new nuclear power plants need and status asq-eed 31 st energy & environmental division...
TRANSCRIPT
New Nuclear Power PlantsNeed and Status
ASQ-EED 31st Energy & Environmental Division Conference
September 12, 2004
Adrian Heymer, [email protected], 202-739-8094
Nuclear Power PlantsCurrent Status
• 103 Operating Units– One under major refurbishment
– Average capacity factor ~ 90% over last 4 years
• 20% of US electricity capacity -- Nuclear• 30% US generation is emission-free
– 70% Nuclear; Hydro 18%; Wind 1%; Solar 0.1%
• Eliminates ~700 million tons/year of Greenhouse gases
Safety & Economic Improvement
20
30
40
50
60
70
80
90
100
90 91 92 93 94 95 96 97 98 99 00 01 '02 '03
65
70
75
80
85
90
95
Relative CostRisk (CDF) Capacity Factor
Year
Based on UDI, DOE & NUS Data plus info. from ERIN Eng & EPRI
Relative Cost
Relative Risk
CapacityFactor
The Need for New Nuclear
• US needs 300,000+MW of new generation by 2025
• Increased environmental controls raise siting and cost problems for fossil fuel plants
• US industry needs low cost energy to sustain global competitiveness– A diverse and balanced generating portfolio– Non/low-emission base-load generation – Greater energy independence
• Nuclear lowest cost base-load generating option
Natural Gas PricesHenry Hub
Mar-2003$8.06
Jan-2001$9.13
$0.00
$1.00
$2.00
$3.00
$4.00
$5.00
$6.00
$7.00
$8.00
$9.00
$10.00
Jan-95
Jul-95
Jan-96
Jul-96
Jan-97
Jul-97
Jan-98
Jul-98
Jan-99
Jul-99
Jan-00
Jul-00
Jan-01
Jul-01
Jan-02
Jul-02
Jan-03
Jul-03
Jan-04
$/M
MB
tu
Why No New Nuclear for 30 Years?
• Until mid 90s, anemic operating record• Unpredictable licensing & regulatory process• Design/Construct-As-You-Go approach
– Unreliable and prolonged construction
• Cost of financing large capital intensive projects in competitive market– Need for innovative approach to financing– Not unique to nuclear
• Need for certainty in spent fuel disposal
Improved Approach for Licensing New Plants
• Make licensing process more efficient and performance-based– Resolve issues as early as possible
– Make more information available earlier
– ITAAC concept
– One hearing -- opportunity for a second, if acceptance criteria not satisfied
– Bank sites & pre-approve standard designs
• Complete design prior to construction
Financing New Nuclear Plants
• Significant changes since 1970s– Many companies not operating in cost-of-service
• Wall Street nervous over improved, yet unproven licensing process
• Large capital projects diminish financial performance metrics
• Innovative approaches to financing large capital projects– Consortium approach– Public-Private financial structure for large projects that support
essential national infrastructure– Loan guarantees, accelerated depreciation, low cost loans,…
Public Perception
• Wide ranging policymaker support– Congress & current Administration
• Majority of US public support nuclear power plants (60% vs 36%)– Greater among graduates
• Public support is substantial, but not deep– Need for continuing education
– Existing plants need to maintain high standards of safety performance
New Plant Status
• Three designs certified -- Eight in pipeline– LWR & non-LWR designs
• Three Early Site Permits under review -- 2006• Three consortia testing new COL process
– DOE-industry partnership -- awaiting DOE decision– 16 companies involved– Industry committed to multi-year project - $650M– Trial license applications being developed– Decisions to order ~ 2008– Start construction 2009-2010
New Plant Status
• Combined construction and operating license application guideline scheduled to be submitted 12/04 for NRC endorsement in 2005
• 24 issues linked to new licensing process• Most being addressed through the NRC review of the COL
application guide
• NEI Executive Task Force provides oversight of industry issue task forces
• Interactions with Congress, States & Wall Street
Need for Continued US Global Leadership in New Nuclear
• One third of the world has no electricity• Estimate 70%+ growth in global demand for
electricity over next 20 years– If fossil, what’s the impact on the environment &
price?
– If not fossil, then?
• US is a leader in nuclear power technology– If no new nuclear orders in US, technical leadership
will be relinquished to Asia, Africa & Europe
Generation IV & Hydrogen
• Without Gen III (AP1000 et al) no Gen IV– 50% of workforce will retire in the next decade– Knowledge retention a major issue
• Hydrogen – need for pilot plant activities to test & develop infrastructure– Hydrogen is where gasoline was in 1890s
• Huge potential for nuclear energy• Long-term need for simplified designs
Need for Involvement
• Get involved– YGN, Dominion, a superb example of nuclear
workers advocating, on their own time, the benefits & need for nuclear energy
– Speak out & attend meetings in your local area– Write to your Congressman, Senator and local
officials
New Nuclear Plants?
• Yes, if:– Prove new licensing process is predictable & stable
– Establish a financial structure for financing large capital cost projects
– Nation gets serious about environment
– Certainty on spent fuel disposal
• Energy costs, the economy & environmental issues will overcome hard-core opposition
Nuclear Energy• Nuclear power plants are safe• US needs a diversified and balanced energy
portfolio that provides low-cost and reliable electricity– Nuclear energy is an essential element in
maintaining US global competitiveness
• More information at: – http://www.nei.org – Public website– http://member.nei.org/ -- for NEI members