new construction - berea city school district · 2019-11-25 · alternate no. 1 - additional...
TRANSCRIPT
New Construction
PROGRESS UPDATE
October 2019
Brook Park Elementary School
TA B L E O F C O N T E N T S
1
2
3
4
5 - т
у
ф
м0 - 17
EXECUTIVE SUMMARY
PROJECT SUMMARY/ KEY PLAN
COST SUMMARY / CHANGE LOG/ CONTINGENCY (Ford Demo)
COST SUMMARY (Brook Park)
CHANGE LOG (Brook Park)
CONTINGENCY RECONCILIATION (Brook Park)
PROJECT SCHEDULE
PROGRESS PHOTOS
EXECUTIVE SUMMARY
PROGRESS: Brook Park Elementary School
Area A:
• Roofing — 90% Complete
• Brick Veneer — 90% Complete
• Windows — 60% Complete
• Interior Wall — 90% Complete
• Electrical Rough-in — 100% Complete
• Plumbing Rough-in — 100% Complete
Area B:
• Roofing — 85% Complete
• Exterior Stud Walls — 80% Complete
• Brick Veneer — 90% Complete
• Interior Stud Wall — 50% Complete
• Electrical Rough-in — 85% Complete
• HVAC Piping Rough-in — 75% Complete
• Ductwork Rough-in — 75% Complete
• Plumbing Rough-in — 100% Complete
• Drywall — 50% Complete
Area C
• Brick Veneer — 100% Complete
• Windows — 100% Complete
• Interior Stud Wall — 100% Complete
• Electrical Rough-in — 100% Complete
• HVAC Piping Rough-in — 100% Complete
• Plumbing Rough-in — 100% Complete
• Ductwork Rough-in — 100% Complete
• Fire Sprinkler Rough-in — 100% Complete
• Drywall — 80% Complete
• Drywall Finishing — 75% Complete
• Paint — 15% Complete
• Overhead Doors — 70% Complete
• Tele/Comms Rough-in — 75% Complete
Area D: 1st Floor
• Brick Veneer — 100% Complete
• Windows — 100% Complete
• Interior Stud Wall — 100% Complete
• Electrical Rough-in — 100% Complete
• HVAC Piping Rough-in — 100% Complete
• Plumbing Rough-in — 100% Complete
• Ductwork Rough-in — 100% Complete
• Fire Sprinkler Rough-in — 100% Complete
• Drywall — 5% Complete
Area D: 2nd Floor
• Roofing — 40% Complete
• Brick Veneer — 100% Complete
• Windows — 100% Complete
• Interior Stud Wall — 80% Complete
• Electrical Rough-in — 15% Complete
• HVAC Piping Rough-in — 50% Complete
• Ductwork Rough-in — 70% Complete
• Plumbing Rough-in — 50% Complete
Sitework:
• Site Underdrain — 65% Complete
• House Gas Line — 100% Complete
• Water/Fire Line — 100% Compete
• Electrical Service — 100% Complete
• Site Lighting — 100% Complete
• Sidewalks — 70% Complete
• Rough Grading — 95% Complete
• Curbs — 80% Complete
PROJECT SUMMARY
Brook Park Elementary School project is the new construction of the elementary school is place on the
demoed Ford Intermediate School, while connecting to new school to the existing Auditorium.
• Area A: Administration Area & Existing Auditorium
• Area B: Gymnasium, Kitchen & Mechanical Rooms
• Area C: Single Story Academic Wing
• Area D: Two Story Academic Wing
PROJECT KEY PLAN
Brook Park Elementary
PHASE/GMP CONTRACT VALUE CHANGE ORDERS BILLED THROUGH PAID TO DATE RETAINED TO DATE REMAINING TO BILL
August 31st October 31st
Ford intermediate $1,160,025.25 $0.00 $1,116,893.79 $1,086,895.67 $29,998.12 $43,131.46
TOTALS $1,160,025.25 $0.00 $1,116,893.79 $1,086,895.67 $29,998.12 $43,131.46
CONTRACTOR APPROVED CHANGESCURRENT CONTRACT
VALUE
COLEMAN TRUCKING ($23,984.04) $183,065.96
MODERALLI
EXCAVATING$21,919.00 $910,594.00
STATUS COST ALLOCATION
Accepted/Closed 16,275.96$ CMR
Accepted/Closed (40,260.00)$ CMR
Accepted/Closed 56,919.00$ CMR
Accepted/Closed (35,000.00)$ CMR
Credit for assumed ACM per report, tested negative
Premium stone at main storm lines
CHANGE LOG
DESCRIPTION
Removal of unknown ACM (Gym Siding)
TOTAL AFTER PENDING CHANGES
TOTAL CONTINGENCY
APPROVED/CLOSED CHANGES
REVIEWED/ACCEPTED CHANGES
REMAINING AFTER CHANGES
PENDING CHANGES $0.00
$29,668.26
-$23,984.04
CONTINGENCY RECONCILIATION
02A - ASBESTOS ABATEMENT
02B - DEMOLITION
$207,050.00
$888,675.00
FORD INTERMEDIATE - ABATEMENT AND DEMOLITION
PROJECT COSTS
BID PACKAGE
CONTRACTS
CONTRACT VALUE
OWNER CONTINGENCY
utilize onsite material for foundation backfill
CMR CONTINGENCY
$0.00BUDGET CHANGES
$27,603.22
$21,919.00
$29,668.26
PHASE/GMP CONTRACT VALUE CHANGE ORDERS BILLED THROUGH PAID TO DATE RETAINED TO DATE REMAINING TO BILL
September 30th August 31st
Brook Park Elementary $24,173,740.58 $128,473.64 $14,378,979.59 $12,671,873.81 $423,160.67 $9,923,234.63
TOTALS $24,173,740.58 $128,473.64 $14,378,979.59 $12,671,873.81 $423,160.67 $9,923,234.63
CONTRACT VALUE APPROVED CHANGESCURRENT CONTRACT
VALUE
$1,844,900.00 $147,868.28 $1,992,768.28
$2,102,906.96 $43,648.22 $2,146,555.18
$1,575,339.60 $139,453.82 $1,714,793.42
$960,005.00 $44,203.02 $1,004,208.02
$680,050.00 $38,367.00 $718,417.00
$4,339,125.00 $343,765.71 $4,682,890.71
$417,238.50 $25,033.23 $442,271.73
$159,355.00 $10,353.00 $169,708.00
$772,177.00 ($772,177.00) $0.00
$245,652.50 $18,740.50 $264,393.00
$4,188,256.89 $16,184.03 $4,204,440.92
$2,211,849.50 $44,465.10 $2,256,314.60
$776,120.94 $24,863.14 $800,984.08
$902,312.45 $174,820.45 $1,077,132.90
$1,025,000.00 $117,614.84 $1,142,614.84
GUENTHER MECHANICAL, INC
31A - SITEWORK KENTS EXCAVATING SERVICES
28A - SECURITY, SOUND AND TECHNOLOGY MIDWEST TELEPHONE
03A - Concrete
04A - MASONRY
05A - METALS
08A - GLASS AND GLAZING
12B - FF&E ALLOWANCE
26A - ELECTRICAL
032A - FINAL SITE DEVELOPMENT
PLATFORM CONTRACTING
VALENTINE CONTRACTORS, INC
LIVI STEEL, INC
ENVIRONMENTAL GLASS, INC
TBD
EINHEIT ELECTRIC
CT TAYLOR
07A/07B - ROOFING AND METAL PANELS
BROOK PARK ELEMENTARY
PROJECT COSTS
BID PACKAGE
CONTRACTS
CONTRACTOR
FOX ENTERPRISE SERVICES
09A - GENERAL TRADES RFC CONTRACTING
11A - FOOD SERVICE EQUIPMENT TriMark SS KEMP
12A - CASEWORK SOUTHERN CABINETRY, INC
21A - FIRE SUPPRESSION RM RIGGLE
22A/23A - PLUMBING AND HVAC
PRs DESCRIPTION STATUS COST ALLOCATION
001 Vent at grease intercepter APPROVED/CLOSED $0.00 Owner - E/O
002 Revise wall section A4/A-309 APPROVED/CLOSED $3,387.34 Owner - E/O
003 Dumpster enclosure finish APPROVED/CLOSED $3,499.94 Owner - E/O
004 Civil Revisions APPROVED/CLOSED $28,375.60 Owner - AHJ
005 Door hardware revisions APPROVED/CLOSED ($1,270.03) Owner - AHJ
006 Wall revisions in Area A APPROVED/CLOSED $2,414.31 Owner - E/O
007 Eye Wash (#54) removal APPROVED/CLOSED ($1,091.52) Owner - E/O
008 Revise Projector Specification 11 52 13 APPROVED/CLOSED $8,133.66 Owner
009 Revise cabling schematic PENDING $4,673.83 Owner - E/O
010 Add basketball hoop height adjusters APPROVED/CLOSED $2,799.25 Owner - E/O
011 Technology revisions APPROVED/CLOSED ($6,248.32) Owner - E/O
012 Revise door hardware and select doors APPROVED/CLOSED $10,896.54 Owner
013 Monumental sign rough in APPROVED/CLOSED $6,629.27 Owner
014 Provide stone at mulched area of playground (D1/L-502) APPROVED/CLOSED $12,823.72 Owner - E/O
015 Revise fire line and additional hydrants APPROVED/CLOSED $171,440.26 CO 03 - AHJ
016 Add panel and wiring for 2nd floor kitchen gates APPROVED/CLOSED $1,394.01 Owner - E/O
017 Provisions for future scoreboard APPROVED/CLOSED $1,382.49 Owner
018 Revise gas service location APPROVED/CLOSED $2,566.92 Owner - AHJ
019 Revise VAV Schedule APPROVED/CLOSED $3,769.07 Owner - E/O
020 Sectional door revisions APPROVED/CLOSED $18,861.15 Owner
021 Auditorium Scupper BUDGET $30,000.00 Owner
022 Revise Door C106A APPROVED/CLOSED $0.00 Owner - E/O
023 Revise Detail A1-A315 Gable end of C APPROVED/CLOSED $338.18 Owner - E/O
024 Curtainwall elevation CW-1 APPROVED/CLOSED $0.00 Owner - E/O
025 Omit vapor retarder at shingle roofs APPROVED/CLOSED ($1,184.00) Owner - E/O
026 Curtainwall framing CW-2 APPROVED/CLOSED $7,500.20 Owner - E/O
027 Site revisions to courtyrad area REVIEWED/ACCEPTED ($4,395.01) Owner
028 Revised detail D4/A-502 APPROVED/CLOSED ($5,144.00) Owner - E/O
029 Auditorium exterior door at catwalk APPROVED/CLOSED $5,009.39 Owner - E/O
030 Fur masonry wall with metal studs/gyp board APPROVED/CLOSED $2,336.82 Owner - E/O
031 Wall revisions to Classroom C100 and C114 PENDING $4,315.36 Owner - E/O
032 Classroom - Teacher Prep room revisions PENDING $9,146.31 Owner - E/O
033 Technology rough in revisions APPROVED/CLOSED ($5,336.16) Owner - E/O
034 Group restroom walls revision in Area D APPROVED/CLOSED $0.00 Owner - E/O
035 Louvers in gable ends Area C/D REVIEWED/ACCEPTED $9,388.08 Owner - E/O
036 Residential refrigerator revision APPROVED/CLOSED ($918.00) Owner - E/O
037 Omit second exhaust fan motor (backup) APPROVED/CLOSED ($604.77) Owner
038 Hardware schedule revisions PENDING ($3,393.47) Owner
039 Mobile Casework PENDING $97,765.45 Owner
040 Omit sound absorbing panels PENDING ($59,603.00) Owner
041 Area D plumbing chase PENDING $3,413.09 Owner - E/O
042 Chase wall types PENDING ($2,923.70) Owner- E/O
BROOK PARK ELEMENTARY
CHANGE LOG
043 Omit solids interceptor Owner
044 Soffit extension at Lobby Owner - E/O
045 Plumbing Isolation valves APPROVED/CLOSED $938.83 Owner
046 Wall type change at Lobby REVIEWED/ACCEPTED $1,659.20 Owner- E/O
047 Landscape Boulders PENDING $1,350.05 Owner
048 CB 1073 Replacement T&M Owner-
049 Fence at gas meter REVIEWED/ACCEPTED $4,487.94 Owner- AHJ
050 Soffit panel revisions Owner- E/O
051 Garden Revisions - 4 options Owner-
052 Revised Kitchen Quarry Tile APPROVED/CLOSED $0.00 Owner-
ASIs DESCRIPTION STATUS COST ALLOCATION
001 Added Plumbing Keynotes REVIEWED/ACCEPTED $0.00 -
002 Revise Insulation Specification 07 21 00 REVIEWED/ACCEPTED $0.00 -
003 Revise jamb details REVIEWED/ACCEPTED $0.00 -
004 Revise ceiling tile REVIEWED/ACCEPTED $0.00 -
005 Mock-up Panel REVIEWED/ACCEPTED $0.00 -
006 Revised stemwall detail PENDING $8,126.13 -
007 CCU-1 and ECU-1 on emergency power REVIEWED/ACCEPTED $0.00 -
008 Electrical reisions to gym equipment REVIEWED/ACCEPTED $0.00 -
009 Anchor Bolt Repairs -
010 VAV Schedule REVIEWED/ACCEPTED $0.00 -
011 Learning stair detail PENDING $302.44 -
012 Future monitor heights
013 Deck edge detail -
014 Restroom dimensions for C115a and C118a -
015 Area D roof return
016 Jamb detail 18 clarification -
017 Area C Mech Room vapor barrier (insulate duct) PENDING $2,343.21 -
018 Area C Mech Room wall
019 Interior control joints Area C
020 Interior control joints Area D
021 Roof edge detail above CW 4 and 5
RFIs DESCRIPTION STATUS COST ALLOCATION
077 Elevator security card rough in APPROVED/CLOSED $4,003.64 Owner
078 Area C rake detail APPROVED/CLOSED $6,216.20 Owner - E/O
081 Parapet blocking APPROVED/CLOSED $7,750.10 Owner -E/O
119 Truss bearing conflict PENDING $7,078.48 Owner - E/O
125
132 CFMF on column line L.D REVIEWED/ACCEPTED $8,073.56 Owner - E/O
142 Area C Parapet T&M
BROOK PARK ELEMENTARY
CHANGE LOG - CONTINUED
MISC DESCRIPTION STATUS COST ALLOCATION
Alternate No. 1 - additional building square footage ACCEPTED/CLOSED $1,080,071.23 GMP
Remove FF&E Allowance and accepted value engineering ACCEPTED/CLOSED ($1,123,037.85) CO 01
Increase interior foundation depth ACCEPTED/CLOSED $70,212.65 CMR
Chemically stabilze Area A building pad ACCEPTED/CLOSED $32,505.20 Allow
Food Service Contractor Change ACCEPTED/CLOSED $26,124.75 CMR
Temporary Aprons per City REVIEWED/ACCEPTED $11,225.77 OWNER-AHJ
Omit expansion joint at perimeter SOG REVIEWED/ACCEPTED ($1,920.00) OWNER
Unsuitable soil at East Drive and South Lot ACCEPTED/CLOSED $33,058.25 Allow
Demuck building pad in Area C for slab placement ACCEPTED/CLOSED $17,468.20 CMR
Demuck building pad in Area D for slab placement ACCEPTED/CLOSED $29,712.79 CMRPremium Time - (Feb. Mar. May) REVIEWED/ACCEPTED $2,229.52 CMRGenerator Pad REVIEWED/ACCEPTED $2,389.00 Owner - E/OTechnology Equipment Credit PENDING ($123,631.67) OWNEROmit Air Curtain at Kitchen (utilize Curtain from MEC) REVIEWED/ACCEPTED ($1,901.68) OWNER
BROOK PARK ELEMENTARY
CHANGE LOG - CONTINUED
CMR CONTINGENCY OWNER CONTINGENCY
$574,200.45 $0.00
$574,200.45 $0.00
$143,518.39 $119,229.83
$2,229.52 $29,006.86
$428,452.54 ($148,236.69)
$0.00 ($44,821.29)
$0.00 $42,500.00
$428,452.54 ($145,915.40)
ALLOWANCE COMMITTED BALANCE
AUDITORIUM $75,000.00 $22,878.08 $52,121.92
FIRST RESPONDER $45,195.00 $0.00 $45,195.00
SIGNAGE $15,000.00 $0.00 $15,000.00
UNSUITABLE SOIL $100,000.00 $65,563.45 $34,436.55
TOTAL ALLOWANCE $235,195.00 $88,441.53 $146,753.47
CONTINGENCY RECONCILIATION
BROOK PARK ELEMENTARY
ALLOWANCE RECONCILIATION
TOTAL AFTER PENDING CHANGES
Brook Park Elementary
TOTAL CONTINGENCY
APPROVED/CLOSED CHANGES
REVIEWED/ACCEPTED CHANGES
REMAINING AFTER CHANGES
PENDING CHANGES
BUDGET CHANGES
Activity Name OrigDur
%Comp
Start Finish TotalFloat
Brook Park Elementary School 442 06-26-18 A 03-06-20 -5New Construction (Phase II) 442 06-26-18 A 03-06-20 -5Project Milestones 618 06-28-18 A 03-06-20 -7Notice to Proceed 0 100% 06-28-18 ACommence Work On-site 0 100% 08-22-18 ACommence Foundations 0 100% 10-08-18 ATemp Electrical Available 0 100% 01-24-19 ATemp Enclosure/ Start Temp HVAC - Area B 0 100% 01-24-19 ATemp Enclosure/ Start Temp HVAC - Area C 0 100% 01-24-19 ATemp Enclosure/ Start Temp HVAC - Area A 0 100% 01-24-19 ATemp Enclosure/ Start Temp HVAC - Area D 0 100% 01-24-19 ASubstantial Completion 0 0% 02-25-20* -11Final Completion/ Owner Occ. 0 0% 03-06-20* -7
Site Mobilization 10 06-26-18 A 10-31-18 AInitial Site Mobilization 5 100% 06-26-18 A 06-28-18 ASecure Site/ Establish Access 5 100% 06-28-18 A 06-28-18 AEstablish Temp Facilities 10 100% 06-26-18 A 10-31-18 A
Material Procurement 236 07-13-18 A 05-23-19 ASubmittals 141 07-13-18 A 01-23-19 AReceive Site Structure Submittals 1 100% 07-13-18 A 07-13-18 AReceive Initial Foundations Submittals 1 100% 07-13-18 A 07-13-18 AReceive HVAC Equipment Submittals 1 100% 10-25-18 A 10-25-18 AReceive Initial Structural Steel Submittals 1 100% 10-25-18 A 10-25-18 AReceive Windows/ Glazing Submittals 1 100% 01-23-19 A 01-23-19 A
Submittal Review 150 07-16-18 A 02-08-19 AReview Initial Foundation Submittals 10 100% 07-16-18 A 07-27-18 AReview Site Structure Submittals 10 100% 07-16-18 A 07-27-18 AReview Initial Structural Steel Submittals 10 100% 10-26-18 A 11-08-18 AReview HVAC Equipment Submittals 10 100% 10-26-18 A 11-08-18 AReview Windows/ Glazing Submittals 10 100% 01-23-19 A 02-08-19 A
Deliveries 221 08-20-18 A 05-23-19 AInitial Site Structure Delivery 1 100% 08-20-18 A 08-20-18 AInitial Foundations Delivery 1 100% 09-04-18 A 09-04-18 AInitial HVAC Equipment Deliveries 1 100% 12-10-18 A 12-28-18 AInitial Steel Delivery 1 100% 01-04-19 A 01-05-19 AInitial Windows/ Glazing Delivery 1 100% 05-22-19 A 05-23-19 A
Site Prep/ Rough-in 237 08-21-18 A 11-12-19 -7Site Prep 21 08-22-18 A 10-08-18 ASite Demo/ Clearing 15 100% 08-22-18 A 09-13-18 AEstablish Building Pad 8 100% 09-17-18 A 09-24-18 ASite Rough Grading 15 100% 09-14-18 A 09-27-18 ALayout Building 2 100% 10-07-18 A 10-08-18 A
Site Rough-in 222 08-21-18 A 11-12-19 -7Site Storm Sewers (NE at Lawn Area) 6 100% 08-21-18 A 08-28-18 ASite Storm Sewers (NW Corner) 5 100% 09-10-18 A 09-14-18 ASite Storm Sewers (South) 7 100% 08-29-18 A 10-05-18 ASite Storm Sewers (N. Includes Retention) 15 100% 09-18-18 A 10-08-18 ASite Electrical Feeder Conduit 15 100% 09-27-18 A 10-15-18 ASite Sanitary Sewers 5 100% 10-19-18 A 10-24-18 ASite Tech Feeder Wire 5 100% 12-03-18 A 12-10-18 ASite Tech Feeder Conduit 5 100% 12-03-18 A 12-10-18 ASite Gas Line 10 100% 01-22-19 A 04-23-19 ASite Water Line 10 100% 10-29-18 A 06-20-19 A
J J A S O N D J F M A M J J A S O N D J F M018 2019 2020
BPE-16-1:Brook ParkElementary SchoolBEREA C4 PortraitRun Date 11-01-19Data Date 10-31-191 of 14
Berea City School District Brook Park Elementary School
Revised Updated Construction Schedule(11-01-19)
Brook Park Elementary School: PROGRESS PHOTOS
Area A — Brick Veneer
Area A — Drywall Interior Walls
Brook Park Elementary School: PROGRESS PHOTOS
Area B — Ductwork in Kitchen
Area B — HVAC Heating Water System Area B — Domestic Hot Water System
Brook Park Elementary School: PROGRESS PHOTOS
Area B — Structural earning Stairs
Area B — Main Entrance Structural Canopy
Area B — Main IT/Control Room w/
Chilling Unit in Ceiling
Brook Park Elementary School: PROGRESS PHOTOS
Area C — Overhead Classroom Doors
Area C — Painting Ongoing
Brook Park Elementary School: PROGRESS PHOTOS
Area C — Technology Room
Area D — Drywall 1st Floor
Area C — Interior Storefront Workroom
Brook Park Elementary School: PROGRESS PHOTOS
Area D — Interior Stud Wall 2nd Floor
Area D — HVAC Rough-Ins
Brook Park Elementary School: PROGRESS PHOTOS
Area D — Electrical Room 2nd Floor
Site — Topsoil & Seeding (South)
Area D — Roof Shingles Ongoing
Site — Mechanical Yard Screen Wall
Brook Park Elementary School: PROGRESS PHOTOS
Site — Sidewalks/Curbs (North)
Site — Sidewalks/Curbs (South)