Flow direction colour code
Project management schedule, methodology and execution planning For EPC projects.
Caution Good to go
Proceed with Utmost Caution
Marketing and advertisement to reach customer. Project contract legal to be signed with customer including all legality with penalties and rewards.
IF initial sale is done , one get the project order.
Marketing , getting order and sales methodology.
Start
End
Start of project life cycle.
Project Planning after Initial sales or initial project order, This step is done in-house in engineering and management department.
Initial project conceptualisation with the study of project area and environment, government policies, landscape etc. This step is done with the earlier step or process .
Yes feasible.
A2 A1
A1 A2
Engineering planning and engineering design with costing and engineering risk calculation, etc.
Management planning, costing with management risk costing calculation.(logistic, Human resource, licenses, etc.)
If costing calculated is less than payment to be done by customer than project is good to go otherwise negotiations with customer.
B- B+
B- B+
If payment by customer is less than expected after calculation of engineering and management team and negotiation fails for further increase in payment. “Need to abandon the project can rise too.
C-
If payment by customer is greater or equal to costing calculated by engineering costing + management costing team + expected margin , project is good to go.
C+
If Negotiation succeeded and customer agrees to increase payment
C- C+
Discussion among management and entire project team over what went wrong in the project should be done, All the negative and positive lesson and understanding and records should be maintained for future betterment and avoidance of the reasons of failure.
End of process for this project
Setup of project office at site, if mobile office is available move it to site establish it. And arrangement of living spaces for contract and permanent workers
Order for the requirement should be placed with vendors and own production unit, with all specification and policies and schedule of delivery at site.
Requirement for further contract workers should be forwarded to Human resource department, with schedule expected.
E1 F1 D1
Arrangement through advertisement and selection through different HR firm dealing in contract workers of different skills and educational background.
E1
Rough Quality check prior to loading of supply material to site or before start of logistic from vendor to site.
Arrival of contract workers to site.
D1
D11
Logistic of the accessories and equipment required for the construction to site, This process can be given any reputed reliable logistic company.
E11
F1
Inspection of the Site office for standards and security prior to start of proper construction at site.
F11
D11
Assignment of supervisor for contract labours and managers to contract engineers if any. Assignment of safety officers etc.
E11
Rough Quality check after offloading of the equipment or construction material at site. Assessment of damage. Record should be kept for monetary assessment.
F11
Handing over the construction site office, living space and equipment to assigned authority and workers.
D22 E22 F22
D22 E22 F22
Onsite construction needs and action.
It is better to have construction of site in division of small modules, Quality check should be done after completion of each small modules, If quality is good. Not good dismantle check with other same part.
Keep records of the product and supplier. For monetary assessment.
Up to expectation
Complete project till end with all modules or segments M1
M0
M0M1
Final Quality check before commissioning. With all modules
Check for good commission.
Yes No
Hand over to customer. Check for default, then rectify.
End of project process
M1M2 M2M3
Learning
All the pros and cons should be listed while doing the project. Deviation from pre planned activity should be listed and discussed. If there is change in project implementation cost , it should be listed and discussed further. All deviation and wastage of money, material and time should be listed. Six Sigma methodology should be followed with the project through out, and deviation should be listed and pondered upon.
Learning
M(n)M(n+1) This is module section symbol. Module construction can be done Parallel, in Series or Mixed Parallel and Series. Beginning & End location Say Valve can be fixed. Construction can be done between fixed location. Few Onsite pipe construction and modelling can be done to compensate any deviation. For any deviation there are processes to go through in each firm.
Series and parallel construction of modules.
Total time will be calculated on type of construction. If all parallel(though is not good and feasible) time required for one module is time required for all modules. If all series time required will be summation of time for all modules. If x1 time is time for first phase parallel for M0M1,M1M2,M2M3 modules and y1, y2, y3 for further series for M3M4,M4M5,M5M6 modules total time would be(x1+y1+y2+y3) for 6 above written modules.
Time Schedule Calculation of project.
For contract workers, Safety Officers can be deployed as group manager and contact person for controlling the group, If safety officer have prior experience with construction then it is good to have safety officer as group leader. For engineering Managers one can also have safety manager with prior qualification in bachelor of engineering and management experience and safety experience. Both managers group can be used as window of communication between Management and Contract workers and engineers. For Site project.
Supervisor and Engineering onsite manager
As line production and as inventory is maintained , logistic requirement and schedule should also be maintained for required material, and orders should be placed on requirement. Setup of quality check offices should be done for inventory management and scheduling.
Few Actions that is to be taken on site.