nei 07-10a [revision 01" process controls and parameters for processing "wet wastes"...

42
NEI 07-10A [Revision 01 Generic FSAR Template Guidance for Process Control Program (PCP) March 2009

Upload: others

Post on 01-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

NEI 07-10A [Revision 01

Generic FSAR TemplateGuidance for ProcessControl Program (PCP)

March 2009

NEI 07-10A [Revision 0]

Nuclear Energy Institute

Generic FSAR TemplateGuidance for ProcessControl Program (PCP)

March 2009

Nuclear Energy Institute, 1776 1 Street N. W., Suite 400, Washington D.C. (202. 739.8000)

ACKNOWLEDGEMENTS

This program description document, Generic FSAR Template Guidance for Process ControlProgram (PCP), NEI 07-10A, Revision 0, was developed by the NEI New Plant RadiationProtection and Radioactive Waste Task Force. We appreciate the time, efforts and expertise ofthe individuals who contributed to the development of this guideline.

NOTICE

Neither NEI, nor any of its employees, members, supporting organizations, contractors, orconsultants make any warranty, expressed or implied, or assume any legal responsibility for theaccuracy or completeness of, or assume any liability for damages resulting from any use of, anyinformation apparatus, methods, or process disclosed in this report or that such may notinfringe privately owned rights.

NEI 07-IOA (Revision 0)March 2009

EXECUTIVE SUMMARY

NEI 07-1 OA, Generic FSAR Template Guidance for Process Control Program (PCP), Revision0, provides a complete generic program description for use in developing construction andoperating license (COL) applications. The document reflects contemporary Nuclear RegulatoryCommission (NRC) guidance, including Regulatory Guide 1.206, "Combined LicenseApplications for Nuclear Power Plants," and industry-NRC discussions regarding the applicablestandard review plan section. A main objective of this program description is to assist inexpediting NRC review and issuance of the combined license.

i

NHE 07-IOA (Revision 0)March 2009

TABLE OF CONTENTS

EXECUTIVE SUMMARY ............................................................................................... i

1 INTRODUCTION ................................................................................................... 1

2 APPLICABILITY AND CONTROLS ................ ........................................................... 1

2.1 PROCESS CONTROL PROGRAM .................................................................................. 1

3 PROCESS DESCRIPTION GUIDLINES ..................................................................... 2

3.1 RESPONSIBILITIES ............................................................ 2

3.2 ADMINISTRATION OF THE PCP AND SUPPORT DOCUMENTS ........... ........................ 2

3.3 APPROVAL PROCESS FOR QA APPROVED SUPPLIERS ............................................. 3

3.4 PCP REQUIREMENTS FOR VENDOR PROCESSES AND SERVICES ............................. 3

3.5 W ASTE TYPES ........................................................................................................... 4

3.6 PCP SOLIDIFICATION PROCESS DESCRIPTION ......................................................... 4

3.7 PCP DEWATERING PROCESS DESCRIPTION ............................................................ 5

3.8 ACCEPTABILITY ........................................................................................................ 5

3.9 WASTE CLASSIFICATION, CHARACTERIZATION AND MANIFEST .................................. 6

3.10 QUALITY ASSURANCE ................................................................................................. 6

4 DEFINITIONS ............................................................................................................. 6

4.1 FREE STANDING LIQUID (FSL) ................................................................................. 6

4.2 SOLIDIFICATION ......................................................................................................... 6

4.3 DEWATERING ....................................................................................... o .......................... 7

4.4 PROCESS PARAMETERS ............................................. , .................................................... 7

4.5 PCP ACCEPTANCE CRITERIA .................................................................................... 7

5 REFERENCES ............................................................................................................. 8

5.1 REGULATORY REQUIREMENTS ....................................................................................... 8

5.2 REGULATORY GUIDANCE ...................................................... 8

5.3 PROGRAMMATIC REFERENCES -SITE SPECIFIC ..................................................... 10

APPENDIX A - FINAL SAFETY EVALUATION ............................................................ A-1

APPENDIX B - NRC REQUEST FOR ADDITIONAL INFORMATION ............................. B-1

iii

NEI 07-IOA (Revision 0)March 2009

iv

NEI 07-10A (Revision 0)March 2009

GENERIC FSAR TEMPLATE GUIDANCE FOR PROCESS CONTROLPROGRAM (PCP)

1 INTRODUCTION

This Process Control Program (PCP) Description identifies the administrative andoperational controls for waste processing, process parameters, and surveillancerequirements which assure that the final waste product meets the requirements ofapplicable Federal, State and Disposal Site waste form requirements for burial at a 10CFR 61 licensed Low Level Waste (LLW) disposal site. The mobile radioactive wasteprocessing system conforms to applicable requirements in Regulatory Guide 1.143 andGeneric Letters applicable to wet solid waste. The PCP complies with 10 CFR 61.55 and1OCFR 61.56 for wet solid wastes. The PCP presents the methods by which liquid, andwet waste are processed and disposed in accordance with 10 CFR Part 61 and packagedand transported in accordance with 10 CFR Part 20,10 CFR Part 71 and 49 CFR Parts171-180.

The PCP implementation of process methods considers the plants efforts to minimize thequantity of radioactive waste produced (volume and/or activity).

The users of this template should review the reference section for additional informationrelated to NRC regulatory requirements and guidance. This template describes theelements of the PCP at the functional level consistent with 10 CFR 52.79 and if theseprograms are implemented as described, they do not require implementation ofinspections, tests, analyses and acceptance criteria in the COL application.

2 APPLICABILITY AND CONTROLS

2.1 PROCESS CONTROL PROGRAM

2.1.1 The Solid Waste Management System shall be operated in accordance with therequirements given in the PCP for the solidification or dewatering and packaging ofradioactive wastes in order to comply with the requirements of 10 CFR Part 20 and of 10CFR Part 71 prior to shipment of radioactive wastes from the site (Reference 5.2.1).

2.1.2 The PCP is applicable to the Solid Waste Management System in the solidification ofliquid or wet radioactive wastes or the dewatering of wet radioactive wastes to be shippedfor direct burial to a 10 CFR Part 61 licensed disposal site.

Radioactive wastes shipped off-site for processing are not required to be solidified or,dewatered to meet disposal requirements and are not subject to the solidification ordewatering requirements of the PCP (Reference 5.2.1).

1

NET 07-IOA (Revision 0)March 2009

2.1.3 The above controls of 2.1.1 and 2.1.2 are applicable at all times. If the packagingrequirements of 10 CFR Part 20, 10 CFR Part 61 or burial site requirements and/or 10CFR Part 71 are not satisfied, shipments of defectively packaged solid waste from the sitewill be suspended. The PCP will include surveillance checks necessary to demonstratecompliance with the above controls (Reference 5.2.21/5.2.22).

2.1.4 The PCP is ýnly applicable to Mixed Waste when it is solidified for disposal at a 10 CFRPart 61 disposal site. Waste streams with the potential for having the presence ofhazardous chemicals and radioactive materials, mixed waste, will be identified, processedand disposed in accordance with applicable Federal, State and local regulations(Reference 5.1.1).

2.1.5 The PCP confirms that incidental levels of waste petroleum-based oil contained inradioactive waste. meets the disposal site requirement for shipment.

2.1.6 The PCP identifies required implementing procedures for radioactive waste interimstorage of liquid or wet waste to meet the current final waste form requirements forfree standing liquids.

2.1.7 The interface between plant processing equipment (permanent or non-permanent) andequipment used for solidification and/or dewatering of wet solid radioactive waste willbe controlled in site procedures (Reference 5.2.5).

2.1.8 Samples will be obtained and analyzed for a batch of waste in accordance with siteprocedures for waste to be processed in the PCP. Analysis will be performed to ensurethat the waste falls within the acceptable parameters forsolidification/dewatering/drying (Reference 5.2.3).

3 PROCESS DESCRIPTION GUIDLINES

3.1 RESPONSIBILITIES

Each licensee will designate a site organization to be the owner, sponsor and administratorfor the PCP. Examples of the organization's PCP responsibilities include review andapproval of revisions; document administration; PCP technical content; and supporting thesite compliance with the PCP.

3.2 ADMINISTRATION OF THE PCP AND SUPPORT DOCUMENTS

Any changes to the PCP or implementing procedures require a review to assure that therequirements of the SRP Sections 11.4 and 11.5, BTP 11-3, 10 CFR 20, 61, and 71, 49CFR 171-180, state regulations, disposal and process facility waste acceptance criteria, andother requirements governing the disposal of solid radioactive waste (contained in the

2

NEI 07-10A (Revision 0)March 2009

references to this plan), are met. PCP changes will be sent to the NRC in the site's AnnualRadioactive Effluent Report for the period in which the changes were implemented.

Implementing procedures are developed, approved, and maintained for performing theactivities in support of the PCP. Examples Of functions included in site specificimplementation procedures are:

" Sampling, analysis, scaling of difficult to measure radionuclides, and wasteclassification of waste type and waste form,

" Process controls and parameters for processing "wet wastes" for land disposal and forprocessing Waste Class B and C wastes,

" Processing and disposal of "mixed waste" which is a waste containing bothradioactive material and hazardous material,

* Control and acceptance of vendor waste processing equipment and processes for siteand offsite processing of radioactive waste,

* Verification of compliance with disposal and processor site acceptance criteria," Mobile system conformance to Regulatory Guide 1.143 and Generic Letters 80-009

and 81-039.

In addition to the implementing procedures for PCP activities, site procedures will bedeveloped that describe the following activities associated with packaging and shippingradioactive wastes:

.0 Preparing radioactive material for shipment, preparation of the uniform radioactivewaste manifests, preparation of shipping papers, notifications, and shipment security,

" Container specifications and inspections, vehicle inspections, proper loading andshoring of shipments,

* Radioactive survey requirements and limitations for radioactive material shipments," Maintaining waste disposal records as required by 10 CFR 20.2108 and reporting

information on radioactive waste disposal.

3.3 APPROVAL PROCESS FOR QA APPROVED SUPPLIERS

Any supplier providing PCP services will be reviewed and approved prior to providingthose services. The site identifies the criteria that the waste processor will meet for theservices provided. Examples of criteria include the vendor PCP Topical Reports orequivalent, radioactive material license, state licensing, compliance with DOT regulations*for packaging, shipment, packages, transportation, and 10 CFR Part 61 disposalrequirements.

3.4 PCP REQUIREMENTS FOR VENDOR PROCESSES AND SERVICES

The vendor-supplied processes for solidification or dewatering will have a Topical Reportor other certification documenting appropriate approval of the process and associatedcontainers used. The vendor approved for solidification or dewatering services will haveNRC or appropriate regulatory certification documenting compliance with waste form

3

NEI 07-IOA (Revision 0)March 2009

requirements of the final product. The vendor Topical Report or equivalent certifies thatthe final product conforms to the appropriate waste form for Class A, B, or C waste.

Any vendor-supplied high integrity containers (HIC's) will have an NRC or appropriateregulatory approved report documenting compliance with waste form requirements.

Each container of processed waste will be classified as Class A, B or C waste using a sitespecific 10 CFR Part 61 Waste Form, Waste Classification and Waste CharacterizationImplementation Program(Reference 5.3).

Vendors providing PCP services on-site will meet the applicable requirements of the PCPand quality assurance requirements identified by the site contract. The vendor equipmentwill meet the design, construction, operation and quality assurance provisions of NRCBTP 11-3 (Reference 5.2.3) and Regulatory Guide 1.143 (Reference 5.2.5).

Vendors providing PCP services offsite will meet the requirements of their PCP processand applicable quality assurance requirements.

3.5 WASTE TYPES

'There are various types of radioactive waste expected to be generated at the plant site thatwill require processing, including solidification, or dewatering, or drying, or offsiteprocessing prior to burial. These radwaste types can be categorized based on theirchemical and physical properties. Typical waste types generated at a plant site may includebut are not limited to; bead resin, powdered resin, demineralizer sludge/slurries, filtercartridges, oily waste, and dry active waste.

Dry wastes do not, normally require stabilization processing and are treated asradioactively contaminated solids and packaged for disposal or offsite processing inaccordance with applicable Federal/ State regulations and burial site criteria.

3.6 PCP SOLIDIFICATION PROCESS DESCRIPTION

Waste solidification will be performed to approved procedures that ensure all applicableregulatory and disposal site criteria are met. The specific waste processing technology andmethod and process parameters used to process waste are described in site procedures. Theparameters should include (depending on the type of waste):

0 waste pH;* water content;* oil content;* waste density;* content of chelating agents;1 ratio of stabilization agent to chemical additives by types of wastes;" waste form;" mixer speed; mixing time; curing time;

4

NEI 07-10A (Revision 0)March 2009

" pre-solidification hazardous waste characterization;* specific activity and gamma analysis.

The minimum solidification acceptance criteria will include free standing liquid criteria;physical criteria and chemical criteria based on the disposal site. A representative sampleof the waste to be solidified will be obtained for bench scale testing based on a frequencyidentified by the disposal site. The process parameters should include any of the aboveparameters that are applicable.

3.7 PCP DEWATERING PROCESS DESCRIPTION

The methods used for removal of liquid from wet waste for final disposal will complywith the specific disposal site requirements where the waste is being disposed.Dewatering/drying of wet wastes will be performed in a manner equivalent to the processguidelines described below using approved procedures with enough detail to implementapplicable requirements. Examples of dewatering/drying process parameters include:

* Settling time* Drain time* Pumping time" Dewatering pump suction vacuum (inches Hg)* Drying time" Additional dewatering/drying cycles

Mechanical filters (e.g., cartridge, bag, membrane) are dewatered so that accumulation offree standing liquid in the disposal container does not exceed disposal site limits. The-method of dewatering is in accordance with a previously defined, evaluated anddocumented process.

Dewatering of"slurried" wet wastes (e.g., resin, carbon, Zeolite, filter precoat, filterbackwash, sludge) removes the interstitial liquid from solids such that the disposalcontainer meets the applicable regulatory and burial free standing liquid criteria fordisposal.

Wet wastes may also be dewatered using a drying process that adds an absorber materialresulting in a product with no free standing liquid (e.g. a monolithic salt block in a storagedrum). This method of dewatering by drying will be in accordance with a previouslydefined, evaluated and documented process.

3.8 ACCEPTABILITY

The solidification and dewatering/drying process product is verified and documented tomeet the PCP Acceptance Criteria requirements, for that process. Verification mayinclude bench scale test, full scale test, verification of PCP process compliance, orverification that the amount of free-standing liquid is within disposal site criteria for thecontainer and the standing water requirements of 10 CFR Part 61.

5

NEI 07-IOA (Revision 0)March 2009

Product verification failures will be documented, reported if required, investigated andremedial actions taken. Any misuse, mishaps, or failure of a waste form or container willbe reported to responsible site personnel for action.

3.9 WASTE CLASSIFICATION, CHARACTERIZATION AND MANIFEST

All waste will be classified in accordance with the requirements of 10 CFR 61.55 asimplemented by site procedures. Analysis will be performed on the waste streams at leastannually (biannually for Class A waste), to determine the isotopic abundance of non-gamma emitting isotopes in the waste streams. Scaling factors, for the non-gammaemitting and transuranic constituents, will be developed from these analyses (Reference5.2.8 and 5.2.18).

All wastes shall meet the waste characteristics requirements of 10 CFR 61.56 as applicableand waste packages will be marked to identify the waste-class as required by 10 CFR,61.57. The manifesting requirements of 10 CFR 20.2006 andAppendix G to 10 CFR Part20 will be implemented by site shipping instructions (Reference 5.2.23).

3.10 QUALITY ASSURANCE

Quality related activities for the PCP will be implemented as described in site proceduresto meet the applicable requirements of Regulatory Guide 1.143 and/or ANSI 55.6(Reference 5.2.5 and 5.2.9). The activities include verification that all solid radioactivewaste meets applicable State and Federal regulations and burial site criteria.

4 DEFINITIONS

4.1 FREE STANDING LIQUID (FSL)

Liquid that is in a disposal container but is not bound by the waste in the container iscalled a free-standing liquid (FSL). FSL is the liquid available for release if disposalcontainer integrity is lost. The amount of FSL in a radioactive waste disposal container isless than a specified amount to meet 10 CFR Part 61, state regulations, and disposal sitecriteria.

4.2 SOLIDIFICATION

Solidification is a process that converts radioactive waste into a product meeting 10 CFRPart 61, state, and disposal site requirements for waste-form stability and FSL.Solidification is accomplished by mixing measured amounts of liquid or wet radioactivewaste, binder and required additives that, after sufficient curing time, produce a solidhomogeneous, freestanding monolith. At the end of the curing period, the absence of

6

NEI 07-IOA (Revision 0)March 2009

excessive FSL is verified by confirmation that the PCP was followed or by physicalverification/testing.

4.3 DEWATERING

Dewatering removes the loosely bound liquid from a wet radioactive waste such thataccumulation of Free Standing Liquid in disposal container is unlikely to approach thedisposal limit threshold values defined by applicable regulations and disposal site criteria.NRC regulations require that the process used to dewater radioactive wastes to meetdisposal criteria shall be governed by a PCP.

4.4 PROCESS PARAMETERS

*Those conditions measured or observed during a solidification or dewatering process toensure an acceptable product are the process parameters. These are determined for eachwaste type and are specific to the process method used.

4.5 PCP ACCEPTANCE CRITERIA

The PCP acceptance criteria are the bounding numerical values for the solidificationprocess parameters that produce an acceptable product or the bounding numerical valuesfor the dewatering process parameters that ensure free standing liquid requirements aremet.

7

NEI 07-10A (Revision 0)March 2009

5 REFERENCES

5.1 REGULATORY REQUIREMENTS

5.1.1 10 CFR 20.2006, 20.2007, 20.2108 and Appendix G of 10 CFR Part 20

5.1.2 10 CFR Part 50, Appendix A, General Design Criterion 60, "Control of Releases ofRadioactive Materials to the Environment." General Design Criterion 64, "MonitoringRadioactivity Releases."

5.1.3 10 CFR 61.55, 61.56, 61.57, "Licensing Requirements for Land Disposal of RadioactiveWaste."

5.1.4 10 CFR Part 71, "Packaging and Transportation of Radioactive Material."

5.1.5 40 CFR Part 266" Storage, Treatment, Transportation, and Disposal of Mixed Waste"

5.1.6 49 CFR Parts 171-180 "Hazardous Materials Regulations"

5.1.7 Licensed radioactive waste burial site

5.1.8 State hazardous waste regulations

5.2 REGULATORY GUIDANCE

5.2.1 NUREG-0133, "Preparation of Radiological Effluent Technical Specifications forNuclear Power Plants.

5.2.2 NUREG-0800, SRP 11.4, "Solid Waste Management Systems"

5.2.3 NUREG-0800, Branch Technical Position 11-3 "Design Guidance for Solid RadioactiveWaste Management Systems Installed in Light-Water-Cooled Nuclear Power ReactorPlants"

5.2.4 Generic Letter 89-01, "Guidance for the Implementation of Programmatic Controls ForRETS in The Administrative Controls Section of Technical Specifications and theRelocation of Procedural Details of Current RETS to the Offsite Dose CalculationManual or'Process Control Program"

5.2.5 Regulatory Guide 1.143, "Design Guidance for Radioactive Waste Management Systems,Structures, and Components Installed in Light-Water-Cooled Nuclear Power Plants."

5.2.6 USNRC, Branch Technical Position, "Technical Position on Waste Form", Rev. 1,January, 1991 and HPPOS-290, "Waste Form Technical Position, Revision 1"

8

NEI 07-10A (Revision 0)March 2009

5.2.7 Issuance of Final Technical Position on Concentration Averaging and Encapsulation,Revision in Part to Waste Classification Technical Position January 17, 1995

5.2.8 "Final Waste Classification and Waste Form Technical Position Papers" dated May 11,1983

5.2.9 ANSI 55.6, "Liquid Radioactive Waste Processing Systems for Pressurized WaterReactor Plants"

5.2.10 ANSI/ANS 40.37-1993, "Mobile Radioactive Waste Processing Systems"

5.2.11 Regulatory Guide 8.8, "Information Relevant to Ensuring That Occupational RadiationExposures at Nuclear Power Stations Will Be As Low As Is Reasonably Achievable."

5.2.12 Generic Letter 80-009, "Low Level Radioactive Waste Disposal."

5.2.13 Generic Letter 81-038, "Storage of Low Level Radioactive Wastes at Power ReactorSites."

5.2.14 Generic Letter 81-039, "NRC Volume Reduction Policy"

5.2.15 Information Notice 87-07, "Quality Control of Onsite Dewatering / SolidificationOperations By Outside Contractors"

5.2.16 IE Bulletin 79-19, "Packaging, Transport and Burial of Low-Level Radioactive Waste"

5.2.17 Information Notice 90-3 1, "Update on Waste Form and High Integrity ContainersTopical Report Review Status, Identification of Problems with Cement Solidification,and Reporting of Waste Mishaps"

5.2.18 Information Notice 86-020, "Low-Level Radioactive Waste Scaling Factors, 10 CFR Part61"

5.2.19 Information Notice 84-072, "clarification of Conditions For Waste Shipments Subject ToHydrogen Gas Generation"

5.2.20 Information Notice 85-092, "Surveys of Wastes Before Disposal from Nuclear ReactorFacilities"

5.2.21 NUREG- 1301 "Offsite Dose Calculation Manual Guidance: Standard RadiologicalEffluent Controls for Pressurized Water Reactors."

5.2.22 NUREG-1302 "Offsite Dose Calculation Manual Guidance: Standard RadiologicalEffluent Controls for Boiling Water Reactors."

5.2.23 NUREG/BR-0204 "Instructions for Completing NRC's Uniform Low-Level RadioactiveWaste Manifest"

9

NEI 07-IOA (Revision 0)March 2009

5.3 PROGRAMMATIC REFERENCES -SITE SPECIFIC

5.3.1 Technical Specifications 5.0 Administrative Controls

5.3.2 Site Specific Licensee Commitments

5.3.3 Site Specific FSAR

5.3.4 Site Quality Assurance Program

5.3.5 Vendor Quality Assurance Program

5.3.6 Plant PCP Procedures for Specific Waste Processing Methods such as Dewatering,Solidification, or HIC Integrity Verification.

5.3.7 Plant implementation procedures on 10 CFR Part 61 waste form, waste classification andwaste characterization.

5.3.8 Plant procedures on the requirements for interim storage for processed waste.

10

APPENDIX A

FINAL SAFETY EVALUATION REPORT

A-1

A-2

January 8, 2009

Mr. Russell J. Bell, DirectorNew Plant LicensingNuclear Generation DivisionNuclear Energy Institute1776 I Street, NW, Suite 400Washington, DC 20006-3708

SUBJECT: FINAL SAFETY EVALUATION FOR TOPICAL REPORT NEI 07-10, "GENERICFINAL SAFETY ANALYSIS REVIEW TEMPLATE GUIDANCE FOR PROCESSCONTROL PROGRAM," REVISION 3 (TAC NO. Q00159)

Dear Mr. Bell:

By letter dated September 27, 2007, the Nuclear Energy Institute (NEI) submitted for U.S.Nuclear Regulatory Commission (NRC) staff review it's proposed Topical Report, NEI 07-10,"Generic Final Safety Analysis Review Template Guidance for Process Control Program,"Revision 0: Based on comments and input from NRC staff, NEI submitted Revision 1 of theProcess Control Program (PCP) generic template on October 18, 2007 and Revision 2 onFebruary 28, 2008.

In response to the NRC staff's May 6, 2008, request for additional information (RAI), NEIsubmitted NEI 07-10, Revision 3 on May 30, 2008.

Enclosed is the staffs safety evaluation (SE) which defines the basis for acceptance ofNEI 07-10, Revision 3. The NRC staff finds that for combined license applications (COLAs),NEI 07-10, Revision 3, provides an acceptable template for assuring that the administrative andoperational controls for waste processing, process parameters, and surveillance requirementswithin the scope of the PCP will meet the requirements of Title 10 of the Code.of FederalRegulations, Section 52.79.

Our acceptance applies only to material provided in NEI 07-10, Revision 3. We do not intend torepeat our review of the acceptable material described in the NEI 07-10, Revision 3. When theNEI 07-10, Revision 3 appears as a reference in COLAs, our review will ensure that the materialpresented applies to the specific application involved. Licensing requests that deviate fromNEI 07-10, Revision 3, will be subject to a plant-specific or site-specific review in accordancewith applicable review standards.

A-3

R. Bell -2-

In accordance with the guidance provided on the NRC website, we request that NEI publish theaccepted version of NEI 07-10, Revision 3 within 3 months of receipt of this letter. Theaccepted version should incorporate this letter and the enclosed SE after the title page. Theaccepted version should also contain historical review information, including NRC RAIs andyour responses. The accepted versions shall include a "-A" (designating accepted) followingthe report identification symbol.

If future changes to the NRC's regulatory requirements affect the acceptability of NEI 07-10,Revision 3, NEI will be expected to revise NEI 07-10 appropriately, or justify its continuedapplicability for subsequent referencing.

If you have any questions, please contact Sheryl A. Burrows at (301) 415-6086 or via email atSheryl. Burrows)nrc.qov.

Sincerely,

IRA/

William D. Reckley, ChiefRulemaking, Guidance, andAdvanced Reactor Branch

Division of New Reactor LicensingOffice of New Reactors

* Project No. 689

Enclosure:Safety Evaluation

cc w/encl: See next page

A-4

R. Bell -2-

In accordance with the guidance provided on the NRC website, we request that NEI publish theaccepted version of NEI 07-10, Revision 3 within 3 months of receipt of this letter. Theaccepted version should incorporate this letter and the enclosed SE after the title page. Theaccepted version should also contain historical review information, including NRC RAIs andyour responses. The accepted versions shall include a "-A" (designating accepted) followingthe report identification symbol.

If future changes to the NRC's regulatory requirements affect the acceptability of NEI 07-10,Revision 3, NEI will be expected to revise NEI 07-10 appropriately, or justify its continuedapplicability for subsequent referencing.

If you have any questions, please contact Sheryl A. Burrows at (301) 415-6086 or via email atSheryl. Burrows(dnrc.,ov.

Sincerely,

IRAI

William D. Reckley, ChiefRulemaking, Guidance, andAdvanced Reactor Branch

Division of New Reactor LicensingOffice of New Reactors

Project No. 689

Enclosure:Safety Evaluation

cc w/encl: See next page

DISTRIBUTION:PUBLIC SBernal, NRO RidsNroDcipNRGA R/F GCicotte, NRO RidsNroDcipChpbCHPB R/F JDehmel, NRO RidsAcrsAcnwMailCenterSBurrows, NRO RidsNroDnrl RidsOgcMailCenterRRobinson, NRO RidsNroDnrlNrga

ADAMS Accession No.: ML082910077 NRO-002

OFFICE DNRL/NRGA:PM DNRL/NRGA:LA DCIP/CHPB:BC OGC, DNRL/NRGA:BCNAME SBurrows RRobinson TFrye* MSpencer .WReckley

DATE 10/17/2008 10/17/2008 9/30/2008 01/ 08/2009 NLO 01/08/2009OFFICIAL RECORD COPY

*See SER dated 9/30/2008, ML082180177

A-5

SAFETY EVALUATION

FINAL SAFETY EVALUATION FOR THE NUCLEAR ENERGY INSTITUTE'S TECHNICAL

REPORT NEI 07-10, "GENERIC FINAL SAFETY ANALYSIS REVIEW TEMPLATE GUIDANCE

FOR PROCESS CONTROL PROGRAM," REVISION 3 (TAC NO. Q00159)

1.0 BACKGROUND

On September 27, 2007, the Nuclear Energy Institute (NEI) submitted for U.S. NuclearRegulatory Commission (NRC) staff review its proposed Topical Report, NEI 07-10, "GenericFinal Safety Analysis Report Template Guidance for Process Control Program" Revision 0[Agencywide Documents Access Management System (ADAMS) accession no. ML072740309].NEI-07-10 was developed by the NEI to assist in expediting NRC review and approval ofcombined licenses (COLs). Based on comments and input distributed at a series of publicmeetings in the intervening period, NEI submitted Revision 1 of the Process Control Program(PCP) template on October 18, 2007 [ADAMS accession no. ML072840029] and Revision 2 onFebruary 28, 2008 [ADAMS accession no. ML080640463]. The staff determined that additionalinformation was necessary to complete its review, and on April 1, 2008, an email of a requestfor additional information (RAI) was transmitted to NEI staff, with follow-up letter datedMay 6, 2008 [ADAMS accession no. ML080940250]. On May 31, 2008, the NEI formallyresponded to the RAI by submission of Revision 3 of the Technical Report [ADAMS accessionno. ML081720166]. The Technical Report provides a generic PCP description for use withcombined license applications (COLAs). NEI-07-10 is not applicable to the review and issuanceof construction permits or operating licenses under Title of the Code of Federal Regulations,Part 50 (10 CFR Part 50).

2.0 REGULATORY EVALUATION

The NRC staff verified that NEI-07-1 0, Revision 3 complies with the following regulations,regulatory guidance, and NUREGs:

* 10 CFR Part 20, "Standards for protection against radiation."

* 10 CFR Part 21, "Reporting of defects and noncompliance."

* 10 CFR Part 50, "Domestic licensing of production and utilization facilities."

* 10 CFR Part 52, "Licenses, certifications, and approvals for nuclear power plants;

Subpart A, Subpart B, Subpart C."

0 10 CFR Part 61, "Licensing requirements for land disposal of radioactive waste."

* 10 CFR Part 71, "Packaging and transportation of radioactive material."

0 Regulatory Guide (RG) 1.143, "Design Guidance for Radioactive Waste Management

Systems, Structures, and Components Installed in Light-Water-Cooled Nuclear Power

Plants."

Enclosure

A-6

-2-

" NUREG-0800, Standard Review Plan (SRP), Section 11.4, Revision 3, "Solid WasteManagement System."

* NUREG-0800, SRP, Branch Technical Position (BTP) 11-3, Revision 3, "DesignGuidance for Solid Radioactive Waste Management Systems Installed inLight-Water-Cooled Nuclear Power Reactor Plants."

3.0 TECHNICAL EVALUATION

The staffs review concentrated on the proposed PCP as one element of the Process andEffluent Monitoring and Sampling Program. The staff also reviewed the template to ensure thatthe generic PCP addressed those items pertaining to the Process and Effluent Monitoring andSampling Program, and proposed milestones were included under the requirements of Section13.4 of the final safety analysis review (FSAR). In evaluating the adequacy of the program, thestaff followed the guidance of the SRP (NUREG-0800), Section 11.4, "Solid Waste ManagementSystem."

To satisfy Section 13.4 of each FSAR application, Operational Program Procedures under NEI07-10 are to be developed, but will not necessarily all be implemented, prior to fuel load. Underthe requirements of a license condition, a COL holder is required to make available to the NRCa plant-specific PCP. The plant-specific PCP developed under the requirements of the licensecondition will be verified by the NRC through inspection and shall replace and supersede thegeneric NEI 07-10 Template. Accordingly, NEI 07-10 fulfills licensing requirements starting withthe submission of a COLA, and ending with the fulfillment of the license condition specifying theavailability of and verification by the NRC of a plant-specific PCP prior to fuel load. Finally, inaccordance with SECY 05-0197, the implementation of operational programs identified in NEI07-10 does not necessitate inspections, tests, analyses, and acceptance criteria (ITAAC) in adesign certification (DC) or COLA.

NEI-07-10 is organized into guidelines for responsibilities and administration of the program,approval process for quality assurance (QA) approved suppliers, waste types, solidification,dewatering, acceptability, waste characterization, waste classification, shipment manifests, andQA for the program itself. The safety evaluation (SE) follows the organization of the PCP.

3.1 Responsibilities and Administration

The "Responsibilities" and "Administration" sections of NEI-07-10 describes the basicorganizational responsibilities and controls over the administration of the program to assure thatNRC guidance will be followed and requirements will be met. The program includes acommitment to develop procedures and practices to achieve the program objectives.

NEI-07-10 does not specifically include a timeline for development of the complete program.The PCP does outline the procedures that will be developed, and which will be required to bedeveloped and inspected after issuance of the license but prior to fuel load.

Based on the staff s review of the "Responsibilities" and "Administration" sections of NEI-07-10outlined above, the staff concludes that NEI-07-10 sufficiently describes, in terms of scope andlevel of detail, these aspects of the PCP to enable a reasonable assurance finding of

A-7

-3-

acceptability for issuance of a COL with verification of the PCP after completing the constructioninspection program in implementing the plant-specific PCP under the requirements of a licensecondition.

3.2 Approval Process for (QA) Approved Suppliers, PCP Requirements for VendorProcesses and Services

The "Approval Process for (QA) Approved Suppliers" and "PCP Requirements for VendorProcesses and Services" sections of NEI-07-10 indicate that suppliers will be evaluated andapproved prior to providing related services, and vendor processes will ensure that processedmaterials will conform to waste class, form, and content stipulated by regulations and contractspecifications. The PCP also requires that containers used for shipment offsite be designedand/or certified consistent with regulatory approvals such as' certificates of compliance or designspecifications. Vendor equipment used on site is required to meet design, construction,operation, and quality assurance provisions of NUREG-0800, SRP, BTP 11-3, "DesignGuidance for Solid Radioactive Waste Management Systems Installed in Light-Water-CooledNuclear Power Reactor Plants," which includes provisions for collection of spilled materials(curbing/collection), connection of temporary and portable systems, corrosion prevention, leakand spill minimization, and prevention. of cross-connection with, or contamination of,non-radioactive systems.

Based on the staffs review of the "Approval Process for(QA) Approved Suppliers" and "PCPRequirements for Vendor Processes and Services" sections of NEI-07-10 outlined above, thestaff concludes that NEI-07-1 0 sufficiently describes, in terms of scope and level of detail, theseaspects of the PCP to enable a reasonable assurance finding of acceptability for issuance of aCOL with verification of these program elements after completing the construction inspectionprogram in implementing the plant-specific PCP under the requirements of a license condition.

3.3 Waste Types

The "Waste Types" section of NEI-07-10 describes in general terms the variety of waste typestypically encountered from operations, and addresses categorization based on chemical andphysical properties as required by NRC regulation. Stabilization of wastes is briefly addressed..Processing of the various waste types, and programs and processes to address waste types notspecifically listed, are addressed throughout the PCP template.

Based on the staffs review of the "Waste Types" section of NEI-07-10 outlined above, the staffconcludes that NEI-07-10 sufficiently describes, in terms of scope and level of detail, wastetypes sufficient to enable a reasonable assurance finding of acceptability for issuance of a COLwith verification of these program elements after completing the construction inspection programin implementing the plant-specific PCP under the requirements of a license condition.

3.4 PCP Solidification/Dewaterinq Process Descriptions

The "PCP Solidification Process Description" and "PCP Dewatering Process Description"sections of NEI-07-10 addresses approved procedures for solidification and dewatering of liquidand wet solid wastes. Parameters relevant to determination of the appropriate process areaddressed, such as chemical and physical forms, hazardous waste characterization, media, and

A-8

-4-

minimum. acceptance criteria. Limitations on free standing liquids, slurried or otherheterogeneous wastes containing liquids, and removal of interstitial liquids are also addressed.

Based on the staff's review of the "PCP Solidification Process Description" and "PCPDewatering Process Description" sections of NEI-07-10 outlined above, the staff concludes thatNEI-07-1 0 sufficiently describes, in terms of scope and level of detail, solidification anddewatering processes sufficient to make a reasonable assurance finding of acceptability forissuance of a COL with verification of these program elements after completing the constructioninspection program in implementing the plant-specific PCP under the requirements of a licensecondition.

3.5 Acceptability

The "Acceptability" section of NEI-07-10 describes in general terms the verification process toensure that wastes are acceptable for disposal consistent with the requirements of the disposalfacility and land disposal regulations. Verification procedures, compensatory action upon failureof solidification or dewatering processes, and mishaps or unsuccessful processes are brieflyaddressed.

The template provides for acceptability of materials for interim storage awaiting disposal throughdevelopment of site-specific procedures, consistent with NRC guidance. The template does notrequire that radioactive materials be stored in containers suitable for transportation underDepartment of Transportation regulations, but does require that storage be according toprocedures developed under the template and subject to site-specific NRC inspection andverification. With regard to storage, the template is consistent with NRC Generic Letter (GL) 81-038. Due to site-specific differences in availability of disposal capacities and variations in theneed for storage.capacity pending disposal, COL applicants will need to provide information ona case-by-case basis with respect to long-term management and storage of solid wastes usingthe guidance of RG 1.206 and SRP Section 11.4, Revision 3 (NUREG-0800).

Based on the staffs review of the "Acceptability" section of NEI-07-10 outlined above, the staffconcludesthat NEI-07-10 sufficiently describes, in terms of scope and level of detail,acceptability of process controls sufficient to enable a reasonable assurance finding ofacceptability for issuance of a COL with verification of these program elements after completingthe construction inspection program in implementing the plant-specific PCP under therequirements of a license condition.

3.6 Waste Characterization, Classification, and Manifests

The "Waste Characterization, Classification, and Manifests" section of NEI-07-10 describes thatwaste classification will be implemented by site-specific procedures in accordance with10 CFR 61.55, "Waste classification." The section requires at least annual waste streamassessment through analysis (biannually for Class A waste) for radionuclide distribution andconcentrations, and addresses non-gamma emitters, transuranics, and scaling factors. Thesection requires waste characteristics to be consistent with 10 CFR 61.56, "Wastecharacteristics." The section also refers to identification of waste class as required by10 CFR 61.57, "Labeling," and indicates that site shipping instructions be developed consistentwith NUREG/BR-0204, "Instructions for Completing NRC's Uniform Low-Level RadioactiveWaste Manifest", 10 CFR 20.2006, "Transfer for disposal and manifests", and 10 CFR Part 20,

A-9

-5-

Appendix G, "Requirements for Transfers of Low-Level Radioactive Waste Intended forDisposal at Licensed Land Disposal Facilities and Manifests."

Based on the staffs review of the "Waste Characterization, Classification, and Manifests"section of NEI-07-10 outlined above, the staff concludes that NEI-07-10 sufficiently describes, interms of scope and level of detail, acceptability of waste characterization, classification, andmanifests, sufficient to make a reasonable assurance finding of acceptability for issuance of aCOL with verification of these program elements after completing the construction inspectionprogram in implementing the plant-specific PCP under the requirements of a license condition.

3.7 QA Proqrams

The "QA Programs" section of NEI-07-10 indicates that site procedures will be implementedconsistent with RG 1.143, "Design Guidance for Radioactive Waste Management Systems,Structures, and Components Installed in Light-Water-Cooled Nuclear Power Plants" and/orAmerican National Standards Institute 55.6, "Liquid Radioactive Waste Processing Systems forPressurized Water Reactor Plants."

Based on the staffs review of the "QA Programs" section of NEI-07-10 outlined above, the staffconcludes that NEI-07-10 sufficiently describes, in terms of scope and level of detail,acceptability of QA programs, sufficient to enable a reasonable assurance finding ofacceptability for issuance of a COL, with verification of these program elements after completingthe construction inspection program in implementing the plant-specific PCP under therequirements of a license condition.

3.8. NRC Post Combined License Activities

Before the implementation of a plant specific PCP, the NRC staff will inspect the elements of thePCP in accordance with the NRC Construction Inspection Program as outlined in the NRCInspection Manual Chapter 2504. The objectives of these inspections are to determine thereadiness of the PCP program in performing its intended objectives. The inspection will confirmthat solid waste management systems (SWMS) equipment, administrative programs, andoperational procedures implementing the functional elements of the PCP are consistent with theDC, supplemental information or departures described in the COL; regulatory requirements of10 CFR Part 20, 10 CFR Part 61, 10 CFR Part 71, 49 CFR Parts 171-180; GL 89-01;NUREG-1 301 for PWR Plants or NUREG-1 302 for BWR plants and NUREG-0133 for eitherplant; RGs 1.21 and 1.33, and applicable NRC and industry guidance, as listed in NEI 07-10.

The NRC inspection will confirm that the COL holder has successfully completed all applicableITAACs for those portions of the liquid waste management systems (LWMS) and SWMS usedto process solid and wet wastes under the PCP. The ITAACs are described in DCD Tier 1 ofDCs and Section 14.3 of the FSAR of COL applications. The staff will confirm whether the COLholder has addressed all relevant ITAACs for liquid and solid waste processing systems,including confirming their descriptions, functional arrangements, and operating characteristics.The ITAACs, once performed by the COL holder and meeting their respective acceptancecriteria, provide reasonable assurance that a plant that incorporates the features described in itsDC, and operates in accordance with the DC and PCP, will meet the provisions of NRCregulations.

A-10

-6-

4.0 CONCLUSION

Construction Health Physics Branch (CHPB) staff used the acceptance criteria of SRPSection 11.4, "Solid Waste Management System," and BTP 11-3, "Design Guidance for SolidRadioactive Waste Management Systems Installed in Light-Water-Cooled Nuclear PowerReactor Plants," as the basis for evaluating the acceptability of NEI-07-10, "Generic FSARTemplate Guidance for Process Control Program," Revision 3. The CHPB staff has determinedthat NEI-07-10 Revision 3 is consistent with the requirements, guidance, and industry standardsfor a PCP as outlined in Section 2.0 of this evaluation with verification of the program aftercompleting the construction inspection program in implementing the plant-specific PCP underthe requirements of a license condition. Any processing, storage, or handling of wastes offsiteare required to be consistent with onsite controls, and are to be addressed by applicants assite-specific information.

The PCP described in NEI-07-10 incorporates standards and guidance that allow an applicantto operate and maintain the facility, in a safe manner, during normal operation and anticipatedoperational occurrences. The PCP will be developed and maintained in compliance with thefacility license and applicable regulations. The PCP calls for processes to be periodicallyevaluated and revised to reflect industry experience; to incorporate changes to the facility,procedures, regulations, and quality assurance requirements; and to support facilitymanagement in determining the overall program effectiveness as well as compliance with NRCregulations and state agency disposal site regulations. The template requires that the storageof waste pending disposal be developed under site-specific NRC review and verification byinspection, such as addressed in NRC GL 81-038. Due to site-specific differences in availabilityof disposal capacities and variations in the need for storage capacity pending disposal,applicants will need to provide information on a case-by-case basis with respect to long-termmanagement and storage of solid wastes using the guidance of RG 1.206 and SRP Section11.4, Revision 3 (NUREG-0800).

The final PCP prepared under a license condition will be further described in site and/oroperating procedures as specified in the PCP template. Sufficient records will be maintainedand kept available for NRC inspection during construction to verify adequacy of the program.

On the basis of its review, the staff concludes that NEI-07-10, "Generic FSAR TemplateGuidance for Process Control Program," Revision 3 adequately provides guidance forestablishing the PCP. Accordingly, NRC staff concludes that NEI-07-10 Revision 3 complieswith the applicable NRC regulations, guidance, and industry standards and can be utilized byapplicants for COLAs.

A-1I

-7-

5. REFERENCES

5.1 Bell, R. J., NEI, to the U.S. NRC, "Response to NRC April 28 Request for AdditionalInformation on NEI 07-09 and May 6 Request for Additional Information on NEI 07-10,"May 30, 2008.

5.2 NUREG-0800, SRP, Section 11.4, Revision 3, "Solid Waste Management System,"March 2007.

5.3 NUREG-0800, SRP, BTP 11-3, Revision 3, "Design Guidance for Solid RadioactiveWaste Management Systems Installed in Light-Water-Cooled Nuclear Power ReactorPlants," March 2007.

5.4 RG 1.206, "Combined License Applications for Nuclear Power Plants (LWR Edition)"Section C.I. 11, "Radioactive Waste Management," June 2007.

3{

A-12

DCWG - Combined (All)cc:

(Revised 12/15/2008)

Mr. Glenn H. ArchinoffAECL Technologies481 North Frederick AvenueSuite 405Gaithersburg, MD 20877

Mr. Ray AycockField SupervisorU.S. Fish and Wildlife ServiceMississippi Ecological Services Office6578 Dogwood View ParkwayJackson, MS 39213

Mr. Richard L. BakerBechtel Power Corporation5275 Westview DriveFrederick, MD 21703-8306

Scott BondCallaway PlantP.O. Box 620Fulton, MO 65251

Ms. Michele BoydLegislative DirectorEnergy ProgramPublic Citizens Critical Mass Energy

and Environmental Program215 Pennsylvania Avenue, SEWashington, DC 20003

Ms. Cindy BrizesU.S. Department of EnergyP.O. Box AAiken, SC 29802

Mr. Barton Z. Cowan, EsquireEckert Seamans Cherin & Mellott, LLC600 Grant Street, 44th FloorPittsburgh, PA 15219

DirectorDivision of Compliance & InspectionBureau of Radiation ControlTexas Department of State Health Services1100 West 49th StreetAustin, TX 78756-3189

Mr. Eugene S. GrecheckVice PresidentNuclear Support ServicesDominion Energy, Inc.5000 Dominion Blvd.Glen Allen, VA 23060

Mr. Jay M. GutierrezMorgan, Lewis & Bockius, LLP111 Pennsylvania Avenue, NWWashington, DC 20004

Ms. Sophie GutnerP.O. Box 4646Glen Allen, VA 23058

Mr. Brian HastingsPublic Utility CommissionWilliam B. Travis BuildingP.O. Box 133261701 Noth Congress AvenueAustin, TX 78701-3326

Mr. Tim E. HerrmannVice President, Nuclear EngineeringAmerenUEP.O. Box 620Fulton, MO 65251

Mr. Ronald KinneySouth Carolina DHEC2600 Bull StreetColumbia, SC 29201

A-13

-2-

DCWG - Combined (All)

Dr. Regis A. MatzieSenior Vice President and

Chief Technology OfficerWestinghouse Electric Company20 International DriveWindsor, CT 06095

Mr. Norris McDonaldPresidentAAEA9903 Caltor LaneFt. Washington, MD 20744

Dr. Masanori OnozukaMitsubishi Nuclear Energy Systems, Inc.2300 Wilson Blvd.Suite 300Arlington, VA 22201-5426

Dr. C. Keith PaulsonMitsubishi Nuclear Energy Systems, Inc.300 Oxford Drive, Suite 301Monroeville, PA 15146

PBMR Pty. LimitedLake Buena Vista Building1267 Gordon Hood AvenuePO Box 9396Centurion 0046Republic of South Africa

Charles PetersonPillsbury, Winthrop, Shaw & Pittman, LLP2300 "N" Street, NWWashington, DC 20037

Mr. Tom SlivaVice PresidentNew Plants Project ManagementAREVA, NP, Inc. 3315Old Forest RoadP.O. Box .10935Lynchburg, VA 24506-0935

Mr. David W. SutherlandChesapeake Bay Field OfficeU.S. Fish and Wildlife Service177 Admiral Cochrane DriveAnnapolis, MD 21401

Mr. Robert E. SweeneyIBEX ESI4641 Montgomery AvenueSuite 350Bethesda, MD 20814

Mr. Ed WallaceGeneral Manager - ProjectsPBMR Pty LTDP. 0. Box 9396Centurion 0046Republic of South Africa

Mr. Gary Wright, DirectorDivision of Nuclear Facility SafetyIllinois Emergency Management Agency1035 Outer Park DriveSpringfield, IL 62704

Mr. Ernest ReedLiving Education Centerfor Ecology and the Arts

P.O. Box 2612Charlottesville, VA 22902

A-14

-3-

DCWG - Combined (All)

[email protected] (Andrea Sterdis)[email protected] (Amy Monroe)[email protected] (Al Paglia)[email protected] (Adrian Heymer)[email protected] (Anne W. Cottingham)[email protected] (Barbara Lee-Murphy)[email protected] (Barbara Perdue)[email protected] (Bob Evans)[email protected] (Bill Moore)[email protected] (Robert E. Brown)[email protected] (Charles Brinkman)[email protected] (Brock Degeyter)[email protected] (Mario D. Carelli)[email protected] (Carey Fleming)[email protected] (Chris Maslak)[email protected] (Keith Paulson)[email protected] (C.K. Paulson)[email protected] (EdwardW. Cummins)[email protected] (C. Waltman)[email protected] (Dan Williamson)[email protected] (David Hinds)[email protected] (David Lewis)[email protected] (R. DeLaBarre)[email protected] (David Lochbaum)[email protected] (Don Lewis)[email protected] (David Poole)[email protected] (Donald Woodlan)[email protected] (E. Cullington)[email protected] (Eddie Grant)[email protected] (Eddie R. Grant)[email protected] (Frank Quinn)[email protected] (Fred Madden)[email protected] (Garry D. Miller)[email protected] (Guy Cesare)[email protected] (George Edgar)[email protected] (George Honma)[email protected] (George Wadkins)[email protected] (Patrick Gove)[email protected] (James Gresham) "[email protected] (G. W. Curtis)[email protected] (George Alan Zinke)[email protected] (Thomas Hicks)[email protected] (Ian C. Richard)[email protected] (James Beard)

A-15

-4-

DCWG - Combined (All)

[email protected] (Jan Caldwell)[email protected] (Jean Amundson)[email protected] (Jeff Simmons)[email protected] (Jay M. Gutierrez)[email protected] (James Riccio)[email protected] (Jim Warren)[email protected] (James J. Nesrsta)[email protected] (Joel Friday)[email protected] (John Conly)John.O'[email protected] (John O'Neill)[email protected] (John Sorensen)Joseph [email protected] (Joseph Hegner)joseph [email protected] (Joe Tapia)joseph [email protected] (Joseph Tapia)junichi [email protected] (Junichi Uchiyama)[email protected] (Karen Hadden)[email protected] (K. C. Rogers)[email protected] (Kathryn M. Sutton)[email protected] (Kenneth 0. Waugh)[email protected] (Lawrence J. Chandler)[email protected] (Lois Chalmers)[email protected] (Lou Lanese)Marc. [email protected] (Marc Brooks)[email protected] (Maria Webb)[email protected]@wsms.com (Mark Beaumont)[email protected] (Marvin L. Smith)[email protected] (Masanori Onozuka)[email protected] (Masayuki Kambara)[email protected] (Matias Travieso-Diaz)[email protected] (Brad Mauer)[email protected] (Marty Bowling)[email protected] (Scott Peterson)[email protected] (M. Giles)[email protected] (Mike Blevins)mike [email protected] (Mike Moran)[email protected] (Mitch Lucas)[email protected] (Marvin Fertel)[email protected] (M. Wetterhahn)[email protected] (Michael Mariotte)[email protected] (Pareez Golub)[email protected] (Patricia L. Campbell)[email protected] (Paul Gaukler)[email protected] (Paul Gunter)[email protected] (Peter Jordan)

A-16

-5-

DCWG - Combined (All)

[email protected] (Paul Hinnenkamp)[email protected] (Peter Hastings)[email protected] (Bobby Bird)[email protected] (Ronald Clary)[email protected] (Biff Bradley)[email protected] (Rebecca Smith-Kevern)[email protected] (Russell Bell)[email protected] (R.K. Temple)[email protected] (Robert H. Kitchen)[email protected] (Roberta Swain)[email protected] (Sandra Sloan)[email protected] (Robert C. Sauer)[email protected] (Stephen P. Frantz)[email protected] (Shinji Kawanago)[email protected] (Shinji Kawanago)[email protected] (Sid Kere)[email protected] (Steven Hucik)[email protected] (Tim Gilder)[email protected] (Tria Kibler)[email protected] (Thomas P. Miller)[email protected] (Tom McCallum)[email protected] (Tyson Smith)[email protected] (Vanessa Quinn)[email protected] (Bill Victor)[email protected] (Ronald P. Vijuk)[email protected] (Wanda K. Marshall)[email protected] (Wayne Marquino)[email protected] (W. Horin)

A-17

APPENDIX BNRC REQUEST FOR ADDITIONAL INFORMATION

B-1

B-2

May 6, 2008

Mr. Russell J. Bell, DirectorNew Plant LicensingNuclear Generation DivisionNuclear Energy Institute1776 I Street, NW, Suite 400Washington, DC 20006-3708

SUBJECT: REQUEST FOR ADDITIONAL INFORMATION REGARDING NUCLEARENERGY INSTITUTE TOPICAL REPORT 07-10, GENERIC FINAL SAFETYANALYSIS REPORT TEMPLATE GUIDANCE FOR PROCESS CONTROLPROGRAM, REVISION 2 (PROJECT NO. 689; TAC MD6860)

Dear Mr. Bell:

By letter dated September 27, 2007, the Nuclear Energy Institute (NEI) submitted forU.S. Nuclear Regulatory Commission staff review its proposed topical report, NEI 07-10,"Generic Final Safety Analysis Report Template Guidance for Process Control Program (PCP)"RevisiOn 0. Based on comments and input distributed at public meetings, NEI submittedRevision 1 of the PCP template in October 2007 and Revision 2 in February 2008. The staffhas determined that additional information is necessary to complete its review. OnApril 1, 2008, an'electronic copy of the enclosed request for additional information (RAI) wastransmitted to Ralph Andersen of NEI. Although this RAI has already been provided to you .

electronically, we will not expect a response until 30 days following the date of issuance of thisletter; therefore, please let me know if you will not be able to provide your written reply withinthat time period.

If you have any questions or comments regarding this matter, please contactMs. Sheryl A. Burrows by telephone at (301) 415-6086 or by e-mail at Sheryl.Burrowsanrc.qov.

Sincerely,

IRA/

William D. Reckley, ChiefRulemaking, Guidance andAdvanced Reactor Branch

Division of New Reactor LicensingOffice of New Reactors

Project No. 689

Enclosure:As stated

cc: See next page

B-3

May 6, 2008Mr. Russell J. Bell, DirectorNew Plant LicensingNuclear Generation DivisionNuclear Energy Institute1776 I Street, NW, Suite 400Washington, DC 20006-3708

SUBJECT: REQUEST FOR ADDITIONAL INFORMATION REGARDING NUCLEARENERGY INSTITUTE TOPICAL REPORT 07-10, GENERIC FINAL SAFETYANALYSIS REPORT TEMPLATE GUIDANCE FOR PROCESS CONTROLPROGRAM, REVISION 2 (PROJECT NO. 689; TAC MD6860)

Dear Mr. Bell:

By letter dated September 27, 2007, the Nuclear Energy Institute (NEI) submitted forU.S. Nuclear Regulatory Commission staff review its proposed topical report, NEI 07-10,"Generic Final Safety Analysis Report Template Guidance for Process Control Program (PCP)"Revision 0. Based on comments and input distributed at public meetings, NEI submittedRevision 1 of the PCP template in October 2007 and Revision 2 in February 2008. The staffhas determined that additional information is necessary to complete its review. OnApril 1, 2008, an electronic copy of the enclosed request for additional information (RAI) wastransmitted to Ralph Andersen of NEI. Although this RAI has already been provided to youelectronically, we will not expect a response until 30 days following the date of issuance of thisletter; therefore, please let me know if you will not be able to provide your written reply withinthat time period.

If you have any questions or comments regarding this matter, please contact

Ms. Sheryl A. Burrows by telephone at (301) 415-6086 or by e-mail at Sheryl.Burrows()nrc.,qov.

Sincerely,

IRA/

William D. Reckley, ChiefRulemaking, Guidance and

Advanced Reactor BranchDivision of New Reactor LicensingOffice of New Reactors

Project No. 689

Enclosure:As stated

cc: See next page

ADAMSOFFICE

NAMEDATE

ACCESSION NO.: ML080940250PM:DNRL/NRGA LA:DNRLSBurrows/ rxr4 DClarke04/03/08 04/03/08

BC:DCIP/CHPBLRE TFrye

104/09/08

,L RECORD COPY

BC:DNRL/NRGAWReckley05/06/08 '1

OFFICI.

B-4

SUBJECT: REQUEST FOR ADDITIONAL INFORMATION REGARDING NUCLEAR ENERGYINSTITUTE TOPICAL REPORT 07-10, GENERIC FINAL SAFETY ANALYSIS REPORTTEMPLATE GUIDANCE FOR PROCESS CONTROL PROGRAM (PCP), REVISION 2(PROJECT NO. 689; TAC MD6860)

Distribution:PUBICNRGA R/FSBurrows, NRODClarke, NRORidsNroDnrlNrgaRidsOgcMailCenterRidsNroDnrlRidsAcrsAcnwMailCenter

RidsNroDcipChpbRidsNroDnrlNoepRidsNroDnrlNgelRidsNroDnrlNge2RidsNroDnrlNwelRidsNroDnrlNwe2RidsNroDnrlNmip

B-5

Request for Additional InformationGeneric FSAR Template Guidance for Process Control Program

NEI 07-10 Rev. 2, February 2008

Consistent with Regulatory Guide 1.206, Section C.IV.1, and 10 CFR 52.79, a CombinedLicense (COL) Application must contain a Final Safety Analysis Report (FSAR) that includesinformation "at a level sufficient to enable the Commission to reach a final conclusion on allsafety matters that must be resolved ... before issuance of a COL." The following is a requestfor additional information (RAI) on the Nuclear Energy Institute's (NEI's) Template No.NEI 07-10, titled "Generic FSAR Template Guidance for Process Control Program (PCP),"Revision 2, dated February 2008, which is contemplated to be incorporated by reference byapplicants as a sufficient program description consistent with the above.

The listed item addresses technical and regulatory clarifications remaining to be resolved inorder to develop a safety evaluation of the generic program, based on the staffs review of thetemplate against U.S. Nuclear Regulatory Commission (NRC) regulatory and technicalrequirements and guidance. The RAI is tied to a specific section of the NEI template, andincludes a suggested modification to the existing text for the purpose of addressing thetechnical issue identified by NRC staff. The staff recognizes other approaches may be used inachieving the same objectives. The recommendation is presented for the purpose of attaininga mutual understanding of issues identified by the staff and facilitate NEI's effort in revising thetemplate. The comment does not address editorial or typographic topics the authors may wishto review prior to finalization for NRC staff evaluation.

1. Executive Summary / Section 1, Introduction

The Executive Summary on page i, or a third paragraph in Section 1 on page 1, should beedited to include statements.that users should review the reference section for additionalinformation related to NRC regulatory requirements and guidance, that the template describesthe elements of the PCP at the functional level consistent with 10 CFR 52.79, and that if theseprograms are implemented as described, they do not require implementation of inspections,tests, analyses and acceptance criteria in the COL application.

Enclosure

B-6

Combination Mailing List:cc: (page 1)

Mr. Laurence ParmeManager, GT-MHR Safety & LicensingGeneral Atomics CompanyP.O. Box 85608San Diego, CA 92186-5608

Mr. David Lochbaum, Nuclear Safety EngineerUnion of Concerned Scientists1707 H Street, NW, Suite 600Washington, DC 20006-3919

Mr. Paul GunterNuclear Information & Resource Service1424 16th Street, NW, Suite 404Washington, DC 20036

Mr. James RiccioG reenpeace702 H Street, NW, Suite 300Washington, DC 20001

Mr. Adrian HeymerNuclear Energy InstituteSuite 4001776 I Street, NWWashington, DC 20006-3708

Mr. George Alan ZinkeProject ManagerNuclear Business DevelopmentEntergy NuclearM-ECH-6831340 Echelon ParkwayJackson, MS 39213

Ms. Marilyn KrayVice President, Special ProjectsExelon Generation200 Exelon Way, KSA3-EKennett Square, PA 19348

Mr. Charles BrinkmanWestinghouse Electric Co.Washington Operations12300 Twinbrook Pkwy., Suite 330Rockville, MD 20852

Mr. Joseph D. HegnerLead Engineer - LicensingDominion GenerationEarly Site Permitting Project5000 Dominion BoulevardGlen Allen, VA 23060

Mr. Edward L. QuinnLongenecker and AssociatesUtility Operations Division23292 Pompeii DriveDana Point, CA 92629

Mr. Paul LeventhalNuclear Control Institute1000 Connecticut Avenue NWSuite 410Washington, DC 20036

Mr. Jay M. GutierrezMorgan, Lewis & Bockius, LLP1111 Pennsylvania Avenue, NWWashington, DC 20004

Mr. W. Edward CumminsAP600 and AP1000 ProjectsWestinghouse Electric CompanyP.O. Box 355Pittsburgh, PA 15230-0355

Mr. Gary Wright, ManagerOffice of Nuclear Facility SafetyIllinois Department of Nuclear Safety1035 Outer Park DriveSpringfield, IL 62704

B-7

Combination Mailing List:cc: (page 2)

Mr. Brendan HoffmanResearch Associate on Nuclear EnergyPublic Citizens Critical Mass Energy andEnvironmental Program215 Pennsylvania Avenue, SEWashington, DC 20003

Mr. Lionel BattyNuclear Business TeamGraftech12300 Snow RoadParma, OH 44130

Mr. Ian M. GrantCanadian Nuclear Safety Commission280 Slater Street, Station BP.O. Box 1046Ottawa, OntarioK1 P 5S9

Mr. Glenn H. ArchinoffAECL Technologies481 North Frederick AvenueSuite 405Gaithersburg, MD 20877

Mr. Ed Wallace, General ManagerProjectsPBMR Pty LTDPO Box 9396Centurion 0046Republic of South Africa

Mr. Dobie McArthurDirector, Washington OperationsGeneral Atomics1899 Pennsylvania Avenue, NW, Suite 300Washington, DC 20006

Carlos SiscoSenior ParalegalWinston & Strawn LLP1700 K Street NWWashington, DC. 20006

Ms. Vanessa E. Quinn, ChiefRadiological EmergencyPreparedness Branch

Nuclear and Chemical Preparednessand Protection Division

Department of Homeland Security1800 South Bell Street, Room 837Crystal City-Arlington, VA 22202

Mr. Ron Simard6170 Masters Club Drive -Suwanee, GA 30024

Ms. Sandra SloanAreva NP, Inc.3315 Old Forest RoadP.O. Box 10935Lynchburg, VA 24506-0935

Ms. Anne W. CottinghamAssistant General-CounselNuclear Energy Institute1776 I Street, NW, Suite 400Washington, DC 20006

Mr. David RepkaWinston & Strawn LLP .1700 K Street, NW •Washington, DC 20006-3817

Mr. Robert E. SweeheyIBEX ESI4641 Montgomery AvenueSuite 350Bethesda, MD 20814

Mr. Eugene S. GrecheckVice PresidentNuclear Support ServicesDominion Energy, Inc5000 Dominion Blvd.Glen Allen, VA 23060

B-8