neh arr pps 11aug09 lcls neh hutch protection system e. michael saleski; qc manager michael g....

10
NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

Upload: julian-hawkins

Post on 30-Dec-2015

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

LCLS NEH Hutch Protection System

E. Michael Saleski; QC Manager

Michael G. Harms, Patrick Bong, James Murphy, Alan Hill;

Engineers

Page 2: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

Hutch Protection Systems (HPS)Utilizes existing PLC system architecture, with some differences.Generally follow SSRL user-interface model

Two Access States: ‘Permitted’ and ‘No Access/Search Set’Experimenters can set access at will and perform their own searchesStoppers controlled from PPS Hutch Users Panel near each Hutch entrance.PPS Hutch Users Panel has one door-release key which may be removed from the panel when stoppers are confirmed ‘in’SSRL Personnel Hutch door design is utilizedRoll-up Equipment Door is interlocked; locked administratively.There is one ‘search preset key’ per hutch, given only to personnel with adequate trainingEach Hutch has an Online/Offline Keyswitch that prevents completion of the search and removal of stoppers

Page 3: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

Flowchart Illustrating X-Ray Beam Steering Controls, Commissioning Config

Photons from Undulator

M1SMirror

M3/4SMirror

IN

OUT

M3S

M4S Beam toSXR inHutch 2

Beam toAMO inHutch 1

XPP OUT

Beam toXPP inHutch 3

S1

S2

SH1 SH2

FEE PPS Enclosure

Hutch 3Enclosure

Hutch 2Enclosure

Hutch 1Enclosure

S0

Electron Dump PPS Enclosure

Page 4: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

‘SH1’ST1, ST2

‘S1’ST1, ST2

‘S2'ST1, ST2

Hutch 2Hutch 1

Hutch 3AMO

SXR

XPP

EO EO

EOEO

EOEO

EOEO

EO EO

PrPr

Pr Pr

PrPr

EOEOEO

PPS Stopper

EO

Pr

Emergency Off Button

Search Preset

Search Reset/Door Key

BSOIC

Annunciator

Equipment Access Doors

Pr Pr

Page 5: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

Hutch 1 Detailed Floor Plan

EO

EO

EOEO Pr3Pr4

HUP

RA

D

Pr2Pr1

SH1S2S1

EO

Pr#

HUP

RAD

Emergency Off Button

Search Preset (number indicated)

Yellow/Magenta Lights

Radiation Warning light, strobe, and Sonalert

Hutch Users Panel

KEY

BSOIC

HPS Stoppers

Page 6: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

Hutch Users Panel

LED Indicator

Push Button

Key Switch

Not Used(future expansion)

KEY[a]

[b]

[c] [d] [e]

[f][g]

[h]

[i][j]

[k]

[l][m][n]

[n] Reference

Page 7: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

Safety Systems QA PlanNew project QA approach

Bench and pre-IAT field test of system softwareNEH Software Bench Test (CD-SS-PPS-06-12-04)

NEH Hutch Software Field Test (CD-SS-PPS-06-12-19)

Acceptance tests performed for assemblies and chassis’s (such at stoppers)

HPS Stopper Acceptance Test (CD-SS-PPS-06-12-03)

Cold and energized checkout of installed hardwareHutch 1 PPS Hardware Checkout (CD-SS-PPS-06-12-16)

NEH Hutch Software Field Test (CD-SS-PPS-06-12-19)

Formal IAT reviews with stakeholdersHutch 1 IAT (CD-SS-PPS-06-12-13)

Page 8: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

Established SSS Design Review Process

Scope Defined

Memo to Engineering Group Leader initiating

change request

Proposal Accepted

Start

Assign EngineerECO Initiated

Formal Requirements

Produced

Engineer/Design Work

Weekly Peer-Review ‘as needed,’

including Risk Assessment

Ready for Formal

Review?

Yes

NO

Conduct Formal Review

Approve

Action Item Management

System

Implement Action Items

Action Item Close-out Memo Issued

RSWCF (and WAF if applicable)

Work is Performed

Assessment of work performed during weekly meetings

Yes

NO

NO

Drop Request

Notification to ADSO/RSO of

job, risk assessment,

and review plan

Yes

Evaluation by Controls

Department Management

RSO/RSC Review

Strengths:Emphasis on review and development process and documentation

Collects development and review docs for auditability

Page 9: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

PPS Review Status for NEH PPSMajor Review to Date

LCLS SCR: May 31st 2007 [Bong, Stefan, Horton, Hastings]

LCLS PDR: Feb 29th 2008 [Lessard, Tompkins, Schmerge, Anthony]

LCLS FDR: Oct 22nd 2008 [Anthony, Mueller(LBNL), Lessard]

RSC: Oct 31st 2008LCLS FDR2: Apr 22nd 2009 [Perry Anthony, Zoe Van Hoover, Luc Lessard, Paul Miller, Robert Mueller, Mike Woods ]

Safety Systems Section IAT Review: July 2009 [Zoe Van Hoover, Mike Horton, Mike Stanek, James Murphy, Alan Hill, Michael Harms]

RSC: Aug 4th 2009

Page 10: NEH ARR PPS 11AUG09 LCLS NEH Hutch Protection System E. Michael Saleski; QC Manager Michael G. Harms, Patrick Bong, James Murphy, Alan Hill; Engineers

NEH ARR PPS

11AUG09

NEH HPS ReadinessHutch 1 HPS:

Is fully commissioned, Initial Acceptance Test (IAT) executed on 06AUG09.

Mechanical sliding door improvements needed (all hutches)

Hutch 2 HPS:is nearly ready for Software Field Test and IAT Validation (then IAT execution)

Hutch 3 HPS:Has some outstanding field hardware installationWill be ready for Software Field Test, etc., in a couple of weeks.Ready for IAT execution by end of this month.