uses a number of maintenance-
specific parameters to estimate the maintenance cost for a given period of time, in
addition to the development cost of the software. The maintenance cost is allocated into
corrective, adaptive, perfective maintenance, and minor enhancement cost categories.
Major enhancements and re-engineering are not included in the software
maintenance cost, but are treated separately as a new software development project.
SEER-SEM handles major enhancements and new development similarly except that
their differences are reflected in the way that the effective size of the software is
determined.
-
21
The effective size, Se, of the software is calculated as
Se = New + [P x (0.4 A + 0.25 B + 0.35 C)] (Eq. 2-9)
Where,
New and P are the new size and the pre-existing software size, respectively. The
size can be measured in either function points or lines of code. Discarded code
is not included in calculating the effective size of the pre-existing software (P).
A, B, and C are the respective percentages of code redesign, code
reimplementation, and code retest required to adapt the pre-existing software.
The element [P x (0.4 A + 0.25 B + 0.35 C)] in formula (Eq. 2-9) is the
equivalent size of rework or reuse of the pre-existing software. The parameters A, B, and
C are subjective, and their values range from 0 to 100%. The SEER-SEM user manual
provides formulas and guidelines to help determine these parameters [Galorath 2002]. It
does not give details, however, on how to reevaluate these parameters when the
completed software is available (it is important to collect the actual size data because the
actual size data is used to recalibrate the model and to measure the actual productivity,
defect density, etc). The parameters A, B, and C maximum limit of 100% might
potentially result in underestimation of the rework because it does not account for
possible code expansion, full retest and integration of the pre-existing code.
-
22
2.2.3 PRICE-S
PRICE-S was originally developed by Frank Freiman of RCA for estimating
acquisition and development of hardware systems in the late 1960s and then released as
a first commercial software cost estimation model in 1977. After multiple upgrades,
extensions, and changes of ownership, the current model, True S, is now implemented as
a component in the TruePlanning tool marketed by PRICE Systems4. As True S is built
on the same core methodology as its predecessor, this review uses the name PRICE-S to
maintain its originality.
PRICE-S is an activity based estimation model that estimates the effort required
for each activity. In PRICE-S, an activity represents the work that people, equipment,
technologies, or facilities perform to produce a product or deliver a service [PRICE-S
2009]. As described in [IPSA 2008], the effort E of each activity is modeled in the form
of
E = S x PB x PA (Eq. 2-10)
Where,
S is the software size that can be measured in source lines of code, function
points, predictive object points (POPs) or use case conversion points (UCCPs).
POPs is an object oriented (OO) metric introduced by PRICE Systems to
measure the size of OO projects [Minkiewicz 1998], and UCCPs is a metric
used to quantify the size of use cases.
4 www.pricesystems.com
-
23
BP is the ideal baseline productivity of an industry or an application domain.
PA is the productivity adjustment factor that accounts for the overall effects of
cost drivers on the productivity of the project.
PRICE-S views the software maintenance phase as an activity that focuses on
fixing latent defects, deployment, and changing the software release to improve
performance, efficiency or portability. Thus, the maintenance cost is determined by these
activities other than as a function of how much the software cost is modified. PRICE-S
assumes that the maintenance cost only includes changes required to improve
performance, efficiency, and portability or to correct defects. Other changes not included
in the maintenance cost (i.e., functional enhancements) are estimated the same way as the
development project. The model uses a number of maintenance-specific parameters to
calculate the cost of software maintenance.
The costs associated with functional enhancements and adaptations for pre-
existing software involve specifying the amount of new, adapted, reused, changed, and
deleted code. Other size measures are also used such as the Percentage of Design
Adapted, Percentage of Code Adapted, and Percentage of Test Adapted, which are
similar to those of SEER-SEM. But unlike SEER-SEM, PRICE-S does not use the
effective size aggregated from different types of code in its model calculations. Rather, it
uses the different size components separately in various calculations to determine the
effort.
-
24
2.2.4 KNOWLEDGEPLAN (CHECKPOINT)
KnowledgePlan is a commercial software estimation tool developed and first
released by Software Productivity Research (SPR5) in 1997. KnowledgePlan is an
extension of several previous tools, Checkpoint and SPQR/20, which were originally
based on Capers Jones works [Jones 1997]. According to the KnowledgePlan users
guide, the model relies on knowledge bases of thousands of completed projects to provide
estimation and scheduling capabilities [KnowledgePlan 2005].
KnowledgePlan estimates effort at project, phase, and task levels of granularity.
In addition to the effort, the model main outputs include resources, duration, defects,
schedules and dependencies. Estimating and scheduling project tasks are enabled through
the knowledge bases containing hundreds of standard task categories to represent typical
activities in software projects. These standard task categories cover planning,
management, analysis, design, implementation, testing, documentation, installation,
training, and maintenance. Each of these task categories is associated with predefined
inclusion rules and algorithms that are used to suggest relevant tasks and determine the
size of deliverables and productivity for the given size of the project being estimated.
The KnowledgePlan tool supports different project types such as new
development, enhancement, reengineering, reverse engineering, and maintenance and
support of a legacy system. KnowledgePlan uses eight sizing categories called code
types, including New, Reused, Leveraged, Prototype, Base, Changed, Deleted, and
System Base. Differences in project types may be reflected in the distribution of size 5 www.spr.com
-
25
estimates of these categories. For example, a new development project typically has a
high proportion of New code while enhancement may have a high value of Base code.
2.2.5 COCOMO
The Constructive Cost Model (COCOMO), a well-known cost and schedule
estimation model, was originally published in the text Software Engineering Economics
[Boehm 1981]. This original model is often referred to as COCOMO 81. The model was
defined based on the analysis of 63 completed projects from different domains during the
1970s and the early 1980s. To address the issues emerging from advancements and
changes in technologies and development processes, the USC Center for Systems and
Software Engineering has developed and published COCOMO II. The model was
initially released in [Boehm 1995] and then published in the definitive book [Boehm
2000b]. Among the main upgrades are the introduction of new functional forms that use
scale factors, new cost drivers, and a new set of parameters values.
COCOMO II comprises three sub-models, Applications Composition, Early
Design, and Post-Architecture. The Applications Composition model is used to compute
the effort and schedule to develop the system that is integrated from reusable components
and other reusable assets using integrated development tools for design, construction,
integration, and test. The Applications Composition model has a different estimation
form from the other models. It uses a size input measured in terms of Application Points
or Object Points [Kauffman and Kumar 1993, Banker 1994] and a productivity rate to
calculate effort. The Early Design model is used in the early stages of the project when
-
26
the project information is not detailed enough for a fine-grained estimate. When the
detailed information is available (i.e., the high level design is complete, development
environment is determined), the Post-Architecture model is used alternatively. The Early
Design and Post-Architecture models use source lines of code as the basic size unit and
follow the same arithmetic form.
The general form of the effort formulas of the COCOMO 81, Early Design, and
Post-Architecture models can be written as
* *p
Bi
iPM A Size EM= (Eq. 2-11)
Where,
PM is effort estimate in person months.
A is a multiplicative constant, which can be calibrated using historical data.
Size is an estimated size of the software, measured in KSLOC.
B is an exponential constant (COCOMO I) or scale factors (COCOMO II).
EM specifies effort multipliers, which represent the multiplicative component of
the equation.
In COCOMO 81, the B term is an exponential constant, which is usually greater
than 1.0, indicating diseconomies of scale. In COCOMO II, B is defined as a function of
scale factors, in form of =
+=5
110
iiSFB where 0 and 1 are constants, and SFi is one
of the five scale factors. The COCOMO 81 model identifies 15 effort multipliers.
-
27
COCOMO II uses 7 in the Early Design model and 17 in the Post-Architecture model.
The effort multipliers are the cost drivers that have multiplicative impact on the effort of
the project while the scale factors have exponential impact. The Early Design and Post-
Architecture models have the same set of scale factors while the cost drivers in the Early
Design model were derived from those of the Post-Architecture model by combining
drivers that were found to be highly correlated. The COCOMO II Post-Architecture
models rating values of the model cost drivers were calibrated using the Bayesian
technique on a database of 161 project data points [Chulani 1999a].
Table 2-1. COCOMO Sizing Models
Development Type Source Code Types Sizing Model
New
New/Added New SLOC New System
Pre-existing Adapted, Reused Reuse
Major enhancements Pre-existing Adapted, Reused Reuse
Maintenance (repairs
and minor updates)
Pre-existing Added, Modified Maintenance
COCOMO II provides different models to determine the source code size of the
project, dependent on the origin of the code (new, pre-existing) and types of change
(addition, modification, reuse, automatic translation). Table 2-1 shows the sizing models
for various development types. In COCOMO, software maintenance involves repairs and
minor updates that do not change its primary functions [Boehm 1981]. Major
enhancements, which include changes that are not considered as maintenance, are
-
28
estimated similarly to software new development except that the size is determined
differently. The model uses the same ratings of the cost drivers for both maintenance and
new software development with a few exceptions. The Required Development Schedule
(SCED) and Required Reusability (RUSE) cost drivers are not used in the estimation of
effort for maintenance, and the Required Software Reliability (RELY) cost driver has a
different impact scale (see Section 0).
2.2.5.1 MODEL CALIBRATIONS AND EXTENSIONS
As COCOMO is a non-proprietary model, its details are available in the public
domain, encouraging researchers and practitioners in the software engineering
community to independently evaluate the model. There have been many extensions
independently reported, e.g., [Kemerer 1987, Jeffery and Low 1990, Gulezian 1991,
Menzies 2006]. Menzies et al. use machine learning techniques to generate effort models
from the original COCOMO model [Menzies 2006]. Gulezian proposed a calibration
method by transforming the model equation into a linear form and estimating the model
parameters using standard linear regression techniques [Gulezian 1991]. This calibration
method has been adopted by the COCOMO development team in their calibration work,
e.g., [Clark 1998, Chulani 1999b, Yang and Clark 2003, Chen 2006, Nguyen 2008].
COCOMO has also been a model used to validate new estimation approaches such as
fuzzy logic and neural networks (e.g., [Idri 2000, Huang 2005, Reddy and Raju 2009]).
The COCOMO development team continues to calibrate and extend the model
using different calibration approaches on more augmented data sets [Boehm and Royce
-
29
1989, Clark 1998, Chulani 1999b, Yang and Clark 2003, Chen 2006, Nguyen 2008].
Table 2-2 shows the best results obtained by main studies performed by the team.
PRED(0.30) is the percentage of estimates that fall within 30% of the actuals. For
example, PRED(0.30) = 52% indicates that the model in Clark [1998] produces estimates
that are within 30% of the actuals, 52% of the time. Two types of results are often
reported, fitting and cross-validation. The fitting approach uses the same data set for both
training and testing the model while the cross-validation approach uses different data
sets: one for training and the other for testing. The accuracies reported from cross-
validation better indicate the performance of the model because the main reason to build
a model is to use it in estimating future projects.
Table 2-2. COCOMO II Calibrations
Study Fitting PRED(0.30)
Cross-validation
PRED(0.30)
COCOMOII.1997 [Clark 1998] 52% -
COCOMOII.2000 [Chulani 1999b] 75% 69%
COCOMOII.2003 [Yang and Chark 2003] 56% -
Chen [2006] - 76%
Nguyen [2008] 80% 75%
In COCOMOII.1997, the parameters are weighted averages of data-driven
regression results and expert-judgment rating scales, in which the latter scales account for
90% of the weight. The COCOMOII.2000 calibration was based on the Bayesian analysis
using a data set of 161 data points, and the COCOMOII.2003 calibration used the same
Bayesian analysis, but it included 43 additional new data points. On the same data set as
-
30
COCOMOII.2000, Chen et al. [2006] used a subset selection technique to prune model
parameters, and Nguyen et al. [2008] applied constraints on regression models; they both
attempted to reduce variances in the model. As shown in Table 2-2, their results indicate
noticeable improvements in estimation accuracies, suggesting that using appropriate
machine learning techniques can potentially improve the model performance.
2.3 MAINTENANCE COST ESTIMATION MODELS
Although the area of software maintenance estimation has received less attention
as compared to that of new development, given the importance of software maintenance,
a number of models have been introduced and applied to estimating the maintenance
costs (see Table 2-3). These models address diverse sets of software maintenance work,
covering, for instance, error corrections, functional enhancements, technical renovations,
and reengineering. They can be roughly classified into three types based on the
granularity level of the estimation focus: phase-, release-, and task-level maintenance
estimation models.
2.3.1 PHASE-LEVEL MODELS
A set of the maintenance models focuses on the effort of routine maintenance
work for a certain period or the whole phase of the software maintenance. The routine
maintenance work refers to all activities performed during the operation of a software
system after it is delivered. It involves fault corrections, minor functional changes and
enhancements, and technical improvements of which the main purpose is to ensure the
regular operation of the system. The maintenance models integrated in COCOMO,
-
31
SEER-SEM, PRICE-S, SLIM, and KnowledgePlan are of this kind. In these models,
maintenance costs are usually a part of the estimates produced when estimating the cost
of a new system to be developed. Thus, the size of the system is a key input to estimate
the maintenance effort. Most of these models use additional cost drivers that are specific
to software maintenance. For example, COCOMO uses two drivers, namely software
understanding (SU) and the level of unfamiliarity of the programmer (UNFM) for its
sizing of the maintenance work; SEER-SEM uses such parameters as maintenance size
growth over time and maintenance rigor (the thoroughness of maintenance activities to
be performed) in its maintenance cost calculations [Galorath 2002].
Estimating the maintenance cost for a system of which the development cost is
being estimated is important for the architectures trade-off analysis and making
investment decisions on the system being evaluated. However, because many
assumptions are made about the system that has yet to be developed, it is difficult to
estimate the system maintenance cost accurately. This difficulty could be a reason that, to
the best of my knowledge, there is no empirical study published to evaluate and compare
the estimation accuracies of these models. Another possible reason is that these models,
with the exception of COCOMO, are proprietary and their details have not been fully
published, making them difficult to be investigated in the research context.
To estimate the adaptation and reuse work, COCOMO, SEER-SEM, PRICE-S,
SLIM, and KnowledgePlan provide methods to size the work and compute the effort and
schedule estimates using the same models developed for estimating new software
development. Obviously, these models assume that the adaptation and reuse work has the
-
32
same characteristics with new software development. Unfortunately, this assumption has
never been validated empirically.
2.3.2 RELEASE-LEVEL MODELS
Instead of estimating the cost of the maintenance phase as a whole, another group
of models focuses on the maintenance cost at a finer-grained level, estimating the effort
of a planned set of maintenance tasks or a planned release. This approach usually
involves using data from the past releases and analyzing the changes to estimate the cost
for the next release.
Basili et al., together with characterizing the effort distribution of maintenance
releases, described a simple regression model to estimate the effort for maintenance
releases of different types such as error correction and enhancement [Basili 1996]. The
model uses a single variable, SLOC, which was measured as the sum of added, modified
and deleted SLOC including comments and blanks. The prediction accuracy was not
reported although the coefficient of determination was relatively high (R2 = 0.75),
indicating that SLOC is a good predictor of the maintenance effort.
Considering the maintenance work after the initial delivery of the system as being
organized into sequences of operational releases, Ramil and Lehman introduced and
evaluated linear regression models to estimate the effort required to evolve the system
from a release to the next [Ramil 2000, 2003]. Their models take into account all
maintenance tasks necessary to grow the system, which can include error corrections,
functional enhancements, technical improvements, etc. The model predictors are size
-
33
metrics measured at coarse granularity levels, modules (number of added, changed
modules) and subsystems (number of added, changed), and number of changes to
modules plus all changed modules. The models were calibrated and validated on the data
sets collected from two case studies. In terms of MMRE and MdMRE, the best model
achieved MMRE = 19.3%, MdMRE=14.0% and PRED(0.25)=44%. This best model
seems to be based on coarse-grained metrics (subsystems), which is consistent with a
prior finding by Lindvall [1998], in which coarse-grained metrics, e.g., the number of
classes, were shown to estimate change effort more accurately than other finer-grained
metrics. However, it is important to note that this best model did not generate the best
(highest) PRED(0.25), indicating that the model evaluation and ensuing inferences are
likely contingent upon the estimation accuracy indicators used [Myrtweit 2005].
Caivano et al. described a method and a supporting tool for dynamic calibration
of the effort estimation model of renewal (reverse engineering and restoration) projects
[Caivano 2001]. The model accepts the change information gathered during the project
execution and calibrates itself to better reflect dynamics, current and future trends of the
project. At the beginning of the project, the model starts with its most common form
calibrated from completed projects. During the project execution, the model may change
its predictors and constants using the stepwise regression technique. The method uses
fine-grained metrics obtained from the source code such as number of lines of source
code, McCabes cyclomatic complexity, Halsteads complexity, number of modules
obtained after the renewal process. They validated the method using both data from a
legacy system and simulation. They found that fine-grained estimation and model
-
34
dynamic recalibration are effective for improving the model accuracy and confirmed that
the estimation model is process-dependent. A later empirical study further verifies these
conclusions [Baldassarre 2003]. Other studies have also reported some success in
improving the prediction accuracies by recalibrating estimation models in the iterative
development environment [Trendowicz 2006, Abrahamsson 2007].
Sneed proposed a model called ManCost for estimating software maintenance
cost by applying different sub-models for different types of maintenance tasks [Sneed
2004]. Sneed grouped maintenance tasks into four different types, hence, four sub-
models:
- Error correction: costs of error correction for a release.
- Routine change: maintenance costs implementing routine change requests.
- Functional enhancement: costs of adding, modifying, deleting, improving
software functionality. The model treats this type the same as new development in
which the size can be measured in SLOC or Function Point, and the effort is
estimated using adjusted size, complexity, quality, and other influence factors.
- Technical renovation: costs of technical improvements, such as performance and
optimization.
Sneed suggests that these task types have different characteristics; thus, each
requires an appropriate estimation sub-model. Nonetheless, the adjusted size and
productivity index are common measures used in these sub-models. The adjusted size
was determined by taking into account the effects of complexity and quality factors.
-
35
Although examples were given to explain the use of the sub-models to estimate the
maintenance effort, there was no validation reported to evaluate the estimation
performance of these sub-models. Sneed also proposed several extensions to account for
reengineering tasks [Sneed 2005] and maintenance of web applications [Sneed and
Huang 2007].
The wide acceptance of the FSM methods has attracted a number of studies to
develop and improve maintenance estimation models using the FSM metrics. Most of
these studies focused on the cost of adaptive maintenance tasks that enhance the system
by adding, modifying, and deleting existing functions. Having found that the FPA did not
reflect the size of small changes well, Abran and Maya presented an extension to the FPA
method by dividing the function complexity levels into finer intervals [Abran and Maya
1995]. This extension uses smaller size increments and respective weights to discriminate
small changes that were found to be common in the maintenance environment. They
validated the model on the data obtained from a financial institution and demonstrated
that a finer grained sizing technique better characterizes the size characteristics of small
maintenance activities.
Niessink and van Vliet described a Maintenance Function Point (MFP) model to
predict the effort required to implement non-corrective change requests [Niessink and
van Vliet 1998]. The model uses the same FPA procedure for enhancement to determine
the FP count, but the Unadjusted FP count was adjusted by a multiplicative factor,
namely Maintenance Impact Ratio (MIR), to account for the relative impact of a change.
The approaches were validated using the data set collected from a large financial
-
36
information system, the best model producing relatively low prediction accuracies
MMRE = 47% and PRED(0.25) = 28%. The result also shows that the size of the
component to be changed has a higher impact on the effort than the size of the change.
This result indicates that the maintainers might have spent time to investigate not only the
functions affected by the change but also other functions related to the change.
Abran et al. reported on the application of the COSMIC-FFP functional size
measurement method to building effort estimation models for adaptive maintenance
projects [Abran 2002]. They described the use of the functional size measurement
method in two field studies, one with the models built on 15 projects implementing
functional enhancements to a software program for linguistic applications, the other with
19 maintenance projects of a real-time embedded software program. The two field studies
did not use the same set of metrics but they include three metrics, effort, Cfsu, and the
level of difficulty of the project. The authors showed that while project effort and
functional size has a positive correlation, this correlation is strong enough to build good
effort estimation models that use a single size measure. However, as they demonstrated, a
more reliable estimation model can be derived by taking into account the contribution of
other categorical factors, such as project difficulty.
2.3.3 TASK-LEVEL MODELS
The task-level model estimates the cost of implementing each maintenance task
which comes in the form of error reports or change requests. This type of model deals
with small effort estimates, usually ranging from a few hours to a month.
-
37
Sneed introduced a seven-step process and a tool called SoftCalc to estimate the
size and costs required to implement maintenance tasks [Sneed 1995]. The model uses
various size measures, including SLOC (physical lines of code and statements), function
points, object-points, and data points (the last two were originally proposed in the same
paper). The size of the impact domain, the proportion of the affected software, was
determined and then adjusted by complexity, quality, and project influence factors. The
maintenance effort was computed using the adjusted size and a productivity index.
Rather than generating an exact effort estimate, it would be beneficial to classify
maintenance change requests in terms of levels of difficulty or levels of effort required,
and use this classification information to plan resources respectively. Briand and Basili
[1992] proposed a modeling approach to building classification models for the
maintenance effort of change requests. The modeling procedure involves four high-level
steps, identifying predictable metrics, identifying significant predictable metrics,
generating a classification function, and validating the model. The range of each
predictable variable and effort was divided into intervals, each being represented by a
number called difficulty index. The effort range has five intervals (below one hour,
between one hour and one day, between one day and one week, between one week and
one month, above one month) which were indexed, from 1 to 5 respectively. To evaluate
the approach, Briand and Basili used a data set of 163 change requests from four different
projects at the NASA Goddard Space Flight Center. The approach produced the
classification models achieving from 74% to 93% classification correctness.
-
38
Briand and Basilis modeling approach can be implemented to dynamically
construct models according to specific environments. Organizations can build a general
model that initially uses a set of predefined metrics, such as types of modification; the
number of components added, modified, deleted; the number of lines of code added,
modified, deleted. This general model is applied at the start of the maintenance phase, but
it will then be then refined when data is sufficient. However, as Basili et al. pointed out,
it is difficult to determine the models inputs correctly as they are not available until the
change is implemented [Basili 1997].
Basili et al. presented a classification model that classifies the cost of rework in a
library of reusable software components, i.e. Ada files [Basili 1997]. The model, which
was constructed using the C4.5 mining algorithm [Quinlan 1993], determines which
component versions were associated with errors that require a high correction cost (more
than 5 hours) or a low correction cost (no more than 5 hours). Three internal product
metrics, the number of function calls, the number of declaration statements, the number
of exceptions, were shown to be relevant predictors of the model. As these metrics can be
collected from the component version to be corrected, the model can be a useful
estimation tool.
Jorgensen evaluated eleven different models to estimate the effort of individual
maintenance tasks using regression, neural networks, and pattern recognition approaches
[Jorgensen 1995]. In the last approach, the Optimized Set Reduction (OSR) was used to
select the most relevant subset of variables for the predictors of effort [Briand 1992b]. All
of the models use the maintenance task size, which is measured as the sum of added,
-
39
updated, and deleted SLOC, as a main variable. Four other predictors were selected as
they were significantly correlated with the maintenance productivity. These are all
indicator predictors: Cause (whether or not the task is corrective maintenance), Change
(whether or not more than 50% of effort is expected to be spent on modifying of the
existing code compared to inserting and deleting the code), Mode (whether or not more
than 50% of effort is expected to be spent on development of new modules), Confidence
(whether or not the maintainer has high confidence on resolving the maintenance task).
Other variables, type of language, maintainer experience, task priority,
application age, and application size, were shown to have no significant correlation with
the maintenance productivity. As Jorgensen indicated, this result did not demonstrate that
each of these variables has no influence on maintenance effort. There were possible joint
effects of both investigated and non-investigated variables. For example, experienced
maintainers wrote more compact code while being assigned more difficult tasks than
inexperienced maintainers, and maintainers might be more experienced in large
applications than in the small ones. To validate the models, Jorgensen used a data set of
109 randomly selected maintenance tasks collected from different applications in the
same organization. Of the eleven models built and compared, the best model seems to be
the types of log linear regression and hybrid type based on pattern recognition and
regression. The best model could generate effort estimates with MRE = 100% and
PRED(.25) = 26% using a cross-validation approach [Bradley and Gong 1983]. This
performance is unsatisfactorily low. Considering low prediction accuracies achieved,
Jorgensen recommended that a formal model be used as supplementary to expert
-
40
predictions and suggested that the Bayesian analysis be an appropriate approach to
combining the estimates of the investigated models and expert predictions.
Fioravanti et al. proposed and evaluated a model and metrics for estimating the
adaptive maintenance effort of object-oriented systems [Fioravanti 1999, Fioravanti and
Nesi 2001]. Using the linear regression analysis, they derived the model and metrics
based on classical metrics previously proposed for effort estimation models. They
evaluated the model and metrics using the data collected from a real project, showing that
the complexity and the number of interfaces have the highest impact on the adaptive
maintenance effort.
Several previous studies have proposed and evaluated models for exclusively
estimating the effort required to implement corrective maintenance tasks. Lucia et al.
used the multiple linear regression to build effort estimation models for corrective
maintenance [De Lucia 2005]. Three models were built using coarse-grained metrics,
namely the number of tasks requiring source code modification, the number of tasks
requiring fixing of data misalignment, the number of other tasks, the total number of
tasks, and SLOC of the system to be maintained. They evaluated the models on 144
observations, each corresponding to a one-month period, collected from five corrective
maintenance projects in the same software services company. The best model, which
includes all metrics, achieved MMRE = 32.25% and PRED(0.25) = 49.31% using leave-
more-out cross-validation. In comparison with the non-linear model previously used by
the company, the authors showed that the linear model with the same variables produces
higher estimation accuracies. They also showed that taking into account the difference in
-
41
the types of corrective maintenance tasks can improve the performance of the estimation
model.
-
Table 2-3. Maintenance Cost Estimatio
Model/Study Maintenance Task Type Effort Estimated For Modeling Approach Ke
COCOMO Regular maintenance Major enhancement (Adaptation and reuse)
Maintenance period Adaptation and reuse project
Linear and Nonlinear Regression Bayesian Analysis
SLSU
KnowledgePlan Regular maintenance Major enhancement
Maintenance period Adaptation and reuse project
Arithmetic SLreucha
PRICE-S Regular maintenance Major enhancement
Maintenance period Adaptation and reuse project
Arithmetic SLnew
SEER-SEM Corrective Adaptive Perfective
Maintenance period Adaptation and reuse project
Arithmetic MaYe(m
SLIM Corrective Adaptive Perfective
Maintenance period
Heuristic SL
Basili 1996 Error correction and enhancement
Release Simple linear regression
SLdel
Basili 1997 Corrective Component version Classification (C4.5 algorithm)
Nusta
Niessink and van Vliet 1998
Adaptive (functional enhancement)
Individual change request
Linear regression IFPRa
Abran 1995 Adaptive (functional enhancement)
A set of activities resulting a maintenance work product (Release)
Arithmetic Ex
Abran 2002 Adaptive (functional enhancement)
Release (project) Linear and nonlinear regression
CO
6 The selection of the best model is dependent on the performance indicators used [Myrtweiindicators MMRE and PRED(0.25) are reported, and MMRE is used to indicate the best mo
42 4