Constructing Excellence
Oxford Club
14 January 2016
Ruth Leuillette - Sponsor
Jonathan Davies - Senior Programme Manager
![Page 2: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/2.jpg)
2
Oxford Corridor Overview – Ruth Leuillette
Engineering Overview – Jonathan Davies
![Page 3: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/3.jpg)
3
Oxford Corridor Overview
Ruth Leuillette
![Page 4: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/4.jpg)
Network Rail
Investment as set out in Strategic Business Plan agreed with
Department for Transport (DfT)
Since reclassification in 2014 - Arms Length Body of DfT
We maintain, manage and improve every aspect of the infrastructure
• each weekday 4m passengers carried on our network - last year
there were 1.27bn separate journeys and 100 million tonnes of
freight was transported
• £1.84m spent every day operating, maintaining and renewing the
railway
4
![Page 5: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/5.jpg)
Oxford Corridor
Aims:
• Increased passenger capacity, flexibility & reduced journey times
• Increased freight train paths available and supporting freight train
lengthening
• Supporting the economy through renewal and enhancement of the
rail infrastructure in the Oxford area, delivered by providing:
• New track layout to accommodate electrification
• Upgrading signalling to Thames Valley Signal Control Centre
• Associated civils works to structures to support new layout
5
![Page 6: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/6.jpg)
Oxford Corridor
Future proofing for future phases including:
• Additional through platform
• East West Rail 2 aspiration of 4 trains per hour
• Wider masterplan proposals
• Possible Cowley Branch passengerisation
• GWR aspiration for increase in Cotswold line services
6
![Page 7: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/7.jpg)
Oxford Corridor Phase 0
![Page 8: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/8.jpg)
Oxford Corridor Phase 1
![Page 9: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/9.jpg)
Oxford Corridor Electrification
![Page 10: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/10.jpg)
Oxford Corridor – Future Phase
![Page 11: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/11.jpg)
11
Jonathan Davies
– Senior Programme Manager
22-Jan-16
![Page 12: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/12.jpg)
8400 Points Modular Turnout Beeston Yard Inspections 26 & 27 Nov 12
Modular Switch and Crossing
22-Jan-16 1
2
![Page 13: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/13.jpg)
13
► Factory build straight to site
► Safer - staff now not employed building S & C units ‘ in the hole’
► Cost efficiencies
► Reduced disruption in Engineering Access requirements
Modular Switch and Crossing (S&C)
22-Jan-16
![Page 14: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/14.jpg)
High Output Track Renewals
22-Jan-16 1
4
![Page 15: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/15.jpg)
High Output Track Renewals
22-Jan-16 1
5
![Page 16: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/16.jpg)
Cost efficiencies
Adjacent Line working
Higher Line Speed Opening
Improved Track Quality
Safer
High Output Track Renewals
22-Jan-16 16
![Page 17: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/17.jpg)
High Output Plant System - Electrification
1722-Jan-16
![Page 18: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/18.jpg)
High Output Plant System - Electrification
1822-Jan-16
Piling Rig for masts foundations
Steelworks Erects masts, portal booms & twin track cantilevers
Excavation capability and concrete batching unit
SPS & Wiring
![Page 19: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/19.jpg)
Safer
Adjacent Line Working
Lean Working
Modularised Build
Ripe Continuous Improvement
High Output Track Renewals
22-Jan-16 19
![Page 20: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/20.jpg)
Signalling – Axle Counters and Points
► Factory build straight to site
► Safer - staff now not employed in rectifying faults
► Cost efficiencies
► Reduced disruption
2022-Jan-16
![Page 21: Network Rail Developments](https://reader033.vdocuments.us/reader033/viewer/2022042511/58a7bcb31a28ab70368b69e9/html5/thumbnails/21.jpg)
Thank You