navfac mid-atlantic 11/14/2007 naval station newport installation restoration program budget update...
TRANSCRIPT
11/14/2007
NAVFAC MID-ATLANTIC
NAVAL STATION NEWPORT INSTALLATION RESTORATION PROGRAM
BUDGET UPDATE – FY 2007 ACTUAL COSTS AND FY 2008 EXECUTION PLAN
11/14/20072 Naval Station Newport IR Program
FY07 ACTUAL EXECUTION
PROJECT COST REMARKS
Basewide Background Study $77,088 Addt’l Fieldwork
Site 1 – McAllister Point Landfill O&M Onshore & Offshore
$455,442 Annual Cost
Site 8 – NUSC Fieldwork $832,068 Ecological Sampling
Site 8 – NUSC Fieldwork $804,200 Hydrogeological Sampling
Site 9 – OFFTA Implement Removal Action
$938,206 Fieldwork
Sites 12&13 – Tank Farms 4&5
$522,159 Data Gap Fieldwork
Site 13 – Tank Farm 5 $169,797 P&T System Demo Design
Site 17 – Gould Island Phase 2 RI & BERA
$235,000 Incl. Work Plan Only
Site 17 – Gould Island Phase 2 RI & BERA
$709,031 Incl. Fieldwork and Reporting
11/14/20073 Naval Station Newport IR Program
FY07 ACTUAL EXECUTION
PROJECT COST REMARKS
Site 19 – Derecktor Shipyard Sandblast Grit Removal Action
$78,766 Addt’l Funding to complete Removal
Site 21 – Melville Water Tower $732,780 Removal Action
UST Site 8 – Building 70 $425,913 Addt’l Remediation
UXO Site 1 – Carr Point $341,769 Incl. WP, Fieldwork, and Reporting
TOTAL $6,322,219
Color denotes project was added as a new requirement
Color denotes project was moved up from a future fiscal year requirement
11/14/20074 Naval Station Newport IR Program
FY07 ACTUAL EXECUTION
FY06 ACTUAL
$1,420,102
FY 07 PLAN
$4,937,779
FY 07 ACTUAL
$6,322,219
11/14/20075 Naval Station Newport IR Program
FY08 PLANNED EXECUTION
Site 1 – O&M Onshore & Offshore $400,000 Annual Cost
Site 8 – Addt’l RI Fieldwork Requirements $350,000 Potential Cost Impacts to Planned Actions
Site 9 – PRAP/ROD $125,000 Pending Completion of FS Phase
Site 9 – Addt’l Removal Action Requirements
$400,000 Potential Cost Impacts to Planned Actions
Site 9 – Shoreline Protection (Revetment) $1,000,000 Design currently under development
Sites 12 & 13 – Addt’l Data Gap Fieldwork $155,000 Potential Cost Impacts (Work Plan still under Development )
Site 13 – Dismantle Pump & Treat System $450,000 Design currently under development
Site 19 – PRAP/ROD for Marine Sediments
$200,000 Pending Completion of Marine Sediment FS
Site 19 – Onshore Fieldwork $220,000 Groundwater Sampling (WP/Fieldwork/Reporting)
Site 21 – Melville Water Tower $220,000 Groundwater
PROJECT COSTS (ESTIMATED) REMARKS
11/14/20076 Naval Station Newport IR Program
FY08 PLANNED EXECUTION
UST Site 8 – Building 70 $60,000 Groundwater Monitoring
TOTAL $3,580,000
PROJECT COSTS (ESTIMATED) REMARKS