NATIONAL SOLAR WATER HEATER (NSWH) PROGRAMME Summary / Discussions 1 Purpose: Summarise Workshop Discussion Date: 04 September 2015

Upload: jesse-peters

Post on 04-Jan-2016

214 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: NATIONAL SOLAR WATER HEATER (NSWH) PROGRAMME Summary / Discussions 1 Purpose: Summarise Workshop Discussion Date: 04 September 2015

NATIONAL SOLAR WATER HEATER (NSWH)PROGRAMME

Summary / Discussions

1

Purpose: Summarise Workshop DiscussionDate: 04 September 2015

Page 2: NATIONAL SOLAR WATER HEATER (NSWH) PROGRAMME Summary / Discussions 1 Purpose: Summarise Workshop Discussion Date: 04 September 2015

Summary …• DoE provided a historical background to the national solar water heater

programme (NSWHP) and further advised that:– On the 24 June 2015 the Cabinet Approved that the re-appropriation of funds to DoE

be consulted with the Minister of Finance. – The programme’s institutional arrangements have been re-engineered. – DoE will implement the new programme as outlined in the Revised Conceptual

Framework which was presented in the Municipal Engagement Workshop– All programme management and implementation is now centralised at DoE. – DoE seeks to test/pilot the revised programme implementation framework prior to

considering delegating some of its elements to municipalities.– The categorisation of the programme as low and high pressure programme has now

been replaced by the social and load reduction programme respectively.– Approved HP SWH systems, with a volume of up to 150L, will also be installed in the

low-end market.– Systems under the social programme will be fully subsidised whilst partial subsidies

will be offered for costlier systems (> 150L) under the LRP.– No Service Providers have been contracted by DoE to implement the NSWHP.

2

Page 3: NATIONAL SOLAR WATER HEATER (NSWH) PROGRAMME Summary / Discussions 1 Purpose: Summarise Workshop Discussion Date: 04 September 2015

Summary …– There’s currently no SWH funding application process. – Municipalities should therefore no longer sign Letters of Intent/Service Level

Agreements/Memorandums of Understanding in anticipation of DoE SWH funds.– In due course municipalities will receive a DoE-Municipal Framework Agreement that

outlines, among other things, the conditions for participation in the NSWHP.– The designation of installation areas by municipalities should be treated as a matter

of urgency.

3

Page 4: NATIONAL SOLAR WATER HEATER (NSWH) PROGRAMME Summary / Discussions 1 Purpose: Summarise Workshop Discussion Date: 04 September 2015

Next Steps• DoE will share the following documentation on 07 September 2015:

– Workshop presentations– Summary discussion for the workshop– Scanned attendance registers– Latest list of municipalities that have made SWH RFI submissions– Envisaged roles for the NSWHP SteerCo participating organisations

• Once internal processes are concluded, DoE will circulate the Framework Agreement for municipal sign-off.

• DoE further committed to share the narrative for the NSWHP Conceptual Framework no later than the end of Q3: 2015/16.

4

Page 5: NATIONAL SOLAR WATER HEATER (NSWH) PROGRAMME Summary / Discussions 1 Purpose: Summarise Workshop Discussion Date: 04 September 2015

Common Questions/Issues

5

Issue Response

Requirement for participating in the NSWHP

RFI Submission and signing of the Framework Agreement

Maintenance and repair plan for previously installed systems

To be attended to in parallel with new installations

Inclusion of rural municipalities with specific reference to technical requirement

Technical constraints need to be reported to DoE for further consideration by the relevant SteerCo participant(s)

Climatic zone recognition when implementing the project

Freeze resistance status systems to be appropriately considered

Criteria for qualification of trainees Presentation on training of locals

Appointment/accreditation of manufacturers and installers

All procurement of goods, services and works will be done by DoE