national highways authority of indianhai.org.in/spw/process/m_p_r february15.pdfnational highways...
TRANSCRIPT
NATIONAL HIGHWAYS AUTHORITY OF INDIA
(MINISTRY OF ROAD TRANSPORT & HIGHWAYS)
GOVERNMENT OF INDIA
Four - Laning of Panvel - Indapur Section
Of NH-17 (Presently, NH-66) From Km 0.000 to 84.000 In The State Of Maharashtra
(Package No: NHDP - III/DL4/05)
Monthly Progress Report No - 37
February 2015
Yongma Engineering Co., Ltd.
Feedback Infra Private Limited.
In Association with
Panvel - Indapur MPR No-37 February ‘15 Page 1
TABLE OF CONTENTS
Page
Executive Summary 03
1.0 THE PROJECT 10
1.1 Project Background 10
1.2 Project Location 10
1.3 Terrain and Alignment 12
1.4 Salient Features 12
1.5 Project Milestones 28
1.6 Location Map 28
2.0 THE ESTABLISHMENT 31
2.1 Project Organisation 31
2.2 Plant & Machinery 35
3.0 PROGRESS OF WORKS 38
3.1 Land Handing Over 38
3.2 Tree Cutting 39
3.3 Utility Shifting 39
3.4 Design Review 40
3.5 Progress of Major Works 42
3.6 Miscellaneous Works 44
3.7 Status of Project Facilities 44
3.8 Overall Physical / Financial Progress 44
4.0 QUALITY CONTROL & QUALITY ASSURANCE 53
4.1 Quality Control & Quality Assurance 53
4.2 Compliance / Non-Compliance 53
4.3 Routine Inspection by Independent Engineer 53
5.0 TRAFFIC & SAFETY 82
5.1 Safety Issues 82
5.2 Accident Data 82
5.3 Maintenance of Existing Highway 82
6.0 CONTRACTUAL ISSUES 84
6.1 Changes of Scope 84
6.2 Project Milestones 86
6.3 Land Acquisition issue between Balganga and Balivali Bridges 89
6.4 Un-approved Steel in use 90
6.5 Non construction of Exit/Entry Ramps 90
7.0 CRITICAL ISSUES AND RECOMMENDATIONS 91
8.0 PROJECT PHOTOGRAPHS 97
Panvel - Indapur MPR No-37 February ‘15 Page 2
Appendices Page
A Comments on Concessionaire’s Monthly Progress Report 98
B Weather 99
C Important Visits 100
D Minutes of Progress Review Meeting 101
E Site Inspection Notes by Independent Engineer 102
F Letters from NHAI to Independent Engineer 105
G Letters from Concessionaire to Independent Engineer 107
H Letters Issued by Independent Engineer 108
I Accident Data & Observation 112
J Highway - Progress 114
K Structures - Progress 115
L Status Of Vehicular Underpasses - Progress 135
M Status Of Pedestrian Underpasses - Progress 138
N Slab/Box Culverts - Progress 142
O Pipe Culverts - Progress 145
Panvel - Indapur MPR No-37 February ‘15 Page 3
Executive Summary
National Highways Authority of India (NHAI) has entrusted the work of design,
construction, development, finance, operation and maintenance of Four-Laning of the
Panvel - Indapur section of NH-17 (Presently, NH-66) in the state of Maharashtra under
NHDP phase - III on DBFOT basis (Package No : NHDP-III/DL4/05) to the Concessionaire
Supreme Panvel-Indapur Tollways Pvt. Ltd. (SPITPL). Concessionaire has deployed two EPC
Contractors for the construction of the Project (M/s Mahavir Roads and Infrastructure Pvt.
Ltd. and M/s Supreme Infrastructure India Limited). M/s Yongma Engineering Co., Ltd. in
association with M/s Feedback Infra Private Limited has been appointed as the Independent
Engineer [IE] for the Project.
The Project stretch runs in plain and short stretch of hilly terrain. The Project includes
6 nos. Major Bridges, 23 nos. Minor Bridges, 2 nos. Flyovers, 3 nos. ROB’s, 11 nos.
Vehicular Underpasses, 15 nos. Pedestrian/Cattle Underpasses, 135+1 nos. Box/Slab
Culverts, 208+20 Pipe Culverts and 2 nos. Toll Plaza’s. The length of service road on LHS is
19.79 Km at on RHS is 17.76 Km totaling to 37.55 Km. and mostly located at urban areas of
the Project highway. The Panvel - Indapur section passes through the towns of Pen,
Vadkhal, Nagothane, Kolad and ends at km 84 before Indapur town.
Concession Agreement was signed on 21-01-2011 and the Appointed Date was 19-12-2011.
The scheduled date of completion of construction was 16-06-2014 (with 910 days
construction period).
Shifting of electrical poles, lines and MJP water pipeline are very slow. Shifting of ISPAT
water pipe line is still in progress. NHAI has given approval for laying CIDCO water pipeline
along the Project Highway. CIDCO has procured pipes and started laying pipes.
The quantities and percentage progress reported earlier by Concessionaire are on higher
side. Also, the lengths of highway works reported are more than actual lengths completed
at site. Independent Engineer approximately estimated the progress details. Now, as the
new construction programme alongwith Extension of Time (EOT) request by Concessioniare
is approved by NHAI Executive Committee, the progress details are evaluated based on the
scheduled progress given thereof. Though the scheduled construction period is over by 16-
06-’14, the cumulative achieved Physical Progress is 34.86 % as against Scheduled Physical
Progress of 39.89 %. That means, the slip is 5.03 %. The cumulative achieved Financial
Progress is Rs. 425.62 Crores (35.30%) as against scheduled Financial Progress of Rs.
482.83 Crores (40.04 %). That means, the slip is Rs. 57.21 Crores (4.74%).
Land Acquisition: Total land to be acquired is approximately 504 Ha. As per the
Concession Agreement, NHAI shall make best efforts to procure and grant, no later than 90
days from the Appointed Date, the Right of Way to the Concessionaire in respect of all land
included in the Appendix. NHAI may speed up balance land acquisition process.
Forest Land: Approval of Forest land except Ch. 0+000 to 20+100 issued by NHAI vide
letter No. NHAI/PIU/PANVEL/PI/SPITPL/ Forest/2013/1201 dt.23-08-’13. The portion from
Panvel - Indapur MPR No-37 February ‘15 Page 4
Ch 0+000 to 20+100 comes under Eco-sensitive zone. Approval for non core area (length
16.6 km) of Eco-Sensitive Zone has been obtained. However, PCCF Maharashtra has asked
to obtain NGT approval. Proposal for obtaining NBWL approval for core area (3.5 Km) has
been resubmitted to NBWL for reconsideration. Additional land of 1.3 Ha affecting 300m
length in Sukheli Khind need to be approved by MoEF.
No Progress of RE Wall Works: The construction RE wall started long back and now
completely stopped. This is major critical activity of the Project.
Non-Removal of Encumbrances : NHAI has issued notice under section 26 of the
Control of National Highways (Land and Traffic) Act, 2002 to unauthorized occupants in
some of the villages. Police support is sought. Most of the encroachments in Kollad, Pui,
Khamb, Varas gaon villages are removed. However, some buildings are yet to be removed
in other villages for want of payment, valuation etc. Concessionaire has not submitted the
programme for encroachment removal/building removal in spite of several reminders.
Concession Agreement, Clause 5.1.4 (e) specifies that “Concessionaire should make
reasonable efforts to facilitate the acquisition Concession Agreement, Clause 5.1.4 (e)
specifies that “Concessionaire should make reasonable efforts to facilitate the acquisition of
land required for the purpose of the Agreement”. Also, Concession Agreement, Clause 4.1.4
specifies that “Each party shall make all reasonable endeavors to satisfy the conditions
precedent within the time stipulated and shall provide the other party with such reasonable
cooperation as may be required to assist that party in satisfying the conditions precedent
for which that party is responsible”.
Very Slow Progress of Structures: The progress of structures (especially, major
bridges, flyovers and ROB’s) is very slow. Concessionaire should improve the progress of
structures. Overall progress is only 35%. Out of the total 26 underpasses not even single
underpass structure and its approaches completed so far.
Decision on Change of Scope Proposals: Concessionaire has submitted many Change
of Scope proposals. Some of them are still pending with NHAI for decision. Our records
show that Concessionaire has not submitted necessary clarifications /details for the following
Changes of Scope in spite of several reminders:
Sl No
Description of Change of Scope
Status
1 Deletion of Palaspe Flyover at Ch. 0+260
Approved in principle by NHAI. Concessionaire has not submitted detailed quantities in proper order so far.
2 Nallah diversion through box culvert at Ch. 4+900 to 4+993
Clarifications are yet to be submitted by Concessionaire.
3 Deletion of pipe culvert at Ch. 22+798
Concessionaire is advised to submit clarifications.
4 VUP at 23+450 (Hamarapur) on RHS main carriageway.
Proposal to be modified by Concessionaire considering that the additional VUP (as envisaged in CA) to be constructed at this location. Concessionaire is advised to submit details.
Panvel - Indapur MPR No-37 February ‘15 Page 5
Sl No
Description of Change of Scope
Status
5 Underpasses in Pen City Approved in principle by NHAI. Concessionaire has not submitted detailed quantities so far.
6 Additional Culverts at various locations
Approved in principle by NHAI. Concessionaire has not submitted detailed quantities so far.
7 Exit/Entry Ramps at Start and End of Service road
Compliance to the observations not yet submitted.
Distress in new pavement: The newly laid DBM/BC is showing distress at many
locations. Concessionaire is advised to investigate in detail regarding such re-occurrence of
pavement distress during construction. Independent Engineer has insisted Concessionaire
to follow good engineering practices during pavement construction. It has been reminded
many times the importance of constructing kerb before taking up bituminous works, use of
PTR for DBM layer, constructing median drain and chutes, proper drainage arrangements
during construction, temperature control etc.
Un-approved Steel in use: Conditional Source approval for steel from M/s Shree
Vaishnav Alloys Pvt. Ltd was concurred on 01-05-’12 based on the condition that the
challans for billets (from main and major producers) and Manufacturer Test Certificate
(MTC) will be submitted. Meanwhile, NHAI informed that the steel shall be procured from
main and major producers only as per IRC: SP: 84-2009 which are SAIL, IRNL, TATA,
ESSAR, ISPAT, JSW Steel Ltd and JSL. No re- rolled steel shall be permitted in NHAI works.
In some of the minor bridges, Concessionaire has used Sangam TMT, SUN TMT etc. also
which were notified to the Concessionaire through various NCR’s, Site Inspection Reports.
Concessionaire was strictly advised to use steel produced from main and major producers
only as per NHAI’s circulars. The source approval for M/s Shree Vaishnav Alloys Pvt. Ltd.
was withdrawn with affect from 25-07-’13. Even after withdrawing concurrence,
Concessionaire has been using un-approved steel in many structures. Engineer has issued
letter to Concessionaire warning them that IE will be constrained to initiate necessary
punitive action as per the provisions of Concession Agreement without any further notice.
Project Milestones
The statues of various project milestones are given below:
Milestone Description Scheduled
Date Progress
Requirements Status
Milestone-I First anniversary of the Appointed Date
19-12-2012
Physical Progress : Not less than 25%
Expended Cost : Not less than 25% of total capital cost
Milestone - I was achieved on 01-05-’13. (That is during Extension of Time period). However, EOT is recently approved by the Executive Committee of NHAI.
Milestone-II
Second anniversary of the Appointed Date
19-12-2013
Physical Progress : Not less than 65%
Expended Cost : Not less than 65% of total
Concessionaire vide their letter no SPITPL/ P-NHAI/ 2003-14/ 2471 dt. 28-01-’14 claimed and informed NHAI that they have achieved Milestone-II
Panvel - Indapur MPR No-37 February ‘15 Page 6
Milestone Description Scheduled
Date Progress
Requirements Status
capital cost considering the available land. Recently, Executive Committee of NHAI has given Extension of Time (EOT) for achievement of Milestone-II upto 31-10-2015.
Four Laning (Project Completion)
910th day from the Appointed Date
16-06-2014 Four Lane completion in accordance with Concession Agreement
Concessionaire has not achieved Four Laning (Project completion) by scheduled date. Concessionaire has submitted request for Extension of Time (EOT) for Four - Laning upto November 2016. Executive Committee of NHAI has given approval for Extension of Time (EOT) upto 31-03-2016 (except eco-sensitive zone).
Very Slow Progress of Works:
(a) In spite of prevailing good working season, absolutely no work is in progress in both sections.
It appears that the works are held up for want of fund cement, bitumen, diesel, manpower,
machinery, and other resources. The physical progress during August ’14 to February ‘15 are
0.01%, 0.04%, 0.03%, 0.02%, 0.0%, 0.00% and 0.02% respectively. The length of highway
works completed(m) during these months are given below:
Description Aug.’ 14 Sept. ’14 Oct. ’14 Nov. ’14 Dec. ’14 Jan.’15 Feb. ‘15
Clearing & Grubbing 0 0 0 0 0 310 0
Embankment 0 0 0 0 0 350 160
Subgrade 0 0 0 288 0 260 240
Granular Sub base (GSB) 0 0 0 30 0 70 250
Wet Mix Macadam (WMM) 0 0 0 0 0 0 0
Dense Bituminous Macadam (DBM)
0 0 60 0 0 0 0
Bituminous Concrete (BC) 0 0 0 0 0 0 0
(b) It has also been observed that at following underpass locations works can start/continue:
Sl No Chainage Description Concessionaire’s Comments Our Comments
1 25+860
Khopoli VUP
Panvel
approach
CIDCO pipeline is the major
hurdle: CIDCO pipeline on LHS is
not yet removed by the
authority. There is still land
acquisition problem which is not
sorted out in totally.
CIDCO pipeline will not
affect approach
construction. There is
absolutely no problem
to construct the
approaches.
2 30+930 Wadkhal
VUP Indapur
Land problem and the continuous
stretch of land is not available for
There is no problem in
constructing the
Panvel - Indapur MPR No-37 February ‘15 Page 7
(c) The works for Rest area, busbays, truck laybyes etc. are not yet started.
(d) Independent Engineer’s review on the progress of work on highway alongwith land availability
shows that at following locations, highway works should have been in progress.
Sl No
Chainage Side
Length (Km)
Remarks From To
1 0+400 1+000 B/S 600 BC can be done after rectification of distressed DBM 2 1+500 4+300 B/S 2,800 BC can be done after rectification of distressed DBM 3 5+500 6+800 B/S 1,300 BC can be done after rectification of distressed DBM 4 21+300 23+500 RHS 2,200 BC can be done after rectification of distressed DBM 5 22+950 23+350 LHS 400 Slow Progress 6 31+000 31+600 B/S 600 Work yet to be started 7 40+100 41+900 B/S 1,800 BC can be done after rectification of distressed DBM 8 51+500 51+900 LHS 400 WMM work still not completed 9 59+400 60+300 LHS 900 No work 10 59+700 59+900 RHS 200 Earthwork is not completed 11 60+800 61+700 LHS 900 No work 12 62+400 63+100 LHS 700 No work 13 63+900 65+900 LHS 2,000 Work is slow progress 14 70+000 72+300 LHS 2,300 No work 15 74+800 76+200 RHS 1,400 Work is slow progress 16 76+550 76+850 LHS 300 No work 17 77+000 77+700 RHS 700 No work 18 81+500 82+600 LHS 1,100 No work
approach construction activity. approaches.
3 49+280
Koleti PUP
approaches
both ends
Award passed, no payment made
to land owners. Land problem to
be dealt by NHAI.
Service road can be
constructed on LHS and
accordingly approaches
can be constructed.
4 50+845
Palas PUP
approaches
on both ends
Verification of land required from
Dy. SLR for confirmation of
encroachment of private land.
The Vaishali Hotel owner
allowing any construction
activity.
There is no problem in
constructing service
road on LHS and thus
constructing the
approaches.
5 54+450 Nagothane
VUP
Govt. land/court matter & the
embankment toe is going
Railway land (ROW) on LHS.
Matter needs to be sorted for
starting the construction activity.
There is no problem for
constructing RHS
service road and the
approaches.
6 68+320 Khmab PUP
Still there are 9 structures on site
which not in vacant position,
continuous stretch of land is not
RE wall.
Concessionaire should
proactively support for
encroachment removal
if any.
7 79+140 Ratwad PUP
No payment made to land
owners. Land owners are not
allowing for work, land problem
to be solved by NHAI.
There is no problem in
constructing the
approaches.
Panvel - Indapur MPR No-37 February ‘15 Page 8
Sl No
Chainage Side
Length (Km)
Remarks From To
19 81+200 82+400 RHS 1,200 GSB work is not completed 20 81+500 82+600 LHS 1,100 No work
Total 22,900
The above details show that in spite of sufficient work fronts available the Concessionaire could
not achieve better progress due to lack of various resources such as fund, machinery, diesel,
manpower etc.
Non - Maintenance of The Project Highway : It has been observed that at many locations
(most of them are in new carriageway) many Potholes/Patchwork are not yet repaired in spite
of continuous follow up with Concessionaire. Non-maintenance of the highway is leading to lot
of criticism by the road users, administration and print media. Non-maintenance of the highway
will have to be considered as default of obligations by the Concessionaire as per the terms of
Concession Agreement. Detailed list of such maintenance issues were informed to the
Concessionaire.
Many Pending Designs and Drawings: Many design and drawings for highway and
structures are still pending with Concessionaire. An updated list was issued to
Concessionaire vide letter no. PIP/IE/SPITPL/2014/2806 dt. 04-12-’14. In spite of several
reminders no action is taken by Concessionaire for last nine months.
Non - Closure Of NCR’s, Site Inspection Reports, Audit Reports: Concessionaire
has not closed out many NCR’s Site Inspection Reports / Audit Reports in spite of several
reminders. Non-closure of such NCR’s/Site Inspection Report/Audit Reports/ letters on
quality issues etc. is of major quality concern and will lead to contractual complications.
Insufficient Resources: Concessionaire has not mobilised sufficient resources such as
fund manpower, machinery, plant etc. Resources mobilised are very less. Construction
works were held up many times for want of fund, cement, bitumen, diesel, manpower,
machinery and other resources etc.
Crusher Production in Section - II : It has been observed that crusher production in
Section - II is very less and will not cater for requirement and this has been reported to
Concessionaire vide letter no. PIP/IE/SPITPL/2014/2773 dt. 21-11-’14. Most of the time,
the crusher is break down.
Status of ROB Approvals: The following is the status of approval of ROB’s:
Sl No
Chainage (Km)
Location Status
1 16+062 Kharpada
(1) GAD (General Arrangement Drawing) - Approved by
Railways.
(2) SAD (Structure Arrangement Drawing) - Done
(3) TAD (Temporary Arrangement Drawing) - Done
(4) CRS (Commissioner Railway Safety) - Sanction Obtained
(5) P & E charges deposited by NHAI
Panvel - Indapur MPR No-37 February ‘15 Page 9
Sl No
Chainage (Km)
Location Status
(6) Codal charges not paid by Concessionaire.
(7) MoU executed.
2 28+283 Pen
(1) GAD (General Arrangement Drawing) - Approved by
Railways.
(2) SAD (Structure Arrangement Drawing) - Done
(3) TAD (Temporary Arrangement Drawing) - Done
(4) CRS (Commissioner Railway Safety) - Sanction Obtained
(5) P & E charges deposited by NHAI
(6) Codal charges not paid by Concessionaire.
(7) MoU executed.
3 33+877 Wadkhal Bypass
(1) GAD (General Arrangement Drawing) - Approved by
Railways.
(2) SAD (Structure Arrangement Drawing) - Not Submitted
(3) TAD (Temporary Arrangement Drawing) - Not Submitted
to Railways
(4) CRS (Commissioner Railway Safety) - Sanction not
Obtained
(5) Codal charges not paid by Concessionaire
(6) MoU executed.
Details of Utility Shifting:
Sl No
Description Total Length
(m) Status
A CIDCO Water Pipe Lines 5080 m In-principle approval given for shifting. Shifting works already started. This is affecting 2.0 Km length of main carriageway.
B Reliance / NOCIL Gas Pipeline 690 m
The exact location of pipeline identified. Concessionaire has to submit proposal by modifying the piers P11 (L), P12 (L), P13 (L) and P15 (R). The abutment A1 may be converted to pier and retaining wall type. The 4” pipe which comes in embankment portion may be encased by utility owner.
C
MSEDCL Electrical Lines & Poles (17 DTC Transformers, 665 HT Poles, 841 LT Poles, 96 HT Crossings, 138 LT Crossings and 3 river crossings)
4,850m LHS
21,050m RHS
Very slow progress. Out of total 237 crossings, only 3 nos. crossings done so far.
D MJP Water Pipeline (200 to 450 mm Ø Water line)
19,840m LHS
4,180m RHS
Shifting works in very slow progress. Pipe laid for 7 Km only out of total length of 23.5 Km. The MJP officials have many times shown their protest against such slow progress by the Concessionaire.
E ISPAT Water Pipeline 21,670m LHS
70m RHS
Shifting works in progress. 4.1 Km length shifting completed.
F ZP water pipeline 5,090m LHS
4,030m RHS Slow progress in shifting.
Panvel - Indapur MPR No-37 February ‘15 Page 10
1.0 THE PROJECT
1.1 Project Background
The National Highway Authority of India (NHAI) has decided to take up the
development of various National Highways Stretches / Corridors under the National
Highways Development Programme (NHDP). NHAI had accordingly invited proposals by
its Notice Request for Qualification No. NHAI/NHDP-III/MAHA/BOT/PI dated 29-01-
2010 (the "Request for Qualification" or "RFQ") for short listing of bidders for
construction, operation and maintenance of the of NH-17 (Presently, NH-66) on DBFOT
basis and had shortlisted certain bidders including, the consortium comprising M/s
Supreme Infrastructure India Ltd., M/s China State Construction Engineering (Hong
Kong) Ltd. and M/s Mahavir Roads and Infrastructures Private Ltd. with M/s Supreme
Infrastructure India Ltd. as its Lead Member. Further, NHAI had accepted the bid of
the Consortium and issued its Letter of Award No. NHAI/BOT-I/11012/62/2005/14902
dated 28-10-2010 to the Consortium. On 21-01-2011, NHAI entered into agreement
with Consortium “Supreme Panvel Indapur Tollways Private Limited (SPITPL)” as
Concessionaire, a company incorporated under the provisions of the Companies Act,
1956 and having its registered office at Supreme City, Hiranandani Complex, Powai,
Mumbai - 400076, Maharashtra, India, for execution of the Project on DBFOT basis.
Thus, National Highways Authority of India (NHAI) has entrusted the work of design,
construction, development, finance, operation and maintenance of Four-Laning of the
Panvel - Indapur section of NH-17 (Presently, NH-66) sin the state of Maharashtra
under NHDP phase - III on DBFOT basis (Package No : NHDP-III/DL4/05) to the
Concessionaire M/s Supreme Panvel-Indapur Tollways Pvt. Ltd. (SPITPL).
Concessionaire has deployed two EPC Contractors for the construction of the Project.
M/s Yongma Engineering Co., Ltd. in association with M/s Feedback Infra Private
Limited has been appointed as the Independent Engineer [IE] for the Project.
The Project is having 84.6 Km length, located in the state of Maharashtra passing along
and adjacent to the Arabian Sea coast. The Project basically constitute upgradation
involving construction of 4-lanes highway including bridges, widening and rehabilitation
of existing bridges and culverts, elevated structures, ROB’s, wayside amenities,
realignment, bypasses etc. The Project forms part of the National Highway
Development Project (NHDP Phase-III) Programme.
1.2 Project Location The Panvel - Indapur section of NH-17 (Presently, NH-66) is located in the district of
Raigarh, which in turn is located in the State of Maharashtra. The State lies in the
western part of the Indian peninsula and is surrounded by the States of Gujarat,
Madhya Pradesh, Chhattisgarh, Andhra Pradesh and Karnataka.
Panvel - Indapur MPR No-37 February ‘15 Page 11
Maharashtra has an area of 307,690 sq. km with a population of 96,752,247 and
Mumbai is the state capital. The population density per sq. km is 314.44. It has a
literacy rate of 77.3 %, the second highest in the country, against the average Indian
scenario of 65.4 %. More than 900 educational institutions provide 1,69,000 technical
manpower each year and 30% share of new patents, setting the pace for innovation in
India. There are in all 35 districts in Maharashtra. Raigarh district is situated in the
western part of Maharashtra. Raigarh district is surrounded by Thane district in the
north; Pune district in the east; Ratnagiri district in the south; and the Arabian Sea in
the west. According to 2001 census, the population of Raigarh was 2,205,972 with
population density of 309 persons per Sq Km. The district, being a part of Konkan
region receives heavy rainfall during the monsoon.
The National Highway No-17 (Presently, NH-66) is on the west coast linking Panvel
(Maharashtra) and Cochin (Kerala). This section of the National Highway is heavily
trafficked by both passenger vehicles and freight transport vehicles. To meet the need
for road safety and development of the area, Government of India through the
National Highways Authority of India (NHAI) is implementing the Project of
strengthening and widening of the existing two-lane roadway to a four-lane dual
carriageway. Apart from the four laning, flyovers, vehicular underpasses, pedestrian
underpasses, service roads, highway traffic management systems and other road
safety measures will be provided in these sections. The concession period is 21 years
including construction period of 910 days (approximately 2.5 years). The
implementation of the Project will reduce the time and cost of travel for traffic plying
between Panvel and Indapur in the Raigarh district of Maharashtra State. It will also
add to the development of tourism in the State.
NH-17 (Presently, NH-66) mainly traverses through the west coast of India, sometimes
touching shores of Arabian Sea. This highway touches the Arabian Sea
at Maravanthe in Karnataka and Thalassery in Kerala. It passes through the States of
Maharashtra, Goa, Karnataka and Kerala.
NH-17 (Presently, NH-66) start from the junction with NH-4B near Panvel connecting
Indapur, Mahad, Rajapur, Kudal in Maharashtra, Panaji and Margoa in Goa, Karwar,
Honavar, Udupi, Mangalore in Karnataka, Kasaragod, Kannur, Ponnani, Edappalli etc.
NH-17 (Presently, NH-66) allows for movement of goods by trucks from hinterland to
major sea ports of India. The trade and commerce in the region has increased due to
expansion of markets for agricultural and sea food produced in the region connected
by this highway.
The Project stretch runs in plain and short stretch of hilly terrain. The Project includes
6 nos. Major Bridges, 23 nos. Minor Bridges, 2 nos. Flyovers, 3 nos. ROB’s, 11 nos
Vehicular Underpasses, 15 nos. Pedestrian / Cattle Underpasses, 136 nos. Box/Slab
Culverts, 228 Pipe Culverts and 2 nos. Toll Plaza’s. The length of service road on LHS is
19.79 Km at on RHS is 17.76 Km totalling to 37.55 Km. and mostly located at urban
areas of the Project highway. The Panvel - Indapur section passes through the towns
of Pen, Vadkhal, Nagothane, Kolad and ends at Km 84 before Indapur town.
Panvel - Indapur MPR No-37 February ‘15 Page 12
1.3 Terrain and Alignment
The Project passes primarily through plain & rolling terrain except for the two small
Ghat sections (Km 8 to 9 & Km 64 to 66) where the terrain can be classified as hilly.
The alignment is single carriageway comprising two lanes with width ranging from 7 m
to 10 m and earthen shoulder on either side. The alignment is generally straight with
reasonably large radii curves that are generally appropriate for high speeds except for
some sharp curves in the Karnala Bird Sanctuary portion and Sukheli Khind ghat
section. In these hilly stretches the alignment follows a winding path and several sharp
curves with limited sight distance are present. These curves need to be redesigned to
the extent possible within the available ROW and the overall visibility improved. In the
plain / rolling stretch the highway is not having any major cutting and filling whereas in
the Ghat areas some sections involve large to deep cuts. About 80 % of the Project
Highway runs on an embankment of 1.0 to 2.0 m height. However, significant
variations in heights of embankment are observed at low-lying fields and also at bridge
approaches.
The highway passes through rural agricultural areas and villages, such as Pen (Km
26+600 to 30+000), Wadkhal (Km 32+000 to 34+600), Nagothane (Km 53+000 to
56+200) and Kolad (Km 71+500 to 74+000). The adjoining land use is predominantly
barren with patches of agricultural land, forest and built-up locations. The highway
passes through several towns and many villages some of which have settlements in
close proximity of the highway.
The existing highway has a single two-lane carriageway with pavement width varying
from 10 m to 11.0 m and 1.0 m wide soft shoulder on either side till Km 33. Beyond
this, the width is 7.0 m with soft shoulders of 1.5 to 2.0 m, till the end of the Project.
The highway is on an embankment for most of the length except in Ghat areas from
Km 8 to 9 and Km 64 to 66 where it lies in cutting. The embankment height in general
varies between 1.0 to 5.0 m but there are several locations where it is less than 1m.
However, there is no history of submergence or overtopping of the pavement at these
locations. The depth of cutting in Ghat Sections varies between 1.0 to 10.0 m. The
pavement condition is found to be fair to good for the almost the entire length except
for the stretch from Km 20 to 25 and Km 40 to 42 where substantial raveling and
rutting is observed. The riding quality as such also varies from fair to quite good. Most
of these stretches have been overlaid recently by the Department.
No organised drainage system exists along the Project Highway. However, the highway
level is sufficiently raised and earthen drains have been constructed to drain the
surface water to the nearby culverts. At some locations, lined drains have also been
constructed adjacent to the shoulders. Local enquiries reveal that there is no history of
overtopping of the road at any location.
1.4 Salient Features
Contract data is given in Table 1.1. Salient features are given in Table 1.2.
Panvel - Indapur MPR No-37 February ‘15 Page 13
Table 1.1 Contract Data
Description Details
Name of Project
Design, Construction, Development, Finance, Operation and Maintenance of Four-Laning of Panvel-Indapur section of NH-17 from Km. 0+000 to 84+000 in the State of Maharashtra under NHDP Phase-III on DBFOT Basis.
Package No. NHDP-III/DL4/05
Source of Funding DBFOT Basis
Client/Employer National Highway Authority of India (NHAI), G-5 & 6, Sector 10, Dwaraka, New Delhi. PIN: 110 075
Concessionaire Supreme Panvel Indapur Tollways Private Limited, 9th Floor, (901-905), Millennium Tower B, Opp. IFFCO Chowk, Metro Station, M.G. Road, Gurgaon-122 002, Haryana-India.
Independent Engineer
Yongma Engineering Co., Ltd.
24, Dunchon-daero 388 beon-gil, Joongwon-Gu, Seongnam-
Si, Gyeonggi-Do (Sangdaewon-Dong, Woolim Lions Valley
3rd 12F), 462-819, KOREA
in association with
M/s Feedback Infra Private Limited.
15th Floor, Tower 9B, DLF Cyber City Phase-III, Gurgaon.
PIN : 122 002
Project Management Consultants
M/s Sowil Limited
EPC Contractors
Ch. 0+000 to 42+000: M/s Mahavir Roads and Infrastructure Pvt. Ltd, 5, Basement, Vasant Industrial Estate, Saki-Vihar Road, Sakinaka, Andheri (E), Mumbai.
Ch. 42+000 to 84+000: M/s Supreme Infrastructure India Limited, Supreme House, 94/C, Pratap Gad, Opp. IIT Main Gate, Powai, Mumbai - 400 076
Date Concession Agreement signed
21-01-2011
Development Period 21-01-2011 to 18-12-2011
Appointed Date 19-12-2011
Concession Period 21 years (19-12-2011 to 18-12-2032)
Letter of Acceptance NHAI/BOT-1/11012/62/2005/14902
Scheduled Construction Completion Date
16-06-2014 (910 days construction period)
Project Cost as per (Concession Agreement)
942.69 Rs. Crores
Project Cost (As Reported by Concessionaire)
1205.72 Rs. Crores
Annual Premium 33.95 Rs. Crores
Panvel - Indapur MPR No-37 February ‘15 Page 14
Table 1.2 Salient Features
Description Length/ Nos.
Length of the project 84 Km
Major Bridges 6 Nos.
Minor Bridges 23 Nos.
Slab/Box culverts 135+1 Locations
Pipe culverts 208+20 Locations
Flyovers 2 Nos.
ROB’s 3 Nos
Pedestrian Underpasses
15 nos.
[14 as per CA + 2 additional as per CA + 1 additional as per COS - 2 converted to VUP as
per COS]
Vehicular Underpasses
11 nos.
[7 as per CA + 2 additional as per CA + 2 converted to VUP as per COS]
Major Intersections 12 Nos.
Minor Intersections 94 Nos.
Main Line Toll Plaza 2 Nos (Design Chainage 15+000 & 66+775)
Busbays 52 Nos
Truck Layby 4 Nos (Design Chainage 3+145 LHS, 5+654 RHS, 62+749 LHS and 63+513 RHS)
Rest Area 1 No. (Design Chainage 60+300 RHS)
Panvel - Indapur MPR No-37 February ‘15 Page 15
Table 1.3 Details of Major Bridges
Sl. No.
CA Chainage
(Km)
Design Chainage
(Km)
Name of the River
Details of Existing Structures Details of the Proposed Structures
Type of Superstructu
re
No. of Spans x Span Length (m)
Width of bridge
(m) Remarks
Total Length
(m)
Width (m)
Remarks
1 15+480 15+878 Kharpada
RCC Girder (2 span x 27.0 ) +
10.90 To be retained with repair and rehabilitation.
12.00 (2 lane)
New Construction on
LHS side. Span over railway line to be finalised in consultation with railway authority.
PSC Girder (5 spans x 42.50 ) +
RCC Girder (10 spans x 27.80 ) +
RCC Girder (1 span x 14.41 ) + 817.755
PSC Girder (1 span x 38.20 ) +
RCC Girder (1 span x 21.987 ) +
RCC Girder (7 spans x 27.80 )
2 20+097 20+144 Balganga RCC Girder & deck slab
(1 span x 16.50 ) + (2 span x 21.50 ) + ( 1 span x 16.50 )
8.450 To be retained with repair and rehabilitation
76 12.00
(2 lane) New Construction on RHS side.
3 26+152 26+188 Bhogeshwari MS I - Girder & RCC Deck
(10 spans x 12.80 ) 7.850 Dismantling and reconstruction
128 2 x 12.00 (4 lane)
New Construction
4 44+119 44+155 Nigade RCC Girder &
deck slab
(1 span x 12.60 ) + (1 span x 12.20 ) + (1 span x 17.00 ) +
(3 spans x 19.50 ) + (1 span x 12.20 ) + (1 span x 12.60 )
8.100 To be retained with Repair and rehabilitation
125.1 12.00
(2 lane)
New Construction on
RHS side.
5 58+857 58+857 Amba CR Masonry arch deck
(9 spans x 10.65 ) 6.900 Existing bridge to be abandoned.
95.85 2 x 12.00 (4 lane)
New Construction.
6 72+876 72+936 Kundalika CR Masonry arch deck
(12 spans x 10.50 ) 6.70 To be retained with Widening.
126 12.00
(2 lane) New Construction on RHS side.
Panvel - Indapur MPR No-37 February ‘15 Page 16
Table 1.4 Details of Minor Bridges
Sl No
CA
Chainage (km)
Design Chainage
(Km)
Name of River
Details of Existing Structure Proposed Structure
Type of Superstructure
No. of Spans x Span Length
(m) Width (m) Remarks
Total Length
(m)
Width Of Bridge
(m) Remarks
1 0+544 0+544 Local Nallah RC Beam & Deck slab 3 spans x 6.70 12.90 Repair, Widening on both side.
20.10 27.50
(4 lane) Concentric widening of existing bridge.
2 9+363 9+363 Local Nallah RCC Solid Slab (40 skew )
2 spans x 7.10 11.10 Dismantling and New Construction.
18.00 25.00
(4 lane) New Construction.
3 20+780 20+754
RCC Solid Slab 4 spans x 6.80 13.00 Repair and rehabilitation. 27.20 12.00
(2 lane) New Construction on LHS side.
4 29+728 29+728 Vashi Nallah RCC Solid Slab 3 spans x 7.10 12.60 Repair and rehabilitation. 21.30 12.00
(2 lane) New Construction on LHS side.
5 30+557 30+557 Uchede Nallah
RCC Solid Slab (250 skew )
2 spans x 6.10 12.40 Widening with Repair and rehabilitation.
12.20 27.50
(4 lane) Concentric widening of existing bridge.
6 52+089 52+155 Nidi RCC Solid Slab (16.30 skew )
4 spans x 8.80 12.05 Repair and rehabilitation. 35.20 12.00
(2 lane) New Construction on RHS side.
7 57+926 57+997 Patansai
CR Masonry arch extended by RCC
solid slab on both side
4 spans x 4.00 12.00 Repair and rehabilitation. 16.00 12.00
(2 lane)
New Construction on
RHS side.
8 59+335 59+396 Canal Crossing
RCC Solid Slab 1 span x 10.70 8.50 Widening with repair and rehabilitation.
10.70 12.00 (2
lane) New Construction on RHS side.
9 59+797 59+848 Godsai CR Masonry arch extended by RCC solid slab
2 spans x 3.80 12.90 Repair and rehabilitation. 7.60 12.00
(2 lane) New Construction on RHS side.
10 62+285 62+133 Local Nallah RCC Solid Slab 2 spans x 4.60 13.00 Repair and rehabilitation. 9.20 12.00
(2 lane) New Construction on RHS side.
11 63+233 63+284 Canal Crossing
CR Masonry arch extended by RCC solid slab on both sides
2 spans x 3.70 12.00 Repair and rehabilitation. 7.40 12.00
(2 lane) New Construction on LHS side.
12 64+187 64+249 Canal Crossing
RCC Solid Slab 2 spans x 7.25 8.30 Widening with repair and rehabilitation.
14.50 12.00
(2 lane) New Construction on RHS side.
Panvel - Indapur MPR No-37 February ‘15 Page 17
Sl No
CA
Chainage (km)
Design Chainage
(Km)
Name of River
Details of Existing Structure Proposed Structure
Type of Superstructure
No. of Spans x Span Length
(m) Width (m) Remarks
Total Length
(m)
Width Of Bridge
(m) Remarks
13 66+683 66+742 Nandavali RCC solid slab 2 spans x 4.70 12.10 Repair and rehabilitation. 9.40 12.00
(2 lane) New Construction on RHS side.
14 67+043 67+099 Local Nallah RCC solid slab 2 spans x 4.60 12.05 Repair and rehabilitation. 9.20 12.00
(2 lane) New Construction on RHS side.
15 67+820 67+878 Irrigation Canal
RCC Solid Slab (510 skew )
(1 span x 9.95) + (1 span x
8.95) 7.70
Widening with repair and rehabilitation.
18.90 27.50
(4 lane) Concentric widening of existing bridge.
16 68+927 68+988 Local Nallah
CR Masonry arch extended by RCC solid slab on both sides
4 spans x 3.20 12.00 Repair and rehabilitation. 12.80 12.00
(2 lane) New Construction on LHS side.
17 69+081 69+140 Local Nallah RCC solid slab widened on both side
3 spans x 3.70 12.50 Repair and rehabilitation. 11.10 12.00
(2 lane) New Construction on RHS side.
18 72+196 72+250 Mahisdara Nallah
RCC I Girder (180 skew )
3 spans x 18.30 8.00 Repair and rehabilitation. 54.90 12.00
(2 lane) New Construction on RHS side.
19 73+290 73+350 Godi Masonry arch & RCC cantilever slab
(1 span x 7.70) + (3 spans x
7.00) + (1 span x 7.70)
13.65 Repair and rehabilitation. 36.40 12.00
(2 lane) New Construction on RHS side.
20 77+744 77+804 Bhuvan Nallah
CR Masonry arch
extended by RCC solid slab on both side
5 spans x 3.10 11.90 Repair and rehabilitation. 15.50 12.00
(2 lane) New Construction on RHS side.
21 81+606 81+660 Vave Nallah RCC Solid Slab 3 spans x 7.45 12.20 Repair and rehabilitation. 22.35 12.00
(2 lane) New Construction on RHS side.
22 83+861 83+920 Canal Crossing
RCC Solid Slab 1 span x 6.40 8.15 Widening with repair and rehabilitation.
6.40 12.00
(2 lane) New Construction on LHS side.
23 84+431 84+488 Indapur RCC Solid Slab 3 spans x 10.45 11.95 Repair and rehabilitation. 31.35 12.00
(2 lane) New Construction on RHS side.
Panvel - Indapur MPR No-37 February ‘15 Page 18
Table 1.5 Details of Flyovers
Sl No
CA
Chainage (Km)
Design Chainage
(Km Name of structure
Details Of Existing Structure Details Of Proposed Structure
Total Span Length
Width (m)
Remarks Total
Length (m)
Width (m) Remarks
1 0+250 0+250 Palaspe Junction Not Applicable 390 12.00
(2 lane) Proposed to be deleted
2 33+670 33+670 Wadkhal Bypass Not Applicable 1092 2 x 12.00 (4 lane)
Span over railway line to be decided in consultation with railway authorities.
Table 1.6 Details of ROB’s
Sl No
CA Chainage
(Km)
Design Chainage
(Km
Name of structure
Details Of Existing Structure Details of proposed structures
Type of Superstructure
Spans x Length
Width
(m) Remarks
Total Length
(m) Width Remarks
1 15+480 16+062 Kharpada PSC Girder and RCC deck slab
1 Span x 38.20 m
10.90 To be retained with repair and rehabilitation.
38.20 12.00 m (2 lane)
New Construction on LHS side.
2 28+283 28+283 Pen
MS Built-up ' I '
girder and RCC deck slab
2 Spans x 13.50 m
11.50 To be retained with repair and rehabilitation.
27.00 12.00 m (2 lane)
New Construction on LHS side.
3 33+670 33+877 Wadkhal Bypass
- - -
28.00 2 x 12.0 m
(4 lanes) New Construction
Table 1.7 Details of RUB’s
Sl
No
CA Chainage
(Km)
Design Chainage
(Km
Details of Existing Structure
Name of Structure
Type of Superstructure
No. X size of Openings
Remarks
1 33+860 33+877 Wadkhal Steel girders 1 X 24 Abandoned since bypass is proposed - Due to Wadkhal bypass not applicable
2 56+560 56+560 Nagothane Steel girders 1 X 24 Widening not required as opening size is sufficient to accommodate 4 lane highway.
3 73+250 73+250 Kolad PSC girder and RCC deck slab
3 X 26 Widening not required as opening size is sufficient to accommodate 4 lane highway.
Panvel - Indapur MPR No-37 February ‘15 Page 19
Table 1.8 Details of Service Road (LHS) - As per Concession Agreement
Sl No
From (Km) To (Km) Length (Km)
Location
1 0+950 2+260 1.31 Palaspe
2 4+650 5+380 0.73 Chinchwan
3 13+440 14+210 0.77 Tara
4 17+950 18+970 1.02 Jite
5 25+340 26+060 0.72 Pen
6 26+370 28+000 1.63 Pen
7 28+460 29+590 1.13 Pen
8 29+950 30+480 0.54 Uchede
9 31+300 31+680 0.38 Wadkhal
10 37+080 37+800 0.72 Gadab
11 41+350 42+860 1.51 Kasu, Pandapur, Patni
12 44+710 45+810 1.10 Nigade
13 49+000 49+500 0.50 Koleti
14 55+090 56+590 1.50 Nagothane
15 67+910 68+830 0.92 Khamb
16 73+400 75+450 2.05 Kolad
17 75+940 76+500 0.56 Talavali
Total 17.09
Table 1.9 Details of Service Road (RHS) - As per Concession Agreement
Sl No
From (Km) To (Km) Length (Km)
Location
1 0+920 2+260 1.34 Palaspe
2 4+650 5+380 0.73 Chinchwan
3 13+430 14+210 0.78 Tara
4 17+950 18+970 1.02 Jite
5 26+760 28+000 1.24 Pen
6 28+510 29+600 1.09 Pen
7 29+950 30+470 0.52 Uchede
8 31+300 31+630 0.33 Wadkhal
9 34+100 34+640 0.53 Wadkhal
10 37+080 37+800 0.72 Gadab
11 44+570 45+600 1.03 Nigade
12 49+000 49+500 0.50 Koleti
13 54+840 56+530 1.69 Nagothane
14 67+920 68+830 0.91 Khams
15 73+400 75+450 2.05 Kolad
16 75+940 76+500 0.56 Talavali
Total 15.04
In addition to above, Concession Agreement has provision for providing additional length
of 5.40 Km Service Road. However, as per Concessionaire’s design the following are the
details of Service Road:
Panvel - Indapur MPR No-37 February ‘15 Page 20
Table 1.10 Details of Service Road - LHS - As per Concessionaire’s Design
Sl No Location Chainage
Length (Km) Status From To
1 Palaspe 0+950 2+260 1.31 Concurred
2 Chinchwan 4+570 5+340 0.77 Concurred
3 Tara 13+470 14+400 0.93 Concurred
4 Jite 18+300 19+330 1.03 Concurred
5 Khopoli 25+330 26+050 0.72 Concurred
6 Pen 26+380 28+020 1.64 Concurred
7 Ramwadi 28+370 29+500 1.13 Concurred
8 Uchede 29+910 30+920 1.01 Concurred
9 Wadkhal 34+220 34+750 0.53 Not Submitted
10 Gadab 37+210 37+930 0.72 Concurred
11 Khapale 39+430 40+040 0.61 Not Submitted
12 Kasu 41+350 42+840 1.49 Concurred
13 Nigade 44+710 45+810 1.10 Concurred
14 Koleti 48+940 49+590 0.65 Concurred
15 Palas 50+490 51+220 0.73 Concurred
16 Nagothane 53+520 56+580 3.06 Concurred
17 Khamb 68+000 68+900 0.90 Concurred
18 Kolad 73+500 75+440 1.94 Concurred
19 Talavali 76+050 76+590 0.54 Concurred
Total (LHS) 20.81
Table 1.11 Details of Service Road - RHS - As per Concessionaire’s Design
Sl No
Location Chainage
Length (Km)
Status From To
1 Palaspe 0+920 2+260 1.34 Concurred
2 Chinchwan 4+570 5+340 0.77 Concurred
3 Tara 13+470 14+400 0.93 Concurreds
4 Jite 18+300 19+330 1.03 Concurred
5 Pen 26+780 28+020 1.24 Concurred
6 Ramwadi 28+370 29+460 1.09 Concurred
7 Uchede 29+900 30+940 1.04 Concurred
8 Wadkhal 34+300 34+750 0.45 Concurred
9 Gadab 37+210 37+930 0.72 Concurred
10 Nigade 44+570 45+600 1.03 Concurred
11 Koleti 48+940 49+590 0.65 Concurred
12 Palas 50+490 51+220 0.73 Concurred
13 Nagothane 53+520 56+530 3.01 Concurred
14 Khamb 68+000 68+900 0.90 Concurred
15 Kolad 73+500 75+455 1.95 Concurred
16 Talavali 76+050 76+590 0.54 Concurred
Total (RHS) 17.42
Panvel - Indapur MPR No-37 February ‘15 Page 21
Table 1.12 Details of Vehicular Underpasses as per Concession Agreement
Sl
No
Chainage (Km) Opening Size (m)
Width
(m) Village
Anticipated Type As per CA As per Design
1 4+992 5+000 2 x 12 x 5.5 24.0 Chinchwan RCC Solid slab
2 25+873 25+860 2 x 12 x 5.5 12.0 Khopoli Junction RCC Solid slab
3 28+040 27+760 2 x 12 x 5.5 24.0 Pen RCC Solid slab
4 31+660 30+930 1x 12 x 5.5 24.0 Wadkhal Bypass RCC Solid slab
5 32+465 32+485 1 x 6 x 5.0 24.0 Wadkhal Bypass RCC Solid slab
6 55+968 56+060 2 x 12 x 5.5 24.0 Nagothane RCC Solid slab
7 73+699 73+760 2 x 12 x 5.5 24.0 Kolad RCC Solid slab
Table 1.13 Details of Pedestrian / Cattle Crossing Underpasses as per Concession Agreement
Table 1.14 Details of Busbays as of now
Sl
No
Chainage (Km) Opening Size (m)
Width
(m) Village Anticipated Type
As per CA As per Design
1 1+219 1+230 6.0 x 3.5 24.0 Palaspe Box structure
2 13+796 13+788 6.0 x 3.5 24.0 Tara Box structure
3 18+229 18+700 6.0 x 3.5 24.0 Jite Box structure
4 27+136 27+100 6.0 x 3.5 24.0 Pen Box structure
5 28+550 28+535 6.0 x 3.5 24.0 Pen Box structure
6 30+276 30+270 6.0 x 3.5 24.0 Uchede Box structure
7 37+453 37+529 6.0 x 3.5 24.0 Gadab Box structure
8 42+075 42+155 6.0 x 3.5 24.0 Kasu Box structure
9 45+149 45+225 6.0 x 3.5 24.0 Nigade Box structure
10 49+280 49+280 6.0 x 3.5 24.0 Koleti Box structure
11 55+749 55+840 6.0 x 3.5 24.0 Nagothane Box structure
12 68+248 68+320 6.0 x 3.5 24.0 Khamb Box structure
13 76+250 76+315 6.0 x 3.5 24.0 Talavali Box structure
14 79+080 79+140 6.0 x 3.5 24.0 Ratvad Box structure
Sl No Chainage (Km)
Side Village As per CA As per Design
1 1+058 1+058 RHS Palaspe
2 1+140 1+140 LHS Palaspe
3 2+560 2+435 LHS Turmale
4 2+620 2+435 RHS Girwale
5 4+244 4+244 RHS Shirdon
6 4+415 4+244 LHS Shirdon
7 11+162 11+162 RHS Kolhe
8 11+406 11+406 LHS Kolhe
9 13+700 13+700 RHS Tara
10 13+902 13+902 LHS Tara
Panvel - Indapur MPR No-37 February ‘15 Page 22
11 14+599 14+599 RHS Kasarbhat
12 14+568 14+568 LHS Kasarbhat
13 16+666 16+512 RHS Kasarbhat
14 16+725 16+512 LHS Kasarbhat
15 18+271 18+550 RHS Kharpada
16 18+349 18+870 LHS Kharpada
17 26+003 25+450 LHS Chinchghar
18 26+003 25+492 RHS Chinchghar
19 28+610 28+610 RHS Pen
20 28+659 28+659 LHS Pen
21 29+495 29+300 RHS Pen
22 29+495 29+300 LHS Pen
23 30+250 30+090 RHS Pen
24 30+250 30+096 LHS Pen
25 37+700 37+700 LHS Gadab
26 37+951 37+700 RHS Gadab
27 39+414 39+617 RHS Gadab
28 39+418 40+133 LHS Gadab
29 42+137 41+845 RHS Kasu
30 42+152 42+245 LHS Kasu
31 44+342 44+354 RHS Salinde
32 44+364 44+402 LHS Salinde
33 45+046 45+092 RHS Nigdi
34 45+064 45+142 LHS Nigdi
35 48+903 48+972 RHS Koleti
36 49+129 49+200 LHS Koleti
37 61+324 61+387 RHS Kansai
38 61+368 61+437 LHS Kansai
39 63+200 63+388 LHS Sukeli
40 68+145 68+315 RHS Kharwali
41 68+265 68+315 LHS Kharwali
42 70+392 70+392 RHS Pugaon
43 70+407 70+407 LHS Pugaon
44 75+320 75+060 LHS Kolad Railway station
45 76+126 76+200 RHS Talavali
46 76+137 76+200 LHS Talavali
47 78+439 78+107 RHS Bhuvan
48 78+468 78+107 LHS Bhuvan
49 79+600 79+707 RHS Ghotwal
50 79+600 79+707 LHS Ghotwal
51 82+570 82+462 RHS Nagroli
52 84+330 84+222 RHS Potner
Panvel - Indapur MPR No-37 February ‘15 Page 23
Table 1.15 Details of Proposed Vehicular Underpasses as of now
Table 1.16 Details of Proposed Pedestrian / Cattle Crossing Underpasses as of now
Total number of Pipe Culverts: 208 + 20 Nos.
Total number of Slab Culverts: 135 + 1 Nos.
Table 1.17 Details of Proposed Bypass
Sl. No.
Village
As per Concession Agreement As per Approved Change of
Scope
Start Chainage
End Chainage
Length (Km)
Start Chainage
End Chainage
Length (Km)
1 Wadkhal 31+500 34+300 2.8 30+700 34+300 3.6
Sl No
Chainage (Km) Village Remarks As per
CA As per Design
1 4+992 5+000 Chinchwan VUP
2 23+460 23+460 Hamrapur VUP
3 25+873 25+873 Khopoli VUP- Half Portion
4 27+136 27+100 Pen PUP converted to VUP - approved in principle by NHAI
5 28+040 27+760 Pen VUP - Shifted to this Place - approved in principle by
NHAI
6 28+550 28+535 Pen/Ramwadi PUP converted to VUP - approved in principle by NHAI
7 31+660 30+930 Vadkhal VUP
8 32+465 32+485 Vadkhal VUP
9 - 54+450 Nagothane (SH-91) Additional VUP as per CA
10 55+968 56+060 Nagothane VUP
11 73+699 73+760 Roha/Kolad (SH-62) VUP
Sl No
Chainage (Km) Village Remarks
As per CA As per Design
1 1+219 1+230 Palaspe
2 13+796 13+625 Tara
3 18+229 18+700 Jite
4 - 27+420 Pen Change of Scope approved in principle by NHAI
5 30+276 30+112 Uchede
6 37+453 37+529 Gadab
7 39+740 39+743 Khapale Additional PUP as per CA
8 42+075 42+155 Kasu
9 45+149 45+225 Nigade
10 49+280 49+280 Koleti
11 50+845 50+845 Palas Additional PUP as per CA
12 55+749 55+840 Nagothane
13 68+248 68+320 Khamb
14 76+250 76+315 Talavali
15 79+080 79+140 Ratwad
Panvel - Indapur MPR No-37 February ‘15 Page 24
Table 1.18 Status of Design and Drawings of Major Junctions
Table 1.19 List of Minor Junctions.
Sl. No.
Chainage Km
Typ
e o
f
Cro
ssin
g
Destination
Details
As per CA As per Design
Left Right
1 1+140 1+200 T - Palaspe MDR
2 1+220 1+230 T Palaspe - MDR
3 1+490 1+500 T - Palaspe VR
4 2+550 2+600 T - Turmale VR
5 2+630 2+650 T Giravale - VR
6 3+330 3+350 T - Sangivali VR
7 4+340 4+350 T Shirdhon - VR
8 4+990 5+000 T Shirdhon - MDR
9 NA 9+100
10 11+310 11+315 T - Kolhe VR
11 12+020 12+000 Y - Bandarwadi VR
12 13+800 13+800 T Tara - MDR
13 16+540 - Y Kharpada - VR
14 18+230 18+240 Y Jite - MDR
15 19+040 19+450 T Tharoshi - VR
16 20+220 20+200 Y Durshet - MDR
17 21+100 21+100 T Balivali - VR
18 21+690 21+680 T - Kopsar VR
19 22+450 22+455 Y Ambivali - VR
Sl No
Chainage (Km)
Typ
e o
f
Cro
ssin
g
Destination
Details As per
CA As per Design
Left Right
1 0+250 0+250 + Pune Uran Flyover-NH Crossing
2 14+730 14+730 T Aapta Phata - At Grade improvement (SH-83)
3 25+870 25+850 T Khopoli - Vehicular Underpass (left
carriageway only) SH-87
4 27+730 27+730 + Pen City Pen Railway
station At Grade
5 33+670 33+746 T Alibaug Flyover (SH-87)
6 35+800 35+890 Y - At-grade improvement-ISPAT
Factory
7 54+380 54+450 T - At-grade improvement (SH-91)
8 55+970 56+040 Y Nagothane Vehicular Underpass
9 58+660 58+750 T Pali - At-grade improvement (SH-92)
10 58+960 59+025 T Alibaug At-grade improvement (SH-93)
11 73+700 73+760 T Roha Vehicular Underpass (SH-62)
12 74+730 74+800 T Pune - At-grade improvement
Panvel - Indapur MPR No-37 February ‘15 Page 25
Sl. No.
Chainage Km
Typ
e o
f
Cro
ssin
g
Destination
Details
As per CA As per Design
Left Right
20 23+470 23+440 T - Paramanandwadi VR
21 24+210 24+220 T - Virwadi MDR
22 25+280 25+290 T Tarankhop - VR
23 25+440 25+600 T Tarankhop - VR
24 27+080 27+100
Y - Pen VR
25 27+140 Y Pen - MDR
26 27+300 27+300 T Pen - VR
27 28+550 28+535 + Village Ramwadi VR
28 29+120 29+100 + Kitwane colony Umbrade VR
29 29+660 29+700 Y - Vashi MDR
30 30+270 30+100 T - Uchade VR
31 30+670 30+650 T Kandlepada - VR
32 31+360 - T - Kandle VR
33 32+650 32+500 + Wadkhal Wadkhal VR
34 31+590 34+680 T - Dolvi VR
35 36+480 36+570 T Karave - MDR
36 37+150 37+200 T - Gadab VR
37 37+470 37+500 T - Gadab VR
38 39+670 39+750 T Gadab - VR
39 40+410 40+550 T - Devroli VR
40 40+730 40+900 T Jui - VR
41 41+390 41+400 T Karajtape - VR
42 41+650 41+700 T Salindeg - VR
43 42+080 42+155 T Kasu - VR
44 42+230 42+300 T Kasu - VR
45 42+430 42+500 T Patani - VR
46 42+680 42+500 T Pandapur - VR
47 43+150 43+240 T Aakadevi temple - MDR
48 44+000 44+090 + Salinde - VR
49 44+420 44+500 T - Nigade VR
50 44+740 44+820 T - Palkar MDR
51 44+920 45+000 T - Amtem VR
52 45+150 45+200 T - Amtem VR
53 45+250 45+300 T - Amtem VR
54 46+360 46+400 + Amtem Amtem VR
55 47+380 47+450 T Khartale - VR
56 48+510 48+600 T - Kolotichiwadi VR
57 49+020 49+100 + Village Kolotichiwadi VR
58 50+780 50+850 T Palas - VR
59 52+730 52+800 T Nidi - VR
60 53+080 53+100 T - Nidi VR
61 53+330 53+400 T Kond - VR
62 54+090 54+150 T Miranagar - VR
Panvel - Indapur MPR No-37 February ‘15 Page 26
Sl. No.
Chainage Km
Typ
e o
f
Cro
ssin
g
Destination
Details
As per CA As per Design
Left Right
63 54+920 55+000 T - Village VR
64 55+180 55+250 T Ramnagar - MDR
65 56+320 56+400 T Nagothane - MDR
66 56+940 57+050 T Chikani - VR
67 61+240 61+300 T MSEB (Kansui) - VR
68 61+880 61+940 T Tamsoli - VR
69 63+190 63+260 T - Sukeni VR
70 64+330 64+400 T Kherwadi - VR
71 68+180 68+260 T Khamb - VR
72 68+260 68+300 T - Khamb VR
73 68+350 68+400 T Khamb - VR
74 68+680 68+740 T - School MDR
75 69+740 69+800 T - Village VR
76 69+850 69+900 T Village - VR
77 70+830 70+890 T Village - VR
78 71+360 71+420 T - Village VR
79 71+730 71+800 T Village - VR
80 71+940 72+000 T Pugaon - VR
81 74+530 74+600 T - Waras VR
82 75+330 75+400 T Kolad Rly. Station - VR
83 76+260 76+300 T - Talawali VR
84 76+440 76+500 T Tise - VR
85 77+710 77+740 Y - Bhuvan MDR
86 78+320 78+400 T Ghotwal - MDR
87 79+090 79+140 + School Ratwade VR
88 79+490 79+490 Y - Village MDR
89 81+150 81+200 T Nilaj - VR
90 81+450 81+500 T - Wavediwali VR
91 81+680 81+700 Y - Wavediwali MDR
92 82+580 82+625 T - Potner VR
93 82+710 82+750 T Gangewadi - VR
94 83+220 82+300 T Rudroli - VR
95 84+330 84+400 T - Nagroli MDR
Table 1.20 Details of U-Turn Facilities
Sl
No Chainage Village name Type of Crossing
Distance between
Opening (m) Remarks
1 2+580 Turmale T Junction
2 5+000 Chinchwan VUP 2420
3 7+000 Mid block opening 2000
4 9+080 Karnala Kila T Junction 2080
Panvel - Indapur MPR No-37 February ‘15 Page 27
Sl
No Chainage Village name Type of Crossing
Distance between
Opening (m) Remarks
5 11+995 Kolhe T Junction 2915
6 14+729 Apta Phata
(SH-83) T Junction 2734 No other cross road in between
7 17+560 Mid block opening 2831 Steep gradient in between
8 19+860 Mid block opening 2300 S-Curve in between
9 22+450 Ambivali T Junction 2590 Steep gradient & Curve portion
10 24+200 Virwadi T Junction 1750
11 25+860 Khopoli Jn (SH-87)
VUP 1660
12 27+100 VUP 1240 PUP converted to VUP - approved in principle by NHAI
13 27+760 VUP 660 VUP shifted to this place - approved in principle by NHAI
14 28+535 VUP 775 PUP converted to VUP - approved in principle by NHAI
15 29+660 Vashi T Junction 1125
16 30+930 Wadkhal VUP 1270
17 32+940 Mid block opening 2010
18 35+880 Ispat factory Y junction 2940
19 38+590 Mid block opening 2710
20 40+900 Jui T Junction 2310
21 43+200 Aakadevi Temple
T Junction 2300
22 46+450 Amate X Junction 3250
23 47+480 Khatale T Junction 1003
24 52+800 Nidi T Junction 5347 Many PUP’s in between
25 54+451 Nagothane
(SH-91) VUP (Additional) 1651
26 56+060 Nagothane VUP 1609
27 58+720 Pali T Junction 1120
28 59+021 Alibaug (SH-93) T Junction 301
29 60+300 Rest Area Mid block opening 1279
30 61+295 MSEB (Kansui) T Junction 995
31 63+244 Sukeli T Junction 1949
32 69+400 Mid block opening 6156 Hilly terrain 64 to 66, 66+700 toll plaza, 68+320 Khamb PUP
33 72+000 Pugaon T Junction 2600
34 73+760 Kolad (SH-62) VUP 1760
35 74+780 SH-60 VUP (Additional) 1020
36 76+900 Mid block opening 2120
37 78+388 Ghotwale T Junction 1488
38 81+825 Wavediwali T Junction 3112 No important cross road in between.
39 82+760 Gangewadi T Junction 1260
40 84+387 Nagroli T Junction 1627
Panvel - Indapur MPR No-37 February ‘15 Page 28
1.5 Project Milestones
The Project Milestones details are given in Table 1.21
Table 1.21 Project Milestones
Milestone Description Scheduled
Date Progress
Requirements Status
Milestone-I
First anniversary of the Appointed Date
19-12-2012
Physical Progress : Not less than 25%
Expended Cost : Not
less than 25% of total capital cost
Milestone - I was achieved on 01-05-’13. (That is during Extension of Time period). However, EOT is recently approved by the Executive Committee of NHAI.
Milestone-II
Second anniversary of
the Appointed Date
19-12-2013
Physical Progress : Not less than 65%
Expended Cost : Not less than 65% of total capital cost
Concessionaire vide their letter no SPITPL/ P-NHAI/ 2003-14/ 2471 dt. 28-01-’14 informed NHAI that they have achieved Milestone-II considering the available land. Recently, Executive Committee of NHAI has given Extension of Time (EOT) for achievement of Milestone-II upto 31-10-2015.
Four Laning (Project Completion)
910th day from the Appointed Date
16-06-2014 Four Lane completion in accordance with Concession Agreement
Concessionaire has not achieved Four Laning (Project completion) by scheduled date. Concessionaire has submitted request for Extension of Time (EOT) for Four - Laning upto November 2016. Executive Committee of NHAI has given approval for Extension of Time (EOT) upto 31-03-2016 (except eco-sensitive zone).
1.6 Location Map
Raigarh District Map is given in Figure 1.1. The road network map of Raigarh district is
shown in Figure 1.2.
Panvel - Indapur MPR No-37 February ‘15 Page 29
Figure 1.1 District map of Raigarh
Figure 1.2 Road network in Raigarh District
Panvel - Indapur MPR No-37 February ‘15 Page 31
2.0 THE ESTABLISHMENT
2.1 Project Organisation
NHAI
NHAI have established a Project Implementation Unit at Panvel. The Project
Director is Mr. Prashant J. Fegade. He is supported by the Manager (Tech.) Mr.
Narayankar and other Administrative Staff.
Concessionaire
The Organization of Concessionaire’s is represented by its SPV Manager, Mr.
Pradeep Garole. He is responsible for day to day activities of the Concessionaire
and he also provides information to IE/NHAI as and when necessary.
Concessionaire has established their office near Km 27+800 at Pen.
Concessionaire’s Organisation chart is given in Figure 2.1.
Figure - 2.1 Concessionaire’s Organisation Chart
Concessionaire has appointed M/s Sowil Limited as Project Management
Consultants (PMC) and they have established their office at the same premises
that of the Concessionaire.
Independent Engineer
The Independent Engineer, Yongma Engineering Co., Ltd in Association with
Feedback Infra Private Limited. mobilised on 28-12-’11 and the Consultancy
Agreement was signed on 11-01-‘12. The team at site is headed by the Team
Leader cum Sr. Highway Engineer. All Key-Professionals are already mobilised.
Part Time / Intermittent staff is visiting site on as and when required basis apart
AGM (Planning):
Mr. Umapathi T B
G M (Finance):
Mr. Kamlesh Chechani
GM (Projects)
Vice President:
Mr. P.S. Garole
Acting Team Leader :
Gangadharan C.P.
Director:
Mr. Vikas Sharma
Panvel - Indapur MPR No-37 February ‘15 Page 32
from reviewing Design, Drawings and Submittals from main / satellite offices. In
addition to above, Project Manager and Project Director at Head Office work as
link between site office and main office for co-ordinating issues beyond day to day
works. The Table 2.1 below shows the deployment of Independent Engineer.
Table 2.1 Deployment Details of Independent Engineer
Sl
No Position Name
Date of
Mobilisation
Date of De-
Mobilisation Remarks
A Key Professional Staff
1 Team Leader cum Sr.
Highway Engineer Mr. Gangadharan C P 30-12-‘11
2 Sr. Bridge Design Engineer
Mr. Magesh Santhanam 17-01-‘12 16-06-‘12
Mr. Nandadulal Dasgupta 07-02-‘13
3 Resident Cum Highway
Engineer Mr. Rajat Parkash Sharma 28-12-‘11
4 Highway Design
Engineer Mr. Dadan Singh 23-08-‘12 11-04-‘14
Manmonths
completed -
Demobilised
5 Bridge/Structural
Engineer Mr. H. Nagaraja Rao 02-02-‘12
6 Sr. Pavement Specialist Mr. Manish Kumar Shah 27-02-‘12
7 Sr. Quality cum Material
Expert Mr. M.V.K. Appa 16-01-‘12
8 Traffic and
Transportation Expert Mr. Krishna Prasad 12-04-‘12
9 Road Safety Expert Mr. Baljit Sidhu 05-09-‘12
10 Finance Expert Mr. Pankaj Sachdeva 13-06-‘12
11 Legal Expert Mr. Sunil Malhotra 21-08-'12
B Sub-Professional
Staff
12 Survey Engineer-1 Mr. Sena Prasad 05-04-‘13 21-04-‘14
Manmonths
completed -
Demobilised
13 Survey Engineer-2 Mr. Suresh Kumar 06-06-‘12
14 Asst. Highway Engr-1
Mr. Ravindra P Dongre 01-03-‘12
Mr. Neeraj Mahadeorao
Patil 28-02-‘14
15 Asst. Highway Engr-2 Mr. Arun Rajan Pillai 17-10`12
16 CAD Expert TBN -
17 Environmental Engineer Mr. Raj Kumar Singh 19-03-‘12
18 Asst. Bridge Engr-1 Mr. Shatrunjay Kumar 09-03-‘12
19 Asst. Bridge Engr-2 Mr. Vinod S Bawankar 19-04-‘12
Panvel - Indapur MPR No-37 February ‘15 Page 33
20 Asst. Quality cum
Materials Engr-1 Mr. Raffiudin N Badure 05-04-‘12
21 Asst. Quality cum
Materials Engr-2 Mr. Sanjay Maharana 07-08-'12
22 Electrical Engineer Mr. Anand Mohan
Jayaswal 05-06-‘12
23 HTMS / Toll Expert TBN -
24 Quantity Surveyor Mr. Satish. N.L 22-10-‘12
25 Horticulture cum
Landscaping Expert TBN -
C Support Staff
26 Office Manager Mr. Praveen Kumar 01-02-‘12
27 Accountant Ms. Vidya Baburao Ubale 01-03-12 01-08-‘12
Ms. Madhumati P Kumar 22-08-‘12
28 Cashier Ms. Shubhangi Mohre 13-02-‘12 01-07-‘12
Ms. Reshma Newalkar 01-07-‘12
29 Photocopy Machine
Operator Mr. Santosh Sharma 22-02-‘12
30 Steno Ms. Jyoti Vishnu Jadhav 23-02-‘12
31 Computer Operator Ms. Reshma Ananda
Katekar 23-02-‘12 31-01-‘15
32 Guard-1 Mr. RamCharan Vajpayee 26-03-‘12
33 Guard-2 Mr. Ganesh Bhadur 26-03-‘12
34 Office Boy Mr. Mohammed Rafiq 17-01-’12 16-07-‘12
Mr. Aditya Shetye 16-07-‘12
The office of the Independent Engineer (IE) is located at First Floor, Tejaswini
Arcade, Above PMC Bank, Takka village, Old Panvel. PIN: 410 206. The office
contact numbers are: Telephone: 022-27450391, E-Mail Id: [email protected].
Independent Engineer’s Organisation Chart is given in Figure 2.2.
Panvel - Indapur MPR No-37 February ‘15 Page 34
Figure 2.2. Independent Engineer’s Organisation Chart
Resident cum Highway Engineer:
Mr. Rajat Parkash Sharma
Team Leader/ Sr. Highway Engineer:
Mr. Gangadharan C.P.
Sr. Quality cum Material Expert:
Mr. M V K Appa
AHE - 1: Mr. Neeraj Mahadeorao Patil
AHE - 2: Mr. Arun Rajan Pillai
Survey Engr. - 1: (Demobilised)
ABE -1: Mr. Shatrunjay Kumar
ABE -2: Mr. Vinod S Bawankar
Survey Engr.-2: Mr. Suresh Kumar
AQME -1: Mr. Raffiudin N Badure
AQME -2: Mr. Sanjay Maharana
Bridge /Structural Engineer:
Mr. Nagaraja Rao
Short Term Key Professionals:
Sr. Pavement Specialist: Mr. Manish Kumar Shah
Sr. Bridge Design Engineer: Mr. Nandadulal Dasgupta
Traffic & Transportation Expert: Mr. Krishna Prasad
Road Safety Expert: Mr. Baljit Sidhu
Highway Design Engineer: (Demobilised)
Financial Expert: Mr. Pankaj Sachdeva
Legal Expert: Mr. Sunil Malhotra
Support Staff:
Office Manager: Mr. Praveen Kumar
Accountant: Ms. Madhumati P Kumar
Cashier: Ms. Reshma Newalkar
Steno: Ms. Jyoti Vishnu Jadhav
Computer Operator:
Photocopy Machine Operator: Mr. Santhosh Sharma
Office Boy: Mr. Aditya Shetye
Guard-1: Mr. Ram Charan Vajpayee
Guard-2: Mr. Ganesh Bhadur
Short Term Sub-Professionals:
Quantity Surveyor: Mr. Satish. N.L HTMS / Toll Expert: TBN
Electrical Engineer: Mr. Anand M Jayaswal
Horticulture cum Landscaping Expert: TBN
CAD Expert: TBN Environmental Engineer: Mr. Raj Kumar
Singh
Panvel - Indapur MPR No-37 February ‘15 Page 35
EPC Contractors
Two EPC Contractors were appointed by the Concessionaire for the
construction of the Project. Details of EPC Contractors are given Table 2.2:
Table 2.2 Details of EPC Contractors
2.2 Plant & Machinery
Table 2.3 Details of Plants Mobilised
Sl No Description Location Capacity
Section-I
1 Laboratory 23+600
2 Stone Crusher Bombay Pada 200 TPH
3 Concrete Batching Plant 23+600 60 Cum /Hr
4 WMM Plant 23+600 200 TPH
5 Hot Mix Plant Bombay Pada 120 TPH
Section-II
6 Laboratory 58+000
7 Stone Crusher 58+000 200 TPH
8 Concrete Batching Plant 58+000 30 Cum /Hr
9 WMM Plant 58+000 200 TPH
10 Hot Mix Plant 58+000 160 TPH
Table 2.4 Details of Machinery
Sl No Description Available
(Nos) Photo
1 JCB 5
Sl No Location EPC Contractor
1 Km 0+000 to 42+000 M/s Mahavir Roads and Infrastructure Pvt. Ltd.
2 Km 42+000 to 84+000 M/s Supreme Infrastructure India Limited
Panvel - Indapur MPR No-37 February ‘15 Page 36
Sl No Description Available
(Nos) Photo
2 Excavator /
Poclain 7
3 Paver 1
4 Grader 2
6 Tippers 15
Panvel - Indapur MPR No-37 February ‘15 Page 37
Sl No Description Available
(Nos) Photo
7 Water Tanker 2
8 Vibratory
Roller 2
9 Transit Mixer 5
10 Plate
Compactors Nil
11 Hydra 2
13 Tandem Roller Nil
14 Pneumatic Tyred Rollers
(PTR)
Nil
15
Emulsion
Sprayer / Browser
1
Concessionaire has demobilised some of the Pavers, Graders, Pneumatic Tyred
Rollers, and Tipper etc. The present set of machinery is insufficient to complete the
project in time.
Panvel - Indapur MPR No-37 February ‘15 Page 38
3.0 PROGRESS OF WORKS
3.1 Land Handing Over
Concession Agreement Vol-I, Clause 10.3 specify that on or prior to the Appointed
Date (that is 19-12-2011), NHAI shall have granted vacant access and Right of Way
such that the Appendix shall not include more than 20% of the total area of the Site
required and necessary for the Four-Laning of Project Highway. Also, NHAI shall
make best efforts to procure and grant, no later than 90 days from Appointed Date
(that is 18-03-2012), the Right of Way to the Concessionaire in respect of all land
included in the Appendix. Total land to be acquired is 504 Ha. At following locations
the construction work is affected due to non-clearance by Forest Department:
Table 3.1 Details of Forest areas
Eco-Sensitive Zone: NHAI vide their letter No. NHAI/PIU/PNVL/BOT/NH-17/PNL-
IND/ECO/2012/1841 dt. 24-12-‘12 has instructed Concessionaire to stop the
Sl No Chainage
Length (m) From To
1 2+545 2+610 65
2 6+300 6+500 200
3 6+500 6+620 120
4 6+620 6+680 60
5 6+850 6+930 80
6 6+960 7+400 440
7 7+500 7+770 270
8 7+850 7+915 65
9 7+915 8+350 435
10 8+600 10+100 1,500
11 10+580 10+625 45
12 10+625 10+640 15
13 10+640 10+680 40
14 11+135 11+275 140
15 11+630 11+900 270
16 11+900 11+950 50
17 12+110 12+220 110
18 12+220 12+580 360
19 12+580 12+925 345
20 12+925 13+130 205
21 13+130 13+250 120
22 13+250 13+565 315
23 13+565 13+620 55
24 13+910 14+120 210
25 14+310 14+575 265
26 15+745 15+775 30
27 15+775 15+790 15
28 16+540 16+800 260
TOTAL 6,085
Panvel - Indapur MPR No-37 February ‘15 Page 39
construction works in the Eco-Sensitive zone (Ch. 0+000 to 20+100). Approval for
non core area (length 16.6 km) of Eco-Sensitive Zone has been obtained. However,
PCCF Maharashtra has asked to obtain NGT approval.
Salt Pan Land (Ch. 31+700 to 33+200): NHAI vide their letter no.
NHAI/PIU/Panvel/PI/SPITPL/2015/2371 dt. 23-02-’15 has informed Concessionaire
regarding handing over of possession of salt plan land.
3.2 Tree Cutting & Plantation
Details of tree cutting are given in Table 3.2. Tree cutting works are in advanced
progress.
Table 3.2 Details of Tree Cutting
Description Scheduled Trees Non-Scheduled Trees Remarks
Total 2390 7964
Removed / Cut 4985
Balance 5369
Table 3.3 Details of Plantation done by Concessionaire
Description Chainage
Status From To
Median Plantation
(Shrubs) - -
Not yet done.
Project construction is still in progress.
Avenue Plantation
(trees) - -
Not yet done.
Project construction is still in progress.
3.3 Details of Utility Shifting
Details of utility shifting is given in Table 3.4 Table 3.4 Details of Utility Shifting
Sl No
Description Total
Length (m) Status
A CIDCO Water Pipe Lines
5080 m CIDCO water pipe line shifting work has recently started.
B Reliance / NOCIL Gas Pipeline
690 m
The exact location of pipeline identified. Concessionaire has to submit proposal by modifying the piers P11 (L), P12 (L), P13 (L) and P15 (R). The abutment A1 may be converted to pier and retaining wall type. The 4” pipe which comes in embankment portion may be encased by utility owner.
C MSEDCL Electrical Lines & Poles (17 DTC Transformers,
4,850m LHS
21,050m RHS
Very slow progress. Out of total 237 crossings, only 3 nos. crossings done so far.
Panvel - Indapur MPR No-37 February ‘15 Page 40
3.4 Design Review
Table 3.5 Design Review
Sl No
Description Status
1 Plan & Profile Drawing Main Carriageway
77.747 Km Concurred. Concessionaire for Ch. 43+000 to 44+000 withdrawn. 3.000 Km (Ch. 7+500 to 10+500) not yet concurred.
2 Plan & Profile Drawing Service Road 19.67 Km. on LHS concurred. 17.42 Km. on RHS Concurred.
3 Structures 746 Nos. drawings concurred.
4 Major Junctions 11 nos are Concurred.
5 Minor junctions 88 nos are Concurred.
6 Quality Assurance Manual Concurred. Two more copies to be submitted by Concessionaire.
7 Health, Safety and Environment Plan Concurred. Two more copies to be submitted by Concessionaire.
8 Environmental Management Plan (EMP) Concessionaire has not submitted EMP incorporating IE’s comments.
9 Construction Programme
Concessionaire has recently submitted request for Extension of Time (EOT) upto Nov ’16. Recently detailed programme submitted which is recommended to NHAI for approval alongwith EOT upto March ’16 (Ch 20+100 to 84+600) and June ’16 (0+000 to 20+100)
10 Borrow Areas for Section-1 18 nos are concurred.
11 Borrow Areas for Section-2 27 nos are concurred.
12 Section - I Concrete mix designs M10,M15, M20, M25, M30,M35,M40, M40-pile, with Natural sand +Crusher sand ,M-45 PSC With 100% Natural sand
Concurred
13 Section - II Concrete mix designs M15, M20, M25, Concurred
665 HT Poles, 841 LT Poles, 96 HT Crossings, 138 LT Crossings and 3 river crossings)
D MJP Water Pipeline (200 to 450 mm Ø Water line)
19,840m LHS
4,180m RHS
Shifting works in very slow progress. Pipe laid for 7 Km only out of total length of 23.5 Km.
E ISPAT Water Pipeline
21,670m LHS
70m RHS
Shifting works in progress. 4.1 Km length shifting completed.
F ZP water pipeline 5,090m LHS
4,030m RHS Slow progress in shifting.
Panvel - Indapur MPR No-37 February ‘15 Page 41
Sl No
Description Status
M30, with Natural sand +Crusher sand , M-45PSC With 100% Natural sand
14 Hume pipes source approval for M/s Sagar Spun Pipes Concurred
15 GSB Mix design. Concurred
16 WMM Mix design. Concurred
17 DBM Mix Designs - Grading I for both sections Concurred
18 DBM Mix Designs - Grading II for Section - I Concurred
19 BC Mix Design - Grading II for Section - II Concurred
20 Source Approval for Coarse aggregates, Fine aggregates, water, ACC cement OPC Grade-53, SS1 & RS1 for section I
Concurred
21 Source Approval for Coarse aggregates, Fine aggregates, water, Ambuja cement OPC Grade-53 for section II
Concurred
22 Source Approval for Bitumen VG30 (BPCL) for both Sections
Concurred
23 BM Mix Design for section - I & II Concurred
24 Section-1 Concrete mix design M-10, M-20, M-30, M-
35, with 100% crusher sand with Ambuja & ACC cement.
Concurred
25 Concrete mix design M-20 for Kerb both sections Concurred
26 Concrete mix design M-40 grade with 100% crusher sand for Crash Barrier for section- I
Concurred
27 Concrete Mix Design for Cable Grout with Cebex 100
FOSROC Concurred
28 Source Approval for Bitumen Emulsion SS-1 & RS-1 from IWL INDIA Ltd
Concurred
29 Source Approval for Curing Compound BASF MASTERKURE 1061
Concurred
30 Source Approval for Procurement of Steel
Reinforcement, Fe-500 Grade-RINL (Vizag Steel) Concurred
31 Source Approval for Procurement of Cement, 53 Grade- Ultra Tech Cement
Concurred
32 Source Approval for Procurement of Steel Reinforcement, Fe-500 Grade-SAIL
Concurred
33 Source Approval for Procurement of Cement, 53
Grade- ACC Cement Concurred
34 Source Approval for Procurement Wedge and Anchor Cones
Concurred
35 Source Approval for Procurement of Admixture, Fosroc - Conplast SP 430
Concurred
36 Source Approval for Procurement of Admixture, BASF Rheobuild 821 EJ
Concurred
37 Source Approval for Procurement of Cement, 53 Grade- SANGHI Cement
Concurred
Panvel - Indapur MPR No-37 February ‘15 Page 42
Sl No
Description Status
38 Section-II- Concrete Mix Design of M-30 (RE Block) With ACC Cement 53 Grade
Concurred
39 Section-II- Concrete Mix Design of M-40 RCC With Ambuja Cement 53 Grade
Concurred
40 Source Approval for Procurement of Admixture, Chembond KEM SP 40
Concurred
41 Source Approval for Procurement of Steel SAIL TMT EQR
Concurred
42
Section - II Concrete Mix Design for M-15 PCC, M-20 RCC, M- 20 PCC Kerb, M-25 RCC, M-30 RCC, M- 35 RCC and M-40 RCC with ACC Cement (53 Grade) With CHEMBOND and BASF Admixture with 100% Crusher Sand.
Concurred
43
Section - II Concrete Mix Design for M-15 PCC, M-20 RCC, , M-25 RCC, M-30 RCC, M- 35 RCC and M-40 RCC with SANGHI Cement (53 Grade) With CHEMBOND and BASF Admixture with 100% Crusher Sand.
Concurred
44 Source Approval for HT strands Procured From TATA Steel
Concurred
45 Concurrence of Mix Design for Mastic Asphalt For Section-(I Km 0+000 to 42+000)
Concurred
46 Mix Design For Dry Lean Concrete. Concurred
47 Mix Design For Pavement Quality Concrete. Concurred
48
Concrete Mix Design for M-15 PCC, M-20 RCC, , M-25
RCC, M-30 RCC, M- 35 RCC and M-40 RCC with Ultratech Cement (53 Grade) With CHEMBOND Admixture.
Concurred
49 Concrete Mix Design for M-15 PCC, M-20 RCC, , M-25 RCC, M-30 RCC, M- 35 RCC and M-40 RCC with Ultratech Cement (53 Grade) With BASF Admixture.
Concurred
50 Concrete Mix Design for M-20 PCC (Kerb) with Ultratech Cement (53 Grade).
Concurred
51 Source Approval for Procurement of Emulsion Bitumen (SS-1 & RS-1) from M/s HINDUSTAN COLAS LIMITED
Concurred
3.5 Progress of Major Works
The cumulative quantities are given in Table 3.6.
Table 3.6 Cumulative Quantities Executed
Sl No
Description Unit Cumulative Planned*
Cumulative Executed
Reported by Concessionaire*
Assessed by IE
1 Excavation Soil -Highway
Cum 8,90,545 8,66,675
2 Excavation - Hard rock Cum - 39,240
Panvel - Indapur MPR No-37 February ‘15 Page 43
*CConcessionaire has not submitted Progress Report for the month. Revised
construction programme was submyet to be approved.
Table 3.7 Highway Works Lengths Completed
Description LHS (m) RHS (m)
Clearing & Grubbing 31,560 52,630
Embankment 31,450 46,240
Subgrade 23,937 40,470
Granular Sub base (GSB) 21,710 36,280
Wet Mix Macadam (WMM) 20,610 33,205
Dense Bituminous Macadam (DBM) 18,460 31,310
Bituminous Concrete (BC) 1,940 2,600
Table 3.8 Summary of Progress of Structures
Sl No Description Total Nos Work in
Progress Not yet Started
1 Major Bridges 6 6 0
2 Flyovers 2 0 1 (1 no Deleted)
3 ROB’s 3 1 2
4 Minor Bridges 23 20 3
5 Vehicular Underpasses 11 6 5
6 Pedestrian Underpasses 15 6 9
7 Pipe culverts 208+20 116 112
8 Box culverts 135+1 105 31
3 Embankment Cum 36,28,182 35,49,095
4 Subgrade Cum 6,10,108 4,71,229
5 Granular Sub base Cum 2,03,340 1,60,076
6 Wet Mix Macadam Cum 1,61,171 1,28,810
7 Bituminous Macadam Cum 31,141 0
8 Dense Bituminous Macadam
Cum 59,823 43,955
9 Bituminous Concrete Cum 7,486 1,580
10 Excavation-Structures Cum 69,685 64,200
11 PCC M15 Cum 6,834 6,383
12 RCC M20, M25, M30 Cum 47,918 43,191
13 RCC M35 / RE wall fascia blocks
Cum 10,228 8,559
14 RCC M40,M45 Cum 3,334 3,055
15 Reinforcement Tonne 4,644 4,128
16 PSC Strand Tonne - 60
Panvel - Indapur MPR No-37 February ‘15 Page 44
3.6 Miscellaneous Works
Miscellaneous works are not yet started.
3.7 Status of Project Facilities
Sl No Proposed facility Chainage (Km) Status
1 Traffic aid post Not yet constructed
2 Medical aid post Not yet constructed
3 Vehicle rescue post Not yet constructed
4 Toll plaza administrative building
(1) 0+000 To 42+000
(2) 42+000 To 84+600 Not yet constructed
5 Telecom System Not yet constructed
3.8 Overall Progress
Concessionaire’s reported progress details are on higher side. Independent Engineer
estimated the approximate quantities executed and accordingly approximate
percentage progress was estimated.
Total Project Cost: Rs. 942.69 Crores. (As per Con cession Agreement)
Total Project Cost: Rs. 1205.72 Crores (As reported by Concessionaire) Time Elapsed: 38.5 Months
Description Planned
Achieved
Reported by
Concessionaire*
Assessed by
IE
Physical Progress :
Cumulative Physical Progress (%) 39.89 % 34.86 %
Cumulative Percentage Physical Lag (-) / Lead (+)
(-) 5.03 %
Financial Progress :
Cumulative Financial Progress (Rs. Crores)
482.83 425.62
Cumulative Financial Progress (%) 40.04 % 35.30 %
Cumulative Financial
Lag (-) / Lead (+)
(-) 57.21 Crores
(-) 4.74 %
* Concessionaire has not submitted Progress Report for the month.
Panvel - Indapur MPR No-37 February ‘15 Page 45
Table 3.9 Details of Physical Progress
Month Monthly Physical Progress (%) Cumulative Physical Progress (%)
Scheduled Actual Scheduled Actual
Dec. ‘11 0.36 % 0.00 % 0.36 % 0 %
Jan. ‘12 1.57 % 1.75 % 1.93 % 1.75 %
Feb. ‘12 3.17 % 1.22 % 5.10 % 2.97 %
Mar. ‘12 4.50 % 0.60 % 9.60 % 3.57 %
Apr. ‘12 5.01 % 0.90 % 14.61 % 4.47 %
May ‘12 4.90 % 1.30 % 19.51 % 5.77 %
Jun. ‘12 2.48 % 0.99 % 21.99 % 6.76 %
Jul. ‘12 1.79 % 0.33 % 23.78 % 7.09 %
Aug. ‘12 1.25 % 0.69 % 25.03 % 7.78 %
Sept. ‘12 0.3 % 0.69 % 25.33 % 8.47 %
Oct. ‘12 0.60 % 1.58 % 25.93 % 10.05 %
Nov. ‘12 0.85 % 2.14 % 26.78 % 12.19 %
Dec. ‘12 0.76 % 0.45 % 27.54 % 12.64 %
Jan. ‘13 3.49 % 1.61 % 31.03 % 14.25 %
Feb. ‘13 4.39 % 2.90 % 35.42 % 17.15 %
Mar. ‘13 4.92 % 3.21 % 40.34 % 20.36 %
Apr. ‘13 5.20 % 4.59 % 45.54 % 24.95 %
May ‘13 5.65 % 2.77 % 51.19 % 27.72 %
Jun. ‘13 4.40 % 0.25 % 55.59 % 27.97 %
Jul. ‘13 2.71 % 0.29 % 58.30 % 28.26 %
Aug. ‘13 2.86 % 0.22 % 61.16 % 28.48 %
Sept. ‘13 3.27 % 0.17 % 64.43 % 28.65 %
Oct. ‘13 4.39 % 0.30 % 68.82 % 28.95 %
Nov. ‘13 4.89 % 0.78 % 73.71 % 29.73 %
Dec. ‘13 5.62 % 0.49 % 79.33 % 30.22 %
Jan. ‘14 5.90 % 0.53 % 85.23 % 30.75 %
Feb. ‘14 6.06 % 0.42 % 91.29 % 31.17 %
Mar. ‘14 6.41 % 1.37 % 97.70 % 32.54 %
Apr. ‘14 1.47 % 1.02 % 99.17 % 33.56 %
May ‘14 0.83 % 0.72 % 100.00 % 34.28 %
June ‘14 0.00 % 0.40 % 100.00 % 34.68 %
July ‘14 - 0.05 % - 34.73 %
Aug ‘14 - 0.01 % - 34.74 %
Sept. ‘14 - 0.04 % - 34.78 %
Oct. ‘14 - 0.03 % - 34.81 %
Nov. ‘14 - 0.02 % - 34.83 %
Dec. ‘14 - 0.00 % - 34.83 %
Jan. ‘15 - 0.01 % - 34.84 %
Month Monthly Physical Progress (%) Cumulative Physical Progress (%)
Scheduled Actual Scheduled Actual
Cum. Upto end Jan '15
- - - 34.84 %
Feb. ‘15 5.05 % 0.02 % 39.89 % 34.86 %
Mar. ‘15 5.14 % 45.03 %
Apr. ‘15 5.59 % 50.62 %
May ‘15 5.80 % 56.42 %
June ‘15 5.85 % 62.27 %
July ‘15 2.63 % 64.90 %
Panvel - Indapur MPR No-37 February ‘15 Page 46
Aug ‘15 2.13 % 67.03 %
Sept. ‘15 2.12 % 69.15 %
Oct. ‘15 5.42 % 74.57 %
Nov. ‘15 5.44 % 80.01 %
Dec. ‘15 5.15 % 85.16 %
Jan. ‘16 5.05 % 90.21 %
Feb. ‘16 5.03 % 95.24 %
Mar. ‘16 1.66 % 96.90 %
Apr '16 1.13 % 98.03 %
May '16 1.12 % 99.15 %
June '16 0.85 % 100.00 %
Table 3.10 Details of Financial Progress
Month
Monthly Financial Progress Cumulative Financial Progress
Rs. Crores Percentage (%) Rs. Crores Percentage (%)
Scheduled Actual Scheduled Actual Scheduled Actual Scheduled Actual
Dec. ‘11 117.57 98.72 9.75 % 8.19% 117.57 98.72 9.75 % 8.19%
Jan. ‘12 18.93 16.12 1.57 % 1.34% 136.50 114.84 11.32 % 9.53%
Feb. ‘12 20.93 11.7 1.74 % 0.97% 157.43 126.54 13.06 % 10.50%
Mar. ‘12 25.08 6.72 2.08 % 0.56% 182.51 133.26 15.14 % 11.06%
Apr. ‘12 28.75 9.22 2.38 % 0.76% 211.26 142.48 17.52 % 11.82%
May ‘12 33.05 12.41 2.74 % 1.03% 244.31 154.89 20.26 % 12.85%
Jun. ‘12 28.75 9.90 2.38 % 0.82% 273.06 164.79 22.65 % 13.67%
Jul. ‘12 22.84 4.44 1.89 % 0.37% 295.90 169.23 24.54 % 14.04%
Aug. ‘12 17.74 7.45 1.47 % 0.62% 313.64 176.68 26.01 % 14.66%
Sept. ‘12 21.74 7.57 1.80 % 0.63% 335.38 184.25 27.82 % 15.29%
Oct. ‘12 24.16 14.40 2.00 % 1.19% 359.54 198.65 29.82 % 16.48%
Nov. ‘12 30.27 14.98 2.51 % 1.24% 389.81 213.63 32.33 % 17.72%
Dec. ‘12 34.31 4.24 2.85 % 0.35% 424.12 217.87 35.18 % 18.07%
Jan. ‘13 38.96 15.18 3.23 % 1.26% 463.08 233.05 38.41 % 19.33%
Feb. ‘13 44.91 26.9 3.72 % 2.23% 507.99 259.95 42.13 % 21.56%
Mar. ‘13 50.11 30.27 4.16 % 2.51% 558.1 290.22 46.29 % 24.07%
Apr. ‘13 53.86 43.44 4.47 % 3.60% 611.96 333.66 50.75 % 27.67%
May ‘13 58.28 26.34 4.83 % 2.18% 670.24 360.00 55.59 % 29.85%
Jun. ‘13 45.96 2.40 3.81 % 0.20% 716.20 362.4 59.40 % 30.05%
Jul. ‘13 29.36 0.98 2.44 % 0.08% 745.56 363.38 61.84 % 30.13%
Aug. ‘13 30.76 2.05 2.55 % 0.17% 776.32 365.43 64.39 % 30.30%
Sept. ‘13 34.82 1.61 2.89 % 0.13% 811.14 367.04 67.27 % 30.43%
Oct. ‘13 47.02 2.89 3.90 % 0.24% 858.16 369.93 71.17 % 30.67%
Nov. ‘13 51.96 7.36 4.31 % 0.61% 910.12 377.29 75.48 % 31.28%
Dec. ‘13 59.16 4.56 4.91 % 0.38% 969.28 381.85 80.39 % 31.66%
Jan. ‘14 62.96 5.07 5.22 % 0.42% 1032.24 386.92 85.61 % 32.08%
Feb. ‘14 64.56 3.97 5.35 % 0.33% 1096.8 390.89 90.97 % 32.41%
Mar. ‘14 73.75 12.91 6.12 % 1.07% 1170.55 403.80 97.08 % 33.48%
Panvel - Indapur MPR No-37 February ‘15 Page 47
Month
Monthly Financial Progress Cumulative Financial Progress
Rs. Crores Percentage (%) Rs. Crores Percentage (%)
Scheduled Actual Scheduled Actual Scheduled Actual Scheduled Actual
Apr. ‘14 20.90 9.52 1.73 % 0.79% 1191.45 413.32 98.82 % 34.27%
May ‘14 14.27 6.87 1.18 % 0.57% 1205.72 420.19 100.00 % 34.84%
June ‘14 0.00 3.74 0.00 % 0.31% 1205.72 423.93 100.00 % 35.15%
July ‘ 14 - 0.48 - 0.04% - 424.41 - 35.19%
Aug ‘14 - 0.12 - 0.01% - 424.53 - 35.20%
Sept. ‘14 - 0.37 - 0.03% - 424.90 - 35.23%
Oct. ‘14 - 0.24 - 0.02% - 425.14 - 35.25%
Nov. ‘14 - 0.24 - 0.02% - 425.38 - 35.27%
Dec. ‘14 - 0.00 - 0.00% - 425.38 - 35.27%
Jan. ‘15 - 0.01 - 0.00% - 425.39 - 35.27%
Month
Monthly Financial Progress Cumulative Financial Progress
Rs. Crores Percentage (%) Rs. Crores Percentage (%)
Scheduled Actual Scheduled Actual Scheduled Actual Scheduled Actual
Cu. Upto Jan ’15
- - - - - 425.39 - 35.27%
Feb. ‘15 57.44 0.23 4.76 % 0.02% 482.83 425.62 40.04% 35.29%
Mar. ‘15 58.26 4.83 % 541.09 44.88%
Apr. ‘15 62.41 5.18 % 603.50 50.05%
May ‘15 64.49 5.35 % 667.99 55.40%
June ‘15 64.98 5.39 % 732.97 60.79%
July ‘ 15 34.64 2.87 % 767.61 63.66%
Aug ‘15 29.83 2.47 % 797.44 66.14%
Sept. ‘15 29.83 2.47 % 827.27 68.61%
Oct. ‘15 60.94 5.05 % 888.21 73.67%
Nov. ‘15 60.92 5.05 % 949.13 78.72%
Dec. ‘15 58.24 4.83 % 1007.37 83.55%
Jan. ‘16 57.34 4.76 % 1064.71 88.30%
Feb. ‘16 57.17 4.74 % 1121.88 93.05%
Mar. ‘16 25.40 2.11 % 1147.28 95.15%
Apr '16 20.36 1.69 % 1167.64 96.84%
May '16 20.33 1.69 % 1187.97 98.53%
June ‘16 17.69 1.47 % 1205.72 100.00%
Panvel - Indapur MPR No-37 February ‘15 Page 48
Cumulative Physical Progress (%)
34.86%
65.14%
Achieved Balance
Cumulative Financial Progress (%)
35.30%
64.70%
Achieved Balance
Panvel - Indapur MPR No-37 February ‘15 Page 49
Physical Progress (%) S - Curve
0
10
20
30
40
50
60
70
80
90
100
De
c '1
1Ja
n '1
2Fe
b '1
2M
ar '1
2A
pr
'12
May
'12
Jun
'12
Jul '
12
Au
g '1
2Se
p '1
2O
ct '1
2N
ov
'12
De
c '1
2Ja
n '1
3Fe
b '1
3M
ar '1
3A
pr
'13
May
'13
Jun
'13
Jul '
13
Au
g '1
3Se
p '1
3O
ct '1
3N
ov
'13
De
c '1
3Ja
n '1
4Fe
b '1
4M
ar '1
4A
pr
'14
May
'14
Jun
e '1
4Ju
ly '1
4A
ug
'14
Sep
t '1
4O
ct '1
4N
ov
'14
De
c. '1
4Ja
n. '
15
Feb
'15
Mar
'15
Ap
r '1
5M
ay '1
5Ju
ne
'15
July
'15
Au
g '1
5Se
pt '
15
Oct
'15
No
v '1
5D
ec.
'15
Jan
. '1
6Fe
b '1
6M
ar '1
6A
pr
'16
May
'16
Jun
e '1
6
Cum. Scheduled Progress (New Programme) Cum. Achieved Progress Cum. Scheduled Progress (Original programme)
65
25
MILE STONE - II (65%)
MILE STONE - I (25%)M
ILE S
TO
NE -
I (2
5 %
)
MIL
ESTO
NE
-II
(65
%)
MIL
E S
TO
NE -
I (2
5%
)
Panvel - Indapur MPR No-37 February ‘15 Page 50
Physical Progress (%) - Histogram
0
1
2
3
4
5
6
7
De
c '1
1
Jan
'12
Feb
'12
Mar
'12
Ap
r '1
2
May
'12
Jun
'12
Jul '
12
Au
g '1
2
Sep
'12
Oct
'12
No
v '1
2
De
c '1
2
Jan
'13
Feb
'13
Mar
'13
Ap
r '1
3
May
'13
Jun
'13
Jul '
13
Au
g '1
3
Sep
'13
Oct
'13
No
v '1
3
De
c '1
3
Jan
'14
Feb
'14
Mar
'14
Ap
r '1
4
May
'14
Jun
e '1
4
July
'14
Au
g '1
4
Sep
t '1
4
Oct
'14
No
v '1
4
De
c. '1
4
Jan
. '1
5
Feb
'15
Mar
'15
Ap
r '1
5
May
'15
Jun
e '1
5
July
'15
Au
g '1
5
Sep
t '1
5
Oct
'15
No
v '1
5
De
c. '1
5
Jan
. '1
6
Feb
'16
Mar
'16
Ap
r '1
6
May
'16
Jun
e '1
6
Scheduled Actual Progress
Panvel - Indapur MPR No-37 February ‘15 Page 51
Financial Progress (Rs. Crores) S - Curve
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
De
c '1
1Ja
n '1
2Fe
b '1
2M
ar '1
2A
pr
'12
May
'12
Jun
'12
Jul '
12
Au
g '1
2Se
p '1
2O
ct '1
2N
ov
'12
De
c '1
2Ja
n '1
3Fe
b '1
3M
ar '1
3A
pr
'13
May
'13
Jun
'13
Jul '
13
Au
g '1
3Se
p '1
3O
ct '1
3N
ov
'13
De
c '1
3Ja
n '1
4Fe
b '1
4M
ar '1
4A
pr
'14
May
'14
Jun
'14
July
'14
Au
g '1
4Se
pt '
14
Oct
'14
No
v'1
4D
ec
'14
Jan
'15
Feb
'15
Mar
'15
Ap
r '1
5M
ay '1
5Ju
ne
'15
July
;15
Au
g '1
5Se
pt '
15
Oct
'15
No
v '1
5D
ec
'15
Jan
'16
Feb
'16
Mar
'16
Ap
r '1
6M
ay '1
6Ju
ne
'16
Cum. Scheduled Progress ( New Programme) Cum. Actual Progress Cum. Scheduled Progress (Original Programme)
MILESTONE - II (65%)
MILE STONE - I (25%)
MIL
ESTO
NE
-II
(65%
)
MIL
E S
TO
NE -
I (2
5%
)
Panvel - Indapur MPR No-37 February ‘15 Page 52
Financial Progress (Rs. Crores) – Histogram
0
20
40
60
80
100
120
De
c '1
1
Jan
'12
Feb
'12
Mar
'12
Ap
r '1
2
May
'12
Jun
'12
Jul '
12
Au
g '1
2
Sep
'12
Oct
'12
No
v '1
2
De
c '1
2
Jan
'13
Feb
'13
Mar
'13
Ap
r '1
3
May
'13
Jun
'13
Jul '
13
Au
g '1
3
Sep
'13
Oct
'13
No
v '1
3
De
c '1
3
Jan
'14
Feb
'14
Mar
'14
Ap
r '1
4
May
'14
Jun
'14
July
'14
Au
g '1
4
Sep
t '1
4
Oct
'14
No
v'1
4
De
c '1
4
Jan
'15
Feb
'15
Mar
'15
Ap
r '1
5
May
'15
Jun
e '1
5
July
;15
Au
g '1
5
Sep
t '1
5
Oct
'15
No
v '1
5
De
c '1
5
Jan
'16
Feb
'16
Mar
'16
Ap
r '1
6
May
'16
Jun
e '1
6
Scheduled (Rs Crores) Actual (Rs. Crores)
Panvel - Indapur MPR No-37 February ‘15 Page 53
4.0 QUALITY CONTROL & QUALITY ASSURANCE
4.1 Quality Control & Quality Assurance
Quality Assurance of a Project is defined as a process which exercises various checks
at different stages of a work right from its inception till its acceptance, to put it in
services to ensure that the work has been properly designed and constructed as per
approved designs, drawings and specifications.
Quality Control is defined as the procedure adopted and control exercised to ensure
that the materials proposed to be used in production, processes adopted for
production and workmanship of production conform to the prescribed standards and
laid down acceptance criteria.
The Quality Control is exercised by construction agency that ensures that the defined
objective is achieved through appropriate tests, checks and inspections by suitable
qualified personnel. Furthermore, the objective evidences of all tests, checks and
inspections carried out from time to time are documented in prescribed formats for
reference and record.
Independent Engineer’s professional staff is frequently checking various works at site
and wherever found necessary, corrective measures are suggested to the
Concessionaire.
4.2 Compliance/Non-Compliance
Non-Compliance cases are being reported through Non-Conformance Reports.
Concessionaire is constantly advised to take necessary rectifications for such non-
compliances in time. List of NCR’s issued and their statuses are given in Table 4.1. &
4.2. Concessionaire has been constantly advised to make necessary rectifications
and submit for closure of NCR within stipulated time. Many NCR’s are not yet closed
out in spite of several reminders.
4.3 Routine Inspection by Independent Engineer
Independent Engineer is conducting routine inspection of the works at site and
notifying the Concessionaire about any non-compliance observed. List of Site
Inspection Note issued so far is given in Table 4.3. Details of Audit Reports issued to
the Concessionaire are given in Table 4.4. Details of tests carried out are given in
Table 4.5 . Concessionaire has submitted compliances to all the reports together and
was reviewed by Independent Engineer. Many inspection points are not yet
complied. A compiled report of such pending site inspection points are again issued
to Concessionaire for necessary compliance.
Panvel - Indapur MPR No-37 February '15 Page 54
Independent Engineer is conducting routine inspection of the works at site and
notifying Concessionaire about any non-compliance observed.
Details of RFI’s reviewed by Independent Engineer
Month Percentage of RFI’s Reviewed
February ’15 24 %
Table 4.1 Status of NCR’s Issued by Independent Engineer (Closed Out)
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
1 1 18-04-'12 40+246 (RHS) Length of Box Culvert on RHS is less by 500mm.
11-09-‘12
Structure is Constructed as per Revised Drawing No. MRIPL/SC/LSD/40+246, Rev No. R1
2 2 18-04-'12 21+310 to
21+380 (LHS)
WMM works without concurrence of drawings / Mix Design.
14-06-'12
GSB & WMM Mix design concurred vide IE's Letter No. PIP/IE/SPITPL/2012 / 0197 and 198 dt. 03-05-'12.
3 3 20-04-'12 79+940 to
80+530 (RHS)
WMM works without compaction & concurrence of Mix Design.
14-06-'12
GSB & WMM Mix design concurred vide IE's Letter No. PIP/IE/SPITPL/2012/ 0197 and 198 dt. 03-05-'12.
4 4 21-04-'12 0+544 (Minor
Bridge) SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
5 5 21-04-'12 20+144
(Balganga Major Bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
6 6 21-04-'12 26+188
(Bhogeshwari Major Bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
7 7 21-04-'12 52+155 (Nidi Minor bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
8 8 21-04-'12 72+936
(Kundlika Major bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
9 9 21-04-'12 77+804 (Bhuvan
Minor bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
10 10 21-04-'12 81+600
(Wave Minor bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
11 11 21-04-'12 84+488 (Indapur
Major bridge)
SBC of foundation not determined
27-07-'12 Safe Bearing Capacity assessed and details submitted.
12 12 25-04-'12 20+754 Non-Curing of structure. 16-07-'13 Rebound hammer test &
Panvel - Indapur MPR No-37 February '15 Page 55
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
Minor bridge ultra sonic test conducted and found acceptable.
13 13 25-04-'12 80+840 Checking of Horizontal Alignment
29-06-'12 Horizontal alignment checked through RFI No-12058 dt. 22-06-'12
14 14 25-05-'12 38+801 (RHS) Box Culvert-
39/1 Length less by 506 mm 11-09-`12
Structure is constructed as per Revised Drawing No. MRIPL/SC/LSD/38+801, Rev No. R1.
15 15 25-05-'12 39+030 (RHS) Box Culvert-
39/2, Length less by 465mm 11-09-`12
Structure is constructed as per Revised Drawing No. MRIPL/SC/LSD/39+030, Rev No. R1.
16 16 25-05-'12 39+133 (RHS) Box Culvert-
39/3, Length less by 400mm 11-09-`12
Structure is constructed as per Revised Drawing No. MRIPL/SC/LSD/39+133, Rev No. R1.
17 17 25-05-'12 39+562 (RHS) Box Culvert-
40/1, Length less by 500mm 11-09-`12
Structure is constructed as per Revised Drawing No. MRIPL/SC/LSD/39+640, Rev No. R1.
18 18 25-05-'12 39+807 (RHS) Box Culvert-
40/2, Length less by 500mm 11-09-`12
Structure is constructed as per Revised Drawing No. MRIPL/SC/LSD/39+807, Rev No. R1.
19 19 25-05-'12 40+906 (RHS) Box Culvert-
41/2, Length less by 506mm 11-09-`12
Structure is constructed as per Revised Drawing No. MRIPL/SC/LSD/40+906, Rev No. R1.
20 20 25-05-'12 41+189 (RHS) Box Culvert-
41/4, Length more by 1.4m 09-10-`12
Superstructure constructed as per concurred drawing.
21 21 25-05-'12 41+336
(RHS)- Box Culvert-41/5,
Length more by 1.58m 06-10-`12 Superstructure constructed as per concurred drawing.
22 22 26-05-'12 47+244 (RHS) Slab Culvert Concrete bulged due to improper support
11-09-`12 Rectification done.
23 23 15-06-'12 26+188
Bhogeshwari Bridge
Abutment A2-3rd Lift.(RFI No.-2819)
11-07-'13
Rebound hammer test & ultrasonic test conducted. Results found acceptable.
24 24 16-06-'12 45+460 to
45+560 (RHS)
Embankment 8th Layer failed in compaction and boulders present.
06-12-`12
Boulder removed, compacted and retested. Achieved required compaction.
25 27 22-06-'12 79+990 to
80+150 (RHS) & 80+220 to
DBM Mix not Conforming to Concurred JMF.
02-08-`12 Core sample collected and retested. Found acceptable.
Panvel - Indapur MPR No-37 February '15 Page 56
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
80+285
26 29 25-08-'12 45+864 (RHS)
Finished concrete of Corbel is not in line. Honeycombing also observed in final lift wall.
17-12-'12
Rectified as per line and level, offsets was ground and honeycombing repaired with PMC mortar
27 30 06-11-'12 Kharpada Bridge P12 Foundation
Founding Strata is not embedded 1500 mm in Soft rock. Also Confirmatory SBC test not Carried out.
31-12-`12 Further excavated to a depth of 600 mm in hard Rock and PCC laid.
28 32 12-01-'13 69+140,
77+376 & 46+122
Concrete cubes (28 Days) Failed - M20, M25, & M30,
24-04-‘14 Retesting done using ultrasonic pulse velocity and rebound hammer.
29 36 20-02-'13 69+140 (RHS) Minor Bridge
Slab
Superstructure staging and scaffolding was carried out without any design and drawing as per Concession Agreement clause no. - 70.11.
20-11-‘13
Staging and scaffolding RFI’s checked by PMC. The design calculation submitted now. Deck slab concreting successfully completed.
30 40 12-04-‘13 2+200
Diversion plan not Submitted for concurrence. Entry/Exit to diversion are not smoothly merged with the existing road causing sag formation at joining. Location of diversion is chosen wrongly; At entry, one electric pole is obstructing the width of diversion. Sign / diversion boards have not been placed properly.
06-05-‘14 The diversion at Ch. 2+200 is closed and four lane is in operation.
31 42 30-04-'13 25+300 (RHS)
Pipe Culvert
Honeycombing is observed in pipe culvert encasing concrete. Due to this reinforcement is exposed.
28-05-'13 Honeycombing repairing done.
32 43 30-04-'13 26+188 (RHS)
PCC is carried out without safe bearing capacity test. Founding level is 1.381m above founding level as per concurred drawing.
03-07-'13
(1) The rock sample at the PCC level where the foundation is to be rest is tested at third party laboratory.
(2) The foundation for Abutment A1 on RHS is resting at level 0.653 m which is 0.95m below design foundation level.
33 44 01-04-'13 39+430 to
39+450 (RHS)
GSB sample collected and tested in Lab and found on coarser side.
05-05-‘14
Joint re-sampling done and observed that GSB material is within specification limits.
34 46 02-05-'13 20+144 (RHS) Balganga P1
M-35 grade concrete cubes has failed for 28 day's
16-07-'13 Rebound hammer test & ultra sonic test
Panvel - Indapur MPR No-37 February '15 Page 57
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
Footing strength. conducted and found acceptable.
35 49 16-05-'13 6+490
Diversion plan not submitted to IE for Concurrence. Diversion is sharp and unsafe.
05-05-‘14 The diversion at Ch. 6+490 is closed.
36 51 16-05-'13 38+801 (RHS)
Approach slab not laid as per drawing no. MRIPL/SC/LSD/38+801 R1. It was already intimated wide Letter No. PIP/IE/SPITPL/2013/ 0908 dt. 30-01-’13 and inspection note no-17.
16-05-‘14 Approach slab cast (RFI No. 55163 dt. 18-02-2014)
37 52 16-05-'13 39+030 (RHS)
Approach slab not laid as per drawing no. MRIPL/SC/LSD/ 39+030 R1. It was already intimated earlier Letter No. PIP/ IE/SPITPL/2013 /0908 dt. - 30-01-’13 and inspection note no-17.
16-05-‘14 Approach slab cast (RFI No. 55010 dt. 12-02-2014)
38 53 16-05-'13 39+133 (RHS)
Approach slab not laid as per drawing no. MRIPL/SC/LSD/ 39+133 R1. It is already intimated wide Letter No. PIP/IE/SPITPL/2013/ 0908 dt. 30-01-’13 and inspection note no-17.
16-05-‘14 Approach slab cast (RFI No. 55076 dt. 17-04-2014)
39 54 16-05-'13 40+564 (RHS)
Approach slab not laid as per drawing no. MRIPL/SC/LSD/ 40+564 R1. It was already intimated wide Letter No. PIP/IE/SPITPL/2013/ 0908 dt. 30-01-’13 and inspection note no-17.
16-05-‘14 Approach slab cast (RFI No. 52175 dt. 01-09-2013)
40 55 16-05-'13 40+750 (RHS)
Approach slab not laid as per drawing no. MRIPL/SC/LSD/ 40+750 R1. It was already intimated wide Letter No. PIP/IE/SPITPL/2013/ 0908 dt. 30-01-’13 and inspection note no-17.
16-05-‘14
Approach slab cast (RFI No. 52106 dt. 24-08-2013 & 52152 dt. 29-08-2013)
41 56 16-05-'13 40+906
Box Culvert
Approach slab not laid as per drawing no. MRIPL/SC/LSD/ 40+906 R1. It was already intimated wide Letter No. PIP/IE/SPITPL/2013/ 0908 dt. 30-01-’13 and inspection note no-17.
16-05-‘14 Approach slab cast (RFI No. 52104 dt. 25-08-2013)
42 57 22-05-'13 40+246 (RHS) Box Culvert
Honeycombing was observed in both sides of
09-07-'13 The finishing rectification of concrete
Panvel - Indapur MPR No-37 February '15 Page 58
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
crash barrier wall. surface for crash barrier done as per specifications.
43 59 28-05-'13
Wadkhal Flyover P-31 Foundation
RHS
Reinforcement steel used is brittle and cracks are developed in bending of reinforcement steel (32 mm dia).
10-5-‘14
The reinforcement cage was removed and the foundation P-31 (RHS) is discarded and will not be put in use.
44 60 28-05-'13 4+375 (RHS)
NP4 pipe laid is not fitted and matched properly. Gap is observed in jointing at pipes.
05-07-'13 The finishing of the pipe joint is done as per Specifications.
45 66 17-06-'13 39+920 to
39+930 (RHS)
DBM surface totally damaged (New Construction).
07-06-‘14
Existing damaged DBM surface completely removed and new DBM layer laid.
46 67 18-06-'13 39+130
Box Culvert Settlement near box culvert.
07-06-‘14
Existing damaged DBM surface completely removed and new DBM layer laid.
47 68 18-06-'13 41+110 to
41+120 (RHS) Patches on DBM Surface on new carriageway.
07-06-‘14
Existing damaged DBM surface completely removed and new DBM layer laid.
48 69 18-06-'13 40+210 to
40+220 (RHS) Patches on DBM Surface on new carriageway.
07-06-‘14
Existing damaged DBM surface completely removed and new DBM layer laid.
49 85 23-07-'13 84+488
Indapur Side
The centerline of highway and bridge structure not matching.
13-05-‘14 Works are carried out as per revised plan and profile drawing.
50 87 07-08-'13 Amba Bridge SAIL EQR steel is used for girder reinforcement without source approval.
21-12-‘13
Source approval of steel SAIL TMT EQR accorded as per Letter no. PIP/IE/ SPITPL/2013/1849 dt. 21-12-’13.
51 89 08-08-'13 RE Panel Casting
Lifting hook not been provided with Epoxy Paint.
02-05-‘14
Will be discarding the RE panels (Agency M/s Enviro Geo) and will not be put in use.
52 96 27-08-'13 57+650
RE Block (LHS)
Unapproved cement “SANGHI” is used for casting at RE blocks.
25-11-‘13
Now, the SANGHI cement source approval is concurred vide IE’s letter No. PIP/IE/SPITPL/2013 / 1724 dt. 08-11-‘13
53 97 31-08-‘13 Wadkhal
Flyover J2 outer girder
Prestressing girder is failed during second pre-stressing. Cones have gone inside and cracks have developed on diaphragm. This might have happened due to improper supporting system, poor quality of concrete and improper compaction of concrete.
02-05-‘14
Wadkhal Flyover damaged girder J2 (Casting dt. 05-07-’13) is discarded and will not be put in use.
Panvel - Indapur MPR No-37 February '15 Page 59
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
54 98 31-08-‘13 Wadkhal
Flyover J2 outer girder
Prestressing girder is failed during second pre-stressing. Cones have gone inside and cracks have developed on diaphragm. This might have happened due to improper supporting system, poor quality of concrete and improper compaction of concrete.
02-05-‘14
Wadkhal Flyover damaged girder J2 (Casting dt. 30-05-’13) is discarded and will not be put in use.
55 99 01-10-‘13 Wadkhal Flyover
Procedure for CPCC treatment is not being followed. Steel which is being used for reinforcement of Wadkhal girder has rust.
27-05-‘14 CPCC Treatment done and checked through RFI No-55680
56 100 04-10-‘13 Wadkhal
Girder P20 - P21 (LHS)
Anchor cone plate was broken and went inside after second stage stressing. This may be happened due to improper supporting system, poor quality of concrete and improper compaction of concrete.
02-05-‘14
Wadkhal Flyover damaged girder P20 -P21 (LHS) is discarded and will not be put in use.
57 103 07-01-‘14 5+000 VUP
(LHS)
During the concreting it was observed that the concrete mix of M-30G, slump measured 175 mm which is more than the specification limit of 75-125mm. This will affect the quality and durability of the structure.
07-05-‘14
Non-destructive test reports (Rebound Hammer test and Ultra Sonic Pulse Velocity test) conducted and observed that the concrete is of acceptable quality.
58 106 20-01-‘14 42+000 to 84+000
Hume pipes of 1200 mm diameter (NP3) procured for pipe culverts. These are not as per specifications. Also the frequency testing is not being carried out before procurement.
18-03-‘14
The RCC hume pipes intended for the Project were tested. Test results are satisfactory.
59 107 23-01-‘14 15+878
Reinforcement steel not stacked properly. Major stock of the steel is lying on the ground which leads to the corrosion.
25-05-‘14
The steel was re-stacked and checked through RFI No. 27298 dt. 08-02-2014
60 110 28-01-‘14
RE Panel Casting in Section-I
Casting Yard
Curing is not carried out on RE panel which is stacked in the casting yard. Further casting date is not mentioned in RE panels. This will effect the quality & durability of the RE panel.
10-05-‘14
Non-destructive test reports (Rebound Hammer test and Ultra Sonic Pulse Velocity test) conducted and observed that the concrete is of acceptable quality.
61 118 19-02-‘14 26+188 (RHS) Bhogeshwari
Concreting is carried out from transit mixer which
07-07-‘14 Cube compressive
strength results are
Panvel - Indapur MPR No-37 February '15 Page 60
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed on
Details of Rectifications Done
Bridge P1 & P2 crash barrier
parked on existing bridge without any safety measures. Also it is observed that concrete poured in chute without proper angle. This improper way of concreting is not acceptable.
acceptable.
Concessionaire confirmed that the traffic police was deployed to control the traffic movement. However, the Concessionaire is warned about the safety aspects during such works in future.
62 120 21-04-‘14 42+155 (RHS)
Unapproved/unsuitable soil dumped in the Panvel side approach of PUP at Ch. 42+155 (Kasu). This was notified during site inspection on 12-04-‘2014.
28-07-‘14
Un-approved material removed and balance material tested and found within acceptable limits.
63 126 21-04-‘14 42+155 (RHS)
RE wall backfill material laid without approval of the material.
19-07-‘14
The Third party test results for RE wall fill material conducted at SSA Lbs. Pvt. Ltd and found within specifications.
Table 4.2 Status of NCR’s Issued by Independent Engineer (Not yet closed out)
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
1 25 22-06-'12
21+200 to 21+890 Diversion
(RHS)
Diversion Plan not concurred and No Sign Board Provided.
2 26 22-06-'12 80+040 (RHS)
DBM Works without Removal of Electric Pole Ch. 80+040 (RHS) Main Carriageway.
3 28 16-07-'12 44+194
Nigade bridge A2 Raft.
Concreting was carried out With excavator and Chute without planning. Height of fall of concrete is more than 1.5 m and concrete is totally segregated. Due to delay placing of concrete, cold joints were formed and rain protection is not done.
4 31 22-11-'12 78+200 to 78+510 (RHS)
DBM Carried without Casting of Kerb, Development of Cracks, and DBM thickness is not adequate.
5 33 23-01-'13 68+988 Minor
Bridge
Highway alignment & structure alignment not matching
6 34 30-01-'13 52+155 (RHS) Minor Bridge
Honeycombing in Pier, 7th lift. This might have
Panvel - Indapur MPR No-37 February '15 Page 61
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
happened due to improper support, vibration and poor quality of concrete.
7 35 04-01-'13 23+650 (RHS)
Retaining wall under construction without concurrence of design & drawings. Provision for existing Pipe culvert on the retaining wall not provided.
8 37 20-02-'13 69+140 (RHS) Minor Bridge
Slab
SANGAM steel is used for reinforcement of deck slab without source approval.
9 38 21-02-'13 57+533
Box Culvert
The vertical main bars and slab main reinforcement SUN - TMX Un - approved steel used.
10 39 02-04-‘13
80+850 to 80+890 (Fresh Kerb Casting) and 80+890 to 81+140 (Old Laid Kerb) -
Casting of Kerb after cutting already laid DBM resulting in gap between Kerb and DBM. Development of crack on freshly laid Kerb. Saw cut grooves not made in the previously laid / old Kerb, development of cracks. No curing arrangement / application of curing compound.
11 41 17-04-‘13 24+550 to 24+730 (RHS)
DBM levels checked and found beyond permissible limits.
12 45 01-04-'13 52+335
Slab Culvert Slab culvert is widened on RHS side with pipe culvert.
13 47 03-05-'13 0+530 to 1+020
Diversion plan not submitted to IE for Concurrence. Entry (LHS) is very close to Minor bridge (km 0+545), where width is restricted due to construction of RCC crash barriers. Earthen shoulders in the entire stretch has not been made fully on LHS and RHS widening towards, existing road.
14 48 03-05-'13 25+330 to
25+900 (RHS)
Diversion plan not submitted to IE for Concurrence. Entry/exit are not smooth with sufficient length. Possible chances for overtopping of loaded vehicle coming from Indapur side and going towards Panvel while shifting from new carriageway to existing carriageway through
Panvel - Indapur MPR No-37 February '15 Page 62
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
insufficient length of merging due to big level difference and sharp turning towards left.
15 50 16-05-'13 0+544
DBM is laid on deck slab of minor bridge. (As per concurred drawing wearing course consists of 25 mm thick mastic asphalt overlaid by bituminous concrete).
16 58 28-05-'13 29+610 (LHS)
Non - removal of tree stump located at the left edge of existing road is safety hazard.
17 61 31-05-'13 70+560 (RHS)
NP4 pipe laid is not fitted and matched properly. Gap is observed in jointing of pipes and PCC is partially done below pipe.
18 62 14-06-'13
Due to improper stacking of RCC girders, one of the girder is tilled. It will affect the quality and safety of the structure.
19 63 15-06-'13 77+900 (RHS)
DBM Surface Totally damaged (new construction).
20 64 15-06-'13 78+180 to 78+460 (RHS)
DBM Surface Totally damaged (new construction).
21 65 15-06-'13 80+650 (LHS) DBM Overlaid surface totally damaged.
22 70 19-06-'13 2+400 (LHS)
Damage of DBM Edges due to Non Construction of Proper earthen Shoulders to left hand Carriageway.
23 71 19-06-'13 46+620 (RHS)
Damage of DBM towards Shoulder and lack of protection made to the slope of return wall of structure.
24 72 19-06-'13 0+000 to 42+800
Diversions provided on Project road are not conforming to IRC: SP: 55 and IRC: SP: 84.
25 73 19-06-'13 2+400 (RHS) and 2+780
(LHS)
DBM Settlement in the full width of New Carriageway.
26 74 19-06-'13 42+000 to 84+000
Diversions provided on Project road are not conforming to IRC: SP: 55 and IRC: SP: 84.
27 75 16-07-'13 53+661 (RHS)
“Vaishnav Prime” Steel used in slab Box culvert and it’s working drawing not
Panvel - Indapur MPR No-37 February '15 Page 63
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
submitted for IE’s Concurrence.
28 76 18-07-'13 81+606
Vave Bridge
Highway alignment and bridge alignment appears to be not matching.
29 77 19-07-'13 44+119
Nigade Bridge
Pile foundation work is carried out without conducting the initial pile load test and routine pile load test at P2 & P4 locations as per Clause-1113 of MoRTH specifications.
30 78 19-07-'13 15+480
Kharpada Bridge
Pile foundation work is carried out without conducting the initial pile load test and routine pile load test at A1, P1, P3, P4 & P5 locations as per Clause-1113 of MoRTH specifications.
31 79 22-07-'13 57+976 Patansai
The centerline of highway and bridge structure not matching. Center line of alignment not checked.
32 80 22-07-'13 62+348
Local Nallah
The centerline of highway and bridge structure not matching. Center line of alignment not checked.
33 81 22-07-'13 69+140 Local
Nallah
The centerline of highway and bridge structure not matching. Center line of alignment not checked.
34 82 23-07-'13 77+804
Bhuwan Bridge
The centerline of highway and bridge structure not matching. Center line of alignment not checked.
35 83 23-07-'13 52+089
Nidi Bridge
The centerline of highway and bridge structure not matching. Center line of alignment not checked.
36 84 23-07-'13 63+300
Local Nallah
The centerline of highway and bridge structure not matching. Center line of alignment not checked.
37 86 02-08-'13 15+878
kharpada bridge
Girder G-2 stacked improperly on ground. Supports are not provided on bearing point of girder and supports are sunk, due to poor ground strata. Cracks also observed on surface of girder, diaphragm wall reinforcement are bent.
Panvel - Indapur MPR No-37 February '15 Page 64
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
38 88 07-08-'13 Pali Plant
“VAISHNAVI PRIME” steel is used for reinforcement of friction slab and crash barrier without source approval.
39 90 08-08-'13
Wadkhal Flyover girder
(J-2 outer 7 no.)
Precast girder is lifted and shifted to the stacking yard without carrying the grouting operation of cable. Further, support provided below girder is not proper. This will affect the quality and durability of structure.
40 91 21-08-'13
Wadkhal Flyover girder
No-1 to 9 (J-2 outer)
Pre-stressed girder concrete for Wadkhal Flyover was done with 100 % crusher sand.
41 92 21-08-'13 15+878 (RHS)
SAIL EQR and VAISHNAV Prime steel used in G-A type (P-12 to P-13) girder without source approval. There is no CPCC treatment carried out on reinforcement.
42 93 27-08-'13
26+188 Bhogeshwari
Bridge (RHS)
“VAISHNAV Prime” steel used in deck slab (P4- P5) Without source approval. Also concrete slump observed at site is 180 mm. This is not acceptable as per MoRTH specification Clause-81704.1.
43 94 27-08-'13
26+188 Bhogeshwari
Bridge (RHS)
Structure cracks formed at the girder no. G4 (P5-A2) span near A2 side bearing.
44 95 27-08-'13 23+450 to 23 +480 (RHS)
Work carried out for the wall without concurrence of drawing. Also, SBC test is not carried out for foundation strata.
45 101 20-11-‘13 Minor/Major
Bridge Location
Crash barrier/hard rails are missing / broken in many locations. This is dangerous for the traffic and road users.
46 102 02-12-‘13
57+976 RHS Patansai
Bridge
The centerline of highway and bridge are not matching. The issue was notified many times, NCR No-79 already issued, slab is cast, and Centerline is still not modified.
47 104 07-01-‘14 5+000 (LHS)
Unapproved steel Vaishnav Prime TMT steel is used in Raft without concurrence
Panvel - Indapur MPR No-37 February '15 Page 65
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
from IE. Concreting of raft also done without concurrence.
48 105 18-01-‘14 22+800
Pipe Culvert
Pipe culvert at Ch. 22+800 is not constructed. Road work including WMM is completed at above location without construction of pipe culvert required as per Concession Agreement and concurred drawing.
49 108 27-01-‘14 27+100 (LHS)
Concreting of raft foundation is abruptly stopped due to shortage of cement. Due to this cold joint formed more than 50% area of raft which is structurally unsafe. Further concreting is resumed after more than 10 hours without concurrence of IE.
50 109 27-01-‘14
26+188 Bhogeshawari
Bridge Abutment A2
& Independent Return Wall.
Filter media behind abutment A2 is being laid without cleaning of weep holes.
51 111 30-01-‘14
26+188 (RHS)
Bhogeshwari Bridge
Major honey combing was observed in the bottom of I girder of P1-P2 span of Bhogeshwari bridge. This might have happened due to poor quality concrete and improper vibration.
52 112 30-01-‘14 38+245 to 39+380 (LHS)
DBM first layer had been laid from 38+245 to 39+380 (LHS) and diversion. During routine lab testing retained stability was found 67.42%, which is less than the required minimum stability (80% as per MoRTH).
53 113 30-01-‘14
22+705 to 22+900
(RHS) DBM
DBM is having very high marshall stability (2300 kg against the design of 1150 kg). The flow observed is 75 mm against the MoRTH value of 2-4 mm.
54 114 30-01-‘14
38+800 to 41+600 (LHS) and 22+700 to 22+900 (RHS)
Pneumatic Tyred Roller (PTR) has not been used for DBM compaction as per approved method statement.
Panvel - Indapur MPR No-37 February '15 Page 66
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
55 115 04-02-‘14 45+751 (LHS)
Structural cracks developed on the independent retaining wall (Panvel side) 3rd lift. This might have happened due to non-curing of structure.
56 116 04-02-‘14 60+984 (RHS)
Pipe culvert at above chainage is constructed without concurrence of working drawing. Also, it appears that pipe culvert top level is above Finished Road Level.
57 117 12-02-‘14 0+000 to 84+000
Drawing for applicable typical cross sections not yet submitted in spite of several reminders. This is very important during Project execution.
58 119 01-03-‘14 66+808 (RHS)
PCC and foundation is carried out without establishing/ confirming safe bearing capacity of foundation strata.
59 121 21-04-‘14
69+200 to 69+340 (RHS) & 69+800 to
69+900 (RHS).
Bituminous Concrete laid without constructing kerb.
60 122 21-04-‘14 58+040 (RHS)
(1) Kink formation due to abrupt merging of kerb near structure location. (2) Kerb line is out of alignment and not matching as per the latest concurred drawings.
61 123 21-04-‘14 61+330 to 61+410 (RHS)
Heaps of WMM mix dumped directly on the Bed of WMM first layer couple of days ago. The moisture from the WMM mix has already been dried up whereas it was required to be placed and rolled at a moisture content +1 or -2% of OMC.
62 124 21-04-‘14 44+155
Nigade (RHS)
Even after several reminders initial pile load test is not carried out. Further piling/ sub structure work is carried out at P2 and P4 locations without doing the initial and routine pile load tests.
Panvel - Indapur MPR No-37 February '15 Page 67
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
63 125 21-04-‘14 15+878 (LHS)
Even after several reminders initial pile load test is not carried out. Further piling/ substructure work is carried out at A1, P1, P3, P4, P5, P22, P23 and P24 locations without doing the initial and routine pile load tests.
64 127 21-04-‘14 70+227
Bituminous Concrete is laid on culvert slab and approach slab without laying mastic asphalt.
65 128 21-04-‘14 69+849
Bituminous Concrete is laid on culvert slab and approach slab without laying mastic asphalt.
66 129 21-04-‘14 57+976 (RHS)
Settlement of DBM and development of Cracks towards shoulder of freshly laid DBM in the approach to the minor bridge.
67 130 21-04-‘14 69+200 to 70+380 (RHS)
Surface Regularity Test not Carried Out Over DBM Surface - BC carried out in the above stretch without conducting the surface regularity test over the previously laid DBM surface.
68 131 21-04-‘14 26+188
Bhogeshwari bridge (RHS)
Abutment A2 Retaining Wall, it is observed that weep hole is not provided/cleaned before placing of filter media as per concurred drawing.
69 132 21-04-‘14 26+188
Bhogeshwari bridge (RHS)
Unapproved VAISHNAV 500 PRIME steel is used for reinforcement.
70 133 21-04-‘14 30+930 VUP Raft (RHS)
Unapproved SUN TMX and VAISHNAV 500 PRIME steel is used for reinforcement.
71 134 21-04-‘14 28+535 ROB R/w
(LHS)
Unapproved SUN TMX and VAISHNAV 500 PRIME steel is used for reinforcement.
72 135 21-04-‘14 71+000 to
71+050 (RHS)
Laying temperature of BC in the above stretch was checked and found 75.4° C, which is much below the required temperature as per MoRTH specifications.
Panvel - Indapur MPR No-37 February '15 Page 68
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
73 136 13-05-‘14
Kharpada Bridge G-1 Type 5/5 G. No-21 at Ch.
15+828
Compressive strength of M45 grade concrete found less than 45N/mm2 for 28 days strength testing (observed strength 39.56 N/mm2). The data recorded during test is enclosed.
74 137 13-05-‘14 Diversion at
Ch. 52+250 to 53+380
Diversion plan not submitted for IE’s concurrence. Diversion made at site is not as per IRC:SP:55 & Clause-112 of MoRTH specifications. Entry/Exit are not smooth.
75 138 13-05-‘14
Diversion at Ch.59+900 to
61+260
Diversion plan not submitted for IE’s concurrence. Diversion made at site is not as per IRC:SP:55 & Clause-112 of MoRTH specifications. Entry/Exit are not smooth.
76 139 13-05-‘14
Diversion at Ch. 69+200 to
71+990.
Diversion plan not submitted for IE’s concurrence. Diversion made at site is not as per IRC:SP:55 & Clause-112 of MoRTH specifications. Entry/Exit are not smooth.
77 140 23-05-‘14 Many locations
in Section-II
Excavated bituminous material spread over shoulder at many locations in section-II, which is a major environmental hazard. This was intimated through letter, site inspection etc many times. However, the same system is still being followed, which is highly un-acceptable.
78 141 26-05-‘14 46+500 (LHS). Shoulder not constructed and no Safety Barrier provided.
79 142 26-05-‘14 GSB at Ch. 52+500 to
52+750 (LHS)
GSB being spread haphazardly using JCB/Poclain and not with grader. The material used for GSB seems to be mixed with WMM material and not uniform. This is against the specifications and good engineering practice.
Panvel - Indapur MPR No-37 February '15 Page 69
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
80 143 26-05-‘14
WMM IInd Layer at Ch. 52+000 to
53+100 (LHS)
WMM IInd layer material directly dumped on the Ist layer and not being placed uniformly with paver and compacted immediately at OMC. This is against the specifications and Good Engineering Practice.
81 144 30-05-‘14 Kharpada
Bridge P5 Pier Cap
During site inspection it was observed that 16 mm, 12 mm, 10 mm, Vaishnav Prime TMT Steel is used for pier cap reinforcement. CPCC treatment not carried out properly.
82 145 30-05-‘14
Deck Slab of Nallah
diversion Ch. 4+930 to
4+950 (RHS)
Unapproved Vaishnav Prime TMT steel is used in pile Cap without source approval. CPCC of steel is not carried out properly.
83 146 30-05-‘14
Pier P3 Pile cap of
Kharpada Bridge
Unapproved steel Vaishnav Prime TMT was used in deck slab without source approval. CPCC of the steel is not carried out properly. Cover to the reinforcement not as per concurred drawing. Formwork, joint are not Leak proof and strong.
84 147 12-06-‘14
Pier Kharpada Bridge at Ch. 15+878- Pier P-9 to P-10
No safety arrangements are done at girder launching location. Gangway with handrail not constructed over pier cap. Ladder erected to inspect launching activity is very steep and without any hand rail. This is very dangerous and major safety hazard.
85 148 01-07-‘14
P11-P12 Girder No-25 & 26 Inner
Girder- Kharpada
Bridge
VAISHNAV 500 Prime steel is used for reinforcement. The above reinforcement steel source approve is not concurred by IE.
86 149 01-07-‘14
VUP Hamarapur at Ch. 23+460 (RHS) Raft
During site inspection of VUP Hamarapur raft, it is observed that VAISHNAV 500 Prime steel is used for reinforcement. The above reinforcement steel source approve is not concurred by IE.
Panvel - Indapur MPR No-37 February '15 Page 70
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
87 150 02-07-‘14 0+990 to
1+500
Road work carried out not as per concurred plan, profile and cross section drawings.
88 151 02-07-‘14 17+600 to
18+400
Road work carried out not as per concurred plan, profile and cross section drawings.
89 152 03-07-‘14 55+640 to
55+950
Road work carried out not as per concurred plan, profile and cross section drawings.
90 153 17-07-‘14
Box Culvert (Widening -
Service Road) at Ch. 41+960
(RHS)
“VAISHANV PRIME Steel 10 mm, 12mm, 16mm dia bar used in deck slab reinforcement. Vaishnav Prime steel source not concurred by IE.
91 154 18-07-‘14
Damage of DBM on New Carriageway
Ch. 61+090 to 61+150 (RHS)
DBM damaged badly on the stretch of new carriageway on RHS.
92 155 19-07-‘14
Development of many
Potholes/distress in BC in the stretch
Ch. 45+860 to 47+800 (LHS)
MCW
Several potholes/cracks have been developed in the newly laid BC at Ch. 45+870, 45+990, 46+470, 46+600, 46+760, 47+000, 47+040, 47+050, 47+250, 47+360 to 47+390, 47+10, 47+660.
93 156 22-08-‘14 Slab Culvert Ch. 77+997
(LHS)
Shoulder not constructed and no safety barrier provided (in spite of several reminders) at culvert.
94 157 22-08-‘14 Slab Culvert Ch. 78+167
(LHS)
No safety barrier provided (in spite of several reminders) and shoulder not constructed.
95 158 23-08-‘14
Deck Slab Reinforcement
VUP at Ch. 27+755 (LHS)
Un-approved “VAISHNAV PRIME TMT” steel is used in deck slab of VUP without source approval. CPCC treatment for steel is not carried out properly.
96 159 23-08-‘14 Box Culvert at Ch. 39+133
(LHS)
No safety barrier provided (in spite of several reminders) and shoulder not constructed.
Panvel - Indapur MPR No-37 February '15 Page 71
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
97 160 23-08-‘14 Median Drain at Ch. 80+700
to 81+100
(1) Work executed without concurrence of median drain drawings. (2) The cross chutes are constructed perpendicular to the highway which is not correct and not acceptable.
98 161 23-08-‘14
Development of Many
potholes/patches in the
newly laid BC at Ch. 69+200
to 71+800 (RHS)
Development of many potholes/patches in the newly laid BC at Ch. 69+200 to 69+380, 69+760 to 69+780, 69+965, 70+120 to 70+180, 70+570 & 71+040 and increasing day by day.
99 162 23-09-‘14
Pali Concrete Batching Plant at Ch. 66+545
to 66+599 (RHS)
PQC M(40) - The proportion of ingredients for PQC produced is different from mix design.
100 163 24-09-‘14 Badly
Distressed DBM locations
Badly Distressed DBM locations:
(1) 0+540 to 0+920 (LHS).
(2) 1+740 to 1+780 (LHS).
(3) 1+990 to 2+050 (RHS).
(4) 3+530 to 3+560 (LHS).
(5) 22+680 to 22+710 (RHS).
(6) 22+800 to 23+200 (RHS)
(7) 22+380 to 22+400 (RHS).
(8) 40+520 to 40+535 (LHS)
101 164 24-09-‘14 Badly
Distressed DBM locations
Badly Distressed DBM locations:
(1) 40+410 to 40+940 (LHS).
(2) 41+250 to 41+470 (LHS).
(3) 41+880 to 41+920 (LHS).
(4) 43+200 to 43+500 (LHS).
(5) 43+350 to 43+400 (RHS)
(6) 46+070 to 46+150 (RHS).
(7) 46+350 to 46+400 (RHS).
(8) 48+200 to 48+600 (LHS).
Panvel - Indapur MPR No-37 February '15 Page 72
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
102 165 24-09-‘14 Badly
Distressed DBM locations
Badly Distressed DBM locations:
(1) 52+240 to 52+590 (RHS).
(2) 53+210 to 53+240 (RHS).
(3) 54+930 to 60+060 (RHS).
(4) 60+190 to 60+210 (RHS).
(5) 61+150 to 61+230 (RHS).
(6) 63+450 to 63+850 (LHS).
(7) 63+730 to 63+530 (RHS).
(8) 69+530 to 69+600 (LHS).
103 166 24-09-‘14 Badly
Distressed DBM locations
Badly Distressed DBM locations:
(1) 77+880 to 77+910 (RHS).
(2) 77+900 to 78+800 (LHS).
(3) 78+300 to 78+310 (RHS).
(4) 79+780 to 81+120 (LHS).
(5) 80+120 to 80+160 (RHS).
(6) 80+200 to 80+300 (RHS).
(7) 80+400 to 80+500 (RHS).
(8) 80+700 to 80+750 (RHS).
104 167 24-09-‘14 Badly
Distressed DBM locations
Badly Distressed DBM locations:
(1) 81+000 to 81+500 (RHS).
(2) 81+250 to 81+450 (LHS).
(3) 82+730 to 83+020 (RHS).
(4) 82+880 to 82+940 (LHS).
105 168 29-09-‘14
Box Culvert Retaining Wall At Ch. 51+690
(LHS)
Concreting of retaining wall raft (Panvel side LHS is carried out without vibrators (Compaction not carried out). Also Vaishanv Prime steel is used in reinforcement for which source is not concurred.
Panvel - Indapur MPR No-37 February '15 Page 73
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
106 169 09-10-‘14 Box culvert at Ch. 45+977
(LHS)
Crash barrier finished concrete surface is not in line and level and totally bulged. This might have happened due to improper support and formwork is not strong. Honeycombing also observed in retaining wall 4th lift.
107 170 15-11-‘14 Slab culvert at Ch. 82+583
(LHS)
Unapproved steel Vaishnav Prime TMT used in crash barrier without concurrence from IE.
108 171 15-11-‘14
Median Drain at Ch. 69+980 to 70+350 & 82+900 to 84+300
(1) Work executed without concurrence of design and drawing.
(2) Proper curing is not done, several cracks developed in median drain wall and bottom PCC.
109 172 15-11-‘14
Median Drain at Ch. 45+890 to 46+120, 46+300 to 46+610, 47+210 to 47+620 and 52+330 to 52+670-
(1) Work executed without concurrence of design and drawing.
(2) Proper curing is not done, several cracks developed in median drain wall and bottom PCC.
110 173 19-11-‘14
Retaining Wall Raft at Ch. 23+400 to
23+410 (RHS)
“Vaishnav Prime TMT-500” steel is used for raft reinforcement without source approval. CPCC has not been carried out properly.
111 174 19-11-‘14
Retaining Wall Raft at Ch. 23+473 to
23+490 (LHS)
“Vaishnav Prime TMT-500” steel is used for raft reinforcement without source approval.
112 175 26-11-‘14 Retaining Wall at Ch. 83+920
(RHS)
Concreting done with chute having height of fall more than 1.5 m and concrete is totally segregated. This is not acceptable as per MoRTH specifications.
113 176 09-12-‘14
Approaches to Pen ROB- broken &
missing railing on either
sides-safety hazard
Railing provided on either sides of the approaches to pen ROB are found to be broken/missing at many places resulting into a major safety hazard to the road users. Concessionaire have not done the barricading in
Panvel - Indapur MPR No-37 February '15 Page 74
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
spite of several reminders.
114 177 09-12-‘14
Improper barricading at Ch. 22+600 to
23+250 (LHS)- safety
hazard
Deep road cutting on LHS improper and non-continuous barricading is provided causing safety hazard to the road users. Concessionaire have not provided crash barrier in spite of several reminders.
115 178 15-12-‘14
Retaining Wall Raft at Ch. 23+510 to
23+530 (RHS)
In spite of availability of concrete pump, concreting of raft was carried out using chute. Due to this, concrete is segregated and honey-combing developed. Reinforcement also not covered with concrete.
116 179 22-12-‘14
DBM top Level Checking
Ch. 40+220 to 40+780 (RHS) - RFI No. 6556 Ch. 51+920 to 52+090 (RHS) - RFI No. 22251. Ch. 57+360 to 57+510 (RHS) - RFI No. 22438.
With reference to above mentioned RFI’s, levels of DBM top surface were checked and found beyond permissible limits. These were intimated for rectification vide Our letter no. PIP/IE/SPITPL / 2014 / 2243 dated. 28-04-2014 but no rectification is carried out till date.
117 180 24-12-‘14
Section-I-Non Calibration of
Lab Equipments and Plant
Due date of machinery and plant calibration are finished and they are not re-calibrated.
118 181 24-01-‘15
Box Culvert Retaining wall
Raft at Ch. 51+690 (RHS).
Following deficiencies observed in formwork and reinforcement of foundation:
(1) Bottom cover is 20 mm only.
(2) Shuttering is not provided on One side.
(3) Totally waterlogged.
(4) Reinforcement lapping is not provided.
(5) Vaishnav Prime steel is used. (This source was never concurred).
In spite of above deficiencies, concreting was carried out.
Panvel - Indapur MPR No-37 February '15 Page 75
Sl No.
NCR No
Date Chainage
& Side
Description Rectifications Proposed
on
Details of Rectifications Done
119 182 09-02-‘15 Pipe Culvert at
Ch. 50+808 (RHS)
NP4 pipes laid is damaged
and reinforcement of pipe
also exposed near the joint.
Gap between jointing of
pipe is not as per
specification and finishing at
jointed surface is not in
consistence with exterior
and interior surface at pipe.
Honey combing also
observed in head wall of
pipe culvert. This is not
acceptable. This issue was
already discussed with EPC
Contractor and PMC.
120 183 26-02-‘15 Box Culvert at Ch. 66+808
(RHS)
(1) Construction joint for
the wall not done as
per specifications.
(2) Vaishanv Prime steel
used for both wall and
slab.
(3) Reinforcement steel
completely corroded
and not cleaned.
(4) Cover to reinforcement
is 30mm only which is
less than 50 mm.
121 184 28-02-‘15 Ch. 66+850 to 66+870 (LHS)
DLC not done
properly. The DLC
surface is loose and
having undulations.
Table 4.3 Details of Site Inspection Notes.
Inspection Note No Date
Site Inspection No-1 22-02-2012 & 29-02-2012
Site Inspection No-2 15-03-2012
Site Inspection No-3 29-03-2012
Site Inspection No-4 20-04-2012
Site Inspection No-5 30-05-2012
Site Inspection No-6 11-06-2012
Site Inspection No-7 23-06-2012
Site Inspection No-8 28-08-2012
Panvel - Indapur MPR No-37 February '15 Page 76
Inspection Note No Date
Site Inspection No-9 22-10-2012
Site Inspection No-10 07-11-2012
Site Inspection No-11 03-12-2012
Site Inspection No-12 20-12-2012
Site Inspection No-13 04-01-2013
Site Inspection No-14 16-01-2013
Site Inspection No-15 31-01-2013
Site Inspection No-16 13-02-2013
Site Inspection No-17 26-02-2013
Site Inspection No-18 15-03-2013
Site Inspection No-19 26-03-2013
Site Inspection No-20 12-04-2013
Site Inspection No-21 29-04-2013
Site Inspection No-22 27-05-2013
Site Inspection No-23 15-06-2013
Site Inspection No-24 17-07-2013
Site Inspection No-25 23-08-2013
Site Inspection No-26 26-09-2013
Site Inspection No-27 28-10-2013
Site Inspection No-28 28-11-2013
Site Inspection No-29 31-12-2013
Site Inspection No-30 15-01-2014
Site Inspection No-31 19-02-2014
Site Inspection No-32 19-03-2014
Site Inspection No-33 10-04-2014
Site Inspection No-34 22-04-2014
Site Inspection No-35 08-05-2014
Site Inspection No-36 22-05-2014
Site Inspection No-37 13-06-2014
Site Inspection No-38 16-07-2014
Site Inspection No-39 08-08-2014
Site Inspection No-40 30-09-2014
Site Inspection No-41 21-10-2014
Site Inspection No-42 25-11-2014
Site Inspection No-43 17-12-2014
Site Inspection No-44 13-01-2015
Site Inspection No-45 06-02-2015
Panvel - Indapur MPR No-37 February '15 Page 77
Table 4.4. Details of Audit Reports
Table 4.5 Details of Tests Carried Out (Nos)
Material Test Reference Up to Last
Month
During the
Month
Cumulative Including this Month
Cumulative
Failed
Cumulative Nos
Witnessed by IE
Earthwork in Embankment
(a) Sand Content IS:2720 (Part-4) 2153 0 2153 0 472
(b) Liquid Limit Test IS:2720 (Part-5) 2152 0 2152 0 472
(c ) Plasticity Test IS:2720 (Part-5) 2152 0 2152 0 472
(d) Lab. Density test IS:2720 (Part-8) 2152 0 2152 0 472
(f) Moisture content test IS:2720 (Part-2) 3398 153 3551 0 355
(g) Field Density by sand replacement method
IS:2720 (Part-28) 4769 465 5234 5 503
Subgrade
(a) Sand Content IS:2720 (Part-4) 808 12 820 0 88
(b) Liquid Limit Test IS:2720 (Part-5) 808 12 820 0 88
(c) Plasticity Test IS:2720 (Part-5) 808 12 820 0 88
(d) Lab. Dry Density IS:2720 (Part-8) 808 12 820 0 88
(f) Moisture content test IS:2720 (Part-2) 3668 42 3710 0 373
(g) CBR Test IS:2720 (Part-16) 399 13 412 0 50
(h) Field Density by sand replacement method
IS:2720 (Part-28) 4834 150 4984 17 501
Granular Subbase
(a) Gradation IS 2386 (Part-1) 1420 9 1429 0 155
(b) Liquid Limit Test IS:2720 (Part-5) 1402 9 1411 0 147
(c) Plasticity Test IS:2720 (Part-5) 1402 9 1411 0 147
(d) Moisture content Prior to compaction
IS: 2720 ( Part-2) 2533 4 2537 0 260
(e) CBR test IS:2720 (Part-16) 2 0 2 0 1
(f)Density of compacted layer
IS:2720 (Part-28) 3677 27 3704 1 376
(g) Water absorption IS: 2386 ( part-3) 16 0 16 0 2
(h) 10% Fines BS:812 (Part-III) 6 0 6 0 2
Wet Mix Macadam (Crushed Stone Aggregates)
(a) Gradation IS 2386 (Part-1) 2173 3 2176 0 226
(b) Aggregate Impact value
IS:2386 (Part-4) 1925 2 1927 0 196
(c) Water Absorption IS: 2386 ( Part-3) 26 0 26 0 14
(d) Flakiness and Elongation Index
IS: 2386 (Part-1) 1653 2 1655 0 173
(e) Liquid Limit Test IS:2720 (Part-5) 1969 2 1971 0 202
(f) Plasticity Test IS:2720 (Part-5) 1955 2 1957 0 202
(g ) Field Density by sand replace method
IS:2720 (Part-28) 2892 6 2898 7 291
Ordinary Portland Cement
(a) Fineness
277 3 280 0 52
(b) Initial Setting time 292 3 295 0 42
(c) Final Setting time 292 3 295 0 42
(d) Compressive Strength
3 Days 288 3 291 0 41
7 Days 285 3 288 0 41
28 Days 281 1 282 0 40
Sl. No Audit Report No Date of Audit
1 Audit Report No-1 13-12-2012
2 Audit Report No-2 14-12-2012
Panvel - Indapur MPR No-37 February '15 Page 78
Material Test Reference Up to Last
Month
During the
Month
Cumulative Including this Month
Cumulative
Failed
Cumulative Nos
Witnessed by IE
(e) Chemical Requirements
5 0 5 0 -
Coarse Aggregates
(a) Gradation Individual & All in One Agg.
IS:383 and MORT&H
Table1000-1 4367 54 4421 0 465
(b) Water absorption IS:2386 (Part3) 188 0 188 0 20
(c) Specific gravity IS:2386 (Part3) 159 0 159 0 17
(d)Los Angeles abrasion value
IS:2386 (Part4) 107 0 107 0 10
(e) Aggregate Impact value
837 4 841 0 100
(f) Flakiness and Elongation Index
IS:2386 (Part-1) 772 4 776 0 89
(g) Soundness IS:2386 (Part5) 14 0 14 0 0
(h)Alkali-aggregate reactivity
IS:2386 (Part7) 11 0 11 0 0
Fine Aggregates
(a) Gradation IS:383 and
MORT&H Table 1000-1
2219 18 2237 0 419
(b) Water absorption IS:2386 (Part3) 150 0 150 0 15
(c) Specific gravity IS:2386 (Part3) 132 0 132 0 15
(d) Fineness Modulus Section 1008 of
MORT&H 2150 18 2168 0 419
Water Chemical Tests
(a) Organic matter
10 0 10 0 -
(b) Inorganic matter 10 0 10 0 -
(c) Sulphates(as So4) 22 0 22 0 2
(d) Suspended matter 10 0 10 0 -
(e) Chlorides(as Cl) 22 0 22 0 2
(f) pH Value 22 0 22 0 2
Admixtures
(a) Dry material content
16 0 16 0 -
(b) Ash content 16 0 16 0 -
(c) Relative Density 16 0 16 0 -
(d) Chloride ion content 16 0 16 0 -
(e) pH value 16 0 16 0 -
Concrete
(a)Compressive/ Flexural Strength
Section 900 and Section 1700 of
MORT&H IS:516 - - - - -
For M-15 Grade 7 Days 1354 2 1356 1 384
28 Days 1940 0 1940 0 550
For M-20 Grade 7 Days 2031 17 2048 2 568
28 Days 3454 9 3463 3 648
For M-25 Grade 7 Days 790 2 792 1 154
28 Days 1203 2 1205 1 348
For M-30 Grade 7 Days 998 2 1000 1 204
28 Days 2269 0 2269 2 450
For M-35 Grade 7 Days 721 0 721 0 133
28 Days 1157 0 1157 5 326
For M-40 Grade (Str.) 7 Days 318 1 319 2 36
28 Days 326 0 326 0 52
For M-20 Grade Kerb 7 Days 328 0 328 1 51
28 Days 487 0 487 0 99
For M-35 Kharpada 7 Days 88 0 88 0 8
28 Days 246 0 246 0 25
For M-40 Kharpada 7 Days 21 0 21 0 2
28 Days 76 0 76 0 7
For M-45 Girder 7 Days 32 0 32 1 5
Panvel - Indapur MPR No-37 February '15 Page 79
Material Test Reference Up to Last
Month
During the
Month
Cumulative Including this Month
Cumulative
Failed
Cumulative Nos
Witnessed by IE
28 Days 95 0 95 3 15
For PQC 7 Days 24 0 24 0 5
28 Days 24 0 24 0 5
For DLC
9 1 10 0 5
Reinforcing Steel
(a) Chemical Analysis
IS:1786-1985 IS:1608-1972 IS:226-1975 IS:1599-1974
IS:2770 (Part 1)-1967
- - - - -
% of Carbon 40 0 40 0 0
% of Sulphur 40 0 40 0 0
% of Phosphorus 40 0 40 0 0
(b) Nominal Mass 298 0 298 0 0
(c) 0.2 %Proof Stress 299 0 299 0 0
(d) Tensile Strength 299 0 299 0 0
(e) Elongation % 299 0 299 0 0
(g) Bend Test 299 0 299 0 0
(h) Rebend Test 299 0 299 0 0
NP4 class precast 1000mm dia pipe
Physical test IS: 458 28 0 28 0 1
NP4 class precast 1200mm dia pipe
Physical test
28 0 28 0 1
Prime Coat (Bituminous Emulsion)
Rate of Application IS:8887 &
MORT&H CI.502 891 0 891 0 90
Track Coat (Bituminous Emulsion)
Rate of Application IS:8887 &
MORT&H CI.503 923 0 923 0 92
Dense Bituminous Macadam
(a) Quality of Binder (VG-30)
IS:73 - - - - -
(i) Presentation IS:73 65 0 65 0 30
(ii) Softening Point IS:73 65 0 65 0 30
(iii) Ductility IS:73 65 0 65 0 7
(iv) Flash and Fire Point IS:73 40 0 40 0 5
(b) Aggregate Impact Value
IS:2386 (Part-4)
879 0 879 0 88
(c) Los Angeles Abrasion test
17 0 17 0 7
(d) Flakiness and Elongation Index
IS:2386 (Part-1) 879 0 879 0 88
(e) Stripping Value IS:6241 and
AASTHO-T182 25 0 25 0 3
(f) Water Absorption of Aggregated
2 0 2 0 1
(g) Soundness I670S:2386 (Part-
5) 2 0 2 0 0
(h) Grading MORT&H Tables 500.9
MORT&H 265 0 265 0 48
(i) Bitumen Content % 265 0 265 0 48
(j) Density of Compacted layer % by 100mm Dia core
1758 0 1758 0 283
(k) Stability of Mix ASTM D 1559 and As per MORT&H Tables 500-11
265 0 265 2 36
(l) Flow of Mix 265 0 265 0 36
Panvel - Indapur MPR No-37 February '15 Page 80
Material Test Reference Up to Last
Month
During the
Month
Cumulative Including this Month
Cumulative
Failed
Cumulative Nos
Witnessed by IE
(m) Water sensitivity of Mix
4 0 4 1 1
Bituminous Concrete
(a) Aggregate Impact value
IS:2386 (Part-4) 32 0 32 0 4
(b) Flakiness and Elongation Index
IS:2386 (Part-1) 32 0 32 0 4
(c) Stripping value IS: 6241
and AASTHO T- 182
1 0 1 0 1
(d) Grading MORT&H Table 500.9
MORT&H 10 0 10 0 3
(e) Bitumen Content % 10 0 10 0 4
(f) Density of Compacted layer % by 100mmDia core
163 0 163 0 18
(g) Stability of Mix ASTM D 1559 and
As per MORT&H Table
500-11
10 0 10 0 4
(h) Flow of Mix 10 0 10 0 4
(i) Water Sensitivity of mix
1 0 1 0 1
It has been observed that the following equipments which are required as per MoRTH norms
are not available in the laboratory:
Section-I:
Sl. No
Name of Equipment Capacity Required (as per MoRTH )
Remarks
1 Hydro Meter 1.2 gram per/CC 1 No -
2 Compression Testing
Machine(CTM) Standard 1 No -
3 Marshall Mould Testing Machine (Stability Test)
Standard 1 No -
4 Viscosity Machine for Emulsion
Standard 1 No -
5 Thin Film oven Standard 1 No -
6 High Speed Stirrer Standard 1 No -
7 Hot Plates 200 dia (1500W) 1500w 1 No -
8 Kinematic Viscometer Standard 1 No -
9 Absolute Viscometer Standard 1 No -
10 Specific Gravity Bottle 25 ml 2 Nos -
11 Sand Equivalent Apparatus Standard 1 No -
Panvel - Indapur MPR No-37 February '15 Page 81
Section-II:
* Concessionaire has been advised many times to procure above missing items for their
laboratory.
Sl. No
Name of Equipment Capacity Required (as per
MORTH)
Remarks
1 Hydro Meter 1.2 gram per/CC 1 No -
2 Stop watch 0.5 sec accuracy 1 No -
3 UCS Testing Machine Standard 1 No -
4 Aggregate Crushing Value Standard 1 No -
5 10% Fines Value Standard 1 No -
6 Loss Angeles Abbrassion Value
Standard 1 No Break down
7 Wire Basket for WA/SP GR 2.36 mm Mesh 1 No Not in order
8 DLC Hammer (chipper) 15 cm cube
Assemble 1 No Break down
9 Water Testing Kit Standard 1 No -
10 GMM Test Vaccune Pump
with Glass Flask 2 lit 1 No -
11 Ductility Test Standard 1 No -
12 Viscosity Machine for Emulsion
Standard 1 No -
13 Thin Film oven Standard 1 No -
14 High Speed Stirrer Standard 1 No -
15 Kinematic Viscometer Standard 1 No -
16 Absolute Viscometer Standard 1 No -
17 Specific Gravity Bottle 25 ml 2 Nos -
18 Sand Equivalent Apparatus Standard 1 No -
Panvel - Indapur MPR No-37 February '15 Page 82
5.0 TRAFFIC & SAFETY
5.1 Safety Issues
(1) There is an urgent need to provide all the required traffic control & safety
devices viz., signs, delineators, blinkers, barriers, etc. at the work sites as per
relevant standards viz, NHAI-Technical Specifications, IRC-SP-55 & IRC-SP-84
wherever lapses are observed.
(2) All ‘Working Zone’ must be provided with adequate lateral & longitudinal buffer
clearances as per IRC-SP-55.
(3) Workers at site must be provided with necessary PPE viz., Safety Shoe, Gloves,
Jackets, etc.
(4) Traffic Diversions are potential accident spots since vehicles approach the
diversions at high speeds. Appropriate temporary signs, delineators, blinkers,
New Jersey barriers & barricades must be provided at the diversions and at
proper locations to guide the vehicles to safety before passing by the work
zones.
(5) The Concessionaire have been advised to comply the deficiencies observed in
the traffic safety measures taken.
(6) Traffic diversions are potential accident spots during construction period.
Necessary signs to be provided at such locations. Many of the diversions
provided at site are sharp and not with proper geometry which leads to
accidents. Many letters are issued to Concessionaire to rectify the safety issues
at site.
5.2 Accident data
The accident data is given in Appendix-I.
5.3 Maintenance of Existing Highway
Concessionaire is being advised to maintain the existing highway to traffic-worthy
condition. Site Inspection notes / letters are issued to Concessionaire in this regard.
Many potholes / patches were observed on the Project Highway. Further, advices
were given to the Concessionaire to maintain the hand rail of structures, vents of
structures etc. But, The Concessionaire is not maintaining the Project highway
properly in spite of several reminders.
Concession Agreement, Vol-I, Clause-12.2 specifies that “During the construction
period the Concessionaire shall maintain, at its cost, the existing lane(s) of the
Project Highways so that the traffic worthiness and safety thereof are at no time
Panvel - Indapur MPR No-37 February '15 Page 83
materially inferior as compared to their condition 7 (Seven) days prior to the date of
this Agreement, and shall undertake the necessary repair and maintenance works for
this purpose; provided that the Concessionaire may, at its cost, interrupt and divert
the flow of traffic if such interruption and diversion is necessary for the efficient
progress of Construction Works and conforms to Good Industry Practice; provided
further that such interruption and diversion shall be undertaken by the
Concessionaire only with the prior written approval of the Independent Engineer
which approval shall not be unreasonably withheld. For the avoidance of doubt, it is
agreed that the Concessionaire shall at all times be responsible for ensuring safe
operation of the Project Highway.”
Panvel - Indapur MPR No-37 February '15 Page 84
6.0 CONTRACTUAL ISSUES
6.1 Change of Scope
The Details of Change of Scope proposals considered are given in Table 6.1. The Change of
Scope Proposal rejected by Independent Engineer are given in Table 6.2.
Table 6.1 Details of Change of Scope Proposals considered:
Sl No
Description of Change of Scope
Appr. Cost Implication
(Rs. Crores)
Status
1 Deletion of Palaspe Flyover at Ch. 0+260
(-) 28.30** Approved in principle by NHAI. Concessionaire has not submitted detailed quantities in proper order so far.
2 Nallah diversion through box culvert at Ch. 4+900 to 4+993
(+) 3.449* Clarifications are yet to be submitted by Concessionaire. Change of Scope is pending at NHAI HQ.
3 Mitigation Measures in Karnala Bird Sanctuary Area.
(+) 55.88 **
NHAI has approved in principle. Concessionaire was advised to submit detailed proposal. However, NBWL’s clearance not yet obtained.
4 Shifting the location of Jite PUP (from Ch. 18+240 to 18+700)
Nil NHAI has approved this Change of Scope with no Financial implication
5 Deletion of pipe culvert at Ch. 22+798
- Concessionaire is advised to submit clarifications.
6 VUP at 23+450 (Hamarapur) on RHS main carriageway.
-
Proposal to be modified by Concessionaire considering that the additional VUP (as envisaged in CA) to be constructed at this location. Concessionaire is advised to submit details.
7 Underpasses in Pen City (+) 8.38 * Approved in principle by NHAI.
8 Change in number of spans of ROB at Pen Ch. 28+283
(+) 14.25 * Recommended to NHAI. Clarifications also sent to NHAI. Pending with NHAI.
9 Increase in length of Wadkhal Bypass by 805m
(+) 0.81 * Approved in principle by NHAI.
10 Increase in Span for Structure at Ch. 38+336 and Ch. 43+133
(+) 0.6663 * Change of Scope proposal recommended to NHAI. Clarifications submitted to NHAI. Pending with NHAI, HQ.
11 Additional Culverts at various locations
(+) 2.52 * Approved in principle by NHAI.
12 Increase in Length of Service Road
Nil Recommended to NHAI. Clarifications submitted to NHAI. Pending with NHAI, RO.
13 Exit/entry Ramps at the Start and End of Service Road
- Concessionaire yet to submit the compliances.
* Excluding overhead cost claimed by Concessionaire.
** Including Overhead Cost.
Table 6.2 Details of Change of Scope Proposals Rejected by Independent Engineer
Sl No
Description of Change of Scope
Appr. Cost Implication
(Rs. Crores)
Status
1 Nallah diversion through box (+) 7.6147 * Sufficient land available for diversion of
Panvel - Indapur MPR No-37 February '15 Page 85
Sl No
Description of Change of Scope
Appr. Cost Implication
(Rs. Crores)
Status
culvert at Ch. 4+700 to 4+800 and 5+700 to 5+800.
Nallah. Accordingly, Change of Scope is not admissible.
2 Retaining wall at Ch. 16+720 to 16+870 (LHS & 23+430 to 23+480 (LHS)
(+) 1.07 * In both the stretches the ROW available is 60m. Hence Change of Scope is not admissible.
3 Retaining Wall at Ch. 23+400 to 23+640 (RHS)
(+) 1.95 *
Concessionaire has not followed the procedures for Change of Scope. CIDCO water pipeline at this location was already buried in embankment without any protection measures. Thus, Change of scope not admissible.
4 Wadkhal Bypass by changing ROB to RUB
(+) 20.63 Concessionaire is advised to construct ROB as per provisions of Concession Agreement.
5 Reconstruction of Damaged Slab culvert at Ch 39+030 & 39+133
(+) 0.265 * Change of scope not admissible as it comes under rehabilitation.
6
Additional VUP on both ends of Amba Bridge. (Pali Junction at Ch. 58+660 and Roha/ Alibaug Junction at Ch. 58+960)
(+) 23.38 * NHAI has rejected the proposal and advised Concessionaire to proceed as per Concession Agreement.
7
Difference in width of median for approach to Underpasses / Flyovers / ROB etc Type - X Section
- Rejected as it is not admissible as per Concession Agreement provisions
8 Concrete pavement below RUB at Ch. 56+560 (Nagothane)
- Rejected as it is required as per site conditions and vertical clearance requirements.
* Excluding overhead cost.
Our records show that Concessionaire has not submitted necessary clarifications /details
for the following Changes of Scope in spite of several reminders:
Sl No
Description of Change of Scope
Status
1 Deletion of Palaspe Flyover at Ch. 0+260
Approved in principle by NHAI. Concessionaire has not submitted detailed quantities in proper order so far.
2 Nallah diversion through box culvert at Ch. 4+900 to 4+993
Clarifications are yet to be submitted by Concessionaire.
3 Deletion of pipe culvert at Ch. 22+798
Concessionaire is advised to submit clarifications.
4 VUP at 23+450 (Hamarapur) on RHS main carriageway.
Proposal to be modified by Concessionaire considering that the additional VUP (as envisaged in CA) to be constructed at this location. Concessionaire is advised to submit details.
5 Underpasses in Pen City Approved in principle by NHAI. Concessionaire has not submitted detailed quantities so far.
6 Additional Culverts at various locations
Approved in principle by NHAI. Concessionaire has not submitted detailed quantities so far.
Panvel - Indapur MPR No-37 February '15 Page 86
Sl No
Description of Change of Scope
Status
7 Exit/Entry Ramps at Start and End of Service road
Compliance to the observations not yet submitted.
6.2 Project Milestones
Project Milestone - I
The Concessionaire has to achieve Project Milestone - I by 19-12-2012 as per
Schedule - G of the Concession Agreement. They have requested/applied for shifting
the date of Project Milestone - I for a period of 135 days. The Independent Engineer
advised the Concessionaire to submit the details of actual progress (both Physical &
Financial) with substantiating supporting details to enable Independent Engineer to
critically analyse the case.
Concession Agreement, Clause-13.4, Specify that ”Without prejudice to the provision
of Clause 12.4.2 if the Concessionaire does not achieve any of Project Milestone or
the Independent Engineer shall have reasonably determined that the rate of Progress
of Construction works is such that Four-Laning is not likely to be achieved by the
Scheduled Four-laning date, it shall notify the Concessionaire to this effect, and the
Concessionaire shall, within 15 (fifteen) days of such notice, by a communication
inform the Independent Engineer in reasonable detail about the steps it proposes to
take to expedite Progress and the period within which it shall achieve the Project
Completion Date”.
Concession Agreement Clause-12.4.2 Specify that “The Concessionaire shall construct
the Project Highway in accordance with the Project completion Schedule set forth in
Schedule-G. In the invent that the Concessionaire fails to achieve any Project
Milestone within the period of 90 (Ninety) days from the date set forth for such
Milestone in Schedule-G, unless such failure has occurred due to force Majeure or for
reasons solely attributable to the Authority, it shall pay Damages to the Authority in a
Sum calculated at the rate of 0.1% (zero point of one per cent) of the amount of
Performance Security for delay of each day until such Milestones is achieved;
provided that if any or all project milestone or the scheduled four-Laning Date are
extended in accordance with the provisions of this Agreement, the date set forth in
Schedule-G shall be deemed to be modified accordingly and the Provisions of this
Agreement shall apply as if schedule-G has been amended as above; provided further
that in the event Project Completion Date is achieved on or before the scheduled
Four- Laning, date the Damage paid under this Clause- 12.4.2 shall be refunded by
the Authority to the Concessionaire, but without any interest thereon. For the
avoidance of doubt, it is agreed that recovery of Damage under this Clause-12.4.2
Panvel - Indapur MPR No-37 February '15 Page 87
shall be without prejudice to the right of the Authority under this Agreement
including the right of Termination thereof.”
Independent Engineer has critically assessed the allowable Extension of Time (EOT)
for achieving Milestone-1. Accordingly, it was observed that the allowable Extension
of Time (EOT) due to various issues such as delayed handing over of land, delay in
approval of GAD for ROB’s, delay in shifting of various utilities etc. is assessed to be
152 days (That is upto 20-05-2013). However, Concessionaire requested for
Extension of Time, for 135 days from stipulated Milestone -1 date (That is upto 03-
05-2013). Accordingly, Independent Engineer has recommended the Extension of
Time upto 03-05-2013, based on following conditions to be agreed by
Concessionaire.
(a) Concessionaire will not be eligible for any extension of Concession Period on
account of extension of Milestone No-1.
(b) Concessionaire will complete the Milestone No-1 by 03-05-2013 (135 days from
scheduled Milestone No-1 date).
(c) No damages for delay in handing over of land/approval of estimate for utility
shifting/Force Majeure during the period upto extended period of Milestone No-1
(that is upto 03-05-2013) will be claimed as the Extension of Time (EOT)
granted is mutually agreeable to the Concessionaire.
(d) The additional machineries and manpower as promised will be mobilized
immediately.
(e) Further scheduled completion milestone dates including final completion will not
get extended due to extension of Milestone No-1 as provided in schedule ‘G’ of
the Concession Agreement.
While recommending Extension of Time for Milestone no-1, Independent Engineer
has critically assessed and concluded that Concessionaire is eligible for 152 days
extension (That is upto 20-05-2013). However, Concessionaire has requested for
Extension of Time for 135 days only which fall on 03-05-2013. The Milestone no-1
was achieved on 01-05-2013 that is 133rd day from Schedule milestone no-1 date,
which was within the recommended period of Extension of Time. Executive
committee of NHAI has approved EOT upto 01-05’2013
Project Milestone - II
The Concessionaire has to achieve Project Milestone-II by 19-12-2013 as per
Schedule-G of the Concession Agreement. Concessionaire vide their letter no.
SPITPL/P-NHAI/2013-14/2471 dt 28-01-’14 has claimed and informed NHAI that they
have achieved Milestone-II by 19-12-’13 considering the land made available for
Panvel - Indapur MPR No-37 February '15 Page 88
construction. Independent Engineer has reviewed and commented vide letter
no. PIP/IE/NHAI/2014/2164 dt. 03-04-2014. NHAI has advised Concessionaire to
submit undertaking specifying unconditional waiver. In the modified revised
construction programme for Project completion submitted by Concessionaire, they
have indicated that they will achieve Milestone-II by August 2015. The executive
committee of NHAI has approved Extension of Time to achieve Milestone - II upto
31-10-2015.
Four Laning (Project Completion)
Concessionaire did not achieve the Four Laning (Project Completion) as stipulated in
Concession Agreement. Concessionaire has cited various issues such as delay in
handing over of encumbrance - free land, utility shifting, non - removal of
encroachments etc. Concessionaire has requested Extension of Time (EOT) for 898
days (That means upto 30 Nov 2016). It is to be re- iterated that Concessionaire
should also continue to initiate pro-active role in land acquisition and removal of
encumbrances. Further, in the review meeting by Member (PPP) at NHAI Hq on 31-
10-‘14, it was advised to re-visit the EOT issue and submit revised recommendations
alongwith draft supplementary agreement. Accordingly, Independent Engineer
critically analysed various aspects of the issues related to Four Laning (Project
Completion) and following recommendations were made:
(a) The status and Independent Engineer’s recommendations for various
Milestones are given below :
Project Milestone Dates specified
in CA Revised dates
Milestone - I (25% Physical Progress and 25% Financial Progress)
19-12-2012 Already achieved on 01-05-2013
Milestone - II (65% Physical Progress and 65% Financial Progress )
19-12-2013 31-10-2015
Four-Laning (except Eco-Sensitive zone) 16-06-2014 31-03-2016
Completion of the Eco-Sensitive Zone provided land is made available within three months from date of this
Supplementary Agreement
16-06-2014 30-06-2016
(b) The Concessionaire has not been able to achieve completion of Four-Laning on
scheduled date (16-06-2014) but the delay is not solely attributable to the
Authority. However, land fronts are hindered at some locations due to
requirement of forest diversion, missing guts, pending valuation of structures,
variation in the area notified and acquired, non-payment of existing structures
on acquired land, re-measurements, non-payment for land acquired, area falls
in the ROW of 60m but not notified under 3A/3D etc., lack of sufficient support
Panvel - Indapur MPR No-37 February '15 Page 89
from revenue authorities for finalisation of joint measurement of disputed land
etc. It may be noted that the delay is beyond the control of Authority /
Concessionaire. Accordingly, it is recommended that a Supplementary
Agreement may be executed. Draft Supplementary Agreement in this regard
was submitted to NHAI.
(c) Concessionaire may be instructed to submit corrected and detailed catch-up
programme considering the Extension of Time (EOT) upto 31-03-2016.
(d) Both the parties ie, NHAI and Supreme Panvel Indapur Tollways Pvt. Ltd.
hereby mutually waive off all damages/penalties payable on account of not
fulfilling conditions precedent as per Articles 4, 10, 35 of Concession Agreement
or any other provision of the Concession Agreement.
(e) The Concessionaire also undertakes to provide all the necessary assistance to
Authority in terms of equipments, machineries, manpower, construction
materials etc. for:
(i) Getting the encroachments cleared from the project site.
(ii) Taking over the project sections and starting the construction work
immediately on Project sections where encroachments are removed or
land acquisition/possession is handed over and complete the same within
the extended period.
(f) The Concessionaire also agrees to maintain the project highway in traffic
worthy condition as per provisions in the Concession Agreement.
Concessionaire has recently submitted detailed construction programme showing
completion of stretch from 0+000 to 20+100 by June ’16 and stretch from 20+100
to 84+600 by March ’16. Independent Engineer has recommended the same to NHAI
for approval alongwith EOT. The executive committee of NHAI has approved
Extension of Time upto 31-03-2016 (Except Eco-Sensitive Zone).
6.3 Land Acquisition issue between Balganga Major Bridge (Ch. 20+144) and
Balivali Minor Bridge (Ch. 20+754):
As per Concession Agreement, Vol-II, Schedule-B, Appendix B1, page no-41A, two
lane new bridge for Balganga river at Ch 20+144 has to be constructed on RHS and
as per Appendix B2, page no-41B, two-lane new bridge has to be constructed on LHS
for Balivali river at Ch. 20+754. Balganga bridge is in advanced stage of construction
and Balivali bridge has almost completed. The land acquisition is done on the right
side between the above two bridges and thus the highway portion between two
bridges cannot be constructed.
Panvel - Indapur MPR No-37 February '15 Page 90
6.4 Un-approved Steel in use:
Conditional Source approval for steel from M/s Shree Vaishnav Alloys Pvt. Ltd was
concurred on 01-05-’12 based on the condition that the challans for billets (from
main and major producers) and Manufacturer Test Certificate (MTC) will be
submitted. Meanwhile NHAI informed that the steel shall be procured from main and
major producers only as per IRC: SP: 84-2009 which are SAIL, IRNL, TATA, ESSAR,
ISPAT, JSW Steel Ltd and JSL. No re- rolled steel shall be permitted in NHAI works.
In some of the minor bridges, Concessionaire has used Sangam TMT, SUN TMT etc.
also which were notified to the Concessionaire through various NCR’s, Site Inspection
Reports, letters etc. Concessionaire was strictly advised to use steel produced from
main and major producers only as per NHAI’s circulars. The source approval for M/s
Shree Vaishanav Alloys Pvt. Ltd. was withdrawn with affect from 25-07-’13. Even
after withdrawing concurrence, Concessionaire has been using un-approved steel in
many structures. Engineer has issued letter to Concessionaire warning them that IE
will be constrained to initiate necessary punitive action as per the provisions of
Concession Agreement without any further notice.
6.5 Non construction of Exit/Entry Ramps for Service Road:
Due to non-availability of additional land for constructing the entry/exit ramps for
service road as stipulated in IRC: SP : 84-2010, it was proposed to construct tapers
at such locations. NHAI has made queries on this proposal and Concessionaire is yet
to comply with the queries including the approximate cost implication. The issue is
still pending with the Concessionaire.
Panvel - Indapur MPR No-37 February '15 Page 91
7.0 CRITICAL ISSUES AND RECOMMENDATIONS
(1) Land Acquisition: As per the Concession Agreement, NHAI shall make best efforts
to procure and grant, no later than 90 days from the Appointed Date, the Right of
Way to the Concessionaire in respect of all land included in the Appendix. NHAI may
speed up further land acquisition process.
(2) Very Slow Progress of RE Wall Works: Though Concessionaire has initiated
some RE wall works, it is completely stopped. This will be critical activity on the
Project. Concessionaire should immediately pursue this matter. Out of the total 26
underpasses not even single underpass structure and its approaches is completed.
(3) Non-Removal of Encumbrances : NHAI has issued notice under section 26 of the
Control of National Highways (Land and Traffic) Act, 2002 to unauthorized occupants
in some of the villages. Police support is sought. Encroachments are removed in
Kollad, Pui, Khamb, Varas gaon villages. However, some buildings in other villages
are yet to be removed for want of payment, valuation etc. Concessionaire has not
submitted the programme for encroachment removal/building removal in spite of
several reminders.
Concession Agreement, Clause 5.1.4 (e) specifies that “Concessionaire should make
reasonable efforts to facilitate the acquisition of land required for the purpose of the
Agreement”. Also, Concession Agreement, Clause 4.1.4 specifies that “Each party
shall make all reasonable endeavours to satisfy the conditions precedent within the
time stipulated and shall provide the other party with such reasonable cooperation as
may be required to assist that party in satisfying the conditions precedent for which
that party is responsible”.
(4) Very Slow Progress of shifting of Electrical Posts and Lines, MJP Water
Pipe Lines by Concessionaire : The shifting of electrical poles and lines is very
slow. Hardly any crossing is done so far. The shifting of MJP water pipeline is very
slow. Concessionaire should speed up these activities.
(5) Eco-Sensitive Zone / Forest Land: Approval of Forest land except Ch. 0+000 to
20+100 issued by NHAI vide letter No. NHAI/ PIU/ PANVEL/ PI/ SPITPL/ Forest/
2013/ 1201 dt. 23-08-’13. The approval for the forest land between Ch. 0 + 000 to
20+100 is still pending. This portion comes under Eco-sensitive zone. Approval for
non core area (length 16.6 km) of Karnala Bird Sanctuary has been obtained.
However, PCCF Maharashtra has asked to obtain NGT approval. Proposal for
obtaining NBWL approval for core area (3.5 Km) has been resubmitted to NBWL for
reconsideration. Additional land of 1.3 Ha affecting 300m length in Sukheli Khind
need to be approved by MoEF.
Panvel - Indapur MPR No-37 February '15 Page 92
(6) Very Slow Progress of Structure Works: The progress of structures (especially,
major bridges, flyovers and ROB’s) is very slow. Concessionaire should improve the
progress of structures. The overall progress so far is 35% only.
(7) Pavement Distress at many Locations: During the rainy seasons of year 2013
and 2014, the newly laid DBM and BC has distressed at many locations. Many
pothole/patch were observed. The Concessionaire was advised to remove such
distressed layer fully to appreciable length and relay with new materials. Also,
Concessionaire is advised to investigate in detail on such recurring problems and
submit detailed report. Independent Engineer has insisted Concessionaire to follow
good engineering practices during pavement construction. It has been reminded
many times the importance of constructing kerb before taking up bituminous works,
use of PTR for DBM layer, constructing median drain and chutes, proper drainage
arrangements during construction, temperature control etc.
(8) Very Slow Progress of Works :
(a) In spite of prevailing good working season, absolutely no work is in progress in both
sections. It appears that the works are held up for want of fund cement, bitumen,
diesel, manpower, machinery and other resources. The physical progress during
August ’14 to February ‘15 are 0.01%, 0.04%, 0.03%, 0.02%, 0.0%, 0.00% and
0.02% respectively. The length of highway works completed(m) during these months
are given below:
Description Aug.’14 Sept.’14 Oct.’14 Nov.’14 Dec.’14 Jan.’14 Feb.’15
Clearing & Grubbing 0 0 0 0 0 310 0
Embankment 0 0 0 0 0 350 160
Subgrade 0 0 0 288 0 260 240
Granular Sub base (GSB) 0 0 0 30 0 70 250
Wet Mix Macadam (WMM) 0 0 0 0 0 0 0
Dense Bituminous Macadam (DBM)
0 0 60 0 0 0 0
Bituminous Concrete (BC) 0 0 0 0 0 0 0
(b) It has also been observed that at following underpass locations works can
start/continue:
Sl No Chainage Description Concessionaire’s Comments Our Comments
1 25+860
Khopoli VUP
Panvel
approach
CIDCO pipeline is the major
hurdle: CIDCO pipeline on LHS is
not yet removed by the
authority. There is still land
acquisition problem which is not
sorted out in totally.
CIDCO pipeline will not
affect approach
construction. There is
absolutely no problem to
construct the
approaches.
Panvel - Indapur MPR No-37 February '15 Page 93
(c) The works for Rest area, busbays, truck laybyes etc. are not yet started.
(d) Independent Engineer’s review on the progress of work on highway alongwith land
availability shows that at following locations, highway works should have been in
progress.
Sl No
Chainage Side
Length (Km)
Remarks From To
1 0+400 1+000 B/S 600 BC can be done after rectification of distressed DBM 2 1+500 4+300 B/S 2,800 BC can be done after rectification of distressed DBM 3 5+500 6+800 B/S 1,300 BC can be done after rectification of distressed DBM 4 21+300 23+500 RHS 2,200 BC can be done after rectification of distressed DBM 5 22+950 23+350 LHS 400 Slow Progress 6 31+000 31+600 B/S 600 Work yet to be started 7 40+100 41+900 B/S 1,800 BC can be done after rectification of distressed DBM 8 51+500 51+900 LHS 400 WMM work still not completed 9 59+400 60+300 LHS 900 No work 10 59+700 59+900 RHS 200 Earthwork is not completed 11 60+800 61+700 LHS 900 No work 12 62+400 63+100 LHS 700 No work
2 30+930
Wadkhal VUP
Indapur
approach
Land problem and the
continuous stretch of land is not
available for construction
activity.
There is no problem in
constructing the
approaches.
3 49+280
Koleti PUP
approaches
both ends
Award passed, no payment
made to land owners. Land
problem to be delft by NHAI.
Service road can be
constructed on LHS and
accordingly approaches
can be constructed.
4 50+845
Palas PUP
approaches
on both ends
Verification of land required from
Dy. SLR for confirmation of
encroachment of private land.
The Vaishali Hotel owner
allowing any construction
activity.
There is no problem in
constructing service
road on LHS and thus
constructing the
approaches.
5 54+450 Nagothane
VUP
Govt. land/court matter & the
embankment toe is going
Railway land (ROW) on LHS.
Matter needs to be sorted for
starting the construction activity.
There is no problem for
constructing RHS service
road and the
approaches.
6 68+320 Khmab PUP
Still there are 9 structures on
site which not in vacant position,
continuous stretch of land is not
RE wall.
Concessionaire should
proactively support for
encroachment removal if
any.
7 79+140 Ratwad PUP
No payment made to land
owners. Land owners are not
allowing for work, land problem
to be solved by NHAI.
There is no problem in
constructing the
approaches.
Panvel - Indapur MPR No-37 February '15 Page 94
Sl No
Chainage Side
Length (Km)
Remarks From To
13 63+900 65+900 LHS 2,000 Work is slow progress 14 70+000 72+300 LHS 2,300 No work 15 74+800 76+200 RHS 1,400 Work is slow progress 16 76+550 76+850 LHS 300 No work 17 77+000 77+700 RHS 700 No work 18 81+500 82+600 LHS 1,100 No work 19 81+200 82+400 RHS 1,200 GSB work is not completed 20 81+500 82+600 LHS 1,100 No work
Total 22,900
The above details show that in spite of sufficient work fronts available the Concessionaire
could not achieve better progress due to lack of various resources.
Non-Maintenance of The Project Highway : It has been observed that at some
locations (most of them are in new carriageway) many Potholes/Patchwork are not yet
repaired in spite of continuous follow up with Concessionaire. Non-maintenance of the
highway is leading to lot of criticism by the road users, administration and print media. Non-
maintenance of the highway will have to be considered as default of obligations by the
Concessionaire as per the terms of the Concession Agreement.
Many Pending Designs and Drawings: Many design and drawings for highway and
structures are still pending with Concessionaire. An updated list was issued to
Concessionaire vide letter no. PIP/IE/SPITPL/2014/2806 dt. 04-12-’14. In spite of several
reminders no action is taken by Concessionaire for last nine months.
Non-Closure Of NCR’s, Site Inspection Reports, Audit Reports: Concessionaire
has not closed out many NCR’s Site Inspection Reports / Audit Reports in spite of several
reminders. Concessionaire has been advised many times that whatever works carried out
above the work where NCR/site inspection note issued will also be considered Non-
acceptable. In spite of such reminders Concessionaire has not yet improve the quality of
works. Non-closure of such NCR’s/Site Inspection Report/Audit Reports/ letters on
quality issues etc. is of major quality concern and will lead to contractual complications.
Insufficient Resources: Concessionaire has not mobilised sufficient resources such as
fund, manpower, machinery, plant etc. Resources mobilised are very less. Construction
works were held up many times for want of fund, cement, bitumen, diesel, manpower,
machinery, and other resources etc.
Crusher Production in Section - II : It has been observed that crusher production in
Section - II is very less and will not cater for requirement and this has been reported to
Concessionaire vide letter no. PIP/IE/SPITPL/2014/2773 dt. 21-11-‘14
Panvel - Indapur MPR No-37 February '15 Page 95
Status of ROB Approvals: The following is the status of approval of ROB’s:
Sl No
Chainage (Km)
Location Status
1 16+062 Kharpada
(1) GAD (General Arrangement Drawing) - Approved by Railways.
(2) SAD (Structure Arrangement Drawing) - Done
(3) TAD (Temporary Arrangement Drawing) - Done
(4) CRS (Commissioner Railway Safety) - Sanction Obtained
(5) P & E charges deposited by NHAI
(6) Codal charges not paid by Concessionaire.
(7) MoU executed.
2 28+283 Pen
(1) GAD (General Arrangement Drawing) - Approved by Railways.
(2) SAD (Structure Arrangement Drawing) – Done
(3) TAD (Temporary Arrangement Drawing) – Done
(4) CRS (Commissioner Railway Safety) - Sanction Obtained
(5) P & E charges deposited by NHAI
(6) Codal charges not paid by Concessionaire.
(7) MoU executed.
3 33+877 Wadkhal Bypass
(1) GAD (General Arrangement Drawing) - Approved by Railways.
(2) SAD (Structure Arrangement Drawing) - Not Submitted
(3) TAD (Temporary Arrangement Drawing) - Not Submitted to
Railways
(4) CRS (Commissioner Railway Safety) - Sanction not Obtained
(5) Codal charges not paid by Concessionaire
(6) MoU executed.
Section - I EPC Contractor’s camp closed down:
For last six months the Section - I EPC Contractor’s camp site is closed down.
Independent Engineers are not allowed to enter their premises. Photos taken from
outside of their premises given below:
Panvel - Indapur MPR No-37 February '15 Page 96
The reinforcement steel which was already tied up for the slab of VUP at Ch. 28+860 (Khopoli
Underpass) has been removed. The shutter arrangements also removed. Photos taken from site
given below:
Panvel - Indapur MPR No-37 February '15 Page 97
8.0 PROJECT PHOTOGRAPHS
Photo - 01 WMM First layer at Ch. 61+470 to 61+650 (RHS).
Photo - 02 GSB at Ch.64+400 to 64+460 (RHS).
Photo -03 Embankment First Layer at Ch. 74+290 to 74+430 (LHS).
Photo-04 Nigade bridge at Ch.44+195 pile P2 work in progress
Photo-05 Toll plaza Administrative building at Ch. 66+608 work in progress
Panvel - Indapur MPR No-37 February '15 Page 98
Appendix-A
Comments on Concessionaire’s Monthly Progress Report
Concessionaire has not yet submitted the Progress Report for the month January ’15 and
February ’15 so far in spite of several reminders.
Panvel - Indapur MPR No-37 February '15 Page 99
Appendix-B
Weather
Date
Section-I* Section-II
Temperature (◦C) Rainfall (mm)
Temperature (◦C) Rainfall (mm) Minimum Maximum Minimum Maximum
26-01-‘15 17.9 31.1
27-01-‘15 18.6 31.8
28-01-‘15 18.5 31.9
29-01-‘15 18.8 31.6
30-01-‘15 18.6 32.0
31-01-‘15 18.4 32.2
01-02-‘15 18.0 32.4
02-02-‘15 18.6 32.8
03-02-‘15 18.5 32.9
04-02-‘15 19.1 33.4
05-02-‘15 18.9 33.0
06-02-‘15 18.4 32.8
07-02-‘15 18.8 32.9
08-02-‘15 19.1 33.4
09-02-‘15 17.6 32.9
10-02-‘15 19.4 33.4
11-02-‘15 19.5 33.9
12-02-‘15 19.1 32.2
13-02-‘15 18.9 33.5
14-02-‘15 19.0 33.2
15-02-‘15 18.8 33.0
16-02-‘15 18.6 33.6
17-02-‘15 18.9 33.4
18-02-‘15 18.6 33.2
19-02-‘15 19.1 33.8
20-02-‘15 18.9 33.9
21-02-‘15 18.6 33.4
22-02-‘15 18.4 34.0
23-02-‘15 18.9 33.6
24-02-‘15 18.5 33.4
25-02-‘15 18.6 34.1
* Details not given by Concessionaire.
Panvel - Indapur MPR No-37 February '15 Page 101
Appendix-D
Minutes of Monthly Progress Review Meeting
Four-Laning of Panvel-Indapur Section of NH-17 (Package No : NHDP-
III/DL4/05)
Meeting could not be conducted since Concessionaire’s representative has not
attending the site inspection and scheduled Progress Review Meeting.
Panvel - Indapur MPR No-37 February '15 Page 102
Appendix-E
Four-Laning of Panvel-Indapur Section of NH-17 (Package No: NHDP-III/DL4/05)
Site Inspection Note No -45
Inspection Note
No. : 45
Date : 11-02-2015
Construction
Package :
Four Laning of Panvel-Indapur Section of NH-17 (From Km 0+000 to
84+000) in the State of Maharashtra under NHDP Phase-III on DBFOT
Basis (Package No : NHDP-III/DL4/05)
Concessionaire : Supreme Panvel Indapur Tollways Private Limited
Independent
Engineer :
M/s Yongma Engineering Co., Ltd. In association with M/s Feedback
Infra Private Limited
Project
Management
Consultants
: M/s Sowil Limited
EPC Contractors : Ch. 0+000 to 42+000: M/s Mahavir Roads and Infrastructure Pvt. Ltd.
Ch. 42+000 to 84+000 : M/s Supreme Infrastructure India Limited
Appointed Date : 19-12-2011
Scheduled date of
Completion : 16-06-2014 (910 Days Construction Period)
Attendees :
(1) Mr. Gangadharan C. P, TL-IE
(2) Mr. R.P. Sharma, RE-IE
(3) Mr. Pathankar, material Engineer-EPC
(4) Mr. Sengupta, Sr. Bridge Enginner-EPC.
(5) Mr. Mulani , Bridge Engineer-EPC
(6) Mr. Ankush, Highway Enginner -EPC
Sl
No Chainage/
Location Description of Problem Photo
45.1 50+845 (LHS)
Palas Underpass
Approaches
Normal soil dumped on the
underpass approaches where
selected soil having specific C & Ø
value should be used. RE wall
foundation should not be on buit
up embankments.
Panvel - Indapur MPR No-37 February '15 Page 103
Sl
No Chainage/
Location Description of Problem Photo
45.2 61+600 (RHS)
It appears that dust is added to the
GSB surface. Without proper
compaction of GSB layer, WMM laid
at some portion.
45.3 Sukheli Khind
Proper safety arrangements to be
made before hard rock excavation as
traffic is plying on the highway.
Panvel - Indapur MPR No-37 February '15 Page 104
Sl
No Chainage/
Location Description of Problem Photo
45.4 67+520 (LHS)
widening portion
Type of profile correction course
(PCC) to be anaylsed and submitted
to IE for concurrence. Widening
portion should be in tune with the
PCC.
45.5 74+430 to 74+570
(LHS)
Boulders to be removed from the
earth work.
45.6 At various Locations Potholes need maintenance. Many
letters already issues.
45.7 At Various
Locations
New encroachments, hoarding and
OFC cables coming up along the
Project highway. Many letters already
issued to Concessionaire.
Panvel - Indapur MPR No-37 February ‘15 Page 105
Appendix-F
Letters from NHAI to Independent Engineer
Sl
No Date Letter No. Subject
1 02-02-'15 NHAI/PIU/Panvel/PI/IE/2015/2167 RTI application.
2 02-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2174 New Encroachment at Ch. 73+780 to 73+980 both sides.
3 03-02-'15 NHAI/PIU/Panvel/PI/Safety/2015/2204 Report on construction stage audit (6th Quarter) & work zone safety audit (5th
Quarter).
4 07-02-'15 NHAI/PIU/PNVL/P-I/EOT/2015/2211 Revised Construction Programme Four Laning.
5 10-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2254 Exposed CPCC treated reinforcements.
7 10-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2258 Representation Sh. Rajendra Manohar Raut.
8 10-02-'15 NHAI/PIU/PNVL/P-I/SALT PAN LAND/2015/2261 Transfer of Salt Pan Land to NHAI.
9 10-02-'15 NHAI/PIU/Panvel/PI/IE/2015/2262 RTI application.
10 10-02-'15 NHAI/PIU/PANVEL/SPITPL/2015/2259 Representation.
11 11-02-'15 NHAI/PIU/Panvel/PI/IE/Retail/Outlet/2015/2263 Permission to have access for proposal Retail outlet on S. No. 205A of Village
Shirdhone, Tal Panvel, Dist. Raigad on NH-17.
12 14-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2266 Objection to erection of 22KV line along NH-17 from Jite to Hamrapur Phata
and Pen to Kolety Goan.
13 14-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2280 Maintenance of the Highway and Safety Measures.
14 14-02-'15 NHAI/PIU/Panvel/PI/IE/2015/2281 Site status & other Issue.
15 14-02-'15 NHAI/PIU-Panvel/PI/Utility/2015/2287 OFC line by TATA Telecom.
16 17-02-'15 NHAI/MJPRCL/PIU/PANVEL/NOC-
Survey/2015/2290 Seeking Permission for conducting road survey on NH-4B & SH-54 (NH-348A).
17 17-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2292 Repair-Maintenance of NH-17.
18 17-02-'15 NHAI/PIU/PANVEL/PI/ROB/2015/2294 Proposal of Panvel-Pen-Roha doubling project Railway bridge.
Panvel - Indapur MPR No-37 February ‘15 Page 106
19 17-02-'15 NHAI/PIU/PNVL/P-I/EOT/2015/2309 Revised Construction Programme Four Laning.
20 23-02-'15 NHAI/PIU/Panvel/PI/CIDCO/2015/2293 CIDCO pipe line.
21 23-02-'15 NHAI/PIU/PANVEL/PI/Utility/2015/2326 MJP-Water supply pipe line.
22 23-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2327 Non submission of Monthly Progress Report of January 15.
23 23-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2333 Demarcation of ROW at Village Karnala-Tara.
24 23-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2338 Representations.
25 23-02-'15 NHAI/PIU/PNVL/P-I/SPITPL/2015/2348 Maintenance of existing Bhogeshwari Bridge.
26 23-02-'15 NHAI/PIU/PANVEL/PI/ROB/2015/2366 MOU signing for construction of ROB at Pen, Kharpada & Wadkhal.
27 23-02-'15 NHAI/PIU/PANVEL/PI/SPITPL/2015/2371 Salt Pen Land.
28 23-02-'15 NHAI/PIU/Panvel/PI/OFC/2015/2372 Permission for laying Optical Fiber Cable along NH-17 from Km 28.824 to km
84.000 for the total length of 55.176 km.
29 23-02-'15 NHAI/PIU/Panvel/Pi/IE/2015/2377 Representation.
30 27-02-'15 NHAI/PIU/PNVL/P-I/Conc./2015/2410 Extension of Time (EOT) for schedule 4 laning.
Panvel - Indapur MPR No-37 February ‘15 Page 107
Appendix-G Letters from Concessionaire to Independent Engineer
Sl
No Date Letter No. Subject
1 03-02-'15 SPITPL/P-NHAI/2014-15/3361 Site Status.
2 03-02-'15 SPITPL/P-NHAI/2014-15/3380 Submission of Revised Work Programme.
3 12-02-'15 SPITPL/P-NHAI/2014-15/3382 Submission of Modified Revised Construction Programme.
4 28-02-'15 SPITPL/P-NHAI/2014-15/3383 Submission of Working Drawings for Box Culverts.
5 28-02-'15 SPITPL/P-NHAI/2014-15/3384 Submission of Working Drawings for Box Culverts.
6 28-02-'15 SPITPL/P-NHAI/2014-15/3385 Submission of Working Drawings for Box Culverts.
7 28-02-'15 SPITPL/P-NHAI/2014-15/3386 Source approval for procurement of stripe seal Expansion joint MAGEBA
Bridge 14 Products.
Panvel - Indapur MPR No-37 February ‘15 Page 108
Appendix-H
Letters Issued by Independent Engineer
Sl
No Date Letter No. To Subject
1 02-02-'15 PIP/IE/NHAI/2015/2946 NHAI Invoice No - PIP/38 (January ’15).
2 02-02-'15 PIP/IE/NHAI/2015/2947 NHAI Leave Absence of Asst. Quality cum Material Engineer Mr. Raffiuddin .N. Badure.
3 02-02-'15 PIP/IE/NHAI/2015/2948 NHAI Intimation Regarding Ms. Reshma Katekar, Computer Operator Leaving the Project
Team.
4 02-02-'15 PIP/IE/SPITPL/2015/2949 Concessionaire Site Inspection No-045 and Progress Review Meeting.
5 02-02-'15 PIP/IE/NHAI/2015/2950 NHAI Leave Absence of Team Leader Cum Sr. Highway Engineer.
6 02-02-'15 PIP/IE/SPITPL/2015/2951 Concessionaire Project Monitoring Information System (PMIS) to be Updated-Reminder No-2.
7 02-02-'15 PIP/IE/NHAI/2015/2952 NHAI Request For Extension of Time For Independent Engineer Consultancy Agreement-
Reminder.
8 02-02-'15 PIP/IE/NHAI/2015/2953 NHAI Revised Construction Programme Four Laning-Comments.
9 03-02-'15 PIP/IE/SPITPL/2015/2954 Concessionaire New Encroachment at Ch. 26+270 To 26+350 (RHS).
10 03-02-'15 PIP/IE/SPITPL/2015/2955 Concessionaire Hoarding Inside Right of Way.
11 03-02-'15 PIP/IE/NHAI/2015/2956 NHAI Permission for Laying of 1500 mm dia MS Water Supply Pipeline under CIDCO
Hetwane water supply Scheme in Right of Way of NH-17-Comments.
12 03-02-'15 PIP/IE/SPITPL/2015/2957 Concessionaire Hoarding Inside Right of Way.
13 03-02-'15 PIP/IE/SPITPL/2015/2958 Concessionaire Exposed CPCC Treated Reinforcements.
14 03-02-'15 PIP/IE/NHAI/2015/2959 NHAI Application Under the RTI Act, from Shri Vivek N. Datar.
15 04-02-'15 PIP/IE/SPITPL/2015/2960 Concessionaire Transaction Statements of Escrow Account -Reminder No-7.
16 06-02-'15 PIP/IE/SPITPL/2015/2961 Concessionaire Various Quality Issues.
17 06-02-'15 PIP/IE/SPITPL/2015/2962 Concessionaire Cracks Observed in Approach Slab at Various Locations.
18 07-02-'15 PIP/IE/SPITPL/2015/2963 Concessionaire Core Cutting Pattern for DBM Works.
19 07-02-'15 PIP/IE/SPITPL/2015/2964 Concessionaire Representation.
Panvel - Indapur MPR No-37 February ‘15 Page 109
Sl
No Date Letter No. To Subject
20 07-02-'15 PIP/IE/SPITPL/2015/2965 Concessionaire Further Distressed DBM at Various Locations.
21 07-02-'15 PIP/IE/NHAI/2015/2966 NHAI Leave Absence of Assistant Highway Engineer Mr. Pillai Arun Rajan.
22 07-02-'15 PIP/IE/SPITPL/2015/2967 Concessionaire Development of Potholes/Patches on the Newly Laid DBM/BC-Investigation Through
Govt. Agency.
23 09-02-'15 PIP/IE/SPITPL/2015/2968 Concessionaire NCR No-182-Pipe Culvert at Ch. 50+808 (RHS).
24 09-02-'15 PIP/IE/NHAI/2015/2969 NHAI Leave Absence of Bridge Engineer Mr. Nagaraja Rao.
25 09-02-'15 PIP/IE/SPITPL/2015/2970 Concessionaire Electrical Poles at Ch.21+200 to 22+800 (LHS).
26 09-02-'15 PIP/IE/SPITPL/2015/2971 Concessionaire Safety Issue at Ch. 2+100 to 2+200 (RHS).
27 09-02-'15 PIP/IE/NHAI/2015/2972 NHAI Accident Data and Horticulture Report.
28 09-02-'15 PIP/IE/SPITPL/2015/2973 Concessionaire Non-Submission of Monthly Progress Report of January ’15.
29 09-02-'15 PIP/IE/SPITPL/2015/2974 Concessionaire Construction Works Not Yet Resumed Properly.
30 09-02-'15 PIP/IE/SPITPL/2015/2975 Concessionaire Change of Scope Pending With the Concessionaire-Reminder No-5.
31 09-02-'15 PIP/IE/NHAI/2015/2976 NHAI Monthly Progress Report No-36 (January ‘15).
32 11-02-'15 PIP/IE/SPITPL/2015/2977 Concessionaire Hoarding Inside Right of Way.
33 11-02-'15 PIP/IE/SPITPL/2015/2978 Concessionaire Encroachment by Reliance Jio OFC Cable Laying.
34 11-02-'15 PIP/IE/SPITPL/2015/2979 Concessionaire Profile Corrective Course (PCC) for Existing Carriageway- Reminder No- 10
35 11-02-'15 PIP/IE/NHAI/2015/2980 NHAI Application Under the RTI Act, from Shri Johny Dsouza.
36 12-02-'15 PIP/IE/NHAI/2015/2981 NHAI Leave Absence of Assistant Highway Engineer Mr. Neeraj. M. Patil.
37 12-02-'15 PIP/IE/SPITPL/2015/2982 Concessionaire Site Inspection Note No-45 dt. 10-02-’15.
38 12-02-'15 PIP/IE/SPITPL/2015/2983 Concessionaire Quality Issues.
39 13-02-'15 PIP/IE/SPITPL/2015/2984 Concessionaire Maintenance of Existing Bhogeshwari Bridge-Reminder No-02.
40 13-02-'15 PIP/IE/SPITPL/2015/2985 Concessionaire Pending Maintenance Activities.
41 13-02-'15 PIP/IE/NHAI/2015/2986 NHAI Modified Revised Construction Programme Four Laning-Comments.
42 14-02-'15 PIP/IE/NHAI/2015/2987 NHAI Site Status and Other Issues-Comments.
43 14-02-'15 PIP/IE/NHAI/2015/2988 NHAI Leave Absence of Resident cum Highway Engineer Mr. R.P. Sharma.
Panvel - Indapur MPR No-37 February ‘15 Page 110
Sl
No Date Letter No. To Subject
44 14-02-'15 PIP/IE/SPITPL/2015/2989 Concessionaire Section- II-Stone Polishing Value Test- Reminder No-8.
45 14-02-'15 PIP/IE/SPITPL/2015/2990 Concessionaire Embankment Material with Boulders.
46 16-02-'15 PIP/IE/NHAI/2015/2991 NHAI Leave Absence of Accountant Mrs. Madhumati. P. Kumar.
47 23-02-'15 PIP/IE/NHAI/2015/2992 NHAI Transaction Statements of Escrow Account not being Submitted by the
Concessionaire.
48 23-02-'15 PIP/IE/SPITPL/2015/2993 Concessionaire Non- Closure of Long Pending NCR’s, Site Inspection Reports and Letters on Quality
Issues- Reminder No-10.
49 24-02-'15 PIP/IE/NHAI/2015/2994 NHAI Permission for Laying of 1500 mm dia MS Water Supply Pipeline under CIDCO
Hetwane water supply Scheme in Right of Way of NH-17-Comments.
50 24-02-'15 PIP/IE/NHAI/2015/2995 NHAI Some of the Staff Out of Station on 25-02-2015.
51 26-02-'15 PIP/IE/SPITPL/2015/2996 NHAI Hoarding Inside Right of Way.
52 26-02-'15 PIP/IE/SPITPL/2015/2997 Concessionaire Construction Works Not Yet Resumed Properly-Reminder No-11.
53 26-02-'15 PIP/IE/SPITPL/2015/2998 Concessionaire Continued Use of Un-approved Steel-Major Quality and Durability Issue-Show Cause
Notice- Reminder No-2.
54 26-02-'15 PIP/IE/SPITPL/2015/2999 Concessionaire Lack of Equipments in the Laboratory-Reminder No-5.
55 26-02-'15 PIP/IE/SPITPL/2015/3000 Concessionaire Environmental Management Plan-Corrected Report-Reminder No-8.
56 26-02-'15 PIP/IE/SPITPL/2015/3001 Concessionaire Various Issues- Reminder No-5.
57 26-02-'15 PIP/IE/SPITPL/2015/3002 Concessionaire Section-II- Non-Calibration of Plants and Equipments- Reminder No-4.
58 26-02-'15 PIP/IE/SPITPL/2015/3003 Concessionaire Hoarding Inside Right of Way.
59 26-02-'15 PIP/IE/SPITPL/2015/3004 Concessionaire Encroachment of OFC Cable Laying.
60 26-02-'15 PIP/IE/SPITPL/2015/3005 Concessionaire NCR No-183-Box Culvert at Ch. 66+808 (RHS).
61 26-02-'15 PIP/IE/SPITPL/2015/3006 Concessionaire Slow Progress of Shifting of MJP Water Pipeline.
62 28-02-'15 PIP/IE/SPITPL/2015/3007 Concessionaire Encroachment by OFC Cable Laying at Ch. 0+400 to 0+500 (LHS)
63 28-02-'15 PIP/IE/SPITPL/2015/3008 Concessionaire NCR No-184- Ch. 66+850 to 66+870 (LHS).
64 28-02-'15 PIP/IE/SPITPL/2015/3009 Concessionaire Representation From M/s Vibhor Steel Tubes (P) Ltd. at Ch. 63+700 -Comments.
Panvel - Indapur MPR No-37 February ‘15 Page 111
Sl
No Date Letter No. To Subject
65 28-02-'15 PIP/IE/NHAI/2015/3010 NHAI Updating of Project Monitoring System Data and uploading Data For Project Specific
Website.
Panvel - Indapur MPR No-37 February ‘15 Page 112
Appendix-I
1. Stretch Panvel to Indapur Accident Data & Observations
2. Stretch Chainage 0+000 to 84+600.
3. State Maharashtra.
4. District Raigarh
5. Police Station Palaspe, Nagothane, New Panvel, SP Traffic Control Office
Alibag.
6. National Highway No. NH - 17
Month : February 2015
Sl
No
Date Time of Accident
(am/pm)
A B C D E F G H
Vehicle
Responsible
No. of Affected Persons No. of
Animals
Killed, if
any
Help
provided by
Ambulance/
Patrol Vehicle
Remarks Accident Location
Nature of Accident
Classificati
on
of Accident
Causes Road
Features
Road
Conditi
on
Intersec
tion Type &
Control
Weather Condition
Fatal Grievous Minor Non-
Injured
1
2
3
4
5
6
7
8
9
10
'A' : Urban / Rural and Details of surrounding land use
'B' : 1 - Overturning, 2-Head on collision, 3 - Rear End Collision, 4 - Collision Brush / Side Wipe, 5 - Right Turn Collision, 6-Skidding, 7 - Right Turn Collision, 8 - Others (Pls Specific)
'C' : 1- Fata, 2 - Grievous Injury, 3 - Minor Injured, 4 - Non Injury
'D' :1 - Drunken, 2 - Overspending, 3 - Vehicle out of control, 4 - Fault of driver of motor vehicle / driver of other vehicle / cyclist / pedestrarian /, 5 - Defect in mechanical condition of motor vehicle /
road condition
'E' : 1 - Single lane, 2 - Two lanes, 3 - three lanes or more without central divider (median), 4 - Four lanes or emore with Central divider
‘F’ : 1 - Straight road, 2 - Slight curve, 3 Sharp Curve, 4 - Flat Road, 5-Gentlre incline, 6 - Steel incline, 7 - Hump, 8-Dip
'G' : 1-T-Junction, 2 - Y-Junction, 3 - Four arm junction, 4-Staggered junction, 5-Junctioin with more than 4 arms, 6-Roundabout junction 7 - Manned rail crossing, 9-Unmanned rail crossing
'H' : 1 - Fine, 2 - Mist / Flag, 3- Cloudy, 4 - Light rain, 5-Heavy rain, 6-Hail / Sleet, 7 - Strong Wind, 9-Dust Storm, 10-Very Hot, 11-Very Cold, 12-Othe extraordinary weather condition
Accident data is not provided by Concessionaire in spite of several reminders.
Panvel - Indapur MPR No-37 February ‘15 Page 113
The Accident data reported since May ’12 shows that frequent accidents are occurring at following locations:
Sl. No. Chainage (km) Village
1 37 + 500 Gadab
2 56 + 320 Nagothane
3 62 + 500 Sukheli
4 68 + 180 Khamb
Independent Road Safety Consultants (M/s CRAPHTS Consultants Pvt. Ltd.) has identified
the following locations as black spots:
(1) Nagothane (Ch. 54+000)
(2) Sukheli Khind (Ch. 65+000)
Panvel - Indapur MPR No-37 February ‘15 Page 116
`
P-12 P-13
Progress during this month
A-1 P-1 P-2 P-3
Wadhkal Flyover at ch-33+860 RHS (Indapur bound)
P-18 P-19P-8 P-9 P-10 P-11A-1
P-7P-5P-4 P-14 P-15 P-16 P-19P-8 P-9 P-10 P-11
P-7
Wadhkal Flyover at ch-33+860 LHS (Indapur bound)
P-6 P-17 P-18
Work Completed Till End of Last Month
P-1 P-3P-12 P-13 P-14 P-15 P-16 P-17P-2 P-4 P-5 P-6
Panvel - Indapur MPR No-37 February ‘15 Page 117
`
`
Total no of Girders : 304 Nos
No. of Girder Erected till end of last month : 0 No
No. of Girder Erected during this month : 0NosNo. of Girder cast during this month : 0NosWork Completed Till End of Last
Month
Progress during this month Total no of Girders : 304 Nos
No. of Girder cast till end of last month : 14 No
P-27 P-28 P-29P-20 P-21 P-22 P-23 P-24 P-25 P-26 P-30 P-31 P-39 A-2P-33 P-34 P-35 P-36 P-37 P-38P-32
A-2
Wadhkal Flyover at ch-33+860 LHS (Indapur bound)
Wadhkal Flyover at ch-33+860 RHS (Panvel bound)
P-27 P-28 P-29 P-30 P-31 P-32P-20 P-21 P-34 P-39P-35 P-36 P-38P-22 P-23 P-24 P-25 P-26 P-37P-33cc c c c c c c c c
c c c c c c c c c c
Panvel - Indapur MPR No-37 February ‘15 Page 118
A-1 P-2P-1 P-3 P-4 A-2
PEN ROBPEN ROB APPROACH RETAINING WALL
(LHS)
`
Panvel - Indapur MPR No-37 February ‘15 Page 119
`
No. of Girder cast till end of last month :24 Nos No. of Girder Erected till end of last month :8 Nos
No. of Girder Erected during this month : 8 Nos
P-5P-4
P-6 P-7 P-8 P-9
P-2P-1
Total no of Girders : 91 Nos
P-24 A-25P-18 P-19 P-20 P-21 P-22 P-23A-1
P-16 P-17P-11
Major Bridge at Ch. 15+879 (Kharpada)P-3
P-10 P-12 P-13 P-14 P-15
Progress during this month Total no of Girders : 91 Nos
No. of Girder cast during this month : 0 NosWork Completed Till End of Last Month
Panvel - Indapur MPR No-37 February ‘15 Page 120
No. of Girder cast till end of last month : 16Nos (Casting Completed)
A1P1 P2 P3
A2
Progress during this month
Major Bridge at Ch. 20+144 (Balganga)-RHS
Work Completed Till End of Last Month
Total no of Girders : 16 Nos
No. of Girder Erected till end of last month :8 Nos
No. of Girder Erected during this month : 8 Nos
Panvel - Indapur MPR No-37 February ‘15 Page 121
`
Major bridge at Ch. 26+188 (Bhogeshwari)-RHS-New Construction
P-4 P-5 P-6
A-2A-1 P-1 P-2 P-3
No. of Girder cast till end of last month : 28Nos (Casting Completed)
Total no of Girders : 28 Nos
Progress during this month
No. of Girder Erected till end of last month :28 Nos (Erection Completed)Work Completed Till End of Last Month
Panvel - Indapur MPR No-37 February ‘15 Page 122
Progress during this month
Work Completed Till End of Last Month
Total no of Girders : 28 Nos
Major bridge at Ch. 26+188 (Bhogeshwari)-LHS-Existing Bridge Reconstruction
Panvel - Indapur MPR No-37 February ‘15 Page 123
Total No. of Girder : 24 No.
P-2 P-4
A-2A-1 P-1 P-3 P-5
Progress during this month
Work Completed Till End of Last Month
Major bridge at Ch. 44+195 (Nigade)-RHS
No. of Girder cast ti l l end of last month : 11 Nos
No. of Girder cast during this month : 0
No. of Girder Erected till end of last month :0 Nos
No. of Girder Erected during this month : 0 Nos
Panvel - Indapur MPR No-37 February ‘15 Page 124
P-3 A-2P-1 P-4
Major bridge at Ch. 58+928 (Amba)-LHS
A-1 P-2
Panvel - Indapur MPR No-37 February ‘15 Page 125
Total No. of Girder : 40 No.
No. of Girder cast till end of last month : 16 Nos
No. of Girder cast during this month : 0 Nos.Work Completed Till End of Last Month
Progress during this month
Major bridge at Ch. 58+928 (Amba)-RHS
No. of Girder Erected till end of last month :0 Nos
No. of Girder Erected during this month : 0 Nos
A-1 P-2 P-3 A-2P-1 P-4
Panvel - Indapur MPR No-37 February ‘15 Page 126
P-11A-1
P-1 P-2 P-3 P-4
Work Completed Till End of Last Month
P-10
A-2
Progress during this month
P-9
Major bridge at ch. 72+936 (Kundlika)-RHS
P-5 P-6 P-7 P-8
Panvel - Indapur MPR No-37 February ‘15 Page 127
Minor Bridge at Ch. 0+554 (LHS)
A-1P-1
P-2 A-2
A-2
Minor Bridge at Ch. 0+554 (RHS)
A-1 P-1 P-2
A2P-1 A-2
A1Minor Bridge at Ch. 9+363-LHS
A2
Work Completed Till End of Last Month
A-2A1
Minor Bridge at Ch. 9+363-RHS
Progress during this month
P-1
Panvel - Indapur MPR No-37 February ‘15 Page 128
Minor Bridge at Ch. 20+754 (Balivali) -LHS
A2A1P1 P2 P3
A-1 P-2 A-2P-1
Minor Bridge at Ch. 29+728 (LHS)
A2A-2A1
Minor Bridge at Ch. 30+557 (Uchede)-RHS
P-1
Panvel - Indapur MPR No-37 February ‘15 Page 129
P3 A2
Minor Bridge at Ch. 52+155 (Nidhi)-RHS
A1 P1 P2
A2P-1 A-2A1
Minor Bridge at Ch. 57+997 (Patansai)-RHS
A2A- 2A-1
Minor Bridge at Ch. 59+395 (RHS)
A2
Work Completed Till End of Last Month
Progress during this month
A- 2A-1 Minor Bridge at Ch. 59+861 (Godsai)-RHS
Panvel - Indapur MPR No-37 February ‘15 Page 130
62+01
`
A2
Minor Bridge at Ch. 62+345-(RHS) A- 2A-1
A2
Minor Bridge at Ch. 63+296-(RHS) A- 2A-1
A2P-1 A-2A1
Minor Bridge at Ch. 64+249 (RHS)
A2
Minor Bridge at Ch. 66+808(LHS)
Progress during this month
Work Completed Till End of Last Month
Panvel - Indapur MPR No-37 February ‘15 Page 131
A2
Minor Bridge at Ch. 66+808(RHS)
A2A-1 A- 2
Minor Bridge at Ch. 67+099 (LHS)
A2A1 A-2
Minor Bridge at Ch. 67+099-(RHS)
A2
Minor Bridge at Ch. 67+878 (RHS)
Work Completed Till End of Last Month
Progress during this month
P-1 A-2A1
Panvel - Indapur MPR No-37 February ‘15 Page 132
A2
Minor Bridge at Ch. 68+988-(RHS) A- 2A-1
A2A- 2A-1 Minor Bridge at Ch. 69+140-(RHS)
A-1 P-2 A-2P-1
Minor Bridge at Ch. 72+255-(LHS)
Work Completed Till End of Last Month
A-1 P-2
Minor Bridge at Ch. 73+353-(RHS)
A-2P-1P-3
P-4
Progress during this month
Panvel - Indapur MPR No-37 February ‘15 Page 133
Minor Bridge at Ch. 77+804 (BHUVAN)-(RHS)
A1 P1 A2
Minor Bridge at Ch. 81+665 (RHS)
A-1 A-2P-2P-1
A2
Minor Bridge at Ch. 83+920(LHS)
A- 2A-1
Panvel - Indapur MPR No-37 February ‘15 Page 134
A2
Minor Bridge at Ch. 83+920(RHS)
A- 2A-1
P-2 A-2P-1A-1A-2
Work Completed Till End of Last Month
Minor Bridge at Ch. 84+488 (INDAPUR)-(RHS)
A-1 P-1 P-2
Progress during this month
Panvel - Indapur MPR No-37 February ‘15 Page 135
Appendix-L
Status of Vehicular Underpasses
Vehicular Underpass (VUP) at Ch. 5+000 - Chinchvan
RHSLHS
Vehicular Underpass (VUP) at Ch. 23+460
RHS
Vehicular Underpass (VUP) at Ch. 25+873 (LHS) - Khopoli
Work Completed Till End of Last Month
Progress during this month
Vehicular Underpass (VUP) at Ch. 27+155 - Pen(Converted to VUP)
LHS RHS
Panvel - Indapur MPR No-37 February ‘15 Page 136
Vehicular Underpass (VUP) at Ch. 27+760 - PEN
LHS RHS
Vehicular Underpass (VUP) at Ch. 28+535 - (PEN) PUP Converted to VUPLHS RHS
LHS RHS
Vehicular Underpass (VUP) at Ch. 30+930 WADKHAL
Work Completed Till End of Last Month
LHS RHS
Vehicular Underpass (VUP) at Ch. 32+485 WADKHAL
Progress during this month
Panvel - Indapur MPR No-37 February ‘15 Page 137
Vehicular Underpass (VUP) at Ch. 54+450 - Nagothane (Additional As Per CA)LHS RHS
Vehicular Underpass (VUP) at Ch. 56+060 - NagothaneLHS RHS
Progress during this month
Work Completed Till End of Last Month
Vehicular Underpass (VUP) at Ch. 73+760 - Kolad LHS RHS
Panvel - Indapur MPR No-37 February ‘15 Page 138
Appendix-M
Status of Pedestrian Underpasses
Pedestrian Underpass (PUP) at Ch. 1+230 - Palaspe
LHS RHS
Pedestrian Underpass (PUP) at Ch. 13+625 -Tara
LHS RHS
Pedestriann Underpass (PUP) at Ch. 18+700 - Jite
LHS RHS
Pedestriann Underpass (PUP) at Ch. 27+420
LHS RHS
Panvel - Indapur MPR No-37 February ‘15 Page 139
Pedestrian Underpass (PUP) at Ch. 30+112 (UCHEDE)
LHS RHS
Pedestrian Underpass (PUP) at Ch. 37+529
LHS RHS
Pedestrian Underpass (PUP) at Ch. 39+740 KHAPALE (Additional as per CA)
LHS RHS
Pedestrian Underpass (PUP) at Ch. 42+155 - KasuLHS RHS
Panvel - Indapur MPR No-37 February ‘15 Page 140
q
Pedestrian Underpass (PUP) at Ch. 45+225 - NigadeLHS RHS
Pedestrian Underpass (PUP) at Ch. 49+280 - KoletiLHS RHS
Pedestrian Underpass (PUP) at Ch. 50+845 -PALAS (Additional As Per CA)
LHS RHS
Pedestrian Underpass (PUP) at Ch. 55+840 - NagothaneLHS RHS
Panvel - Indapur MPR No-37 February ‘15 Page 141
Pedestrian Underpass (PUP) at Ch. 68+320 - KhambLHS RHS
RHSPedestrian Underpass (PUP) at Ch. 76+315 - Talavali
LHS
Work Completed Till End of Last Month
LHS RHSPedestrian Underpass (PUP) at Ch. 79+140 - Ratvad
Progress during this month
Panvel - Indapur MPR No-37 February ‘15 Page 142
Appendix-N
1 5+349 5+359
2 5+435 5+440
3 6+524 6+530
4 6+864 6+872
5 7+011 7+014
6 8+087 8+095
7 8+305 8+248
8 8+541 8+498
9 8+915 8+879
10 9+571 9+570
11 9+937 9+984
12 16+815 16+813
13 17+514 17+531
14 18+040 18+038
15 18+446 18+481
16 20+963 20+968
17 24+259 24+249
18 27+524 27+521
19 28+383 28+091
20 30+898 30+940
21 32+740 32+946
22 33+050 33+019
23 34+100 34+130
24 34+273 34+348
25 34+594 34+667
26 34+726 34+804
27 35+706 35+786
28 35+941 36+019
29 36+157 36+235
30 36+319 36+408
31 36+504 36+581
32 36+665 36+743
33 36+837 36+915
34 37+028 37+106
35 37+432 37+520
36 38+269 38+336
37 38+801 38+801
38 38+952 39+030
39 39+030 39+133
40 39+358 39+436
41 39+454 39+532
42 39+640 39+640
43 39+807 39+807
44 40+246 40+246
45 40+564 40+564
Progress during this Month
Su
b
str
uctu
re
Status Of Slab Culverts/Box CulvertsMCW RHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
b
str
uctu
re
Ex
ca
va
tio
n
Sl.
No
Ch
ain
ag
e (
As
pe
r C
A)
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
SR RHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
De
sig
n C
ha
ina
ge
SR LHS
Ex
ca
va
tio
n
PC
C
Su
b
str
uctu
re
Su
pe
r
str
uctu
re
MCW LHS
Su
b
str
uctu
re
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
Work Completed Till End of Last Month
Panvel - Indapur MPR No-37 February ‘15 Page 143
46 40+750 40+750
47 40+906 40+906
48 41+125 41+125
49 41+268 41+268
50 41+414 41+414
51 41+481 41+559
52 41+888 41+961
53 42+170 42+249
54 42+442 42+520
55 42+967 42+922
56 43+055 43+045
57 43+326 43+133
58 45+264 45+343
59 45+489 45+568
60 45+672 45+751
61 45+784 45+864
62 45+889 45+977
63 45+939 46+016
64 46+042 46+122
65 46+238 46+313
66 46+544 46+619
67 47+169 47+244
68 47+353 47+428
69 47+428 47+627
70 47+752 47+750
71 47+833 47+909
72 48+725 48+722
73 48+800 48+870
74 50+093 50+163
75 50+460 50+531
76 51+407 51+478
77 51+611 51+681
78 52+269 52+335
79 52+416 52+484
80 52+773 52+841
81 53+390 53+456
82 53+594 53+661
83 53+825 53+900
84 54+746 54+815
85 55+266 55+335
86 56+099 56+165
87 56+449 56+517
88 56+583 56+651
89 57+022 57+090
90 57+256 57+325 i
Work Completed Till End of Last Month Progress during this Month
Status Of Slab Culverts/Box Culverts
Sl.
NoC
ha
ina
ge
(A
s
pe
r C
A)
MCW LHS MCW RHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
De
sig
n
Ch
ain
ag
e
SR LHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
SR RHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
Su
b
str
uctu
re
Su
b
str
uctu
re
Su
b
str
uctu
re
Su
b
str
uctu
re
Panvel - Indapur MPR No-37 February ‘15 Page 144
91 57+465 57+533
92 57+733 57+802
93 58+133 58+201
94 64+057 64+119
95 64+317 64+391
96 67+977 68+036
97 68+556 68+615
98 68+768 68+827
99 69+789 69+849
100 70+167 70+227
101 70+477 70+480
102 70+636 70+694
103 70+911 70+971
104 71+019 71+086
105 71+441 71+502
106 71+626 71+685
107 73+577 73+686
108 74+264 74+323
109 74+404 74+463
110 74+611 74+650
111 74+750 74+809
112 74+877 74+936
113 75+100 75+159
114 75+306 75+365
115 75+502 75+561
116 75+548 75+608
117 75+530 75+790
118 75+852 75+912
119 75+906 75+963
120 76+038 76+097
121 76+141 76+200
122 76+393 76+452
123 76+512 76+571
124 76+979 77+038
125 77+206 77+265
126 77+315 77+376
127 77+934 77+997
128 78+105 78+167
129 78+803 78+855
130 79+221 79+280
131 79+403 79+464
132 80+110 80+169
133 80+494 80+554
134 81+155 81+213
135 82+525 82+583
136 84+252 84+308
Work Completed Till End of Last Month Progress during this Month
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
Su
b
str
uctu
re
Su
b
str
uctu
re
MCW RHS
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
Ex
ca
va
tio
n
Su
b
str
uctu
re
Su
b
str
uctu
re
Status Of Slab Culverts/Box Culverts
De
sig
n
Ch
ain
ag
e
SR LHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
re
SR RHS
Ex
ca
va
tio
n
PC
C
Fo
un
da
tio
n
Su
pe
r
str
uctu
reSl.
No
Ch
ain
ag
e (
As
pe
r C
A)
MCW LHS
Panvel - Indapur MPR No-37 February ‘15 Page 145
Appendix-O
1 0+393 0+402
2 0+578 0+607
3 0+657 0+698
4 0+900 0+900
5 1+188 1+198
6 1+280 1+288
7 1+667 1+678
8 1+774 1+753
9 2+092 2+100
10 2+196 2+208
11 2+395 2+405
12 2+660 2+774
13 3+066 3+075
14 3+242 3+251
15 3+403 3+467
16 3+658 3+676
17 3+884 3+893
18 4+365 4+375
19 4+794 4+804
20 5+031 5+040
21 5+331 5+360
22 5+637 5+638
23 5+724 5+731
24 5+756 5+767
25 5+845 5+852
26 6+012 6+021
27 6+103 6+103
28 6+183 6+19029
29 6+448 6+45430
30 6+595 6+605
31 6+728 6+736
32 7+170 7+174
33 7+308 7+310
34 7+567 7+571
35 7+811 7+816
36 8+047 8+055
37 8+195 8+130
38 8+246 8+192
39 8+303 8+306
40 8+499 8+444
41 8+606 8+538
42 8+670 8+606
43 8+723 8+672
44 8+758 8+725
45 8+967 8+920
46 9+107 9+110
47 9+265 9+264
48 9+460 9+460
49 9+612 9+612
50 9+705 9+709
51 9+844 9+849
52 10+164 10+168
53 10+260 10+264
54 10+412 10+413
Work Completed Till End of Last Month Progress during this Month
Sl.
No
Ch
ain
ag
e
Status Of Pipe Culverts
MCW LHS
He
ad
Wa
ll
De
sig
n C
ha
ina
ge
SR LHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
SR RHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
MCW RHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
Panvel - Indapur MPR No-37 February ‘15 Page 146
55 10+464 10+466
56 10+602 10+603
57 10+901 10+903
58 11+100 11+102
59 11+175 11+174
60 11+292 11+295
61 11+422 11+421
62 11+481 11+480
63 11+595 11+594
64 11+678 11+677
65 11+760 11+764
66 11+877 11+880
67 12+055 12+057
68 12+144 12+148
69 12+259 12+258
70 12+497 12+497
71 12+566 12+567
72 12+658 12+659
73 12+825 12+826
74 13+179 13+180
75 13+395 13+394
76 13+527 13+524
77 13+924 13+922
78 14+172 14+170
79 14+242 14+272
80 14+380 14+380
81 14+511 14+511
82 14+858 14+858
83 15+169 15+170
84 17+970 17+970
85 18+379 18+428
86 18+482 18+557
87 18+556 18+935
88 18+808 19+322
89 18+918 19+425
90 19+208 19+711
91 19+323 19+820
92 21+284 21+284
93 21+551 21+554
94 22+169 22+168
95 22+804 22+798
96 23+077 23+070
97 23+166 23+158
98 23+315 23+377
99 23+562 23+564
100 23+945 23+950
101 23+643 23+635
102 24+454 24+460
103 24+710 24+701
104 24+848 24+841
105 24+930 24+921
106 25+181 25+172
107 25+447 25+450
108 25+301 25+292
109 25+672 25+667
110 25+668 25+701
111 25+968 25+954
Work Completed Till End of Last Month Progress during this Month
Status Of Pipe Culverts
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
SR LHS SR RHS
Ex
ca
va
tio
n
Sl.
No
MCW LHS MCW RHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
He
ad
Wa
ll
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
Ch
ain
ag
e
De
sig
n
Ch
ain
ag
e
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
Panvel - Indapur MPR No-37 February ‘15 Page 147
112 26+409 26+410
113 26+587 26+574
114 26+662 26+660
115 26+769 26+769
116 26+863 26+865
117 27+132 27+122
118 27+493 27+459
119 27+785 27+768
120 28+583 29+103
121 29+298 29+291
122 29+959 29+950
123 30+201 30+193
124 30+700 30+679
125 31+007 31+017
126 31+315 31+323
127 31+449 31+461
128 32+220 32+217
129 34+445 34+522
130 34+791 34+871
131 35+003 35+079
132 35+040 35+254
133 35+178 35+501
134 35+238 35+606
135 35+425 35+519
136 35+529 35+725
137 37+223 37+301
138 37+378 37+368
139 37+586 37+664
140 37+694 37+771
141 37+805 37+883
142 41+736 41+783
143 42+134 42+060
144 42+325 42+382
145 42+844 42+809
146 43+436 43+514
147 43+637 43+719
148 44+415 44+620
149 44+731 44+838
150 48+265 48+230
151 48+375 48+340
152 48+652 48+609
153 49+073 49+146
154 49+178 49+250
155 49+527 49+597
156 49+683 49+756
157 49+963 50+033
158 50+040 50+111
159 50+365 50+435
160 50+562 50+694
161 50+738 50+808
162 50+874 50+916
163 51+303 51+367
164 51+705 51+775
165 51+758 51+829
166 51+916 51+985
167 52+604 52+672
Work Completed Till End of Last Month Progress during this Month
Status Of Pipe Culverts
Sl.
No
Ch
ain
ag
e
SR RHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
He
ad
Wa
ll
De
sig
n
Ch
ain
ag
e
SR LHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
MCW RHS
Ex
ca
va
tio
n
MCW LHS
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
Ex
ca
va
tio
n
Pip
e L
ay
ing
He
ad
Wa
ll
PC
C
Panvel - Indapur MPR No-37 February ‘15 Page 148
168 53+126 53+185
169 53+276 53+315
170 53+977 54+015
171 54+254 54+254
172 54+446 54+515
173 54+563 54+630
174 54+971 54+980
175 54+987 55+055
176 55+018 55+087
177 55+553 55+621
178 55+794 55+862
179 56+166 56+234
180 56+544 56+612
181 57+952 58+018
182 58+173 58+241
183 58+222 58+290
184 58+632 58+700
185 59+290 59+350
186 60+921 60+984
187 62+397 62+460
188 63+000 63+063
189 63+486 63+548
190 63+805 63+866
191 64+149 64+210
192 64+608 64+665
193 64+685 64+742
194 64+808 64+808
195 64+874 64+842
196 64+915 64+931
197 65+069 65+060
198 65+115 65+127
199 65+348 65+407
200 65+987 66+0691
201 66+073 66+135
202 66+314 66+373
203 67+485 67+544
204 67+676 67+735
205 67+743 67+801
206 68+207 68+266
207 68+328 68+400
208 68+408 68+480
209 69+520 69+580
210 70+477 70+537
211 70+574 70+660
212 70+765 70+825
213 71+018 71+078
214 71+205 71+265
215 72+016 72+085
216 72+213 72+374
217 72+391 73+450
218 72+491 73+550
219 74+591 74+575
220 74+970 75+029
221 76+341 76+400
222 78+537 78+598
223 78+697 78+755
224 79+714 79+764
225 80+912 80+981
226 81+772 81+861
227 82+986 82+900
228 83+629 83+687
Work Completed Till End of Last Month Progress during this Month
SR RHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
He
ad
Wa
ll
Status Of Pipe Culverts
Pip
e L
ay
ing
De
sig
n C
ha
ina
ge
He
ad
Wa
llSl.
No
Ch
ain
ag
e
MCW LHS MCW RHS
Ex
ca
va
tio
n
PC
C
SR LHS
Ex
ca
va
tio
n
PC
C
Pip
e L
ay
ing
Pip
e L
ay
ing
He
ad
Wa
ll
Ex
ca
va
tio
n
PC
C
He
ad
Wa
ll