next linear collider 8-pack project d. atkinson system review, april 3 the 8-pack project at nlcta...
TRANSCRIPT
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
The 8-Pack Project at NLCTAAn overview of the status and schedule for the project.
Modulator and klystrons startup in July, 2002High power checkout in January, 2003DLDS operation in July 2004
Phase 1 SLED layout
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
The 8-Pack ProjectDemonstrate full NLC RF power & stored energy,
1st with SLED, Test DLDS components at full power prior to DLDS assembly
Then with DLDSDeliver full NLC RF power to NLCTA accelerating structures
• Phase-1: 4-Pack– Assemble system with:
• 2 XP3 klystrons to power the SLED, additional XP3 klystron(s) as available• A solid state modulator (from the ‘4-dog’)• SLED system• A simplified LLRF control system allowing SLED operation
– Produce NLC spec. power: 600 MW 400 ns • Benchmark as a power source for the NLC
– Test DLDS components at full power before installing
• Phase-2: 8-pack– Assemble 8 (total) XP3 klystrons with a (new) solid state modulator and
an NLC spec. LLRF control system – Attach DLDS system with two half arms reaching to two girders of high
gradient accelerating structures in NLCTA (from FNAL).
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
Goals – Phase 1
• Use multimoded SLED II pulse compression on 2 tubes to attain >600 MW, 400 ns (@ cross potent)
– meeting the NLC spec.
• Set up a station for high power tests of DLDS components & begin testing components
• Gain experience with 75 MW klystron operation
• Not to interfere with the High Gradient Structure Tests
klystrons
TE02
TE01
TE01
TE02
mode-preserving taper (TE02 cutoff at small end)
iris
Dual-Moded Pulse Compression System
mode mixer
cross potent
dual-mode directional coupler
load trees
reflective TE01 TE 02 mode converter / tuning plunger
jog-converter
dual-mode combiner
height taper
T/4
T/4
dual-mode-preserving taper
TE01
TE11or
TE01or
TE11(unSLEDed)
dual-mode splitter
bend -converter
circ-rect taper
E-plane bend
H-plane bend
TE11or
TE01(unSLEDed)
possible add-on
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
Goals – Phase 2
• Demonstrate DLDS pulse compression to attain NLC power specs. – 500 MW, 396 ns
(@ girder)– Power NLCTA girders
• Test DLDS system and high gradient structures to full energy (200J – 400J)
• Investigate operational, stability, maintenance issues associated with DLDS
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
Modulator
Solid State Modulator in the 4-dog Test Stand
Move to NLCTA 5/28
Stand and tank being designed and built by LLNL
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
KlystronsUnit #2 under test by
the SLAC klystron group.
Schedule:
Install #2:
7/19-7/25
Install #3:
8/21-8/27
XP3 PPM #275MW
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
Phase 1 schedule overview
Held system design review 2/22
75% of individual systems completed design reviews
Civil and infrastructure complete 6/5
Commission modulator at NLCTA 7/18
Klystron #2 power to loads 8/2
SLEDII system installation begins 10/1
Pump down SLEDII 1/22/03
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
Phase 2 schedule overview
Begin DLDS design during FY’02
High-power test DLDS components April-October 2003
Remaining klystron parts fabricated in FY’03
Install remainder of klystrons January-February 2004
DLDS system with controls installed June 2004
DLDS testing begins July 2004
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
8-pack project spending needs
in direct, FY’02 dollarsPhase 1:4-Pack and SLED
Phase 2:8-Pack and DLDS
System FY’02 FY’03 FY’04
System Eng. & Admin.
$510k $510k $515k
Infrastructure 730 220 75
Modulator 130 30 0
Klystrons 260 2310 975
RF distribution 1645 2290 1510
Controls & DAQ 930 1080 370
Total $4,205k $6,440k $3,440k
In FY’02, $2.4M spent by NLC for R&D in klystrons, modulators, and SLEDII/DLDS component development - hardware used in 8-Pack Phase 1.
In Phase 2 the 8-Pack project must pick this up and purchase remaining hardware, including 5 klystrons and DLDS system
Next Linear Next Linear ColliderCollider
8-Pack Project8-Pack Project
D. Atkinson System Review, April 3
No contingency in plan, either cost or schedule
In Phase 2, Project must purchase all remaining hardware
Klystrons fabrication pushed out of ’02 by budgetDLDS fabrication and testing
Must compete for SLAC services with PEP-II, SPEAR 3, LCLS, & NLC structures development
If we had more dollars, we couldOutsource more fabrication work to secure scheduleAccelerate parts for remaining klystron in FY’02Enhance the diagnostics in the control system in FY’02
Currently in the process of resource loading the schedule
Costs and tasks may shift when complete
Issues and Concerns for the 8-Pack Project (Remember, this is an R&D project)