nazg 388212240 road expo 05 2014 eng road expo 2014
TRANSCRIPT
1
ROAD DEVELOPMENT WORKS TO BE
IMPLEMENTED IN ULAANBAATAR CITY
IN 2014
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
CAPITAL CITY ULAANBAATAR IS THE
HOME OF 1.3 MILLION POPULATION WHICH IS
43.7 PERCENT OF NATIONAL POPULATION
AND 321200 UNITS OF VEHICLES OR 54.1
PERCENT OF TOTAL REGISTERED VEHICLE
FLEET OF THE COUNTRY ARE PARTICIPATING
IN CITY’S DAILY TRAFFIC.
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
TOTAL LENGTH OF THE PAVED ROAD OF
MONGOLIA IS 4771 KM,OUT OF WHICH 657.67
KM OF ROADS BEEN USED IN ULAANBAATAR
CITY.
IN THE COUNTRY WE HAVE 12.335 L/
METER CONCRETE BRIDGES, OUT OF WHICH
ULAANBAATAR CITY HAS 3.606.6 L/METER
BRIDGES.
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
Ulaanbaatar city has 321.200 units of
vehicles. Out of which 170.000 are
participating in the city’s daily traffic and the
city inbound traffic from the country side reach
average 9000 units of vehicles daily.
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
CONTENT
ONE. Brief information on the projects and
measures implemented in the road sector
of Ulaanbaatar city in 2013
TWO. Projects and measures to be
implemented in the road sector of
Ulaanbaatar in 2014
6
One.
Brief information on the projects and
measures implemented in the road
sector of Ulaanbaatar city in 2013
Total of 88 projects and measures are implemented, with
budgeted cost of 221.8 billion tugrugs, and 145.5 км
road and 368.7 l/мeter bridges are constructed.
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
Rehabilitation of 3.6 km road and extension of 1.2 km further in Zuun salaa
of Songino Khairkhan district
Client Ulaanbaatar Department of roadsContractor “ОDND” LLCWidth of the roadway 7 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and pedestrian walkways.
Rehabilitation and widening of 2.8 км paved road from Dorj street, Tuul
Jinpan intersection to east to Tsaiz market
Client Ulaanbaatar Department of roadsContractor “Bering” LLCWidth of the roadway 19.8 мeterBase layer 5 смSurface layer 4 смOther parameters Has street lighting and pedestrian walkways and drainage
system
Rehabilitation and widening of 1.6 км paved road from east south
intersection of School #39 to Khuchit shonkhor market bus terminal
Client Ulaanbaatar Department of roadsContractor “Batcubic” LLCWidth of the roadway 7 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and pedestrian walkways and drainage
system
Rehabilitation of 1.7 км paved road from Bayanburd roundabout in
Chingeltei district to 32nd Roundabout
Client Ulaanbaatar Department of roadsContractor “Naranbulag Khan” LLCWidth of the roadway 7 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and pedestrian walkways and drainage
system
Construction of 0.2 км road and railway tunnel connecting Narnii road of
Bayanzurkh district with Bayanmongol khoroolol
Client Ulaanbaatar Department of roadsContractor “Tuuliin guur dalai” LLCWidth of the roadway 9 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and drainage system
Rehabilitation of Selbe twin bridge 58х2 l/мeter
Client Ulaanbaatar Department of roads
Contractor “Мотоr service” LLC
Width of the roadway 24 меter
Other parameters Has street lighting and pedestrian walkways
Rehabilitation of 4.5 км paved road from East intersection-Officer’s palace-
Chuluun ovoo to Trolleybus terminal
Client Ulaanbaatar Department of roadsContractor “Yalguusan” LLCWidth of the roadway 21 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and pedestrian walkways and drainage
system
Rehabilitation and widening of 3.2 км paved road from Sapporo
roundabout – Moscow street- Trade union street to 5 shar
Client Ulaanbaatar Department of roadsContractor “Тоtal inj” LLCWidth of the roadway 23 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and pedestrian walkways and drainage
system
Rehabilitation and widening of 3.4 км paved road from Trade union street
to Bayankhoshuu
Client Ulaanbaatar Department of roadsContractor “Huvai Mongolia” LLCWidth of the roadway 14 меterBase layer 4 смSurface layer 3 смOther parameters Has street lighting and pedestrian walkways and drainage
system
Rehabilitation of 4.1 км paved road from Dund river – Trade union street
and 19th Micro district
Client Ulaanbaatar Department of roadsContractor “CFC group” LLCWidth of the roadway 14 меterBase layer 5 смSurface layer 4 смOther parameters Has street lighting and pedestrian walkways and drainage
system
In 2014:
Roads to be rehabilitated – 54.9 км
Roads to be newly constructed – 40.4 км
Bridge repair, rehabilitation – 243.2 l/мeter
Surface drainage system – 9 locations
Underground tunnel for Vehicle traffic – 1
Flyover bridge for pedestrians – 2
Natural stone road – 1.84 км and total budgeted cost
is 74 billion 130 million tugrugs.
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
2.1. Major projects and measures to
be implemented over the years
НИЙСЛЭЛИЙН АВТО ЗАМЫН ГАЗАР
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
Rehabilitation and widening of 13.7 km paved road from Yarmag
bridge –Nisekh – Nisekh tollgate- Sonsgolon intersection to Yarmag
tollgate
Contractor “HKB International Holding” LLC
Work progress 65%
Note: The drainage and base course works done. As it listed in the projects that funding is “freezed” the implementation period is unknown so far.
Rehabilitation and widening of
22.5 км paved road from Nisekh tollgate- Biocombinat to Shuvuun
Fabric /with 99.2 l/мeter bridge/
Contractor “Тоtal Inj” LLC
Work progress 75%
Note: Base layer is done. Out of 30.5 billion tugrug total budget 2 billion is allocated in 2012, 15 billion is allocated in 2013, and 13.5 billion is budgeted for the year 2014. Depending on the funding the work couldn’t be executed on its intended commissioning date.
Construction of 4.5 км paved road in Selkhe summer housing area
Contractor “PCF” LLC
Implementation period 2014.06.15
Work progress 68%
Note: The embankment work is done and pavement for 1.8 km section is done. The pavement work on the remaining section will be done and also the pedestrian walkway and street lighting will be installed.
Construction of 6.0 км paved road as the continuation of the
horisontal arterial road south of the railway line /from Dunjingarav trading
center to Uliastay intersection/
Contractor “Khansuun zam” LLC
Implementation period 2014.10.15
Work progress 10%
Note: The drinking water reserve fence which is under the road right of way is not possible to be relocated.
10. Construction of the pedestrian flyover near the Central stadium in
Khan-uul district’s 8th khoroo
Contractor “MBAS" LLC, “Giatsint” LLC partnership
Implementation period 2014.05.20
Work progress 5%
11. Construction of the pedestrian flyover near the 100 ail
construction market in Sukhbaatar district’s 10th khoroo
Contractor “ZMZ” LLC
Implementation period 2014.05.20
Work progress 5%
12. Construction of 17.6 км paved road from Bayanzurkh toll gate to
Yarmag Bridge alongside the North of Bogd Mountain
Contractor “ЭСТО” ХХК
Implementation period 2014.08.01
Work progress 60%
Тайлбар: Замын трасст орсон 23 объектыг нэн даруй чөлөөлөх шаардлагатай. Улсын баяр наадмаас өмнө ашиглалтад өгөхөөр зорьж байна.
14. Rehabilitation and widening of Beijing street to be implemented
under the PRC Government grant funding
/0.9 км, 74 l/meter bridge/
Contractor “Beijing Construction engineering Group” LLC
Implementation period 2014.11.30
Work progress Work just has began.
2.2. Projects and measures to be
implemented under new planning
НИЙСЛЭЛИЙН АВТО ЗАМЫН ГАЗАР
Implementation Agency of the Capital city Mayor
DEPARTMENT OF ROADS
№ Name of the project and measures, location and capacity Comment
1
Rehabilitation of 1.3 км of paved road from Petrovis
Gasoline station to Tsaiz market intersection in Nalaikh
district
The open tender selection
process is ongoing.
2
Construction of 0.5 km of paved road and underground
tunnel from Narnii road to Ikh Mongol empire road
connecting under the railway
Detailed designing is ongoing.
3Rehabilitation of 2.5 km road and construction of 3.1 km
paved roads in Sharga Morit Valley
Detailed designing is ongoing.
4
Rehabilitation and widening of 0.54 km paved road from
Sukhbaatar district, 1st Khoroo, Choidog Street, Central
library to Central Hospital #1
The open tender selection
process is ongoing.
НИЙСЛЭЛИЙН АВТО ЗАМЫН ГАЗАР
№ Name of the project and measures, location and capacity Comment
5
Rehabilitation and widening of 4.6 km paved road from
Khuvisgalchis street, Zuragt’s new bus terminal to
Bayankhoshuu intersection
The open tender selection
process is ongoing.
6 Rehabiliatation of 0.5 km paved road of Sansar Tunnel Detailed designing is ongoing.
7Construction of 1.2 km paved road from Bayanzurkh
district, 22nd khoroo, Monel to Zuun Altan-ulgii
The open tender selection
process is ongoing.
8Construction of 0.5 km approach road at Temporary
bridge next to the Yarmag existing bridge
The open tender selection
process is ongoing.
НИЙСЛЭЛИЙН АВТО ЗАМЫН ГАЗАР
№ Name of the project and measures, location and capacity Comment
9
Construction of rain water drainage system in Chingeltei
district, 1st khoroo, Juulchin street, Gutal 22 nd outlet
and Jigjidjav street surroundings
The open tender selection
process is ongoing.
10
Construction of rain water drainage system in Bayangol
district, 3rd khoroo, Railway police department, Gan
zam hotel and its surroundings
The open tender selection
process is ongoing.
11
Construction of rain water drainage system in
Bayanzurkh district, 13 th Microdistrict, Building 21 nad
its surroundings
The open tender selection
process is ongoing.
12
Construction of rain water drainage system in Chingeltei
district, 5th and 6th khoroos and their surroundingsThe open tender selection
process is ongoing.
НИЙСЛЭЛИЙН АВТО ЗАМЫН ГАЗАР
№ Name of the project and measures, location and capacity Comment
13
Construction of rain water drainage system for 2.3 km of
road from Amgalan- Botanic Trollyebus terminal to
Uliastay river Bridge
The open tender selection
process is ongoing.
14
Construction of new rain water drainage system in
Gandi Street and reinforcing the pavement /From
Dunjingarav intersection to Chinggis Avenue/
The open tender selection
process is ongoing.
15Construction of district rain water drainage system in
XIX microdistrict, 120 Myangat, Khan-uul district
The open tender selection
process is ongoing.
НИЙСЛЭЛИЙН АВТО ЗАМЫН ГАЗАР
THANK YOU FOR YOUR
ATTENTION
ULAANBAATAR DEPARTMENT OF ROADS
2014