32
Application Reference EN020015 September 2018 DOCUMENT 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North Wales Connection Project) Regulation 5(2)(a) including (l) and (m) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009

Upload: others

Post on 31-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Application Reference EN020015 September 2018

DO

CU

ME

NT

5.11.2.5

Walkover Survey Chapter 11 – Appendix 5

National Grid (North Wales Connection Project)

Regulation 5(2)(a) including (l) and (m) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009

Page 2: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North
Page 3: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 i

North Wales Connection Project

North Wales Connection Project

Volume 5

Document 5.11.2.5 Appendix 11.5 Walkover Survey

National Grid National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA Final September 2018

Page 4: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 ii

North Wales Connection Project

Page intentionally blank

Page 5: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 iii

North Wales Connection Project

Document Control

Document Properties

Organisation AECOM

Author William Hartas

Approved by Nick Struggles

Title Appendix 11.5 Walkover Survey

Document Reference Document 5.11.2.5

Version History

Date Version Status Description/Changes

September 2018

Rev A Final Final for submission

Page 6: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 iv

North Wales Connection Project

Page intentionally blank

Page 7: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 v

North Wales Connection Project

Contents

1.1 Braint Tunnel Head House/Cable Sealing End Compound 1

1.2 Tŷ Fodol Tunnel Head House/Cable Sealing End Compound 4

1.3 Nant Y Garth Landfill 5

1.4 Penmynydd Road Construction Compound 6

1.5 Llanfechell Waste Water Treatment Works 9

1.6 Local Authority Contaminated Land Features Refs 2148 and 2162 11

1.7 Surface Working Features Refs 30, 194-328, 506 and 687 (Pond) 13

1.8 Surface Woking Feature (Quarry) at Pylon 4ZA078 (Figure Refs 340, 772) 14

1.9 Former Petrol Station, Star, Anglesey 17

1.10 Former Private Water Supply – Dryll, Amlwch 19

1.11 Private Water Supply – Tyddn Fadog 21

1.12 Private Water Supply – Maen Eryr 23

Page 8: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 vi

North Wales Connection Project

Page intentionally blank

Page 9: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 1

North Wales Connection Project

1.1 BRAINT TUNNEL HEAD HOUSE/CABLE SEALING END COMPOUND

PHOTOGRAPHIC LOG Braint THH/CSEC

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

Southerly

Description:

General site

conditions from.

Note trackway from

Ground

Investigation works.

1 Walkover Survey

Page 10: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 2

North Wales Connection Project

Photo No.

2

Date:

22/03/17

Direction Photo

Taken:

South-easterly

Description:

General site

conditions

Photo No.

3

Date:

22/03/17

Direction Photo

Taken:

Southerly

Description:

General site

conditions

Page 11: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 3

North Wales Connection Project

Photo

No.

4

Date:

22/03/17

Direction Photo

Taken:

North-easterly

Description:

General site

conditions. Note

soft ground

conditions. Ground

Investigation in

progress.

Photo

No.

5

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

General Site

Conditions

Page 12: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 4

North Wales Connection Project

1.2 TŶ FODOL TUNNEL HEAD HOUSE/CABLE SEALING END COMPOUND

PHOTOGRAPHIC LOG Tŷ Fodol THH/CSEC

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

General Site

Conditions

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Westerly

Description:

General Site

Conditions

Page 13: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 5

North Wales Connection Project

1.3 NANT Y GARTH LANDFILL

PHOTOGRAPHIC LOG Nant Y Garth Landfill

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

General site

conditions of

landfill.

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description: Front

gate photograph

taken from B4547.

Natural Resources

Wales confirmed

licence number and

active Inert Waste

Landfill Status.

Page 14: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 6

North Wales Connection Project

1.4 PENMYNYDD ROAD CONSTRUCTION COMPOUND

PHOTOGRAPHIC LOG Penmynydd Road Construction Compound

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

South-westerly

Description:

General condition

of access to

proposed

compound area

and track.

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Westerly

Description:

Gas pipeline

crosses access

track approximately

30 m from access

point on the B5420

(Bellmouth

Reference D3).

Page 15: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 7

North Wales Connection Project

Photo

No.

3

Date:

22/03/17

Direction Photo

Taken:

North-westerly

Description:

General condition

of former quarry.

Note that it is

infilled with organic

farm waste, soils,

building refuse,

tarmacadam,

plastic.

Photo

No.

4

Date:

22/03/17

Direction Photo

Taken

North-westerly

Description:

General condition

of former quarry.

Note that it is

infilled with organic

farm waste, soils,

building refuse,

tarmacadam,

plastic.

Page 16: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 8

North Wales Connection Project

Photo

No.

5

Date:

22/03/17

Direction Photo

Taken:

Westerly

Description:

Tarmacadam within

the historical Ty’n-

y-felin quarry

adjacent to the

Penmynydd Road

Construction

Compound.

Photo

No.

6

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

General site

conditions of field to

be used as

Penmynydd Road

Construction

Compound.

Page 17: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 9

North Wales Connection Project

1.5 LLANFECHELL WASTE WATER TREATMENT WORKS

PHOTOGRAPHIC LOG Llanfechell Waste Water Treatment Works

Photo

No.

1

Date:

23/03/17

Direction Photo

Taken:

North-westerly

Description:

Llanfechell Water

Treatment Works.

OHL alignment is

located to the south

west of this feature

with proposed

access utilising

existing access

tracks. This site

was identified as an

active water

treatment works.

Photo

No.

2

Date:

23/03/17

Direction Photo

Taken:

Northerly

Description:

Note soft ground

conditions in

working area

adjacent to

Llanfechell Waste

Water Treatment

Works.

Page 18: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 10

North Wales Connection Project

Photo

No.

3

Date:

23/03/17

Direction Photo

Taken:

Easterly

Description:

Culvert possibly

associated with

water works.

Appears to be very

shallow with ground

heaped ontop.

Culvert runs

westwards from

water treatment

works.

Photo

No.

4

Date:

23/03/17

Direction Photo

Taken:

Northerly

Description:

Second manhole

cover in association

with culvert

potentially

associated with

water treatment

works.

Page 19: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 11

North Wales Connection Project

1.6 LOCAL AUTHORITY CONTAMINATED LAND FEATURES REFS 2148

AND 2162

PHOTOGRAPHIC LOG Local Authority Contaminated Land Features Refs

1248 and 2162

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

Small Depression

located within

centre of field

where this feature

is indicated to be

on the

corresponding map

figure. This may be

associated with the

former pit. Located

at 242462,387311

Page 20: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 12

North Wales Connection Project

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Northerly

Description:

Second Depression

located within

centre of field

where this feature

is indicated to be

on the

corresponding map

figure. This may be

associated with the

former pit. Located

at 242462,387311

Page 21: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 13

North Wales Connection Project

1.7 SURFACE WORKING FEATURES REFS 30, 194-328, 506 AND 687

(POND)

PHOTOGRAPHIC LOG Surface Working Features Refs 30, 194-328, 506 and

687 (Pond)

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

Historical mapping

showed a pond as

a surface working

feature within a

construction area.

This pond was

positively identified.

The ground

conditions were

extremely soft.

Page 22: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 14

North Wales Connection Project

1.8 SURFACE WOKING FEATURE (QUARRY) AT PYLON 4ZA078 (FIGURE

REFS 340, 772)

PHOTOGRAPHIC LOG Surface Working Feature (Quarry) at Pylon 4ZA078

(Figure Refs 340, 772)

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

North-easterly

Description:

General site

conditons at the

location of the

former quarry.

Extents are

potentially from the

vincinty of the the

pylon (left) to the

small rise in ground

level in the

background (right).

Page 23: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 15

North Wales Connection Project

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

North-easterly.

Description:

Evidence of

quarrying activity

within working area.

This is the small

rise in ground level

shown in the

previous

photograph.

Photo

No.

3

Date:

22/03/17

Direction Photo

Taken:

Northerly

Description: Former

quarry located on

the left of the first

photograph in this

series. It is

possible that this

quarry was more

extensive, if infilling

has occurred then it

has not been

recent.

Page 24: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 16

North Wales Connection Project

Photo

No.

4

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

General ground

conditons in the

field where the

former quarry is

located. The

ground shown was

extremely soft.

Photo

No.

5

Date:

22/03/17

Direction Photo

Taken:

Northerly

Description: Further

evidence of

quarrying activity at

location of former

quarry. Ground

conditions within

the area shown

were extremely

soft, it is possible

that some infilling

has occurred in this

location.

Page 25: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 17

North Wales Connection Project

1.9 FORMER PETROL STATION, STAR, ANGLESEY

PHOTOGRAPHIC LOG Former Petrol Station, Star, Anglesey

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

Westerly

Description:

The former petrol

station is now a

hand car wash and

is not deemed to

pose a risk to the

Proposed

Development.

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Southerly

Description: The

access track to the

working area is

located on the hard

standing shown

and progresses

round to the rear of

the furniture store

shown on the left of

the photo.

Page 26: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 18

North Wales Connection Project

Photo

No.

3

Date:

22/03/14

Direction Photo

Taken:

Easterly

Description:

Some minor fly

tipping had occured

behind the furniture

store where the

access track meets

the railway.

Page 27: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 19

North Wales Connection Project

1.10 FORMER PRIVATE WATER SUPPLY – DRYLL, AMLWCH

PHOTOGRAPHIC LOG Former Private Water Supply – Dryll

Photo

No.

1

Date:

22/03/1

7

Direction Photo

Taken:

Easterly

Description:

General ground

conditions where

private water

supply was

indicated to have

been.

Page 28: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 20

North Wales Connection Project

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Easterly

Description:

Scarification in

centre of photo is

where landowner

indicated the former

well was situated. It

was infilled at some

point during the

1950s.

Page 29: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 21

North Wales Connection Project

1.11 PRIVATE WATER SUPPLY – TYDDN FADOG

PHOTOGRAPHIC LOG private Water Supply Tyddn Fadog

Photo

No.

1

Date:

22/03/17

Direction Photo

Taken:

N/A

Description:

The spring feeding

the private water

supply arises and is

collected within this

sump and is fed to

the property with an

electric pump.

Page 30: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 22

North Wales Connection Project

Photo

No.

2

Date:

22/03/17

Direction Photo

Taken:

Southerly

Description:

Overflow arising

from the spring

flows into this

drainage ditch /

stream (centre of

photograph)

Page 31: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 23

North Wales Connection Project

1.12 PRIVATE WATER SUPPLY – MAEN ERYR

PHOTOGRAPHIC LOG Private Water Supply Maen Eryr

Photo

No.

1

Date:

23/03/17

Direction Photo

Taken:

North-easterly

Description:

Porcelain sink

covers borehole

well-head

Photo

No.

2

Date:

23/03/17

Direction Photo

Taken:

Westerly

Description:

Location of well at

property. Note

dilapidated pump

house. Whilst the

well is not currently

in use the owner

indicated that it is

possible that it

could be utilised in

the future.

Page 32: National Infrastructure Planning - 5.11.2 · 2018. 9. 11. · Application Reference EN020015 September 2018 T 5.11.2.5 Walkover Survey Chapter 11 – Appendix 5 National Grid (North

Environmental Statement Appendix 11.5 Walkover Survey Document 5.11.2.5 Page 24

North Wales Connection Project

Photo

No.

3

Date:

23/03/17

Direction Photo

Taken:

Southerly

Description:

Porcelain sink

(background

centre) coveres

another borehole

well-head. The

borheoles feed into

the two black water

tanks(background

right)