UCSF Benioff
Children’s Hospital Oakland
Facilities Master Plan
![Page 2: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/2.jpg)
2
2
Agenda
• Current status of project• Adherence to approved plan• Residential Permit Parking• Construction Management Plan• Local business outreach
![Page 3: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/3.jpg)
3
Current Status
• Turner Construction Company selected as General Contractor
• Environmental Impact Report certified on May 19 by unanimous vote of City Council
• City staff is reviewing construction documents (plans)
• Streetscape work; Parking structure entrance
• Outpatient Center 2
![Page 4: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/4.jpg)
4
Adherence to Plan
• Work to be done in compliance with Standard Conditions of Approval and Mitigation Monitoring Program in EIR
– Noise Monitoring Program– Communications Plan– Construction Management Plan– Councilmember Kalb’s Amendments– Others
![Page 5: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/5.jpg)
5Proposed RPP Boundary
RPP Boundary Map
![Page 6: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/6.jpg)
6
RPP Update• Parking surveys (street occupancies)
completed today by Fehr & Peers (traffic consultant)
• Report will be issued in mid to late July• Door to door petitions can begin at any time• Link to petition is here:
– http://www2.oaklandnet.com/oakca1/groups/pwa/documents/webcontent/oak036303.pdf
![Page 7: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/7.jpg)
• Project Communication– Darrel Graef (Turner Supt) 559-351-2014– Site Signage– Flyers (notifications of change to site conditions as
it pertains to the neighborhood)– Project Website
• Concerns/Issue Reporting– Contact information will be posted on Site Signage
and Project Website
Construction Management Plan
![Page 8: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/8.jpg)
• Site Logistics– Hours of Operation per Conditions of Approval:
• M-F 7 AM to 7 PM• Saturdays as specifically approved by the Building Services
Division– Site Staging
• Confined to fenced construction area– Truck Route as approved by the City of Oakland
• Restricted to MLK, 52nd Street, 55th Street and Telegraph– Traffic Control plan as approved by the City of
Oakland
Construction Management Plan
![Page 9: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/9.jpg)
53RD STREET
![Page 10: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/10.jpg)
![Page 11: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/11.jpg)
Truck Route
![Page 12: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/12.jpg)
Oakland Children’s HospitalConstruction Sequencing
Phase 1: Make Ready | Duration: 5 Months | Average Trade Count: 25
Bus Stop to be Relocated
![Page 13: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/13.jpg)
Oakland Children’s HospitalConstruction Sequencing
Phase 1 Make Ready
Construction Status• Parking Structure Renovation
/ New Entrance Construction• Service Yard Construction• MLK Offsite Work• Demo / Relocation of MLK
Building after 90-day Advertisement
Logistics ItemsA. Potential Temporary Bus
Stop LocationB. Temporary FenceC. Temporary Vehicular Access
C
B
MLK JR Way(Sidewalk Closed)
A
![Page 14: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/14.jpg)
• Construction Parking– NO Parking in the residential neighborhood
• Subcontracts to include compliance with neighborhood and site parking restrictions
• Turner Superintendent to verify and track daily with trade foremen transportation/parking arrangements by their workers
• Violators will be immediately notified and given a warning. Next violation – will be removed from project
• Enforcement of CHO’s Residential Parking Permit program per the Traffic Demand Management Plan
Construction Management Plan
![Page 15: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/15.jpg)
• Parking Mitigations– Public Transit– Hospital Shuttle to
and from BART Station
– CHO Parking Lots • 20+ spaces
– Caltrans Lots• 34 spaces
Construction Management Plan
Assumptions:Trades using Bart/Public Transit – 10 to 15%Trades carpooling – 40 to 50%Established Parking – 50 to 55 spaces
![Page 16: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/16.jpg)
Construction Management Plan
American Lot
West Lot
Caltrans Lot
Caltrans Lot
![Page 17: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/17.jpg)
• Air Pollution/Noise Mitigation– Turner subcontracts include compliance with the
requirements of the Standard Conditions of Approval and Authorities Having Jurisdiction (AHJ)
– Regular discussion/reminder during Turner’s safety orientation and weekly subcontractor meetings
– Monitoring by an independent consultant
Construction Management Plan
![Page 18: Neighborhood meeting presentation june 25, 2015](https://reader034.vdocuments.us/reader034/viewer/2022051520/589b00bb1a28abb85d8b4909/html5/thumbnails/18.jpg)
• Defined as businesses located within the East Bay Green Corridor:– Alameda– Albany– Berkeley– El Cerrito– Emeryville– Hayward– Oakland– Richmond– San Leandro
Project’s Local Business Participation
• Goal = 35%
• Current Projection= 45%