new update to portfolio committee 03 may 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98...

50
Update to Portfolio Committee 03 May 2006

Upload: others

Post on 27-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Update to Portfolio Committee

03 May 2006

Page 2: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Content

• Safety and Health

• Recap of Challenges Highlighted in October 2005

• Overview of Strategic Business Plan

• Overview of FY2007 Budget

• Progress with Implementation of Improvement Initiatives

• Growth Opportunities

• Update on Legal Matters

• Social Responsibility and Transformation

• Conclusion

Page 3: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Safety and Health

Page 4: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Safety and Health Statistics - YTD:

• The RIFR and LTIFR targets are <1.0 and 0.5 respectively

• Good Stats for Alexkor, when considering its extensive diving operation in

comparison to peers

• Regrettably, a fatal accident occurred on the 12/01/06

Injury ClassificationRIFR LTIFR Dressing Cases

Number (of injuries) 4 7 14Rate (Injuries/mmhrs) 0.41 0.72 N/A

Page 5: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Recap on Operational Challenges

Page 6: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Constraints that Continue to Impede Good Performance

• Mining a mineral resource that is defined at an inferred level

• Marine mining methods hampered by unfavourable sea conditions

• The average age of equipment of 12 years calls for a replacement Capex

programme

• Uncertainties that prohibit the development of a long-term mining plan

• Financial provisions for both long-term & other liabilities

– Provision for rehabilitation liability

– Provision for post retirement medical aid

– Other unforeseen expenses related to legal matters

• Lack of ability to fund Capital expansions and exploration programme

Page 7: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Declining Carat Production

0

50000

100000

150000

200000

250000

1992 1994 1996 1998 2000 2002 2004 2006

Car

ats

Land Sea Total

The Challenge is how do we turn this trend upwards?

Page 8: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Snapshot of current mining assets

Front End Loaders (Component Repairs) An example of typical Front end Loader

An example of typical Excavators

Page 9: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Snapshot of current mining assets (cont.)

Noordsif Plant DMS Corroded Steel Structures

Page 10: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

History of under-capitalisation

0

1 0

2 0

3 0

4 0

5 0

6 0

7 0

8 0

1 9 9 6 1 9 9 7 1 9 9 8 1 9 9 9 2 0 0 0 2 0 0 1 2 0 0 2 2 0 0 3 2 0 0 4 2 0 0 5 2 0 0 6

R m

illio

ns

A D D IT IO N S D IS P O S A L S

A review on our investment strategy is required

Page 11: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Inconsistent Exploration Programme

6 .2 9 6 .2 9

1 2 .9 2

3 .8 32 .2 6

1 3 .5

4 .1 8

00

2

4

6

8

1 0

1 2

1 4

1 6

1 9 9 9 2 0 0 0 2 0 0 1 2 0 0 2 2 0 0 3 2 0 0 4 2 0 0 5 2 0 0 6

Rm

A sound exploration programme needs to be implemented

Page 12: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Unpredictability of the number of sea days - 2005/2006

0

2

4

6

8

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Sea

Day

s

FY2006 budget

Over-reliance on good sea weather not sustainable

Page 13: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Turning point on sea weather patterns undeterminable

Continuous Downward Trend on Sea Days

0

20

40

60

80

100

120

140

160

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

bud

Sea Days

Page 14: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Overview of Strategic Plan

Page 15: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Overview of Strategic Plan

• Alexkor’s Strategic Planning Session was held from the 11-13th

December 2005

• In attendance were the Management team, Board members and representatives from DPE and National Treasury

• Separate strategies were developed for ABM and ABT

Page 16: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Update on ABM Strategy• Reduction of unit mining costs to maximise the potential for

identifying an economic resource by– Operating the plants at maximum capacity, 3 shifts – commenced in

April 2006– Operating the mining teams on a 3 shift configuration to utilize the

increased plant capacity – commenced in April 2006

• Development of a mineral reserve base by– Creating an exploration team with the necessary equipment – Planned

for FY 2007– Fabricating an exploration plant – Planned for FY 2007– Conducting an aerial geophysical survey – Planned for FY 2008

• Reduction in the mine’s dependence on diver directed marine operations by– Introducing remote mining techniques – in Q2 2007– Introducing dredger operations – Planned for FY 2008

Page 17: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Update on ABM Strategy

• Maximise the revenue from the sale of the diamonds by– Selling the product on the open market - Immediate– Adding value through branding / marketing individual parcels

• To strengthen management capabilities

• To establish accurate and reliable IT systems – in FY 2007

• Gain approval of amendments to the mine’s EMP and provide provision for the cost of closure – by end of Q3 2007

• To minimize the risk of diamond theft - ongoing

Page 18: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Update on ABT Strategy• Each Business unit ring-fenced as stand alone entity and to be

managed in collaboration with experts within that specific unit

• Obtained professional advice from experienced operators in the

Agricultural sectors for the development of sustainable business plan for

the various ABT units

• Business plans will be developed in conjunction with the community

once the land claims case is settled

• The turnaround strategies implemented for the ostriches and oysters

business units working well

Page 19: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Update on ABT Strategy (cont. )

• Potential exists for the development of sustainable Dairy and Citrus

business units due to favourable climatic conditions

However this will require:

• a study to be conducted on market potential, and

• subsequent capital investment required to build a modern dairy and

planting additional fruit trees

Page 20: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Non Strategic Assets• The following non strategic assets were identified at a strategic held by

Alexkor:

– Town Maintenance, Airport, Hospital , Guesthouses

• Loss for FY 2006 of R 6.8 million is broken down as follows :

– Town Maintenance - ( R 4,1 million)

– Airport - (R ,17 million)

– Hospital - (R 2,6 million)

– Guesthouses - R , 04 million

• Currently engaging with NC Provincial Government for the transfer of the Hospital, Airport and Town Maintenance to the relevant Authorities

• Transfer of the assets could be a potential cost saving of R 6.8 m pa, which is currently subsidized by ABM

Page 21: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Overview of FY2007 Budget

Page 22: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Budget Overview• Assumptions for FY 2007

– Average R/$ exchange rate = R 6.15

– Diamond price ($/ct) = $445

– Carat production = 85,048 ct

Diamond ProductionMarine 48,110 ABM Own Mining 17,450 Land Mining Contractors 4,800 Muisvlak 12,269 Witvoorkop 2,420

Total Carats 85,048

Page 23: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Budget Overview (cont.)

• Alexkor Consolidated BudgetTOTAL INCOME 277,068,326

ABM 245,540,719 DIAMOND 232,760,818 OTHER 12,779,901

ABT 21,794,582 DAIRY 7,757,780 MARICULTURE 960,000 OSTRICHES 3,354,096 CITRUS 112,700 OTHER 9,610,006

NON STRATEGIC BUSINESS UNITS 9,733,025 TOWN 3,602,952 HOSPITAL 4,472,231 AIRPORT - GUESTHOUSES 1,657,842

Page 24: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Budget Overview (cont.)TOTAL EXPENDITURE 276,659,820

ABM 237,684,751 ABT 24,872,308 DAIRY 8,718,700 MARICULTURE 878,744 OSTRICHES 3,139,885 CITRUS 594,199 OTHER 11,540,780

NON STRATEGIC BUSINESS UNITS 14,102,762 TOWN 6,677,227 HOSPITAL 6,582,023 AIRPORT 260,080 GUESTHOUSES 583,432

NET PROFIT/(LOSS) 408,506

Page 25: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Budget Overview (cont.)

• Capex– Capital required to maintain operation R 36,3 million– Capital required to maintain marine production R 42,4 million– Capital required to conduct exploration R 109,6 million– Total Capital Expenditure R 188,3 million

The challenge is to find a source for the funding of capital requirements

Page 26: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Budget Overview (cont.)

Carat Production Split FY 2007

Alexkor20%

Land Contractors

6%

Muisvlak14%

Witvoorkop3%

Marine57%

Carat Production Split FY 2006Alexkor

11%

Land Contractors

7%

Muisvlak15%

Witvoorkop5%

Marine62%

Page 27: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Implementation of Performance Improvement Plans

Page 28: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Improvement Initiatives on Land Mining• Carried out mining operations throughout the December month to minimise impact of the

holiday period

• Arrangements already in place to work additional shifts in FY2007

• Witvoorkop is planned to commence operating in 1Q07

• Muisvlak is planned to commence operating in the 2Q07

• Re-trained and allocated non-production labour to mining areas

• Commenced with triple shift operation for mining plants and screening operations

• Installed new scanner with latest technology to improve security at main access into the

mine

• Place emphasis on cost reduction and control

• Sold March 2006 diamond production on the open market with very good success

Page 29: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Production Improvement to date

Page 30: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Diamond Production Trends – YTD 2006Total Production

0

1000

2000

3000

4000

5000

6000

7000

Ave04-05

Apr-05

May-05

Jun-05

Jul-05

Aug-05

Sep-05

Oct-05

Nov-05

Dec-05

Jan-06

Feb-06

Mar-06

Car

ats

Total Land Production

0

200

400

600

800

1000

1200

1400

1600

Ave04-05

Apr-05

May-05

Jun-05

Jul-05

Aug-05

Sep-05

Oct-05

Nov-05

Dec-05

Jan-06

Feb-06

Mar-06

Car

ats

Marine Production

0

1000

2000

3000

4000

5000

6000

Ave04-05

Apr-05

May-05

Jun-05

Jul-05

Aug-05

Sep-05

Oct-05

Nov-05

Dec-05

Jan-06

Feb-06

Mar-06

Car

ats

Alexkor Own Mining

0

100

200

300

400

500

600

700

800

900

Ave04-05

Apr-05

May-05

Jun-05

Jul-05

Aug-05

Sep-05

Oct-05

Nov-05

Dec-05

Jan-06

Feb-06

Mar-06

Carats

Page 31: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Positive Trend: Reduction in Direct Working Costs

0

20

40

60

80

100

120

140

160

180

200

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Ran

d / C

ubic

Mining Expl Sweep IFS Noord Voltas F Rec Transp

Page 32: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Continuous Effort on Reducing Cut-off Grade

0

10,000

20,000

30,000

40,000

50,000

60,000

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Cub

ics

0.0

2.0

4.0

6.0

8.0

10.0

12.0

Cph

c

Cubics Cut-off (cphc)

Page 33: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Possible Growth Opportunities

Page 34: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

DREDGER PROJECT – A vessel applying techniques on sea floor

Page 35: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Dredger Project - Concept

Dredge• This a vessel that dredges the sea floor sediment and suck it into the hold of the vessel

Sail and Connect• The vessel sails to a land-to-sea pipeline 600m off-shore

Discharge• Contents of the vessel is pumped to land based holding ponds via the pipeline

Treatment• The material is screened, loaded and trucked to a plant for diamond recovery

Page 36: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Dredger project – Financial ImplicationsCapital Required

Pipeline R25,000,000

Mobilisation Once off R15,000,000

Dredging 1 month R750,000 per day R22,000,000

1 month dredging 34 000 cts recovery R88,000,000 revenue

Treatment on land 10 months at Noordsif R6,500,000

Equipment + Infrast. R16,000,000

OPERATING COST (1 month dredging)

REVENUE

PROFIT R44,500,000

Page 37: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Dredger Project - Summary

Successfully undertaken on a trial basis by Namdeb

Positives• Will bring resource deeper than 20m water depth to account•Potential for lower cut off grade than conventional remote mining techniques •Not affected by sea conditions to the same extend as diving operations• Extended life of treatment plants

• Negatives• High overheads associated with the project :

• Pipeline R25 000 000 (reusable)• Mobilisation of vessel (can be shared with Namdeb)• Charter rate of the dredge vessel

Page 38: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Implementation of Remote Mining

• Awarded four remote mining contract, one expected to start in

June 2006

• Vessel based remote mining methods are expected to operate

between 15 and 20 days per month as opposed to the diver

operated units of 4 days per month.

Page 39: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Sale of Production in Open Market

$ 0

$ 1 0 0

$ 2 0 0

$ 3 0 0

$ 4 0 0

$ 5 0 0

$ 6 0 0

A p r-0 5 M a y -0 5 J u n -0 5 J u l-0 5 A u g -0 5 S e p -0 5 O c t-0 5 N o v -0 5 D e c -0 5 J a n -0 6 F e b -0 6 M a r-0 6

D I A M D E L V A L U A T O R S T A T E V A L U A T O R

Page 40: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Product is of good quality – good potential exists

0

100

200

300

400

500

600

Apr-05

May-05

Jun-05

Jul-05

Aug-05

Sep-05

Oct-05

Nov-05

Dec-05

Jan-06

Feb-06

Mar-06

1,000

1,500

2,000

2,500

3,000

3,500

Average $/ct Ave R/ct

Page 41: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Update on Legal Matters

Page 42: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Uncertainties and Litigation Issues• Good progress on the Land Claims case with the signing of the MOU by

Government, Alexkor and CPA

• Awaiting court proceedings and ruling on other legal matters

– Coin Security claim amounting to R 2.7 m

– Ruslyn Mining Claim amounting to R 19 m

– Nabera claim amounting to R 4.2 m and R 119 m (part of claim against State)

• Financial implications include legal fees and possible compensation

• Limited provision has been made for payment of possible settlement amounts

Page 43: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Social Responsibility and Transformation

Page 44: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Social Responsibility and TransformationSkills Development:

• Providing bursaries to six students, of which 3 are females.

• Facilitating mentorship programmes with 11 HDSA Protégés, of which 5 are females.

• Currently training 11 HDSA apprentices, of which 2 are females.

• The earthmoving team comprises 36 employees, of which 3 are females.

• Trained 3 females as infield screen operators in early 2006.

Page 45: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Social Responsibility and Transformation

• Conducting ABET classes to improve literacy, numeracy and life skills of employees and community.

• Alexkor expended 3.14% of total wage bill in 2005/2006 FY on training.

• Providing Health Care and emergency services to Alexander Bay and Richtersveld Communities

• Maintenance of Alexander Bay town, (including water and seweragepurification) and providing portable water to A/Bay and Port Nolloth.

• Ad-hoc donations & rental subsidies of R11 million for period 2000-2005

• Involvement in HIV/Aids awareness projects

• Donated 2 Wheelchairs for disabled members of the community.

Page 46: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Employment Equity, as at 30 April 2006 (ABM)

POSITIONNUMBER OF

INCUMBENTS A C W A C W

% OF DESIGNATED

GROUP DISABLED

Senior Management 6 1 1 3 - 1 - 50%

Professionaly Qualified 14 3 2 5 1 1 2 64% 2

Skilled 71 - 22 38 - 3 8 46%

Semi Skilled 187 5 126 19 - 25 12 90%

Unskilled 26 1 17 - 8 - 100%

Total 304 10 168 65 1 38 22 79% 2

MALE FEMALE

2 Members of Senior Management resigned in February 2006, to be replaced soon.

Page 47: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Marine Mining Contractors Structure

MALE FEMALE

POSITION BEE NON BEE BEE NON BEE

Shareholders 177 46 39 9

Employees 477 18

The BEE shareholding on all Marine contractors is 50%

Page 48: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Conclusion

Page 49: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Conclusion

• Short-term focus is on improving financial performance:

– Optimise the use of available resources

– Implement initiatives for productivity improvement

– Continuous reduction of both operating costs and pay-limit

• Implement short to long term strategic objectives to transform the company

• Collaborate with established companies and leverage on their ability to fund

expansion plans

• Speed up the implementation of remote mining techniques

• Look at ways of obtaining funding for Capex and exploration programs

Page 50: New Update to Portfolio Committee 03 May 2006 · 2015. 1. 30. · 80 100 120 140 160 1 6 97 19 98 19 99 00 20 01 20 02 03 0 4 20 05 06 20 07 bud Sea Days. ... Mining Expl Sweep IFS

Thank you