national human settlements indaba: n2 gateway project, … cape... · 2014-10-20 · •kanana...
TRANSCRIPT
NATIONAL HUMAN SETTLEMENTS INDABA:
N2 Gateway Project, Cape Town
Western Cape Human Settlements Minister Bonginkosi Madikizela
16 - 17 October 2014
Presentation Structure
Partners
Background
Planned Housing units
Target Areas
Units Completed to date
Total Spent
Project Funded
Stakeholder Scope
Challenges
EPWP Programme
Lessons learnt
N2 Gateway Partners
N2 Gateway Contractors
Background
The N2 Gateway Project was approved by National Cabinet on
18 August 2004 as a pilot and lead project in the “Breaking New
Ground (BNG)” strategy.
With the dawn of the new housing strategy in 2004 – “BNG” – the
N2 Gateway Project was conceived as a pilot geared to deliver
housing opportunities with the attendant social facilities and
amenities.
This was to be achieved in two phases – currently still in phase 1.
Planned Housing Units
The project intends to provide housing units for residents of the
informal settlements along the N2 Freeway.
The basic essence was that 22’000 housing opportunities across
the subsidy ranges were envisaged.
Target Areas
Phase 1: Total planned housing units = 16’083
DELFT SYMPHONY
(Phases 1-6)
6139 units
DELFT
(Phases 7-9, 601)
4491units
JOE SLOVO
(Phase 1 - Langa)
705 units
(Phase 2 - Langa)
49 units
(Phase 3 - Langa)
2639 units
BOYSTOWN
(Crossroads)
1392
NEW REST
668
Joe Slovo: Phase 3
After
Before
Joe Slovo: Phase 3
Under construction
Completed units
Boystown, Crossroads
Before
After
Delft 3 &5: Alternative Building Technologies (ABT)
Before
After
Delft 3 &5: Alternative Building Technologies (ABT)
Under construction
Completed units
N2 Phase 2 Project: Target Areas
PHASE 2
Site 1 Site 2 Site 3
• Eerste River:
Penhill• Gxagxa
• Kanana• Barcelona
• Europe
• Vukuzenzele
• Lusaka
• Kosovo
N2 Informal Settlements
N2 PHASE 2: Prospective Beneficiary Communities
Cape Town N2 Informal Settlements & Relocation Sites
Target Areas
The land was identified and contractually given to the Province
for development by the City of Cape Town – reference to LAA.
The N2 Gateway project comprises a number of individual land
components that are not adjacent to each other – that have
been developed as a human settlement project with the inter–
correlation being the relocation to accommodate informal
settlement and backyarders of various communities spread
across the Cape Town metro area.
Continued …
N2 Phase 1 Project: Units Completed To Date
Planned 16 083
Handed over 11 437
In-progress 4 646
N2 Phase 1 Project: Total Spent and Funding
Total Spent
- R1 913 262 572 (R,9 Bn)
Project Funded
- NDoHS: 100% funding of housing subsidies
STAKEHOLDER ROLE PROGRAMME IMPACT
National Department of
Housing
Programme
Sponsor/Chairperson
Funding of Housing Subsidies
Government of Western
Cape
Developer Funding (Top structures and
Internal Services)
Development of bulk services
infrastructure
Development of Top structure
HDA Programme-Project
Manager
Project and Beneficiary
Management as the Agent of the
Province.
NHBRC Homebuilders Regulator Project Enrolment
Quality assurance on built top
structures
DEADP Electrification Funder Electrified Human Settlements.
Implementing Agents
(Contractors)
Construction Construction of infrastructure and
top structure to meet minimum
specifications and requirements.
Community/Interest
Groups
Beneficiaries 100% Community and interest
groups buy-in
Stakeholder Scope
Challenges
Interference by anti –development factions.
Resistance of community to relocate out of construction areas.
Numbers of units available are less than the number of qualifiers.
Identification of additional greenfield land for development.
Ensuring the all parties from the community actively participate in
the development processes.
Relocation of non-qualifiers and excess qualifiers.
Non-qualifiers rejecting relocation to the temporaryaccommodation.
Excess people in projects refusing to relocate out of construction
areas.
Expanded Public Works Programmes (EPWP)
YEAR TARGET WORK OPPORTUNITIES
2012/13 2200 2375
2013/14 248 1181
Lessons Learnt
The interaction with community members and community
structures was clearly the biggest lesson leant on the N2
Gateway. Communities are to be viewed as sophisticated and
well versed within their structures.
Strong political will on the part of government is an essential
cornerstone for informal settlement upgrading, which must be
matched by an equally strong buy-in on the part of
communities
Continued …
Lessons Learnt
Alignment of the 3 spheres of government is critical from the
beginning.
Relationship between partners should be underpinned by
agreements that clearly define different roles, including
accountability.
The identification and securing of sufficient land should be
finalised prior to construction.
Continued …
Lessons Learnt
It is critical to ensure that the funding streams are secured prior
to implementation.
Concluding the selection of beneficiaries is critical before
embarking on construction.
In order to achieve sustainable human settlements, it is
imperative to have reliable and current information about the
community.
Continued …
Lessons Learnt
There is value in building the capacity of the communities in the
engagement process, so as to not only nurture their skills of the
engagement, but also to understand the technical issues.
In-situ upgrading is preferred to relocation in recognition of
social and economic dynamics – the economic and social
disruption costs are high.
There is an inherent paradigm shift from building of single familydwellings towards higher densities as a means to minimize
relocation.
Continued …
Lessons Learnt
Informal settlement does not mean uniform housing products –
communities rarely have homogeneous housing needs. The
diverse vested interests have to be accommodated.
The housing needs of tenants (as secondary beneficiaries) have
to be balanced against those of landlords (as primary
beneficiaries) within a striving rental market.
Thank you