Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
AIRPORTS COMPANY SOUTH AFRICA SOC LIMITED
I
PROJECT NUMBER: GRJ8/2017
I
REFURBISHMENT OF MAINTENANCE STORES AND OFFICES AT GEORGE AIRPORT
II
NEC 3: ENGINEERING AND CONSTRUCTION CONTRACT (ECC)
Between
AIRPORTS COMPANY SOUTH AFRICA SOC LIMITED Applicable at George (Registration Number: 1993/004149/30)
and
(Registration Number: ___________________)
for
Refurbishment of Maintenance Stores and Offices at George Airport
Contents:
No of pages
Part C1 Agreements & Contract Data [●]
Part C2 Pricing Data [●]
Part C3 Scope of Works [●]
Part C4 Site Information [●]
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 2 of 52
Part C1: Agreements and Contract Data
C1.1: Form of Offer and Acceptance
OFFER
The Employer, identified in the Acceptance signature block, has solicited offers to enter into a contract for the procurement of a Contractor for the Refurbishment of the Maintenance Stores and Offices at George Airport.
The tenderer, identified in the Offer signature block, has examined the documents listed in the Tender Data and addenda thereto as listed in the Returnable Schedules, and by submitting this Offer has accepted the Conditions of Tender.
By the representative of the tenderer, deemed to be duly authorised, signing this part of this Form of Offer and Acceptance the tenderer offers to perform all of the obligations and liabilities of the Contractor under the contract including compliance with all its terms and conditions according to their true intent and meaning for an amount to be determined in accordance with the conditions of contract identified in the Contract Data.
THE OFFERED TOTAL OF THE PRICES INCLUSIVE OF VAT IS: (in words) ………………………………………………………………………………….................................... Rands; (in figures) R………………………………………….
THE OFFERED PRICES ARE AS STATED IN THE PRICING SCHEDULE
This Offer may be accepted by the Employer by signing the Acceptance part of this Form of Offer and Acceptance and returning one copy of this document including the Schedule of Deviations (if any) to the tenderer before the end of the period of validity stated in the Tender Data, or other period as agreed, whereupon the tenderer becomes the party named as the Contractor in the conditions of contract identified in the Contract Data.
Signature(s)
Name(s)
Capacity
For the Bidder:
Name & signature of witness
(Insert name and address of organisation)
Date
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 3 of 52
ACCEPTANCE
By signing this part of this Form of Offer and Acceptance, the Employer identified below accepts the tenderer’s Offer. In consideration, thereof, the Employer shall pay the Contractor the amount due in accordance with the conditions of contract identified in the Contract Data. Acceptance of the tenderer’s Offer shall form an agreement between the Employer and the tenderer upon the terms and conditions contained in this agreement and in the contract, that is the subject of this agreement.
The terms of the contract, are contained in:
Part C1 Agreements and Contract Data, (which includes this Form of Offer and Acceptance) Part C2 Pricing Data Part C3 Scope of Work: Works Information Part C4 Site Information
and drawings and documents (or parts thereof), which may be incorporated by reference into the above listed Parts.
Deviations from and amendments to the documents listed in the Tender Data and any addenda thereto listed in the Returnable Schedules as well as any changes to the terms of the Offer agreed by the tenderer and the Employer during this process of offer and acceptance, are contained in the Schedule of Deviations attached to and forming part of this Form of Offer and Acceptance. No amendments to or deviations from said documents are valid unless contained in this Schedule.
The tenderer shall within two weeks of receiving a completed copy of this agreement, including the Schedule of Deviations (if any), contact the Employer’s agent (whose details are given in the Contract Data) to arrange the delivery of any securities, bonds, guarantees, proof of insurance and any other documentation to be provided in terms of the conditions of contract identified in the Contract Data. Failure to fulfil any of these obligations in accordance with those terms shall constitute a repudiation of this agreement.
Notwithstanding anything contained herein, this agreement comes into effect on the date when the tenderer receives one fully completed original copy of this document, including the Schedule of Deviations (if any). Unless the tenderer (now Contractor) within five working days of the date of such receipt notifies the Employer in writing of any reason why he cannot accept the contents of this agreement, this agreement shall constitute a binding contract between the Parties.
Signature(s)
Name(s)
Capacity
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 4 of 52
for the Employer
Name & signature of witness
(Insert name and address of organisation)
Date
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 5 of 52
Schedule of Deviations 1 Subject . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2 Subject . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3 Subject . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Details . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
By the duly authorised representatives signing this agreement, the Employer and the Tenderer agree to and accept the foregoing schedule of deviations as the only deviations from and amendments to the documents listed in the Tender Data and addenda thereto as listed in the returnable schedules, as well as any confirmation, clarification or changes to the terms of the offer agreed by the Tenderer and the Employer during this process of offer and acceptance.
It is expressly agreed that no other matter whether in writing, oral communication or implied during the period between the issue of the tender documents and the receipt by the tenderer of a completed signed copy of this Agreement shall have any meaning or effect in the contract between the parties arising from this agreement.
For the Employer For the Bidder
Signature (s)
Name (s)
Capacity
Name and Address
Airports Company South Africa SOC Limited First Floor, Terminal Building, George Airport
Name & Signature of witness
(Insert name and address of organisation)
(Insert name and address of organisation)
Date
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 6 of 52
Part C1.2a Contract Data
Part one – Data provided by the Employer
The Conditions of contract are selected from the NEC3 Engineering and Construction Contract, April 2013. Each item of data given below is cross-referenced to the NEC3 Engineering Construction Contract which requires it.
Clause Statement Data
1 General
The conditions of contract are the
core clauses and the clauses for
Main Option
Main Option
Dispute resolution Option
B: Priced contract with Bill of Quantities
W1: Dispute resolution procedure
Secondary Options (incorporating
amendments)
X2: Changes in the law
X7: Delay damages
X13: Performance Bond
X16: Retention
X18: Limitation of liability
Z: Additional conditions of contract
of the NEC3 Engineering and Construction Contract, April
2013
10.1
The Employer is (Name)
Airports Company South Africa SOC Limited,
Applicable at George Airport
Address
Telephone
Fax
Airports Company South Africa SOC Limited
George Airport
Old Mossel Bay Road,
George
6530
044 876 9310
044 876 9027
10.1
The Project Manager is
Mr Marclen Stallenberg
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 7 of 52
Address
Telephone
E-mail address
Old Mossel Bay Road
George
6530
044 876 9310
10.1 The Supervisor is The role of the supervisor is combined with that of the Project
Manager
Address
Telephone
Fax
Not Applicable
11.2
The works are
Refurbishment of the Maintenance Stores and Offices at
George Airport
11.2
The following matters will be
included in the Risk Register
• Availability of As Built information
• Access to Site
• Site Constraints and Constructability
• Phasing of Works
• The Structural adequacy of the Maintenance Store
• The structural Adequacy of the Mezzanine Floor
11.2
The Works Information is in
Part C3 ‘Scope of Works’ section of this contract
11.2
The Site Information is in
Part C4 ‘Works Information’ section of this contract
11.2
The boundary of the site is
The confines of the Maintenance Store Site as indicated on
the Site Plan
12.2
The law of the contract is the law
of
the Republic of South Africa
13.1
The language of this contract is
English
13.3
The period of reply is
Seven (7) days
3 Time
31.2 The starting date is TBC after tender award
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 8 of 52
11.2 The completion date is TBC after tender award
30.1 The access date is TBC after tender award
31.1 The Contractor submits a first
(preliminary) programme with the
tender by the tender closing date
By the defined tender submission closure date
32.2 The Contractor submits revised
programmes at intervals no
longer than
Two (2) weeks
35.1 The Employer is not willing to
take over the works before the
completion date
The Employer and Others will have access to the works
during construction or prior to completion. Such access by
the Employer and Others shall not relieve the Contractor from
liability for the completion of the works in accordance with the
Works Information and in terms of this contract.
4 Testing and Defects
42.2 The defects date is Twelve (12) months after Completion of the whole of the
works
43.2 The defects correction period is Two (2) weeks
5 Payment
50.1 The assessment interval is Four weeks
50.1 The currency of this contract is
the
South African Rand
51.2 The period within which payment
is made is
Four (4) weeks
51.4 The interest rate is The prime lending rate of the Nedbank Bank. as determined
from time to time
6 Compensation events
60.1 The weather measurements to be
recorded for each calendar month
are
the cumulative rainfall (mm)
the number of days with rainfall more than 10 mm
the number of days with minimum air temperature less than 0
degrees Celsius
60.1 The place where weather is to be
recorded (on the Site) is
At the Construction Site Office and the records to be kept on
site in a file clearly marked for this purpose
60.1 Assumed values for the ten-year
return weather data for each
weather measurement for each
calendar month are as set out in
the Scope of Works
7 Title No data required for this section of the conditions of contract
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 9 of 52
8 Risks and Insurance
84.1 The Employer provides these
insurances
Refer to the Insurance Clauses which is attached at the end
of the Contract Data
84.2 The Contractor provides the
insurance stated in
The Insurance Clauses which is attached at the end of the
Contract Data. The insurances are in the joint names of the
Parties and provide cover for events which are at the
Contractor’s risk from the starting date until the Defects
Certificate or a termination certificate has been issued.
The minimum limit of indemnity
for insurance in respect of death
of or bodily injury to employees of
the Contractor arising out of and
in the course of their employment
in connection with this contract for
any one event is:
As prescribed by the Compensation for Occupational Injuries
and Diseases Act No. 130 of 1993
9 Termination No data required for this section of the conditions of contract
10 Data for Main Options
B Priced contract with Bill of
Quantities
Bills of Quantities are included in Section C2
11 Data for Option W1
W1.1 The Adjudicator is The person appointed jointly by the parties from the list of
adjudicators contained below
W1.2 The Adjudicator nominating body
is
The current Chairman of Johannesburg Advocate’s Bar
Council
W1.4 The tribunal is Arbitration
W1.4 If the tribunal is arbitration, the
arbitration procedure is
The arbitration procedure is set out in The Rules for the
Conduct of Arbitrations 2013 Edition, 7th Edition, published by
The Association of Arbitrators, (Southern Africa)
W1.4 The place where arbitration is to
be held is
Johannesburg, South Africa.
W1.4 The person or organisation who
will choose an arbitrator
The Arbitrator is the person selected by the Parties as and
when a dispute arises in terms of the relevant Z Clause, from
the Panel of Arbitrators provided under the relevant Z clause
if the arbitration procedure does not state who selects an
arbitrator. The Arbitrator nominating body is the Chairman of
the Johannesburg Advocates Bar Council.
12 Data for Secondary Option
Clauses
X7 Delay Damages
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 10 of 52
Delay damages of the works are Amount per day is 0.5%, to the maximum of 10% of the
Contract value
X13 Performance bond
X13.1 The amount of the performance
bond is
10% of the contract value. Pro-forma draft of a performance
bond to be used is attached to this contract.
X16 Retention
X16.1 The retention percentage is 5% of the Contract value.
X18 Limitation of Liability
X18.1 The Contractor’s liability to the
Employer for indirect or
consequential loss is limited to
Nil - Neither Party is liable to the other for any consequential
or indirect loss, including but not limited to loss of profit, loss
of income or loss of revenue
X18.2 For any one event, the
Contractor’s liability to the
Employer for loss of or damage to
the Employer’s property is limited
to
The total of the Prices
X18.3 The Contractor’s total liability to
the
Employer for defects due to his
design
which are not listed on the
Defects Certificate is limited to
The total of the Prices
X18.4 The Contractor’s total liability to
the Employer for all matters
arising under or in connection
with this contract, other than
excluded matters, is limited to
The Contractor’s total direct liability to the Employer for all
matters arising under or in connection with this contract, other
than the excluded matters, is limited to the total of the Prices
and applies in contract, tort or delict and otherwise to the
extent allowed under the law of the contract.
The e excluded matters are amounts payable by the
Contractor as stated in this contract for
- Loss of or damage to the Employer’s property,
- Delay damages,
- Defects liability,
- Insurance liability to the extent of the Contractor’s risks
- loss of or damage to property (other than the works, Plant
and Materials),
- death of or injury to a person;
- damage to third party property; and
- infringement of an intellectual property right
Z The Additional conditions of
contract are
Z1 – Z20
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 11 of 52
Amendments to the Core Clauses
Z1 Interpretation of the law
Z1.1 Add to core clause 12.3:
Any extension, concession, waiver or relaxation of any action stated in this contract by the Parties,
the Project Manager, the Supervisor, or the Adjudicator does not constitute a waiver of rights, and
does not give rise to an estoppel unless the Parties agree otherwise and confirm such agreement
in writing.
Z2 Providing the Works:
Z2.1 Delete core clause 20.1 and replace with the following:
The Contractor provides the works in accordance with the Works Information and warrants that
the results of the Works, when complete, shall be fit for their intended purpose
Z3 Other responsibilities:
Z3.1
Add the following at the end of core clause 27:
The Contractor shall have satisfied himself, prior to the Contract Date, as to the completeness,
sufficiency and accuracy of all information and drawings provided to him as at the Contract Date
Z3.2 The Contractor shall be responsible for the correct setting out of the Works in accordance with the
original points, lines and levels stated in the Works Information or notified by the Project Manager,
Supervisor or the Employer. Any errors in the positioning of the Works shall be rectified by the
Contractor at the Contractor’s own costs.
Z4 Extending the defects date:
Z4.1
Add the following as a new core clause 46:
If the Employer cannot use the works due to a Defect, which arises after Completion and before
the defects date, the defects date is delayed by a period equal to that during which the Employer,
due to a Defect, is unable to use the works
Z4.2 If part of the works is replaced due to a Defect arising after Completion and before the defects
date, the defects date for the part of the works which is replaced is delayed by a period equal to
that between Completion and the date by when the part has been replaced
Z4.3 The Project Manager notifies the Contractor of the change to a defect date when the delay occurs.
The period between Completion and an extended defects date does not exceed twice the period
between Completion and the defects date stated in the Contract Data
Z5 Termination
Z5.1 Add the following to core clause 91.1, at the second main bullet, fifth sub-bullet point, after
the words “assets or”: “business rescue proceedings are initiated or steps are taken to initiate
business recue proceedings”.
Amendment to the Secondary Option Clauses
Z6 Performance Bond
Z6.1 Amend the first sentence of clause X13.1 to read as follows:
The Contractor gives the Employer an unconditional, on-demand performance bond, provided by
a bank which the Project Manager and the Employer have accepted, for the amount stated in the
Contract Data and in the form set out in C 1.3 of this Contract Data.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 12 of 52
Z6.2 Add the following new clause as Option X13.2:
The Contractor ensures that the performance bond is valid and enforceable until the end of the
contract period. If the terms of the performance bond specify its expiry date and the end of the
contract period does not coincide with such expiry date, four weeks prior to the said expiry date,
the Contractor extends the validity of the performance bond until the end of the contract period. If
the Contractor fails to so extend the validity of the performance bond, the Employer may claim the
full amount of the performance bond and retain the proceeds as cash security
Z7 Limitation of liability:
Z7.1
Insert the following new clause as Option X18.6:
The Employer's liability to the Contractor for the Contractor's indirect or consequential loss is
limited to R0.00
Z7.2 Notwithstanding any other clause in this contract, any proceeds received from any insurances or
any proceeds which would have been received from any insurances but for the conduct of the
Contractor shall be excluded from the calculation of the limitations of liability listed in the contract
Additional Z Clauses
Z8 Cession, delegation and assignment
Z8.1 The Contractor shall not cede, delegate or assign any of its rights or obligations to any person
without the written consent of the Employer, which consent shall not be unreasonably withheld.
This clause shall be binding on the liquidator/business rescue practitioner /trustee (whether
provisional or not) of the Contractor
Z8.2 The Employer maycede and delegate its rights and obligations under this contract to any person
or entity
Z9 Joint and several liability
Z9.1 If the Contractor constitutes a joint venture, consortium or other unincorporated grouping of two or
more persons, these persons are deemed to be jointly and severally liable to the Employer for the
performance of the Contract.
Z9.2 The Contractor shall, within 1 week of the Contract Date, notify the Project Manager and the
Employer of the key person who has the authority to bind the Contractor on their behalf.
Z9.3 The Contractor does not materially alter the composition of the joint venture, consortium or other
unincorporated grouping of two or more persons without prior written consent of the Employer.
Z10 Ethics
Z10.1 The Contractor undertakes:
Z10.1.1 not to give any offer, payment, consideration, or benefit of any kind, which constitutes or could be
construed as an illegal or corrupt practice, either directly or indirectly, as an inducement or reward
for the award or in execution of this contract;
Z10.1.2 to comply with all laws, regulations or policies relating to the prevention and combating of bribery,
corruption and money laundering to which it or the Employer is subject, including but not limited to
the Prevention and Combating of Corrupt Activities Act, 12 of 2004.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 13 of 52
Z10.2 The Contractor’s breach of this clause constitutes grounds for terminating the Contractor’s
obligation to Provide the Works or taking any other action as appropriate against the Contractor
(including civil or criminal action). However, lawful inducements and rewards shall not constitute
grounds for termination.
Z10.3 If the Contractor is found guilty by a competent court, administrative or regulatory body of
participating in illegal or corrupt practices, including but not limited to the making of offers (directly
or indirectly), payments, gifts, gratuity, commission or benefits of any kind, which are in any way
whatsoever in connection with the contract with the Employer, the Employer shall be entitled to
terminate the contract in accordance with the procedures stated in core clause 92.2. the amount
due on termination is A1.
Z11 Confidentiality
Z11.1 All information obtained in terms of this contract or arising from the implementation of this contract
shall be treated as confidential by the Contractor and shall not be used or divulged or published to
any person not being a party to this contract, without the prior written consent of the Project
Manager or the Employer, which consent shall not be unreasonably withheld.
Z11.2 If the Contractor is uncertain about whether any such information is confidential, it is to be
regarded as such until otherwise notified by the Project Manager.
Z11.3 This undertaking shall not apply to –
Z11.3.1 Information disclosed to the employees of the Contractor for the purposes of the implementation
of this agreement. The Contractor undertakes to procure that its employees are aware of the
confidential nature of the information so disclosed and that they comply with the provisions of this
clause;
Z11.3.2 Information which the Contractor is required by law to disclose, provided that the Contractor
notifies the Employer prior to disclosure so as to enable the Employer to take the appropriate
action to protect such information. The Contractor may disclose such information only to the
extent required by law and shall use reasonable efforts to obtain assurances that confidential
treatment will be afforded to the information so disclosed;
Z11.3.3 Information which at the time of disclosure or thereafter, without default on the part of the Contractor, enters the public domain or to information which was already in the possession of the Contractor at the time of disclosure (evidenced by written records in existence at that time);
Z11.4 The taking of images (whether photographs, video footage or otherwise) of the works or any
portion thereof, in the course of Providing the Works and after Completion, requires the prior
written consent of the Project Manager. All rights in and to all such images vests exclusively in
the Employer
Z11.5 The Contractor ensures that all his Subcontractors abide by the undertakings in this clause.
Z12 Employer’s Step-in rights
Z12.1 If the Contractor defaults by failing to comply with his obligations and fails to remedy such default
within 2 weeks of the notification of the default by the Project Manager, the Employer, without
prejudice to his other rights, powers and remedies under the contract, may remedy the default
either himself or procure a third party (including any subcontractor or supplier of the Contractor) to
do so on his behalf. The reasonable costs of such remedial works shall be borne by the
Contractor
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 14 of 52
Z12.2 The Contractor co-operates with the Employer and facilitates and permits the use of all required
information, materials and other matter (including but not limited to documents and all other
drawings, CAD materials, data, software, models, plans, designs, programs, diagrams,
evaluations, materials, specifications, schedules, reports, calculations, manuals or other
documents or recorded information (electronic or otherwise) which have been or are at any time
prepared by or on behalf of the Contractor under the contract or otherwise for and/or in connection
with the works) and generally does all things required by the Project Manager to achieve this end.
Z13 Liens and Encumbrances
Z13.1 The Contractor keeps the Equipment used to Provide the Services free of all liens and other
encumbrances at all times. The Contractor, vis-a-vis the Employer, waives all and any liens which
he may from time to time have, or become entitled to over such Equipment and any part thereof
and procures that his Subcontractors similarly, vis-a-vis the Employer, waive all liens they may
have or become entitled to over such Equipment from time to time
Z14 Intellectual Property
Z14.1 Intellectual Property (“IP”) rights means all rights in and to any patent, design, copyright, trade
mark, trade name, trade secret or other intellectual or industrial property right relating to the
Works.
Z14.2 IP rights remain vested in the originator and shall not be used for any reason whatsoever other
than carrying out the works.
Z14.3 The Contractor gives the Employer an irrevocable, transferrable, non-exclusive, royalty free
licence to use and copy all IP related to the works for the purposes of constructing, repairing,
demolishing, operating and maintaining the works
Z14.4 The written approval of the Contractor is to be obtained before the Contractor's IP made available
to any third party which approval will not be unreasonably withheld or delayed. Prior to making any
Contractor's IP available to any third party the Employer shall obtain a written confidentiality
undertaking from any such third party on terms no less onerous than the terms the Employer
would use to protect its IP
Z14.5 The Contractor shall indemnify and hold the Employer harmless against and from any claim
alleging an infringement of IP rights (“the claim”), which arises out of or in relation to:
Z14.5.1 the Contractor’s design, manufacture, construction or execution of the Works
Z14.5.2 the use of the Contractor’s Equipment, or
Z14.5.3 the proper use of the Works.
Z14.6 The Employer shall, at the request and cost of the Contractor, assist in contesting the claim and
the Contractor may (at its cost) conduct negotiations for the settlement of the claim, and any
litigation or arbitration which may arise from it.
Z16 Dispute resolution:
Z16.1 Appointment of the
Adjudicator
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 15 of 52
An Adjudicator is appointed
when a dispute arises, from
the Panel of Adjudicators
below. The referring party
nominates an Adjudicator,
which nomination is either
accepted or rejected by the
other party. In the instance of a
rejection of the nominated
Adjudicator, the referring Party
refers the appointment
deadlock to the Chairman of
the Johannesburg Bar Council,
who appoints an Adjudicator
listed in the Panel of
Adjudicators below
The Parties appoint the
Adjudicator under the NEC3
Adjudicator’s Contract, April
2013
Panel of Adjudicators
Name Location Contact details
(phone & e mail)
Adv. Ghandi Badela Gauteng +27 11 282 3700
Mr. Errol Tate Pr.
Eng.
Durban +27 11 262 4001
Adv. Saleem Ebrahim Gauteng +27 11 535-1800
Mr. Sebe Msutwana
Pr. Eng.
Gauteng +27 11 442 8555
Mr. Sam Amod Gauteng [email protected]
Adv. Sias Ryneke
SC
Gauteng 083 653 2281
a
Mr. Emeka Ogbugo
(Quantity Surveyor)
Pretoria +27 12 349 2027
Z16.2 Appointment of the
Arbitrator
An Arbitrator is appointed
when a dispute arises from the
Panel of Arbitrators below. The
referring party nominates an
Arbitrator; which nomination is
either accepted or rejected by
the other party. In the instance
of a rejection of the nominated
Arbitrator, the referring Party
refers the appointment
deadlock to the Chairman of
the Johannesburg Bar Council,
who appoints an Arbitrator
listed in the Panel of
Arbitrators below
Panel of Arbitrators
Name Location Contact details
(phone & e mail)
Adv. Ghandi Badela Gauteng +27 11 282 3700
Mr. Errol Tate Pr.
Eng.
Durban +27 11 262 4001
Adv. Saleem Ebrahim Gauteng +27 11 535-1800
Mr. Sebe Msutwana
Pr. Eng.
Gauteng +27 11 442 8555
Mr. Sam Amod Gauteng [email protected]
Adv. Sias Ryneke
SC
Gauteng 083 653 2281
a
Mr. Emeka Ogbugo
(Quantity Surveyor)
Pretoria +27 12 349 2027
Z17 Notification of a compensation event
Z17.1 Delete “eight weeks” in clause 61.3 and replace with “four weeks”. Delete the words “unless the
event arises from the Project Manager or the Supervisor giving an instruction, issuing a certificate,
changing an earlier decision or correcting an assumption.
Z18 BBBEE Certificate
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 16 of 52
Z18.1 The Contractor shall be expected to annually present a compliant BEE Certificate. Failure to do
adhere to these requirements shall be considered a material breach of the conditions of this
Contract, the sanction for which may be a cancellation of this Contract.
Z19 Communication
Z19.1 Add a new Core Clause 14.5 and 14.6 to read as follows:
The Project Manager requires the written consent of the Employer if an action will result in a
change to the design, scope, and Works information that is 5% or more
Z19.2 The Project Manager requires the written consent of the Employer if an action will result in the
Completion Date being extended by more than 30 days.
Z20 Delegation
As stipulated by Section 37(2) of the Occupational Health and Safety Act No. 85 of 1993 as
amended the Contractor agrees to the following:
Z20.1 As part of this contract the Contractor acknowledge that it (mandatory) is an employer in its own
right with duties as prescribed in the Occupational Health and Safety Act No 85 of 1993 as
amended and agree to ensure that all work being performed, or Equipment, Plant and Materials
being used, are in accordance with the provisions of the said Act, and in particular with regard to
the Construction Regulations
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 17 of 52
PART C1.2b CONTRACT DATA
PART TWO – DATA PROVIDED BY THE CONTRACTOR
Clause Statement Data
10.1 The Contractor is (Name):
Address:
Telephone No.
Fax No.
11.2 The working areas are Only the Site Area. See C4 ‘Site Information’
24.1 The Contractor’s Key people are: CV’s to be appended to Tender Schedule
Name: Job: Responsibility: Qualifications: Experience:
Name: Job: Responsibility: Qualifications: Experience:
Name: Job: Responsibility: Qualifications: Experience:
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 18 of 52
Name: Job: Responsibility: Qualifications: Experience:
11.2 The completion date is
11.2 The following matters will be
included in the Risk Register
• Existing Services
• Access to Site
• Delay in supply of material and/or equipment
• Progress of the works against the program
• Travelling public and ACSA stakeholders
• The Structural adequacy of the Maintenance Store
• The structural Adequacy of the Mezzanine Floor
11.2 The Works Information is in Part C3 ‘Scope of Works’ section of this contract
31.1 The programme identified in the Part C3 Scope of Works section of this contract
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 19 of 52
Part C1: Agreements and Contract Data
C1.3: Form of Guarantee
PRO FORMA FOR PERFORMANCE BOND
PERFORMANCE BOND
[TO BE REPLICATED ON BANK’S LETTERHEAD]
Brief description of contract……………………………………………………………………..
Name and address of Beneficiary.......................................................................................................
…………………………………………………….. (whom the contract defines as the Contractor).
We, the undersigned ................................................... and..................................... in our capacities as Guarantor’s...........………………. of ……………. (Registration Number: ….) (hereinafter called “the Bank”) have been informed that …………………………… hereinafter called the ‘Principal’) is your Contractor under such contract, which requires him to obtain an irrevocable, unconditional performance security.
At the request of the Principal, we …………………………………..(name of bank) hereby irrevocably undertake to pay you, the Employer, any sum or sums not exceeding in total the amount of ………………………………(the “Guaranteed Amount”) upon receipt by us of your first written demand stating that such an amount (or lesser amount) as may be claimed is due and payable to the Employer.
This guarantee constitute an irrevocable, unconditional, non-negotiable and non-transferable undertaking to pay in accordance with the above, subject to the proviso that this Letter will not be interpreted as extending the Bank’s liability to anything more than the Guaranteed Amount.
Notwithstanding anything to the contrary herein contained, the Bank’s obligation shall be construed as principal and not as accessory to the contract and shall not be delayed or discharged by the fact that a dispute exists between the Employer and the Contractor.
We undertake to pay you such Guaranteed Amount upon receipt by us, within such period of 14 days, of your first written demand stating that such an amount (or lesser amount) as may be claimed is due and payable to the Employer.
The guarantee shall be governed by and construed in accordance with the laws of the Republic of South Africa Signed at ______________________________ on ____________________20…. For: Registration Number:
Name & Position
As witnesses: 1. ______________________________ 2. ______________________________
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 20 of 52
PART C1: AGREEMENTS AND CONTRACT DATA
C1.4: OCCUPATIONAL HEALTH AND SAFETY AGREEMENT
OCCUPATIONAL HEALTH AND SAFETY AGREEMENT AGREEMENT IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH & SAFETY ACT (ACT 85 Of 1993) & CONSTRUCTION REGULATION 5.1(k) OBJECTIVES To assist Airport Company South Africa (ACSA) in order to comply with the requirements of:
1. The Occupational Health & Safety (Act 85 of 1993) and its regulations and 2. The Compensation for Occupational Injuries & Diseases Act (Act 130 of 1993) also known as the
(COID Act).
To this end an Agreement must be concluded before any contractor/ subcontracted work may commence The parties to this Agreement are:
Name of Organisation: AIRPORTS COMPANY SOUTH AFRICA GEORGE AIRPORT
Physical Address: Airport Company South Africa First Floor, Terminal Building, George Airport
Hereinafter referred to as “Client”
Name of organisation:
Physical Address
Hereinafter referred to as “the Mandatary/ Principal Contractor”
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 21 of 52
MANDATORY’S MAIN SCOPE OF WORK REFURBISHMENT OF THE MAINTENANCE STORES AND OFFICES AT GEORGE AIRPORT
GENERAL INFORMATION FORMING PART OF THIS AGREEMENT
1. The Occupational Health & Safety Act comprises of SECTION 1-50 and all unrepealed
REGULATIONS promulgated in terms of the former Machinery and Occupational Safety Act No.6 of 1983 as amended as well as other REGULATIONS which may be promulgated in terms of the Act and other relevant Acts pertaining to the job in hand.
2. “Mandatary” is defined as including as agent, a principal contractor or a contractor for work, but WITHOUT DEROGATING FROM HIS/HER STATUS IN HIS/HER RIGHT AS AN EMPLOYER or user of the plant
3. Section 37 of the Occupational Health & Safety Act potentially punishes Employers (PRINCIPAL CONTRACTOR) for unlawful acts or omissions of Mandataries (CONTRACTORS) save where a Written Agreement between the parties has been concluded containing arrangements and procedures to ensure compliance with the said Act BY THE MANDATARY.
4. All documents attached or refer to in the above Agreement form an integral part of the Agreement.
5. To perform in terms of this agreement Mandataries must be familiar and conversant with the relevant provisions of the Occupational Health & Safety Act 85 of 1993 (OHS Act) and applicable Regulations.
6. Mandatories who utilise the services of their own Mandatories (contractors) must conclude a similar Written Agreement with them.
7. Be advised that this Agreement places the onus on the Mandatary to contact the CLIENT in the event of inability to perform as per this Agreement.
8. This Agreement shall be binding for all work the Mandatary undertakes for the client. 9. All documentation according to the Safety checklist including a copy of the written Construction
Manager appointment in terms of construction regulation 8, must be submitted 7 days before work commences.
THE UNDERTAKING
The Mandatary undertakes to comply with: INSURANCE
1. The Mandatary warrants that all their employees and/or their contractor’s employees if any are covered in terms of the COID Act, which shall remain in force whilst any such employees are present on the Client’s premises. A letter is required prior commencing any work on site confirming that the Principal contractor or contractor is in good standing with the Compensation Fund or Licensed Insurer.
2. The Mandatary warrants that they are in possession of the following insurance cover, which cover shall remain in force whilst they and /or their employees are present on the Client’s premises, or which shall remain in force for that duration of their contractual relationship with the Client, whichever period is the longest. a. Public Liability Insurance Cover as required by the Subcontract Agreement. b. Any other Insurance cover that will adequately makes provision for any possible losses
and/or claims arising from their and /or their Subcontractors and/or their respective employee’s acts and/or omissions on the Client’s premises.
COMPLIANCE WITH THE OCCUPATIONAL HEALTH & SAFETY ACT 85 OF 1993
The Mandatary undertakes to ensure that they and/or their subcontractors if any and/or their respective employees will at all times comply with the following conditions:
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 22 of 52
1. All work performed by the Mandatary on the Client’s premises must be performed under the close supervision of the Mandatary’s employees who are to be trained to understand the hazards associated with any work that the Mandatary performs on the Client’s premises.
2. The Mandatary shall be assigned the responsibility in terms of Section 16(1) of the OHS Act 85 of 1993, if the Mandatary assigns any duty in terms of Section 16(2), a copy of such written assignment shall immediately be forwarded to the Client.
3. The Mandatary shall ensure that he/she familiarise himself/herself with the requirements of the OHS Act 85 of 1993 and that s/he and his/her employees and any of his subcontractors comply with the requirements.
4. The Mandatary shall ensure that a baseline risk assessment is performed by a competent person before commencement of any work in the Client’s premises. A baseline risk assessment document will include identification of hazards and risk, analysis and evaluation of the risks and hazards identified, a documented plan and safe work procedures to mitigate, reduce or control the risks identified, and a monitoring and review plan of the risks and hazards.
5. The Mandatary shall appoint competent persons who shall be trained on any Occupational Health & Safety aspect pertaining to them or to the work that is to be performed.
6. The Mandatary shall ensure that discipline regarding Occupational Health & Safety shall be strictly enforced.
7. Any personal protective equipment required shall be issued by the Mandatary to his/her employees and shall be worn at all times.
8. Written safe working practices/procedures and precautionary measures shall be made available and enforced and all employees shall be made conversant with the contents of these practises.
9. No unsafe equipment/machinery and/or articles shall be used by the Mandatary or contractor on the Client’s premises.
10. All incidents/accidents referred to in OHS Act shall be reported by the Mandatary to the Provincial Director: Department of Labour as well as to the Client.
11. No user shall be made by the Mandatary and/or their employees and or their subcontractors of any of the Client’s machinery/article/substance/plant/personal protective equipment without prior written approval.
12. The Mandatary shall ensure that work for which the issuing of permit is required shall not be performed prior to the obtaining of a duty completed approved permit.
13. The Mandatary shall ensure that no alcohol or any other intoxicating substance shall be allowed on the Client’s premises. Anyone suspected to be under the influence of alcohol or any other intoxicating substance shall not be allowed on the premises. Anyone found on the premises suspected to be under the influence of alcohol or any other intoxicating substance shall be escorted off the said premises immediately.
14. Full participation by the Mandatary shall be given to the employees of the Client if and when they inquire into Occupational Health & Safety.
FURTHER UNDERTAKING
1. Only a duly authorised representative appointed in terms of Section 16.2 of the OHS Act is eligible to sign this agreement on behalf of the Mandatary. The signing power of this representative must be designated in writing by the Chief Executive Officer of the Mandatary. A copy of this letter must be made available to the Client.
2. The Mandatary confirms that he has been informed that he must report to the Client’s management, in writing anything he/she deems to be unhealthy and /or unsafe. He has versed his employees in this regard.
3. The Mandatary warrants that he/she shall not endanger the health & safety of the Client’s employees and other persons in any way whilst performing work on the Client’s premises.
4. The Mandatary understands that no work may commence on the Client’s premises until this procedure is duly completed, signed and received by the Client.
5. Non-compliance with any of the above clauses may lead to an immediate cancellation of the contract.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 23 of 52
ACCEPTANCE BY MANDATARY In terms of section 37(2) of the Occupational Health & Safety Act 85 of 1993 and section 5.1(k) of the Construction Regulations 2014, I ………………………………… a duly authorised 16.2 Appointee acting for and on behalf of ………………………………………………. (company name) undertake to ensure that the requirements and the provision of the OHS Act 85 of 1993 and its regulations are complied with. Mandatary – WCA/ Federated Employers Mutual No………………………………. Expiry date ……………………………………………………………………………………. ________________________________________ _______ SIGNATURE ON BEHALF OF MANDATARY DATE
(Warrant his authority to sign) _________________________________________ _______________ SIGNATURE ON BEHALF OF THE CLIENT DATE AIRPORT COMPANY SOUTH AFRICA
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 24 of 52
PART C1: AGREEMENTS AND CONTRACT DATA
C1.5: ACSA INSURANCE CLAUSES
INSURANCE CLAUSES FOR CAPEX PROJECTS
The insurance clauses in this document should be extracted and attached to tender documents and to
contracts.
SECTION A: DEFINITIONS
Landside refers to:
• Areas of the airport before the security points, and
• The restricted area beyond the security points but, within the perimeter of gatehouses, passenger
terminals and cargo buildings
Airside refers to:
• The Apron / manoeuvring areas
• Area within the airside boundary/perimeter fence, excluding the internal areas of the passenger
terminals, perimeter gatehouses and cargo building.
SECTION B: INSURANCE CLAUSES
1. Insurance requirements for contracts with a value below R50million on the LANDSIDE
1.1 Contract Works
• With regards to contract works claims, the contractor/consultant is responsible for a deductible
(excess) of R250 000.
• Contractors / consultants may re-insure the deductible
1.2 Public Liability
• In the event of a claim against the contractor / consultant for 3rd party property damage the
contractor / consultant will be responsible for a deductible (excess) of R275 000
• In the event of a claim against the contractor / consultant for removal of lateral support, the
contractor / consultant will be responsible for a deductible (excess) of R500 000
• Contractors / consultants may re-insure the deductibles
1.3 Professional Indemnity
• All consultants are responsible for Professional Indemnity cover of R5million
• Contractors who have a material design element, excluding typical P & G related work, as part of
their scope, are responsible for Professional Indemnity cover of R5million
• In the event of a claim above R5million, the ACSA PI cover will kick in for the amount in excess of
R5m.
• Proof of cover in the form of a certificate of insurance should be provided to ACSA before a contract
is signed between ACSA and the contractor and/or consultant.
2. Insurance requirements for contracts below R50million on the AIRSIDE
2.1 Contract Works
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 25 of 52
• With regards to contract works claims, the contractor / consutant is responsible for a deductible
(excess) of R250 000.
• Contractors / consultants may re-insure the deductible
2.2 Public Liability
• In the event of a claim brought against the contractor / consultant for 3rd party property damage the
contractor / consultant will be responsible for a deductible (excess) of R525 000
• In the event of a claim brought against the contractor / consultant for removal of lateral support, the
contractor / consultant will be responsible for a deductible (excess) of R750 000
• In the event of a claim brought against the contractor / consultant for damage to aircraft, the
contractor / consultant will be responsible for a deductible (excess) of R750 000
• Contractors / consultants may re-insure the deductibles
2.3 Professional Indemnity
• All consultants are responsible for Professional Indemnity cover of R5million
• Contractors who have a material design element, excluding typical P & G related work, as part of
their scope, are responsible for a Professional Indemnity cover of R5million.
• In the event of a claim above R5million, the ACSA PI cover will kick in for the amount in excess of
R5million.
• Proof of cover in the form of a certificate of insurance should be provided to ACSA before a contract
is signed between ACSA and the contractor and/or consultant.
3. Insurance requirements for contracts with a value above R50 million on the LANDSIDE
• Contracts with a value of more R50 million are not automatically covered under the construction
policies. A separate quote is provided by insurers per contract.
3.1 Contract Works
With regards to contract works claims, the contractor / consultant is responsible for the following deductibles:
• All Civil Work and Earthworks – R300 000 deductible (excess)
• All other claims – R300 000 deductible (excess)
• Other property insured – R700 000 deductible (excess)
• Contractors / consultants may re-insure the deductibles
3.2 Public Liability
• In the event of a claim brought against the contractor / consultant for 3rd party property damage the
contractor / consultant will be responsible for a deductible (excess) of R275 000
• In the event of a claim brought against the contractor / consultant for removal of lateral support, the
contractor / consultant will be responsible for a deductible (excess) of R500 000
• Contractors / consultants may re-insure the deductibles
3.3 Professional Indemnity
• All consultants are responsible for Professional Indemnity cover of R10million
• Contractors who have a material design element, excluding typical P & G related work, as part of
their scope, are responsible for a Professional Indemnity cover of R10million
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C1 – Agreements and Contract Data Page 26 of 52
• In the event of a claim above R10million, the ACSA PI cover will kick in for the amount in excess of
R10m
• Proof of cover in the form of a certificate of insurance should be provided to ACSA before a contract
is signed between ACSA and the contractor and/or consultant.
4. Insurance requirements for contracts with a value above R50 million on the AIRSIDE
• Contracts with a value of more R50 million are not automatically covered under the construction
policies. A separate quote is provided by insurers per contract.
4.1 Contract Works
With regards to contract works claims, the contractor / consultant is responsible for the following deductibles:
• All Civil Work and Earthworks excluding Runways – R300 000 deductible (excess)
• Runway Rehabilitation – R300 000 deductible (excess)
• New Runway Construction – R700 000 deductible (excess)
• All other claims – R300 000 deductible (excess)
• Other property insured – R700 000 deductible (excess)
• Contractors / consultants may re-insure the deductibles
4.2 Public Liability
• In the event of a claim brought against the contractor / consultant for 3rd party property damage the
contractor / consultant will be responsible for a deductible (excess) of R1 025 000
• In the event of a claim brought against the contractor / consultant for removal of lateral support, the
contractor / consultant will be responsible for a deductible (excess) of R1 250 000
• In the event of a claim for damage to aircraft, the contractor / consultant will be responsible for a
deductible (excess) of R1 250 000
• Contractors / consultants may re-insure the deductibles
4.3 Professional Indemnity
• All consultants are responsible for Professional Indemnity cover of R10million
• Contractors who have a material design element, excluding typical P & G related work, as part of
their scope, are responsible for a Professional Indemnity cover of R10million
• In the event of a claim above R10million, the ACSA PI cover will kick in for the amount in excess of
R10m
• Proof of cover in the form of a certificate of insurance should be provided to ACSA before a contract
is signed between ACSA and the contractor and/or consultant.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C2 – Pricing Data Page 27 of 52
C2 PRICING DATA
Pages
C2.1 Pricing Instructions 1-2 C2.2 Bills of Quantities 3-19
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C2 – Pricing Data Page 28 of 52
C2.1 Pricing Instructions
1 Measurement and payment shall be in accordance with the relevant provisions of clause 8 of each of the SABS 1200
Standardised Specifications for Civil Engineering Construction referred to in the Scope of Work. The Preliminary and General items shall be measured in accordance with the provisions of SABS 1200-A, General.
2. The units of measurement described in these Bill of Quantities are metric units. Abbreviations used in these Bills of
Quantities are as follows: % = percent
h = hour ha = hectare kg = kilogram kl = kilolitre km = kilometre km-pass = kilometre-pass kPa = kilopascal kW = kilowatt
l = litre m = metre mm = millimetre m² = square metre m²-pass = square metre-pass
m³ = cubic metre m³-km = cubic metre-kilometre
MN = meganewton MN.m = meganewton-metre MPa = megapascal No. = number Prov sum = Provisional sum PC sum = Prime Cost sum R/only = Rate only sum = lump sum t = ton (1000 kg) W/day = Work day
3. For the purpose of these Bills of Quantities, the following words shall have the meanings hereby assigned to them:
Unit: The unit of measurement for each item of work as defined in the SABS 1200 or COLTO Standard Specification for Road and Bridge Works for State Authorities (1998 edition).
Quantity: The number of units of work for each item. Rate: The agreed payment per unit of measurement. Amount: The product of the quantity and the agreed rate for an item. Lump sum: An agreed amount for an item, the extent of which is described in the Bills of Quantities but the
quantity of work of which is not measured in any units. 4. Unless otherwise stated, items are measured net in accordance with the drawings, and no allowance is made for
waste.
5. It will be assumed that prices included in the bills of quantities are based on Acts, Ordinances, Regulations, By-laws, International Standards and National Standards that were published 28 days before the closing date for tenders. (Refer to www.stanza.org.za or www.iso.org for information on standards)
6. The prices and rates in the Bill of Quantities are to be fully inclusive prices for the work described under the several
items. Such prices and rates cover all costs and expenses that may be required in and for the execution of the work described in accordance with the provisions of the Scope of Work, and shall cover the cost of all general risks, liabilities, and obligations set forth or implied in the Contract Data, as well as overhead charges and profit. Reasonable prices shall be inserted as these will be used as a basis for assessment of payment for additional work that may have to be carried out.
7. Where the Scope of Work requires detailed drawings and designs or other information to be provided, all costs
associated therewith are deemed to have been provided for and included in the unit rates and sum amount tendered such items
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C2 – Pricing Data Page 29 of 52
8. A price or rate is to be entered against each item in the Bill of Quantities. An item against which no price is entered
will be considered to be covered by the other prices or rates in the Bill of Quantities.
9. The quantities set out in the Bill of Quantities are approximate and do not necessarily represent the actual amount of work to be done. The quantities of work accepted and certified for payment will be used for determining payments due and not the quantities given in the Bill of Quantities.
10. Reasonable compensation will be received where no pay item appears in the Bill of Quantities in respect of work
required in terms of the Contract and which is not covered in any other pay item.
11. The short descriptions of the items of payment given in the Bill of Quantities are only for the purposes of identifying the items. More details regarding the extent of the work entailed under each item appear in the Scope of Work.
12. Descriptions in the Bill of Quantities are abbreviated and comply generally with those in the SABS 1200
Standardised Specifications. 13. Those parts of the contract to be constructed using labour-intensive methods have been marked in the Bill of
Quantities with the letters Li in a separate column filled in against every item so designated. The works, or parts of the works so designated are to be constructed using labour-intensive methods only. The use of plant to provide such works, other than plant specifically provided for in the scope of work, is a variation to the contract. The items marked with the letters Li are not necessarily an exhaustive list of all the activities which must be done by hand, and this clause does not over-ride any of the requirements in the generic labour intensive specification in the Scope of Works.
14 Payment for items which are designated to be constructed labour-intensively (either in this schedule or in the
Scope of Works) will not be made unless they are constructed using labour-intensive methods. Any unauthorized use of plant to carry out work which was to be done labour-intensively will not be condoned and any works so constructed will not be certified for payment.
SPECIAL NOTES TO TENDERERS
• Quantities in the Bill of Quantities may change within the tendered amount during the course of the contract, due to priority changes. The total contract value will remain fixed.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C2 – Pricing Data Page 30 of 52
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 31 of 52
PART 3: SCOPE OF WORK
Document reference Title No of pages
This cover page 1
C3.1 Employer’s Works Information
C3.2 Contractor’s Works Information1
Total number of pages
.
1 Insert at award stage or delete if not applicable. Delete this note once a selection is made.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 32 of 52
TABLE OF CONTENTS
No Description Page
C3.1 EMPLOYER’S WORKS INFORMATION
1 Description of the Works 34
1.1 General 34
1.2 Drawings 34
1.3 Details of Contract 34
2 Nature of Ground and Sub-Soil Conditions 35
3 Construction Programme and Methods 36
4 Site Facilities Available 36
4.1 Water Supply, Toilet Facilities, Waste Disposal and Power Supply 37
4.2 Location of Contractor’s Camp 37
4.3 Housing for Contractor’s Employees 37
5 Site Facilities Required 37
5.1 Engineer’s Office 37
5.2 Name Boards 37
5.3 Telephone and Internet Facilities 37
5.4 Tests and Samples 37
5.5 Survey Instruments 38
6 Features Requiring Special Attention 38
6.1 Safety Regulations 38
6.2 Setting out of Work and Survey Beacons 38
6.3 “As-Built“ Drawings 38
6.4 Site Instruction Book 38
6.5 Access to buildings 39
6.6 Location and protection of underground services 39
6.7 Interruption of Existing Services 39
6.8 Traffic and safety Control Measures 39
7 Abnormal Rainfall 40
8 Local Labour and Local Sub-Contractors 40
8.1 Introduction 40
8.2 Workload 40
8.3 Local Labour 40
8.4 Work Considered to be Local Labour 40
9 Training Schemes 41
10 Occupational Health and Safety 41
10.1 General Agreement 41
10.2 Health and Safety Specifications and Plans to be Submitted at Tender Stage 41
10.3 Cost of Compliance with the OHSA Construction Regulations 42
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 33 of 52
11 Management Meetings 42
12 Quality Assurance Requirements 42
13 Engineering and Design of the Works 43
14 Construction 44
15 Plant and Materials Standards and Workmanship 47
C3.2 CONTRACTOR’S WORKS INFORMATION 48
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 34 of 52
C3.1: EMPLOYER’S WORKS INFORMATION
1. Description of the works
1.1 General
The Scope of Works is as shown on the drawings which must be read with the remainder of the Contract Documents
This Contract is primarily for the refurbishment of the maintenance stores, the refurbishment and extension of the maintenance offices, the roofing of the container storage area and the upgrading of parking areas and road access to the stores.
1.2 Drawings
The following Drawings describe the scope of the works and are included as part of the tender documentation.
Drawing Number Description
0224/01 Layout
0224/02 Admin Building : Plan and Elevations
0224/03 Warehouse : Plan and Elevations
0224/10 Typical Sewer Details
0224/20 Storm Water Details
0224/40 Typical Road Details
1.3 Details of Contract
The major items of Work included in the Contract are listed in the Bills of Quantities and Tenderers must note that all quantities provided are estimated and subject to re-measurement.
The Work to be done under this Contract includes the following:
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 35 of 52
a Site Establishment
b Setting out of Work
c Site Clearance
d Searching and exposing of Existing Underground Services
e Construction of Storm Water Pipes and Drainage Inlets
f Bulk Earthworks
g Construction of Retaining Walls
h Removal of Surplus Material and Preparation of Roadbed
i Placement of Selected Layerworks
j Construction of Roads and Parking Areas with Interlocking Block Pavers
k Construction of new Steel Mezzanine Floor in Maintenance Shed
l Upgrading of Electrical Installation in Maintenance Shed
m Refurbishment/Replacement of Roller Shutter Doors
n Construction of Lean-to Shed behind Maintenance Store
o Demolishing of Interior Walls in Office Block
p Reconstruction of Interior of Office Block including Ablution Facilities
q Addition of two new Offices to Office Block
r Addition of covered walkway for access to Office Block
s Construction of a smoking area
t Alteration and upgrading of Electrical Installation in Office Block
u Installation of new Data Cable from main airport distribution station
v Cleaning and re-instatement of Site
w Maintenance of all Building Work for a period of three months
x Maintenance of all Civil Work for a period of 12 months
2 Nature of ground and subsoil conditions
There are no rock outcrops in the immediate vicinity of the work.
The site slopes from south towards the north and has already been platformed to accommodate the existing maintenance store. Further excavation will be required to increase the size of the platform to accommodate the lean-to shed and paved areas.
Excavations are expected to be in materials that can be classified as varying from soft to intermediate. The above-mentioned only serves as a guideline and prospective Tenderers shall acquaint themselves with the nature of the conditions on site and the Employer will assume no responsibility for the conclusions reached by the Tenderer.
The nature of the subsoil will be discussed at the site meeting and expected conditions will be indicated.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 36 of 52
3 Construction Programme and Methods
It is a pre-requisite of this contract that minimal disruption of the environment is ensured during construction.
Construction methods must be of such a nature that no property or life is endangered. The Employer accepts no responsibility for any work done outside the site boundaries without the Engineer's approval. The Contractor himself is responsible for liaison and arrangements with the Engineer in connection with the finalization and approval of the construction programme.
The Contractor shall submit a programme of work to the Engineer not later than 14 (fourteen) days after the Contractor has been notified of the acceptance of his tender. This programme must take into account, and allow for possible phased completion of the work. The Engineer may instruct the Contractor to stop construction work at any stage and time, as may be dictated by financial constraints highlighted by the Employer’s Cost Control Programme. If necessary, the Engineer may instruct the Contractor to adjust his programme to suit other activities. During the course of the Contract, the Contractor shall provide the Engineer with a revised programme every 4 weeks at the monthly site meeting.
The programme shall not be in the form of a bar chart only, but shall clearly show the anticipated quantities, the production rates and value of work to be performed each month.
Failure to comply with these requirements will entitle the Engineer to use a programme based on his own assumptions for the purpose of evaluating payment certificates, claims for extension of time or additional payments.
If the programme submitted by the Contractor in terms of Clause 12 of the General Conditions of Contract, has to be revised because the Contractor is falling behind in his programme, he shall submit a revised programme of how he intends to regain lost time to ensure completion of the Works within the period defined in Contract or within a granted extension of time. A proposal to increase the tempo of work must incorporate positive steps to increase production either by more labour and plant on the site, or by using the available labour and plant in a more efficient manner.
Failure on the part of the Contractor to submit or to work according to the programme or revised programmes shall be sufficient reason for the Engineer to take steps in terms of the Contract.
The approval by the Engineer of a programme shall have no contractual significance other than that the Engineer will be satisfied if the work is carried out according to the programme. The said approval shall not limit the right of the Engineer to instruct the Contractor to vary the programme if necessary. The Contractor shall allow for the effect of normal rainfall and special non-working days in his programme.
4 Site Facilities Available
4.1
Water Supply, Toilet Facilities, Waste Disposal and Power Supply
Water for construction and drinking purposes is available on site from ACSA and the contractor shall on his own accord and expense install a connection and a water meter. The water meter will be read on a monthly basis and the Contractor will be billed for water consumed on a monthly basis at the standard municipal rate as paid by ACSA..
The Contractor will be required to provide toilet facilities for the use of his staff. Waterborne sewerage is available on site and the Contractor will of his own accord and expense install a connection to the sewerage system at a suitable position and connect the required number of toilets. He will be required to maintain the toilets in good condition at all times.
Should the Engineer or the Employer’s representative request cleaning of a toilet facility due to any reason, the Contractor shall do so within 8 hours from being instructed do to so. Should any employee of the Contactor be found guilty of using the external areas as a toilet for disposing solid human waste, the contactor will be penalized at R700.00 per head per occurrence.
Any waste other than construction rubble (stone, sand, concrete, etc.) must be removed daily from the construction site. The Contractor must provide a suitable container for the disposal of all foreign matter such as plastic, bottles, cans, cardboards, paper, wrapping or packaging materials, etc.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 37 of 52
Should the Contractor fail to adhere to these measures to control waste , the Engineer will issue a maximum of 3 written warnings in any 10 day cycle, where after the Contractor will be penalized at R500.00 per occurrence.
No extension of time due to delays resulting from obtaining and maintaining these facilities will be granted.
Electricity is available on the site for construction purposes. The Contractor shall on his own accord and expense install a suitable connection and electrical meter. The electrical meter will be read on a monthly basis and the Contractor will be billed for electricity consumed on a monthly basis at the standard municipal or Eskom rate as paid by ACSA..
4.2 Location of Contractor’s Camp
The Contractor will be allocated an area within the confines of the maintenance site for storage of some of the required materials and this area will be pointed out to the Contractor. The camp must be fenced according to the Contractor’s layout requirements for his camp, working space and areas for storage. The position of stockpile areas, which may be allocated outside the fenced area, will be subject to the Engineer’s approval. The Contractor must allow for temporary fencing under the item “Establishment of Facilities on Site” in the Schedules of Quantities. Access to the site and to the Contractor’s camp will be form the adjacent Provincial Road via an existing gate situated in the external perimeter fence. The Contractor will have the exclusive use of this gate and be responsible for the security thereof.
The Contractor is required to submit a detailed drawing to the Engineer showing the proposed positions of site offices, stores, temporary works, fixed constructional plant as well as stockpile areas and fencing for approval before commencing establishment
4.3 Housing for the Contractor's Employees
No housing is available for the Contractor's employees and the Contractor shall make his own arrangements for housing his employees or transporting them to and from the site. The Contractor is in all respects responsible for the housing and transporting of his employees and for the arrangement thereof, and no extension of time due to any delays resulting from this will be granted.
5 Site Facilities Required
Facilities such as an office, telephone, name board, survey equipment, and any relevant services required for the Engineer are described below:
5.1 Engineer’s Office
No office is required for the Engineer.
5.2 Nameboards
One nameboard conforming to the dimensions and colours as specified shall be erected at the Site. The Contractor will be permitted to erect his own and subcontractor’s nameboards elsewhere on site.
5.3 Telephone and internet facilities The Contractor must arrange for adequate telephone or cellular phone communicating to and from the site. The Contractor must have facilities for receipt of e-mail correspondence on a daily basis. All written communication during the contract period between the Engineer and Contractor will be made by e-mail. The Contractor must allow for all phone charges, rentals, call charges, data charges, etc. under the appropriate payment items in the Bills of Quantities.
5.4 Tests and Samples
A Provisional Amount has been included under General for laboratory testing which the Engineer may require for quality control. The Provisional Amount for Tests and Samples does not include for any testing and samples which are in terms of this Contract the responsibility of the Contractor.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 38 of 52
The Contractor must include sufficient time in his Programme for all testing and inspections required in terms of the Contract. The Contractor is responsible for his own detailed and continuous quality control as specified and required in terms of the Contract. The Contractor must allow for all costs connected to transporting, sampling laboratory testing, inspections, etc. as required in the appropriate and relevant items in the Schedule of Quantities.
The contractor must make his own arrangements for testing and sampling as required in terms of the Contract. The Contractor must supply the Engineer within 24 hours after completion of testing with properly authorised and documented test results. The Contractor shall also maintain on site at the site office full records of all test results.
5.5 Survey Instruments
The Contractor is responsible to supply proper and sufficient survey instruments for his setting out of the works, taking levels, checking etc. These survey instruments must be kept on site for the duration of the Contract. The Contractor shall also make available to the Engineer an automatic level and staff should he wish to check any levels set out by the Contractor.
6 Features Requiring Special Attention
6.1 Safety Regulations
Both the "Factories, Machinery and Building Work Act (Act 22 of 1941) and the "Machinery and Occupational Safety Act (Act 6 of 1983)" must be substituted by the "Occupational Health and Safety Act (Act 85 of 1993)".
The Contractor shall apply suitable proven methods for construction so that his activities will not constitute a hazard to the workmen, public or any adjacent property. All excavations shall be suitable safeguarded and barricaded especially during night time, weekends or holidays and any other day of inactivity by the Contractor. The costs for complying with these safety requirements shall be covered under the Contractors general obligations. The Contractor shall also ensure that excavations are shored or otherwise made safe.
6.2 Setting Out of Work and Survey Beacons
The Contractor must do his own setting out from pegs of which positions are shown on the drawings and/or pointed out to him by the Engineer in writing.
Other than in the case of setting out pegs, the Contractor will be liable for costs for the replacement of existing pegs by a qualified Land Surveyor appointed by the Engineer, where such pegs are removed or damaged. Where the construction operation is such due to the nature of the Works that pegs will be unavoidable disturbed, the prior agreement of the Engineer must be obtained for their destruction otherwise the Contractor will be held liable for the cost of their replacement.
Attention in this regard is drawn to Sections 35(1) and (2) of the Land Survey Act of 1927 which lays down the penalties applicable to those who are responsible for interfering with permanent survey beacons, bench marks, reference marks or trigonometric stations.
6.3 "As-built" Drawings
The Contractor must keep accurate records of any changes to the construction drawings and must present marked-up drawings to the Engineer for record purposes. Completion Certificates will not be issued unless the Engineer is satisfied with the accuracy of the Contractor’s “as-built” records.
6.4 Site Instruction Book
A triplicate book for Site Instructions shall be supplied free of charge by the Contractor and shall at all times be kept on the Site and accessible to the Engineer during normal working hours. The Site Instruction book will be used for all Contractual and Financial matters.
A Site Diary must be kept on site and be up to date on all day to day communications and discussions. Each daily record must commence on a new page and a copy of the dairy must be submitted fortnightly to the Engineer for verification and approval. Failure to submit on the required basis may result in the rejection of claims due to inadequate record keeping.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 39 of 52
6.5 Access to Buildings
The Contractor shall organise the work to cause the least possible inconvenience to the operation of the Maintenance Facilities.
6.6 Location and Protection of Existing Underground Services
Prior to commencement of construction the Contractor shall make an appointment with the Engineer to determine the position of all existing services to the satisfaction of the Contractor. The positions of all known existing services are shown on the drawings.
Existing underground services on the Site as shown on the Drawings or pointed out to the Contractor shall be exposed by hand excavation, clearly marked and their positions and levels relative to fixed reference points be recorded on a sketch to be submitted to the Engineer prior to commencing work on the Site.
The Contractor must provide proper and effective measures to ensure the protection of all existing services.
6.7 Interruption of Existing Services
All the work to be carried out in the vicinity of existing services shall be done in such a manner as to ensure that such services shall remain in operation at all times, except where arrangements have been made for the interruption of the service for the purposes of carrying out the Works under this Contract.
Existing overhead and underground services may not be indicated on the drawings. Should the Contractor find evidence of possible buried services, he shall notify the Engineer immediately thereof. The Engineer will assess the situation and instruct the Contractor as to an appropriate course of action to be taken.
The Contractor shall be responsible for checking the locations of all services and to ensure that no damage is cause by construction operations.
The Contractor, before starting any excavations, is to carefully search and probe the terrain in question for any other existing services or indications of the presence of such services. An item has been allowed for in the Bill of Quantities for hand excavation or other methods to search for existing services.
All cables and pipes shall be considered "live" unless confirmed otherwise by the relevant service authority.
The Senior Superintendent Maintenance of Telkom must be notified at least 7 days before work of any nature near or at a Telkom service may be commenced. No mechanical plant whatsoever may be used for excavation within a distance of 3 m from a Telkom service without the prior approval of Telkom's Senior Superintendent.
Electricity and water-supply interruptions to existing buildings shall be kept to a minimum. The Engineers approval shall be obtained prior to such interruptions and the Sanatorium shall be notified.
The Engineer must be notified whenever a breakage occurs and the damage must be repaired immediately.
6.8 Traffic and Safety Control Measures
The Contractor shall provide and properly maintain all barricades, warning signs, notices, lightning, fencing, etc. necessary for safety and traffic control of the Works under this Contract.
The Contractor shall be responsible for the safety of all works on the Site. The Contract must allow for all costs related to traffic and safety under the relevant payment items.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 40 of 52
7 Abnormal Rainfall
The Contractor shall keep daily rainfall records and submit them to the Engineer at every site meeting. No additional payment shall be made for the supply and installation of the rain gauge or for the keeping of the rainfall records and all costs must be included in the appropriate items.
The average rainfall for George is summarized below:
Month Average Monthly Rainfall
(mm)
Average Days per month with more than
10 mm/day Rainfall
January 43 1.6
February 42 1.6
March 48 1.6
April 48 1.6
May 51 1.6
June 48 1.6
July 45 1.6
August 59 2.4
September 58 2.4
October 57 2.4
November 50 1.6
December 43 1.6
TOTAL 592 21.6
8 Local Labour and Local Subcontractors
8.1 Introduction
It is envisaged that the works will be constructed by one Contractor employing local labour and subcontractors.
8.2 Workload
The Contractor is required to execute certain components of this contract with labour-based construction methods as described below.
8.3 Local Labour
It is the intention that this Contract should make maximum use of the local labour force that is presently under-employed. To this end the Contractor is expected to limit non-local employees to key personnel only and to employ and train local labour on this Contract.
The Contractor will be required to arrange his own documentation regarding a contract for locally employed labour and must include provisions for the Occupational Health and Safety Act (1993) and the Compensation for Occupational Injuries and Diseases Act.
8.4 Work Considered to be Labour Based
It is a condition of this contract that the following components of work must be executed using labour based construction methods.
1) The construction of concrete edge restraints/kerbing/channelling. 2) The trimming and finishing of earthworks for pavements. 3) The topsoiling and grassing. 4) The backfilling and compaction of trenches in restricted areas. 5) The location of existing services.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 41 of 52
Note:
The abovementioned work must either be done by local labourers employed by the Contractor or by local subcontractors. A prerequisite for payment of these labour-based excavation items is that the Contractor keeps daily written records with names of labourers, tasks completed, man-hours spent and payments made.
Items excluded from labour based items:
1) Excavation in intermediate and hard material - Mechanical excavators and
blasting allowed. 2) Compaction of layer works - Rollers and plate compactors allowed. 3) Transport of materials LDV, dumpers and other transport equipment allowed. 4) Mixing of concrete - Mechanical mixers allowed. 5) Vibration of concrete - Vibrators compulsory. 6) Compaction of service trenches – Plate compactors and or rammers compulsory.
9 Training Schemes
Certain members of the Contractors staff will be selected from the locally recruited employees, to be subjected to training in tasks related to the execution of the contract. The Contractor should provide for the cost associated with training from own resources.
10 Occupational Health and Safety
10.1 General Agreement It is requirement of this contract that the Contractor shall provide a safe and healthy working environment and to direct all his activities in such a manner that his employees and any other persons, who may be directly affected by his activities, are not exposed to hazards to their health and safety. To this end the Contractor shall assume full responsibility to conform to all the provisions of the Occupational Health and Safety Act No 85 and Amendment Act No 181 of 1993, and the OHSA 1993 Occupational Regulations 2003 issued on 18 July 2003 by the Department of Labour.
10.2
Health and Safety Specifications and Plans to be submitted at tender stage (a) Employer's Health and Safety Specification
The Employer's Health and Safety Specification is included in the tender documents.
(b) Tenderer's Health and Safety Plan
The successful Tenderer shall, on receipt of notification that he has been awarded the contract, submit without delay his own documented Health and Safety Plan for the execution of the work under the contract. His Health and Safety Plan must at least cover the following:
(i) a proper risk assessment of the works, risk items, work methods and
procedures in terms of Regulations 7 to 28;
(ii) pro-active identification of potential hazards and unsafe working conditions;
(iii) provision of a safe working environment and equipment;
(iv) statements of methods to ensure the health and safety of subcontractors, employees and visitors to the site, including safety training in hazards and risk areas (Regulation 5);
(v) monitoring health and safety on the site of works on a regular basis, and keeping of records and registers as provided for in the Construction Regulations;
(vi) details of the Construction Supervisor, the Construction Safety Officers and
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 42 of 52
other competent persons he intends to appoint for the construction works in terms of Regulation 6 and other applicable regulations; and
(vii) details of methods to ensure that his Health and Safety Plan is carried out effectively in accordance with the Construction Regulations 2003.
The Contractor's Health and Safety Plan will be subject to approval by the Employer, or amendment if necessary, before commencement of construction work. The Contractor will not be allowed to commence work, or his work will be suspended if he had already commenced work, before he has obtained the Employer's written approval of his Health and Safety Plan.
Time lost due to delayed commencement or suspension of the work as a result of the Contractor's failure to obtain approval for his safety plan, shall not be used as a reason to claim for extension of time or standing time and related costs.
10.3 Cost of compliance with the OHSA Construction Regulations
The rates and prices tendered by the Contractor shall be deemed to include all costs for conforming to the requirements of the Act, the Construction Regulations and the Employer's Health and Safety Specification as applicable to this contract. Should the Contractor fail to comply with the provisions of the Construction Regulations, he will be liable for penalties as provided in the Construction Regulations and in the Employer's Health and Safety Specification. Items that may qualify for remuneration will be specified in the Safety Specifications included or in the Project specifications.
11 Management meetings
In terms of Clause 16.2 of the Contract Management Meetings/Formal Site Meetings will be held at four weekly intervals, and Progress Meetings will be held at two weekly intervals. The dates and times of these meetings will be agreed between the various parties at the site hand-over meeting. These Meetings will be held on site in the site office of the Contractor. The Site Meetings will be chaired by the Engineer and representatives of the Employer, which shall include the Project Manager or his alternate, and the Contractor will be present at the meetings. The Progress meetings will also be chaired by the Engineer and will be attended by the Contractor and his Site Agent. The Employer may attend Progress meetings at his discretion. The purpose of the meetings will be to monitor the progress of the Works, and to take such decisions as may be necessary to ensure the smooth execution of the project. Minutes of the meetings will be taken by the Engineer and will be circulated within 7 days of the meeting.
12 Quality assurance requirements
Within the period stated in the Contact Data, the Contractor submits his complete quality
control and assurance system (with all quality control and assurance
procedures and manuals) for review and acceptance by the Employer. The
manual includes pro-forma checklists for all requirements of the Contractor’s
quality control and assurance program and those called for in the Scope.
Acceptance by the Employer of the Contractor’s quality assurance programme, quality plans
and/or inspection and/or test plans, or of those of his Subcontractors will not
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 43 of 52
relieve the Contractor of his obligation to provide services which meet the
requirements of the Contract.
13 Engineering and design of the works
Employer’s design
The Design of the Works has been undertaken by the Employer and his Consulting Engineer and the
Contractor is to construct the Works in accordance with this design and the associated
specifications.
Parts of the works which the Contractor is to design2
The Contractor will be required to provide shop drawings for the structural steelwork section of the Works where this is considered necessary. The Contractor will be required to carry out detailed planning of the electrical distribution within the buildings to meet the requirements as indicated on the Engineers’ drawings. All such planning will be to the approval of the Engineer.
Equipment required to be included in the works3
All equipment to be included in the Works is indicated on the drawings and/or detailed in the Bills of
Quantities.
As-built drawings, operating manuals and maintenance schedules
The Contractor is to provide fully marked up drawings to the Engineer indicating all As-built information to enable the Engineer to produce accurate As Built drawings of the Works.
Personnel:
Minimum requirements of people employed on the Site
No restraints
Subcontracting
Preferred subcontractors
No Restraints
Limitations on subcontracting
The Contractor may not subcontract more than 20% of the Works.
Plant and Materials
2 3
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 44 of 52
Plant & Materials provided “free issue” by the Employer
Water and electrical power will be made available to the Contractor free of charge. All other plant and materials will be provided by the Contractor.
Contractor’s procurement of Plant and Materials
No restriction.
Tests and inspections before delivery4
All bricks to be used in the construction of the buildings and all paving bricks shall be tested and approved by the Engineer before delivery to the site.
Marking Plant and Materials outside the Working Areas5
Not Applicable
Contractor’s Equipment (including temporary works)
No Restriction
14 Construction
Temporary works, Site services & construction constraints
Employer’s Site entry and security control, permits, and Site regulations
The site of the Works is landside and the Contractor shall control access to the site in terms of Health and Safety Regulations.
Restrictions to access on Site, roads, walkways and barricades The Site of the Works is a fenced off area containing the Maintenance stores
and the Office Building. As such there are no particular restrictions to access to the site by the Contractor. Normal safety barricading shall be erected to prevent unauthorised access to the site. The Contractor will also be permitted to access the site direct from the adjacent road reserve through an existing gate. This will facilitate the bringing of materials to the site and avoid the necessity of travelling through the airport terminal roads.
People restrictions on Site; hours of work, conduct and records
The Contractor shall control access to the site. The hours of work shall be 07:30 to 17:00, Monday to Friday. The Contractor may request to work outside of these hours for good cause.
Conduct of all workmen on site shall at all times be exemplary and no
disturbance or disruption to the workings of the airport of any nature will be tolerated.
Title to materials from demolition and excavation6
The Contractor is to dispose of surplus materials from excavations and demolition work and has title to such materials in terms of Clause 73.2.
4. 5 6
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 45 of 52
Full record of all workmen on the site are to be kept on a daily basis and copies of these records shall be provided to the Engineer each month. Full records of all materials on site are to be kept by the Contractor and copies of these records shall be provided to the Engineer on a monthly basis.
Contractor’s Equipment
Full records of all plant and equipment on site are to be kept by the Contractor and copies of these records shall be provided to the Engineer on a monthly basis.
Equipment provided by the Employer
No equipment will be made available by the Employer.
Site services and facilities provided by the Employer7
The Employer will provide water and electricity to the Contractor free of charge at points where such services are available within the confines of the Site. The Contractor shall make his own arrangements for the provision of toilet facilities for his workmen. This may be either by way of fully serviced chemical toilets or by connection of temporary waterborne toilets to the existing sewers on the site. All other site services and facilities necessary for providing the Works shall be provided by the Contractor.
Facilities provided by the Contractor
The Contractor shall provide his own site office for erection on the site. The site office will include for a meeting room of sufficient size to seat to seat 10 people around a table for the purposes of holding site meetings. This room shall also have facilities for storing all drawings and site information issued to the Contractor.
The Contractor shall at all times have available on site an automatic level and
staff for the use of the Engineer as necessary. The Contractor shall provide four Containers on site for the purposes of storing
the equipment belonging to the Employer during the Construction of the Maintenance Store and the Offices.
On completion of the Contract, all facilities provided by the Contractor shall be
removed from the site.
Existing premises, inspection of adjoining properties and checking work of Others
Not applicable.
setting out of the works
The Contractor shall be responsible for setting out the Works in accordance with the drawings provided by the Engineer.
site conditions and requirements
The Contractor will be responsible for ensuring that all excavations are kept free of water and where required shall make provision for the supply of all pumps which may be required.
7
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 46 of 52
The Contractor will take every precaution to establish the positions of any underground services before any excavation works are commenced. All such services shall be exposed by the Contractor before excavation work is commenced.
The Contractor shall exercise proper control over noise, dust, water and waste.
Construction requirements
The Contractor will be required to programme his work to ensure minimum
disruption to the maintenance operations of the airport maintenance staff. The following sequence of
work, given in broad outline, is to be applied for the purposes of the tender.
Phase 1: Alterations and extensions to Workshop
Phase 2: Alterations and extensions to Office Block
Phase 3: Construction of Roadworks
Before commencement of the Work, the Contractor is to provide the Engineer with a
comprehensive programme for construction of the Works, for approval.
Completion, testing, commissioning and correction of Defects
Work to be done by the Completion Date8
All work is to be done by the Contractor shall be completed by the Completion Date, save for the following: [list project-specific exceptions and state by when the work should be completed]
The Project Manager cannot certify Completion until all the work except that
listed above has been completed and is also free of Defects which
would have, in his opinion, prevented the Employer from using the
works and Others from doing their work.
Use of the works before Completion has been certified9
Parts of the Works may be used by the Employer before the Completion has been certified. In this case the Engineer will issue a partial Certificate of Completion.
Materials facilities and samples for tests and inspections
The Contractor will provide samples of any materials requested by the Engineer for approval.
Access given by the Employer for correction of Defects10
Not applicable
Performance tests after Completion
8 9
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 47 of 52
Not applicable
15 Plant and Materials, Standards and Workmanship
Building works
The following Standardised Specifications are applicable to this Contract. Particular requirements are shown on the drawings. SANS 10400-A:2010 Part Description A General Principles and Requirements C Dimensions D Public Safety F Site Operations G Excavations H Foundations J Floors K Walls L Roofs M Stairways N Glazing O Lighting and Ventilation P Drainage R Storm water Disposal S Facilities for Persons with Disabilities T Fire Protection V Space Heating W Fire Installation
Civil engineering and structural works
The following Standardised Specifications are applicable to this Contract. Particular requirements are shown on the drawings. SANS 1200: STANDARDISED SPECIFICATIONS A General AH General (Structural) C Site Clearance D Earthworks DA Earthworks (Small Works) DB Earthworks (Pipe Trenches) DM Earthworks (roads, subgrade) G Concrete (Structural) GA Concrete (Small Works) GB Concrete (Ordinary Buildings) H Structural Steelwork HA Structural Steelwork (Sundry Items) HB Cladding and Sheeting HC Corrosion Protection of structural steelwork L Medium Pressure Pipelines LB Bedding (Pipes) LC Cable Ducts LD Sewers LE Storm Water Drainage
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C3 – Scope of Works Page 48 of 52
LF Erf Connections (Water) M Roads ME Subbase MF Base MG Bituminous Surface MH Asphalt Base and Surfacing MJ Segmented Paving MK Kerbing and Channelling MM Ancillary Roadworks
Electrical & mechanical engineering works
The requirements of the Contract are indicated on the drawings
Process control and IT works
Not applicable
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C4: Site Information Page 49 of 52
C3.2 CONTRACTOR’S WORKS INFORMATION
The Contractor will be required to provide Shop Drawings for the construction of the structural steel mezzanine floor, and the lean-to shed. The Contractor is to list in Annexure P the plant which will be available for construction of the Works.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C4: Site Information Page 50 of 52
Document reference Title No of pages
This cover page 1
C4 Site Information
Total number of pages
Core clause 11.2(16) states “Site Information is information which describes the Site and its surroundings and is in the documents which the Contract Data states it is in.” In Contract Data, reference has been made to this Part 4 of the contract for the location of Site Information.
PART C4: SITE INFORMATION
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C4: Site Information Page 51 of 52
Description of the Site and its surroundings
Nature of ground and subsoil conditions
There are no rock outcrops in the immediate vicinity of the work.
The site slopes from south towards the north and has already been platformed to accommodate the existing maintenance store. Further excavation will be required to increase the size of the platform to accommodate the lean-to shed and paved areas.
Excavations are expected to be in materials that can be classified as varying from soft to intermediate. The above-mentioned only serves as a guideline and prospective Tenderers shall acquaint themselves with the nature of the conditions on site and the Employer will assume no responsibility for the conclusions reached by the Tenderer.
The nature of the subsoil will be discussed at the site meeting and expected conditions will be indicated.
General description
The site of the Works is the Maintenance area of the George airport. The entire maintenance area is demarcated with a perimeter fence and is as indicated on the site drawing.
Existing buildings, structures, and plant & machinery on the Site
The site drawing indicates the position of the existing facilities within the confines of the maintenance site. The following items form the relevant improvements to the site :
• Existing Roads
• Office Building
• Maintenance Stores
Subsoil information
Nature of ground and subsoil conditions
There are no rock outcrops in the immediate vicinity of the work.
The site slopes from south towards the north and has already been platformed to accommodate the existing maintenance store. Further excavation will be required to increase the size of the platform to accommodate the lean-to shed and paved areas.
Excavations are expected to be in materials that can be classified as varying from soft to intermediate. The above-mentioned only serves as a guideline and prospective Tenderers shall acquaint themselves with the nature of the conditions on site and the Employer will assume no responsibility for the conclusions reached by the Tenderer.
The nature of the subsoil will be discussed at the site meeting and expected conditions will be indicated.
Project No: GRJ8/2017 Refurbishment of Maintenance Stores and Offices at George Airport
Part C4: Site Information Page 52 of 52
Hidden services
All known hidden services have been indicated on the drawings. Before any excavation work is carried out, the Contractor is to carry out a thorough investigation of the area to establish the position of any hidden services. Such services are to be exposed by hand excavation before excavation work by machine is carried out.
Other reports and publicly available information
Not applicable.