NFPA 3

A  Fire  Alarm  Contractors’  Perspective  

Shane M. Clary, Ph.D.Bay Alarm CompanyAFAA Webinar Series November, 2011

Commissioning Basics

A process of documentation, adjustment, testing, verification and training, performed specifically to ensure that the finished facility operates  in  accordance  with  the  owner’s  documented project requirements and the construction documents.

It begins in pre-design and continues through design, construction and the life of the facility.

2

Commissioning Basics

Performance verification is demonstrated through inspection, testing and documentation of these activities.

3

Commissioning Basics

The ultimate goal of systems or building commissioning is to ensure that a facility meets the operational needs of building owners and provides for the continued efficient and effective operation of the building or systems throughout its intended service life.

4

What Commissioning is Not

Completing standard forms Contractors’  QA/QC  program Verification  of  the  contractors’  QA/QC  

program Construction inspection Construction management

5

NFPA 3

1.1 Scope. This recommended practice provides the recommended procedures, methods, and documentation for commissioning and integrated testing of active and passive fire protection and life safety systems and their interconnections with other building systems.

6

NFPA 3

1.2 Purpose. The purpose of this recommended practice is to describe the commissioning process and integrated testing that will ensure fire protection and life safety systems perform in conformity with the design intent.

7

Key Definitions

Commissioning (Cx). A systematic process that provides documented confirmation that specific and interconnected fire and life safety systems function according to the intended design criteria set forth in the project documents  and  satisfy  the  owner’s  operational  needs, including compliance requirements of any applicable laws, regulations, codes and standards requiring fire and life safety systems.

8

Key Definitions

Integrated System. A combination of systems that are required to operate together as a whole to achieve the fire protection and life safety objectives.

9

Key Definitions

Integrated Testing. An assessment of fire protection and life safety systems function and operation using direct observation or other monitoring methods to verify the correct interaction and coordination of multiple systems in conformance with the fire protection and life safety objectives.

10

11

The Process

Construction Phase

1)Confirm that the commissioning schedule is still valid, and update if required2)Verify that submittals, including, but not limited to, working plans and product data sheets are in conformance with the BOD and have been reviewed3)Verify that materials, construction, and installation are in conformance with the BOD4)Confirm qualified specialists are performing commissioning activities per CP

13

Construction Phase

5) Coordinate and document fire protection and life safety commissioning team meetings and progress reports

6) Document any issues and changes to the project and update the CP

7) Complete Cx (QC) construction checklists8) Perform required observation procedures or cause them

to be performed by the responsible party9) Update related documents to record and adjust for any

revisions and/or changes10) Verify and document testing performed in the

construction phase

14

Construction Inspections

Pre-Installation or Preconstruction:1)Address any outstanding issues that are best resolved in this venue2)Verify coordination has taken place amongst trades.3)Identify and establish benchmarks to be met during the construction phase4)Verify submittals are in accordance with design intent documents and approvals and permits are secured

15

Construction Inspections

5) Confirm integrated testing requirements are being addressed

6) Develop test data records.7) Confirm compliance with sequence of operation.

16

Construction Inspections

Rough-In Phase:1)Inspect and verify delivered materials meet requirements2)Verify installation is proceeding in accordance with coordinated, approved shop drawings3)Complete periodic site visits to verify compliance with the owner’s  commissioning  plan4)Inspect installation as outlined in the commissioning plan

17

Construction Inspections

5) Perform testing as applicable6) Update owner project requirements and address any

outstanding issues7) Update commissioning plan as needed8) Issue rough-in phase commissioning progress report

18

Construction Inspections

Finish Phase:1)Inspect and verify delivered materials meet requirements2)Verify installation is proceeding in accordance with coordinated, approved shop drawings3)Complete periodic site visits to verify compliance with OPR4)Inspect installation as outlined in the commissioning plan

19

Construction Inspections

5) Perform testing as applicable (post concealment)6) Update owner project requirements (OPR) and address

any outstanding issues7) Update commissioning plan8) Issue finish phase commissioning progress report

20

Testing and Inspection

1)Verify installation is in accordance with coordinated, approved shop drawings2)Inspect overall installation as outlined in the commissioning plan3)Perform preliminary testing of all systems to provide proper functionality and to ensure interoperability4)Perform and document testing of all systems to provide proper functionality, to ensure integration, and to ensure the systems were left in a state of operational readiness

21

Testing and Inspection

5) Update owner project requirements and address any outstanding issues

6) Update commissioning plan/record7) Issue completion/acceptance phase commissioning

progress report8) Verify compliance and accuracy of sequence of operation

22

Testing and Inspection

Closeout Documents :1)Compiled list of all deficiencies and resolutions; and verify resolution achieved2)Operations and maintenance manuals3)Compile test results and certificate4)As-built drawings

23

Testing and Inspection

5) Warranty and extended warranties6) Spare parts list and supplier listings7) Re-commissioning plan (integrated testing)8) Sequence of operation

24

Integrated System Testing

Applies to the testing of integrated systems provided for fire protection or life safety.

25

Integrated System Testing

Test Method.Integrated testing should demonstrate that the final integrated system installation complies with the specific design objectives for the project and applicable codes and standards. Integrated testing of fire protection and life safety systems should verify the interconnections function properly.

26

Integrated System Testing

During integrated testing, equipment should be tested in accordance with the applicable installation standard to verify systems perform according to their design function.

27

Integrated System Testing

DocumentationThe ITA should maintain a record of faults, failures, and discrepancies discovered through the testing process in an official Issues Log.

28