nerc - reliability standards complete set-rscompleteset

1710
 3353 Peachtree Road NE Suite 600, North Tower  Atlanta, GA 30326 404-446-2560 | www.nerc.com Reliability Standards for the Bulk Electric Systems of North  America Updated June 12, 2014 

Upload: armando-ribeiro

Post on 13-Oct-2015

39 views

Category:

Documents


0 download

TRANSCRIPT

 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 1 of 12
2.  Number: BAL-001-1
4.  Applicability:
4.1.  Balancing Authorities
5.  Effective Date:  The WECC Regional Variance to NERC Reliability Standard BAL-001- 1 is to be effective on the first day of the second quarter, after regulatory approval.
B. Requirements
R1.  Each Balancing Authority shall operate such that, on a rolling 12-month basis, the average of the clock-minute averages of the Balancing Authority’s Area Control Error (ACE) divided by 10B (B is the clock-minute average of the Balancing Authority Area’s Frequency Bias) times the corresponding clock-minute averages of the Interconnection’s Frequency Error is less than a specific limit. This limit ε1
2 is a constant derived from a targeted frequency bound (separately calculated for each Interconnection) that is reviewed and set as necessary by the
 NERC Operating Committee.
ACE = (NIA − NIS) − 10B (FA − FS) − IME 
where:
•   NIA is the algebraic sum of actual flows on all tie lines.
•   NIS is the algebraic sum of scheduled flows on all tie lines.
•  B is the Frequency Bias Setting (MW/0.1 Hz) for the Balancing Authority. The constant factor 10 converts the frequency setting to MW/Hz.
•  FA is the actual frequency.
•  FS is the scheduled frequency. FS is normally 60 Hz but may be offset to effect manual time error corrections.
•  IME is the meter error correction factor typically estimated from the difference between the integrated hourly average of the net tie line flows (NIA) and the hourly net interchange demand measurement (megawatt-hour). This term should normally be very small or zero.
R2.  Each Balancing Authority shall operate such that its average ACE for at least 90% of clock- ten-minute periods (6 non-overlapping periods per hour) during a calendar month is within a specific limit, referred to as L10.
10minute10 )(   L ACE  AVG i   ≤−  
1
* 10
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 2 of 12
L10= )10)(10(65.1 10   si   B B   −−∈  
ε10 is a constant derived from the targeted frequency bound. It is the targeted root-mean-square (RMS) value of ten-minute average Frequency Error based on frequency performance over a given year. The bound, ε10, is the same for every Balancing Authority Area within an Interconnection, and Bs is the sum of the Frequency Bias Settings of the Balancing Authority Areas in the respective Interconnection. For Balancing Authority Areas with variable bias, this is equal to the sum of the minimum Frequency Bias Settings.
R3.  Each Balancing Authority providing Overlap Regulation Service shall evaluate Requirement R1 (i.e., Control Performance Standard 1 or CPS1) and Requirement R2 (i.e., Control Performance Standard 2 or CPS2) using the characteristics of the combined ACE and combined Frequency Bias Settings.
R4.  Any Balancing Authority receiving Overlap Regulation Service shall not have its control  performance evaluated (i.e. from a control performance perspective, the Balancing Authority has shifted all control requirements to the Balancing Authority providing Overlap Regulation Service).
C. Measures
M1.  Each Balancing Authority shall achieve, as a minimum, Requirement 1 (CPS1) compliance of 100%.
CPS1 is calculated by converting a compliance ratio to a compliance percentage as follows:
CPS1 = (2 - CF) * 100%
The frequency-related compliance factor, CF, is a ratio of all one-minute compliance  parameters accumulated over 12 months divided by the target frequency bound:
2
1 )(
month12
∈ =   − CF 
CF 
where: ε1 is defined in Requirement R1.
The rating index CF12-month is derived from 12 months of data. The basic unit of data comes from one-minute averages of ACE, Frequency Error and Frequency Bias Settings.
A clock-minute average is the average of the reporting Balancing Authority’s valid measured variable (i.e., for ACE and for Frequency Error) for each sampling cycle during a given clock- minute.
10B-10
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 3 of 12
 
 Normally, sixty (60) clock-minute averages of the reporting Balancing Authority’s ACE and of the respective Interconnection’s Frequency Error will be used to compute the respective hourly average compliance parameter.
hour insamplesminute-clock 
  ∑=
 

∑ =
( )


=
= −
 
In order to ensure that the average ACE and Frequency Deviation calculated for any one- minute interval is representative of that one-minute interval, it is necessary that at least 50% of
 both ACE and Frequency Deviation samples during that one-minute interval be present. Should a sustained interruption in the recording of ACE or Frequency Deviation due to loss of telemetering or computer unavailability result in a one-minute interval not containing at least 50% of samples of both ACE and Frequency Deviation, that one-minute interval shall be excluded from the calculation of CPS1.
M2.  Each Balancing Authority shall achieve, as a minimum, Requirement R2 (CPS2) compliance of 90%. CPS2 relates to a bound on the ten-minute average of ACE. A compliance percentage is calculated as follows:
( ) 100*
PeriodseUnavailablPeriodsTotal
 
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 4 of 12
 
Each Balancing Authority shall report the total number of violations and unavailable periods for the month. L10 is defined in Requirement R2.
Since CPS2 requires that ACE be averaged over a discrete time period, the same factors that limit total periods per month will limit violations per month. The calculation of total periods
 per month and violations per month, therefore, must be discussed jointly.
A condition may arise which may impact the normal calculation of total periods per month and violations per month. This condition is a sustained interruption in the recording of ACE.
In order to ensure that the average ACE calculated for any ten-minute interval is representative of that ten-minute interval, it is necessary that at least half the ACE data samples are present for that interval. Should half or more of the ACE data be unavailable due to loss of telemetering or computer unavailability, that ten-minute interval shall be omitted from the calculation of CPS2.
D. Compliance
One calendar month.
1.3.  Data Retention
The data that supports the calculation of CPS1 and CPS2 (Appendix 1-BAL-001-0) are to  be retained in electronic form for at least a one-year period. If the CPS1 and CPS2 data for a Balancing Authority Area are undergoing a review to address a question that has
 been raised regarding the data, the data are to be saved beyond the normal retention  period until the question is formally resolved. Each Balancing Authority shall retain for a rolling 12-month period the values of: one-minute average ACE (ACEi), one-minute average Frequency Error, and, if using variable bias, one-minute average Frequency Bias.
1.4.  Additional Compliance Information
2.  Levels of Non-Compliance – CPS1
2.1.  Level 1:  The Balancing Authority Area’s value of CPS1 is less than 100% but greater than or equal to 95%.
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 5 of 12
2.3.  Level 3: The Balancing Authority Area’s value of CPS1 is less than 90% but greater than or equal to 85%. 
2.4.  Level 4:  The Balancing Authority Area’s value of CPS1 is less than 85%.
3.  Levels of Non-Compliance – CPS2 
3.1.  Level 1:  The Balancing Authority Area’s value of CPS2 is less than 90% but greater than or equal to 85%.
3.2.  Level 2: The Balancing Authority Area’s value of CPS2 is less than 85% but greater than or equal to 80%.
3.3.  Level 3: The Balancing Authority Area’s value of CPS2 is less than 80% but greater than or equal to 75%. 
3.4.  Level 4: The Balancing Authority Area’s value of CPS2 is less than 75%.
E. Regional Differences
E.A.  The ERCOT Control Performance Standard 2 Waiver  approved November 21, 2002.
E.B.  Regional Variance for the Western Electricity Coordinating Council
The following Interconnection-wide variance shall be applicable in the Western Interconnection and replaces, in their entirety, Requirement R1 and Section D.2. (i.e., under Compliance replace Levels of Non-Compliance – CPS1). Please note that the ACE equation is replaced in its entirety with the following equation identified in Requirement E.B.1.
Requirements and Measures
E.B.1.  Each Balancing Authority shall operate such that, on a rolling 12-month basis, the average of the clock-minute averages of the Balancing Authority’s Area Control Error (ACE) divided by 10B (B is the clock-minute average of the Balancing Authority Area’s Frequency Bias) times the corresponding clock-minute averages of the Interconnection’s Frequency Error is less than a specific limit. This limit ε1
2 is a constant derived from a targeted frequency bound (separately calculated for each Interconnection) that is reviewed and set as necessary by the NERC Operating Committee.
The equation for ACE in the Western Interconnection is:
( ) ( )   ATEC   ME S  AS  A
  I  I  F  F  B NI  NI  ACE    +−−−−=   10  
where:
•   NIA is the algebraic sum of actual flows on all tie lines.
•   NIS is the algebraic sum of scheduled flows on all tie lines.
1
* 10
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 6 of 12
•  B is the Frequency Bias Setting (MW/0.1 Hz) for the Balancing Authority. The constant factor 10 converts the frequency setting to MW/Hz.
•  FA is the actual frequency.
•  FS is the scheduled frequency. FS is normally 60 Hz but may be offset to effect manual time error corrections.
•  IME is the meter error correction factor typically estimated from the difference  between the integrated hourly average of the net tie line flows (NIA) and the hourly net interchange demand measurement (megawatt-hour). This term should normally
 be very small or zero.
( )   H Y   I  ATEC 
− =  when operating in Automatic Time Error Correction control mode.
I ATEC  shall be zero when operating in any other AGC mode.
•  Y = B / BS.
•  H = Number of Hours used to payback Primary Inadvertent Interchange energy. The value of H is set to 3.
•  BS = Frequency Bias for the Interconnection (MW / 0.1 Hz).
•  Primary Inadvertent Interchange (PIIhourly) is (1-Y) * (IIactual - B * ΔTE/6) 
•  IIactual is the hourly Inadvertent Interchange for the last hour.
•  ΔTE is the hourly change in system Time Error as distributed by the Interconnection Time Monitor. Where:
ΔTE = TEend hour  – TE begin hour  – TDadj – (t)*(TEoffset)
•  TDadj is the Reliability Coordinator adjustment for differences with Interconnection Time Monitor control center clocks.
•  t is the number of minutes of Manual Time Error Correction that occurred during the hour.
•  TEoffset is 0.000 or +0.020 or -0.020.
•  PIIaccum is the Balancing Authority’s accumulated PIIhourly in MWh. An On-Peak and Off-Peak accumulation accounting is required.
Where:
 peak on/off 
accum  + PIIhourly 
M.E.B.1.  Each Balancing Authority shall achieve, as a minimum, Requirement E.B.1 (CPS1) compliance of 100%.
CPS1 is calculated by converting a compliance ratio to a compliance percentage as follows:
CPS1 = (2 - CF) * 100%
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 7 of 12
where: ε1 is defined in Requirement E.B.1.
The rating index CF12-month is derived from 12 months of data. The basic unit of data comes from one-minute averages of ACE, Frequency Error and Frequency Bias Settings.
A clock-minute average is the average of the reporting Balancing Authority’s valid measured variable (i.e., for ACE and for Frequency Error) for each sampling cycle during a given clock-minute.
10B-10



 
   
 
 
 Normally, sixty (60) clock-minute averages of the reporting Balancing Authority’s ACE and of the respective Interconnection’s Frequency Error will be used to compute the respective hourly average compliance parameter.
hour insamplesminute-clock 
  ∑ =
 

∑ =
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 8 of 12
 
In order to ensure that the average ACE and Frequency Deviation calculated for any one- minute interval is representative of that one-minute interval, it is necessary that at least 50% of both ACE and Frequency Deviation samples during that one-minute interval be
 present. Should a sustained interruption in the recording of ACE or Frequency Deviation due to loss of telemetering or computer unavailability result in a one-minute interval not containing at least 50% of samples of both ACE and Frequency Deviation, that one- minute interval shall be excluded from the calculation of CPS1.
E.B.2.  Each Balancing Authority shall limit the absolute value of IATEC, the Automatic Time Error Correction term as follows: [Violation Risk Factor: Medium] [Time Horizon: Real-
time Operations] 
 I  ATEC  ≤ Lmax. 
M.E.B.2.  Forms of acceptable evidence for Requirement E.B.2 may include, but are not limited to: •  Dated Energy Management System (EMS) displays, •  WECC Interchange Tool, EMS application code, or •  Other archived data that demonstrates compliance.
E.B.3.  Each Balancing Authority shall set Lmax within the limits as follows:
0.20 * |B| ≤ Lmax  ≤  L10.
[Violation Risk Factor: Medium] [Time Horizon: Operations Planning]
M.E.B.3.  Forms of acceptable evidence for Requirement E.B.3 may include, but is not limited to: Dated Energy Management System (EMS) displays, WECC Interchange Tool, EMS application code, or Other archived data that demonstrates compliance.
E.B  Compliance
1.  Evidence Retention
The following evidence retention periods identify the period of time an entity is required to retain specific evidence to demonstrate compliance. For instances where the evidence retention period specified below is shorter than the time since the last audit, the Compliance Enforcement Authority may ask an entity to provide other evidence to show that it was compliant for the full time period since the last audit.
 
Page 9 of 12
Table of Compliance Elements
Lower VSL Moderate VSL High VSL Severe VSL
E.B.1 Real-time Operations
Medium The Balancing Authority Area’s value of CPS1 was less than 100% but greater than or equal to 95%.
The Balancing Authority Area’s value of CPS1 was less than 95% but greater than or equal to 90%. 
The Balancing Authority Area’s value of CPS1 was less than 90% but greater than or equal to 85%. 
The Balancing Authority Area’s value of CPS1 was less than 85%. 
E.B.2 Real-time Operations
Medium N/A   N/A   N/A  The Balancing Authority Area’s absolute value for  
 I  ATEC  was greater than   Lmax. 
E.B.3 Operations Planning
Medium N/A   N/A   N/A  The Balancing Authority did not set Lmax to within the limits in E.B.3 (i.e.,
0.20 * |B| ≤  Lmax ≤ L10). 
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 10 of 12
0 February 8, 2005 BOT Approval New
0 April 1, 2005 Effective Implementation Date New
0 August 8, 2005 Removed “Proposed” from Effective Date Errata
0 July 24, 2007 Corrected R3 to reference M1 and M2 instead of R1 and R2
Errata
0a December 19, 2007 Added Appendix 2 – Interpretation of R1 approved by BOT on October 23, 2007
Revised
0a January 16, 2008 In Section A.2., Added “a” to end of standard number
In Section F, corrected automatic numbering from “2” to “1” and removed “approved” and added parenthesis to “(October 23, 2007)”
Errata
0 January 23, 2008 Reversed errata change from July 24, 2007 Errata
0.1a October 29, 2008 Board approved errata changes; updated version number to “0.1a”
Errata
1 December 19, 2012 Adopted by NERC Board of Trustees
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 11 of 12
CPS1 DATA Description Retention Requirements
ε1  A constant derived from the targeted frequency  bound. This number is the same for each Balancing Authority Area in the Interconnection.
Retain the value of ε1 used in CPS1 calculation.
ACEi  The clock-minute average of ACE. Retain the 1-minute average values of ACE (525,600 values).
Bi  The Frequency Bias of the Balancing Authority Area.
Retain the value(s) of B i used in the CPS1 calculation.
FA  The actual measured frequency. Retain the 1-minute average frequency values (525,600 values).
FS  Scheduled frequency for the Interconnection. Retain the 1-minute average frequency values (525,600 values).
CPS2 DATA Description Retention Requirements
V Number of incidents per hour in which the absolute value of ACE clock-ten-minutes is greater than L10.
Retain the values of V used in CPS2 calculation.
ε10  A constant derived from the frequency bound. It is the same for each Balancing Authority Area within an Interconnection.
Retain the value of ε10 used in CPS2 calculation.
Bi  The Frequency Bias of the Balancing Authority Area.
Retain the value of Bi used in the CPS2 calculation.
Bs  The sum of Frequency Bias of the Balancing Authority Areas in the respective Interconnection. For systems with variable
 bias, this is equal to the sum of the minimum Frequency Bias Setting.
Retain the value of Bs used in the CPS2 calculation. Retain the 1-minute minimum bias value (525,600 values).
 
Stan da rd BAL-001-1 — Real Power Balan cing Con trol Performanc e
Page 12 of 12
Guidance and Rationale
Rationale for E.B.1
Premise: When a Balancing Authority Area uses the ACE equation with an ATEC correction component for both control and assessing performance, it provides a more accurate measurement of the Control Performance methodology while at the same time achieving the same reliability objective as the existing BAL-001-0.1a standard.
Justification : Adding the I ATEC  term to the ACE equation reduces the number of manual time error corrections and PIIaccum.
Goal: To establish an ACE equation that permits the implementation of Automatic Time Error Correction.
Rationale for E.B.2
Premise: I ATEC greater than  Lmax may result in a risk to reliability caused by large ATEC  payback.
Justification : Balancing Authorities should not control their Balancing Authority Areas using an approach that puts system reliability at risk.
Goal: The goal of Requirement E.B.2 is to limit I ATEC to Lmax in order to reduce potential reliability risks to the interconnection caused by a large ATEC payback term.
Rationale for E.B.3
Premise: Operating within an Lmax less than 0.20 * |B| may not provide sufficient correction for PII and operating with an Lmax greater than L10 may result in potential reliability risks caused by a large ATEC payback term.
Justification : Lmax should be limited to prevent Balancing Authorities from creating potential reliability risks caused by a large ATEC payback term.
 
Page 1 of  9 
2.  Number:  BAL0012 
3.  Purpose:  To control Interconnection frequency within defined limits. 
4.  Applicability: 
4.1.  Balancing Authority 
4.1.1  A Balancing Authority receiving Overlap Regulation Service is not subject 
to Control Performance Standard 1 (CPS1) or Balancing Authority ACE 
Limit (BAAL) compliance evaluation. 
4.1.2  A Balancing Authority that is a member of  a Regulation Reserve Sharing 
Group is the Responsible Entity only in periods during which the 
Balancing Authority is not in active status under the applicable 
agreement or the governing rules for the Regulation Reserve Sharing 
Group. 
5.  (Proposed) Effective Date: 
5.1.  First day of  the first calendar quarter that is twelve months beyond the date 
that this standard is approved by applicable regulatory authorities, or in those 
 jurisdictions where regulatory approval is not required, the standard becomes 
effective the first day of  the first calendar quarter that is twelve months 
beyond the date this standard is approved by the NERC Board of  Trustees, or as 
otherwise made effective pursuant to the laws applicable to such ERO 
governmental authorities. 
B. Requirements 
R1.  The Responsible Entity shall operate such that the Control Performance Standard 1 
(CPS1), calculated in accordance with Attachment 1, is greater than or equal to 100 
percent for the applicable Interconnection in which it operates for each preceding 12 
consecutive calendar month period, evaluated monthly. [Violation Risk  Factor: 
Medium] [Time Horizon: Real time Operations] 
R2.  Each Balancing Authority shall operate such that its clockminute average of  Reporting 
ACE  does not exceed its clockminute Balancing Authority ACE Limit (BAAL) for more 
than 30 consecutive clockminutes, calculated in accordance  with Attachment 2, for 
the applicable Interconnection in which the Balancing Authority operates.[Violation 
Risk  Factor: Medium] [Time Horizon: Real time Operations] 
C. Measures 
M1.  The Responsible Entity shall provide evidence, upon request, such as dated calculation 
output from spreadsheets, system logs, software programs, or other evidence (either 
 
Page 2 of  9 
M2.  Each Balancing Authority shall provide evidence, upon request, such as dated 
calculation output from spreadsheets, system logs, software programs, or other 
evidence (either in hard copy or electronic format) to demonstrate compliance with 
Requirement R2. 
D. Compliance 
1.  Compliance Monitoring Process 
1.1.  Compliance Enforcement Authority 
As defined in the NERC Rules of  Procedure, “Compliance Enforcement Authority” 
means NERC or the Regional Entity in their respective roles of  monitoring and 
enforcing compliance with the NERC Reliability Standards. 
1.2.  Data Retention 
The following evidence retention periods identify the period of  time an entity is 
required to retain specific evidence to demonstrate compliance.  For instances 
where the evidence retention period specified below is shorter than the time 
since the last audit, the Compliance Enforcement Authority may ask an entity to 
provide other evidence to show that it was compliant for the fulltime period 
since the last audit. 
The Responsible Entity shall retain data or evidence to show compliance for the 
current year, plus three previous calendar years unless, directed by its 
Compliance Enforcement Authority, to retain specific evidence for a longer 
period of  time as part of  an investigation.  Data required for the calculation of  
Regulation Reserve Sharing Group Reporting Ace, or Reporting ACE, CPS1, and 
BAAL shall be retained in digital format at the same scan rate at which the 
Reporting ACE is calculated for the current year, plus three previous calendar 
years. 
If  a Responsible Entity is found noncompliant, it shall keep information related to 
the noncompliance until found compliant, or for the time period specified above, 
whichever is longer. 
The Compliance Enforcement Authority shall keep the last audit records and all 
subsequent requested and submitted records. 
1.3.  Compliance Monitoring and Assessment Processes 
Compliance Audits 
Self Certifications 
Spot Checking 
Compliance Investigation 
Self Reporting 
Page 3 of  9 
1.4.  Additional Compliance Information 
R1  The CPS 1 value 
of  the 
Responsible Entity, for 
the preceding 12 
applicable 
Interconnection. 
 
Page 4 of  9 
0  February 8, 
0  August 8, 2005  Removed “Proposed” from Effective Date  Errata 
0  July 24, 2007  Corrected R3 to reference M1 and M2 
instead of  R1 and R2 
Errata 
approved by BOT on October 23, 2007 
Revised 
standard number 
numbering from “2” to “1” and removed 
“approved” and added parenthesis to 
“(October 23, 2007)” 
0.1a  October 29, 
version number to “0.1a” 
1  Inclusion of  BAAL and WECC Variance and 
exclusion of  CPS2 
Adopted by NERC Board of  Trustees 
 
Page 5 of  9 
CPS1 is calculated as follows: 
CPS1 = (2  CF) * 100%
The frequencyrelated compliance factor (CF), is a ratio of  the accumulating clockminute 
compliance parameters for the most recent preceding 12 consecutive calendar months, 
divided by the square of  the target frequency bound: 
Where  ε1I is the constant derived from a targeted frequency bound for each 
Interconnection as follows: 
  Eastern Interconnection  ε1I = 0.018 Hz 
  Western Interconnection  ε1I = 0.0228 Hz 
  ERCOT Interconnection  ε1I = 0.030 Hz 
  Quebec Interconnection  ε1I = 0.021 Hz 
The rating index CF12month is derived from the most recent preceding 12 consecutive 
calendar months of  data.  The accumulating clockminute compliance parameters are 
derived from the oneminute averages of  Reporting ACE, Frequency Error, and Frequency 
Bias Settings. 
A clockminute average is the average of  the reporting Balancing Authority’s valid 
measured variable (i.e., for Reporting ACE (RACE) and for Frequency Error) for each 
sampling cycle during a given clockminute. 
And, 
The Balancing Authority’s clockminute compliance factor (CF clockminute) calculation is: 
minute-clock incyclessampling
minute-clock incyclessampling
minute-clock  n
F  F 
Page 6 of  9 
Normally, 60 clockminute averages of  the reporting Balancing Authority’s Reporting ACE 
and Frequency Error will be used to compute the hourly average compliance factor (CF clock
hour). 
The reporting Balancing Authority shall be able to recalculate and store each of  the 
respective clockhour averages (CF clockhour averagemonth) and the data samples for each 24
hour period (one for each clockhour; i.e., hour ending (HE) 0100, HE 0200, ..., HE 2400). 
To calculate the monthly compliance factor (CF month): 
To calculate the 12month compliance factor (CF 12 month): 
To ensure that the average Reporting ACE and Frequency Error calculated for any one
minute interval is representative of  that time interval, it is necessary that at least 50 
percent of  both the Reporting ACE and Frequency Error sample data during the one
minute interval is valid.  If  the recording of  Reporting ACE or Frequency Error is interrupted 
such that less than 50 percent of  the oneminute sample period data is available or valid, 
then that oneminute interval is excluded from the CPS1 calculation. 
A Balancing Authority providing Overlap Regulation Service to another Balancing Authority 
calculates its CPS1 performance after combining its Reporting ACE and Frequency Bias 
hour insamplesminute-clock 
Page 7 of  9 
Settings with the Reporting ACE and Frequency Bias Settings of  the Balancing Authority 
receiving the Regulation Service. 
Page 8 of  9 
Equations Supporting Requirement R2 and Measure M2 
When actual frequency is equal to Scheduled Frequency, BAALHigh and BAALLow do not apply. 
When actual frequency is less than Scheduled Frequency, BAALHigh does not apply, and 
BAALLow is calculated as: 
F F 

10  
When actual frequency is greater than Scheduled Frequency, BAALLow does not apply and 
the BAALHigh is calculated as: 
 
F FTL F FTL B BAAL

BAALLow is the Low Balancing Authority ACE Limit (MW) 
BAALHigh is the High Balancing Authority ACE Limit (MW) 
10 is a constant to convert the Frequency Bias Setting from MW/0.1 Hz to MW/Hz 
Bi is the Frequency Bias Setting for a Balancing Authority (expressed as MW/0.1 Hz) 
F  A is the measured frequency in Hz. 
FS  is the scheduled frequency in Hz. 
FTLLow  is the Low Frequency Trigger Limit (calculated as FS  3ε1I Hz) 
FTLHigh is the High Frequency Trigger Limit (calculated as FS + 3ε1I Hz) 
Where  ε1I is the constant derived from a targeted frequency bound for each 
Interconnection as follows: 
  Eastern Interconnection  ε1I = 0.018 Hz 
  Western Interconnection  ε1I = 0.0228 Hz 
  ERCOT Interconnection  ε1I = 0.030 Hz 
  Quebec Interconnection  ε1I = 0.021 Hz 
To ensure that the average actual frequency calculated for any oneminute interval is 
representative of  that time interval, it is necessary that at least 50% of  the actual 
frequency sample data during that oneminute interval is valid.  If  the recording of  actual 
 
Page 9 of  9 
data is available or valid, then that oneminute interval is excluded from the BAAL 
calculation and the 30minute clock would be reset to zero. 
A Balancing Authority providing Overlap Regulation Service to another Balancing Authority 
calculates its BAAL performance after combining its Frequency Bias Setting with the 
 
Page 1 of  24 
2. Number: BAL-001-TRE-1
4. Applicability: 
4.2.1 Existing generating facilities regulated by the U.S. Nuclear Regulatory Commission prior to the Effective Date are exempt from Standard BAL-
001-TRE-01.
condenser mode are exempt from Standard BAL-001-TRE-01.
4.2.3 Any generators that are not required by the BA to provide primary frequency response are exempt from this standard.
5. Background: 
The ERCOT Interconnection was initially given a waiver of BAL-001 R2 (Control Performance Standard CPS2). In FERC Order 693, NERC was directed to develop a
Regional Standard as an alternate means of assuring frequency performance in the
ERCOT Interconnection. NERC was explicitly directed to incorporate key elements of the existing Protocols, Section 5.9. This required governors to be in service and
 performing with an un-muted response to assure an Interconnection minimum
Frequency Response to a Frequency Measurable Event (that starts at t(0)).
This regional standard provides requirements related to identifying Frequency Measureable Events, calculating the Primary Frequency Response of each resource in
the Region, calculating the Interconnection minimum Frequency Response and
monitoring the actual Frequency Response of the Interconnection, setting Governor deadband and droop parameters, and providing Primary Frequency Response
 performance requirements.
Under this standard, two Primary Frequency Response performance measures are
calculated: “initial” and “sustained.” The initial PFR performance (R9) measures the actual response compared to the expected response in the period from 20 to 52 seconds
after an FME starts. The sustained PFR performance (R10) measures the best actual
response between 46 and 60 seconds after t(0) compared to the expected response based
 
Page 2 of  24 
6. (Proposed) Effective Date: 
After final regulatory approval and in accordance with the 30-month Implementation Plan to allow the BA and each generating unit/generating facility time to meet the
requirements. See attached Implementation Plan (Attachment 1).
B. Requirements  
R1. The BA shall identify Frequency Measurable Events (FMEs), and within 14 calendar
days after each FME the BA shall notify the Compliance Enforcement Authority and make FME information (time of FME (t(0)), pre-perturbation average frequency, post-
 perturbation average frequency) publicly available.
[Violation Risk Factor = Lower] [Time Horizon = Operations Assessment]  
M1. The BA shall have evidence it reported each FME to the Compliance
Enforcement Authority and that it made FME information publicly available within 14 calendar days after the FME as required in Requirement R1.
R2. The BA shall calculate the Primary Frequency Response of each generating unit/generating facility in accordance with this standard and the Primary Frequency
Response Reference Document.1  This calculation shall provide a 12-month rolling
average of initial and sustained Primary Frequency Response performance. This
calculation shall be completed each month for the preceding 12 calendar months.
2.1. The performance of a combined cycle facility will be determined using an
expected performance droop of 5.78%.
2.2. The calculation results shall be submitted to the Compliance Enforcement Authority and made available to the GO by the end of the month in which they were completed.
2.3. If a generating unit/generating facility has not participated in a minimum of (8) eight FMEs in a 12-month period, its performance shall be based on a rolling
eight FME average response.
[Violation Risk Factor = Lower] [Time Horizon = Operations Assessment]  
M2. The BA shall have evidence it calculated and reported the rolling average initial and
sustained Primary Frequency Response performance of each generating unit/generating facility monthly as required in Requirement R2. 
R3. The BA shall determine the Interconnection minimum Frequency Response (IMFR)
in December of each year for the following year, and make the IMFR, the methodology for calculation and the criteria for determination of the IMFR publicly
available.
1  The Primary Frequency Response Reference Document contains the calculations that the BA will use to determine
Primary Frequency Response performance of generating units/generating facilities. This reference document is a
 
Page 3 of  24 
[Violation Risk Factor = Lower] [Time Horizon = Operations Planning]  
M3. The BA shall demonstrate that the IMFR was determined in December of
each year per Requirement R3. The BA shall demonstrate that the IMFR,
the methodology for calculation and the criteria for determination of the
IMFR are publicly available.
R4. After each calendar month in which one or more FMEs occurs, the BA shall determine and make publicly available the Interconnection’s combined Frequency Response
 performance for a rolling average of the last six (6) FMEs by the end of the following
calendar month.
[Violation Risk Factor = Medium] [Time Horizon = Operations Planning]  
M4. The BA shall provide evidence that the rolling average of the
Interconnection’s combined Frequency Response performance for the last six (6) FMEs was calculated and made public per Requirement R4.
R5. Following any FME that causes the Interconnection’s six-FME rolling average
combined Frequency Response performance to be less than the IMFR, the BA shall direct any necessary actions to improve Frequency Response, which may include,  but are not limited to, directing adjustment of Governor deadband and/or droop settings.
[Violation Risk Factor = Medium] [Time Horizon = Operations Planning]  
M5. The BA shall provide evidence that actions were taken to improve the
Interconnection’s Frequency Response if the Interconnection’s six-FME rolling
average combined Frequency Response performance was less than the IMFR,  per Requirement R5.
R6. Each GO shall set its Governor parameters as follows:
6.1. Limit Governor deadbands within those listed in Table 6.1, unless
directed otherwise by the BA.
Table 6.1 Governor Deadband Settings 
Generator Type  Max. Deadband
 All Other Generating Units/Generating Facilities  +/- 0.017 Hz 
6.2. Limit Governor droop settings such that they do not exceed those listed in Table 6.2, unless directed otherwise by the BA.
Table 6.2 Governor Droop Settings 
 
Page 4 of  24 
Hydro  5%
Nuclear 5%
Combustion Turbine (Combined Cycle) 4%
Steam Turbine (Simple Cycle) 5%
Steam Turbine (Combined Cycle)* 5%
Diesel  5%
Renewable (Non-Hydro) 5%
  *Steam Turbines of combined cycle resources are required to comply with Requirements R6.1, R6.2 and R6.3. Compliance with Requirements R9 and R10
will be determined through evaluation of the combined cycle facility using an
expected performance droop of 5.78%.
6.3. For digital and electronic Governors, once frequency deviation has exceeded the Governor deadband from 60.000 Hz, the Governor setting shall follow the slope
derived from the formula below.
where MWGCS is the maximum megawatt control range of the Governor control
system. For mechanical Governors, droop will be proportional from the deadband
 by design.
[Violation Risk Factor = Medium] [Time Horizon = Operations Planning]  
M6. Each GO shall have evidence that it set its Governor parameters in accordance with Requirement R6. Examples of evidence include but are
not limited to:
  Governor test reports
  Governor setting sheets
Page 5 of  24 
  Performance monitoring reports
R7. Each GO shall operate each generating unit/generating facility that is connected
to the interconnected transmission system with the Governor in service and
responsive to frequency when the generating unit/generating facility is online and
released for dispatch, unless the GO has a valid reason for operating with the Governor not in service and the GOP has been notified that the Governor is not
in service.
[Violation Risk Factor = Medium] [Time Horizon = Real-time Operations]  
M7. Each GO shall have evidence that it notified the GOP as soon as practical
each time it discovered a Governor not in service when the generating
unit/generating facility was online and released for dispatch. Evidence may include but not be limited to: operator logs, voice logs, or electronic
communications.
R8. Each GOP shall notify the BA as soon as practical but within 30 minutes
of the discovery of a status change (in service, out of service) of a Governor.
[Violation Risk Factor = Medium][Time Horizon = Real-time Operations]
M8. Each GOP shall have evidence that it notified the BA within 30 minutes of
each discovery of a status change (in service, out of service) of a Governor.
R9. Each GO shall meet a minimum 12-month rolling average initial Primary Frequency
Response performance of 0.75 on each generating unit/generating facility, based on
 participation in at least eight FMEs.
9.1. The initial Primary Frequency Response performance shall be the ratio of the Actual Primary Frequency Response to the Expected Primary
Frequency Response during the initial measurement period following
the FME.
9.2. If a generating unit/generating facility has not participated in a minimum of
eight FMEs in a 12-month period, performance shall be based on a rolling eight-FME average.
9.3. A generating unit/generating facility’s initial Primary Frequency Response performance during an FME may be excluded from the rolling
average calculation due to a legitimate operating condition that
 prevented normal Primary Frequency Response performance. Examples of legitimate operating conditions that may support exclusion of FMEs
include:
 
Page 6 of  24 
request raw data from the GO as a substitute.
[Violation Risk Factor = Medium] [Time Horizon = Operations Assessment]  
M9. Each GO shall have evidence that each of its generating units/generating facilities achieved a minimum rolling average of initial Primary Frequency
Response performance level of at least 0.75 as described in Requirement
R9. Each GO shall have documented evidence of any FMEs where the
generating unit performance should be excluded from the rolling average calculation.
R10. Each GO shall meet a minimum 12-month rolling average sustained Primary Frequency Response performance of 0.75 on each generating unit/generating facility, based on
 participation in at least eight FMEs.
10.1. The sustained Primary Frequency Response performance shall be the
ratio of the Actual Primary Frequency Response to the Expected Primary
Frequency Response during the sustained measurement period following
the FME.
10.2. If a generating unit/generating facility has not participated in a minimum of
eight FMEs in a 12-month period, performance shall be based on a rolling eight- FME average.
10.3. A generating unit/generating facility’s sustained Primary Frequency
Response performance during an FME may be excluded from the rolling
average calculation due to a legitimate operating condition that prevented normal Primary Frequency Response performance. Examples of legitimate
operating conditions that may support exclusion of FMEs include:
  Operation at or near auxiliary equipment operating limits (such as boiler feed pumps, condensate pumps, pulverizers, and forced draft fans);
  Data telemetry failure. The Compliance Enforcement Authority may
request raw data from the GO as a substitute.
[Violation Risk Factor = Medium] [Time Horizon = Operations Assessment]  
M10. Each GO shall have evidence that each of its generating units/generating
facilities achieved a minimum rolling average of sustained Primary Frequency Response performance of at least 0.75 as described in Requirement R10. Each
GO shall have documented evidence of any Frequency Measurable Events
 
Page 7 of  24 
2. Compliance Monitoring Period and Reset Time Frame 
2.1. If a generating unit/generating facility completes a mitigation plan and implements corrective action to meet requirements R9 and R10 of the standard, and if
approved by the BA and Compliance Enforcement Authority, then the generating
unit/generating facility may begin a new rolling event average performance on the next performance during an FME. This will count as the first event in the
 performance calculation and the entity will have an average
frequency performance score after 12 successive months or eight events per R9
and R10.
3. Data Retention 
3.1. The Balancing Authority, Generator Owner, and Generator Operator shall keep
data or evidence to show compliance, as identified below, unless directed by its
Compliance Enforcement Authority to retain specific evidence for a longer period of time as part of an investigation:
  The BA shall retain a list of identified Frequency Measurable Events and
shall retain FME information since its last compliance audit for Requirement R1, Measure M1.
  The BA shall retain all monthly PFR performance reports since its last compliance audit for Requirement R2, Measure M2.
  The BA shall retain all annual IMFR calculations, and related methodology
and criteria documents, relating to time periods since its last compliance audit for Requirement R3, Measure M3.
  The BA shall retain all data and calculations relating to the
Interconnection’s Frequency Response, and all evidence of actions taken
to increase the Interconnection’s Frequency Response, since its last compliance audit for Requirements R4 and R5, Measures M4 and M5.
  Each GOP shall retain evidence since its last compliance audit for Requirement R8, Measure M8.
  Each GO shall retain evidence since its last compliance audit for
Requirements R6, R7, R9 and R10, Measures M6, M7, M9 and M10. 
If an entity is found non-compliant, it shall retain information related to the non-
compliance until found compliant, or for the duration specified above, whichever
is longer.
 
Page 8 of  24 
Compliance Audits
days but less than 31 days after
identification of the event. 
days but less than 51 days after
identification of the event. 
days but less than 71 days after
identification of the event. 
days after identification of the
event. 
than one month but
reporting month. 
than 50 days but less
than 71 days after the end of the reporting
month. 
than 70 days but less
than 91 days after the end of the reporting
month. 
report within 90 days
R3  The BA did not make
the calculation and criteria for
determination of the
the IMFR publicly available. 
for the following year in December. 
The BA did not
calculate the IMFR for a calendar year. 
R4   N/A   N/A The BA did not make  public the six-FME rolling average
Interconnection combined Frequency
month. 
The BA did not calculate the six- FME rolling average
Interconnection combined Frequency
FME occurred. 
Page 9 of  24 
R5   N/A   N/A N/A The BA did not take action to improve Frequency Response
when the
Interconnection’s
> 10% and ≤ 20%
Any Governor  parameter setting was
> 20% and ≤ 30%
Any Governor  parameter setting was
> 30% and ≤ 40%
Any Governor  parameter setting was
> 40% outside setting
set to step into the droop curve. 
R7   N/A   N/A N/A The GO operated with its Governor out
of service and did not
notify the GOP upon discovery of its
Governor out of
service. 
R8  The GOP notified the BA of a change in Governor status
 between 31 minutes and one hour after
the GOP was notified
of the discovery of the change. 
The GOP notified the BA of a change in Governor status more
than 1 hour but
within 4 hours after
the GOP was notified
The GOP notified the BA of a change in
Governor status more
of the discovery of the change. 
The GOP failed to notify the BA of a change in Governor
status within 24 hours after the GOP was notified of the
discovery of the change. 
average initial Primary Frequency
Response
Response
Response
Response
Page 10 of  24 
2. Attachment 2 – Primary Frequency Response Reference Document, including Flow
Charts A and B.
and R10. This reference document is a Texas RE-controlled document
that is subject to revision by the Texas RE Board of Directors. It is not  part of the FERC-approved regional standard.
 b. The following process will be used to revise the Primary Frequency
Response Reference Document. A Primary Frequency Response Reference
Document revision request may be submitted to the Texas RE Reliability Standards Manager, who will present the revision request to the Texas RE
Reliability Standards Committee (RSC) for consideration. The revision
request will be posted in accordance with RSC procedures. The RSC shall discuss the revision request in a public meeting, and will accept and consider
verbal and written comments pertaining to the request. The RSC will make a
recommendation to the Texas RE Board of Directors, which may adopt the
revision request, reject it, or adopt it with modifications. Any approved revision to the Primary Frequency Response Reference Document shall be
filed with NERC and FERC for informational purposes.
Version History 
1 8/15/13 Adopted by NERC Board of Trustees
1 1/16/14 FERC Order issued approving BAL- 001-TRE-1. (Order becomes effective
April 1, 2014.)
Page 11 of  24 
Prerequisite Approvals:  None
New Definitions:    Frequency Measurable Event (FME)
  Governor  
  Primary Frequency Response (PFR)
Compliance with the Standard 
The following entities are responsible for being compliant with requirements of BAL-001-TRE-1:  
  Balancing Authority (BA)
  Generator Owners (GO)
  Generator Operators (GOP)
  Exemptions: o Existing generating facilities regulated by the U.S. Nuclear Regulatory Commission prior to
the Effective Date are exempt from Standard BAL-001-TRE-01. o Generating units/generating facilities while operating in synchronous condenser mode are
exempt from Standard BAL-001-TRE-01.
o  Any generators that are not required by the BA to provide primary frequency response are
exempt from this standard.
Effective Date  The Effective Date of this standard shall be the first day of the first calendar quarter after final regulatory approval. Registered Entities must be compliant with the Requirements in accordance with the 30-month Implementation Plan set forth below.
  12 months after Effective Date o The BA must be compliant with Requirement R1  o  At least 50% of the GO’s generating units/generating facilities must be compliant with 
Requirement R6 (if >1 unit/facility) o  At least 50% of the GO’s generating units/generating facilities must be compliant with
Requirement R7 (if >1 unit/facility) o The GOP must be compliant with Requirement R8 
  18 months after Effective Date o The BA must be compliant with Requirements R2, R3, R4, and R5  o 100% of the GO’s generating units/generating facilities must be compliant with 
Requirement R6
o 100% of the GO’s generating units/generating facilities must be compliant with  Requirement R7
BAL-001-TRE-1 Compliance Implementation Plan Document January 2013
 
Page 12 of  24 
  24 months after Effective Date o  At least 50% of the GO’s generating units/generating facilities must be compliant with 
Requirement R9 (if >1 unit/facility) o  At least 50% of the GO’s generating units/generating facilities must be compliant with
Requirement R10 (if >1 unit/facility)
  30 months after Effective Date o 100% of the GO’s generating units/generating facilities must be compliant with 
Requirement R9 o 100% of the GO’s generating units/generating facilities must be compliant with
Requirement R10
 
Page 13 of  24 
Requirements R2, R9 and R10 Performance Metric Calculations
I. Introduction
This Primary Frequency Response Reference Document provides a methodology for determining the Primary 
Frequency Response (PFR) performance of  individual generating units/generating facilities following 
Frequency Measurable Events (FMEs) in accordance with Requirements R2, R9 and R10.  Flowcharts in 
Attachment A (Initial PFR) and Attachment B (Sustained PFR) show the logic and calculations in graphical 
form, and they are considered part of  this Primary Frequency Response Reference Document.  Several Excel 
spreadsheets implementing the calculations described herein for various types of  generating units are 
available1 for reference and use in understanding and performing these calculations. 
This Primary Frequency Response Reference Document is not considered to be a part of  the regional 
standard.  This document will be maintained by Texas RE and will be subject to modification as approved by 
the Texas RE Board of  Directors, without being required to go through the formal Standard Development 
Process. 
Revision Process:  The following process will be used to revise the Primary Frequency Response Reference 
Document.  A Primary Frequency Response Reference Document revision request may be submitted to the 
Texas RE Reliability Standards Manager, who will present the revision request to the Texas RE Reliability 
Standards Committee (RSC) for consideration.  The revision request will be posted in accordance with RSC 
procedures.  The RSC shall discuss the revision request in a public meeting, and will accept and consider 
verbal and written comments pertaining to the request.  The RSC will make a recommendation to the Texas 
RE Board of  Directors, which may adopt the revision request, reject it, or adopt it with modifications.  Any 
approved revision to the Primary Frequency Response Reference Document shall be filed with NERC and 
FERC for informational purposes. 
As used in this document the following terms are defined as shown: 
High Sustained Limit (HSL) for a generating unit/generating facility: The limit established by the 
GO/GOP, continuously updatable in RealTime, that describes the maximum sustained energy 
production capability of  a generating unit/generating facility. 
1  These spreadsheets are available at www.TexasRE.org. 
 
Page 14 of  24 
Low Sustained Limit (LSL) for a generating unit/generating facility: The limit established by the 
GO/GOP, continuously updatable in RealTime, that describes the minimum sustained energy 
production capability of  a generating unit/generating facility. 
In this regional standard, the term “resource” is synonymous with “generating unit/generating facility”.
II. Initial Primary Frequency Response Calculations
Requirement 9
R9.  Each GO shall meet a minimum 12month rolling average initial Primary Frequency Response 
performance of  0.75 on each generating unit/generating facility, based on participation in at
least eight FMEs. 
9.1. The initial Primary Frequency Response performance shall be the ratio of  the Actual Primary 
Frequency Response to the Expected Primary Frequency Response during the initial 
measurement period following the FME. 
9.2.  If  a generating unit/generating facility has not participated in a minimum of  eight FMEs in a 
12month period, performance shall be based on a rolling eightFME average response. 
9.3. A generating unit/generating facility’s initial Primary Frequency Response performance 
during an FME may be excluded from the rolling average calculation due to a legitimate 
operating condition that prevented normal Primary Frequency Response performance. 
Examples of  legitimate operating conditions that may support exclusion of  FMEs include: 
  Operation at or near auxiliary equipment operating limits (such as boiler feed 
pumps, condensate pumps, pulverizers, and forced draft fans); 
  Data telemetry failure.  The Compliance Enforcement Authority may request raw 
data from the GO as a substitute. 
Initial Primary Frequency Response Performance Calculation Methodology
This portion of  this PFR Reference Document establishes the process used to calculate initial Primary 
Frequency Response performance for each Frequency Measurable Event (FME), and then average the events 
over a 12 month period (or 8 event minimum) to establish whether a resource is compliant with 
Requirement R9. 
This process calculates the initial Per Unit Primary Frequency Response of  a resource [P.U. PFRResource] as a 
ratio between the Adjusted Actual Primary Frequency Response (APFRAdj), adjusted for the preevent 
ramping of  the unit, and the Final Expected Primary Frequency Response (EPFRFinal) as calculated using the 
Preperturbation and Postperturbation time periods of  the initial measure. 
This comparison of  actual performance to a calculated target value establishes, for each type of  resource, 
the initial Per Unit Primary Frequency Response [P.U.PFRResource] for any Frequency Measurable Event (FME). 
Initial Primary Frequency Response performance requirement
 
Page 15 of  24 
 ..  0.75,  where P.U. PFRResource is the per unit measure of  the initial Primary Frequency Response of  a resource 
during identified FMEs. 
..        where P.U. PFRResource for each FME is limited to values between 0.0 and 2.0. 
The Adjusted Actual Primary Frequency Response (APFRAdj) and the Final Expected Primary Frequency 
Response (EPFRFinal) are calculated as described below. 
EPFR Calculations use droop and deadband values as stated in Requirement R6 with the exception of  
combinedcycle facilities while being evaluated as a single resource (MW production of  both the combustion 
turbine generator and the steam turbine generator are included in the evaluation) where the evaluation 
droop will be 5.78%.2 
 Actual Primary Frequency Response (APFRadj)
The adjusted Actual Primary Frequency Response (APFRadj) is the difference between Postperturbation 
         
where: 
  ∑   #  
  ∑   #  
Ramp Adjustment:  The Actual Primary Frequency Response number that is used to calculate P.U.PFR is 
adjusted for the ramp magnitude of  the generating unit/generating facility during the preperturbation 
minute.  The ramp magnitude is subtracted from the APFR. 
Ramp Magnitude = (MWT4  – MWT60)*0.59 
2  The effective droop of  a typical combinedcycle facility with governor settings per Requirement R6 is 5.78%, assuming 
a 2to1 ratio between combustion turbine capacity and steam turbine capacity.  Use 5.78% effective droop in all 
combinedcycle performance calculations. 
Page 16 of  24 
(MWT4  – MWT60) represents the MW ramp of  the generator resource/generator facility for a full 
minute prior to the event. The factor 0.59 adjusts this full minute ramp to represent the ramp that 
should have been achieved during the postperturbation measurement period. 
Expected Primary Frequency Response (EPFR)
For all generator types, the ideal  Expected Primary Frequency Response (EPFRideal) is calculated as the 
difference between the EPFRpostperturbation  and the EPFRpreperturbation. 
     
 
  60.0 60     1  
  60.0 60     1    
When the frequency is outside the Governor deadband and below 60 Hz:
  60.0 60     1  
  60.0 60     1     For each formula, when frequency is within the Governor deadband the appropriate EPFR value is 
zero.  The deadbandmax and droopmax quantities come from Requirement R6. 
Where: 
  ∑   #  
 
Page 17 of  24 
  ∑   #  
Capacity and NDC (Net Dependable Capacity) are used interchangeably and the term Capacity will be 
used in this document. Capacity is the official reported seasonal capacity of  the generating 
unit/generating facility.  The Capacity for windpowered generators is the real time HSL of  the wind 
plant at the time the FME occurred. 
Power Augmentation:  For Combined Cycle facilities, Capacity is adjusted by subtracting power 
augmentation (PA) capacity, if  any, from the HSL.  Other generator types may also have power 
augmentation that is not frequency responsive.  This could be “overpressure” operation of  a steam 
turbine at valves wide open or operating with a secondary fuel in service.  The GO should provide the BA 
with documentation and conditions when power augmentation is to be considered in PFR calculations. 
EPFRfinal for Combustion Turbines and Combined Cycle Facilities 
      60.0 10 0.00276 Note:  The 0.00276 constant is the MW/0.1 Hz change per MW of  Capacity and represents the MW 
change in generator output due to the change in mass flow through the combustion turbine due to 
the speed change of  the turbine during the postperturbation measurement period. This factor is 
based on empirical data from a major 2003 event as measured on multiple combustion turbines in 
ERCOT. 
 
Page 18 of  24 
The Rated Throttle Pressure and the Pressure curve, based on generator MW output, are provided by 
the GO to the BA.  This pressure curve is defined by up to six pair of  Pressure and MW breakpoints 
where the Rated Throttle Pressure and MW output, where Rated Throttle Pressure is achieved, is the 
first pair and the Minimum Throttle Pressure and MW output, where the Minimum Throttle Pressure is 
achieved, as the last pair of  breakpoints.  If  fewer breakpoints are needed, the pair values will be 
repeated to complete the six pair table. 
The K factor is used to model the stored energy available to the resource. The value ranges between 0.0 
and 0.6 psig per MW change when responding during a FME.  The GO can measure the drop in throttle 
pressure when the resource is operating near 50% output of  the steam turbine during a FME and 
provide this ratio of  pressure change to the BA.  K is then adjusted based on rated throttle pressure and 
resource capacity.  An additional sensitivity factor, the Steam Flow  Change Factor, is based on resource 
loading (% steam flow) and further modifies the MW adjustment.  This sensitivity factor will decrease 
the adjustment at resource outputs below 50% and increase the adjustment at outputs above 50%.  The 
GO should determine the fixed K factor for each resource that generally results in the best match 
between EPFR and APFR (resulting in the highest P.U.PFRResource).  For any generating unit, K will not 
change unless the steam generator is significantly reconfigured. 
EPFRfinal for Other Generating Units/Generating Facilities 
 X  EPFR EPFR ideal final    
where X is an adjustment factor that may be applied to properly model the delivery of  PFR. The X 
factor will be based on known and accepted technical or physical limitations of  the resource.  X may 
be adjusted by the BA and may be variable across the operating range of  a resource.  X shall be zero 
unless the BA accepts an alternative value. 
III. Sustained Primary Frequency Response Calculations
Requirement 10
R10.  The GO shall meet a minimum 12month rolling average sustained Primary Frequency Response 
performance of  0.75 on each generating unit/generating facility, based on participation in at least 
eight FMEs. 
10.1  The sustained Primary Frequency Response performance shall be the ratio of  the Actual 
Primary Frequency Response to the Expected Primary Frequency Response during the 
sustained measurement period following the FME.
10.2  If  a generating unit/generating facility has not participated in a minimum of  eight FMEs in a 
 
Page 19 of  24 
10.3  A generating unit/generating facility’s sustained Primary Frequency Response performance 
during an FME may be excluded from the rolling average calculation due to a legitimate 
operating condition that prevented normal Primary Frequency Response performance. 
Examples of  legitimate operating conditions that may support exclusion of  FMEs include: 
  Operation at or near auxiliary equipment operating limits (such as boiler feed pumps, 
condensate pumps, pulverizers, and forced draft fans); 
  Data telemetry failure.  The Compliance Enforcement Authority may request raw data 
from the GO as a substitute. 
Sustained Primary Frequency Response Performance Calculation Methodology
This portion of  this PFR Reference Document establishes the process used to calculate sustained Primary 
Frequency Response performance for each Frequency Measurable Event (FME), and then average the events 
over a 12 month period (or 8 event minimum) to establish whether a resource is compliant with 
Requirement R10. 
This process calculates the sustained Per Unit Primary Frequency Response of  a resource [P.U. SPFRResource] as 
a ratio between the maximum actual unit response at any time during the period from T+46 to T+60, 
adjusted for the preevent ramping of  the unit, and the Final  Expected Primary Frequency Response (EPFR) 
value at time T+46.3 
This comparison of  actual performance to a calculated target value establishes, for each type of  resource, 
the Per Unit Sustained Primary Frequency Response [P.U.SPFRResource] for any Frequency Measurable Event 
(FME). 
Sustained Primary Frequency Response performance requirement:
The standard requires an average performance over a period of  12 months (including at least 8 measured 
events) that is  ≥0.75. 
  ..  0.75 
 AvgPeriod  .. is either:    the average of  each resource’s sustained Primary Frequency Response performances [P.U. 
SPFRResource] during all of  the assessable Frequency Measurable Events (FMEs), for the most recent 
rolling 12 month period; or 
  if  the unit has not experienced at least 8 assessable FMEs in the most recent 12 month period, the
average of  the unit’s last 8 sustained Primary Frequency Response performances when the unit 
provided frequency response during a Frequency Measurable Event. 
3  The time designations used in this section refer to relative time after an FME occurs.  For example, “T+46” refers to 46 
seconds after the frequency deviation occurred. 
 
Page 20 of  24 
..       
P.U. SPFRResource is the per unit (P.U.) measure of the sustained Primary Frequency Response of a resource during identified Frequency Measurable Events. For any given eventP.U.SPFRResource for each FME will be limited to values between 0.0 and 2.0.
 Actual Sustained Pr imary Frequency Response ( ASPFR) Calculations
     
where: 
  ∑   #  
and:
 MW  MaximumResponse= maximum MW value telemetered by a unit from T+46 through T+60 during low
 frequency events and the minimum MW value telemetered by a unit from T+46 through T+60 during
a high frequency event. 
    
RampMW Sustained (MW)  – The Standard requires a unit/facility to sustain its response to a 
Frequency Measureable Event.  An adjustment available in determining a unit’s sustained Primary 
Frequency Response performance (P.U. SPFRResource ) is to account for the direction in which a 
resource was moving (increasing or decreasing output) when the event occurred (T0).  This is the 
RampMW  Sustained adjustment: 
RampMW  Sustained  = (MW (T 4) –  MW (T 60)) x 0.821 
Note:  The terminology  “MW (T 4)”  refers to MW  output  at  4 seconds before the Frequency  
Measurable Event  (FME) occurs at  (T0). 
 
Page 21 of  24 
By subtracting a reading at 4 seconds before, from a reading at 60 seconds before, the formula 
calculates the MWs a generator moved in the minute (56 seconds) prior to T0. 
The formula is then modified by a factor to indicate where the generator would have been at T+46, 
had the event not occurred: the “RampMW  Sustained .”  It does this by multiplying the MW change 
over 56 seconds before the event (MW(T4)  – MW(T60)) by a modifier.  This extrapolates to an 
equivalent number of  MWs the generator would have changed if&