  • SEA Scoping Workshop for the NATIONAL CAPITAL INTEGRATED COASTAL DEVELOPMENT

    DHI Water & Environment AFISCO Contributions from: Integra Consulting

  • DHI

    Project & Workshop Objective SEA Scoping Principles and Methods Review of NCICD Masterplan NCICD Scoping Methodology Relevant Baseline Features of Greater Jakarta and Jakarta

    Bay Scoping Results

    Operational Stage of Masterplan: Physio-chemical, Ecological environment & Socio-economic

    Construction and Intermediate Stages: Physio-chemical, Ecological environment & Socio-economic

    Recommendation for SEA TOR and Follow up Analysis / Management

    #2

    Agenda: NCICD Scoping Workshop

  • Goals of NCICD Stakeholder Consultation

    DHI

    The Objectives of the NCICD Stakeholder Scoping Workshop are:

    Present the scoping results (via GIS/spatial analysis)

    Obtain and document stakeholders feedbacks or concerns

    Include scoping outcome in TOR for SEA to ensure all environment and social impact are sufficiently addressed

  • DHI

    Overall Project Objectives

    Preliminary compilation of baseline data to allow for scoping analysis Preliminary Baseline Analysis

    Executing scoping analysis to identify key issues for coverage in the NCICD SEA Scoping

    The execution by the appointed SEA consultant Impact Evaluation and Reporting

    #4

    To prepare a SEA TOR, with preliminary scoping analysis, that will ensure that the appointed SEA expert conducts a NCICD SEA that is sufficient to uncover and mitigate major irreversible strategic issues related to the NCICD Masterplan.

  • Review of SEA Principles

    DHI

  • Step by Step

    DHI

    1. Scoping / baseline analysis Determination of key issues that should be considered in NCICD Analysis of key issues i.e. past trends, the current situation and likely future

    evolution if the plan or programme is not implemented

    2. Assessment of effects of the plan or programme on the key issues and development of mitigation measures (including monitoring scheme)

    3. Compilation of the TOR and scoping report

    #6

    4. Taking information generated for comprehensive SEA and explaining decision in publicly accountable manner

  • Relationship Between SEA & Planning

    DHI

    Planning analyzes and proposes development interventions SEA examines individual outputs of the planning process and it may propose

    any necessary amendments Optimally, SEA should be carried out in parallel with planning, when

    The lead process is the planning process, and SEA fits into the logic and steps of the planning process

    Thus, both processes can be seen as mutually reinforcing tools within one robust planning system for more sustainable development

    #7

  • NCICD Masterplan

    DHI

  • DHI

    Availability of Relevant Masterplan & Baseline Information

    What we have: General NCICD Masterplan Baseline data (physio-chemical, environment, socio-economic) from secondary

    data, previous DHI study in Jakarta, recent survey A basic understanding of autonomous developments

    What we dont have Certain detail regarding design and planning e.g.:

    Dike enhancement design, new sewage and water pipe design, inland water quality treatment, sea wall gates and pumping system, coastal habitat compensation

    Intermediate profiles and construction works/phasing What is possible?

    Scoping at conceptual level to identify key impacts related to the operational and construction phases of NCICD

  • DHI

  • NCICD Scoping Methodology

    DHI

  • Definition of a Strategic Issue for NCICD

    DHI #12

    Strategic environmental impacts (or issues) are those that can only be adequately assessed at the planning, policy, or program stage

    In relation to the NCICD a strategic sustainability issue is further defined in relation to:

    Cumulative impacts Interactive impacts Wide-scale impacts Eco-

    system

    Socio-economic

    Physico-chemical

    Baseline

    NCICD Planning

    Zoned areas

    Project

    Project

    Project Existing activities

    Project

  • Scoping Approach

    DHI

    The scoping aimed at identifying issues of strategic concern related to NCICD master planning

    Scoping sessions applied GIS / spatial data and analysis matrices a focus on utilizing

    Key baseline information Understanding autonomous development (i.e. planned reclamation and land use) Identifying potential environmental risks / issues, as per the an applied definition, from NCICD

    planning

    Stakeholder scoping feedback to obtain new insight/data and verify initial scoping findings

    Providing TOR and scoping report, for the appointed NCICD SEA expert

    #13

  • NCICD SEA Scoping Sessions

    DHI

    Review of key baseline information in studies and via spatial referenced maps Scoping was further organised in relation to:

    The Operational Phase (i.e. final configuration of Masterplan) The Construction Phase (e.g. construction works and intermediate profiles)

    Each phase was further categorised according to location of risks/issues, i.e. DKI Jakarta, Tangerang, Bekasi, and inside / outside of seawall (retention lake)

    strategic sustainability receptor categories, namely:

    1. Physic-chemical Coastal Dynamic Riverine and Drainage Sedimentation Water Quality

    2. Ecosystem Coastal Habitat Biodiversity

    3. Socio-economic Resource-utilization Human Health Livelihood

    #14

  • NCICD SEA Scoping Sessions

    DHI

    A scoping matrix was developed in relation to assessment Phases Locations (incl. distinction between marine and terrestrial) Receptors Risk/issue definitions

    The nature of the issues/risk were recorded in relation to: the definition of a strategic issue or risk (i.e. wide-scale, cumulative, potential

    planning conflict) indicated positive (+) or negative (-) nature additional information such as, location or rational, and the need for further

    analysis

    #15

  • DHI #16

    NCICD Scoping Matrix Example

  • Overview of Relevant Baseline Data

    DHI

  • DHI

    Overview of Relevant Baseline Data Coastal dynamics

    Bathymetry Hydrodynamic Wave Sedimentation Coastal Dynamic Bathymetry is relatively uniform

    and shallow Tidal range is the order of 1.5 m Currents are driven by tide, and

    relatively mild Wave are mild Wave components are dominated

    by local winds and swell component is very minor

    Cohesive sediment deposition thickness is up to 12 m at Jakarta Bay

  • DHI

    Overview of Relevant Baseline Data Rainfall, river and drainage:

    Rainfall Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Year

    Rainfall (mm) 402 284 219 131 113 90 58 61 64 101 128 204 1855

    Average rainy days 19 17 16 11 9 7 6 5 6 8 12 14 130

    source: Climate-Data.org

    Rivers and Drainage

    Rainfall, Rivers and Drainage Rainfall distribution characteristic is

    very related to monsoon seasonal variation

    13 significant rivers flow through Jakarta into the Bay, while several others (Tangerang and Bekasi) also discharge into the Bay

    The rivers discharges contains sediment and poor water quality

    DHI

  • DHI

    Overview of Relevant Baseline Data Ecology: Coral Reef & Mangrove Biodiversity Ecology:

    Live coral cover 0 10%, except in Damar Besar Island (26 50%), Untung Jawa and Rambut Island (11-25%)

    Mangrove species Angke Kapuk Protected Forest incl. Avicenia sp. and Rhizophora sp.

    Government established Wildlife Nature Reserve Muara Angke / Recreational Park Kapuk / Angke Kapuk Protected Forest

    Important Bird Area in Muara Angke, Muara Gembong and Rambut Island

    Biodiversity Bird, Mussels, Fish,

    Crustacean, Reptiles, Mammals

  • DHI

    Overview of Relevant Baseline Data Socio-economic: Existing Land-use Livelihood Poverty Recreation

  • DHI

    Overview of Relevant Baseline Data Socio-economic:

  • DHI

    Overview of Relevant Baseline Data Socio-economic:

  • DHI

    Overview of Relevant Baseline Data Socio-economic:

    Year Kel. Kamal Muara (Org) Kel. Cilincing (Org) Jumlah Pembuididaya (Org)

    Owner Worker Total Owner Worker Total Owner Worker Total

    2007 - - 0 60 175 235 60 175 235

    2008 412 824 1,236 307 1,535 1,842 719 2,359 3,078

    2009 135 245 380 326 1,300 1,626 461 1,545 2,006

    2010 120 212 332 286 1,144 1,430 406 1,356 1,762

    2011 149 415 564 242 906 1,148 391 1,321 1,712

    2012 140 382 522 222 812 1,034 362 1194 1,556

    Trend of green mussel farmer

  • DHI

    Overview of Relevant Baseline Data Socio-economic:

    Year

    Kel. Kamal Muara Kel. Cilincing Total

    Liftnet Production Liftnet Production Liftnet Production

    (Unit) (Ton/year (Unit) (Ton/year (Unit) (Ton/year 2007 - - 630 90,780 630 90,780

    2008 1,216 18,240 1,396 34,900 2,612 53,140

    2009 389 4,668 1,030 31,100 1,419 35,768

    2010 320 4,120 987 29,936 1,307 34,056

    2011 420 15220 796 10215 1216 25,435

    2012 420 14,850 753 9,512 1,155 24,362

    Trend of production of liftnet

  • DHI

    Overview of Relevant Baseline Data Socio-economic:

  • DHI

    Overview of Relevant Baseline Data Resource Utilization: Port Power Plants Industrial Pipeline & Cable

  • DHI

    Overview of Relevant Baseline Data Autonomous Development

    Autonomous Plan 14 proposed islands (DKI Jakarta) & 3

    proposed islands (Tangerang) NCICD assumes the presence of these

    projects in their Master planning DKI Jakarta land use planning

    allocates areas for settlements, business (central), and industries (east)

    NCICD Scoping included this autonomous planning

  • Presentation of Findings: Conceptual Operational Phase

    DHI

  • DHI

    Physio-Chemical (DKI Jakarta) Issues/Risk: Marine Component (outside sea wall): Slight Increase in tidal amplitude due to

    shift of the tidal prism Slight Increase in current speed, due to

    increase in tidal amplitude Increase in wave reflection due to the

    giant sea wall Issues/Risk: Marine Component (inside sea wall): Major change in tidal amplitude and

    current speed (related to environmental & engineering conditions)

    Possible backwater influences The wave conditions are significantly

    reduced Increase in sedimentation inside the

    retention lakes due to poor flushing Poor water quality inside the retention

    lakes

  • DHI

    Physio-Chemical (DKI Jakarta)

    Issues/Risk: Terrestrial Component: Potential flooding and poor

    water quality (i.e. related to environmental & engineering conditions)

    The new piped water supply system will help reducing land subsidence and coastal erosion

  • DHI

    Physio-Chemical (Tangerang) Issues/Risk: Marine Component (outside sea wall): Slight Increase in tidal amplitude due to shift of the tidal prism Slight Increase in current speed, due to increase in tidal

    amplitude Increase in wave reflection Change of coastal formation in Tangerang due to change in

    wave climate

    Issues/Risk: Marine Component (inside sea wall): see previous slide

    Issues/Risk: Terrestrial Component: Potential flooding Poor water quality The new piped water supply system will help reducing land

    subsidence and coastal erosion

  • DHI

    Physio-Chemical (Bekasi) Issues/Risk: Marine Component (outside sea wall): Slight Increase in Tidal amplitude due to shift of the tidal prism due to

    proposed sea wall. Slight Increase in current speed, due to increase in tidal amplitude. Increase in wave reflection due to the giant sea wall Issues/Risk: Marine Component (inside sea wall): see previous slide

    Issues/Risk: Terrestrial Component: Potential flooding Poor water quality The new piped water supply system will help reducing land

    subsidence and coastal erosion

  • DHI

    Operational Phase: Physio-Chemical: Air Quality

    Issues/Risk: Existing poor air quality Unless carefully positioned in NCICD

    master planning, relocated power plants, i.e. combined with existing and new sources of atmospheric emissions, can exacerbate or transfer air quality problems to other locations in or around the master plan area

    On the other hand, good planning and greener designs can help abate air quality problems

  • DHI

    Ecological Environment (DKI Jakarta) Issues/Risk: Marine Component (outside sea wall) Loss of coral reef habitat due to reclamation Secondary impact of water outflows from

    retention lake that cause change in salinity, temperature and turbidity that negatively affecting nearby coral reefs and seagrass beds

    Loss of coral reef biodiversity (reptiles, fish, crustaceans, mollusc)

    Loss of seagrass biodiversity (reptiles, fish, crustaceans, mollusc)

    Marine Component (inside sea wall) Loss of mangrove habitat due to change in

    water salinity. Loss of mangrove biodiversity (mangrove,

    birds, reptiles, mammals, fish, crustaceans, mollusc)

    Loss of benthic communities in Jakarta Bay due to succession

    Transformation from salt water to fresh water fish habitat

  • DHI

    Ecological Environment (DKI Jakarta)

    Issues/Risk: Terrestrial Component Noise disruption to sensitive

    species in mangrove habitat (i.e. birds) due to increased traffic noise from economic activities

  • DHI

    Ecological Environment (Tangerang) Issues/Risk: Marine Component (outside sea wall) Potential change to the mangrove ecology (i.e. community structure) due to

    change in wave climate and increase of current speed

    Marine Component (inside sea wall) Loss of mangrove habitat due to change in water salinity Loss of mangrove biodiversity (mangrove, birds, reptiles, mammals, fish,

    crustaceans, mollusc, etc.) Loss of estuary habitat due to transformation from salt/brackish water to fresh

    water environment Loss of estuary biodiversity (brackish water fish, crustaceans, mollusc, etc.)

    Issues/Risk: Terrestrial Component Possible mangrove habitat fragmentation / loss due to the constructed road Loss of mangrove biodiversity due to fragmentation

  • DHI

    Ecological Environment (Bekasi) Issues/Risk: Marine Component (outside sea wall) Potential change to the mangrove ecology (i.e. community structure) due to

    change in wave climate and increase of current speed

    Marine Component (inside sea wall) Loss of mangrove habitat due to change in water salinity Loss of mangrove biodiversity (mangrove, birds, reptiles, mammals, fish,

    crustaceans, mollusc, etc.) Loss of estuary habitat due to transformation from salt/brackish water to fresh

    water environment Loss of estuary biodiversity (brackish water fish, crustaceans, mollusc, etc.)

    Issues/Risk: Terrestrial Component Possible mangrove fragmentation due to the constructed road Reduction of mangrove coverage due to constructed road. Loss of mangrove diversity due to fragmentation

  • DHI

    Socio-economic Environment Issues/Risk: Stimulate new job opportunities / job creation Increase productivity (by decreasing time spend in traffic

    jam) Removal of pelabuhan Tegar in Marunda and existing

    fishing port along the coast of North Jakarta will lead to changes of livelihood to the workers

    Potential improvement / degradation of local livelihood changes of livelihood pattern of traditional fisherman

    and provision of seafood products opportunity for local communities social conflict due to changes of social structure

    Potential community health impact due to water / air pollution / noise

    Potential better access to health systems / facilities

    DKI Jakarta

  • DHI

    Socio-economic Environment Tangerang

    Issues/Risk: Stimulate new job opportunities / job creation Increase productivity (by decreasing time spend in traffic jam) Removal of Dadap fishing port will lead to changes of

    livelihood to the workers Potential improvement / degradation of local livelihood

    changes of livelihood pattern of traditional fisherman and provision of seafood products

    opportunity for local communities social conflict due to changes of social structure

    Increase in land value due to opening of new road access to new commercial, residential and industrial areas

    Potential community health impact due to water / air pollution / noise

    Potential better access to health systems / facilities

  • Socio-economic Environment

    DHI

    Bekasi Issues/Risk: Stimulate new job opportunities / job creation Increase productivity (by decreasing time spend in traffic jam) Removal of Muara Tawar fishing port will lead to changes of

    livelihood to the workers Potential improvement / degradation of local livelihood

    changes of livelihood pattern of traditional fisherman and provision of seafood products

    opportunity for local communities social conflict due to changes of social structure

    Increase in land value due to opening of new road access to new commercial, residential and industrial areas

    Potential community health impact due to water / air pollution / noise

    Potential better access to health systems / facilities

  • DHI

    Resource Utilization and Infrastructure (DKI Jakarta) Issues/Risk: Marine Component Loss of Port accessibility from sea Impact to navigation to all existing

    marinas, and fishing port along the coast except Tanjung Priok Port

    Relocation of anchorage area for Tanjung Priok Port.

    Relocation of existing subsea gas pipeline and telecommunication cable

    Possible relocation of 4 existing steam power plants.

    Loss of existing green mussel aquaculture activities by local communities due to changes in salinity

    Loss of existing marine fishing ground and aquaculture

    Potential change to fresh water fishing activities

  • DHI

    Resource Utilization and Infrastructure (DKI Jakarta) Issues/Risk: Marine Component Relocation of local fishermen

    communities and fish landing Loss of sea view from the existing

    housing (apartment) and hotels Issues on accessibility to Industrial

    area and special port of Marunda and others

    Possible impact on accessibility and water quality in Taman Impian Jaya Ancol and other coastal recreation

  • DHI

    Resource Utilization and Infrastructure (DKI Jakarta) Issues/Risk: Terrestrial Component Inland access to existing Tanjung

    Priok port Changes in road network and traffic

    density Improve public transportation

    facilities (e.g. MRT, Busway) and stimulate new transportation mode through channels (eg. Water taxi)

    Improve accessibility and reduce traffic

    Improve accessibility for goods and services distribution jam around north Jakarta area

    Improve accessibility to recreational areas

  • DHI

    Resource Utilization and Infrastructure (Tangerang) Issues/Risk: Marine Component Impact to accessibility to existing fishing ports in Dadap Loss of existing green mussel aquaculture activities by local communities due

    to changes in salinity Loss of existing marine fishing ground and aquaculture. Potential change to fresh water fishing activities Relocation of local fishermen communities Issues/Risk: Terrestrial Component Changes in road network Potential increase in traffic density to/from Pantura to airport Improve accessibility from Tangerang to Bekasi Access to new areas will lead to expansion of new commercial and residential

    area

    Stimulate the expansion of new industrial areas

  • DHI

    Resource Utilization and Infrastructure (Bekasi) Issues/Risk: Marine Component Loss of pelabuhan Tegar in Marunda Loss of accessibility to existing fishing ports in Muara Tawar Loss of navigation channel for Pelabuhan Tegar. Relocation of existing subsea gas pipeline Potential impact to Muara Tawar Steam Power plant (PLTU) Loss of existing green mussel aquaculture activities by local communities due

    to changes in salinity Loss of existing marine fishing ground and aquaculture. Potential change to fresh water fishing activities Relocation of local fishermen communities and fish landing Loss of marine access to existing Marunda center industrial area (storage).

  • DHI

    Resource Utilization and Infrastructure (Bekasi) Issues/Risk: Terestrial Component Changes in road network Improve accessibility from Bekasi to Tangerang Access to new areas will lead to expansion of new commercial and residential

    area

    Stimulate the expansion of new industrial areas

  • Presentation of Findings: Construction Impact / Intermediate Phases

    DHI

  • DHI

    Construction Phase: Physio-Chemical (DKI Jakarta, Tangerang, Bekasi) Likely Construction Activities

    Dredging & dredge material dumping

    Relocation of current residences / businesses

    Logistics Construction camps Transport of the materials (via

    water or road) Diversion of roads

    Canal diversions

    Intermediate profiles

  • DHI

    Physio-Chemical (DKI Jakarta, Tangerang, Bekasi) Issues/Risk: Marine Component Change of current speed and

    reverted current due to construction of new structures

    Local wave change such as refraction, diffraction due to construction of new structures

    Increase of TSS due to dredging and dumping process

    Increase/decrease of TSS concentration supplied from the reverted canal/river

    Issues/Risk: Terrestrial Component Possible flooding due to the

    temporary river/drainage diversions

  • DHI

    Ecological Environment (DKI Jakarta) Issues/Risk: Marine Component Potential interference to mangrove,

    seagrass and coral reef due to dredging activities (spill)

    Loss of coral reef habitat due to reclamation project footprint

    Increased stress to marine and coastal species (e.g. coral reefs, fish, birds, mammals, reptiles, etc.)

    Issues/Risk: Terrestrial Component Increase stress to local species due

    to noise from construction activities

  • DHI

    Ecological Environment (Tangerang & Bekasi) Issues/Risk: Marine Component Potential interference to mangrove

    and seagrass due to dredging spill (contaminated sediment)

    Increase stress to marine and coastal species (e.g. fish, birds, etc.)

    Terrestrial Component Potential mangrove fragmentation

    due to the road construction Increase stress to local species due

    to noise from construction activities

  • DHI

    DKI Jakarta, Bekasi, Tangerang Issues/Risk: High potential for job creation Decrease of fishermen income due to loss of

    access to fishing ground and mariculture area Potential impact of pollution to the community

    health during constructions phase Increasing social conflicts because of conflict

    between land reclamation, fishing grounds, and mariculture area

    Potential increase of social conflict due to increase of in-migration worker, decreasing marine activities income, social pressure and less public space

    Flood damage / losses

    Socio-economic Environment

  • DHI

    Specific to Bekasi & Tangerang Issues/Risk:

    Coastal residences / businesses Potential inundation from altered tidal levels and

    temporary flooding

    Coastal aquaculture and agriculture Potential inundation from altered tidal levels and

    temporary flooding TSS impacts from dredge and reclamation

    works

    Socio-economic Environment

  • DHI

    Resource Utilization and Infrastructure (DKI Jakarta) Issues/Risk: Marine Component Interference of port activities and

    navigation from construction traffic Disruption of subsea gas pipeline

    and communication cable, if no relocation take place

    TSS /sedimentation disruption to water Power Plant inlet / outlet systems

    Disruption of aquaculture activities (green mussel)

  • DHI

    Resource Utilization and Infrastructure (DKI Jakarta) Issues/Risk: Marine Component Increase of noise during

    construction phase to existing commercial and residential areas

    Interference of accessibility to industrial areas (e.g. loading and unloading of goods)

    Recreational area will be less convenient and attractive

  • DHI

    Resource Utilization and Infrastructure (DKI Jakarta) Issues/Risk: Terestrial Component Traffic congestion to existing road

    network due to new road construction

    Traffic congestion due to new facilities / infrastructure (water supplies, sanitation, public transport facilities) construction

    Disturbance to commercial activities and residential areas (e.g. noise, dust and traffic congestion)

    Disturbance to industrial activities (e.g. traffic congestion)

    Recreational area will be less convenient and attractive

  • DHI

    Resource Utilization and Infrastructure (Tangerang) Issues/Risk: Marine Component Interference of port activities due to relocation (Dadap) and increase of ship

    traffic during construction Interference of navigation due to increase of ship traffic during construction Disruption of fishing activities and decrease of fish catch. Disruption of aquaculture activities (green mussel, fish ponds) due to

    dredging spills Increase of noise during construction phase to Existing commercial and

    residential area

    Issues/Risk: Terrestrial Component Relocation of the Dadap port Traffic congestion in existing road due to new road construction Traffic congestion due to new facilities / infrastructure (water supplies,

    sanitation, public transport facilities) construction Disturbance toward the commercial activities and residential areas (e.g. noise,

    dust and traffic congestion) Disturbance toward the industrial activities (e.g. traffic congestion)

  • DHI

    Resource Utilization and Infrastructure (Bekasi)

    Issues/Risk: Terestrial Component Relocation of the pelabuhan Tegar in Marunda and fishing ports in Muara Tawar Traffic congestion in existing road due to new road construction Traffic congestion due to new facilities / infrastructure (water supplies,

    sanitation, public transport facilities) construction Disturbance toward the commercial activities and residential areas (e.g. noise,

    dust and traffic congestion) Disturbance toward the industrial activities (e.g. traffic congestion)

    Issues/Risk: Marine Component Interference of port activities due to relocation (Pelabuhan Tegar in Marunda

    and fishing ports in Muara Tawar) and increase of ship traffic during construction

    Interference of navigation due to increase of ship traffic during construction Disruption of subsea gas pipeline if no relocation take place Disruption of fishing activities and decrease of fish catch. Disruption of aquaculture activities (green mussel, fish ponds) due to

    dredging spills

  • Key Recommendations

    DHI

  • Recommended NCICD SEA Tasks

    DHI

    Task 1 & 2 Investigation & Identification Fill in gaps of baseline data collection and impact identification Additional stakeholders consultation

    Task 3 Quantification & Analysis Suitable level of numerical modelling of coastal dynamics Expert analysis

    Task 4 Analysis & Assessment Final assessment and ranking of key social and environmental issues

    Task 5 & 6 Mitigation & Monitoring Recommend mitigation measures to allow conceptual Masterplan to proceed Describe mitigation actions (road-map) for subsequent phases of NCICD Masterplan development

    and engineering Develop requirements for continuous environmental monitoring for subsequent phases of NCICD

    development

  • Minimum level of Data Collection & Analysis

    DHI

    SEA Component Baseline Data Collection

    Comprehensive secondary data It is preferable to have:

    Remote sensing of coastal habitat with ground-truthing Spot-check verification of habitat quality ADCP measurements (at least 2 locations) for 1 month and a full

    bathymetric survey

    Analysis of Coastal Dynamics

    Preliminary validated numerical modelling (hydrodynamic*, coastal morphology*), tidal analysis, wave analysis (reflection due to project), expert analysis

    Analysis of Ecosystem Issues

    GIS Mapping, established tolerance limits, expert analysis

    Analysis of Socio-economic Issue

    GIS Mapping, expert analysis, stakeholder engagement IFC Rapid Socio-economic impact analysis methodology

    * Its recommended to use validated existing internationally recognized model of Jakarta bay

  • Strategic Issues for Further Analysis: Jakarta

    DHI

    Inside Retention Lakes

    Further detailed analysis of: changes in Backwater

    conditions water quality and sedimentation

    issues in the retention lakes

    Outside Retention Lakes

    Further detailed analysis of: changes to

    current speed, tidal level, and wave climate

    Sedimentation, erosion and turbidity water quality

    Resulting impact to mangrove, sea grass and coral habitat

    social impact in livelihood changes and created job opportunities

    social impact in poverty reduction and increase

    potential social conflict

  • Strategic Issues for Further Analysis: Tangerang & Bekasi

    DHI

    Outside Retention Lakes

    Further detailed analysis of: changes to

    current speed, tidal level, and wave climate Sedimentation, erosion and turbidity water quality Additional focus on coastal morphology and flooding

    Resulting impact to mangrove, sea grass and coral habitat Coastal aquaculture and agriculture (ponds) social impact in livelihood changes and created job opportunities social impact in poverty reduction and increase potential social conflict

  • Outline of Subsequent Analysis, Management & Monitoring

    DHI

    NCICD Master Plan Scoping & SEA ToR

  • Plenary Session

    DHI

  • Discussion and Q-A Session

    DHI

    Instructions Please spilt into 2 groups (if time permits) Please, as a group, review the findings via the presentation material and if needed,

    the GIS database In your analysis please determine or develop

    If there is additional information relevant to the SEA Substantiated feedback on the validity or inaccuracy of the presented findings Alternative analysis requirements for the NCICD SEA

    Elect a representative and provide a brief summary of your groups findings

  • Thank you