new alara recommendations proposed by the a lara r eview w orking g roup (arwg)
DESCRIPTION
New ALARA recommendations proposed by the A LARA R EVIEW W ORKING G ROUP (ARWG). Heinz Vincke on behalf of ARWG LS1 committee meeting 24.05.2013. Classification of interventions in radiation areas until now - 5 criteria, 3 levels. ALARA procedures – 3 levels: - PowerPoint PPT PresentationTRANSCRIPT
1
New ALARA recommendations
proposed by the ALARA REVIEW WORKING GROUP
(ARWG)
Heinz Vincke on behalf of ARWGLS1 committee meeting 24.05.2013
Classification of interventions in radiation areas until now - 5 criteria, 3
levels
ALARA procedures – 3 levels:o If the rad. risk is low <> very light procedure
o If it is medium <> an optimization effort is required
o If it is high <> an optimization effort is required, the procedure will be submitted to and presented at the ALARA committee
2
3
Retour d’experience until
2011/2012Many positive examples prove that job optimization (reduction in dose to personnel) was, is and has to remain the main goal.
But
• All DIMR Level III are prepared, not all DIMR Level II
• ALARA criteria are questioned
• No coherent approach in A&T departments and LHC experiments for Level I interventions
• RP act(ed) as “owner” of DIMRs
• Follow-up of recommendations not systematically done
• No clear guidelines for waiving ALARA committees meetings.
• ...
DIMR = Dossier d’Intervention en Milieu Radioactif
4
ALARA Review
Working GroupMEMBERS:
Chair: H. Vincke (DGS/RP)Sc. Sec.: T. Wijnands (EN/HDO)
• RP (including RP group leader)
• RSOs from all departments and from the LHC experiments (GLIMOS from ATLAS repl. ATLAS RSO)
• ‘experts/user’ o R. Catherall o I. Efthymiopouloso P. Bonnal
5
ARWG was expected to
deliver:
• Proposal for ALARA criteria
• Proposal on how to initiate, to follow up and to archive the DIMRs (for all three levels)
• Proposal of guidelines for presentations to the ALARA committee
• Proposal of procedure waiving an ALARA committee meeting
6
ALARA criteria
AL
AR
A C
rite
ria
ALARA criteria and levels at CERN:
7
AL
AR
A C
rite
ria
risk
assessm
ent require
d ->
RSO and RP decid
e on ALARA
Level
5 mSv
hard limits
old new
8
DIMR & WDPDossier d’Intervention en Milieu Radioactif & Work and Dose Planning
DIM
R &
WD
P
9
DIM
R &
WD
P
2006-2008:DIMR (Dossier d’Intervention en Milieu Radioactif)
Started in 2009: DIMR based on a SharePoint site –
…. to edit and store work and dose planning documents
• Create a new work and dose planning folder
• Create a new work and dose planning document
• Create a new radiological work permit
10
IMPACT - DIMR & WDP
IMPACT (Intervention Management Planning & Activity Coordination Tool), is a general tool to manage work and activities + related aspects, i.e. planning, infrastructure, co-activities, permits, requests and documentation.
ARWG also strongly supported the idea to use IMPACT for DIMRs and they have been implemented into IMPACT already
DIM
R &
WD
P
11
Formal Approach
All work needs to be announced to superintendent (Work Planning coordinators for experiments)
RP, RSOs/GLIMOS and the superintendents (Work Planning coordinators for experiments) check the list of works and make a ‘first’ DIMR level classification.
DIMR Level 1: • Work planning by maintenance/repair team• IMPACT no documented WDP needed• Approval by RSSO/RPE
DIMR Level 2 and 3:• Work and dose planning by maintenance/repair team, RP and RSO/RSSO• Approval by department GL, RSO, RP for DIMR Level II• If DIMR Level 3 -> ALARA Committee• IMPACT with DIMR
LHC experiments apply DIMR/WDP also for Level 1 – integrated into the access request
DIM
R &
WD
P
DIMR & WDP RP=DGS/RP
13
Guidelines for presentations in the ALARA committee meeting
AL
AR
A C
om
mit
tee
Guidelines for presentations in the ALARA committee
• Short description of intervention and the type (planned, unanticipated, urgent unanticipated)
• Justification of intervention & consequences in case the intervention does not take place
• Put the intervention into context using events in the past (if applicable).
o Similar activities on the same installation, REX, etc.
o Last maintenance performed
o Envisaged revisions or replacements in the future
• Presentation of the DIMR – should contain at least :
o Detailed description of major steps of the intervention and the time estimates
o Results of mock-up tests and dry-runs (if applicable) justifying the estimated times and working methods
o Measures that have been retained to optimize the intervention (remote handling, local shielding etc …..)
o Summary of the optimization measures that were considered but not retained
o Present the ALARA parameters for the optimized and for the non-optimized version of the DIMR
o Assessment of risks of accidents and incidents and measures that have been taken to minimize these risks
• Summary of the intervention14
AL
AR
A C
om
mit
tee
15
Waiving of an ALARA committee meeting
AL
AR
A C
om
mit
tee
16
Waiving of the ALARA committee meeting
Circumstances• Repetitive intervention
o A procedure has been worked out under which circumstances a waiving of the ALARA committee meeting could be possible – valid for interventions approved already once in the ALARA committee.
• Urgent maintenance/repair
Suggestion: generic DIMRs should be worked out and approved a priori in an ALARA committee meeting.
AL
AR
A C
om
mit
tee
17
…in case of waiving
• Waiving of the ALARA committee meeting has to be recorded
• This action shall also be noted in the DIMR. • The outcome will be presented in the next
Radiation Safety Officer Committee (RSOC) meeting
• ... and summarized in the next ALARA committee meeting.
18
The ARWG discussed and looked into
proposals for:
• ALARA criteria:o Criteria and Levels
o Operational margins
o Emergency intervention
• DIMRs &WDP:o Ownershipo Procedure to create, check,
validate and closeo Work optimization processo Retour d’expérienceo Controlso Functionality, routing, CERN
integrationo Contractors, PCRo Approval roundso Implementation issues
• ALARA committee:o Guideline for presentationso Frequencyo Quorumo Roleso Waiving of the ALARA committee
meeting
19
…were approved by S. Myers and R. Trant
on 20 April 2013!
Final report(s) from ARWG …
EDMS doc # 1244380
20
Existing ALARA documents (EDMS 825353, 810178 and 810176) will be combined into a single document and updated with the recommendations from the ARWG
Next steps
+
The new rules have become effective on 20. April 2013