nesma water and energy - irp-cdn.multiscreensite.com · nesma holding profile • founded in 1979...
TRANSCRIPT
NESMA Water and Energy
Corporate Presentation
Website Version
Table of Contents• NESMA Holding
– NESMA Holding Profile
– NESMA Group of Companies
• NW&E Company Introduction
– Vision & Mission
– Our Services
• Projects Details & Progress
• Manpower Progress
• Our Added Value
• Leadership Team
NESMA Holding
• Nesma Holding Profile
• Nesma Group of Companies
NESMA Holding Profile
• Founded in 1979
• Headquarters in Jeddah, Saudi Arabia
• One of the top private Saudi Company
• Employee base of over 35,000
• Over 40 Subsidiary
NESMA Holding Profile• NESMA Water & Energy is a subsidiary of Nesma Holding
Group.
• NESMA Holding Offices.
Head Office:
Jeddah City
Main Offices:
Riyadh
Khobar
Makkah
And other major cities in KSA
Satellite Offices:
China Turkey
Egypt Korea
UK UAE
USA
NESMA Business Lines
Hospitality & Tourism
Chocolate
Industrial& Manufacturing
Projects
Oil& Gas
EPC
IT& Telecom
Water & Energy
Convenience Stores
Restaurants
ElectronicsReal Estate & Property
Management
Supplies & Logistics
Transport & Travel
Sup
po
rt Service
s
Co
nsu
me
r Pro
du
cts
Co
ntractin
g
Promotional Gifts
Freight Forwarding
&
Marine Services
Nesma Group of Companies
Engineering &
Construction
NESMA&
Partners
KAEFER
NESMA Havatek
Industrial & Manufacturing
NESMA Ommat
NESMARecycling
NESMABatterjee
Nesma Group of Companies
Services
NESMA Trading
NESMASecurity
TRAP
Pioneer
Transportation
& Marine Services
Namma Cargo
Namma Marine
IstanbulLines
NESMA Airlines
Nesma Companies in Turkey
1. Namma Uluslararasi A.S.
2. Istanbul Lines A. S. Bostan Denizcilik LTD (Bostan N)
Hidiv Denizcilik LTD (Istanbul N)
Etis Logistik A.S.
3. Marmara N Denizcilik A.S. (Marmara N)
Ro-Ro Truck Ferries
NESMA Airlines
Four Airbus A320 aircraft
All Economy Configuration, 180 seats.
Air (Carrier) Operators Certificate from the Egyptian Civil Aviation Authority
Head office in Cairo, Egypt
Nesma Group of Companies
Telecommunications
NESMA Telecom
Norconsult
TCIL
Travel
&
Leisure
Mawaddah
Namma Tours
NESMA Travel
Nesma Group of Companies
Technology
Mihnati
Jadarah
Nesma Advanced
Technology
Water
&
Electricity
NESMAW&E
Koncareu
NESMA Electric
Nesma Group of Companies
Retail
Jollibee
NESMAChocolate
Building Materials
NESMA Orbit
UniTrade
Nesma Real State
Financial Position
• Due to diversity, Nesma Holding has established anastonishing financial stability & Security.
• NESMA is more than capable of investing in any of thebusiness sectors available today.
• Annual Revenue:
Year Annual Revenue (SAR)
201320142015
7.5 Billion7.7 Billion8.2 Billion
Introduction
• NW&E Company Introduction
– Vision & Mission
– Our Services
Vision & Mission
To Be The Regional Leading Contractor and Services Provider inThe Water and Power Sector.
To Address The Increasing Demand of Our Customers and BeCommitted To Our Partner’s Expectations and ClientSatisfaction by Providing Exceptional Design, Construction andServices, While Maintaining Standards of Safety and ExcellenceThat Will Not Be Compromised.
Our Services
Power Plants
Water Reservoirs
Water Treatment Plants
Desalination Plants
Transmission Systems
– Water desalination.
– Water and wastewater treatment.
– Infrastructure and transmission lines• Storm water drainage
• Sewer network
• Potable water network
• TSE network
• LV&MV cable laying
– Water reservoirs (concrete & steel)
– Power and electrical network
– Operation and maintenance services
– Build Operate Own Transfer (BOOT)
Some of Our Major Success Stories
• NWC JCBU Water Meters House Connections Project.
• Affif & Dawadmi Water Operation & Maintenance.
• Riyadh Water Supply Enhancement.
• King Abdullah Economical City Industrial Valley
Infrastructure
• King Abdullah Economical City Al-Murooj BC2
Infrastructure
• Jeddah Wall Meters Replacement
• MODON Portable Water Treatment Plants
• Residential & Industrial Combined Infrastructure Works
NWC Water House Connection & Meters
Replacement Project :
Location :
Client :
Duration:
Scope:
NWC Water House Connection & Meters
Replacement – 4 projects
Jeddah
National Water Company
2011 (8 Months)
• House Connections in Jeddah City
• Serviced 96,000 Houses.
Completion Certificate
Affif & Dawadmi Water O&M
Location :
Client :
Value :
Project Duration:
Scope of Work:
Dawadmi & Affif City
Ministry of Water & Electricity in Riyadh
SR. 20,000,000 + 24,000,000 (Re-Award)
Jan, 2012 (36 Months) + Jan, 2015 (36 Months)
• Capacity: 50,000m3/Day
• 25 pumping stations:
A) 4 Main
B) 21 Sub
• 15+5 Wells (around 300m depth)
• Network from Dawadmi to Affif (around 230km)
• 20 Filling stations (around 800m3/Day)
• Tanks
• Water meters (house connections) from 0.5” to 3.5”
Highly Qualified O&M Team
Our Own Multipurpose O&M Fleet
Modern Monitoring & Control Equipment
Affif & Dawadmi Water O&M
Completion Certificate
Riyadh Water Supply Enhancement
Location :
Client :
Value :
Project Duration :
Scope of Work :
Riyadh
National Water Company
SR.509,000,000
2013 (6 Months Construction & 24 Months O&M + 11 Months
(extension)
To increase supply of the drinking water for Riyadh city, in line with
future demand throw:
• Total Capacity of 65,000 m3/day
• Digging 13 deep water wells:
• A) 1,700- 2,400 m depth
B) 5,000 m3/Day flow rate
Containerized RO treatment plants (WTP) @ 5,000m3/Day
• 2 years O & M services
• GLS tanks water reservoirs at @ 5,000m3 capacity.
• Cooling towers
Riyadh Water Supply Enhancement
Location
Equipment
Containerized WTP
Well Drilling Rigs
Well Pumps
Equipment
Power Generators Transfer (Booster) Pumps
GLS Tank
Completion Certificate
Global Facts
• National Water Company made a worldwide breakthrough.
• Awarded the “Best Global Water Project award for 2014”
During the “Global Water Summit Awards”, in Paris
Project Video Link: http://www.youtube.com/watch?v=_5qRytjzVck
KAEC IV2 Infrastructure
Client :
Location:
Value :
Duration:
Scope:
King Abdullah Economic City (KAEC), Emaar The Economic City (EEC)
King Abdullah Economic City
SR.310,800,000
2014 (12 Months)1- Water Utilities Infrastructure:
a. Potable Water Network
I. HDPE (32-300 mm) total of 30km
II. Ductile Iron (400-900 mm) total of 8km
b. Sewage Water Network
I. UPVC (150-300 mm) total of 2km
II. GRP (300-1600 mm) total of 10km
c. Treated Sewage Effluent (TSE) Network
I. HDPE (32-300 mm) total of 10km
II. Ductile Iron (400-900 mm) total of 4km
d. Storm Water Drainage Network
I. GRP (300-2100 mm) total of 18km
2- Power Utilities Infrastructure:
a. Low Voltage Network (34km, 4X35 mm2)
b. Medium Voltage Network (113km, 3X300 mm2)
c. 6 Substations (Transformer, RMU and panel)
d. Telecommunication Network
e. 644 Light Poles
IV2 Overall Location
IV2 Site Offices
IV2 Materials Storage
IV2 Pipes Installation
Phase 2.5&2.1: Highway Network
Phase 2.5&2.1: Highway Network
Completion Certificate
KAEC Al-Murooj BC2 Infrastructure
Client :
Location:
Value :
Duration:
Scope:
King Abdullah Economic City (KAEC), Emaar The Economic City (EEC)
King Abdullah Economic City
SR.73,000,000
2014 (18 Months)1- Water Utilities Infrastructure:
a. Potable Water Network
I. HDPE (110-160 mm) total of 6km
b. Sewage Water Network
I. UPVC (160-400 mm) total of 10.3km
II. GRP (250 mm) total of 1km
c. Irrigation & Fire Fighting System
I. HDPE (90-200 mm) total of 7.2km
d. Storm Water Drainage Network
I. UPVC (200-630 mm) total of 5.5km
II. Concrete (700-1500 mm) total of 2.9km
2- Power Utilities Infrastructure:
a. Low Voltage Network (72.4km, 4X25 mm2)
b. Medium Voltage Network (6.5km, 3X300 mm2)
c. 17 Substations (Transformer, RMU and panel)
d. Telecommunication Network
e. Light Poles
KAEC Al-Murooj BC2 Infrastructure
KAEC Al-Murooj BC2 Infrastructure
Completion Certificate
Wall-Mounted Water House Connection & Meters
Location :
Client :
Value:
Duration:
Scope:
Jeddah
National Water Company
18 SRM
2015 (18 Months)
• House Connections in North & South of Jeddah City
• Serviced 26,000 Houses.
Wall-Mounted Water House Connection & Meters
NWC MODON Portable Water Treatment Plants
Replacement Location :
Client :
Value :
Project Duration:
Scope of Work:
Riyadh, Durma, Hail & Al-Hasa
Saudi Industrial Property Authority (MODON)
SR.65,000,000
Dec 2015 (16 months Construction + 12 months O&M)
• Total Capacity: 7,000m3/Day
• 4 Pumping Stations
• Deep Water Wells (around 1000m depth)
• Evaporation pond
• GLS Tanks
• Buildings
NWC MODON Portable Water Treatment Plants
Replacement
Hejaz Utility Yard
Project :
Location :
Client :
Value :
Project Duration:
Scope of Work:
Power & Water Utilities Infrastructure
King Abdullah Economic City
King Abdullah Economic City (KAEC), Emaar The Economic City
SR.8,000,000
Sep 2016 (8 months Construction)
• Power Utilities
• Communication Utilities
• Water Utilities
• GLS Tanks
• Buildings
Hejaz Utility Yard
Residential & Industrial Combined Infrastructure Works
Location :
Client :
Value :
Project Duration:
Scope of Work:
King Abdullah Economic City (KAEC), Emaar The Economic City (EEC)
King Abdullah Economic City
SR.7,000,000
2014 (18 Months)
• IV2 Ph 2.1 Traffic Signals
• IV2 Ph 2.1 Sewage & Potable Connections
• IV2 Panad Facility Gate Infrastructure
• IV2 Al-Zahid Facility Gate Infrastructure
Residential & Industrial Combined Infrastructure Works
Our Added Value
• Diversified group of companies
• Local presence in the Kingdom.
• Financial stability.
• Capability to invest in MEGA projects.
• Local and international highly qualified team.
• Partners specialized in various related fields.
Our Leadership Team
CEO and Managing Director – Eng. Mahmoud Yahya Fallatah
• Bachelor Degree in Applied Chemical Engineering from King Fahd University of Petroleum and Minerals
• Executive Management Diploma- University of North Carolina
• Executive Managers Development- UK Institute of Senior Executive Learning Expedition
• More than 23 years of experience in the petrochemical and water
Chairman and President (NESMA Holding) – Sheikh Saleh Al-Turki
• Bachelor's degree in Public Administration from the American University of Beirut
• Master's degree in Administration from California State University
• More than 30 years experience in Business and Management World.
Our Leadership Team
Our Leadership Team
Corporate Development Director – Eng. Mohammad Abbas• Master Degree , Chemical Engineering from Birmingham, UK
• More than 30 years of experience of which 10 years in Senior Management
• Wide background in Corporate Development & Strategies.
• Technical expertise in Water & Waste Water treatment and membrane technology
Business Support Director – Eng. Abdullah Alsalem
• Master in Business Administration (MBA)
• BSc Chemical Engineer
• O&M certified from California State University, Sacramento
• 16 years of experience in Water and Power Sector.
Finance Manager – Mr. Hakem Al Shammary• Bachelor of Commerce-Accounting section
• More than 27 Years in Accounting and Finance
• Financial analysis, Budgeting ,Cost control
• Financial and Strategic Planning
Our Leadership Team
Internal Auditor - Mr. Aftab Quraishi• Master’s in business & administration
• Specialized in Database programming
• More than 40 years experience in Saudi Arabia
• Human Resources, Systems, Controls, Policies and Procedures Adviser
Operation & Maintenance Manager – Eng. Ahmad Ramadan•BSc Automatic control and industrial electronics.
•10 years of experience in operation and maintenance of water projects.
•Expert in RO, SCADA control and infrastructure systems
Business Development Manager – Eng. Rayan Bukhari
• Master’s in business & administration
• BSc Electrical Engineer (Biomedical)
• 10 years of experience in environmental issues, water and business development.
• Creating and evaluating business models, JV’s and Strategic partnerships
Our Leadership Team
Salah M. Omer Al Haj - Procurement Manager
• B.Sc. Chemical Engineering
• Certified Supply Chain Manger
• 20 years experience in Supply Chain Management in Saudi Arabia
• Procurement, Materials Planning & logistics
Thank You