new update to portfolio committee 03 may 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98...
TRANSCRIPT
Update to Portfolio Committee
03 May 2006
Content
• Safety and Health
• Recap of Challenges Highlighted in October 2005
• Overview of Strategic Business Plan
• Overview of FY2007 Budget
• Progress with Implementation of Improvement Initiatives
• Growth Opportunities
• Update on Legal Matters
• Social Responsibility and Transformation
• Conclusion
Safety and Health
Safety and Health Statistics - YTD:
• The RIFR and LTIFR targets are <1.0 and 0.5 respectively
• Good Stats for Alexkor, when considering its extensive diving operation in
comparison to peers
• Regrettably, a fatal accident occurred on the 12/01/06
Injury ClassificationRIFR LTIFR Dressing Cases
Number (of injuries) 4 7 14Rate (Injuries/mmhrs) 0.41 0.72 N/A
Recap on Operational Challenges
Constraints that Continue to Impede Good Performance
• Mining a mineral resource that is defined at an inferred level
• Marine mining methods hampered by unfavourable sea conditions
• The average age of equipment of 12 years calls for a replacement Capex
programme
• Uncertainties that prohibit the development of a long-term mining plan
• Financial provisions for both long-term & other liabilities
– Provision for rehabilitation liability
– Provision for post retirement medical aid
– Other unforeseen expenses related to legal matters
• Lack of ability to fund Capital expansions and exploration programme
Declining Carat Production
0
50000
100000
150000
200000
250000
1992 1994 1996 1998 2000 2002 2004 2006
Car
ats
Land Sea Total
The Challenge is how do we turn this trend upwards?
Snapshot of current mining assets
Front End Loaders (Component Repairs) An example of typical Front end Loader
An example of typical Excavators
Snapshot of current mining assets (cont.)
Noordsif Plant DMS Corroded Steel Structures
History of under-capitalisation
0
1 0
2 0
3 0
4 0
5 0
6 0
7 0
8 0
1 9 9 6 1 9 9 7 1 9 9 8 1 9 9 9 2 0 0 0 2 0 0 1 2 0 0 2 2 0 0 3 2 0 0 4 2 0 0 5 2 0 0 6
R m
illio
ns
A D D IT IO N S D IS P O S A L S
A review on our investment strategy is required
Inconsistent Exploration Programme
6 .2 9 6 .2 9
1 2 .9 2
3 .8 32 .2 6
1 3 .5
4 .1 8
00
2
4
6
8
1 0
1 2
1 4
1 6
1 9 9 9 2 0 0 0 2 0 0 1 2 0 0 2 2 0 0 3 2 0 0 4 2 0 0 5 2 0 0 6
Rm
A sound exploration programme needs to be implemented
Unpredictability of the number of sea days - 2005/2006
0
2
4
6
8
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Sea
Day
s
FY2006 budget
Over-reliance on good sea weather not sustainable
Turning point on sea weather patterns undeterminable
Continuous Downward Trend on Sea Days
0
20
40
60
80
100
120
140
160
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
bud
Sea Days
Overview of Strategic Plan
Overview of Strategic Plan
• Alexkor’s Strategic Planning Session was held from the 11-13th
December 2005
• In attendance were the Management team, Board members and representatives from DPE and National Treasury
• Separate strategies were developed for ABM and ABT
Update on ABM Strategy• Reduction of unit mining costs to maximise the potential for
identifying an economic resource by– Operating the plants at maximum capacity, 3 shifts – commenced in
April 2006– Operating the mining teams on a 3 shift configuration to utilize the
increased plant capacity – commenced in April 2006
• Development of a mineral reserve base by– Creating an exploration team with the necessary equipment – Planned
for FY 2007– Fabricating an exploration plant – Planned for FY 2007– Conducting an aerial geophysical survey – Planned for FY 2008
• Reduction in the mine’s dependence on diver directed marine operations by– Introducing remote mining techniques – in Q2 2007– Introducing dredger operations – Planned for FY 2008
Update on ABM Strategy
• Maximise the revenue from the sale of the diamonds by– Selling the product on the open market - Immediate– Adding value through branding / marketing individual parcels
• To strengthen management capabilities
• To establish accurate and reliable IT systems – in FY 2007
• Gain approval of amendments to the mine’s EMP and provide provision for the cost of closure – by end of Q3 2007
• To minimize the risk of diamond theft - ongoing
Update on ABT Strategy• Each Business unit ring-fenced as stand alone entity and to be
managed in collaboration with experts within that specific unit
• Obtained professional advice from experienced operators in the
Agricultural sectors for the development of sustainable business plan for
the various ABT units
• Business plans will be developed in conjunction with the community
once the land claims case is settled
• The turnaround strategies implemented for the ostriches and oysters
business units working well
Update on ABT Strategy (cont. )
• Potential exists for the development of sustainable Dairy and Citrus
business units due to favourable climatic conditions
However this will require:
• a study to be conducted on market potential, and
• subsequent capital investment required to build a modern dairy and
planting additional fruit trees
Non Strategic Assets• The following non strategic assets were identified at a strategic held by
Alexkor:
– Town Maintenance, Airport, Hospital , Guesthouses
• Loss for FY 2006 of R 6.8 million is broken down as follows :
– Town Maintenance - ( R 4,1 million)
– Airport - (R ,17 million)
– Hospital - (R 2,6 million)
– Guesthouses - R , 04 million
• Currently engaging with NC Provincial Government for the transfer of the Hospital, Airport and Town Maintenance to the relevant Authorities
• Transfer of the assets could be a potential cost saving of R 6.8 m pa, which is currently subsidized by ABM
Overview of FY2007 Budget
Budget Overview• Assumptions for FY 2007
– Average R/$ exchange rate = R 6.15
– Diamond price ($/ct) = $445
– Carat production = 85,048 ct
Diamond ProductionMarine 48,110 ABM Own Mining 17,450 Land Mining Contractors 4,800 Muisvlak 12,269 Witvoorkop 2,420
Total Carats 85,048
Budget Overview (cont.)
• Alexkor Consolidated BudgetTOTAL INCOME 277,068,326
ABM 245,540,719 DIAMOND 232,760,818 OTHER 12,779,901
ABT 21,794,582 DAIRY 7,757,780 MARICULTURE 960,000 OSTRICHES 3,354,096 CITRUS 112,700 OTHER 9,610,006
NON STRATEGIC BUSINESS UNITS 9,733,025 TOWN 3,602,952 HOSPITAL 4,472,231 AIRPORT - GUESTHOUSES 1,657,842
Budget Overview (cont.)TOTAL EXPENDITURE 276,659,820
ABM 237,684,751 ABT 24,872,308 DAIRY 8,718,700 MARICULTURE 878,744 OSTRICHES 3,139,885 CITRUS 594,199 OTHER 11,540,780
NON STRATEGIC BUSINESS UNITS 14,102,762 TOWN 6,677,227 HOSPITAL 6,582,023 AIRPORT 260,080 GUESTHOUSES 583,432
NET PROFIT/(LOSS) 408,506
Budget Overview (cont.)
• Capex– Capital required to maintain operation R 36,3 million– Capital required to maintain marine production R 42,4 million– Capital required to conduct exploration R 109,6 million– Total Capital Expenditure R 188,3 million
The challenge is to find a source for the funding of capital requirements
Budget Overview (cont.)
Carat Production Split FY 2007
Alexkor20%
Land Contractors
6%
Muisvlak14%
Witvoorkop3%
Marine57%
Carat Production Split FY 2006Alexkor
11%
Land Contractors
7%
Muisvlak15%
Witvoorkop5%
Marine62%
Implementation of Performance Improvement Plans
Improvement Initiatives on Land Mining• Carried out mining operations throughout the December month to minimise impact of the
holiday period
• Arrangements already in place to work additional shifts in FY2007
• Witvoorkop is planned to commence operating in 1Q07
• Muisvlak is planned to commence operating in the 2Q07
• Re-trained and allocated non-production labour to mining areas
• Commenced with triple shift operation for mining plants and screening operations
• Installed new scanner with latest technology to improve security at main access into the
mine
• Place emphasis on cost reduction and control
• Sold March 2006 diamond production on the open market with very good success
Production Improvement to date
Diamond Production Trends – YTD 2006Total Production
0
1000
2000
3000
4000
5000
6000
7000
Ave04-05
Apr-05
May-05
Jun-05
Jul-05
Aug-05
Sep-05
Oct-05
Nov-05
Dec-05
Jan-06
Feb-06
Mar-06
Car
ats
Total Land Production
0
200
400
600
800
1000
1200
1400
1600
Ave04-05
Apr-05
May-05
Jun-05
Jul-05
Aug-05
Sep-05
Oct-05
Nov-05
Dec-05
Jan-06
Feb-06
Mar-06
Car
ats
Marine Production
0
1000
2000
3000
4000
5000
6000
Ave04-05
Apr-05
May-05
Jun-05
Jul-05
Aug-05
Sep-05
Oct-05
Nov-05
Dec-05
Jan-06
Feb-06
Mar-06
Car
ats
Alexkor Own Mining
0
100
200
300
400
500
600
700
800
900
Ave04-05
Apr-05
May-05
Jun-05
Jul-05
Aug-05
Sep-05
Oct-05
Nov-05
Dec-05
Jan-06
Feb-06
Mar-06
Carats
Positive Trend: Reduction in Direct Working Costs
0
20
40
60
80
100
120
140
160
180
200
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Ran
d / C
ubic
Mining Expl Sweep IFS Noord Voltas F Rec Transp
Continuous Effort on Reducing Cut-off Grade
0
10,000
20,000
30,000
40,000
50,000
60,000
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Cub
ics
0.0
2.0
4.0
6.0
8.0
10.0
12.0
Cph
c
Cubics Cut-off (cphc)
Possible Growth Opportunities
DREDGER PROJECT – A vessel applying techniques on sea floor
Dredger Project - Concept
Dredge• This a vessel that dredges the sea floor sediment and suck it into the hold of the vessel
Sail and Connect• The vessel sails to a land-to-sea pipeline 600m off-shore
Discharge• Contents of the vessel is pumped to land based holding ponds via the pipeline
Treatment• The material is screened, loaded and trucked to a plant for diamond recovery
Dredger project – Financial ImplicationsCapital Required
Pipeline R25,000,000
Mobilisation Once off R15,000,000
Dredging 1 month R750,000 per day R22,000,000
1 month dredging 34 000 cts recovery R88,000,000 revenue
Treatment on land 10 months at Noordsif R6,500,000
Equipment + Infrast. R16,000,000
OPERATING COST (1 month dredging)
REVENUE
PROFIT R44,500,000
Dredger Project - Summary
Successfully undertaken on a trial basis by Namdeb
Positives• Will bring resource deeper than 20m water depth to account•Potential for lower cut off grade than conventional remote mining techniques •Not affected by sea conditions to the same extend as diving operations• Extended life of treatment plants
• Negatives• High overheads associated with the project :
• Pipeline R25 000 000 (reusable)• Mobilisation of vessel (can be shared with Namdeb)• Charter rate of the dredge vessel
Implementation of Remote Mining
• Awarded four remote mining contract, one expected to start in
June 2006
• Vessel based remote mining methods are expected to operate
between 15 and 20 days per month as opposed to the diver
operated units of 4 days per month.
Sale of Production in Open Market
$ 0
$ 1 0 0
$ 2 0 0
$ 3 0 0
$ 4 0 0
$ 5 0 0
$ 6 0 0
A p r-0 5 M a y -0 5 J u n -0 5 J u l-0 5 A u g -0 5 S e p -0 5 O c t-0 5 N o v -0 5 D e c -0 5 J a n -0 6 F e b -0 6 M a r-0 6
D I A M D E L V A L U A T O R S T A T E V A L U A T O R
Product is of good quality – good potential exists
0
100
200
300
400
500
600
Apr-05
May-05
Jun-05
Jul-05
Aug-05
Sep-05
Oct-05
Nov-05
Dec-05
Jan-06
Feb-06
Mar-06
1,000
1,500
2,000
2,500
3,000
3,500
Average $/ct Ave R/ct
Update on Legal Matters
Uncertainties and Litigation Issues• Good progress on the Land Claims case with the signing of the MOU by
Government, Alexkor and CPA
• Awaiting court proceedings and ruling on other legal matters
– Coin Security claim amounting to R 2.7 m
– Ruslyn Mining Claim amounting to R 19 m
– Nabera claim amounting to R 4.2 m and R 119 m (part of claim against State)
• Financial implications include legal fees and possible compensation
• Limited provision has been made for payment of possible settlement amounts
Social Responsibility and Transformation
Social Responsibility and TransformationSkills Development:
• Providing bursaries to six students, of which 3 are females.
• Facilitating mentorship programmes with 11 HDSA Protégés, of which 5 are females.
• Currently training 11 HDSA apprentices, of which 2 are females.
• The earthmoving team comprises 36 employees, of which 3 are females.
• Trained 3 females as infield screen operators in early 2006.
Social Responsibility and Transformation
• Conducting ABET classes to improve literacy, numeracy and life skills of employees and community.
• Alexkor expended 3.14% of total wage bill in 2005/2006 FY on training.
• Providing Health Care and emergency services to Alexander Bay and Richtersveld Communities
• Maintenance of Alexander Bay town, (including water and seweragepurification) and providing portable water to A/Bay and Port Nolloth.
• Ad-hoc donations & rental subsidies of R11 million for period 2000-2005
• Involvement in HIV/Aids awareness projects
• Donated 2 Wheelchairs for disabled members of the community.
Employment Equity, as at 30 April 2006 (ABM)
POSITIONNUMBER OF
INCUMBENTS A C W A C W
% OF DESIGNATED
GROUP DISABLED
Senior Management 6 1 1 3 - 1 - 50%
Professionaly Qualified 14 3 2 5 1 1 2 64% 2
Skilled 71 - 22 38 - 3 8 46%
Semi Skilled 187 5 126 19 - 25 12 90%
Unskilled 26 1 17 - 8 - 100%
Total 304 10 168 65 1 38 22 79% 2
MALE FEMALE
2 Members of Senior Management resigned in February 2006, to be replaced soon.
Marine Mining Contractors Structure
MALE FEMALE
POSITION BEE NON BEE BEE NON BEE
Shareholders 177 46 39 9
Employees 477 18
The BEE shareholding on all Marine contractors is 50%
Conclusion
Conclusion
• Short-term focus is on improving financial performance:
– Optimise the use of available resources
– Implement initiatives for productivity improvement
– Continuous reduction of both operating costs and pay-limit
• Implement short to long term strategic objectives to transform the company
• Collaborate with established companies and leverage on their ability to fund
expansion plans
• Speed up the implementation of remote mining techniques
• Look at ways of obtaining funding for Capex and exploration programs
Thank you