new matt gudorf campus energy manager · 2012. 12. 6. · meter specs • 12 channels per board •...

58
Page 1 Matt Gudorf Campus Energy Manager

Upload: others

Post on 17-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 1

Matt GudorfCampus Energy Manager

Page 2: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 2

Quick Facts About UCI• 7.4 Million Square Feet of Conditioned Space• District High Temp and Chilled Water• Campus 12kV owned and operated grid• 4.5 Million Gallon Thermal Energy Storage Tank• 13 MW average load• 120 Million kWh per year

• Laboratories make up 66% of the campus load

Page 3: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 3

0

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

8,000,000

9,000,000

10,000,000

$-

$2,000,000

$4,000,000

$6,000,000

$8,000,000

$10,000,000

$12,000,000

$14,000,000

$16,000,000

$18,000,000

$20,000,000

2004 2005 2006 2007 2008 2009 2010 2011 2012

Cam

pus G

SF

Utility Costs

Total Variable Costs w/o SEP Total Variable Costs with SEP Campus GSF

Co-Gen Installed

UCI Begins SEP Program

Energy Cost Without Projects

Energy Cost with Projects

Page 4: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 4

UCI’s Strategic Energy Plan (SEP)• Identify and implement projects using the energy savings to pay

back the cost of the project.• Maximize Federal, State, and Local incentives to reduce the

project cost.• Combine base projects with low return on investment with “next

steps” to create acceptable returns with large energy savings.

Calendar yearTotal Project Cost Incentive

Received Bond Program Project costs

Annual Loan Payment

Amount(1)

Annual Total Energy Cost

Savings ($/yr)

Ratio of energy savings to debt

2009 $ 14,718,458 $ 4,388,332 $ 9,244,231 $ 963,644 $ 2,053,116 2.13

2010 $ 12,805,306 $ 2,586,284 $ 9,053,838 $ 1,032,800 $ 1,294,404 1.25

2011 $ 12,575,725 $ 2,899,496 $ 8,391,243 $ 872,093 $ 1,281,646 1.47

Page 5: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 5

Monitoring and Verification Capabilities

1. What level of metering do you have?2. What level of metering do you need?3. Where is the information you need?4. What metrics should I trend and make decisions with?

Page 6: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 6

ZONE-LEVEL USE

BUILDING SYSTEM USE

TOTAL ENERGY USE

Look Closer … Find More Savings

BUILDINGElectric and Gas Meter

EMSHVAC, pumps, chillers

EMS, CDCVFume hood use,

IAQ, thermal demand

Submeteringlighting, plug load

EMSboiler, water heater

CDCV, EMSreheat

At the zone level, measurement and verification resolution are so highThat you are essentially constantly commissioning the building .

Page 7: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 7

Building Management System

Page 8: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 8

Cost-Effective SubmeteringMeter Specs

• 12 channels per board• Meter accuracy +/- 0.5%

(0.25% typical)• V, I, active energy, reactive

energy, power factor

Current Transformer Specs• Sensor accuracy +/- 1%• Current transformers 60-400 amps• Clamp-on installation

Page 9: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 9

Clamp-on CTs installed

Meter installedConnected to Internet

Page 10: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 10

00 140610KWH

mel rokC o r p o r a t i o n

dangerhigh vol t age

Acquisition SWSQL Express DB

00 140610KWH

mel rokC o r p o r a t i o n

dangerhigh vol t age

Database Server

Multiple Users

EnerACQ User Interface

User PC

EnerACQ User Interface

User PC

Individual 12 Channel Meters

System Description

Page 11: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 11

Visualization of Lab Energy Use

Page 12: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 12

Dashboard Design

Page 13: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 13

Where did UCI start?Conventional

• Complex, multi-vendor architectures

• Multiple points of failure

• Requires integrator services

• Expensive

Ethernet Interface

Vendor #1 Vendor #2

Vendor #3

Page 14: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 14

Where are we going?MelRoK

Simple & Effective Energy Information Service

W.A.G.E.S.

Big Data Analytics

Utility + Weather Data

EnergiStream

BMS Connectivity

Server

AircuityLab Air Flow Monitoring

Indoor Air Quality MonitoringFume Hood Sash Management

Page 15: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 15

Total Building Load

Watts / Square FootTherms / Square Foot

LightingWatts / Square FootInterior Load vs Exterior LoadDaytime Load vs Nighttime LoadLighting Load per Floor

HVACWatts / Square FootTherms / Square footDaytime Load vs Nighttime LoadCFM per Zone

Plug LoadWatts / Square FootDaytime Load vs Nighttime LoadPlug Load per FloorFixed Load vs User Load

LEED®Energy Star®Labs 21 Benchmarks

Information that is actionable

Metrics That Can Lead to Action

Page 16: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 16

The Framework

• Establish baselines for building pre- and post- energy improvement measures (EIM)

• Establish baselines for energy equipment pre- and post- EIM• Automated and continuous comparison of building and

equipment performance relative to baselines• Fast detection of any deviation from post-commissioning

performance• Automated alerts when anomaly detected at building or

equipment level• Integrated approach: Power, Gas, Chilled Water, Hot Water and

Environmental Sensors

Page 17: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 17

Lighting SEP Projects

Parking Structures HPS to Bi-Level InductionRoadways HPS to InductionPathways HPS and Metal Halide to FluorescentAll T8-32W lamps to T8-25W, NLO Ballast to RLO BallastBi-Level Stairwells / CorridorsDaylighting controlsTime Clock and BMS controls

32 Watt T8

25 Watt T8

NLO Ballast .87-.90 BF

RLO Ballast.71 BF

15,000 Fixtures saving 2,550,000 kWh

Page 18: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 18

Changed how we zone

Auto on to 50% Manual on to 100% Auto off

Changed how we sequence

Page 19: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 19

Lighting is controlled per lab bay -- not per lab -- to maximize savings.

Lighting

Page 20: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 20

LED Task Lighting

Magnetically mountedLED task lighting

Page 21: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 21

Mechanical System SEP Projects

• Constant Air Volume to Variable Air Volume• Constant Flow to Variable Flow• Pneumatic to Direct Digital Control• Static pressure reset• Supply air temperature reset• Occupancy based control of HVAC• Exhaust Stack Discharge Velocity Reduction• Centralized Demand Controlled Ventilation

Page 22: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 22

Centralized Demand Controlled Ventilation

• Monitors the indoor air quality of multiple zones through a network of structured cables and air data routers

• Analyzes the sampled air with a series of sensors• Provides the lab air control system with an input for

increased ventilation when necessary. • The system is only an input to your lab air control system,

no different than a thermostat, or sash position sensor.

Target is 4 air changes per hour in occupied labs and 2 air changes per hour in unoccupied labs.

Page 23: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 23

Lab Room 101 Lab Room 102 Classroom 103 Supply Air Reference

Probe

Web Based User Interface

BMS Connectivity

Sensor Suite with TVOC,

CO2, dewpoint & particulate

sensors

Air Data Router

Vacuum Pump

Server

Room Sampling

Port

Supply Air Duct

General Exhaust Duct

GEX Duct Probe (typ.)

Air Data Router

CDCV System Architecture

Page 24: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 24

CDCV ComponentsSensor Suite

Structured Cable

Duct Probe

Vacuum Pump

Air Data Router

Page 25: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 25

• Air change rates (ACR)• Internal air quality (IAQ)• Sash position of each fume hood• Occupancy• Relative humidity• Temperature• Total supply• Total exhaust

CDCV SystemDashboard and Data Trends for Each Zone

Page 26: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 26

Visualization of lab HVAC use

Page 27: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 27

• Fume hood usage range• This hood shows usage between 0%

open and 65% open.

• Change in average sash position from the month prior• Red indicates poorer average green indicates improved

average sash management

Monitoring Fume Hood Usage

Page 28: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 28

Smart Labs are not just controls and sensors.

Smart Labs provide real time feedback as well as monthly reporting data that is actionable.

Return on investment is directly affected by lab practices.

How many hoods are in use right now in your laband how far open are the sashes?

Page 29: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 29

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

Sun

day

4/3

/11

18

:11

Mo

nd

ay 4

/4/1

1 2

:24

Mo

nd

ay 4

/4/1

1 1

0:5

0

Mo

nd

ay 4

/4/1

1 1

9:0

0

Tue

sday

4/5

/11

3:1

3

Tue

sday

4/5

/11

12

:38

Tue

sday

4/5

/11

20

:45

We

dn

esd

ay 4

/6/1

1 4

:55

We

dn

esd

ay 4

/6/1

1 1

4:5

6

Thu

rsd

ay 4

/7/1

1 0

:46

Thu

rsd

ay 4

/7/1

1 1

1:0

9

Thu

rsd

ay 4

/7/1

1 2

1:0

4

Frid

ay 4

/8/1

1 7

:55

Frid

ay 4

/8/1

1 1

8:2

6

Satu

rday

4/9

/11

2:3

7

Satu

rday

4/9

/11

10

:47

AC

H

CFM

Total Flow & ACHAll labs, Sunday to Saturday

Total Supply

Total ACH

Total Flow and ACH ProfileSix-Day Period

Page 30: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 30

0

2

4

6

8

10

12

14

Sund

ay 4

/3/1

1 18

:11

Mon

day

4/4/

11 2

:24

Mon

day

4/4/

11 1

0:50

Mon

day

4/4/

11 1

9:00

Tues

day

4/5/

11 3

:13

Tues

day

4/5/

11 1

2:38

Tues

day

4/5/

11 2

0:45

Wed

nesd

ay 4

/6/1

1 4:

55

Wed

nesd

ay 4

/6/1

1 14

:56

Thur

sday

4/7

/11

0:46

Thur

sday

4/7

/11

11:0

9

Thur

sday

4/7

/11

21:0

4

Frid

ay 4

/8/1

1 7:

55

Frid

ay 4

/8/1

1 18

:26

Satu

rday

4/9

/11

2:37

Satu

rday

4/9

/11

10:4

7

ACH

Typical Lab flow profileSingle Lab, Sunday to Saturday

RM 1200B.RM 1200 ACH

Air Change Rates for Room 1200Graphed Over Six Days

Page 31: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 31

Plug Load

• Outside the direct control of the facility manager• Growing rapidly with increases in automated lab

equipment• No current method for control or containment?• Lack of Energy Star® label for lab equipment• Few to no requirements to purchase most energy

efficient equipment when using grant funding.

Page 32: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 32

A Pristine (Unassigned) Lab

Page 33: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 33

Page 34: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 34

Page 35: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 35

Page 36: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 36

Page 37: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 37

HDP1 is a distribution board on the 1st floor. It is responsible for feeding several equipment loads, autoclave units EQ2, EQ3, and EQ4. HDP1 is fed directly from the main switchboard at 480/277 volts. The board maximum current rating is 225 amps. The largest load on HDP1 is the medium autoclave EQ2, which is rated at 75kVA.

Auto

clav

e In

Gro

ss H

all

60 kW peak

Zone-Level Resolution Can Lead toPeak Demand Savings

Page 38: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 38Gross Hall average site demand ranges from a baseline of 148kW to an average peak of 205 kW

Autoclave EQ2

Did running the autoclave on peakjust cost you $600 in demand charges?

Zone-Level Resolution Can Lead toPeak Demand Savings

Page 39: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 39

Hewitt Hall vs. Gross Hall

Designed in 2001• Exceeded Title 24 by 23.7%• Biomedical research• Lighting upgrade in 2009• Exhaust stack discharge velocity

Reduction in 2009• Re-commissioned in 2010• 76,905 square feet

Designed in 2009• Exceeded Title 24 by 50.4%• Biomedical research• Designated LEED Platinum - NC• 94,705 square feet

Page 40: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 40

Gross Hall’s Lab UtilizationNearly Twice Hewitt Hall’s

0%

20%

40%

60%

80%

100%

Gross Hall Hewitt Hall

58%27%

Percent Occupied by Building (7 days)

Page 41: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 41

-

1.00

2.00

3.00

4.00

5.00

6.000:

151:

001:

452:

303:

154:

004:

455:

306:

157:

007:

458:

309:

1510

:00

10:4

511

:30

12:1

513

:00

13:4

514

:30

15:1

516

:00

16:4

517

:30

18:1

519

:00

19:4

520

:30

21:1

522

:00

22:4

523

:30

Wat

ts p

er S

quar

e Fo

ot

Time of Day

Watts / Gross Square Foot

Hewitt Hall

Gross Hall

Building Load Per Square Foot

Page 42: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 42

AHU + EF + Pumps + Chilled WaterBuilding Square Feet

0

1

2

3

4

5

6

0:15

0:45

1:15

1:45

2:15

2:45

3:15

3:45

4:15

4:45

5:15

5:45

6:15

6:45

7:15

7:45

8:15

8:45

9:15

9:45

10:1

510

:45

11:1

511

:45

12:1

512

:45

13:1

513

:45

14:1

514

:45

15:1

515

:45

16:1

516

:45

17:1

517

:45

18:1

518

:45

19:1

519

:45

20:1

520

:45

21:1

521

:45

22:1

522

:45

23:1

523

:45

Wat

ts p

er S

quar

e fo

ot

Hewitt Hall Gross Hall Gross Total Building Hewitt Hall Total Building

1 Watt /1000 x 8760 hours x $0.105kWh= $0.92 /SqFt

Page 43: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 43

Previous Best Practice

Space Type GrossHall

0.9 watts/sqft Offices

0.49 watts/sqft

1.1 watts/sqft Labs

0.66 watts/sqft

1 watts/sqft Overall Conditioned Space

0.61 watts/sqft

00.10.20.30.40.50.60.70.80.9

1

0:15

1:30

2:45

4:00

5:15

6:30

7:45

9:00

10:1

511

:30

12:4

514

:00

15:1

516

:30

17:4

519

:00

20:1

521

:30

22:4

50:

00

Wat

ts P

er S

quar

e Fo

ot

24 Hour Actual Watts Per SQFT

Hewitt Hall Watts Per Sqft Gross Hall Watts Per Sqft

02468

101214161820

0:15

1:15

2:15

3:15

4:15

5:15

6:15

7:15

8:15

9:15

10:1

511

:15

12:1

513

:15

14:1

515

:15

16:1

517

:15

18:1

519

:15

20:1

521

:15

22:1

523

:15

kW

24 Hour Demand Curves

Hewitt Hall 2nd Floor Lighting Demand

Gross Hall 2nd Floor Lighting Demand

0.3W/1000 x 8760 x$0.105kWh= $0.2759 /SqFt

Lighting

Page 44: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 44

Lab Air Supply and ExhaustHewitt Hall – 2nd floor• 6 Air changes per hour minimum• No set back during unoccupied periods• Zone presence sensors on fume hoods

Gross Hall – 2nd floor• 4 Air changes per hour minimum occupied• 2 Air Changes per hour minimum unoccupied• Zone presence sensors on fume hoods• Centralized Demand Controlled Ventilation

system adjusting ACH for indoor air quality.

Lab 2501 Lab 2200

Page 45: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 45

Evidence of Where Building’sHVAC Energy Savings are Achieved

• Air change rates are dynamic responding to occupancy, IAQ, sash position, and thermal demands

• Lab 2200 averages 4 air changes per hour

• Air change rates are dependent on sash position and thermal demand.

• Lab 2501 averages 8 air changes per hour Hewitt Hall

Lab 2501

Gross HallLab 2200

Page 46: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 46

Lab Air Flow vs. Time• The HVAC savings of 1 CFM/ft2 at $4-5 per CFM can reduce

operational significantly. • A 1 CFM reduction at Hewitt Hall in just the open lab bays

would reduce operational cost by $83,250 per year

0.00

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

1.80

8/17

/11

13:4

1

8/17

/11

21:4

1

8/18

/11

5:41

8/18

/11

13:4

1

8/18

/11

21:4

1

8/19

/11

5:41

8/19

/11

13:4

1

8/19

/11

21:4

1

8/20

/11

5:42

8/20

/11

13:4

2

8/20

/11

21:4

2

8/21

/11

5:44

8/21

/11

13:4

4

8/21

/11

21:4

4

8/22

/11

5:46

8/22

/11

13:4

6

8/22

/11

21:4

6

8/23

/11

5:48

8/23

/11

13:4

8

8/23

/11

21:4

8

8/24

/11

5:49

8/24

/11

13:4

9

8/24

/11

21:4

9

8/25

/11

5:50

8/25

/11

13:5

0

8/25

/11

21:5

0

8/26

/11

5:52

8/26

/11

13:5

2

8/26

/11

21:5

2

8/27

/11

5:53

8/27

/11

13:5

3

8/27

/11

21:5

3

8/28

/11

5:55

8/28

/11

13:5

6

8/28

/11

21:5

6

8/29

/11

5:57

8/29

/11

13:5

7

8/29

/11

21:5

7

8/30

/11

5:59

CFM

/ Sq

. Ft.

CFM / Square Foot ComparisonGross Hall vs. Hewitt Hall

Gross CFM/ Sq. Ft.

Hewitt CFM / Sq. Ft.

1.53 CFM/ ft2 average.

0.52 CFM/ ft2 average.

Page 47: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 47

BenchmarkingIt is easy to see how campus labs compare to each other but what about across the country?

http://labs21benchmarking.lbl.gov/CompareData.php

Page 48: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 48

Adding Hewitt and Gross Halls

• Hewitt is right at the average• Gross Hall beats the most efficient lab

benchmarked by 18%

Page 49: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 49

Continuous Commissioning

-- Meaningful analysis and reports-- Actionable information-- Verification of actions taken:

physical and behavioral

CDCV• Find failed lab air control

valves• Review of fume hood sash

management• Ensure safe lab air quality• Find excessive air flows

due to point sources of heat

Submetering• Monitoring of fans, pumps,

and lighting control systems

• Verification of energy retrofits

• Reduce demand charges by modifying operations

BMS• Locate simultaneous

heating and cooling• Reset of static pressure to

minimum required• Control run times of office

areas

Page 50: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 50

Troubleshooting a CO2 leakWith the CDCV System

• Researcher connects 4 tanks of CO2 to the lab distribution system and within 8 hours they are empty.

• To find the leak the research staff could have spent hours soaping lines and connections and wasting additional gas listening for the leak.

Page 51: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 51

Suspected location of CO2 leak

Researcher first plotted all rooms for CO2

Page 52: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 52

The leak was quickly located and repaired!

Researcher Then Plotted the Roomwith the Suspected CO2 Leak

Page 53: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 53

The Knowledge Center has been used to locate lab equipment placedtoo close or under thermostats.

Discovery of Lab Equipment Driving Thermal Demand

Page 54: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 54

Return on InvestmentCommissioning

– Cx, Rx, MBCx is approximately $2 per SqFt– Hewitt Hall MBCx $131,309– Net present value for 10 years (MBCx every 5 years) Hewitt Hall

$113,590

$(100,000.00)

$(50,000.00)

$-

$50,000.00

$100,000.00

$150,000.00

$200,000.00

$250,000.00

1 2 3 4 5 6 7 8 9 10 11

Cumulative Cash Flow MBCx Project

MBCx Cumulative Cash Flow MBCx Net Savings

MBCx

Page 55: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 55

$(200,000.00) $-

$200,000.00 $400,000.00 $600,000.00 $800,000.00

$1,000,000.00 $1,200,000.00 $1,400,000.00

1 2 3 4 5 6 7 8 9 10 11

Cumulative Cash Flow

Smart CCx Cumulative Cash Flow Smart CCx Net Savings

Sub metering and monitoring your lab can be very competitive with the cost of a single commissioning effort.

CDCV ~$3.12 per SqFtSub metering $0.20 per SqFtHewitt Hall Sub Metering and CDCV $302,888Net present value for Hewitt Hall continuous commissioning (10 years) $665,903

Page 56: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 56

Return on InvestmentSmart CCx − although a larger initial investment − provides for greater long-term savings as well as strategic analysis, monitoring, and savings that cannot be accomplished with traditional MBCx.

$(200,000.00)

$-

$200,000.00

$400,000.00

$600,000.00

$800,000.00

$1,000,000.00

$1,200,000.00

$1,400,000.00

1 2 3 4 5 6 7 8 9 10 11

Cumulative Cash Flow MBCx vs. SMART CCx

Smart CCx Cumulative Cash Flow Smart CCx Net Savings MBCx Cumulative Cash Flow MBCx Net Savings

Page 57: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 57

Final Thoughts

• Monitoring or constant commissioning is a must.

• UC Irvine has deployed the CDCV system to 13 buildings covering 1500+ zones.

• UC Irvine has awarded a contract to sub meter the almost all campus buildings. Monitoring each building and load centers within each building.

• Maintaining the savings invested in is the keyreason for choosing to deploy the technologies.

Page 58: New Matt Gudorf Campus Energy Manager · 2012. 12. 6. · Meter Specs • 12 channels per board • Meter accuracy +/- 0.5% (0.25% typical) • V, I, active energy, reactive energy,

Page 58

QUESTIONS?