COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
NATIONAL FERTILIZERS LIMITED
(A GOVT of India Undertaking) VIJAIPUR UNIT Distt. GUNA (M.P.)-473111 Fax: 07544-273089, 273109 Mobile no: 9464169624, 9417560184
INVITATION TO BID (ITB)
Name of Work: Design, Engineering, Supply, Erection, Commissioning & GTR of VAM, its Auxiliaries & Replacement of Filter House of GTG’s in CPP and air compressor in Ammonia-II Plants on LSTK basis. National Fertilizers Limited invites sealed bids from eligible EPC vendors having proven experience and sound financial capability for LSTK, Engineering, Supply, Erection, Commissioning & GTR of VAM units along with replacement of existing filter houses, installation of chilling coil & auxiliaries for suction air cooling. These VAM units are to be installed in captive Power Plant (CPP) and Ammonia-II Plant at NFL, Vijaipur as specified in enclosed ITB documents.
To M/s
ITB No. NFVP/PROJ/VAM/ICB/18-19
Date of Issue
Bid Closing Date & Time
Bid Opening Date & Time
Venue of Bid Opening NFL,Vijaipur (India)
Type of Bid Two part bid system, Public
Earnest Money Deposit INR 01 Lakh or equivalent USD
Preferred Completion period As per ITB
Estimated refrigeration load of VAM in CPP is 3300 TR (two or three units) and 1270(one or two units) for Ammonia-II Plant. However, Vendor shall mention actual TR required on the basis of furnished data in the technical ITB in respect of weather data, chilled water, power, cooling water & steam for actual TR so as to achieve specified cooled air temperature at filter house outlet& chilled water temperature at VAM outlet.
Air is to be cooled from 40°C at 41% RH to 15° C at 100% RH in case of GTGs of CPP. In case of Ammonia II, Suction air of Process Air Compressor is to be cooled from 40°C at 41% RH to 15°C at 100% RH and residual refrigeration load is to utilized for cooling third suction synthesis gas from 45°C to 15°C. Value of Annual Rate Contracts for a period of three years excluding guarantee period & two years operation & maintenance spares as lump sum amount shall be separately indicated in the
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
price bid. The cost of 03 years ARC and two years operation & maintenance spares will be considered during evaluation of the price bid.
Cost of Annual required quantity of make-up chemical shall be indicated by the vendor and the same shall be considered for bid evaluation purpose.
Details of all proposed VAMs, pre-qualification criteria & guarantee parameters etc, has been indicated in technical ITB. Bidders are required to visit site & understand the existing system before submitting bid. Following enclosed documents shall form part of invitation to Bid: 1. Commercial ITB 2. Technical ITB for GTGs and Ammonia II
The bid is issued under international competitive bidding procedure. For preparation and submission of bids, evaluation& comparison of bids; kindly refer commercial ITB.
Note:
1. Special conditions of contract shall prevail in case of any variance in respect of terms & conditions of contract.
2. The bidder must take note of current finance bill & EXIM policy while bidding. 3. Two valid e mail ID’s shall be furnished for further communication. The date & time
shall be communicated later on to bidders who shall qualify for price bid opening. For & on behalf of National Fertilizers Limited (V.K. Gupta) Dy. General Manager (TS)
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENTS
ATTACHMENT-I INSTRUCTION TO BIDDER
ATTACHMENT –II GENERAL INSTRUCTION OF CONTRACT
ATTACHMENT –III SPECIAL CONDITIONS OF CONTRACT
ATTACHMENT –IV BID FORM , PRICE SCHEDULE & SUMMARY OF TERMS & CONDTIONS
ATTACHMENT –V BID & BG FORMAT
ATTACHMENT –VI FORMAT FOR EXCEPTION & DEVIATIONS
ATTACHMENT –VII SITE WORKING AND SAFETY CONDITIONS
ATTACHMENT -VIII APPLICABLE INDIAN ACTS RULES & REGULATIONS
ATTACHMENT –IX INTEGRITY PACT
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
INSTRUCTION TO BIDDERS
(ATTACHMENT-I)
FOR
INSTALLATION OF VAM UNIT FOR NFL VIJAIPUR
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
TABLE OF CONTENTS. (Instruction to Bidder Attachment I)
Sr. No. Description Remarks
1. Introduction
2 Site Information
3 Cost of Bidding
4 Bidding Documents
5 Clarification of Bidding Documents
6 Pre bid meet/Amendment of Bidding Documents
7 Language of Bid
8 Documents comprising the Bid
9 Bid Form
10 Bid Price
11 Bid Currencies
12 Pre Qualification Criteria
13 Documents Establishing conformity of Goods of Bidding Documents
14 Bid Security and Earnest Money Deposit
15 Period of Validity of Bids
16 Format & signing of Bids
17 Sealing & marking of Bids
18 Late Bids
19 Modification & withdrawal of Bids
20 Opening & Clarification of Bid
21 Preliminary Examination
22 Conversion to single currency
23 Terms of Payment
24 Bank guarantee
25 Contacting the Owner
26 Bid conformity
27 Owner’s right to accept any bid or all bids
28 Notification of award
29 Signing of Contract Agreement
30 Performance security
31 Completion period
32 Exceptions
33 Contractor’s Data
34 Applicability of custom duty for the project
35 Evaluation & Comparison of Bids
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
INTRODUCTION AND PROJECT SYNOPSIS:
1.0 INTRODUCTION: NATIONAL FERTILIZERS LIMITED (NFL), hereinafter referred to as NFL, is a public sector undertaking under the Ministry of Chemicals & Fertilizers, Government of India. It has four operating units situated at Nangal, Bathinda in the state of Punjab, and Panipat in the state of Haryana and Vijaipur in the State of Madhya Pradesh. Vijaipur Unit is located at Vijaipur in Guna District Madhya Pradesh on Agra-Mumbai National Highway (NH-3), about 550 kilometers from Delhi. Site is well connected by B.G Railway line and road to all parts of India. Nearest Air Port is located in Bhopal. The Vijaipur Unit of National Fertilizers Ltd.(NFL) is operating two Ammonia Plants each of (1350 MTPD design capacity). Both the plants have been reassessed at 1520 MTPD capacity from01.04.2000 by Government of India (GOI). Presently these plants are operating at 1750 MT and 1864 MT after revamp of Vijaipur – I and Vijaipur-II respectively. NFL Vijaipur is also operating two Urea Plants each of 2200 MTPD design capacity. Both the plants have been reassessed at 2620 MTPD capacity from 01.04.2000 by Government of India (GOI). Presently these plants are operating at 3031 and 3231 MTPD after revamp of Vijaipur –I and Vijaipur-II respectively. NFL proposes to install Vapour Absorption Machine (VAM) of estimated load 3300 TR (two or three units) in CPP plant and 1270 TR (one or two units) in Ammonia –II plant along with its auxiliaries & replacement of existing filter house of GTSs of CPP and Process Air Compressor (PAC) of Ammonia –II plant in order to cool inlet suction Air from 40 degree C at 41% RH to 15 degree C at 100% RH. Synthesis Gas of third suction chiller of syn gas compressor is to be cooled from 45 degree C to 15 degree C of Ammonia – II plant. Accordingly Bids are invited from EPC Contractors having proven experience and sound financial capabilities / consortium of EPC Contractors willing to work together under single agreement on LSTK basis for the job of Engineering, Supply,Erection,Pre-Commissioning,Commissioning and GTR of VAM unit,it’s auxiliaries & replacement of existing filter houseof GTGs in CPP and Ammonia-II Process Air Compressor (PAC) in order to coolinlet suction Air from 40 degree C at 41% RH to 15 degree C at 100% RH. Synthesis Gas of third suction chiller of syngas compressor is to be cooled from 45 degree C to 15 degree C of Ammonia – II of Vijaipur Unit.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Scope of Proposal: Bidder is required to undertake the actual implementation of VAM units, it’s auxiliaries & replacement of filter house of GTGs in CPP and Ammonia-II Process Air Compressor (PAC) as per enclosed detailed technical specifications. The scope shall include but not limited to basic design & engineering, detailed engineering, procurement ,supply of equipments , commissioning & GTR along with spares for 2 years operation which must be quoted on lump sum basis based on the spares philosophy specified in the technical specifications, supply of 1st charge of chemicals, lube oil, inspecting / testing / expediting of orders, transportation, comprehensive insurance, assembly, civil works, construction, erection, pre-commissioning and commissioning, guarantee & performance test (GTR) and handling over the plant to Owner, training if required, any optional service if required etc. Dismantle of existing filter house as well as necessary modification, if required, for installation of supplied filter house with silencer shall be in the scope of bidder.
2.0 SITE INFORMATION
The site for the proposed project is located at VIJAIPUR in Guna District of Madhya
Pradesh. It is well connected by rail and road. 3.0 COSTOF BIDDING
The Bidder shall bear all costs associated with the preparation and submission of the
Bid, and National Fertilizers Limited (hereafter referred to as NFL or Owner or Purchaser) , in no case, be responsible or liable for these costs, regardless of the conduct or outcome of the bidding process. In case plant visit is required by Bidder before submitting the bid, it shallbeto bidder’s account. No adjustment in price will be accepted on the basis of insufficient knowledge as well as lack of information.
4.0 BIDDING DOCUMENTS
The Bidder is expected to examine all instructions, forms, terms and conditions in the bidding documents. The invitation to Bid together with all its attachments thereto shall be considered to be read, understood and accepted by the Bidder, unless deviations are specifically stated in seriatim by the Bidder. Failure to furnish shall information required by the bidding documents or submission or a Bid not substantially responsive to the bidding documents in every respect and insufficient no. of copies will be at Bidder’s risk and may result in the rejection of the Bid.
5.0 CLARIFICATION OF BIDDING DOCUMENTS
A respective Bidder requiring any clarification shall obtain the same from Owner’s office in writing by Fax/Email or by letter or in person so as to ensure submission of Bid on or
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
before Bid closing date. The Owner will respond in writing to such queries expeditiously. However, no extension in bid submission shall be granted on this account.
6.0 PRE-BID MEET / AMENDMENT OF TENDER DOCUEMNTS 6.1 At any time prior to the deadline for submission of bids, the Owner for any reason,
whether at its own initiative or in response to a clarification requested by a prospective bidder, may modify the bidding documents by amendment thereto.
6.2 PRE-BID MEET : the pre-bid meeting shall held after one week of issuance of NIT at NFL, Vijaipur site for resolving the issues with respect to Tender Documents Parties / bidders are requested to submit their queries four days prior the date of pre-bid meet.
6.3 The amendment will be notified in writing or by Email/Fax or letter to all prospective bidders who have attended the pre-bid meet and also upload the same on website.
6.4 The Owner/Purchaser may, at their discretion, extend the deadline for the submission of bids by amending the bidding documents in accordance with Articles 6.1 to 6.3above, in which case all rights and obligations of the Owner/Purchaser and Bidder previously subject to the deadline will thereafter be subject to the deadline as extended.
7.0 LANGUAGE OF BID 7.1 The Bid prepared by the Bidder and all correspondence / drawing and documents
relating to the Bid exchanged between the Bidder and the Owner / Purchaser shall be written in English language, provided that any printed literature furnished by the Bidder may be written in another language so long as accompanied by English translation in which case, for purpose of interpretation of the Bid ,the English translation shall govern.
7.2 Metric measurement system shall be applied for weight and dimensions other than pipes and piping connections. All piping material including but not limited to pipes, flanges, fittings, valves etc., shall conform to ASME dimensional requirements.
8.0 DOCUMENTS COMPRISING THE BID
8.1 The bid to be submitted by the bidder is defined as given hereunder: 8.2 Part–I Bid Security / Earnest Money Deposit (EMD)
Part –II Technical & Un-priced commercial Bid and documents relevant to pre-qualification criteria. Part-III Price Bid.
8.3 Part-I :Bid Security or Earnest Money Deposit (EMD) a) The bid shall be accompanied by an EMD as outlined in Artcile-14 and shall be submitted
in a separate cover to be marked with “ITB Number, Bid due date & Part-I of the Bid”.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
b) The envelope containing the EMD will be opened before opening of Part-II. The opening
of Part-II is dependent on the acceptance of the EMD with respect to EMD amount, whether original EMD is enclosed and validity of the Bank Guarantee or Demand Draft as the case may be.
8.4 Part –II: Technical & Un-priced commercial bid and documents relevant to pre-
qualification criteria 8.4.1 Technical Bid shall include / indicate but not limited to the followings: A) ITB No. -------------------------------------- Due Date------------------------------- B) 1. A detailed description of the process offered including overall process scheme and the
specific merits in the process being offered.
2. Process flow diagram of the proposed VAM Unit for normal capacity and turndown capacity. The PFDs (for normal and turn down capacity) shall be furnished for both the capacities of VAM unit i.e. for actual TR calculated by the party as per the conditions specified in technical bid and at turn down ration of 30%, 40% & 50% and its hook up with the existing system indicating flow rates, pressure, temperature and heat duties etc.
C) Details of complete scope of work supported by drawings, documents, brochures,
standards, catalogues, etc as applicable as per ITB. D) Performance Guarantee figures with respect to (For actual TR and Turn down ratio at
30%, 40% & 50%) a) Cooled air temperature b) Chilled water temperature (for demonstration purpose) c) Differential pressure across new filter house. d) LP Steam consumption / condensate consumption e) CW Consumption f) Consumption of power for VAM &it’s auxiliaries
E) List of spare parts for Two year’s operation and maintenance :- A list of spares as per
the spares philosophy specified in the technical specifications of the ITB must be submitted by the bidder. The list of spares shall however be subject to comment & approval of NFL. The quantity of spares mentioned shall be defined in “SET” as well as in “ Number”. Different items considered in one set shall be separately enumerated.
F) List of maintenance tools and materials, lubrication, schedule. G) Layout drawings and sketches with (approximate) dimensions of equipment and
indication of limits of supply.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
H) Bidder shall state the names of the sub-contractor proposed for major equipment / item / materials / services for approval of parties / vendors from NFL.
I) Bidder should certify that they will give shop drawings of main equipment to enable repair, and maintenance after installation at Site. Reproducible of “as built” drawings shall be furnished.
J) Nature of maintenance assistance available / offered by Bidder. K) Completion schedule with bar chart indicating major milestones. L) Reference list of customers of similar plants. M) Complete data sheets as requested by NFL. Indicate time of submission. N) Deviation from Owner’s specifications / technical conditions, ( if any ). O) Training facilities offered. P) Pre-qualification Documents as per Article-12.
8.4.2 Un-priced commercial Bid shall include / indicate the following: A) ( ITB No. _________ Due Date: _____________________ B) Bid form and a price schedule completed in accordance with Article 9,10 and 11. C) Summary of terms and conditions duly filled and signed. D) Un-Priced copy of price schedule indicating “ Quoted /Not quoted” against each head of
price schedule.Un-Priced copy of spare parts for Two year’s operation and maintenance indicating “ Quoted /Not quoted” against each item.
E) All Commercial terms & conditions of offer indicating terms of payment firm prices, completion period, bid validity, Taxes and duties/GST considered etc.
F) Confirmation that validity of bid is 120 days from the Technical Bid opening date indicated in the cover of ITB.
G) For Price bid Format (unpriced), percentage of GST and any other taxes / duties / levies and custom duty are to be given except the price part.
H) Acceptance of General, Special and Site Working & Safety Conditions of Contract or deviations / exception s, if any, in seriatim.
I) Bidder must indicate name of bankers and allterms of letter of credit. J) Bar Chart / Curves showing shop loading up to 2018 vis-à-vis capacity based on orders in
hand shall be submitted by the bidder. K) Organization chart. 8.5 Part-III – Price Bid
The price bid as per enclosed Form F-33 shall be submitted in a separate sealed Envelope marked Part-III Price Bid and ITB No. _________. Bid should include the Bid price and other related costs, in accordance with Article 10, Article 34and appropriate Price Schedule formats.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
9.0 BIDFORM Bidder shall complete the appropriate price schedule format indicating the work to be done, a brief description of the services.
9.0 BID PRICE 10.0 10.1 Bidders shall quote on duly commissioned plant at site basis. The Bidders shall quote
firm lump sum price for the entire scope of work providing commissioned plant as per technical specifications given in schedule of prices of ITB and shall give detailed break up as per format F-33.
10.2 The Bidder shall submit bid price considering applicable custom duty as outlined in Article- 34
10.3 Following information wherever applicable is to be submitted in a separate schedule. a) GST and any other taxes if applicable. b) Bidders shall provide customs tariff heading for each item separately along with
applicable rates of duties as outlined in Article 34. c) Packing, forwarding and loading charges should be included in the quoted prices. d) Bidder must quote the item-wise prices for recommended spare parts separately for
Two year operation and maintenance spares. Spares for commissioning are included in Contractor’s scope. However, Bidder shall provide the list of commissioning spares. The quantity quoted shall be defined in “SET” as well as in Number’s Different items considered in one set shall be separately enumerated.
e) Agency commissioning included for Indian agent, if any, the same should be shown separately as percentage of FOB price and shall be payable in Indian rupees at prevailing exchange rate on date of bill of lading.
f) Charges for inspection / testing should be include in the offer as per requirement of technical documents of ITB.
g) Bidder’s cost of site assembly, pre-commissioning and commissioning until acceptance as per technical specifications wherever applicable.
10.4. Quoted Price shall be Firm Price and shall be valid for entire period of execution of
Contract. 105 Price shall be written in both words and figures. In the event of difference, the price in
words shall be valid and binding. Unit prices shall be considered correct in the event of any discrepancy with regard to total price.
11.0 BID CURRENCIES
11.1 Bidders may quote for imported component of the scope of work including imported
raw material component or indigenous supply of equipments in their home currency, or
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
in Euro or in US$ or in British Pounds or inn Japanese Yen or in any combination thereof, and for Indian component of scope of work in Indian currency.
11.2 In respect to imported component of scope of work including imported raw material component of indigenous supply of equipments,payment to Indian bidders shall be made in Indian currency based on exchange rate prevalent on contracted date of milestone or actual date of completion of components of respective milestone which ever is lower subject to submission of invoice, except to the extent FOREX remittance is otherwise permissible under Foreign Exchange Remittance Guidelines.
11.3 For bid evaluation Conversion will be based on exchange rate on one day prior to price bid opening as per Clause No. 22.
12.0 PRE-QUALIFICATIONS CRITERIA FOR BIDDERS
As contained in Technical part of ITB at Annexure IX& as given below.
12.1 In case bidder is a consortium / joint venture or partnership , the bidder shall produce an agreement and other documents defining the liability, arrangements and responsibility of the partners of EPC consortium / joint venture (requirements under Para 12.2).
In case of detailed engineering is done in-house , EPC Contractor is to submit credentials & details indicating name of the project, client, country, brief scope of work, year of executionand value of work.
In case of detailed engineering is done by other than the EPC Contractor, the bidder should submit the nameof the intended contractor and their credential indicating name of the project, client, country, brief scope of work, year of execution and value of work carried out by them.
In both the above cases, letter from the owner /end user for the satisfactory completion of the project to be submitted.
12.2 CONSORTIUM BIDS (WHERE APPLICABLE) 12.2.1 In case of Consortium BID , in their won interest, the BIDDERS are advised to investigate
capabilities, availability of expertise and resources such as experienced personnel, financial soundness, past experience and concurrent engagements of constituting partners / members. Consortium of Bidders, if any, must clearly define role/scope of work of each partner / member. Further the Contract for a Consortium must accompany the Bid and should clearly define the leader of such a Consortium, who shall co-ordinate with NFL on behalf of the Consortium, during the period which the Bid is under evaluation by NFL or is being negotiated with NFL as well as during execution of Work, in the event the Work is awarded. All the members of theConsortium shall be jointly and severally responsible for the execution of the Work in accordance with the Contract.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
12.2.2 A consortium once established at the time of submitting the BID shall not be allowed to be altered with respect to constituting members of the consortium or their respective roles / scopes of work, except if and when permitted in wiring by OWNER.
12.2.3 If during the evaluation of BID, a Consortium proposes any alterations / changes in
orientation of consortium or replacement or inclusion or exclusion of any partner(s) member(s) of the consortium which had originally summated the BID, to derive some advantage / benefits based on any development(s) having come to his knowledge at any time, the BID submitted by such a consortium may be rejected.
13.0 DOCUMENTS ESTABLISHING CONFORMITY OF GOODS/SERVICES TO BIDDING
DOCUMENTS. 13.1 Pursuant to Article 8, the Bidder shall furnish, as part of the Bid, documents establishing
conformity to the bidding documents of all Goods and services, which the Bidder proposes to supply under the conditions of Contract.
13.2 The documentary evidence of the conformity of the ‘Goods’ and ‘Service’ to the bidding
documents may be in the form of literature, drawings and data and Bidder shall furnish:
a) Detailed description of the Goods and services essential technical and performance characteristics of the Goods.
b) A list, giving full particulars including available sources and current prices of all
spare parts, special tools etc., Necessary for the proper and continuous functioning of the Goods and services for a period of two years following commencement of the use of Goods by the owner.
c) A clause-by-clause comments on the Owner’s technical specifications
demonstrating the “Goods and Services” substantial responsiveness to those specifications or a statement of exceptions to the provisions of the Technical specifications.
13.3 For purpose of the comments to be furnished pursuant to Article 13.2 (c) above, the Bidder
shall not that standards for workmanship, material and equipment and references to brand
names or catalogue numbers, designed by the Owner in his technical specifications are intended
to be descriptive only and not restrictive. The Bidder may substitute alternative standards,
brand names and /or catalogue numbers in his Bid provided that they demonstrates to the
satisfaction of the Owner that the substitutions are substantially equivalent or superior to those
designated in the technical specifications.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
14.0 BID SECURITY / EARNEST MONEY DEPOSIT (EMD)
14.1 The Bidder shall furnish, as part of his Bid, one Bid Security in the form of a Bank
Guarantee, issued by scheduled bank(Excluding Gramin/ Co-Operative Bank) or by an
overseas branch of any Scheduled Indian bank for foreign bidder with validity of offer
validity plus ninety days claim period. In case a foreign bank issues, the same shall
be counter guaranteed by a Scheduled Indian Bank except Gramin/ Co-Operative
Bank. The Bid Security shall be in favour of the National Fertilizers Limited. Bid
security amount will be Rs.1.0 lakh. The Bid Security shall be furnished in the
currency in which the Bid Price is quoted. The Bank Guarantee shall be in prescribed
form of NIT. A Bid Security can be in the form of a demand draft in favour of
National Fertilizers Limited, Vijaipur Unit payable at Bavarikheda Branch code
08455.The bid security can be deposited by RTGS/NEFT.
The bidder shall furnish a Bank Guarantee from any of the Scheduled Bank (excluding
Gramin/Cooperative Bank) in the form specified by NFL against bid Security. The
Bank Guarantee should be valid for a period of offer validity plus three months claim
period thereafter. The Bank Guarantee should be submitted by Bankers directly to
NFL in a sealed cover (Registered Post AD) and not through supplier.
The bidder shall also arrange confirmation of Bank Guarantee (including all
amendments) by their issuing bank through SFMS mode directly to State Bank of
India, N-3,Ist&II
nd Floor, Commercial Branch, SouthExtn. Part I, New Delhi -110049
(ISFC Code – SBIN0000730 or SBININBB220).
14.2 Any Bid not accompanied with EMD shall be rejected by the Owner is non-responsive
14.3. The EMD will be returned to the unsuccessful Bidders on acceptance of one of the
invited bids or when the Bid is cancelled by Owner.
14.4 The successful Bidder’s EMD will be discharged upon the Bidder accepting the Contract and furnishing The Security Cum Performance Bank Guarantee.
14.5 In the following events, the EMD may be forfeited without prejudice to any other right or remedy of Owner: a) If a Bidder withdraws his Bid during the period of Bid validity specified by the Bidder
on the Bid form or b) In case of a successful Bidder, If the Bidder fails:
To Sign the Contract in accordance with Article 30or
To furnish performance Security in accordance with Article 31.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
15.0 PERIOD OF VALIDITY OF BIDS
15.1 Bids shall be kept valid for at least 120 days from the Technical Bid opening date indicate in the cover page of ITB. A Bid valid for a shorter period may be considered as non-responsive and liable to be rejected by the Owner.
15.2 In exceptional circumstances, the Owner may solicit the Bidder’s consent to an extension of the period of validity. The request and the responses thereto shall be made in writing through a letter or by fax / email. A Bidder having been granted the request, will neither be required nor permitted to alter the Bid
16.0FORMAT AND SIGNING OF BID
16.1 The bid must contain in the name, residence and place of business of the person or persons making the bid and must be signed and sealed by the Bidder with his usual signature. The names of all persons signing should be typed or printed below of the signature.
16.2 Bid by partnership firm must be furnished with full names of all partners and be signed with the partnership name followed by the signature and designation of one of the authorized partners or authorized representative(s).
16.3 A bid by a Corporation / Company must be signed with the legal name of the Corporation/ Company by the President, Managing Director or by the Security or other person or persons authorized to bid on behalf of the such Corporation / Company in the matter, with the official seal of the Company.
16.4 A bid by a person who affixed to his signature the work “President “ Managing Director”, “Secretary”, “Agent” or other designation without disclosing his principal will be rejected. Satisfactory evidence of authority of the person signing on behalf of the bidder shall be furnished with the Bids. Bidder shall submit power of attorney on non-judicial stamp paper of minimum Rs. 10 for the person who will sign the bid document.
16.5 The Bidder’s name stated on the proposal shall be the exact legal name of the firm. 16.6 Erasure or other changes in the bid documents shall be over the initials of the person
signing the bid. 16.7 Bids not confirming to the above requirements of signing may be disqualified. 17.0 SEALING AND MARKING OF BIDS 17.1 The Bidder shall submit the offer in three inner envelops as indicated below which shall
be sealed in one outer envelope. i) Envelope –I The 1st inner envelope shall contain the EMD and shall be supper-scribed with (BID
PART-I – EMD ) and ITB NO. --------- Due Date -------- ii) Envelope-II ( Technical& un-priced commercial bid&PQ criteria)
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
The second inner envelope should contain 1 (one) original plus 3 copies of technical Bid together with un-priced commercial Bid and deviations statement if anyas well as documents relevant to pre-qualification criteria, This envelop should be clearly marked (BID PART-II TECHNICAL & UNPRICED COMMERCIAL BID &PQ criteria) and ITB NO. ------- Due Date ---------------
iii)Envelope-III (Price Bid) The third inner envelope should contain 1 (one) original plus 3 copies of PRICED COMMERCIAL BID with price details. The cover should clearly be marked (BID PART-III – PRICE BID ) and ITB NO.------Due Date --------------- All the three above inner envelopes shall be sealed and these sealed envelopes shall be kept in the 4th envelope called outer envelope
17.2 This outer envelope shall be sealed properly. The outer envelope shall be addressed to:
Deputy General Manager (TS) National Fertilizers Limited, VIJAIPUR, DIST. GUNA (MP) PIN – 473111. And bear the title“ INSTALLATION OF VAM AT NFL VIJAIPUR”
ITB No. ________________ BID CLOSING DATE: _____________________- “ DO NOT OPEN BEFORE ------------------- “ The outer envelope shall indicate the name of the address of the bidder to enable the bid to be returned un-opened in case it is received late.
17.3 If the outer envelope is not sealed and marked as required by clause 17.2above, the owner will assume no responsibility for the bid-misplacement or pre-mature opening.
18.0 LATE BIDS Any Bid received after the deadline for submission of bids indicated on main body of
Invitation to Bid or any other date extended in writing will be rejected. 19.0 MODIFICATIONS AND WITHDRAWAL OF BIDS.
19.1 The Bidder may modify or withdraw the Bid after its submission, provided that written notice of the modification or withdrawal is received by the Owner prior to the deadline prescribed for submission of bids.
19.2 A withdrawal notice may also be sent by fax or email but followed by a signed
confirmation copy, post marked not later than the deadline for submission of bids.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
19.3 No Bid may be withdrawn in the interval between the deadline for submission of bids and the expiration of the period of Bid validity specified by the Bidder on the Bid form.
20.0 OPENING AND CALRIFICATIONOF BIDS 20.1 The bids will be opened in presence of bidder’s representatives who wish to be present. 20.2 Owner will open the Bids. The Bids will be opened in public in presence of bidders or
their authorized representative. Only technically acceptable bidder’s representative shall be invited to attend Price Bid Opening who will be given adequate notice to attend the Bid opening.
21.0 PRELIMINARY EXAMINATION 21.1 The owner will examine the bids to determine whether they are complete, whether any
computational errors have been made, whether required EMD has been furnished and pre-qualification criteria is met, whether the documents have been properly signed, whether validity of the Bid is inconformity with ITB and whether the bids are generally in order.
21.2 The prices should be written both in words and figures and in case of any discrepancy, prices in works shall be valid and binding. In case of any error in totals indicated by Bidder, the unit price shall be considered valid and binding on Bidder.
21.3 Prior to the detailed evaluation, the Owner will determine the substantial responsiveness
of each Bid with reference to the bidding documents. For purpose of this article, a substantially responsive Bid is one, which conforms to all the terms and conditions of the bidding documents without material deviations. The Owner’s determination of the Bid’s responsiveness is to be based on the contents of the Bid itself, without recourse to extrinsic evidence.
21.4 A Bid determined as substantially non-responsive is liable to be rejected by the Owner
and may not subsequently be made responsive by the Bidder by correction of the non-conformity.
21.5 The Owner may waive off any minor infirmity or non-conformity or irregularity in a Bid,
which does not in their opinion constitute a material deviation.
21.6 After a preliminary screening based on both technical and up-priced commercial evaluation, bidders will be short-listed. In the event that any clarifications are required, then such clarifications shall be obtained from such short listed bidders only. Based on the clarifications, the technically acceptable bidders shall be asked to submit the price
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
implication (positive or negative) on original quoted price with respect to techno-commercial clarifications if any, (in a sealed cover, Envelope IIIA) on a prefixed date and time which shall be communicated to the bidder.
22.0 CONVERSION TO SINGLECURRENCY
To facilitate evaluation and comparison, the Owner will covert all bid prices expressed in the amounts in various currencies in which Bid price is payable, to Indian rupees based on exchange rate TT selling as published in The Economics Times/ Internet, Delhi Edition for a day prior to the date of Price Bid opening.
23.0 TERMS OF PAYMENT 23.1 The payment to Contractor for the performance of the works for installation of fully
commissioned plants after performing the guarantee test runs to ensure that the plants meet the specifications stipulated under the contract will be made as per terms of payment set forth herein. No payments shall become due and payable before:
a) Acceptance of Letter of intent and Work Order. b) Execution of Agreement. c) Submission of Security cum Performance Bank Guarantee for 10% of the Total
Contract value and acceptance of the same by Owner.
23.2A Advance Payment: No advance payment shall be admissible, however, in exceptional circumstances advance of not more than 10% of Total Contract value as interest bearing advance against submission of Bank Guarantee for equivalent amount and Security cum Performance Bank Guarantee for 10% of Total Contract value shall be made. Such advance will carry interest @ SBI PLR+1% prevalent on the date of release of advance payment till adjustment. Such advance, wherever agreed to, shall be adjusted from the progressive payment.
23.2B Progressive Payments (Indian Bidders)
The Progressive payments shall be made on the basis of achievement of following milestones as per detailed billing submitted by bidder and approved by NFL:
a) 85% after adjustment of advance pro-rata payment, if any, against completion of following activities after physical verification& certification by Owner.
i) Detailed Engineering Fees: 85 % after adjustment of advance, if any, on submission of detailed Engineering Package on pro-rata monthly progress measurement of detailed engineering work.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ii) Civil Work: 85% after adjustment of advance, if any, on pro-rata monthly installments linked with progress of work against certification of Owner as per the billing schedule submitted by the Contractor and approved by the Owner.
iii) Supply of Equipments , machinery, electrical, instruments, piping, Proprietary supplies, two years spares etc, including taxes and duties subject to submission of documentary evidence, Transportation to site, port handling and clearance charges (excluding site fabricated equipment) : 85% after adjustment of advance if any on pro-rata basis on receipt of items at site against physical verification & certification by owner. However, for major equipments this payment can be considered on submission of proof of dispatch. Contractor shall submit the list of such major equipments along with the bid for owners review and finalization.
iv) Erection (including fabrication of site fabricated equipments) 85% after adjustment of advance if any on pro-rata monthly installment linked with progress of work against certification by Owner as per the billing schedule submitted by the Contractor and approved by the Owner.
v) Pre-Commissioning and Commissioning charges: a) 40% after adjustment of advance, if any,on Mechanical completion against
certification by Owner. b) 50% after adjustment of advance, if any, after on commissioning & stabilization of
plant against certification by Owner. vi) Spares including taxes & duties transportation to site, port handling & clearance charges
: 85% after adjustment of advance, if any, on physical handling over of spare and acceptance of the same by Owner.
vii) Insurance Charges : 85% after adjustment of advance, if any ,against the documentary evidence in support of taking insurance cover and on proof of installment payment.
b) MECHANICAL COMPLETION: - 5% of Total Contract value on acceptance & issue of
Mechanical completion Certificate.This 5% payment will be made on issuance of mechanical completion of individual VAM system with filter house i.e CPP Vam and Ammonia II Vam separately.
c) FINAL PAYEMNT: 10% of the Total Contract value on successful completion of guarantee tests as specified in the contract and within 60 days of FINAL ACCEPTANCE of the plants & facilities by the Owner and shall be released subject to fulfillment of conditions of ITB. This 10% payment will be made on issuance of acceptance certificate of individual VAM system with filter house i.e CPPVam and Ammonia II Vam separately.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
23.3 Foreign Bidder
23.3.1 All payment shall be made against presentation of shipping documents through letters of
credit shall be allowed for Foreign Bidders / Contractors /Suppliers. Such letter of credit,
where agreed, shall be on Acceptance of LOI. The Bank charges relating to such letter of
credit outside India and subsequent amendments, if any, shall be to
Bidder/Contractor/Supplier’s account, while the charges payable to Bankers in India shall
be to Owner’s account. If the Contractor/Supplier want confirmed letter of credit, the
charges for the same will be to the Contractor/ Supplier’s account.
85% payment through letter of credit against dispatch/shipping documents and balance
15% as under:
MECHANICAL COMPLETION: - 5% of Total Contract value on acceptance & issue of Mechanical
completion Certificateshall be made through Letter of Credit. This 5% payment will be made on issuance of mechanical completion of individual VAM system with filter house i.e CPP Vam and Ammonia II Vam separately.
FINAL PAYEMNT: 10% of the Total Contract valueshall be made through Letter of Credit on successful completion of guarantee tests as specified in the contract and FINAL ACCEPTANCE of the plants & facilities by the Owner and shall be released subject to fulfillment of conditions of ITB. This 10% payment will be made on issuance of acceptance certificate of individual VAM system with filter house i.e CPPVam and Ammonia II Vam separately.
23.3.2 All Bank charges of Contractor/Supplier’s Bankers shall be to be Contractor/Supplier’s
account.
23.3.3 Dispatches after due delivery date with predetermined damages as per provisions of
article 23.1 of the General Conditions of Contract/Purchase shall be made only after
written approval by Owner which may be accorded at Owner’s discretion in exercise of
options available under aforesaid article 23 of the General Conditions of
Contract/Purchases.
23.3.4 Owner shall pay to the Indian agent towards commission as specified in the contract 50%
of the amount after receipt and acceptance of equipment at site and balance 50% on final
acceptance of plant. Payment shall be made in Indian Rupees against signed commercial
Invoice of Indian agent duly certified and approved for payment by Supplier/Contractor.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
The payment shall be based on exchange rate prevailing at the time of delivery or
contracted date of delivery whichever is earlier.
23.3.5 Payments shall be made in the currencies and amounts stated in the Contract/ Purchase
Order.
23.4 INDIAN AGENTS COMMISSION (IF APPLICABLE)
Owner shall pay to the Indian agent towards Commission as specified in the Contract 50% of the amount within 15 days of mechanical completion of both VAMs i.e.CPP Vam and Ammonia II Vamand balance 50% on final acceptance of plant for both VAMs i.e. CPP Vam and Ammonia II Vam.Payment shall be made in Indian Rupees against signed commercial invoice of Indian agent duly certified and approved for payment by Owner.
23.5 TRAINING EXPENSES:
Training of NFL personnel for VAM and filtration system shall be conducted by the bidder on free of cost at NFL site.
23.5 Advance Payment (Documentation) The preferred payment terms have been indicated above. NFL shall not make any
unsecured advance payment. However in exceptional circumstances,10% of the Total Contract value shall be paid as interest bearing advance to the Contractor on presentation of following documents. i) Unconditional acceptance of LOI / W.O. and Contract copy duly signed by Contractor ii) Commercial Invoice iii) Security deposit cum Performance Bank Guarantee of 10% of the total contract value iv) Bank Guarantee equal to the amount of advance plus interest thereon.
23.6 Full address with Email and Fax No. of the Scheduled Bank (Excluding Gramin/ Co-
Operative Bank) issuing / conforming the bank guarantee shall be indicated. 23.7 Payment shall be made in the currencies and amount stated in the Contract / Work
Order. 24.0 BANK GUARANTEE 24.1 Bidder shall furnish a bank guarantee for the amount to be paid in advance, as per
Performa enclosed from a scheduled bank (except Cooperative and Gramin Bank). The charges for confirmation, if any,will be to the Contractor’s account. The bank guarantees shall have a validity period till completion period plus 90 days claim period
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
from the date of completion stated in the Contract. The validity will be subject to extension if delays in Completion should occur.
24.2 Security deposit cum Performance Bank Guarantee issued or counter guaranteed by any
of the Indian Scheduled Bank (except Cooperative and GraminBank) or any branch of Foreign Bankin India and shall bevalid for the completion period plus defects liability period specified in the contract plus 03 (three) months claim periodthereafter. In case the Contractor fails to supply this bank guarantee within stipulated time, the Owner shall hold back an equivalent sum from payments due to the Contractor. However, such held back sum shall be promptly released on receipt of the confirmed bank guarantee and bank confirmation.
The bidder shall furnish a Bank Guarantee from any of the Scheduled Bank (excluding
Gramin/Cooperative Bank) in the form specified by NFL. The Bank Guarantee should
be submitted by Bankers directly to NFL in a sealed cover (Registered Post AD) and
not through supplier.
The bidder shall also arrange confirmation of Bank Guarantee (including all
amendments) by their issuing bank through SFMS mode directly to State Bank of
India, N-3,Ist&II
nd Floor, Commercial Branch, SouthExtn. Part I, New Delhi -110049
(ISFC Code – SBIN0000730 or SBININBB220).
25.0 CONTACTING THE OWNER
Any effort by a Bidder to influence in the Owner’s Bid evaluation, Bid comparison or Contract award decisions may result in the rejection of the Bidder’s Bid.
26.0 BID CONFORMITY
The Owner will determine to their satisfaction whether the Bidder selected is qualified in their opinion to satisfactorily perform the Contract.
27.0 OWNER’S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY OR ALL BIDS. Notwithstanding anything to the contrary contained herein, the Owner reserves the right
to accept or reject any Bid, and to annul the bidding process and reject all bids, at any time prior to award of Notice of Acceptance without thereby incurring any liability to the affected Bidder, or Bidders, or of any obligation to inform the affected Bidder, or Bidders of the grounds for the Owner’s action.
28.0 NOTIFICATION OF AWARD (LETTER OF INTENT)
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
28.1 The Owner will award the Notification (Letter of Intent) to the successful bidder whose Bid has been determined to be substantially most responsive and has been determined to be substantially most responding and has been determined as the lowest evaluated Bid after the final negotiation held with (If deemed necessary by Owner) the most competitive bidder.
28.2 Prior to the expiration of the period of Bid validity the Owner will notify the successful
Bidder by letter or Email / fax to be confirmed by letter that the Bid has been accepted and the “Letter of Intent” as above will constitute formation of Contract.
28.3 The successful bidder on receipt of “Letter of Intent” which may be in the form of
Email/Fax of intent or other mode shall convey his acceptance by return e-mail/fax and to be confirmed by letter within 7 day failing which it will be deemed that LOI is accepted unconditionally.
28.4 Completion period/schedule shall be counted from the date of “issuance of Fax / Letter
of Intent” 29.0 SINGING OF CONTRACT AGREEMENT. Owner will send format of Contract agreement to the successful Bidder who, within 30
days of the receipt of the same, shall sign and return two copies to the Owner as a token of his unconditional acceptance failing which Owner has a right to cancel / withdraw the Contract and forfeit the Bid Security.
30.0 PERFORMANCE SECURITY
30.1 Within 30 days of the receipt of LOI/WO from the Owner, the successful Bidder shall furnish to the Owner the Security Cum Performance Guarantee equivalent to 10% of the total Contract value in the form of a bank guarantee issued or counter guaranteed by any of the Schedule Banks (except cooperative & Gramin Bank ) or any branch of foreignbank in India in the format as specified by NFL. The bank guarantee for Performance Security shall be valid for a period to cover contract Completion period plus defect liability period of 18 months from the date of successful commissioning, plus a claim period of 03 months thereafter to fulfill all the warranties and guarantees obligations. The bank guarantee towards performance security shall be in the currency quoted by Bidder or U.S. Dollar. The charges for confirmation, if any will be to contractor’s account.
The Bank Guarantee should be submitted by Bankers directly to NFL in a sealed cover
(Registered Post AD) and not through supplier.
The bidder shall also arrange confirmation of Bank Guarantee (including all
amendments) by their issuing bank through SFMS mode directly to State Bank of
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
India, N-3,Ist&II
nd Floor, Commercial Branch, SouthExtn. Part I, New Delhi -110049
(ISFC Code – SBIN0000730 or SBININBB220).
30.2 This bank guarantee shall be extended for a further period as and when required by the
Owner to cover the defect liability period. 30.3 Failure of the successful Bidder to comply with the requirements of Article 30 or Article
31 shall constitute sufficient grounds for the annulment of the award in which event the Owner may make the award to the other responsive Bidder or call for new bids, without prejudice to Owner’s right and remedies as set forth in Article 25 of general condition of contract.
30.4 The non-judicial Stamp paper of appropriate value or equivalent document value
prevailing in the country of the Bidder shall have to be purchased in the name of the bankers executing the bank guarantee and not in the name of Bidders.
31.0 COMPLETION PERIOD 31.1 The Bidders are required to quote their best Completion period effective from date of
issuance of LOI (Notification of Award ) for the Work under this enquiry. 31.2 It shall be noted by Bidder that if a Contract is placed on the Bidder other than the
lowest acceptable Bidder for consideration of completion schedule alone, such selected Bidder/ Contractor shall be liable to pay to the Owner the difference in price between the Contract and corresponding price of the lowest Bidder in case of failure to complete the supplies in terms of such order within the date of completion specified in the Bid and incorporated in the Contract. This is without prejudice to Owner’s rights under the terms of Contract including the price reduction applicable for such delay. The application of such clause shall be notified to Contractor as a part of the contract.
32.0 EXCEPTIONS 32.1 No exceptions are to be taken by the Bidder to the Bid documents including technical
specifications, general and special conditions of contract. However, unavoidable exceptions, if any, both technical and commercial, are required to be listed and submitted separately, including the applicable cost and time of the priced commercial Bid. Exceptions should be clearly stated in the unpriced commercial Bid with a statement that cost implications for exceptions/deviations have been given in the priced commercial Bid. Time implications of withdrawal of exceptions should be given in the unpriced commercial Bid.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Unless the exceptions are listed separately in unpriced commercial bid as explained above, it will be assumed by the Owner that Bidder is complying with the Bid documents, and no cognizance shall be given to any exceptions stated anywhere else in the Bidder’s offer.
33.0 CONTRACTOR’S DATA 33.1 In addition to compilation of documents/ drawings / data required in the technical
specifications, Contractor’s data as noted on the attached Contractor data requirements form is also to be furnished by the dates noted in the applicable column. Contractor is to comply with all “instructions” detailed in this form. All Contractor data are to be submitted to Owner.
33.2 Contractor shall incorporate Contract number, requisition number(s) , item number(s)
description and tag number(s) on all Contractor data as called for on the attached form and any other data required by applicable specifications pertaining to the Contract.
33.3 The reproducible drawings furnished by Contractor must be of top quality from which
legible and clearly defined prints can be obtained. Drawings not meeting this requirement will be until acceptable reproducible are received. Installation, operation and maintenance data, when called for on the attached contractor data requirements form, shall include instruction books, dimensional and sectional drawings, recommended spare parts list and interchange ability, lubricant recommendation and complete parts list with detailed information for each part.
34.0 APPLICABILITY OF CUSTOM DUTY FOR THIS PROJECT. Bids are invited from Bidders for this project with the applicable custom duty only.
35. EVALUATION AND COMPARISION OF BIDS
1. The Owner will evaluate and compare only those bids, which are determined to be substantially responsive pursuant to Article 21.
2. Splitting of order shall not be allowed for CPP and Ammonia Plant VAM & its auxiliaries and Filter houses, a single P.O/W.Oshall be placed on Overall L-1 basis after loading all differential Costs of utilities etc. on both CPP Plant and Ammonia II plant.
3. The Owner’s evaluation of a Bid shall be done on the basis of “Cost as completed at Site” and shall comprise of:
A) Total Contract Price as given in Attachment IV – price schedule (F-33).
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
B) The cost of one set of two year spares as given in Annexure of (F-33). C) Consumption of the Raw Material & Utilities for Pre-commissioning &
Commissioning activities. D) ARC for 3 years in addition to guarantee period of 18 months. E) Loading on various deviations as detailed below:
i. Loading On Account Of Higher Completion Period-
A. In case Completion period offered by the Bidder exceeds beyond the preferred period indicated in the ITB, the Total Contract value shall be loaded by an amount calculated on the basis of 0.5% increase in total contract value for each week ( or part thereof) of extended period offered by the Bidder. This is without prejudice to Owner’s right to treat bids with completion period beyond required completion period indicated in ITB. Earlier Completion Period shall get no credit.
B. The completion period shall be effective from issuance of LOI. In case the
bidder specifies completion period from date of release of advance payment or signing of Contract, the same would be further increased by approximately two months and will be loaded accordingly as per above clause.
C. The loading as mentioned above shall not be applied in case the quoted delivery does not meet the project requirement and the bid shall not be qualified.
D. If the Bidders ask for grace period for applicability of Price reduction clause, the same shall be added to the quoted completion period. The completion period computed on the above basis shall be taken as completion period for each Bidder for the purpose of evaluation.
ii) Guarantees As Offered By Bidders: Proportionate loading shall be done in case Bidder
quotes warrantee / guarantee different in nature and period than required. This is without prejudice to Owner’s right to treat bids with different warranty / guarantee than those indicated in the ITB.
Following loading criteria shall be adopted:
Warranty/guarantee period Loading as % of Total contract value
Less than 18 months from the date of commissioning
10% x (18-quoted warranty in months) /18
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
iii)a Operating Cost: Loading shall be done to take care of the performance and productivity of the process and equipment offered. In case the consumption of the utilities are different for different bidders, extra operating cost over the minimum quoted shall be calculated as given below:
Extra Operating Cost = Difference in Utility Consumption (for actual TR) x unit cost of utility x 7920 x 0.95 x 6.07xNxn Where: 7920 = operating Hours / year 0.95 = Availability Factor 6.07 =The discount factor at an interest rate of PLR (presently 14.25% p.a) on Yearly basis for the period of 15 years. N=Number of years (15 years). n=Number of VAM Machines( 3no)
iii)b For every 5 mm WC increase in total average pressure drop across filtration stage along with cooling coil at GTG compressor intake/PAC compressor intake the GTG /PAC net power output decreases by 0.15% .
The loading factor for difference in average pressure drop over the minimum quoted value of average pressure drop shall be calculated as given below:
Difference in power output (KWH) x(Power cost)x 7920x6.07x0.95xNxn.
Where: 7920 = operating Hours / year 0.95 = Availability Factor 6.07 =The discount factor at an interest rate of PLR (presently 14.25% p.a) on Yearly basis for the period of 15 years. N=Number of years (15 years).
n= Number of Filter house in operation (3 nos) iv) The unit cost of utilities will be follows:
The Unit cost of utilities for loading shall be as follows:
Utilities Cost
Power (Electric) Rs. 4000 per MWH
Bid Closing Date Circulating Cooling Water Rs. 12 per M3
LP steam Rs. 1400 per MT
DM Water Rs. 25 per M3
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
The bidder shall indicate the quantity of power, steam , cooling water flow and other utilities for pre-commissioning and commissioning of the Plant till VAM unit is stabilized for specified conditions. a) The quantity in excess of indicated value shall be recovered from the contractor b) The quantity indicated by the bidder shall be considered for evaluation of bid.
v. Payment Terms:
“Deviation in Payment Terms: NFL will not make any advance payments. In exceptional cases, advance payments can be agreed subject to payment of interest @SBI PLR+1% prevalent on the date of advance released and submission of acceptable unconditional Bank Guarantee (BG) of equivalent amount (including interest amount ) As per “NFL” format. However, the deviation in payment terms with respect to NIT clause shall be loaded for interest @SBI PLR+1% prevalent on the date of price bid opening for the applicable period.
Sr.No. Payment terms Period of loading
1 Advance against LOI/PO Full delivery period +30 days
Interest on interest-free advance payment, if insisted by the bidder, shall be loaded at @SBI PLR+1% prevalent on the date of price bid opening for the Quoted Completion period by the bidderor preferred completion period of this ITB, whichever is higher.
vi. Loading on account of deviation of price reduction clause: If deviation is noted in the quoted price reduction clause. The following loading criterion shall be
adopted:
Sr. No.
quoted price reduction Loading Criterion
1 0.50% per week subject to a ceiling of5.00% of total order value (as per ITB)
No loading
2 Reduction accepted on undelivered value instead of total order value
2.50% loading on total order value
3 Non acceptance of price reduction clause
5.00% loading on total order value
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
vii. Calculation of CIF Price: To arrive at CIF prices for foreign bidders, FOB prices shall be loaded as under Ocean freight @ 3.00% of FOB value Marine Insurance @ 0.11% of FOB value
Port Handling Charges @ 1.00% CIF value
viii. Inland transportation Charges:
Inland transportation Charges shall be calculated @ 1% EXW Price for Indian and CIF Price for
Foreign Bidders.
ix. Inland Insurance:
The inland insurance shall be calculated @ 0.09% of EXW-FOT works for Indian Bidders and Ex
Indian port price for Foreign Bidders.
xi. Any clarification / confirmation having negative price implications received from Bidder after
price Bid opening shall be considered only for ordering purposes and not for evaluation
purposes. However, if during techno commercial clarification / confirmations having any price
implication (positive or negative) shall be considered for evaluation purposes.
xii. NIT CONDITONS: Whenever the bidder is silent about the acceptance of NIT conditions such as performance bank guarantee, warranty period, Price Reduction Clause (Damages) etc. it shall be presumed that the bidder has accepted these conditions andno loading shall be done while undertaking evaluation.
Any other cost resulting due to disagreement of bidder from ITB conditions will be loaded proportionately or higher as quoted by any other bidder.
******
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT-II
GENERAL CONDITIONS OF CONTRACT
INSTALLATION OF VAM FOR NFL, VIJAIPUR
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
TABLE OF CONTETS
(GENERAL CONDITIONS OF CONTRACT ATTACHMENT-II)
SR. NO. DESCRIPTION
1. DEFINITONS
2. SCOPE OF CONTRACT
3 STANDARDS
4. INSTRUCTIONS, DIRECTIONS AND CORRESPONDENCE
5. CONTRACT CONFIRMATION
6. MODIFICATION IN CONTRACT
7. USE OF CONTRACT DOCUMENT AND INFORMATION
8. PATENT RIGHTS
9. PERFORMANCE SECURITY
10. INSPECTION, TESTING AND EXPEDITING
11. TIME SCHEDULE AND PROGRESS REPORTING
12. PACKING & PRESERVATION
13. COMPLETION AND DOCUMENTS
14. INSURANCE
15. DESPATCH,TRANSPORTATIONAND SHIPPING INSTRUCTION
16. INCIDENTAL SERVICES
17. SPARES PART,MAINTENANCE TOOLS AND LUBRICANTS
18. WARRANTIES AND GURANTEES
19. ASSIGNMENT
20. SUB CONTRACT
21. JOINT AND SEVERAL RESPONSIBILITIES
22. DEALYS IN THE CONTRACT’S PERFORMANCE
23. DAMAGE/PRICE REDUCTION
24. REPLACEMENT REJECTIONS, REMOVAL OF REJECTED EQUIPMENT AND REPLACEMENT
25. TERMINATION OF CONTRACT
26. FORCE MAJEURE
27. RESOLUTIONOF DISPUTES / ARBITRATION
28. GOVERNING LANGUAGE
29. NOTICES
30. TAXES AND DUTIES
31. INSTRUCTION FOR INVOICING AND PAYMENT DOCUMENTATION
32. SPECIFICATIONS
33 GENERAL
34 GOVERNMENT CLEARANCES
35 PREFERENCE TO MAKE IN INDIA CLAUSE
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
1.0 DEFINITIONS In this General Conditions of Contract the following terms shall be interpreted as
indicated 1.1 “Contract shall mean and include invitation to bid, agreement entered into between
Owner and the Contractor. Technical Specifications, drawings, General Conditions, Special Conditions, commercial documents, general and special instructions issued from time to time by the Owner in writing, tender documents, letter of acceptance of bid, Letter of Intent (LOI), work order accepted schedule of rates and all these documents taken together and as modified from time to time in writing shall be deemed to form and construe one documents.
1.2 “ Contract Price” means the fixed LSTK price as described under Price Schedule (F-33)
payable by the Owner to the Contractor under Contract as full and final compensation and consideration for Contractor; complete proper performance of all of its obligation including completion of the Plant under and in accordance with the Contract.
1.3 Goods” means all the Equipment, machinery, and / or other materials, which the
Contractor is required, supply / execute to the purchaser under the Contract. 1.4 “Services” means services for design, engineering, procurement, construction,
installation, commissioning, and provision of technical assistance, training and other such obligations of the Contractor covered under the Contract.
1.5 “Owner / Purchaser / NFL” shall mean National Fertilizers Ltd., a Government of India
Undertaking , a company incorporated under the Companies Act, 1956 having its registered office at SCOPE Complex, Core-III,7, Instructional Area, Lodhi Road, New Delhi-110003 and Corporate Office at A-11,Sector-24, Noida, Distt. GautamBudh Nagar,UP-201301 and production units at Nangal, Bathinda (Punjab),Panipat (Haryana ) and Vijaipur (M.P.)
1.6. “Contractor” or “Bidder” shall mean the Contractor / any Consortium or Joint Venture
supplying the Goods/ executing the work / Services under the Contract. 1.7 “Sub-contract” shall mean Order/Contract placed by the Contractor, for any portion of
the Order or Work after necessary consent of Owner. 1.8 “Sub-Contractor” or “Sub-Vendor” or Sub-Contractor:- shall mean any persons or persons
or firm or their legal representatives, successors, assignees to whom part of Order has been sublet by the Contractor.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
1.9 “Site” shall mean the plant location at Vijaipur, for which this Contract has been issued
and where the Equipment shall be erected and commissioned. The location of plant site is in Vijaipur (Madhya Pradesh) India.
1.10 “Battery Limit” shall mean the area within which plant / Equipment are to be located. 1.11 “Equipment” shall mean and include any Equipment, machinery, electrical, instruments,
materials, stores to be provided for under this Contract and amendment thereto. 1.12 “Plant” shall mean entire assembly of the Equipment within specified Battery Limit 1.13 “Drawings” shall mean and include engineering drawings, sketches showing plants,
sections and elevations related to the Contract together with modifications and / or revisions thereto.
1.14 “Specifications” shall mean and include schedules, detailed description, statement of
technical data, performance characteristics, standards (Indian as well as international) as applicable and specified in the Contract.
1.15 “Engineer” shall mean the Engineer or Executive in-charge at Site nominated by Owner. 1.16 “Inspector” shall mean any person or outside agency nominated or agreed by Owner to
inspect Equipment stage-wise as well as final inspection, before dispatch, at Contractor’s work and on receipt at Site as per the terms of the Contractor.
1.17 “Tests” shall mean such process or processes to be carried out by the Contractor as are
prescribed in the Contract or considered necessary by Owner or their representatives in order to ascertain quality, workmanship, performance and efficiency of Equipment or part thereof.
1.18 “ Approval” shall mean and include the written consent, either manuscript, type –
written or printed statement, under signature or seal, as the case may be , of the Owner or their authorized representative on documents drawings or their particulars in relation to the Contract.
1.19 “FOB”, :FCA”, “CFR”,”CIF”, “FAS”, “FOR”,”FOT”, & Ex-Works” shall mean the terms as
defined in the international rules for the interpretation of trade terms, 2010 (Incoterms) with the latest modifications incorporated. The terms FOR and FOT are exclusively meant for Indian bidders only.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
1.20 “Terms” and expressions not herein defined shall have the same meaning as are assigned to them in the Indian sale of Goods Act, 1930, failing that in the Indian Contract Act (1872)and failing that in the General Clauses Act (1897) including amendments thereof, if any.
1.21 “Effective Date” means the date of issuance of Letter of Intent. 1.22 “ Completion Period” shall mean the period starting from the date of issuance of LOI till
the completion of guarantee test and handling over of duly commissioned Plant (All VAM units& accessories) and facilities to Owner WITH THE ISSUANCE OF final acceptance CERTIFICATE BY owner.
2.0 SCOPE OF CONTRACT Bidder shall be responsible for the jobs specified under following:
Design & engineering, review & analysis, codes and standards, drawings and documents, Owner’s review , Procurement of equipment and material, govt. clearance, network schedule, spares & special maintenance tools, construction tools, transportation and storing of equipment, construction, safety and plant security, pre-commissioning, mechanical completion, commissioning, performance guarantees, Post commissioning services, if required, practical experience for Owner’s personnel, if required, laws and regulations, progress monitoring and reporting, technical information, work of sub-contractors coordination etc.
Take into possession the custody and care of GOODs handed over to CONTRACTOR by OWNER at the port of entry in India for imported supplies and EXW for indigenous supplies and arrange services of ocean transportation, insurance and carry out the services of port clearance on behalf of OWNER, inland transportation up to SITE, inland transit insurance, unloading, storage at SITE transportation within SITE, complete services of erection, structural and PRE-COMMISSIONING, COMMISSIONING and PERFORMANCE & GUARANTEE TEST RUNS for PLANT.
Take into possession the custody and care of GOODS handed over by OWNER to CONTRACTOR on furnishing an Indemnity Bond as per prescribed Performa and carry out series of inland transportation up to SITE, inland transit insurance, unloading, storage at SITE, in plant transportation , erection, PRE-COMMISSIONING , COMMISSIONING , PERFORMANCE AND GUARANTEE TEST RUN AND FINAL COMPLETION OF PLANT.
OWNER shall furnish to CONTRACTOR on CONTRACTOR’S request for each shipment delivery documents such as negotiable copy of bill of lading, packing
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
list, invoices etc. duly endorsed in CONTRACTOR’S favour after receipt of an indemnity bond from CONTRACTOR in the prescribed proforma for value of GOODS so that CONTRACTOR shall take prompt action to file the papers with customs authorities on behalf of OWNER , for getting the GOODS cleared from customs.
OWNER shall give to CONTRACTOR possession, custody and care of GOODS and CONTRACTOR is obliged and shall remain absolutely responsible for the safe transit/ protection and custody of GOODS at Site against all risks whatsoever till GOODS are duly used / erected and commissioned in accordance with the terms of the CONTRACT and the plant / packed duly erected and commissioned in accordance with the terms of CONTRACT, CONTRACTO undertake to keep OWNER harmless against loss or damage that may be caused to GOODS.
CONTRACTOR shall take possession of said GOODS from port/customs authorities on behalf of OWNER.
CONTRACTOR shall on behalf of OWNER take all necessary steps and comply with all formalities to get this CONTRACT registered with the appropriate Indian Customs Authorities on behalf of OWNER to have the various imported GOODS assessed at concessional rate of customs duty as applicable.
CONTRACTOR shall be responsible, whenever required, to undertake on behalf of ONWER customs reconciliation work with Indian customs authorities and finalize the customs assessment within three MONTHS of arrival of the last consignment by furnishing the necessary technical documents and technical information etc.to the said authorities.
CONTRACTOR shall be responsible for all penalties and demurrages due to delay in clearance from customs port of imported GOODS due to causes not attribute to OWNER nor to Force Majeure events.
CONTRACTOR shall on behalf of OWNER take all necessary action for inspection of imported GOODS at dock / customs /port and lodge necessary claims under relevant insurance policies for all losses and pursue such claims.
CONTRACTOR shall arrange handling and transportation of GOODS to SITE by rail/road and be responsible for its arrival at SITE.
CONTRACTOR shall unload at SITE inspect, lodge claims under relevant insurance policies, if loss and / or damage is found for GOODS wherever necessary, shift and store at SITE and arrange for preservation, covered storage and security during construction.
CONTRACTOR undertakes that GOODS shall be used exclusively for the performance / execution of the CONTRACT strictly in accordance with its terms and conditions and no part of OODS shall be utilized for or hypothecated to any other work or purpose whatsoever. It is clearly understood by CONTRACTOR that non-observance of the obligations under this CONTRACT by CONTRACTOR shall
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
inter alia constitute a breach of trust on the part of CONTRACTOR for all intents and purposes including legal consequences.
OWNER is and shall at all times remain the exclusive owner of GOODS free from all encumbrances, charges or liens of any kind, whatsoever, GOODS shall at time be open to inspection and checking by Engineer-in charge / Engineer or other employees / agent authorized by him inthis regard. Further OWNER shall always be free at all times take possession of GOODS in whatsoever form GOODS may be,if in its opinion, GOODS are likely to be endangered, mis-utilized or converted to uses other than those specified in CONTRACT by any acts or omission or commission on the part of CONTRACTOR or any other persons or on account of any reason whatsoever and CONTRACTOR binds itself and undertakes to comply with the directions of Demand of OWNER to return GOODS without any demur or reservation.
CONTRACTOR shall erect assembly and commission PLANT for achieving guarantee performance as per TECHNICAL SPECIFICATIONS.
CONTRACTOR shall be responsible for obtaining necessary approvals from the various statutory authorities including inspectorate of boilers and chief Electrical inspectorate for electrical installations in India at no extra cost to OWNER if any.
2.1 Scope of the Contract shall be as defined in the Contract Specifications, Drawings and
Annexure and Attachment thereto. 2.2 The bidder shall furnish Six (06) copies in English language of technical documents, final
drawings preservation instructions, operation and maintenance manuals, test certificates, and spare parts catalogues. Before dispatch under confirmation to the Owner , one reproducible for final Drawings & Two CD/PD shall also be furnished along with above six copies.
2.3 The documents once submitted by the Contractor shall firm and final. The Contractor
shall be responsible for any loss to the Owner consequent to furnishing of the incorrect data / drawings.
2.4 All dimensions and weights should be in metric system. 2.5 All Equipment to be supplied and work to be carried out under the Contract shall
conform to and comply with the provisions of relevant regulations/acts (state Government or Central Government) as may be applicable to the type of Equipment / Work carried out and necessary certificates shall be furnished.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
2.6 The Contractor shall provide cross-sectional drawings wherever applicable to identify the spare part number and their location. The sizes of bearings their make & number shall be furnished. Moreover material of construction, sizes of “O” rings, oil seals packing shall also be indicated clearly.
2.7 Specifications, design and drawings issued to the Contractor along with tender
Specifications and contract are not sold or given but loaned. These remain property of
Owner or their assignees and are subject to recall by Owner. The Contractor and his
employees shall not make use of the Drawings, Specifications and technical information
for any purpose at any time except for execution of work against the Contract and shall
not disclose the same to any person, firm or corporate authorities, without written
permission of Owner. All such details shall be kept confidential.
3.0 STANDARDS 3.1 The Goods and service supplied under this Contract shall conform to the standards
mentioned in the technical Specifications, or such other standards, which ensure an equal or higher quality and when no applicable standards is mentioned, the latest standards issued by an authority / recognized institution in the country of origin of the Goods shall be applicable. In case, more than one standard is indicated in the Contract, the more stringent one shall be followed.
4.0 INSTRUCTIONS, DIRECTIONS AND CORRESPONDENCE. 4.1 The materials and services described in Contract are to be supplied according to the
standards, data sheets, tables, Specifications and Drawings attached hereto and / or enclosed with the Contract itself and according to all conditions both general and specific enclosed with the Contract, unless any or all of them shall have been modified or cancelled in writing as a whole or in part.
I) All the work shall be carried out under the direction of and to the satisfaction of
Owner. ii) All communications including technical/commercial clarifications and / or comments
shall bear reference to the Contract. iii) Invoice for payment against Contract shall be addressed to Owner. iv) The Contract number shall be shown on all invoices, communication, packing lists,
containers and bill of landing etc.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
4.2 All correspondence from Contractor/bidder shall be forwarded in duplicate (02 copies) to OWNER at following address.
Dy. General Manager(TS), National Fertilizers Limited , VIJAIPUR Distt. GUNA (MP)-473111 INDIA Phone: 9464169624, 9417560184
4.3 Correspondence on technical and commercial matters shall be dealt with in separate letters for each Contract and each copy of the letter shall be complete with all Annexure.
4.4 Correspondence for expediting and inspection shall be done directly with Inspector with
two copies to Owner at following address: Dy. General Manager(TS), National Fertilizers Limited , VIJAIPUR Distt. GUNA (MP)-473111 INDIA Phone: 9464169624, 9417560184
5.0 CONTRACT CONFIRMATION 5.1 Within ten (10) days from date of receipt of the LOI/WO, Contractor shall sign the
Contract and return it to the Owner. The copy of the Contract shall be signed by an authorized officer of the company with company seal.
5.2 After Contract confirmation / signing, the terms and conditions contained therein take
procedure over Contractor’s bid conditions and all previous correspondence. 5.3 If after award of Contract, the Contractor does not acknowledge receipt of Award of
Order and / or fails to furnish the security deposit cum performance bank guarantee within the time period specified in the Contract, Owner reserves the right to cancel the Contract without prejudice to various rights and remedies, the Owner may be entitled to as per terms and conditions of Contract and without being liable in any manner whatsoever to the Contractor.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
6.0 MODIFICATIONS IN CONTRACT 6.1 All modifications leading to changes in the Contract with respect to technical or
commercial aspects including terms of completion period shall be considered valid only when accepted in writing by Owner by issuing amendment to the Contract. Issuance of acceptance or otherwise in such cases shall not be any ground for extension of agreed Completion date and also shall not affect the performance of Contract in any manner except to the extent mutually agreed to, through a modification to Contract. Owner shall have the right to modify or amend the Contract subject to an adjustment in the Contract price and/or Completion date in accordance with the applicable provision of the Contract, If any, or pursuant to mutual agreement.
6.2 Owner shall not be bound by any printed conditions, provisions in the Contractor’s bid forms or acknowledgement of Contract, packing list and other documents which purport to impose any conditions at variance with or supplemental to Contract.
7.0 USE OF CONTRACT DOCUMENTS AND INFORMATION 7.1 The Contractor shall not, without the Owner’s prior written consent, disclose the
Contract or any provision thereof, or any specification, plan, drawing, pattern, sample or information furnished by or on behalf of the Owner in connection therewith, to any person other than a person employed by the Contractor in the performance of the Contract. Disclosure to any such employed person shall be made in confidence and shall extend only so far as may be necessary for purpose of such performance.
7.2 The Contractor shall not without the Owner’s prior written consent, make use of any document or information enumerated in Article 7.1 except for purpose of performing the Contract.
7.3 Any documents other than Contract, itself, enumerated in Article 7.1 shall remain the
property of the Owner and shall be returned (all copies) to the Owner on completion of the Contractor’s performance under the Contract, if so required by the Owner.
8.0 PATENT RIGHTS 8.1 The Contractor shall indemnify the Owner against all third party claims of infringement of
patent, trademark of industrial design rights arising from use of the Goods or any part thereof in the Owner’s country.
8.2 Patent Indemnity Contractor shall warrant that the use or sale of the materials delivered under will not
infringe claims of any patent covering such material ( to the extent the design for such
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
materials is not furnished by Owner) and Contractor agrees to be responsible for and to defend at its sole expense all suits and proceedings against Owner based on any such alleged patent infringement and to pay all costs, expenses, judgment and damage which owner may have to pay or incur by reason of any such suit or proceedings and damages which Owner may have to pay or incur by reason of any such suit or proceedings. Notwithstanding the foregoing, Owner does not warrant against and shall not be responsible for claim of patent infringement based solely on the use of such materials in combination with other material or Equipments or in the operation of any process other than such process as may be inherent in the use of such materials.
8.3 Mechanics Lien Contractor agrees to indemnify and hold harmless Owner against all labourer’s material
man’s and / or mechanics liens arising from its work, and shall keep the premises of Owner free from all such claims, liens and encumbrances.
8.4 Permits and Certificates Contractor shall procure, at its expense, all necessary permits, certificates and licenses
required by virtue of all applicable laws, regulations, ordinance and other rules in force at the place where any of the work is to be performed, and Contractor further agrees to hold Owner harmless from liability or penalty which might be imposed by reason of any asserted or established violation of such laws, regulations, ordinances or other rules.
9.0 PEERFORMANCE SECURITY 9.1 Within 30 days after receipt of Notification of Award (LOI)/WO by Contractor, the
Contractor shall furnish to the Owner security cum performance guarantee in the form of a bank guarantee for an amount equivalent to 10% of the value of Contract. Contractor shall inform the Owner, name and address of its banker along with Fax Number and E-mail.
9.2 The proceeds of performance security shall be appropriated by the Owner as compensation for any loss resulting from the Contractors failure to complete its obligations under the Contract without prejudice to any of the rights or remedies the Owner may been entitled to as per terms and conditions of Contract.
9.3 The performance security shall be denominated in the currency of the Contract and shall
be furnished in the form of bank guarantee.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
9.4 The security Deposit Cum Performance Bank Guarantee shall be valid for the duration of the completion period plus 18 months from the date successful commissioningplus three months claim period. The Proforma for security Deposit Cum Performance bank guarantee is enclosed at Attachment V.
Note: Any bank guarantee may it be for Advance Payment, EMD or Security cum Performance shall be issued or counter guaranteed by any of the Scheduled Indian Banks ( except Cooperative and Gramin Bank) in the form specified by NFL. In case of Bank Guarantee issued by the foreign Bank outside India, conformation of the same by any scheduled Bank(excluding Gramin/Cooperative Bank) in India is required. The charges for confirmation shall be to Contractors account. The Bank Guarantee should be submitted by Bankers directly
to NFL in a sealed cover (Registered Post AD) and not through supplier. The party shall also arrange confirmation of Bank Guarantee (including all amendments) by their issuing bank through SFMS mode directly to State Bank of India, N-3 Ist&IInd Floor, Commercial Branch , South Extn. Part I, New Delhi -110049 (ISFC Code – SBIN0000730 or SBININBB220).
10.0 INSPECTION, TESTING AND EXPEDITING 10.1 The Owner or its representatives shall have their right to inspect and / or to test the
Goods to confirm to the Specifications laid down in the Contract. The special conditions of Contract and / or the technical specifications shall specify what inspections and Test the Owner require and where they are to be conducted. The Owner shall notify the Contractor in writing of the identity of any other representatives retained for this purposes. Expediting performed by Owner’s representative in no way relieves the Contractor of obligation under the terms and conditions of this Contract.
10.2 The inspections and Tests may be conducted on the premises of the Contractor or his
Sub-contractor at point of Completion and / or at the Good’s final destination. When conducted on the premises of the Contractor or his sub-contractor, all reasonable facilities and assistance including access to drawings and production data shall be furnished to the Inspector at no charge to the Owner.
10.3 Should any inspected or tested Goods fail to conform to the Specifications, the Owner
may reject them and Contractor shall either replace the rejected Goods or make all alterations necessary to meet Specifications’ requirements free of cost to the Owner.
10.4 The Owner’s right to inspection, Test and where necessary rejection of, the Goods after
the Goods arrival in the Owner’s country shall in no way be limited or waived by reason
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
of the Goods having previously been inspected, tested and passed by the Owner or their representative prior to the Goods shipment from the country of origin.
10.5 The Inspector shall follow the progress of the manufacture of the Equipment under the
Contract to ensure that the requirements outlined in the Contact are not being deviated with respect to schedule and quality.
10.6 Contractor shall allow the Inspector to visit, during working hours, the workshops
relevant for execution of the contract during the entire period of Contract execution. 10.7 In order to enable Owner’s representatives to obtain entry visas in time, Contractor shall
notify Owner two months before assembly, testing and packing of main Equipment. If requested, Contractor shall assist Owner’s representatives in getting visas in the shortest possible time (applicable only in case of foreign order).
10.8 Contractor shall place at the disposal of the Inspector; free of charge all tools,
instruments and other apparatus necessary for the inspection and / or testing of the equipment. The Inspector is entitled to prohibit the use and dispatch of Equipment and / or materials, which have failed to comply with the characteristics required for the equipment during Tests and inspections.
10.9 Contractor shall ensure that the same permission is granted by his Sub-Contractor to the
Inspector. 10.10 In respect of this inspection, Contractor shall advise in writing of any delay in the
Programme at the earliest possible date, describing in detail what has caused the delay and the proposed corrective action.
10.11 All Tests and trails in general, including those to be carried out for materials not
manufactured by Contractor shall be witnessed by the Inspector. Therefore, Contractor shall confirm with the Owner by Email/fax about the exact date of inspection, with at least 30 days notice. Contractor shall specify the Contract items and quantities ready for testing and indicate whether a preliminary or final Test is to be carried out.
10.12 If on receipt of this notice, Owner should waive the right to witness the test; timely
information will be given accordingly to the Contractor. 10.13 Any and all expenses incurred in connection with Tests, preparation of reports and
analysis made by qualified Laboratories / Institutions, necessary technical documents, testing documents, and documents, and Drawings shall be to contractor’s cost. The
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
technical documents shall include the reference and number of the standards used in the construction, wherever deemed practical by the Inspector, with copy of such standards. Contractor shall be held responsible for any possible delay in the approval or testing phase as well as for any possible delay in the remittance of necessary certificates. Delay on the part of the above mentioned instructions will not be considered a case of “Force Majeure”.
10.14 Nothing in this Article 10 shall in any wayrelieve or release the Contractor from any
warranty or to his obligation under this Contract. 10.15 Arrangements for all inspection required,if any by Indian Statutory Authorities and as
specified in Technical Specifications shall be made by Contractor. 10.16 Participation or presence of Owner or their representatives at any Tests or their failure to
be present at or to witness any Tests to be undertaken pursuant hereto shall not in any way or manner relieve or release the Contractor from any of its warranties, guarantees or other obligations under the contract.
10.17 Copies of all Test results / report of the Tests shall be furnished promptly by the
Contractor to the Owner. 11.0 TIME SCHEDULE AND PROGRESS REPORTING 11.1 Time Schedule Network/Bar Chart 11.1.1 Together with the Contract confirmation, Contractor shall submit to Owner, his time
schedule regarding the documentation, supply and manufacture of Equipment and materials as well as information of his Sub-contracts to be placed with their parties, including the dates on which Contractor intends to issue such Sub-Contracts.
11.1.2 The time schedule will be in the form of a network or a bar chart clearly indicating all
main or key events regarding documentation, supply of raw materials, manufacturing testing and Delivery, Erection & Commissioning , Guarantee test & handing over of Plant
11.1.3 The original issue and subsequent revisions of Contractor’s time schedule and or Sub-
Contractor’s time schedule shall be sent to Owner in three copies (of which one shall be soft copy).
The time schedule network /bar chart shall be updated at least every month showing
achieved progress against the scheduled target.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
11.2 Progress Trend Chart /Monthly Report 11.2.1 PERT/CPM shall be provided at the start of execution and revised as and when required. 11.2.2 Contractor shall report monthly to Owner the progress of the execution of Contract and
achievement of targets set out in time bar chart. 11.2.3 The progress will be expressed in percentages shown in the progress trend chart. 11.2.4 The first issue of the progress trend chart will be forwarded together with the time bar
chart along with the Contract confirmation. 11.2.5 The monthly reporting will bear the updating of this progress trend chart. 11.3 PROGRESS PERFORMANCE 11.3.1 Owner or his representatives shall have the right to inspect Contractor’s premises to
evaluate the actual progress of work on the basis of Contractor’s time schedule documentation.
11.3.2 Irrespective of such inspection, Contractor shall advise Owner at the earliest possible
date of any anticipated delay in the Programme indicating the reasons thereof and corrective measures proposed thereto.
11.3.3 In the event that the delay is caused by a delay in the Completion of sub-contracted job,
Contractor shall submit details together with copies of the appropriate orders and agreement entered with such Sub-Contractors.
11.4 Notwithstanding the above, in case progress on the execution of Contract at various
stages is not as per phased time schedule and is not satisfactory in the opinion of the Owner which shall be conclusive or if the Contractor shall neglect to execute the Contract with due diligence and expedition or shall contravene the provisions of the Contract, Owner may give notice of the same in writing to the Contractor calling upon him to make good the failure, neglect or contravention complained of. Should the Contractor fail to comply with such notice within the period of 30 days, the Owner shall have the option and at liberty to take the Contractor wholly or in part out of the Contractor’s risk and cost and recover from the Contractor all extra costs incurred by the Owner on this account and agreed penalty. In such an event Owner shall not be responsible for any loss that the Contractor may incur and Contractor shall not be entitled to any gain. Owner shall, in addition have the right to confiscate performance security in full or part.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
12.0 PACKING AND PRESERVATION 12.1 The Contractor shall provide such packing of the Goods as is sea worthy and is such as
shall prevent damage or deterioration to them or any part thereof during transit to their final destination as indicated in the Contract. The packing shall be sufficient to withstand without limitation to rough handling during transit and exposure to extreme temperatures, salt and precipitation during transit and open storage, packing case size and weights shall be taken into consideration, where appropriate, the remoteness of the Goods’ final destination and the absence of heavy handling facilities at all points in transit.
12.2 The packing marking and documentation within and outside the package, shall comply
strictly with such special requirements as shall be expressly provided for in the Contract and subject to any subsequent instructions issued by the Owner.
12.3 Contractor shall be obliged to make compensation for all losses suffered by Owner due
to Contractor’s improper packing of Equipment.
i) Spares shall be packed separately and identification marks tagged to each of the items, containing the following information and as per instructions specified in the Contract.
a) Details of Equipment and Contract b) Nomenclature of part / component c) Part No. and Drawing No. d) S. No. of part Contract. e) S. No. of part in spares catalogue ii) All fragile and all exposed parts shall be packed with due care and packages shall
bear the worlds “Handle with Care” in English iii) All nozzles, pipes, and all sheets shall be marked with straps bearing progress
numbers. iv) All holes and openings as also all the machined surfaces shall be carefully
protected against weather and damages. v) All manufactured surfaces shall be painted with rust proof paint. vi) All threaded fittings shall be greased and provided with plastic caps. vii) All bright and machined parts shall be coated with appropriate anti-rust
protective / preservative material suitable for tropical and coastal climate conditions.
viii) All small pieces shall be wrapped in jute bags lined with polythene and packed in cases. All pipes shall be bundled in small lots with strong wire in at least four (4)
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
places and 4 metallic tags placed giving information on size, specifications, length and weight of bundle. Both the ends of pipes should be plugged with plastic caps.
ix) No Equipment shall be shipped on deck without specific approval of Owner. x) All on the deck shipments, if permitted, shall be given special protective coating
and packing. xi) Nitrogen at Positive pressure may be required to be maintained, in case of rotors
and some pressure vessels in order to prevent corrosion due to presence of moisture in ambient air. In such Contractor shall provide nitrogen regulator, nitrogen gas, hoses and coupling etc.
12.4 Contractor is fully responsible for specification of the storage conditions for his Equipment and materials, and Contractor is also responsible for any damage incurred due to faulty or missing instructions.
12.5 At least 30 (thirty) days prior or final inspection, Contractor shall submit to Owner a
complete description of the packing. 12.6 The Contractor shall be liable for all damages or breakage to the Equipment due to the
defective of insufficient packing as well as for corrosion due to insufficient protection. In such an event Contractor shall arrange for free replacement without any cost to Owner.
12.7 In each package Contractor will ensure that there is a packing list in English language.
The storage classification shall be agreed with Owner and indicated in the conditions of Contract. A separate packing list in polythene / cellophane cover shall be affixed on to outside of each package.
12.8 Contractor / Supplier shall ensure compliance regarding treatment and marking of the
packing material as per ISPN-15 and other related requirements of Government of India. Wherever required supplier / contractor shall ensure necessary phyto-sanitary certificate for this are made available to custom authority at the time of custom clearance.
13.0 COMPLETION AND DOCUMENTS 13.1 Completion time shall include time for submission of Drawings for approval,
incorporation of comments, if any, and final approval of Drawings by Owner. 13.2 In the event of delay in execution, Contractor shall cause Price Reduction as stipulated
in the Article 23.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
13.3 In case of delayed Completion beyond the stipulated Completion by Contractor even though normal extension of completion time is allowed by Owner, all extra costs on account of changes of statutory regulations / acts, or increase in price on any other account including price variation clause, if any, shall not apply to the Contract price and shall be borne by the Contractor.
13.4. Special care shall be taken by the Contractor to furnish manufacturer’s test certificates,
material of constructions , make, type pressure ratings, wherever applicable , include in the scope of supply of Equipment, before its shipment to enable Owner to obtain permission for import from directorate of explosive or any concerned Statutory Authority in India.
13.5 Contractor shall submit a certificate of origin regarding the origin of Goods to the Owner
as per Contract, which shall be a signed statement of the Contractor with endorsement from trade association, Chamber of Commerce or similar recognized body.
14.0 INSURANCE BIDDER shall take in the joint name of BIDDER and OWNER comprehensive transit
insurance for imported and indigenous GOODs Transit-cum Storage – Erection or its equivalents and third party liability insurance policies with reputed underwriters to cover ALL RISK whatsoever during the whole period starting with dispatch of GOODS from BIDDER / CONTRACTOR’s warehouses FOB port of shipment for imported GOODS and EXW at Contractor’s works for indigenous GOODS and shall further cover for marine insurance, performing services in India for transportation, loading unloading , assembly, erection testing COMMISSIONING OF PLANT till FINAL COMPLETION.
BIDDER shall be fully responsible for pursing and setting all claims under the
underwriters. In the event of accident, injury, damage or loss likely to form a claim under the above insurance policies, BIDDER shall as quickly as possibly submit the insurance claims by underwriters under intimation to OWNER. BIDDER shall also keep OWNER fully informed about progress of each such case. BIDDDER shall undertake immediate repair and replacement of the equipment lost in transit, storage, assembly, erection and COMMISSIONING of PLANT pending settlement of claim thereafter by the underwriters.
14.1 The Contractor at his cost shall arrange, secure and maintain all insurance as may be
pertinent to the works and obligatory in terms of law to protect his interest and interest of Owner against all perils detailed herein. The Form and the limit of such insurance as defined herein together with the under-writer in each case shall be acceptable to the Owner. However, irrespective of such acceptance, the responsibility to maintain
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
adequate insurance coverage at all times including third party liability during the period of contract shall be as of Contractor alone. The Contractor’s failure in this regard shall not relieve him of any of his contractual responsibilities and obligations. The insurance covers to be taken by the contractor shall be in the joint names of Owner and the Contractor. The Contractor shall, however, be authorized to deal directly with insurance company or companies and shall be responsible in regard to maintenance of all insurance covers.
14.2 All insurance including marine insurance is to be covered from insurance company
registered in India. There should be a single cover for marine cum inland transit, storage and erection up to ACCEPTANCE OF PLANT. The insurance premium is reimbursable subject to maximum of the quoted amount under this head. All insurance covers shall be taken by Contractor in joint name of CONTRACTOR and OWNER.
14.3 Any loss or damage to the equipment during handling, transportation, storage, erection,
putting the equipment into satisfactory operation and all activities to be performed till the successful completion of trial operation of the plant shall be to the account of the contractor. The contractor shall be responsible for reference of all claims and make good the damages or loss by way of repairs and /or replacement of the equipment, damaged or lost. The transfer of title shall not in any way relieve the contractor of the above responsibility during the period of contract. The contractor shall provide the Owner with copies of all insurance policies and documents taken out by him in pursuance of the contract. Such copies of documents shall be submitted to the Owner immediately after such insurance coverage. The contractor shall also inform the Owner in the writing at least sixty (60) days in advance regarding the expiry / cancellation and / or change in any of such documents and ensure revalidation, renewal etc.as may be necessary well in time.
14.4 License / facilities, to the extent it remains the responsibility for the Owner, in respect of
supplies to be made by the foreign Contractor from outside India required for purposes of replacement of equipment lost in transit and / or during erection and / or during storage shall be made available by the Owner. Contractor shall however, be required to follow the procedure as may be laid down by the Owner to facilitate him arranging such license / facilities. The perils required to be covered under the insurance shall include, but not be limited to fire and allied risks, miscellaneous accidents (erection risks) workman compensation risks, loss or damage in transit, theft, pilferage, riot and strikes and malicious damages, civil commotion, weather conditions, accidents of all kinds, war risks (during ocean transportation only) etc. The scope of such insurance shall be adequate to cover the replacement / reinstatement cost of the equipment for all risk till the equipment is taken over by the Owner. The insurance policies to be taken should be on replacement value basis and / or incorporating escalation clause.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Notwithstandingthe extent of insurance cover and the amount of claim available from the underwriters, the contractor shall be liable to make good the full replacement / rectification of all equipment / materials and to ensure their availability as per project requirement without additional financial liability to the Owners.
14.5 All cost on account of insurance liabilities covered under the contract will be to the
contractors account and will be included in the contract price. The Contractor, while arranging the insurance, shall ensure to obtain all discounts on premia, which may be available for higher volume or for reason of financing arrangement of the project.
15.0 DESPATCH , TRANSPORTATION /SHIPPING INSTRUCTIONS 15.1 Contractor shall arrange for dispatch of GOODS by sea / rail /road / air after proper
packing and protection as per instructions given in this CONTRACT. The consignment shall be dispatched after inspection and issue of acceptance certificate unless otherwise agreed to in writing.
15.2 In case of imported GOODS On-Deck Shipment should not be without prior permission
of OWNER , which shall not be unreasonably withheld. 15.3 a)Clean on Board Bill of Lading for all Offshore Supplies shall be drawn as under: For FOB / FAS Shipment
Shipper – Govt. of India Consignee – Govt. of India A/c National Fertilizers Ltd. Installation of VAM Vijaipur, Guna , Madhya Pradesh.
b) Property in GOODS
i) As to imported GOODS whether supplied on FOB or FAS basis, title to and property in
GOODS shall pass to OWNER ,FOB Port of Export or in the case of shipment by air freight of delivery to the International Airline at the port of export.
ii) As to GOODS purchased in India title to and property in GOODS shall pass to OWNER ,
supplier shops notwithstanding the transfer of the title to and property in GOODS to
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
OWNER. CONTRACTOR shall carry out all obligations in regard thereto as stipulated in Contract.
iii) The care of custody responsibility of Contractor shall terminate upon Final Completion
and handing over of duly commissioned Plant to Owner. Assembly Marks and Name Plates : 15.4.1 All components / part of Goods when dispatched in unassembled status shall be
adequately visible, indelibly hard marked with identification mark comprising equipment / part numbers and Contract under which shall be shown on drawing to facilitate speedy identification , assembling or dismantling.
15.4.2 Name Plates On each equipment, a name plate indicating basic details, pressure rating, wherever
applicable, code number of equipment, electrical characteristics in case of electrical equipment, name of instrument with tag no. manufacturer’s name shall be fixed at proper place.
15.5 All inland transportation shall be governed by applicable Indian Laws. 15.6 Shipping Arrangements and Forwarding of Documents. 15.6.1 In the case of a shipment on the FOB basis, Owner requires Ocean transportation by
conference vessels or by Indian Vessels. In such case Contractor shall be permitted to use alternative carriers, if the specified carrier is not available within the delivery period required by Contractor. All Shipping arrangements shall then be made by Contractor with the help of Secretary, Shipping Coordination Committee, Ministry of Shipping Transport ,New Delhi (Cable : Transport, New Delhi Telex Vahan ND 2312,2448 and 3104) or through their Forwarding Agent as named below
15.6.2 Forwarding & Shipping Agents Government of India through the chartering wing ( TRANSCHART) have appointed
following freight forwarders for coordination of liner shipments:
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Area Forwarding Agent
UK, North Continent Ports of Europe and Adriatic ports
01)Schenker& Co., Hamburg Schenker Deutschland AG Indian Subcontinent Bei den murhen 5 20457 Hamburg Telefax :+ 4940/36135509 E-mail:dbschenker.com/de 02)Panalpina World Transport Hamburg PanalpineWelttransport (Deutschland) GMBH Am GenterUfer 7, 21129 Hamburg Fax:494023771-1406 E-mail:[email protected]
North and South American including Mexico OPT Overseas Project Transport 1275 Valley Brook Avenue Lyndhurst New Jeresy-07071 USA Fax:001-201-7291625 E-mail [email protected]
Other areas Coordination is done by Shipping Corporation of India ,Shipping House ,245 madam Cama Road
,Mumbai-400021
15.6.3 Bill of lading should be drawn to show Government of India as the shipper and Govt. of India A/C NFL , Vijaipur , Installation of VAM in AMMONIA-II at NFL in Madhya Pradesh as the Consignee. In no case Consignee on the bill of lading shall be the negotiating bank of India.
15.6.4 Adequate notice of not less than six (6) weeks about the readiness of Cargo for
shipment should be given to Forwarding Agent from time to time for finalization the shipping arrangements. All materials shall be shipped on freight to pay.
15.6.5 For the purpose of ascertaining the availability of suitable Conference Lines vessels and
Indian Member Lines vessels and granting dispensation in the event of their non-availability, Contractor should give adequate notice about the readiness of each consignment from time to time at least six week in advance of the required position to the forwarding agent and also endorse a copy thereof to the Shipping Coordination Office, Ministry of Shipping and Transport, New Delhi ( cable:Transchart, New Delhi) as also to the owner.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
15.6.6 To avoid delays in shipments, CONTRACTOR may make his own arrangements for shipping arrangement is not advised by Transchart under the Ministry of Shipping and Transport, to CONTRACTOR within the specified time or if the vessel arranged is scheduled to arrive at the specified port of loading later than 15 days of the date of readiness of cargo.
15.6.7 CONTRACTOR shall avoid the use of over aged vessels for the shipment of the imported
GOODS under this CONTRACT and if so used, the cost of additional insurance, if any, shall be borne by CONTRACTOR.
15.6.8 For arranging clearance of shipment at Indian Port of Entry one set of shipping
document as under are to be dispatched by mail to agents / CONTRACTOR i) 1/3 original of non-negotiable (B/L) ii) 2 copies of non- negotiable copies of B/L iii) 2 copies of packing list iv) 2 copies of signed invoice v) 2 copies of certificate of origin vi) 2 copies of telex/cable to insurance company. vii) Freight bill, if freight is paid by the contractor. viii) Test certificates ix) Inspector Release Note 15.6.9 Contractor shall register himself with Tax authorities in Madhya Pradesh if required and
obtain necessary clearances from government required for entry of materials in the states if any.
16.0 INCIDENTAL SERVICES 16.1 As specified in the special conditions contract, the Contractor may be required to
provide any or all of the following services. i) Performance or supervision or maintenance and / or repair of the supplied
Goods, for a period of time agreed by the parties, provided that this service shall not relieve the Contractor of any warranty obligations under this Contract, and
ii) Conduct training of the Owner’s personnel, at the Contractor’s plant and / or on Site, in assembly, start up operation, maintenance and / or repair of the supplied Goods.
16.2 At the request of Owners, Contractor shall at his expense, dismiss from work and
replace any such employee as Owner, may deem incompetent or careless or whose continued employment is deemed inimical to the interest of the Owner or against public interest.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
16.3 Other conditions of work at Site shall be as per site working & safety conditions as per
Document Site working & safety conditions, attachment VII of ITB. 17.0 SPARE PARTS, MAINTENACE TOOLS AND LUBRICANTS. 17.1 As a specified in the Contract, the Contractor may be required to provide any or all of
the following materials and notifications pertaining to spare parts manufactured or distributed by the Contractor.
i) Such spare parts as the Owner may opt to purchase from the Contractor,
provided that this option shall not relieve the Contractor of any warranty obligations under the Contract, and
ii) All the spares for the Equipment under the contract will strictly conform to the specification and other relevant documents and will be identical to the corresponding main equipment / components supplied under the Contract and shall be fully interchangeable.
iii) The Contractor will provide the Owner with all the addresses and particulars of
his Sub-Contractors/Sub Contractor while placing the order on vendors for items/components / Equipment covered under the Contract and will further ensure with his vendors that the Owner, if so desires will have the right to place order for spares directly on them on mutually agreed terms based on offers of such vendors.
iv) The Contractor shall guarantee the long term availability of spares to the Owner
for the 15 years life of the Equipment covered under the Contract. The Contractor shall guarantee that before going out of production of spare parts of the Equipment covered under the Contract, he shall give the Owner at least 2 years advance notice so that the later may order his bulk requirement of spares, if he so desires. The same provision will also be applicable to Sub-Contractor. Further, in case of discontinuance of manufacture of any spares by the Contractor and / or his Sub-Contractors’, Contractor will provide the Owner, two years in advance, with full manufacturing Drawings, material Specifications and technical information including information on alternative equivalent makes required by the Owner for the purpose of manufacture / procurement of such items.
17.2 Contractor shall complete item-wise list with value of each item of spare parts and
maintenance tools requirements for two years’ operation and maintenance period.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
17.3 Spares parts shall be new and of first class quality as per engineering standards / codes,
free of any defects (patent or latent), deficiency in design, materials and workmanship and also shall be completely interchangeable with the corresponding parts.
17.4 Type, No. and sizes of bearings shall be indicated. Size & material of construction of “O”
rings, oil seals packing shall also indicated. 17.5 Spares parts shall be packed for long storage under tropical and coastal climatic
conditions in suitable cases, clearly marked for the intended purpose. 17.6 A list of special tools and gauges required for normal maintenance and special handling
and lifting appliance if any, for the Equipment shall be submitted to Owner. 17.7 Whenever lubricants are required, Contractor shall indicate the quantity of lubricants
required for the first filling, the frequency of changing, the quantity of lubricants required for 1 year’s continuous operation and the types of recommended lubricants indicating the commercial name (trade mark), quality and grade.
17.8 If Contractor is unable to recommend a specific oil, basic recommended characteristics
of the lubricants may be indicated. 17.9 Contractor shall indicate various equivalents of lubricants available in India. 18.0 WARRANTIES AND GUARANTEES (Applicable for actual TR) 18.1 Materials and Workmanship Warranty 18.1.1 The Contractor shall fully warrant that the Goods supplied under the Contract are new,
unused, of the most recent or current models and incorporate all recent improvements in design and materials unless provided otherwise in the Contract. The Contractor shall further warrant that all Goods supplied under this Contract shall be of first class quality according to Specifications, have no defect (patent or latent) arising from design, materials or workmanship or form any act of omission of the Contractor that may develop under normal use of the supplied Goods in the condition prevailing in the country of final destination.
18.1.2 This warranty shall be valid for 24 months from the date of mechanical completion or 18
months from the date of successful commissioning whichever is earlier. Should any defects be noticed in the design, materials and / or workmanship within 24 months from the date of mechanical completion or 18 months from the date of successful
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
commissioning of plant, whichever is earlier. Owner shall inform Contractor and Contractor shall immediately on receipt of such intimation depute their personnel within 7 days to investigate the causes of defect and arrange rectification / replacement / modification of the defective Equipment at Site without any cost to Owner within a reasonable period. Owner shall be free to take such corrective action as may be deemed necessary at Contractor’s risk and cost, after giving notice to the Contractor. The Owner shall promptly notify the Contractor in writing of any claim arising under this warranty.
18.1.3 Damage to the machinery and / or Equipment deriving from incomplete and erroneous
instructions issued by Contractor will be considered Contractor’s fault and will be treated according to the provisions of this warranty clause.
18.1.4 In case defects are of such nature that Equipment shall have to be taken to Contractor’s
works for ratification etc., the Contractor shall take the Equipment at his cost after giving necessary undertaking or security as may be required by the Owner. Owner shall, if so required by the Contractor, dispatch the Equipment by quickest mode on freight to pay basis to the Contractor’s works. After repairs Contractor shall deliver the Equipment at Site on freight paid basis. All risks in transit to and fro shall be borne by the Contractor.
18.1.5 Equipment or part thereof so repaired or replaced shall have further warranty for a
period of 12 months from the date of acceptanceof plant and the bank guarantee for performance shall be suitably extended.
18.1.6 If the repairs, replacement or modifications referred to, are of such nature as may affect
the efficiency of the Equipment, Owner / shall have the right to give to the Contractor within one month of such replacement /renewal, notice in writing to carryout tests as may be required for acceptance of the Equipment.
18.1.7 If the Contractor fails to meet his obligation to repair or replace defective Goods within
a reasonable period of time, if Contractor refuses, to carry out work under the guarantee clause and implied guarantee conditions, if danger is anticipated or in case of severe urgency Owner shall be entitled to carry out at Contractor’s cost and risk, repair work or replacement deliveries or have it done by a third party. In case not all goods have been delivered by Contractor, Owner is entitled to procure the remaining Goods at Contractors cost and risk. This does not relieve Contractor of any of his guarantee, obligations. Taxes and duties of any kind, whatsoever imposed by the authorities of the country of Contractor or his Sub-contractors until Completion shall be borne by Contractor.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
18.1.8 Damages to EQUIPMENT deriving from incomplete, erroneous instructions issued by CONTRACTOR will be considered CONTRACTOR’s fault and will be treated according to the provision of warranty clause.
18.2 Performance Guarantee 18.2.1 Contractor shall guarantee that the performance of the plant under the Contract shall
be strictly in conformity with the Technical Scope as enclosed in the ITB documents and shall perform the duties specified under the Contract.
18.2.2 If the performance of the Plant fails to prove the guarantee set forth in the
Specifications’, Contractor shall investigate the causes and provide free of cost to Owner design, Engineering, materials, and service and Equipment within a reasonable period to prove guarantees. The Contractor’s liability for reviewing the defect as well as making good any shortcoming shall be limited to total contract value.
18.2.3 If the supplier / Contractor fails to prove the guarantee within the period stipulated in
the contract, the owner shall have the option to take over the equipment and rectify the same, if possible to fulfill the guarantees and / or to make necessary additions to make up the deficiency at supplier’s / contractor risk and cost. All expenditure incurred by the Owner in this regard shall be on Supplier’s / Contractors account.
19.0 ASSIGNMENT The Contractor shall not assign in whole or in part, its obligations to perform under this
Contract, except with the Owner’s prior written consent. 20.0 SUB-CONTRACT AND PURCHASE ORDERS. 20.1 General
All vendors, suppliers, Consultants and Sub-Contractors providing equipment, materials construction equipment, or services to Contractor under a Sub-contract, purchase order or similar purchase form or arrangement with Contractor for the performance of the Work under this Contract are herein referred as “Sub-contractor and any such Sub-contracts , purchase orders and similar purchase forms and arrangement entered into by or on behalf of Contractor with Sub-contractors / Vendors are herein referred to as “sub-Contracts “ provided that none of Owner’s Contractors or Sub-contracts shall be deemed to be a Sub-contractors under of the Contractor. The Contractor shall be obligated to select Sub-contractors it retains in connection with the performance by
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Contractor of the Work from a Sub-contractors list which would be finalized and approved by Owner in the Final Proposal Owner and Contractor may be mutual agreement add to or delete from such list from time to time and approve any successor or replacement of any person listed on such list or any other vendor, supplier, material-man, consultants or sub-Contractor.
20.2 Approval of Major Sub-Contractor / Vendor 20.2.1 Party shall provide the vendor list for procurement of Equipment and the list of Sub-
contractor for NFL’s approval. Any changes to such list of Vendor / Sub-contractor shall require the prior approval of Owner. Contractor shall provide name, address fax / telex number and the name of contact person of major Vendor / Sub-contractor for use in future, to Owner.
20.2.2 The review, approval and consent by Owner as to the agreed Sub-Contractor’s / Vendor
List or as to Contractor’s entering into any Sub-Contract / Purchase Order shall not relieve Contractor of any of its duties, liabilities or obligations under this Contract and Contractor shall be liable hereunder to the same extent as if any such Subcontract had not been entered into.
20.2.3
a) Contractor shall provide to Owner such information concerning the Subcontractors as Owner may from time to time reasonably request and shall ensure that each Subcontract contains provisions in all material respect not less stringent than the provisions of the Contract and shall include terms and provisions required to be included pursuant to the contract. In the event of termination of the Contract under Section 25 herein, Contractor shall forthwith deliver to Owner a copy of each Subcontract.
b) Contractor shall supervise and direct the work of al Sub-contractors as Owner
may from time to time reasonably request and shall ensure that each Subcontract contains provisions in al material respects not less stringent than the provisions of the Contract and shall include terms and provisions required to be included pursuant to the Contract. In the event of termination of the Contract under Section 25herein, Contractor shall forthwith deliver of Owner a copy of each Sub-contractor.
c) If Contractor fails to correct, or commence to correct and prosecute the
correction with due diligence of deficient or defective work performed by any Sub-Contractor / Vendor within seven days, after receipt by Contractor of a
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
notice from Owner with respect thereto, Owner may (but shall not be obligated to), after seven days following receipt by Contractor of an additional notice, and without prejudice to any other right or remedy take all reasonable steps to remedy such defective or deficient work at risk and cost of Contractor.
d) Contractor shall require all Sub-contractors / Vendors to perform the Sub-
contracts in accordance with the relevant requirements of the Contract including Final Proposal, all Applicable Laws and Applicable Permits, Prudent Utility, Practice, Good Engineering Practices, the requirements of the ITB, and all Warranties of Sub-contractors / Vendors and Manufacturers and all insurance policies relating to the Plant or the Work.
e) Contractor shall be solely responsible for paying each Sub-contractor / Vendor
and any other agencies working for Contractor.
20.4 Sub-Contract shall incorporate technical conditions and inspection requirements stipulated on Contact and any amendments and changes thereto.
20.5 Copies of Subcontract shall also be forwarded to Owner / Inspector. 20.6 If Sub-Contractor should appear unfit to carry out his part of the Contract work or the
progress of Sub-contractor’s work is such that the planned time of completion within the terms of Contract is jeopardized, Owner has the right to instruct Contractor, in writing, to terminate the Sub-contract at a short notice.
20.7 Sub-contract must comply with the provisions with respect to eligible Goods and
services indicated in the bidding documents. 21.0 JOINT AND SERVERAL RESPONSIBILITIES. When the supply is a part of group including parts supplied by others, Owner shall hold
Contractor and responsible for the perfect operation of the group. 22. DELAYS IN THE CONTRACTOR’S PERFORMANCE 22.1 Completion of the Plant and performance of services shall be made by the Contractor is
accordance with the time schedule specified by the Owner in the Contract.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
22.2 An unexcused delay by the Contractor in the performance of its completion obligations shall render the Contractor liable to any or all of the following sanctions: Forfeiture of its performance security, imposition of price reduction and / or termination of the Contract for default.
23.3 Extension in Completion terms of Contract, if any, shall be at the sole discretion of the
Owner. 23.0 DAMAGES/ PRICE REDUCTION CLAUSE 23.1 If for reasons not attributable to the Owner or due to conditions constituting Force
Majeure as defined in this Contract, the Work is not completed in accordance with the provisions hereof, within and in accordance with the Time Schedule / time for Completion as indicated in the terms and conditions of the contract, it is agreed that the Owner shall be entitled to recover and / or the Contractor shall pay to the Owner, without prejudice to any other right are remedy available to the Owner, the following amount as mutually agreed compensation;
23.1.1 A sum equivalent to 0.5% of the total Contract value for every complete week or part
thereof, for delay in completion time for VAMas defined in technical ITB subject to a maximum 5% of total contract value.
23.1.2 A sum equivalent to 0.1% of the Contract value for every complete week or part thereof,
for day in supply of Technical documents and Drawings, subject to a maximum of 0.5% of total contract price.
23.1.3 The obligation of Contractor under sub-clause 23.1.1and 23.1.2 are independent of each
other and accordingly the maximum limit of price reduction set out under each of sub-clause 23.1.1 and 23.1.2 are separately provided.
23.1.4 GST will be applicable on the liquidity damages/ penalty recovered by M/s. NFL. 23.2 In the event that the consumption figures exceed the figures guaranteed by the
Contractor, it is agreed that the Owner shall be entitled to recover and /or the Contractor shall pay to the Owner, without prejudice to any other right or remedy available to the owner, the following amount as mutually agreed compensation.
23.2.1 COOLED AIR TEMPERATURE For every 2% increase in the cooled air temperature guaranteed by the vendor,
liquidated damages at 1% of the total contract value shall be payable by the vendor
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
subject to the maximum of 5% of total contract value. If the increase in cooled air temperature by more than10% of the guaranteed figure, is not acceptable & the Bidder shall rectify the plant as required at no cost to the NFL.
23.2.2 LP STEAM CONSUMPTION(Applicable to VAM for GTG only). For every 01 Tons/ hr part there of increase in L.P. Steam consumption in the VAM unit
than the guaranteed figure as mentioned in the contract, there will be penalty @ 0.5% of the total contract value subject to maximum 2.5% of total contract value, under this head. If the LP steam consumption is more than 05 Te / hr over the guaranteed figure, the vendor shall rectify the plant as required at no cost to the NFL.
23.2.3 PRESSURE DROP ACROSS EACH FILTER HOUSE & SILENCER IN CLEAN CONDITION For every 2% increase or part thereof in respect of air pressure drop , liquidated
damages 1% of the total contract value shall be payable by the vendor subject to maximum of 3% of total contract value. If the increase in pressure drop is more than 6% of the guaranteed pressure drop the vendor shall rectify the defects at no cost to the NFL.
Above damages will be calculated separately for the following:
a) Pressure drop across the filter house excluding silencer shall not exceed 30mm
WC.
b) Pressure drop across the silencer inlet and outlet shall not exceed 20mm
WC.(Applicable for GTG VAM only).
23.2.4 CONSUMPTION OF COOLING WATER For every 1% increase of cooling water over guaranteed figure, liquidated damages at @
0.1% of the total contract value shall be payable by the vendor subject to maximum of 0.5% of total contract value. If the cooling water consumption is more than 5% of the guaranteed figure, the vendor shall rectify the defects at no cost of NFL.
23.2.5 CONSUMPTION OF POWER For every 1% increase of power consumption over guaranteed figure, damages @ 0.1%
of the total contract value shall be payable by the vendor subject to maximum of 0.5% of total contract value. If the power consumption is more than 5% of the guaranteed figure, the vendor shall rectify the defects at no cost to NFL.
23.3 The amounts, as set in clause 23.1 & 23.2 is agreed upon and fixed by the parties due to
difficulties in ascertaining , on the date hereof, the exact amount will be actually
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
incurred by the Owner in such event, and parties hereby agreed that amount specified herein are a genuine pre-estimate made by the parties of the loss and damage which the Owner would have suffered and as by way of mutually determined reasonable compensation payable to the Owner and without the Owner required to establish and prove the actual loss / damaged suffered by the Owner, not in the nature of penalty and shall be applicable regardless of the amount of such deduction in value actually sustained by the Owner.
23.4 The parties agree and acknowledge that the amount set of in clause 23.1 & 23.2 above
may be recovered by the Owner from the amount to be paid to the Contractor and the Contract Value shall stand reduced by such amount.
23.5 Contractors maximum aggregate liability under the Article 23.2 shall be limited to 10%
of the total contract value as defined in the contract for not meeting the Performance Guarantee. This is over and above the liability under the article 23.1. However, in the following event Contractor is to “Make Good” the system / plant in addition to the above liabilities or the supplies would stand rejected and Owner will be free to obtain replacement at the risk and cost Contractor with maximum liability up to contract value. The decision in this regard shall be at the sole discretion of owner.
i. The cooled air temperature is more than 16.5 Deg. C
ii a) Pressure drop across the filter house excluding silencer is more than 31.8 mm
WC
b) Pressure drop across the silencer inlet and outlet is more than 21.2 mm WC. (Applicable for GTG VAM only).
iii) The LP steam consumption is more than 5 Te/Hr over the guaranteed
figure(Applicable to VAM for GTG only). iv) Cooling water consumption is more than 5% over the guarantee figure. 24.0 REJECTIONS, REMOVAL OF REJECTED EQUIPMENT AND REPLACEMENT 24.1 Preliminary inspection at Contractor’s manufacturer’s works by Inspector shall not
prejudice Owner’s claim for rejection of the item of GOODS on final inspection at SITE or claims under warranty provisions of Article – 16
24.2 If GOODs supplied are not to its specification or fail to perform specified duties or otherwise are not satisfactory ,all as set out in Technical Specifications, Owner shall be entitled to reject Goods or part thereof and ask for free replacement within reasonable
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
time failing which Owner shall obtain his requirement from any other source at Contractor’s cost and risk.
24.3 In the event of such rejection, Owner shall be entitled to use the Goods in a reasonable
and proper manner for the time reasonably sufficient to enable him to obtain replacement
24.4 Nothing in this Article shall be deemed to deprive Owner and / or effect any rights under
Contract of Owner which he may otherwise have in respect of such defects or deficiencies or in any way relieve Contractor from his obligations under this Contract.
24.5 Goods rejected by Owner shall be removed by Contractor at his cost within 15 days of
notice after repaying the amount received against the supply. 24.6 In case of rejected of Goods , Owner shall have the right to recover the amount paid, if
any form any of Contractor’s invoice pending with Owner under this Contract or by alternative method.
25.0 TERMINATION OF CONTRACT. 25.1 Termination for Default. 25.1.1 The Owner may without prejudice to any other remedy for breach of Contract terms &
conditions, by written notice of default send to the Contractor, terminate /cancel the Contract in whole or in part:
a) If the Contractor fails to complete any or all of the jobs within the time period(s)
specified in the contract, or b) If the Contractor fails to perform any other obligation(s) under the Contract.
c) If the Contractor, in either of the above circumstances does not rectify his failure
within a period of 30 days ( or such longer period as the Owner may authorize in writing) after receipt of the default notice from the Owner.
25.1.2 In the event the Owner terminates the Contract in whole or in part, pursuant to clause
25.1,The Owner may procure, upon such terms and in such manner as it deems appropriate Goods similar to those undelivered and the Contractor shall be liable to the Owner for any excess costs for such similar Goods. However, the Contractor shall continue performance of the Contract to the extent not terminated.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
25.1.3 In the event of termination of contract, Security Deposit-cum PBG shall be forfeited. 25.2 Termination for Insolvency The Owner may at any time terminate the Contract by giving written notice to the
Contractor, without compensation to the contractor, if the Contractor becomes bankrupt or otherwise insolvent , provided that such termination will not prejudice or affect any right of action or remedy which has occurred or will occur thereafter to the Owner
25.3 Termination of Convenience 25.3.1 The Owner may, by written notice send to the Contractor, terminate the Contract, in
whole or in part, at any time for his convenience. The notice of termination shall specify that termination is for the Owner’s convenience, the extent to which performance of work under the Contract is terminated and the date upon which such termination becomes effective.
25.3.2 The jobs that are complete and ready for handover within 30 days after the Contractor’s
receipt of notice of termination shall be accepted by Owner at the Contract terms and Prices. For the remaining jobs, the Owner may opt:
- To have any portion completed and delivered at the Contract terms and Prices, and
or
- To cancel the remainder and pay to the Contractor an agreed amount for partially completed Goods, material, services and parts previously procured by the Contractor, in that event such Goods, shall be the property of the Owner.
26.0 FORCE MAJEURE
26.1 The terms and conditions agreed upon under the contract shall be subject to Force
Majeure. Neither the contractor nor NFL shall be considered in default in the
performance of their obligation contained therein, if such performance is prevented or
delayed or restricted or interfered with by reason of War, Hostilities, Revolutions,
Civil Commotion, Strike, Epidemics, Accidents, Fire Flood, Earthquake,
regulation or ordinance or requirement of any Government or any sub-division
thereof, or authority or representative of any such Govt. and / or due to technical
snag/reasons or any other Act Whatsoever, whether similar or dissimilar to those
enumerated beyond the reasonable control of the parties hereto or because of any act
of GOD. The party so affected, upon giving prompt notice to the other party shall be
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
excused from such performance to the extent of such prevention, delay, restriction or
interference for the period it persists provided that the party so affected shall use its
best efforts to avoid or remove such causes of non-performance if possible and shall
continue performance hereunder with the utmost dispatch whenever such causes are
removed. Should one or both parties be prevented from fulfilling their contractual
obligations by a state of Force Majeure lasting continuously for a period of one week,
the two parties to the contract shall meet and decide about the future course of action
for implementation of the contract.
26.2 Should one or both the parties be prevented from fulfilling the CONTRACTUAL
obligations by a state of force majeure lasting continuously for a period of six (6) weeks
the two parties shall consult each other regarding the future execution of the
CONTRACT/PURCHASE ORDER.
The mere shortage of labour, materials or utilities shall not constitute force majeure
unless caused by circumstances which are themselves force majeure, if due to force
majeure delay caused exceeds more than three(3) months, OWNER shall have the right to
cancel the CONTRACT/PURCHASE ORDER at no charge to OWNER in
CONTRACTOR/SUPPLIER’s favour and OWNER shall be entitled to the
reimbursement of any amount already paid to CONTRACTOR/SUPPLIER.
26.3 CONTRACTOR/SUPPLIER shall endeavour to prevent, overcome or remove the cause
of force majeure
26.4 No ground for exemption can be invoked if CONTRACTOR/SUPPLIER has failed to
give timely notice by registered letter and subsequently supported it by documentary
evidence.
27.0 RESOLUTION OF DISPUTES/ARBITRATION
27.1 The OWNER and the CONTRACTOR/SUPPLIER shall make every effort to resolve
amicably by direct informal negotiations any disagreement or dispute arising between
them under or in connection with the CONTRACT/PURCHASE ORDER.
27.2 If after thirty (30) days from the commencement of such informal negotiations, the
OWNER and the CONTRACTOR/SUPPLIER have been unable to resolve amicably a
CONTRACT/PURCHASE ORDER dispute, either party may require that the dispute, be
referred for resolution to the formal mechanisms as specified hereunder.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
27.3 LEGAL CONSTRUCTION AND JURIDICTION OF COURT
Subject to provision of article 27.4, the CONTRACT/PURCHASE ORDER shall be, in
all respects, construed and operated as an Indian CONTRACT/PURCHASE ORDER and
in accordance with Indian laws as in force for the time being and is subject to the
jurisdiction of the Delhi Court only.
27.4 ARBITRATION
“Except where otherwise provide in the contract all matters questions , dispute’s or
differences whatsoever, which shall at any time arise between the parties hereto, touching
the construction, meaning, operation or effect of the contract, or out of the matter relating
to the contract or breach thereof, or the respective rights or liabilities of the parties,
whether during or after completion of works or whether before or after termination shall
after written notice y either party to the contract be referred to Designated Unit Head /ED
/Functional Director / Chairman & Managing Director, National Fertilizer Limited for
appointment of Arbitrator (Appropriate Designated Authority may be inserted as per
contract value)
The Arbitration proceedings shall be governed by the Arbitration & Conciliation Act,
1996, The Arbitration & Conciliation (Amendment Act 2015) or any further statutory
modifications are re-enactment thereof and the rules made thereunder.
If the arbitrator to whom matter is referred, vacates his/her office by any reason
whatsoever then the next arbitrator so appointed by the authority referred above may start
the proceedings from where his predecessor left or at any such stage he may deem fit.”
Arbitration for foreign Vendors / Parties
Arbitration provision in accordance with the rules of International Chamber of
Commerce (ICC) will be applicable, which may be as under :
“ All disputes arising out of or in connection with the present contract shall be finally
settled under the Rules of Arbitration of the International Chamber of Commerce, India
by one or more arbitrators appointed in accordance with the said Rules.”
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
28.0 GOVERNING LANGUAGE. 28.1 The Contract shall be written in English language as specified by the Owner in the
instructions to bidders. All literature, correspondence and other documents pertaining to the Contract, which are exchanged by the parties, shall be written in English language. Printed literature in any other language shall only be considered, if it is accompanied by English translation. For purpose of interpretation, English translation shall govern and biding on all parties.
29.0 NOTICES 29.1 Any notice given by one party to the other, pursuant to this Contract shall be sent in
writing or fax / email and conformed by post copy in writing to the address specified for that purpose in the special conditions of contact.
29.2 A notice shall be effective when delivered or on the Effective Date, notified in such
notice, whichever is later. 30.0 TAXES AND DUTIES. 30.1 The Bidder must ensure that the following taxes, duties, are included in Contract Price
and the rates has been indicated in their offer as per Article No. 34 of Instruction to Bidders:
Sr.No. Taxes/Duties Percentage Considered
1 Custom Duty
2 GST
3 Others taxes and duties, if any
(GST is to be paid by the owner against submission of GST invoices.) 30.2 The Contractor confirms that it has included GST and allother taxes, duties, levies, etc. as
applicable at prevailing rates, in its Contract Price. In case, Contractor has not included any such taxes, duties ,levies, etc., at all and / or at prevailing rates and Contractor has to pay such taxes, duties, levies, etc. Owner shall not be liable for payment of such liabilities and / or Owner shall not reimburse such taxes, duties, levies, etc. to Contractor.
30.3 Any statutory variation in percentage of taxes, duties as shown under Article – 30.1
shallbe reimbursed by Owner to Contractor or vice-versa on submission of documentary
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
evidence. Foreign exchange variation to indigenous vendors shall not be allowed for imported components. No variation in statutory levies shown under article 30.1 including the custom duty shall be allowed on imports for indigenous vendors. However, in case of delay in Acceptances of Plant due to reasons attributable to Contractor , any increase in percentage of taxes / duties over and above those specified under Article – 30.1 during the delayed period shall be to Contractor’s account and shall not be reimbursed by Owner , however, any decrease in taxes and duties during the delayed period shall be passed on to the Owner.
30.4 The Payment of all taxes is the responsibility of Bidder Owner , however, shall provide
all assistance to Bidder in connection with the same. Any amount which Owner may be required by law to deduct at source towards income tax shall be deducted by owner out of the amount payable to Bidder and the balance amount shall be paid by Owner to Bidder. For the purpose, Owner shall obtain the necessary certificate as per prevalent provisions of the Income Tax Act on the basis of such information and documentation as supplied by Bidder. Owner shall, however, provide Bidder the certificate and challans evidencing the payment of such deducted amount. Owner shall assist and cooperate with Bidder for obtaining Indian personal tax exception for the personnel deputed to India for and in connection with this Contract.
Any other taxes / duties in relation to this contract which the Owner is required to deposit as per the applicable law shall be paid by Owner and recover from the Contractor from any subsequent payment due to the Contractor. Bidder is responsible for obtaining Customs clearance permit for temporary importation on re-export basis of Bidder’s erection equipments, tools and tackles etc. if any duties, taxes and expenses payable on this will be to Bidder’s account. As to imported Goods, Contractor shall be responsible for obtaining all clearances etc required for export of equipment from country of origin. As of the date, import license is not required for the project. However, Owner shall obtain an import license, if and whenever applicable to cover the compete scope of work defined earlier including spares etc. Under this Contract. Bidder shall furnish all necessary information, technical data etc. and assist and cooperate with Owner by preparing the application for import license. Bidder shall also, if necessary accompany and take part in discussions necessary with government authorities in this respect at Bidders’ own cost.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
30.5 INCOME TAX
a) Contract Price shall be inclusive of any and all Indian Income Tax payable in India. Owner shall deduct Indian Income Tax as per IT Act 1962, from the payments due to Contractor and issue tax deducted at source certificate to Contractor. It is the responsibility of the Contractor to file proper income tax return and pay taxes thereon if any, or claim refund thereof if any. The contractor shall give Owner all necessary documents relating to its income tax assessments and to keep the Owner informed about their assessments.
b) Personal income tax payable, if any, in respect of salary and perquisite of Contractor’s personnel in India shall be payable by the individual so deputed by Contractor or Contractor. It is the responsibility of the individual or Contractor to file proper income tax return and pay taxes thereon if any, or claim refund thereof if any. The Contractor shall give Owner all necessary documents relating to income tax assessments of its personnel and to keep the Owner informed about their assessments.
c) On the basis of original tax certificates to be furnished to Contractor by Owner as
referred in this Article. Contractor shall seek in its country Income tax rebate if applicable by utilizing the Indian Income Tax paid under this Contract and shall, when such benefit is finally obtained pass such rebate to Owner. Contractor shall use its best efforts short of litigation to obtain any such rates, which may be available under its Country Laws for Income Tax paid in India under this Contract.
d) Contractor shall make available every year for the period ending 31st December to
Owner certified statement from Contractor’s dependent auditors in their country indicating the amount of rebate claimed and / or obtained by Contractor as on 31st December in their country against Income Tax paid in India in connection with this Contract within 60 days.
e) Contractor shall submit to Owner an undertaking to refund any credit towards
Income Tax if it accrues to it at a future date in its country under the provisions of the Double Taxation Treaty, if any between the Govt. of India and the Govt. of Contractor’s country. Owner, on its part will extend all necessary documents to enable Contractor to obtain tax benefits / refunds in its country as well as in India. Contractor shall arrange submission of certified statements of all tax assessments every year until all tax assessments relating to Work under Contract are finalized in Contractor country or the resulting tax credits have been finally determined, whichever is later. Contractor shall also submit to Owner a certificate every year till the final exhaustion of such tax credits about the quantum thereof available to it.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
31.0 INSTRUCTION FOR INVOICING AND PAYMENT DOCUMENTATION 31.1 Invoicing
Invoicing shall be in compliance with the stipulations of the Contract and the following instructions. Contractor is liable as for all costs arising from non-compliance with the instructions. As far as possible, description of Goods/ Jobs done in invoice and dispatch documents shall match the description in Contract. The invoices shall be issued in the name of: NFL, INSTALLATION OF VAM The invoice shall contain the following information:
i) Contract No. ii) Item No. quantity and compete description iii) Item-wise net price (unit and total) of the Equipment /Services when applicable iv) Net amount payable by deducting advance payment already invoiced, if any, and
the guarantee retention amount, if any, from the total value of the Equipment / Services being invoiced.
v) Statement that the Equipment / Services are meant for national Fertilizers Ltd., Vijaipur, Installation of VAM Project.
Vi) Necessary certification by the Owner’s competent representative regarding completion / progress of the activity achieved.
vii) Statement that if there is any exemption applicable against certain specified duties and taxes along with supporting documentary evidence.
viii) Delivery challan No. /B/L/LR NO. The country of origin is stated in the separate certificate of origin wherever applicable. The duly signed invoices, original and copy shall be made on Contractor’s letterhead and shall be submitted along with the relevant documents mentioned above. Any other documents specified in terms of letter of credit or special conditions of letter of credit.
31.2 Payment Documentation The following documents shall be presented by Contractor to Owner’s bankers to draw payment(s) where such payment(s) is (are) stipulated in the Contract.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
31.2.1 Advance Payment (If applicable)
i) Invoice for agreed advance amount in original and two (2) copies ii) Written, unconditional acceptance of the Contract in one (1) original plus two
copies. iii) Bank guarantee in the prescribed proforma of the amount equal to the advance
payment + interest thereon valid upto Completion period + 90 days claim period issued or counterguaranteed / confirmed by any schedule Indian Bank ( except Cooperative and Gramin Bank). Or any branch of foreign bank of India. In case of Bank Guarantee issued by the foreign bank outside India, confirmation of the same by any nationalized bank of India is required.The Bank Guarantee should be submitted by Bankers directly to NFL in a sealed cover (Registered Post AD) and not through supplier.
The party shall also arrange confirmation of Bank Guarantee (including all amendments) by their issuing bank through SFMS mode directly to State Bank of India, N-3 Ist&IInd Floor, Commercial Branch , South Extn. Part I, New Delhi -110049 (ISFC Code – SBIN0000730 or SBININBB220).
iv) The Security Deposit Cum Performance Bank Guarantee shall be valid for the
duration of the completion period plus guarantee / warrantee period plus three months thereafter. The bank guarantee shall be issued by any of the Scheduled Bank (except Cooperative and Gramin Bank ) in India or any branch of Foreign Bank in India in case of Bank Guarantee issued by the Foreign Bank outside India, confirmation of the same by any nationalized Bank of India is required.The Bank Guarantee should be submitted by Bankers directly to NFL in a sealed cover (Registered Post AD) and not through supplier.
The party shall also arrange confirmation of Bank Guarantee (including all amendments) by their issuing bank through SFMS mode directly to State Bank of India, N-3 Ist&IInd Floor, Commercial Branch , South Extn. Part I, New Delhi -110049 (ISFC Code – SBIN0000730 or SBININBB220).
31.2.2 Progressive Payments
Progressive payment is to be released based on the billing schedule approved by the NFL, Contractor shall submit billing schedule within one month from the date of LOI/WO Progressive payment for the various activities mentioned under article No. 23.2 (B) in Instruction to Bidders shall be made on production of the followings documents.
1. Invoice for progress payment in original and two (2) copies duly certified by Owner
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
2. Performance certificate in one (1) original plus two (2) copies from the beneficiary to the effect that progress achieved in equal to progress invoiced duly certified by Owner.
3. The document indicated in the letter of credit or in the special conditions of letter of credit, where payment is stipulated to be paid through letter of credit in the ITB (for foreign bidder).
32.0 SPECFICATIONS
Contractor agrees that all Equipment or materials furnished will be in strict accordance with the Specifications, provided however, that any apparent omission or error in the Specifications will be met by the contractor if such omission is necessary for the functioning of the Equipment or material to be supplied and that the Contractor, prior to proceeding with the work under Contract, will call to the attention of Owner any such omission or error or ambiguity in the Specifications requiring clarification and get written consent of the owner.
33.0 GENERAL 33.1 In the event that terms and conditions stipulated in the general conditions of Contract
should deviate from technical specifications stipulated in the contract, the latter shall prevail.
33.2 Losses due to non-compliance of instructions Losses or damage occurring to the Owner owing to Contractor’s failure to adhere to any
of the instructions oven by the Owner in connection with Contract execution shall be recoverable from the Contractor.
33.3 Recovery of sums due All costs, damages or expenses which the Owner may have paid for which under the
Contract, Contractor is liable, may be recovered by the Owner ( he is hereby irrevocably authorized to do so) from any money due to or becoming due to the Contractor under this Contract or other Contracts and / or may be recovered by action at law or otherwise. If the sums due to the Contractor be not sufficient to recover the recoverable amount, the Contractor shall pay to the Owner, on demand, the balance amount.
33.4 Payment etc. not to affect right of the Owner.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
No sum paid on account by the Owner nor any extension of the date for Completion granted by the Owner shall effect or prejudice the rights of the Owner against the Contractor or relieve the Contractor of his obligation for the due fulfillment of the Contract.
33.5 Cut off dates No claims by Contractor on this Contract shall be entertained by the Owner after three (3) months after expiry of the performance guarantee. For settlement of final payment, contractor shall submit unconditional No-claim certificate to the Owner for release of Final Payment.
33.6 Paragraph Heading The paragraph heading of various articles / clauses shall not affect the construction thereof.
33.7 Entire Agreement
All the terms and conditions of Contract shall supersede any understanding, promise and presentation, warranty or conditions which conflicts with terms of Contract. No waiver, alteration or modification of any provision hereto shall be binding on either party unless approved in writing by the parties to Contract.
33.8 Acceptance With the acceptance of Contract with all its terms and conditions,Contractor waives and
considers as void any and all of Contractor’s general sales conditions. 33.9 INDEMNIFICATION Contractor does hereby agree to indemnify and hold harmless the Owner from all
claims, losses demand clauses of action or suit arising out of the services, labour, equipment and materials furnished by Contractor hereunder.
34.0 GOVERNMENT CLEARANCES Contractor shall procure at its expenses, all necessary Applicable Permits, certificates
and licenses required by virtue of all applicable laws, regulations, ordinances and other rules in effect at the place where any or Work is to be performed, and Contractor shall further hold Owner harmless from liability or penalty which might be imposed by reason of any asserted or established violation of such laws, regulations, ordinances or other rules. Owner will provide the necessary assistance to Contractor for obtaining permits for Contractor’s personnel to undertake Work in India in connection with Contact.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Contractor shall furnish necessary data / specifications / drawings etc. of Equipment
likely to be imported to Owner for obtaining import license /necessary Government Clearances, for the same . Contractor shall also furnish necessary technical information, data, drawing, etc as and when required to Owner for submission to Government Statutory Agencies. IBR Approval, Electrical Inspectorate and all other approvals shall be in Contractor’s scope.
35.0 PREFERENCE TO MAKE IN INDIA CLAUSE 1.0 Provisions of Public Procurement (Preference to make in India) order 2017 notified
vide order no. P-45021/2/2017 BE-II dated 15th June 2017 of Ministry of Commerce and Industry, Department of Industrial Policy and Promotion (PIPP) shall be applicable.
1.1 Bidders seeking benefits under Purchase Preference to Make in India (linked with local
content) shall have to comply with the provisions specified under the Public Procurement (Preference to Make in India) order 2017. The salient features of which are as under:
a) Minimum local content:- The minimum local content shall ordinarily be 50%. b) Margin of Purchase Preference: - The margin of purchase preference shall be
20%. 1.2 In case of procurement for a value up to Rs. 10 crore, the local supplier at the time of
tender, bidding or solicitation shall be required to provide self certification that the
item offered meets the minimum local content of 50% and shall give details of the
location(s) at which the local value addition is made. In case of procurement for a
value in excess of Rs. 10 crore, the local supplier shall be required to provide a
certificate from Statutory Auditor or Cost Auditor of the Company (in the case of
Company) or from practicing Cost Account or practicing Chartered Accountant (in
respect of supplier’s other than Company) giving the percentage of local content.
1.3 A supplier who has been debarred by any procuring entity for violation of this Order
shall not be eligible for Purchase Preference under this Order for procurement by any
other procuring entity for the duration of the debarment.
A self certificate to the effect that the bidder has not been debarred by any procuring
entity from violation of this order should be enclosed along with techno-commercial
bid.
2.0 NFL reserves the right to relax the norms on prior experience & turnover for startups
(recognized by DIPP) in Public Procurement subject to their meeting of quality and
technical specifications.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
To avail such relaxation, party shall have to submit the relevant certificate issued by
concerned authority.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT-III
SPECIAL CONDITIONS OF CONTRACT
FOR
INSTALLATION OF VAM IN CPP & AMMONIA-II
PLANTS OF NATIONAL FERTILIZERS LTD,
VIJAIPUR
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
1.0 DEFINITIONS:
Wherever used in the contract and unless inconsistent with or otherwise indicated by the context, the following terms shall have the meaning as defined hereunder:
1.1 “Commercial Use” shall mean that use of the Plant, which the contract contemplates or
of which it is commercially capable.
1.2 “Commissioning and guarantee runs” shall mean complete erection, commissioning,
testing and providing guarantees as per the contract within stipulated time and
guaranteed production and operating cost.
1.3 Date of completion and final acceptance” shall mean the date on which the plant has
been commissioned and the guarantees as set forth in the contract have been proved
by the contractor and a certificate to that effect is issued by the Owner.
1.4 “Indian Agent” shall mean that the person, firm or company nominated as such by the
contractor to represent the contractor for this contract in India.
1.5 “MECHANICAL COMPLETION’shallmeanwhen all VAM Units, its auxiliaries and new filter
houses for both CPP and Ammonia II plants are complete after mechanical erection and
pre-commissioning and are ready for acceptance of feed to be introduced to and can
continue to receive feed leading to production of cooled air
1.6 “Month” shall mean calendar month.
1.7 “Plant” shall mean the entire assembly of the equipment with specified battery limits
stated in the contract.
1.8 “Pre-commissioning” shall mean preparation of plant so that it is capable of operating
on a continuous basis for carrying out commissioning activities.
1.9 “Performance and Guarantee Test” shall mean all operational checks and tests required
to determined and demonstrate capacity, efficiency, and operating characteristics as
specified in the contract documents.
1.10 The term “Final Acceptance”/ “Taking Over” shall mean the Owner’s written
acceptance of the works performed under the contract, after successful completion of
performance and guarantee tests, as specified in the accompanying technical
specification or otherwise agreed in the contract.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
1.11 “Commercial Operation” shall mean the conditions of operation in which the complete
plant covered under the contract is officially declared by the Owner to be available for
continuous operation at different loads upto and including rated capacity. Such
declaration by the Owner however, shall not relieve or prejudice the contractor any of
his obligations under the contract.
1.12 “Defects Liability Period” shall mean the eighteen months period commencing from the
successful completion of erection and commissioning and during which the contractor
shall remain liable to repair or replacement of any defective part of the works
performed under contract. Words ‘guarantee period’ and ‘maintenance period’
wherever used shall also have the same meaning.
2.0 CONTRACTOR’S GENERAL RESPONSIBILITY
CONTRACTOR shall provide design and supply of all equipment, machineries,
instrumentation, electrical, accessories, auxiliaries, spares and other related items in
respect of the VAM Unit and its hook up with the existing system for smooth safe and
trouble free industrial operation of VAM Unit along with main CPP & Ammonia-II Plants.
2.1 CONTRACTOR shall provide services of sufficient number of engineers, designers,
draftsmen, buyers, inspectors, expediters and other persons required for the
performance of WORK pursuant to the CONTRACT.
2.2 CONTRACTOR shall in particular provide and be responsible for the tasks described
specifically in clause 3.0
2.3 In the event that there is any item of EQUIPMENT or WORK of the type provided for in
CONTRACT, which is not specifically mentioned in the specifications or drawings set out
in TECHNICAL SCOPE but which is necessary (even though not mentioned in CONTRACT)
for normal, safe, and continuous operation of VAM unit and its auxiliaries and filter
house, CONTRACTOR shall include such items of EQUIPMENT in the design and perform
such items of WORK also free of cost to OWNER as if the same had been originally
included in TECHNICAL SCOPE.
2.4 CONTRACTOR may make use of the services of SUB-CONTRACTOR(S) in accordance with
CONTRACT. The scope of work of the proposed SUB-CONTRACTORS shall be approved
by the OWNER. The obligations and responsibilities of the CONTRACTOR listed in or
referred to in this clause 3.0 and indicated in detail in clause 3.0 is without prejudice to
the generality of the foregoing the enumeration in clause 3.0 and CONTRACT shall not in
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
any manner limit the general scope of obligations and responsibilities of designing,
engineering, procurement, construction, commissioning and proving the performance
guarantees of VAM Unit and its auxiliaries and filter house within the scope of
CONTRACT.
2.5 For all mechanical/electrical/instrumentation equipment CONTRACTOR must provide
the list of proposed vendors in the BID for NFL’s approval.
2.6 The third party inspection wherever applicable shall be got done from
M/s Lloyds /M/s B.V. / M/s TUV
3.0 SCOPE OF CONTRACT WORK
CONTRACTOR shall provide and be responsible for the task specified in this clause under the following headlines: 3.1 Design and Engineering
3.2 Review and Analysis
3.3 Codes and Standards
3.4 Drawings and Documents
3.5 Owner’s Review
3.6 Procurement of Equipment & Materials
3.7 Government Clearances
3.8 Network Schedule
3.9 Spares and Special Maintenance Tools
3.10 Construction Tools
3.11 Transportation and Storing of Equipment
3.12 Construction
3.13 Safety and Plant Security
3.14 Pre-Commissioning
3.15 Commissioning services
3.16 Performance Guarantee
3.17 Practical Experience for Owner’s Personnel (Optional)
3.18 Laws and Regulations
3.19 Progress Monitoring and Reporting
3.20 Technical Information
3.21 Work of Sub-Contractors
3.22 Co-ordination
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
3.1 Design and Engineering
The design and engineering shall be so performed that VAM Unit, its auxiliaries & filter
house shall be capable of meeting the guarantees with respect to quality and quantity of
cooled air, consumption of raw materials and utilities, variable cost of Production, etc.
as guaranteed under CONTRACT and shall be reliable and safe and operable in
accordance with sound engineering practice. CONTRATOR shall ensure that the design
shall have designcapacity in all the sections of the PLANT in accordance with
CONTRACTOR’S experience and expertise for obtaining a full through put under varying
conditions within the limits specified in CONTRACT. CONTRACTOR shall review the basic
design conditions, including soil data, and other conditions furnished by OWNER, if
CONTRACTOR observes any inconsistency or insufficiency in these data, CONTRACTOR
shall bring to the notice of OWNER the same.
3.2 Review and Analysis
CONTRACTOR shall review, analyse and optimize the steam system and Power Network
for the VAM Unit and its auxiliaries. CONTRACTOR shall allow OWNER’S representative
to review the design and engineering and CONTRACTOR shall incorporate in its design
and engineering such additions and changes suggested by OWNER’S representative as
long as these do not conflict with the responsibility of CONTRACTOR in fulfilling its
guarantees under CONTRACT, CONTRACTOR shall not use any technical data, drawing or
document given by OWNER except for purpose of CONTRACT.
3.3 Codes and Standards:
The engineering shall be performed according to acceptable international standards, as
specified in the TECHNICAL SPECIFICATION AND TECHNICAL SCOPE, meeting safety and
other requirements of various national /international Codes and Regulations being in
force as on EFFECTIVE DATE. The design of VAM Unit, its auxiliaries and replacement of
filter house shall be based upon the criteria enumerated in CONTRACT.
3.4 Drawing and Documents:
CONTRACTOR shall prepare or secure and furnish to OWNER all data, specifications,
drawings, plans and other documents required for WORK including but not limited to
the following:
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
a) Process and engineering flow diagram, line conditions list, heat and material balance
including steam, power and utilities.
b) Piping and instrumentation diagrams for process facilities and utility systems
c) Drawings of EUIPMENT (inclusive of shop fabrication drawings)
d) Specifications and data-sheets of EQUIPMENT
e) Characteristic curves of fans, blowers, pumps, etc. wherever applicable as normally
made available by VENDOR
f) Instrumentation and electrical drawings including equipment list and civil foundation
drawings.
g) Detailed specifications of Catalyst (if any) chemicals
h) General arrangement drawings (including plans and elevations and isometrics were
required)
i) Piping design along with piping specifications, piping isometrics and pipe support
drawings
j) Drawings, procedures, and special tools and tackles and devices for the erection of
EQUIPMENT
k) PURCHASE ORDER for all EQUIPMENT
l) Bill of material used for award of CONTRACTS for civil and structural works,
mechanical, electrical and instrumentation erection and other works.
m) Copies of certified drawings, including one reproducible for items of EQUIPMENT
purchased as standard items from VENDOR and copies of pertinent bulletins and
instruction manuals/operating manuals as spelt out in co-coordination procedure,
(which would be annexed to the CONTRACT).
n) Network Schedule for all activities of WORK indicating milestones including
VENDOR’S and sub-Contractor’s activities.
o) Six(6) hard copies and two soft copies (DVDs/ PDs); of the operating and
maintenance manuals for each VAM Unit, its auxiliaries and filter house. These
manuals shall be furnished at least two MONTHS prior to pre-commissioning.
p) Six(6) hard copies and two soft copies (DVDs/PDs) of the final specification books at
least one months before pre-commissioning and Six(6) hard copies and two soft
copies (DVDs/PDs) of the mechanical catalogues (along with EUIPMENT) as would be
defined in the Coordination procedure of the CONTRACT.
q) Six(6) hard copies and two soft copies (DVDs/PDs) of the spare parts Handbook with
complete details and diagrams for EQUIPMENT, parts requiring frequent
replacement shall be listed separately from the parts required for ensuring
reliability in unforeseen emergencies.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
r) During the progress of WORK, CONTRACTOR shall furnish to OWNER such copies of
drawings, specifications and manuals and specified in the Contract.
s) Upon completion of WORK, CONTRACTOR shall furnish one complete set of mylar or
linen or any other reproducible sets of CONTRACTOR’S including Sub-Contractor
final revised drawings for each VAM Unit, its auxiliaries and filter house as referred
to above under paragraphs (a), (b), (c ), (d), (e), (f), (g), (h),(i),(j),(k),(l) and (m).
t) All final drawings and documents should be furnished as soft copies (DVDs/ PDs)
also.
3.5 Owner’s Review
CONTRACTOR shall associate OWNER’S representatives with WORK as carried out by
CONTRACTOR’S and Sub-Contractor’s personnel OWNER’S representatives shall review
for acceptance, or sign written approval of all documents specified in the CONTRACT.
Approval or acceptance given by NFL shall not relieve CONTRACTORS of its obligations
under ITB.
3.6 Procurement of EQUIPMENT and Materials
CONTRACTOR shall carry out procurement of EQUIPMENT required for each VAM Unit,
its auxiliaries and filter house replacement. EQUIPMENT procured shall be according to
CONTRACTOR’S specifications, of the best acceptable quality, proven record of
performance and with suitable delivery time to meet MECHANICALCOMPLETION as
guaranteed by the CONTRACTOR.
CONTRACTOR shall furnish a copy of PURCHASE ORDER for all items of selected
EQUIPMENT together with spares and special maintenance tools covering accurately
all terms and conditions such as specifications requirements for quality, inspection, and
test, warranties and guarantees, erection and commissioning assistance by VENDOR,
delivery schedule, packing, transportation and insurance, and documentation.
Selection of vendor shall be the sole responsibility of the Contractor and the vendor
selected shall be from the VENDOR LIST for the VAM Units, its auxiliaries and
replacement of filter house which will be prepared and submitted by the CONTRACTOR
in the bid and approved by OWNER.
CONTRACTOR shall arrange & furnish /provide to OWNER:
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
a) Lubrication schedule from VENDOR
b) Mechanical specifications and equipment data sheets for approval by OWNER before
manufacturing is started.
c) Shop fabrication drawings as made available by VENDOR
d) Characteristic curves for pumps and motors, etc. as made available by VENDOR
e) Certified drawings including civil scope drawing and loading data, pertinent bulletin,
installation, operation and maintenance manuals and test certificates as received from
VENDOR.
f) Supply of final revised CONTRACTOR’S drawings including one reproducible and soft
copies upon completion of WORK.
CONTRACTOR shall arrange, services of VENDOR’S specialist for installation and commissioning of equipment wherever necessary. CONTRACTOR shall be responsible for the accuracy and completeness of PURCHASE ORDERS. Any approval by OWNER’S representative shall not relieve CONTRACTOR of such responsibility. CONTRACTOR shall establish an inspection and expediting system and use its services for obtaining the EQUIPMENT which conforms to the required technical and quality specifications and delivery according to PURCHASE ORDERS. Copies of expediting and inspection reports, of CONTRACTOR regularly shall be sent to OWNER. For critical items, CONTRACTOR shall provide services for arranging third party inspection and quality certification to be carried out at CONTRACTOR’S cost , CONTRACTOR to indicate the list of critical items. The CONTRACTOR shall detail out the actions to be effected to achieve the targeted dates and the same shall be discussed and reviewed with OWNER, periodically using the updated network based on these reviews, project schedule shall be periodically revised and updated to reflect the latest information.
3.7 GOVERNMENT CLEARANCES:
CONTRACTOR shall procure at its expenses, all necessary APPLICABLE PERMITS
certificates and licenses required by virtue of all applicable laws, regulations, ordinances
and other rules in effect at the place where any of WORK is to be performed, and
CONTRACTOR shall further hold OWNER harmless from liability or penalty which might
be imposed by reason of any asserted or established violation of such laws, regulations,
ordinances or other rules. OWNER will provide the necessary assistance to
CONTRACTOR for obtaining permits for contractor’s personnel to under WORK in India
in connection with CONTRACT.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
CONTRACTOR shall also furnish necessary technical information, data, drawing, etc. as
and when required to OWNER for submission to Government Agencies.
IBR Approval, Electrical Inspectorate and all other approvals shall be in CONTRACTOR’S
Scope.
3.8 Network Schedule:
a) OWNER would be using a Computerized Time and Cost Monitoring System and CONTRACTOR shall provide the necessary input data for the same as per system requirement. Project network shall be updated every MONTH to reflect current status.
b) CONTRACTOR shall develop master schedule at least constituting the following: i) The completion of process engineering and basic engineering of the Project from the
EFFECTIVE DATE OF CONTRACT (LOI) ii) The completion of detailed engineering of the project from EFFECTIVE DATE (LOI) iii) Starting and completion of foundation work from EFFECTIVE DATE (LOI). iv) Starting and completion of Civil Construction form EFFECTIVE DATE (LOI). v) Delivery of all equipment and the bulk materials from EFFECTIVE DATE (LOI). vi) Mechanical completion from EFFECTIVE DATE (LOI). vii) Start and completion of Hooking – up from EFFECTIVE DATE (LOI). viii) Start and completion of Pre-Commissioning activities from EFFECTIVE DATE (LOI). ix) Start and completion of Commissioning from EFFECTIVE DATE (LOI). c) It may clearly be noted that a period of only 10 days of normal turn around period shall
be available for hooking up of VAM unit with the existing Ammonia-I plant. However where practical the work may be spread over more than one shut down.
3.9 Spares and Special maintenance Tools. a) CONTRACTOR shall furnish the information in consultation with VENDOR and based on
experience from other plants, a list of spares and special maintenance tools and fixture
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
for EQUIPMENT, sufficient for commissioning and for 2 years of normal operation and maintenance of each VAM unit, it’s auxiliaries & new filter houses. The itemized list of spares with quantity must be attached with the BID. The list is to be submitted separately for Commissioning spares and 2 years normal operation & maintenance of each VAM unit, it’s auxiliaries & new filter houses. The spares recommended shall be optimum, so as not to fall short during commissioning and two years’ operation thereafter, CONTRACTOR shall obtain for these spares the appropriate guarantees and warranties. CONTRACTOR shall also ensure that spares and special maintenance tools and fixtures are procured along with the related items of EQUIPMENT and form part of the PUCHASE ORDERS for the related items of EQUIPMENT.
b) OWNER may consider purchasing only one set of high value spares such as but not
limited to critical machine parts, etc. Owner shall review the list of critical spares.
3.10 Construction Tools :
CONTRACTOR shall procure and provide special construction aids, tools, tackles, and
fixture, required for construction and during normal operation and maintenance of the
plants. However, the moving machineries with NFL like cranes, trailer & tractor -trolley
for loading /unloading/shifting and erection of equipments within NFL premises shall be
provided by NFL free of cost subject to availability of said machineries. In case of some
additional requirement party may arrange said machineryat their own cost. The party
may check the suitability for the same at site before bidding.
3.10.1 TERMS AND CONDITIONS FOR THE USING OF NFL MOBILE CRANES AND HEAVY EARTH
MOVING EQUIPMENTS:
i) On requirement of said machineries as stated above, the requisition shall be
submitted by the contractor in the prescribed format, signed by the authorized
representative of the contractor and countersigned by the concerned officer of NFL,
well in advance.
ii) The security/safety of the NFL machineries will be responsibility of the contractor for
the period in which machine is deployed for contractor’s work.
iii) The logbook shall be signed by the Operator and the authorized representative of
the contractor immediately after the work is over. It shall also be countersigned by
the requisitioning officer of NFL or his representative.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
iv) In case there is a breakdown of the machine while it is with the contractor for their
job, The breakdown will be reported to the NFL Engineer immediately.
v) The machine can be withdrawn by NFL from the contractor for repair maintenance
and for any other reasons at the discretion of NFL.
vi) The contractor will not attempt overloading beyond the capacity of the machine.
vii) The machine will be operated only by the operators, assigned for this purpose by
NFL.
viii) In case of any accident on the machine the same will be reported to the NFL
Engineer immediately.
ix) The equipments are made available to the contractor with the clear understanding
that in case of any loss due to the failure of NFL equipment, while it is working with
the contractor, NFL shall not be responsible for the same and all losses and claims
shall have to be borne by the contractor himself.
x) The equipment shall be made available to the contractor subject to their availability.
xi) Extension /shortening of the crane boom-length, if required by the contractor for
facilitating execution for his job, shall be Contractor’s responsibility. However
assistance will be provided by NFL.
3.11 Transportation and Storing of Equipment
CONTRACTOR shall be responsible for proper packing, transportation from
manufacturer’s workshop to port or railway station (whether by road, rail, ship or
aircraft), handling and clearances at port or railway station including loading and
unloading, customs clearance, carriage to site, unloading at site warehousing, coding
and tagging storage including proper preservation at site of EQUIPMENT. Any special
clearance, lifting , handling, loading/unloading and transport arrangements for over
dimensional consignments shall also be done by CONTRACTOR, CONTRACTOR shall
ensure timely delivery of EQUIPMENT, CONTRACTOR shall endeavor to have the
consignments in the upper part of the hold to enable early discharge at the Port of
dismemberment. The above arrangement shall be in accordance with the guidelines set
forth in the Co-ordination Procedure. CONTRACTOS shall be responsible for inspection
of equipment on receipt at SITE and for maintenance and management of stores and
warehousing of EQUIPMENT at SITE including all activities connected with the issue of
EQUIPMENT, accounting and final reconciliation and handing over of STORES to OWNER.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
3.12 Construction
CONTRACTOR shall be responsible for all insulating and painting works, erection, site
fabrication, piping, civil work, buildings and structural work, instrumentation
installation, electrical installation, and other miscellaneous construction jobs of each
VAM Unit, its auxiliaries and new filter houses leading to Commissioning COMPLETION.
CONTRACTOR shall organize these activities, in appropriate sequence and use proper
methods giving due regard to the requirements of safety, quality, sound engineering
practice, compliance with relevant Codes and Regulations, and for achieving
Commissioning COMPLETION within the period guaranteed.
3.13 Safety and Plant Security
CONTRACTOR shall observe and also use its best efforts to ensure that all parts of WORK
carried out at site is being done in a safe and satisfactory manner conforming to the
applicable safety rules and regulations. Further, CONTRACTOR shall observe and further
make provisions in contracts that employees working in each VAM Unit, its auxiliaries
and new filter houses observe all the safety rules as required under the Factories Act
and Regulations and other Local Laws and CONTRACTORS to provide safety apparel and
equipment to their employees. OWNER shall have the right to object to any unsafe
practice followed by CONTRACTOR’S, Sub-Contractor’s employees or any
CONTRACTOR’S personnel and direct them to carry out the job in a manner considered
safe by OWNER. CONTRACTOR shall further abide by all the Security Regulations
imposed by OWNER.
CONTRACTOR shall observe all safety rules so that no harm is done to OWNER’S
employees or property. If on account of CONTRACTOR, OWNER’S property or personnel
are likely to suffer any damage, in such cases any directions issued by OWNER shall be
carried out by CONTRACTOR.
3.14 Pre-Commissioning Services
CONTRACTOR shall render and be responsible for supervision and direction of pre-
commissioning activities leading to Commissioning COMPLETION. These activities will
include relevant checking, adjustment, testing, calibration, running in and trial runs of
individual in terms of EQUIPMENT, and other similar jobs. OWNER shall provide
experienced/ trained and suitable operating and maintenance personnel who will
perform their tasks under the supervision and direction of CONTRACTOR. CONTRACTOR
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
shall provide experienced personnel as required for carrying out the pre-commissioning
activities along with OWNER’S personnel. CONTRACTOR shall arrange for VENDOR’S
specialists wherever required. Suitable provision for such services shall be made by
CONTRACTOR at the time of placing the PURCHASE ORDER.
3.15 Commissioning Services
CONTRACTOR shall and be responsible for commissioning activities after pre-
commissioning activities after pre-commissioning activities have been completed giving
due regard to safety of EQUIPMENT according to sound international practice. OWNER
shall provide experienced trained operating and maintenance personnel who shall work
under the supervision of CONTRACTOR. The commissioning activities shall include the
following:
a) Lining up of VAM Unit with chilling coil located in the new filter houses for CPP and
Ammonia-II Plants.
b) Stabilizing each VAM Unit and its auxiliaries and gradual reduction of cooled air
temperature less than guaranteed value.
c) Conducting guarantee tests on each VAM unit and its auxiliaries withnew filter houses
for CPP and Ammonia-II Plantsto prove the performance guarantees.
d) CONTRACTOR shall provide supervisory engineers as required to supervise and direct
the commissioning of each VAM Unit, its auxiliaries and new filter houses.
CONTRACTOR shall be responsible for supervision and direction of each VAM unit, its
auxiliaries and new filter houses operation until the performance guarantees have been
fulfilled and or each VAM Unit, its auxiliaries and new filter houses have been finally
accepted and taken over by OWNER. During the guarantee tests, the range of operating
conditions shall be within the limits of the design conditions and shall meet the
requirements of safety and compliance with relevant Codes and Regulations.
3.16 Performance Guarantees
CONTRACTOR shall, when each VAM Unit, its auxiliaries and new filter houses are
stabilized at full rated production, arrange and supervise the tests to prove the
performance guarantees specified in Technical Scope IN PEAK SUMMER.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
3.17 Practical experience for OWNER’S Personnel
CONTRACTOR shall make arrangements, for training of NFL Engineers to be trained on
plant operation at Owners site and operators at site free of cost. Detailed programme
for practical experience shall be mutually agreed between OWNER and CONTRACTOR.
3.18 Laws and Regulations
CONTRACTOR shall abide, while fulfilling its obligations, by all applicable codes, laws,
and regulations from time to time in force in the State of Madhya Pradesh and in India.
Proposal would be based on the codes, laws and regulations applicable on effective
date. In the event of change in any codes, laws or regulation applicable to each VAM
Unit, its auxiliaries and new filter houses after submission of PROPOSAL which alters the
scope of CONTRACTOR’S obligations under CONTRACT, CONTRACTOR shall agree to
make the necessary change in Scope of Workwithout any implication to NFL.
3.19 Progress monitoring and reporting
CONTRACTOR shall develop a suitable system for monitoring and reporting progress on
the various activities upto commissioning and the subsequent activities of
commissioning and conducting the guarantee test. CONTRACTOR will give detailed
network schedule covering the activities and milestones starting from EFFECTIVE DATE
until ACCEPTANCE DATE. These Master Schedules shall include the activities of
CONTRACTOR, Sub-contractor, Suppliers/Manufacturers, and construction contractors.
CONTRACTOR shall monitor progress continuously and submit to OWNER monthly
progress reports giving the status of the activities, indicating those delayed and action
being taken, or required to be taken, to bring back those activities on schedule. These
reports will also include progress at VENDOR’S workshop and will be supplemented with
photographs, wherever necessary. The Network Schedule shall be updated once in a
month. CONTRACTOR shall also furnish information to OWNER as may be required by
any other Governmental Authority or any other agency such as FINANCING
INSTITUTION, etc.
3.20 Technical Information
CONTRACTOR shall furnish to OWNER, CONTRACTOR’S Technical Information and know-
how as may be necessary for the operation of each VAM Unit, its auxiliaries and new
filter houses. CONTRACTOR will grant to OWNER an irrevocable right to use all technical
information of each VAM Unit, its auxiliaries and new filter houses process and know-
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
how and shall further advise OWNER for a period of five (5) years from ACCEPTANCE
DATE of any improvements in process, know-how, engineering, operation methods, and
other conditions which will result in more efficient operation of each VAM unit, its
auxiliaries and new filter houses that are developed by CONTRACTOR or process
licensee or have come to the knowledge of CONTRACTOR.
3.21 Work of Sub-Contractor and Contractor
CONTRACTOR shall remain responsible for proper execution of such part of WORK as
are carried out by SUB-CONTRACTOR(S) and any failure of Sub-Contractor(s) or
CONTRACTOR(S) shall not relieve CONTRACTOR of its obligations under CONTRACT.
Furthermore, in the event of any default by Sub-contractor(s), CONTRACTOR may either
takeover Sub-Contractor’s part of work on mutually agreed terms or take remedial
action as may be necessary in order to achieve completion of each VAM Unit, its
auxiliaries and new filter houses and any other activities leading to acceptance of each
VAM Unit, its auxiliaries and new filter houses by OWNER.
3.22 Co-Ordination
CONTRACTOR shall render all necessary assistance to OWNER required for overall co-
ordination of all activities connected with PROJECT. For this purpose, CONTRACTOR and
OWNER shall agree on a meeting within one week after EFFECTIVE DATE with sub-
contractor(s) and such other parties as are necessary to settle the following:
a) Review the basic design conditions set forth in TECHNICAL SCOPE and, where
appropriate review possibilities of standardization.
b) Assess the priorities and key dates required to be included in CONTRACTOR’S
schedules.
c) Make an assessment of all items requiring coordination.
d) Fix up a date and agenda of any subsequent meeting as may be required in association
with OWNER.
e) In the event OWNER pursuant to its responsibilities of overall coordination requests
CONTRACTOR to make any alteration to the program, scope or responsibility under
CONTRACT, CONTRACTOR shall do the same.
f) Certain category of equipment/piping fall under the jurisdiction of Indian Boiler
Regulations (IBR) and Inspectorate of Electrical (CEI) wherever applicable irrespective of
the fact whether these are proprietary in nature or not, certification from an
internationally recognized agency such as Lloyds is considered necessary to enable local
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
IBR authorities and electrical authorities to allow their installation and operation. In
such cases, inspection and certification from such authorities will also have to be
arranged by CONTRACTOR. CONTRACTOR shall also submit, as may be required by IBR
authorities or electrical authorities, necessary design calculations from respective
fabricators and /or manufacturers of the EQUIPMENT.
4.0 CHANGE IN WORK
4.1 OWNER shall have the right for request in writing changes in WORK within the scope of
CONTRACT. When the request for a change by OWNER has been agreed and complied
with by CONTRACTOR, then CONTRACTOR’S obligations under CONTRACT shall remain
unaffected unless otherwise agreed.
4.2 For each request for a change in WORK, CONTRACTOR shall promptly inform OWNER in
writing whether this request will fall within the provision of the CONTRACT. If this
request does not fall under the provision of the CONTRACT and CONTRACTOR has to
incur additional expenses, then CONTRACTOR shall promptly submit a cost estimates,
and terms of payment for making the requested change together with the details of any
variation required to be made to any of CONTRACTOR’S or OWNER’S obligations and or
guarantees.
4.3 If in CONTRACTOR’S opinion fulfillment of any of its obligations under CONTRACT would
be jeopardized by a change requested by OWNER then CONTRACTOR shall explain in
writing to OWNER the reasons for not accepting these changes within 15 (fifteen)
workingDAYS of receipt of OWNER’S written request.
4.4 OWNER and CONTRACTOR shall agree upon the basis and terms of the change in WORK
in writing.
4.5 It is understood that no change shall become effective and no change will alter the
scope of WORK until all of the matters referred to have been mutually agreed upon in
writing by OWNER and CONTRACTOR.
4.6 It is agreed by both parties that the following changes shall not be considered change:
a) Changes requested by OWNER and accepted by CONTRACTOR which do not involve any
additional cost or man-hour effort.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
b) Changes in CONTRACTOR’S WORK required on account of CONTRACTOR not having
included any item of EQUIPMENT or WORK which in the opinion of
OWNER/CONTRACTOR is necessary for the normal safe and continuous operation of
each VAM Unit, its auxiliaries and new filter houses.
5.0 MECHANICAL COMPLETION
5.1 MECHANICAL COMPLETION shallmeanwhen all VAM Units, its auxiliaries and new filter
houses for both CPP and Ammonia II plants are complete after mechanical erection and
pre-commissioning and are ready for acceptance of feed to be introduced to and can
continue to receive feed leading to production of cooled air
5.2 MECHANICAL COMPLETION shall include completion of all required activities of
mechanical erection and pre-commissioning including but not limited to the following
activities:
5.3 Mechanical Erection
a) VAM Unit, its auxiliaries and new filter houses or the portion there of is installed in
accordance with the drawings, specifications, and contracts, including any approved
changes thereto, and in accordance with all applicable codes and laws.
b) All coded pressure equipment is hydrostatically or pneumatically tested once either in
the supplier’s shop or in the field in accordance with applicable codes or purchase
specifications.
c) Fired heaters/ boilers are hydrostatically or pneumatically tested. All non-operating
pre-firing checks are made in accordance with applicable codes or purchase
specifications.
d) Compressor, pumps, machinery and all drives are cold aligned, couplings are assembled
and guards installed.
e) Instruments are installed, inspected, and such non-operating checks are made as to
assure operability in the manner required for the process application, instrument air
lines are checked for correct hook-up. Air lines are leak-tested. Orifice plates are
checked for correct bore diameter, ready for OWNER’S installation after completion of
flushing operations.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
f) Relief valves are installed. Prior to this, they will have been checked by the Contractor
in the Vendor’s shop and rechecked at Site.
g) Piping is hydrostatically or pneumatically tested in accordance with the specifications.
Special treatment, such as chemical cleaning, is done as required by the drawings or
specifications. Suction screens are installed. Test blinds are removed. Spring supports,
anchors, and guides are checked for removal of all shipping and erection stops and for
correctness of cold settings.
h) The electrical system is installed integrating with the electrical system of PROJECT and
tested in accordance with and to the extent required by the electrical specifications. All
wiring is checked for correct hook-up. Motor rotation is checked. All power system
protective devices are set.
i) Insulation is complete to the extent necessary to permit the start of commissioning and
start-up.
j) Painting is completed to the extent that the incomplete work does not prevent the start
of commissioning and start up.
5.4 Pre-Commissioning
The following is a list of typical work performed including but not limited to, after each
VAM unit, its auxiliaries and new filter houses is/are mechanically complete:
a) Materials and labour are provided to flush, grease, pack and lubricate all pumps,
compressors, other machinery, and their drives.
b) All machinery and drives are run-in, hot-checked for alignment, and doweled.
Necessary adjustments are made as result of running-in, including resetting turbine over
speed trips.
c) Control valves are installed. Instruments, analyzers, controls, interlocks, alarms, and
related items are commissioned, including operating checks, provision and installation
of seal fluids are required, checking and adjusting settings, standardizing, and calibration
and proof tests.
d) Electrical relays and trips are commissioned, tested and simulated.
e) Feedstock, refrigerants, utilities, catalysts, and chemicals are supplied, handled,
installed, and prepared for operation, including any catalyst preparation procedures.
f) Valves are lubricated packed or re-packed , adjusted , or otherwise serviced.
g) Temporary strainers are removed, cleaned, and reinstalled.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
h) Slip blinds required in preliminary circulation and start-up lines are installed and
removed
i) Equipment and lines are flushed, purged, blown, and dried as required for cleanliness ,
safety, and process consideration. All flanges are boxed up with proper gaskets.
j) Final adjustments are made to pipe, supports and hangers
k) All fire protection and safety facilities are commissioned and put into operation and all
safety provisions initiated, including practices, procedures, permits, and other
precautionary measures needed to ensure the safety of personnel and property.
5.5 CONTRACTOR shall present each VAM Unit, its auxiliaries and new filter houses for
inspection and on being satisfied about its completion, provided each VAM Unit, its
auxiliaries and new filter houses can continue to receive feed leading to production of
cooled air.
5.6 CONTRACTOR shall ensure that MECHANICAL COMPLETION as defined in the bar chart
as per the contract.
6.0 INSURANCE
6.1 The contractor shall take in the joint name of Contractor and “Owner” comprehensive
insurance to cover all risk including marine cum erection insurance (MCE), workmen
compensation for Contractor’s personnel,Contractor’s vehicles, fire risk policy, etc. till
handing over of Plant to Owner duly commissioned and tested.
6.2 The Contractor shall be fully responsible for pursuing and settling all claims with the
underwriters. In the event of accident, injury, damage or loss likely to form a claim
under the above insurance policies, the Contractor shall as quickly as possible submit
such details as are necessary for settling such claims by underwriters and shall also
provide information and assistance necessary to settle the claim. The Contractor shall
also keep Owner/Purchaser fully informed about progress of each such case.
6.3 Owner shall be shown as beneficiary in the policy.
7.0 OWNER’S OBLIGATIONS
Owner’s obligations under this contract shall be limited to the following:
7.1 Owner shall make arrangement to provide the following:
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
a) Water required for construction free of charges at one point in CPP and one
point in Ammonia-II Plant.
b) Power required for construction free of charges and any other utility as per
requirement of Project at one point in CPP and one point in Ammonia-II Plant.
c) Contractors will arrange their own covered office and storage at designated by
Owner.
7.2 Make available area for erection of Plant.
7.3 Make available at one point at site benchmark reference coordinates as may be
necessary. It shall be the responsibility of the Contractor to transfer correctly the levels
and coordinates to the Battery Limit for locating equipment within the battery limits.
7.5 Make available to Contractor space (open) for uncovered storage at site. Contractor
shall make own arrangement for constructing covered space for storage of instrument,
etc.
8.0 WORKS CONTRACT TAX
Not applicable after GST.
9.0 PATENT INFRINGEMENT AND INDEMNIFICATION
9.1 CONTRACTOR shall at all times indemnify and keep indemnified OWNER against all
claims or suits and defend, at its, own cost, any suit or action brought against OWNER
and hold OWNER free and harmless against all costs of such claims or suits which may
be made against OWNER in respect of any infringement of any rights protected by
patent, copyright, trademarks, and trade secrets to the extent that such claim, suit, or
action is a result of the use of CONTRACTOR’S Technical Information for the
construction, maintenance, and operation of each VAM Units, its auxiliaries and new
filter houses and the use of CONTRACTOR’S and /or any other process licenser’s
processes used in each VAM Units, its auxiliaries and new filter houses. OWNER shall
pass on all claims made against it to CONTRACTOR for settlement.
9.2 CONTRACTOR declares that to the best of its knowledge and belief the use of
CONTRACTOR’S Technical Information for the construction, maintenance, and operation
of each VAM Units, its auxiliaries and new filter houses and the use of CONTRACTOR and
/or any other process licenser’s processes used in anyVAM Units, its auxiliaries and new
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
filter house will infringement arise, CONTRACTOR agrees to keep OWNER indemnified
and harmless against such claims and costs thereof and make arrangements that will
allow OWNER to continue the operation of allVAM Units, its auxiliaries and new filter
houses.
9.3 OWNER shall promptly advise CONTRACTOR in writing of any claim of infringement or
any action for infringement of patents brought against it by a third party and based
upon the use of CONTRACTOR’s Technical Information if such use is in accordance with
instructions given in writing by CONTRACTOR, CONTRACTOR shall undertake the
defense, or assist OWNER in the defence, of the claim or suit to final judgment or
settlement.
9.4 CONTRQACTOR shall undertaken the defence on behalf of OWNER and shall have sole
charge and direction of the defence, and shall bear all costs related thereto
CONTRACTOR shall further hold OWNER harmless from any damages or other sums that
may become payable by OWNER harmless from any damages or other sums that may
become payable by OWNER under a final judgment or settlement.
However, OWNER shall render to CONTRACTOR all reasonable assistance that may be
required by CONTRACTOR in the defence, and shall have the right to be represented
therein by advisory counsel of its own selection and at its own expense.
9.5 In addition to the measures specified in clause 9.4 CONTRACTOR may further, at its
option, however, in reasonable consultation with OWNER, seek to abate the alleged
infringement by modification of any VAM Unit, its auxiliaries and new filter house or its
operation without adversely affecting the performance and/or secure for OWNER
immunity from suit for infringement. In such case, CONTRACTOR shall reimburse
OWNER for all costs related to said modifications and to said immunity.
9.6 In the event that OWNER is legally restrained from operating any VAM Unit, its
auxiliaries and new filter house on account of any infringement action or suit,
CONTRACTOR shall take all possible actions to allow OWNER to operate and use each
VAM Unit, its auxiliaries and new filter houses.
9.7 Neither CONTRACTOR nor OWNER shall settle or compromise any suit or action without
the written consent of the other if settlement or compromise obliges the other to make
any payment or part with any property or assume any obligations or surrender any
rights or to be subjected to any injunction by reason of such settlement or compromise.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
10.0 INDEMNITIES
10.1 CONTRACTOR Indemnification for Liabilities
To the fullest extent permitted by Law, CONTRACTOR assumes liabilities for and agrees
to indemnify, protect, save and hold harmless the OWNER from and against any and all
liabilities (including any strict liability), of whatsoever kind and nature and whether or
not involving damage to the Project or the Site that may be imposed on, suffered or
incurred by or asserted against OWNER and in any way relating to or arising out of (i)
the Work, any Material or the Project, (ii) the presence, discharge, treatment, storage,
transportation, disposal, escape or release of any Hazardous Substance, or the threat
thereof, at to or from the Site after commencement of work (iii) The performance of the
Work, or as a result of personal injuries (including wrongful death); (iv) the violation by
CONTRACTOR or any SUB-CONTRACTOR of any Government Approval or applicable Law
relating to the Work or the Project or (v) any breach of CONTRACT with any SUB-
CONTRACTOR; provided, however, that CONTRACTOR shall not be required under this
clause 10.1 to indemnify OWNER for any liability arising out of or resulting from events
or circumstances occurring or existing after preliminary acceptance except where the
liability arises from an act or omission of CONTRACTOR or any SUB-CONTRACTOR or any
other Person directly or indirectly employed by either of them or any one for whose
acts either of them may be liable that was a contributory cause of such liability.
10.2 CONTRACTOR indemnification for Taxes
It is specifically understood that CONTRACTOR hereby accepts and assumes exclusive
liability for shall and save and hold the OWNER harmless from and against of all Taxes
arising from the performance of the Work, and all such Taxes shall be deemed to be
included in the CONTRACT price.
10.3 Indemnification by Sub-Contractors.
Contractor shall obtain from each Sub-Contractor which is an affiliate, and shall use all reasonable efforts to obtain from each other Sub-Contractor, an indemnification materially similar in form and substance to clauses 9, 10.1 and 10.2 of which the Owner shall be named as beneficiary.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
10.4 Common Law Remedies.
The above provisions shall not deprive Owner of any indemnity, action, right or remedy otherwise available to Owner at common law or otherwise.
10.5 Payment of Amounts under this clause.
Except to the extent covered by insurance, all amounts payable by Contractor to Owner under this clause shall be deducted from the Contract Price or any other amounts owed by Owner to Contractor here under. If such amounts payable by Owner to Contractor are less than the amounts payable by Contractor under this clause, Contractor shall be liable to Owner for such excess and shall pay such amount to Owner immediately upon demand.
11.0 LIMITATION OF LIABILITY
11.1 Notwithstanding anything contained elsewhere in Contract or implied to the contrary
Contractor’s entire liability under Contract , but excluding liability under the provisions of clauses 11.2 shall be limited to 10 % of the total Contract value.
11.2 Notwithstanding the provisions of sub-clause 11.1 Contractor’s liability shall be limited
to maximum of total contract value in the following cases. i) The cooled air temperature is more than 16.5 Deg. C
ii a) Pressure drop across the filter house excluding silencer is more than 31.8 mm
WC
b) Pressure drop across the silencer inlet and outlet is more than 21.2 mm WC. (Applicable for GTG VAM only)
iii) The LP steam consumption is more than 5 Te/Hr over the guaranteed
figure(Applicable to VAM for GTG only). iv) Cooling water consumption is more than 5% over the guarantee figure. 12.0 TIME SCHEDULE 12.1 Contractors shall give a complete time schedule activity – wise to meet the completion
time quoted in months from the date of letter of intent.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
12.2 The time for completion and phased time schedule shall be subject to and in accordance with the provisions of sub-article below.
12.3 Neither Owner/ Purchaser nor Contractor shall be considered in default in performance
of their obligations if such performance is prevented or delay by Force Majeure conditions as stated in General Conditions of Contract.
12.4 In case the progress of work is unduly and unreasonably delayed by the Contractor
without sufficient cause, the Owner at the Contractors risk and cost and without prejudice to any of the rights under the contract reserve the right to:
a) Terminate the contract wholly or partially and complete it by the Owner or
reassign it to others after giving 30 days notice in writing to the Contractor to remedy the cause complained of.
b) Make any modifications, deletions, additions to the contract as the Owner may consider necessary to ensure its satisfactory execution after giving 7 days notice to Contractor to remedy in cause complained of.
12.5 Should the Contractor’s preparation for the commencement of the work or any portion
of it or its subsequent rate of progress be from any cause whatsoever, so slow what in the opinion of the Owner, the Contractor will not be able to complete the work or any portion thereof within the stipulated time for completion, the provisions of sub-article 12.4 above shall apply.
12.6 In case of delay in completion beyond stipulated time, notwithstanding the grant of
formal extension of time for completion of work by the Owner, all extra costs, on account of changes in statutory regulations/ acts or increase in prices on any other account during the extended time, shall be borne by Contractor unless delay is due to the fault of the Owners. However, decrease in prices or statutory levies shall be passed on to Owner.
13.0 PRICE & TAXES. 13.1 The price quoted shall be firm and fixed without any escalation whatsoever on any
account. 13.2 The Contractor shall ship the material as per shipping instructions in General Condition
of Contact. 13.3 For taxes clause no 30 of Attachment II i.e. General conditions of Contract may be
referred. GST is to be paid by the owner against submission of GST invoices
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
13.4 Any other taxes / duties in relation to this contract which the Owner is required to
deposit as per the applicable law shall be paid by Owner and recover from the Contractor from the subsequent payment due to the Contractor.
13.5 The prices indicated for spare parts in the item wise lists shall be fixed and not subject
to any escalation. 13.6 In case of award of contract to a foreign Contractor the Contractor shall take all
necessary steps and comply with all formalities to get the contract registered with the appropriate Indian custom authorities to have the various imported equipments including spares assessed at custom duty rates as applicable to project imports.
13.7 In case of award of contract to a foreign Contractor, the Contractor shall be responsible
on completion of contract or whenever required to undertake customs reconciliation work with Indian custom authorities and finalise the customs assessment by furnishing the necessary technical documents, technical information etc. to the said authorities.
14.0 BILLING SCHEDULE The Contractor shall provide a billing schedule based on agreed payment terms within
30 days from the effective date of contract for approval by the Owner. 15.0 GUARANTEE FOR TIME OF COMPLETION 15.1 The Contractor shall guarantee the dates of completion calculated from the date of
issuance of Notification of Award (Letter of intent). For the purpose of determining price reduction on account of delay in completion the date shall be the date of handing over of duly commissioned Plant to Owner.
15.2 Levy of pre-determined charges against price reduction clause for delay in supplies or
completion guarantee runs leading to delay in acceptance or delay in handing over all necessary document specified in technical conditions shall be as per the provision in General Terms and Conditions of contract.
15.3 The Contractor shall undertake immediate repair or replacement of the equipment
damaged or lost in transit or during storage assembly, erection and commissioning of plant pending settlement of claim thereafter by the underwriters.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
16.0 LABOUR AND STAFF 16.1 The Contractor shall make his own arrangement for labour, erection and commissioning
engineers and all other staff required for carrying out the contract. 16.2 The Contractor shall make his own arrangements for providing canteen service to his
labour and staff. Open space for this purpose may be provided by Ownersubject to availability.
16.3 The Contractor shall at his own cost provide office and other accommodation for his
staff and workmen. The contractor shall also provide transport and medical facilities to his staff and workmen.
16.4 The Contractor shall be responsible for all liabilities and statutory obligations and any
other laws in this regard in force from time to time regarding the employment or conditions of service of Contractors workmen or employees and indemnify Owner for any claim put forth by authorities.
16.5 The Contractor shall observe all safety rules as required under various statutories in
India and shall also strictly adhere to safety regulations of Owner. 17.0 FINAL ACCEPTANCE 17.1 After the successful commissioning and guarantee runs the final acceptance and taking
over certificate shall be issued by Owner within 30 days. 18.0 WORK SCHEDULE & COOPERATION 18.1 The Contractor shall draw well in advance detailed schedule of work to be carried out at
site and submit the same for approval of the Owner. 18.2 The Contractor shall not object to the execution of the work by other Contractors or
tradesmen and offer them every facility for the execution of their several works simultaneously with Contractors work. Contractor shall at all times provide sufficient fencing, notice boards, lighting and watchmen to protect and warn the public and guard the works and in default thereof. Owner may provide such facilities at Contractor’s cost.
18.3 Owner shall be at liberty to object to employment of any person at work site and the
objection shall be communicated in writing and Contractors shall make immediate arrangements for removal of such person.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
19.0 CONTRACT CONDITONS 19.1 Whenever the terms & conditions in special conditions of contract are at variance with
General Conditions of Contract and any provision of contract elsewhere, special conditions shall prevail.
19.2 Instructions to Bidders (attachment-I), General Conditions of Contract (Attachment-II),
Site working and safety Conditions (Attachment-VII) shall also be applicable and form part of Contract.
20.0 MODE OF CONTRACT 20.1 Notwithstanding anything stated elsewhere in the bid documents, the contract to be
awarded shall be on the basis of single contract on Lump-sum turnkey basis with single point responsibility.
20.2 The Contract shall be in all respects be constructed and governed in accordance with the
Indian Laws.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT IV
INSTALLATION OF VAM CPP &
AMMONIA-II PLANT
NATIONAL FERTILIZERS LIMITED
BID FORM,
PRICE SCHEDULES AND SUMMARY OF TERMS AND CONDITIONS
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Bid Form -A
Offer No.:__________________________ Sub: ITB No. ________________________________for Installation of
_____________________ Due for closing ___________________ at __________________ reference to your subject Invitation to Bid (ITB)we are pleased to submit our Bid for the installation of ___________________________ in double sealed covers as detailed below:
Part-I Bid Security
Part-II Technical and Un-priced Commercial Bid i) ii) iii)
Part –III Price Bid i) ii) iii)
We undertake that in the event of acceptance of our Bid within the validity period of _______________ days , this Bid as modified by our written changes / amendments till date of notification of award, together with your written notification of award shall constitute a binding contract between us until a formal Contract / Purchase Order is prepared and executed.
We understand that you are not bound to accept the lowest or any Bid that may be received. Date this ________________________________ day of ______________ 2018
Authorized Signatories
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
SUMMARY OF TERMS & CONDITIONS QUOTED (BIDDER MUST CONFIRM / COMMENT POINT BY POINT)
ITB NO.NFVP/ESP-II/VAM/2018/002
FOR INSTALLATION OF VAM FOR NFL VIJAIPUR with all its auxiliaries and filter houses.
BIDDER‟S NAME:____________________________________________________________ BID NO.___________________________________________________________________ WE CONFIRM / CLARIFY AS FOLLOWS
S.NO. DESCRIPTION BIDDER‟S CONFORMATION ACCEPTANCE
1.0 PRICE QUOTED AS PER THE PRICE SCHEDULE
CONFIRMED
2.0 QUOTED FIRM PRICES TILL HANDING OVER THE DULY COMMISSIONED PLANT
CONFIRMED
3.0 PRICES HAVE BEEN QUOTED INCLUDING CUSTOM DUTY
CONFIRMED
4.0 TAXES & DUTIES ALL TAXES, DUTIES AND LEVIES, LAWFULLY ASSESSED AGAINST THE OWNER AND THE CONTRACTOR IN PURSUANCE OF THIS CONTRACT, WILL BE TO CONTRACTORS ACCOUNT. IF REQUIRED, THE CONTRACTOR SHALL HAVE HIMSELF TO GET REGISTERED WITH GST AUTHORITIES AS PER STATUTORY REQUIREMENT
CONFIRMED
5.0 COMPREHENSIVE INSURANCE CHARGES FOR COMPREHENSIVE ALL RISK INSURANCE TILL HANDING OVER OF PLANT TO OWNER
QUOTED / NOT QUOTED
5.1 THE INSURANCE COVERS SHALL BE IN THE JOINT NAMES OF THE OWNER AND THE CONTACTOR TO COVER ALL RISKS TILL HANDING OVER OF UNIT (PLANT)
AGREED
6.0 TERMS OF PAYMENT AS PER ITB AGREED
7.0 BID SECURITY (EMD) : AS PER FORMAT IN ITB (IT IS MANDATORY REQUIREMENT. THE OFFER WITHOUT
FURNISHED/ NOT FURNISHED
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
EMD WILL BE REJECTED)
8.0 A) SECURITY DEPOSIT CUM CONTRACT PERFORMANCE BANK GUARANTEE AS PER ITB REQUIREMENT AND AS PER PROFORMA
AGREED
9. GUARANTEE / WARRANTIES AS PER ARTICLE 18 OF ATTACHMENT -II OF ITB
ACCEPTED
11.0 OBTAINING ALL STATUTORY APPROVALS REQUIRED FORM GOVT. / OTHER AGENCIES IN CONTRACTORS SCOPE AS PER ITB
CONFIRMED
11.1 CUSTOM CLEARANCE, CLEARANCE FROM THE PORT IN INDIA AND TRANSPORTATION UPTO SITE (INDIGENOUS AND IMPORT) IN CONTRACTOR‟S SCOPE
CONFIRMED
12.0 SPARES WITH ITEMIZED PRICE LIST FOR 2 YEARS OPERATION
QUOTED / NOT QUOTED
13.0 CHARGES TOWARDS INSPECTION & TESTING INCLUDING IBR AND THIRD PARTY INSPECTION AS PER ITB REQUIREMENT INCLUDED IN THE TOTAL LSTK PRICE
CONFIRMED
14.0 COMPLETION PERIOD A) MECHANICAL COMPLETION B) COMMISSIONING AND HANDING OVER C) EFFECTIVE DATE SHALL BE THE DATE OF ISSUANCE LOI D) BAR-CHART FOR ARRANGEMENT OF LICENSE, BASIC DESIGN , DETAIL ENGG., MANUFACTURE, DELIVERY, ERECTION & COMMISSIONING , COVERING ALL MAJOR ACTIVITIES.
----- MONTHS ----- MONTHS CONFIRMED ENCLOSED
15.0 A) PRICE REDUCTION FOR DELAY IN COMPLETION AS PER ITB B) PRICE REDUCTION FOR DELAY IN SUBMISSION OF FINAL DOCUMENTS AS PER ITB C) PRICE REDUCTION FOR INCREASE IN OVER CONSUMPTION OF ISBL UTILITIES AS PER ITB
CONFIRMED CONFIRMED CONFIRMED
15.1 FORCE MAJEURE CONDITIONS AS PER ITB ACCEPTED
16.0 VALIDITY 120 DAYS FROM PRICE BID OPENING
CONFIRMED
17.0 TECHNICAL CONFORMITY WITH TECHNICAL SPECN. ( STRIKE WHICHEVER IS NOT APPLICABLE )
THE OFFER IS AS PER ITB. NO DEVIATION OR DEVIATIONS AS PER ENCLOSED SHEET
18.0 Average Pressure drop across filtration stage along with cooling coil for 18 months from the date of commissioning
Quoted/NOT QUOTED
19.0 (A) ALL OTHER TERMS & CONDITIONS AS PER ITB
1) ACCEPTED WITHOUT ANY DEVIATION 2) ACCEPTED WITH
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
B) PRINTED CONDITIONS OF SELLER IN THE OFFER OF INCORPORATED ARE HEREBY WITHDRAWN
UNAVOIDABLE DEVIATIONS AS ENCLOSED CONFIRMED
21 REFERENCE LIST OF USERS OF SIMILAR PLANT ENCLOSED
22. NAME ( CONTRACT PERSON OF BIDDER) DESIGNATION: TELEPHONE NO. FAX NO. E-mail (2e-mail IDs to be furnished
IT IS CONFIRMED THAT IN CASE ANY OF THE TERMS AND CONDITIONS MENTIONED IN THIS SUMMARY ARE AT VARIANCE WITH THOSE INDICATED ANYWHERE ELSE IN OUR OFFER, THE CONDITIONS INDICATED IN THIS SUMMARY SHALL PREVAIL. BIDDER‟S SIGNATURE WITH COMPANY‟S SEAL DATE:
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
(TO BE SUBMITTED BIDDER’S LETTER HEAD) F-33 ITB NO: NFVP/ESP-II/VAM/2018/002
FOR INSTALLATION OF VAM FOR NFL VIJAIPUR with all its auxiliaries and filter houses
Price Bid for NFL, Vijaipur
BIDDER‟S NAME
:_________________________________________________________
BID NO.:________________________________________________________________
BREAK UP OF THE CONTRACT PRICE ON LSTK BASIS
Sl. No.
DESCRIPTION PRICE
FC ( ) IC ( Rs. )
A FOR CPP
A.1 Detailed Engineering Package
A.2 Cost of Two no VAM units along with auxiliaries.
A.3 Cost of three no. filter Houses with silencer
A.4 Civil Works
A.5 Erection Charges
A.6 Chemical, including commissioning spares / charges if any.
A.7 Pre-commissioning & commissioning
A.8 Guarantee test and handing over the plants to owner.
Sub Total A
B FOR AMMONIA II
B.1 Detailed Engineering Package
B.2 Cost of Two no VAM units along with auxiliaries.
B.3 Cost of three no. filter Houses with silencer
B.4 Civil Works
B.5 Erection Charges
B.6 Chemical, including commissioning spares /
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
charges if any.
B.7 Pre-commissioning & commissioning
B.8 Guarantee test and handing over the plants to owner.
SUB TOTAL B
C Common for CPP and Ammonia II
C.1 Comprehensive all – risk insurance charges for marine, storage and erection till handing over of the Plant to Owner.
C. 2 Indian Agency Commission if any.
C.3 Annual make up chemical quantity & cost
C.4 Cost of 03 years ARC excluding guarantee period excluding cost of 02 years operation &maint. Spares.
C.5 Spares of for two years operation
SUB TOTAL C
D TOTAL CONTRACT PRICE (SUB-TOTAL A + SUB TOTAL B + SUB TOTAL C)
Note:
1. IC means Indian Currency (Rs.) and FC means Foreign Currency. Number of man months and man month rates for the expatriate personnel deputed for the contract implementation shall be included. Break up of Equipment cost and other costs shall be submitted.
2. The price quoted above shall be inclusive of all applicable taxes and duties. 4. Bidder must submit billing schedule for approval of NFL after placement of order. 5. Bidder must submit monthly progress schedule in a tabular form. 6. Bidder must submit unit price of each spare & chemical. 7. Price for Plant, Equipment, Machinery & Bulk Materials, commissioning, two year
spares including all costs of testing, inspection , Taxes & duties, transportation to site (Ocean / Air Freight & Inland freight), custom duty, port handling & clearance changes , Insurance etc. are included in quoted price.
8. A copy of this letter (F-33) with prices to be enclosed with Priced Commercial Proposal and one signed copy of letter without prices indicating “Quoted/ not Quoted” against each head should be enclosed with Un-priced Commercial Proposal.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
9. Splitting of order shall not be allowed for CPP and Ammonia Plant VAM & its auxiliaries and Filter houses, a single P.O/W.O shall be placed on Overall L-1 basis after loading all differential Costs of utilities etc. on both CPP Plant and Ammonia II plant.
It is the bidder‟s intention, if awarded the CONTRACT, to comply fully and in all respect with CONTRACT documents.
Yours faithfully, For and on behalf of ------------ Signature of Bidder-------------- Title -------------------------------
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Annexure
Price Bid For Mandatory spares list for 2 years operation and maintenance
Mechanical Spares:
Mandatory spares list for 2 years operation and maintenance ( CPP VAM & filter unit)
Sr. No.
Description UOM Quantity Price
A) Spares Filter elements ( for CPP )
1 Pre filters(G4 reverse pocket and M6)
Set 1
2 Mist eliminator filters
Set 1
3 Fine filters
Set 1
B) Spares for Chilled water Pump ( CPP)
1 Spare impeller ( rated dia.)
set 1
2 Impeller lock nut with washer
set 1
3 Wear Rings ( Impeller )& casing)
set 1
4 Wear Rings (casing)
set 1
5 Bearing set
Set 1
6 Coupling complete
set 1
7 Complete mechanical seal
set 2
8 Mechanical seal faces ( both)
set 1
9 Mechanical seal gasket & O-rings
Set 1
10 Shaft with key
set 1
11 Pump Gasket & O-Rings
set 1
12 Shaft sleeve
set 1
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
C) Spares for condensate Pump ( CPP)
1 Spare impeller ( rated dia.)
set 1
2 Impeller lock nut with washer
set 1
3 Wear Rings ( Impeller )& casing)
set 1
4 Wear Rings (casing)
set 1
5 Bearing ( NDE + DE )
set 1
6 Coupling complete
set 1
7 Complete mechanical seal
set 2
8 Mechanical seal faces ( both)
set 1
9 Mechanical seal gasket & O-rings
Set 1
10 Shaft with key
set 1
11 Pump Gasket & O-Rings
set 1
11 Shaft sleeve
set 1
12 Casing wear ring ( if applicable)
set 1
13 Complete mechanical seal
set 2
14 Complete coupling
set 1
15 Complete pump
set 1
D) Spare Absorbent Pump with coupling( CPP)
lot 1
E) Spares Refrigerant Pump with coupling ( CPP)
lot 1
F) Spare vacuum pump with coupling
lot 1
G) Auto Shut Off valve
Lot 1
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Mandatory spares list for 2 years operation and maintenance ( Ammonia II VAM & filter unit)
Sr. No.
Description UOM Quantity Price
A) Spares Filter elements ( for Amm II )
1 Pre filters(G4 reverse pocket and M6) Set 1
2 Mist eliminator filters Set 1
3 Fine filters Set 1
C) Spares for condensate Pump (for Amm II)
1 Spare impeller ( rated dia.) set 1
2 Impeller lock nut with washer set 1
3 Wear Rings ( Impeller )& casing) set 1
4 Wear Rings (casing) set 1
5 Bearing ( NDE + DE ) set 1
6 Coupling complete set 1
7 Complete mechanical seal set 2
8 Mechanical seal faces ( both) set 1
9 Mechanical seal gasket & O-rings Set 1
10 Shaft with key set 1
11 Pump Gasket & O-Rings set 1
11 Shaft sleeve set 1
12 Casing wear ring ( if applicable) set 1
13 Complete mechanical seal set 1
14 Complete coupling set 1
15 Complete pump set 1
D) Spare Absorbent Pump with coupling( Amm II)
lot 1
E) Spares Refrigerent Pump with coupling (Amm II)
lot 1
F) Spare vacuum pump with coupling lot 1
G) Auto Shut Off valve Lot 1
Electrical Spares:
Sr. No.
Description UOM Quantity Price
1 Ammeter: one no. of each type & rating Lot 1
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
2 Ammeter selector Switch
No. 01
3 Voltmeter one no. of each type & rating
Lot 1
4 Energy Meter
No. 01
5 Push button Assembly
No. 01
6 ACB :01 no. each type
Lot 1
7 Power contactor one no. of each type & rating
Lot 1
8 Numeric Motor Protection and feeder Protection Relay : one no. of each type & rating
Lot 1
9 Auxiliary Contactor: 05 nos of each type
Lot 1
10 LVGP Type Indication Lamp : 05 Noof each type
Lot 1
11 Sensitive Earth fault relay (CTUM‐15) No. 01
12 Core Balance CT for Incomer : (if applicable)
No. 01
13 Current Transformer : one no. of each type & rating
Lot 1
14 Potential transformer
No. 01
15 Power Switch : one no. of each type & rating
Lot 1
16 Control Switch : one no. of each type & rating
Lot 1
17 LV Motor : one no. of each type & rating Lot 1
18 LCS : one no. of each type & rating
Lot 1
19 Fuse : 20% or minimum one no. each type & rating
Lot 1
20 Control Fuse fitting [Base & Carrier] : 20% or minimum one no. each type & rating
Lot 1
21 Thermostat :.
No. 01 No
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
22 Bearing ( DE& NDE) : one no. of each type & rating
Lot 1
23 Cooling fan : one no. of each type & rating
Lot 1
24 Terminal block : one no. of each type & rating
Lot 1
25 Grease nipple &plug (if applicable): one no. of each type & rating
Lot 1
26 Fan cover : one no. of each type & rating
Lot 1
27 Terminal stud with bushing & star link: one no. of each type & rating
Lot 1
28 Inner & outer cover for DE & NDE bearing : one no. of each type & rating
Lot 1
29 Junction Box:. one no. of each type & rating
Lot 1
30 Ducter
No. 01
31 Insulation resistance meter
No. 01
32 LED Light
No. 01
33 Astronomical Timer:
No. 01
34 MCB : 20% or minimum one no. each type & rating
Lot 1
Instrument spares list:
SN EQUIPMENT SPARES UOM QTY Price
1 Control valve TRIM (Plug, Seat, Stem, Balance/Seal Ring, Cage/Guide, Bellow Seal): 1 set for each control valve
Lot 1
Gasket Set: 1 No. for each control valve
Lot 1
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Gland Packing: 1 set for each control valve
Lot 1
Actuator Diaphragm / Seal Kit: 1 set for each control valve
Lot 1
Actuator Spring: 1 set for each control valve
Lot 1
Limit switch: 1 No. for each Type Lot 1
Transfer relay/lockup relay/booster relay: 1 No. for each Type
Lot 1
AFR: 1 No. for each Type Lot 1
Positioner: 20% of installed quantity (Min 1 number)
Lot 1
2 Safety Valve
Nozzle: 1 No of each Safety valve Lot 1
Seat/Disc: 1 No of each Safety valve
Lot 1
Spring: 1 No of each Safety valve Lot 1
Spindle: 1 No of each Safety valve
Lot 1
Gasket Set: 1 No of each Safety valve
Lot 1
3 PLC control system
CPU NO. 1
Power supply module NO. 1
Digital I/O: 1 of each type Lot 1
Analogue I/O: 1 of each type Lot 1
Communication Module NO. 1
Ethernet Switch NO. 1
Barrier: 20% of installed Qty. (Min 1 number)
Lot 1
System cables Lot 1
4 Field Indicators
PG/TG/LG: 20% of installed quantity (Min 1 number)
Lot 1
5 Field Transmitters
PT/DPT/TT/LT: 20% of installed quantity (Min 1 number)
Lot 1
Tx manifold: 1 No of each type Lot 1
6 SMPS NO. 1
7 Solenoid Valves
20% of installed quantity (Min 1 number)
Lot 1
8 Temperature TE/RTD: 20% of installed quantity (Min 1 number)
Lot 1
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Chemicals and refrigerants:
Sr. No.
Description UOM Quantity Price
1 Refrigerant(Li-Br) Ltr 1000
2 Inhibitor Ltr 60
3 OctylAlcohal Ltr 30
Notes:
1. Any other spares as per vendor‟s recommendations shall be quoted separately.
The above mentioned spares are minimum and shall be considered in bid
evaluation. Any other recommended spares shall be quoted separately as
optional which shall not be a part of bid evaluation. The same shall be decided
for procurement at the discretion of NFL later on.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT V
INSTALLATION OF VAM CPP & AMMONIA-II PLANT
NATIONAL FERTILIZERS LIMITED
BID SECURITY FORM,
PERFORMANCE BANK GUARANTEE FORM
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
BID SECURITY (EMD) FORM
DRAFT OF BANK GUARANTEE FOR BID SECURITY DEPOSIT/EMD In consideration of National Fertilizers Limited (NFL), having its registered office at Scope Complex, Core-III, 7 Institutional Area, Lodhi Road, New Delhi-110003 (hereinafter called NFL which expression shall unless repugnant to the subject or context includes its successors and assigns) having agreed to exempt ____________(hereinafter called the, the said tenderer(s)' which expression shall unless repugnant to the subject or context includes his successors and assigns) from the demand under the terms and conditions of tender no ________________for___________________ hereinafter called “the said tenderer' of such bid security deposit for the due fulfilment by the said tenderer(s) of the terms and conditions contained in the said tender ____________for ____________on production of bank guarantee for Rs._________________(Rupees ________________________only). 1. We___________________ Bank hereinafter referred to as 'The Bank' do hereby undertake to pay to „NFL‟ an amount not exceeding Rs.________(Rupees__________only) against any loss or damage caused to or suffered by 'NFL' reason of any breach by the said tenderer(s) of any of the terms and conditions contained in the said tender (the decision of the company as to any such breach having been committed and loss suffered shall be binding on us. 2. We _________________Bank do hereby undertake to pay the amounts due and payable under this guarantee without any demur merely or a demand from 'NFL' stating that the amount claimed is due by way of loss or damage caused to or would cause to or suffered by 'NFL' by reason of any breach by the said tenderer(s) of any of the terms or conditions contained in the said tender or by reason of the said tenderer's failure to keep the tender open. Any such demand made on the bank shall be conclusive as regards the amount due and payable by the bank under this guarantee. However, our liability under this guarantee shall be restricted to an amount not exceeding Rs.______________(Rupess_____________________only). 3. We ____________________Bank further agree that the guarantee herein contained shall remain in full force and effect during the period that would be taken for the finalisation of the said tender and that it shall continue to be enforceable till the said tender is finally decided and order placed on the successful tenderer and/ or till all the dues of „NFL‟ under/or by virtue of the said tender have been fully paid and its claims satisfied or discharged or till a duly authorised officer of NFL certified that the terms and conditions of the said tender have been fully and properly carried out by the said tenderer(s) and accordingly discharges the guarantee. Unless a demand or claim under this guarantee is made on us in writing on or before the _____________to include 3 months claim over and above the period mentioned in the paragraph for the validity of the Bank Guarantee in the tender we shall be discharged from all liability under this guarantee thereafter. 4. We __________________________Bank, lastly undertake not to revoke this guarantee during its currency except with the previous consent of 'NFL' in writing. Dated ________________day of ______________________2018 Corporate Seal for Bank
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
SECURITY DEPOSIT-CUM-PERFORMANCE BANK GUARANTEE FORMAT (To be prepared on Stamp paper issued in the name of Bank) This BANK GUARANTEE No. _____________________________ made this day of ____________________________ between______________________ a bank incorporated and having its registered office at ______________________________ (hereinafter called BANK) which expression shall unless repugnant to the context or contrary to the meaning thereof include its successors and assigns on the one part and NATIONAL FERTILIZERS LIMITED, a Company registered in India under Companies Act, 1956 and having its registered office at Core -III, Scope Complex, 7, Institutional Area, Lodhi Road, New Delhi -110 003, India to the context or contrary to the meaning thereof include its successors and assigns on the other part. WHEREAS in pursuance to the agreement dated ____________________(hereinafter called CONTRACT) entered into between National Fertilizers Limited (hereinafter called OWNER and __________________________________________ a Company incorporated in _______________________ (hereinafter called CONTRACTOR) which expression shall unless repugnant to the context or contrary to the meaning thereof include its successors and assigns, for supply of __________________________ as envisaged in the Contract, Contractor has to submit a Security Deposit-cum-Performance Bank Guarantee for Rs._________. CONTRACTOR accordingly agrees to furnish the Security cum performance Bank Guarantee as hereinafter contained towards fulfilment of all of its obligations under the contract. NOW THIS DEED WITNESSES AS FOLLOWS : The decision of the Owner as to whether the terms and conditions of this Security Depositcum- Performance Bank Guarantee have been observed or not shall be final and binding on the BANK. In any case, however the Bank's responsibility under this Security Deposit-cum- Performance Bank Guarantee is limited to Rs. _____________________. 1. In pursuance of the Contract, the Bank hereby guarantees as a direct responsibility to OWNER that the BANK is holding the amount of Rs.______________________________________at Owner's disposal and hereby promises and shall be bound to pay to OWNER, forthwith at Owner's written notice stating that the contractor has failed to fulfil its obligations under the contract for reasons for which contractor is liable and without any protest or demur and without recourse to contractor and without asking for any reasons as to whether the amount if lawfully asked for by Owner or not, the entire amount or the portion thereof as mentioned by Owner in the notice.
2. This Security Deposit-cum-Performance Bank Guarantee shall be valid for an initial
period of _______________________ months from the date of this Bank Guarantee No. ___________________ dated ______________ given by the Bank to Owner become effective. Upon issuance of Commissioning / certificate according to terms of contract on expiry of _________________ months after the issuance of the above mentioned certificate of commissioning / erection / completion certificate, the Security Deposit-cum- Performance Bank Guarantee shall become null and void. 65
3. This Security Deposit-cum-Performance Bank Guarantee shall be in addition to and shall
not affect or be affected by any other security now or hereafter held by Owner on
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
account of money hereby intended to secure and Owner at its discretion and without any further consent from the Bank, and without affecting its rights against the Bank, may compound with, give time or other indulgence to or make any other arrangement with Contractor and nothing done or omitted to be done by Owner in pursuance of any authority or permission contained in this guarantee, shall effect discharge of the liability of the Bank.
4. UNLESS PREVIOUSLY CANCELLED BY THE OWNER, this Security Deposit-cum-
Performance Bank Guarantee will remain in force initially upto __________________ months from the effective date of Bank Guarantee No. __________dated ____________ given by the Bank to the Owner and subject to provisions of paragraph 2 above will stand automatically cancelled on the expiry of the said period. Unless demand or claim under this Bank Guarantee is made on Bank in writing within three months from the date of expiry of this Bank Guarantee, all the rights of Owner against the Bank shall be forfeited and Bank shall be relieved and discharged from all the liabilities hereunder.
5. Any notice by way of request, demand or otherwise hereunder may be sent by post to
the Bank, addressed as aforesaid, and if sent by post, it shall be deemed to have been given at the time when it would be delivered in due course of post, and in proving such notice, when given by post, it shall be sufficient to prove that the envelope containing the notice was posted and a certificate, signed by an officer of the owners, to the effect that the envelope was so posted, shall be conclusive.
6. The Security Deposit-cum-Performance Bank Guarantee is to be returned to the Bank
after its expiry in terms of Paragraph 4 above.
7. The Bank declares that it has the power to issue this guarantee and the undersigned
have full power to do so. Dated ___________ this _____day of ______2018 (Indicate the name of the Bank with stamp)
(Corporate Seal of Bank)
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT VI
INSTALLATION OF VAM CPP & AMMONIA-II PLANT
NATIONAL FERTILIZERS LIMITED
FORMAT FOR EXCEPTIONS AND DEVIATIONS
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ITB NO. ______________________________ ITEM ___________________________________________
BIDDER REF. NO _______________________NAME OF BIDDER__________________________________
SL NO. BIDDING DOCUMENT REFERENCE SUBJECT DEVIATION
DOCUMENT NO. PAGE NO. CLAUSE NO.
NOTE:
1. If unavoidable, Bidder may stipulate deviations to the requirements of the Bidding
Document only in this format.
2. Bidder shall furnish Technical and Commercial deviations, if any, separately.
3. Any deviations stated elsewhere in the bid shall not be taken into account and may render
the bid non- responsive and liable to be rejected.
STAMP & SIGNATURE OF THE BIDDER :________________________________
NAME OF THE BIDDER :________________________________
DATE :________________________________
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT VII
INSTALLATION OF VAM CPP & AMMONIA-II PLANT
NATIONAL FERTILIZERS LIMITED
SITE WORKING AND SAFETY CONDITIONS
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
TABLE OF CONTENTS
SL. NO. DESCRIPTION
1.0 PROJECT SYNOPSIS
2.0 SITE ESTABLISHMENT
3.0 SUPERVISION OF WORK
4.0 INSPECTION
5.0 EMPLOYMENT OF LABOUR
6.0 REPORTING
7.0 COMPLETION OF WORK
8.0 INSURANCE CLAIM FOR DAMAGES
9.0 WORKING AND SAFETY REGULATIONS
10.0 ELECTRICAL SAFETY REGULATIONS
11.0 STATUTORY REQUIREMENTS
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
1.0 PROJECT SYNOPSIS National Fertilizers Limited is a Government of India Undertaking engaged in the
manufacturer of Industrial Chemicals and Fertilizers at its Plants at Bathinda (Punjab), Nangal (Punjab) , Panipat (Haryana) and at Vijaipur (M.P.). The present project of installation of VAM units in CPP and Ammonia-II plant is proposed at its Plant site at Vijaipur District, Guna, Madhya Pradesh -473111. INDIA. See further information at the web address: nationalfertilizers.com.
2.0 SITE ESTABLISHMENT 2.1 The Contractor shall provide all huts, stores, tarpaulins and other covers for the
accommodation of his staff, workmen and materials. All materials likely to deteriorate in the open shall be stored under suitable cover.
2.2 The Contractor shall advise the Owner within 15 days of the placement of LOI his space
requirement which shall include for office, mess rooms, covered storage, open storage, fabrication space, lavatories etc. depending on availability and requirement , space shall, for the duration of this contract, be allotted to the contractor but he will not be permitted to make use of any other space without the sanction of the Owner. The use of this space shall strictly be made for the execution of this Contractor only. The sanitary conditions of the ground in or around such structures shall at all times be maintained by the Contractor in a manner satisfactory to the Owner.
2.3 the security of the Contractor’s equipment and materials is his own responsibility. He
will ascertain what security arrangements are made on site by the Owner and take further steps/precautions he may think necessary. The Owner accepts no liability for or damage to the Contractor’s plant, tools or materials.
2.4 The material issued to the Contractor, by the Owner will remain under the custody of
the Contractor as a trustee. However, title on the same will remain with the Owner. the Contractor will be responsible for loss or damage to such materials and shall preserve them in good working condition as required for the contract and good construction practices till such time that they are erected, aligned and fully installed in position and handed over to the Owner. In case the Owner feels that arrangements made by the Contractor are not adequate he shall so advise the contractor and the Contractor shall promptly take corrective action . in case the Contractor fails to take corrective action within a reasonable time the shall take such corrective action and recover the cost
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
thereof from the Contractor’s bills Account of such material on completion of work shall be rendered and surplus materials returned to the Owner as per instructions of Owner.
2.5 The Contractor shall clear away immediately any rubbish, scrap materials, etc. and
dump the same in the area indicated by the Owner. All construction material shall be neatly stacked in an orderly manner as directed by the Owner and care shall be taken to allow proper access to workmen and easy movement of men, vehicles, cranes and materials.
2.6 The Contractor shall maintain all the drawings carefully mounted on the board of
appropriate size and well protected from the ravages of termites and other insects. 2.7 The Contractor shall not permit the entry to the site of any person not directly
connected / concerned with work without first having obtained the written permission of Owner.
2.8 The Contractor shall submit a list of tools, tackles, etc. which he will use, to perform the
work. The Contractor shall submit a list in duplicate of al materials, tools and tackles etc. brought inside the plant site duly signed by Owner’s security staff as per rules laid by Owners at site Project. These tools, etc. shall not be removed from the Site till the completion of the job. A gate pass must be obtained from the Owner in order to remove from Site any tools, materials and equipment.
2.9 All items such as keys, instructions and other pertinent data regarding erection/
commissioning and maintenance should be tagged and classified for transmittal in a manner approved by the Owner.
2.10 All employees of the Contractor shall conform to the rules of conduct, etc. established
by Owners. Failure to do so will be sufficient cause for removal of such person from the Site.
2.11 The Contractor will be responsible for providing all plant, tools and tackles, consumable
and scaffolding required for the execution of his work as per the best engineering practices.
2.12 The receipt, off-loading , movement and storage at Site of the entire Contractor’s plant,
tools and materials are his responsibility. The receipt, movement and storage , if required , of material issued by Owners shall be responsibility of the Contractor.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
2.13 Electricity: The Contractor shall advise the Owners within 7 days of the placement of LOI his
electrical power requirements to allow the planning of the temporary electrical distribution. Power, subject to availability, will be made available at one point in CPP and one point in Ammonia II Plant. Contractor shall make his own arrangement at his cost for drawing power from the Owner’s distribution board to his own distribution board. The power supply shall be made available at 415 V 3 phase 50 Hz, four wire system . Electricity will be made available to the Contractor free of charge.
Contractor may be required to use his diesel driven Generator sets at site. In his tender
, contractor should indicate the no. of diesel Gen. sets that can be deployed by him. All temporary wiring from the supply point for either Power or lighting will be the responsibility of the Contractor.
Contractor’s Distribution Board temporary wiring shall be GOI approved / done by
certified electrician and must comply with local regulation and is su8bject the Owner inspection and approval before connection to supply. Owner shall provide some flood lights at site. Additional lights if required by Contractor shall be arranged by Contractor.
2.14(a) Water The Contractor shall advise the Owner within 7 days of the placement of LOI , his water
requirement for hydraulic testing and other requirements. A free supply of water will be made available to one point on the site in CPP Plant and one Point in Ammonia Plant. Any further distribution will be the responsibility of the Contractor.
(b) Plant Air The Contractor shall advise the Owner within 7 days of the placement of LOI, his plant
air requirement for pneumatic chipping devices and other requirements. A free supply of plant air will be made available from the existing plant air header at utility points available in plant. Any further requirement will be responsibility of the Contractor.
2.15 Messing & Accommodation: The Contractor will make his own arrangements. No.
accommodation shall be provided by Owner. 2.16 First Aid:
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
The Contractor may have access to the Owner’s qualified first aid personnel and ambulance, in case of accidents, if available. The Contractor will, however, provide a first-aid post for minor injuries to their staff.
2.17 Safety Equipment: All necessary personal safety equipment like safety belts, helmets,
protective face and eye shields, hand=gloves, overall etc. as required should be made available for the use to the person employed on the site. It is contractor’s responsibility to maintain all safety equipment in good working condition.
3.0 SUPERVISON OF WORK 3.1 The Contractor shall submit to the Owners a resume of his site-supervisors for approval
prior to commencement of the work. Once approved, the Contractor shall not remove his site-supervisors without prior concurrence of the Owners.
3.2 The entire work is to be completed as per the Project time schedule. The programme of
the work in details shall be submitted by the Contractor before commencement of the work. The detailed programmes prepared by the contractor shall conform to the targets set forth in the Time Schedule and will be subject to the approval of the Owners. All the work shall be carried out in such a manner that the work of other agencies operating at site is not hampered due to any action of the Contractor.
4.0 INSPECTION The work of the Contractor is subject to inspection by the Owners at all times. 5.0 EMPLOYMENT OF LABOUR 5.1 The Contactor will be expected to employ on the work only his regular skilled employees
with experience of this particular work. The permission of the Owners must be obtained before tradesmen are recruited locally for the work. This rules does not apply to un-skilled labour. No. person below the age of eighteen years shall be employed. The Contractor shall pay, to hs employees/ workers the minimum wages as per latest State Government notification issued time to time.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
5.2 All travelling expenses including provision of all necessary transport to and from Site, lodging allowances and other payments to the Contractor’s employees are his own responsibility.
5.3 The hours of work on the Site shall be decided by the Owners and Contractor shall
adhere to it Monday to Saturday minimum working hours will be 8 (eight hours per day excluding lunch break etc.
5.4 Contractor’s employees shall wear identification badges while on work site. 5.5 All notices displayed on the Site and any instructions issued by the Owner must be
strictly adhered to by the Contractor’s and / or his sub-contractor’s employees. 5.5.1 Contractor shall arrange labour licenses as per rules from concerned authorities at his
own cost. 5.5.2 Contractor will take insurance cover for all his employees against accident etc. 5.6 Contractor will arrange ration cards and permits, if required 5.7 In case the Owner becomes liable to pay any wages or dues to the labour of the
Contractor or his Sub-Contractor or any Government Agency under any of the provision of the Minimum Wages Act, Workmen Compensation Act or any other law due to act of omission of the Contractor, the Owner shall promptly make such payment and shall recover the same from the Contractor’s bills.
5.8 The Contractor shall be required to produce documentary evidence to the effect that he
has discharged his obligations under the Employees Provident Fund Act, 1952, for his / subcontractor’s employees working at site.
5.9 The OWNER shall allocate only space to the Contractor for his labour colony. It shall be
the responsibility of Contractor to provide suitable accommodation including all necessary facilities. However, subject to availability, electricity and water shall be provided at one place on chargeable basis. Further distribution, as required , shall be done by Contractor.
6.0 REPORTING
(a) The Contractor must report the following information to the Owner in writing each Friday:-
i) Number of employees, trades-wise, ii) Progress achieved; iii) Expected dates of completion of work;
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
iv) Any actual or potential delay in programme caused by the action or inaction of Owner and other Contractor working at site.
(b) If during excavation any materials such as but not limited to precious materials or treasure etc. are found, the same shall be reported to Owner immediately and shall be the property of Owner.
7.0 COMPLETION OF WORK: Before finally leaving site, all the Contractor’s huts,plant, tools and rubbish must be
removed and the site left clean and tidy. 8.0 INSURANCE CLAIM FOR DAMAGES On receipt of material at site, the Contractor shall promptly check for damages if any
and notify the Owner and shall take necessary action for lodging insurance claim for damages.
9.0 WORKING AND SAFETY REGULATIONS: 9.1 The Contractor will observe all statutory and legal requirements of Central and State
Governments applying to the work as well as any local regulations applying to the site issued by the Consultant or any other authority.
9.2 Particular attention is drawn to the following:-
i) In case of accident, the Owner shall be informed in writing forthwith. The Contractor shall strictly follow regulations laid down by Factory Inspector, Government and state authorities in the regard.
ii) Fencing all Contractor’s plant , platforms, excavations etc. iii) Compliance with all electricity regulations. Iv) Compliance with statutory requirements for inspection and test of all lifting
appliances and auxiliary lifting gear. 9.3 Staircase, doors and gangways must not be obstructed in any way that will interfere
with means of access or escape. 9.4. No excavation will be started without the permission of the Owner , who will inform the
Contractor of the position of any pipes or cables known to be buried in the area. All excavations must be effectively railed off at all times, or completely broaded over the properly marked during the hours of darkness by red warning lamps, using flameproof warning lamps in non-smoking areas. Debris or material which cannot be immediately
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
removed must be heaped in such a way as to leave adequate passage way. Any finds such as relics or antiques coins or fossils, etc shall be promptly handed over tot eh Owner.
9.5 The Contractor will notify the Owner of his intention to bring on the site any equipment , such as space heating or welding apparatus or any container holding liquid or gaseous fuel or other substance which might create a hazard. The Owner will have a right to prohibit the use of such equipment or to prescribe the conditions under which such equipment may be used. The owner will have the right to inspect any construction plant, and to forbid its use if in his opinion it is unsuitable or unsafe. No claim arising thee from shall be made by the Contractor. The Contractor or any one acting on his instructions will not bring on to the site any radio-active substance or any apparatus using such substances or any Z-ray apparatus until written permission and direction regarding the use of such equipment has been received from the Owner.
9.6 The Contractor will meet all requirements, and act on the instructions of the Owner
where it is necessary to operate a permit-to work” system. 9.7 Where it is necessary to provide any / or store petroleum products or petroleum
mixtures and explosive, the Contractor shall be responsible for carrying out such provision and / or storage in accordance with the rules and regulations laid down in Petroleum Act, 1934, Explosive Act, 1948 and Petroleum and Carbide of Calcium Manual published by the Chief Inspector of Explosives of India. All such storage shall have prior approvals of the Owner. In case any approval is necessary from the Chief Inspector of Explosives or any statutory authorities, the Contractor shall be responsible for obtaining the same.
9.8 The Contractor shall have his own fire fighting extinguishers and equipment. 9.9 The Contractor shall be responsible for the provision of all safety notices and safety
equipment required by both the relevant legislation and such as the Owner may deem necessary.
9.10 The Contractor shall be responsible for the safe storage of the radio-graphic sources or
those of his sub-contractors. 10.0 ELECTRICAL SAFETY REGULATIONS: 10.1 In no circumstances will be Contractor interfere with fuses and electrical equipment
belonging to the Owner or Contractor.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
10.2 Before the Contractor connects any electrical appliances to any plug or socket belonging
to the other Contractor or Owner , he will -
i) Satisfy the Owner that the appliance is in good working conditions. ii) Inform the Owner of the maximum current rating, voltage and phase of the
appliance. iii) Obtain permission of the Owner dealing the sockets to which the appliances may
be connected. 10.3 The Owner will not grant permission to plug in until he is satisfied that-
i) The appliance is in good condition and is fitted with a suitable plug; ii) The appliance is fitted with a suitable cable having two earth conductors, one of
which shall be an earthed metal sheath surrounding the cores. 10.4 No electric cable in use by the other Contractor / Owner will be distributed without
prior permission. No weight of any description will be imposed on any such cable and no ladder or similar equipment will rest against or be attached to it.
10.5 The voltage for all portable equipment e.g. drilling machines, temporary lighting etc. will
not exceed 240 volts. 10.6 No work must be carried out on any live equipment. The equipment must be made safe
and a “permit-to-work” issued before any work I carried out. 10.7. Contractor shall employ authorized electrician to maintain his temporary electrical
installation. 11.0 STATUTORY REQUIEMENTS: The contractor shall conform to the provisions of Acts of Parliament or State
Legislatures and to any bye-laws, rules orders or notifications of any Government, Municipal or local authority for the time being in force affecting the work undertaken by him and will give all necessary notices to and obtain requisite sanction and permits of and from the Municipal and any other authority in respect of the said work of the materials to be used threat and generally will comply with building and other regulations of such authorities and will keep the Owner/ Consultant indemnified against all claims , penalties and losses that may be incurred by it by reasons of any breach by the contractor of any statutes bye-laws, rules regulations , notification etc.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT VIII INSTALLATION OF VAM IN CPP &
AMMONIA-II PLANT
NATIONAL FERTILIZERS LIMITED
APPLICABLE INDIAN ACTS RULES AND REGULATIONS
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Applicable Indian Acts, Rules & Regulations 1. Indian Electricity Act (Modified) 1952 (Act IX, 1910) 2. The Electricity Supply Act (LIV) of 1948 3. Factories Act, 1948 4. Indian Explosives Act, 1948 5. Indian Boiler Act, 1884 6. The Petroleum Act 1934 7. Industrial Disputes Act, 1947 8. Income Tax Act 9. GST Act 10. Madhya Pradesh Transfer of Property Act 11. Indian Customs Act 12. The Indian Electricity Rule 13. Regulations for the Electrical Equipment of Buildings, 1958 14. IS-5572-1978: Classification of Hazardous Area 15. IS-2148-1968: Flame Proof Enclosures of Electrical Equipment 16. IS-5571-1970:Guide for Selection of Electrical Equipment for Hazardous Area 17. Fire Insurance Regulation 18. National Electrical Code (NEC) of National Fire Protection Association (NEPA ) USA 19. Fire Protection Manual (Red – Book)] 20. The Petroleum and Carbide of Calcium Manual\ 21. Explosive Rules, 1940
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
22. Indian Boiler Regulations 23. Indian Power Alcohol Rules. 24. IS-875-1987: Part 1,2,3,4 and 5 Codes of Practice for Design Loads for Buildings and Structures. 25. IS-1893-1987: Criteria for Earthquake Resistance Design of Structure IS-4326: Code of Practice
for Earthquake Resistance Design and Construction of Building. 26. The water (Prevention and Control Pollution ) Act, 1974, as amended up to date 27. The Water (Prevention and Control pollution ) Rules 1975 28. The Water (Prevention and Control Pollution ) (Procedure for Transaction of Business) Rules,
1975 NOTIFICATIONS I) Constitution of Appellate Authority
ii) Delegation of Powers as State Board by the Central Board to various Union Territory Administrations.
29. The Water ( Prevention and Control Pollution ) Cess Act , 1977,as amended by Amendment Act,
1991 30. The Air (Prevention and Control Pollution) Act, 1981, as amended by amendment act, 1987 31. The Air (Prevention and Control Pollution) Act, 1982 32. The Environmental laboratories and Analysis. NOTIFICATIONS
i) Environmental laboratories and Analysis Officers authorized for taking cognizance of offences.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
ATTACHMENT IX INSTALLATION OF VAM IN CPP &
AMMONIA-II PLANT
NATIONAL FERTILIZERS LIMITED
INTEGRITY PACT FORMAT
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
(To be executed on plain paper and submitted along with technical
bid/tender documents for tenders having a value of Rs.1 crore or more. To be signed by the bidder and NFL.)
National Fertilizers Limited (NFL) hereinafter referred to as “The Principal”.
AND
____________________________hereinafter referred to as “The Bidder/Contractor”
PREAMBLE
The Principal intends to award, under laid down organizational procedures, contract/s for ___________________________. The Principal values full compliance with all relevant laws of the land, rules, regulations, economic use of and of fairness/transparency in its relations with its Bidder(s) and/or Contractor(s). In order to achieve these goals, the Principal will appoint an Independent External Monitor (IEM), who will monitor the tender process and the execution of the contract for compliance with the principles mentioned above.
Action 1 – Commitments of the Principal.
1. The Principal commits itself to take all measures necessary to prevent corruption and to observe the following principles :-
a. No employee of the Principal, personally or through family members, will in connection with the tender for, or the execution of a contract, demand, take a promise for or accept, for self or third person, any material or immaterial benefit which the personal is not legally entitled to.
b. The Principal will during the tender process treat all Bidder(s) with equity and reason. The Principal will in particular, before and during the tender process, provide to all Bidder(s) the same information and will not provide to any Bidder(s) confidential/additional information through which the Bidder(s) could obtain an advantage in relation to the process or the contract execution.
c. The Principal will exclude from the process all known prejudiced persons. 2. If the Principal obtains information on the conduct of any of its employees which is a
criminal offence under the IPC/PC Act, or if there be a substantive suspicion in this regard, the Principal will inform the Chief Vigilance Officer and in addition can initiate disciplinary actions.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
Section 2 – Commitments of the Bidder(s)/Contractor(s)
1. The Bidder(s)/Contractor(s) commit himself to take all measures necessary to prevent corruption. He commits himself to observe the following principles during his participation in the tender process and during the contract execution.
a. The Bidder(s)/contractor(s) will not, directly or through any other persons or firm, offer promise or give to any of the Principal‟s employees involved in the tender process or the execution of the contract or to any third person any material or other benefit which he/she is not legally entitled to, in order to obtain in exchange any advantage or during the execution of the contract.
b. The Bidder(s)/Contractor(s) will not enter with other Bidders into any undisclosed agreement or understanding, whether formal or informal. This applies in particular to prices, specifications, certifications, subsidiary contracts, submission or non submission of bids or any other actions to restrict competitiveness or to introduce cartelization in the bidding process.
c. The Bidder(s)/Contractor(s) will not commit any offence under the relevant IPC/PC Act; further the Bidder(s)/Contractors will not use improperly, for purposes of competition or personal gain, or pass on to others, any information or documents provided by the Principal as part of the business relationship, regarding plans, technical proposals and business details, including information contained or transmitted electronically.
d. The Bidder(s)/Contractor(s) of foreign origin shall disclose the name and address of the Agents/representatives in India, if any. Similarly, the bidder(s)/contractor(s) of Indian Nationality shall furnish the name and address of the foreign principals, if any. All the payments made to the India agent/representative have to be in Indian Rupees only.
e. The Bidder(s)/Contractor(s) will, when presenting his bid, disclose any and all payments he has made, is committed to or intends to make to agents, brokers or any other intermediaries in connection with the award of the contract.
2. The Bidder(s)/Contractor(s) will not instigate third persons to commit offences outlined above or be an accessory to such offences.
Section 3: Disqualification from tender process and exclusion from future
contract If the Bidder(s)/Contractor(s), before award or during execution hascommitted a transgression through a violation of Section 2 above or inany other form such as to put his reliability or credibility in question,
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
the Principal is entitled to disqualify the Bidder(s)/Contractor(s) from the tender process or
to terminate the contract, if already signed, for such reasons.
Section 4: Compensation for Damages
1. If the Principal has disqualified the Bidder(s) from the tender process prior to the award according to Section 3, the Principal is entitled to demand and recover the damages equivalent to Earnest Money Deposit/Bid Security.
2. If the Principal has terminated the contract according to Section3, or if the Principal is entitled to terminate the contract according to Section3, the Principal shall be entitled to demand and recover from the Contractor liquidated damages of the Contract value or the amount equivalent to Performance Bank Guarantee.
Section 5: Previous Transgression
1. The Bidder declares that no previous transgressions occurred in the last three years with any other company in any country conforming to the TII‟s anti corruption approach or with any other public sector enterprise in India that could justify his exclusion from the tender process.
2. If the bidder makes incorrect statement on this subject, he can be disqualified from the tender process and appropriate action can be taken including termination of the contract, if already awarded, for such reason.
Section 6: Equal treatment of all Bidders/Contractors/Subcontractors.
1. The Principal will enter into agreements with the identical conditions as this one with all bidders, contractors and sub-contractors.
2. The Principal will disqualify from the tender process all bidders who do not sign this Pact or violate its provisions.
Section 7: Criminal charges against violation Bidder(s)/Contractor(s)/Sub-contractors(s). If the Principal obtains knowledge of conduct of a Bidder(s)/Contractor(s) which constitutes corruption, or if the Principal hassubstantive suspicion in this regard, the Principal will inform thesame to the Chief Vigilance Officer.
Section 8: Independent External Monitor/Monitors
1. The Principal appoints competent and credible Independent External Monitor for this Pact. The task of the Monitor is to review independently and objectively, whether and to what extent the parties comply with the obligations under this agreement.
2. The Monitor is not subject to instructions by the representatives of the parties and
performs his functions neutrally and independently. It will be obligatory for him to
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
treat the information and documents of bidders /contractors as confidential. He
reports to the Chairman & Managing Director, NFL.
3. The Bidder(s)/Contractor(s) accepts that the Monitor has the right to access without
restriction to all project documentation of the Principal including that provided by the
Contractor. The Contractor will also grant the Monitor, upon his request and
demonstration of a valid interest, unrestricted and unconditional access to his project
documentation. The same is applicable to Subcontractors. The Monitor is under
contractual obligation to treat the information and documents of the
Bidder(s)/Contractor(s)/Subcontractor(s) with confidentiality.
4. The Principal will provide to the Monitor sufficient information about all meetings
among the parties related to the Project provided such meetings could have an
impact on the contractual relations between the Principal and the Contractor. The
parties offer to the Monitor the option to participate in such meetings.
5. As soon as the Monitor notices, or believes to notice, a violation of this agreement,
he will so inform the Management of the Principal and request the Management to
discontinue or take corrective action, or to take other relevant action. The monitor
can in this regard submit non-binding recommendations. Beyond this, the Monitor
has no right to demand from the parties that they act in a specific manner, refrain
from action or tolerate action.
6. The Monitor will submit a written report to the Chairman & Managing Director,, NFL
within 8 to 10 weeks from the date of reference or intimation to him by the Principal
and, should be occasion arise, submit proposals for correcting problematic
situations.
7. Monitor shall be entitled to compensation on the same terms as being extended
to/provided to Independent Directors on NFL Board.
8. If the Monitor has reported to the Chairman & Managing Director, National Fertilizers
Limited, a substantiated suspicion of an offence under relevant IPC/PC Act, and the
Chairman & Managing Director, NFL has not, within the reasonable time taken
visible action to proceed against such offence or reported it to the Chief Vigilance
Officer, the Monitor may also transmit this information directly to the Central
Vigilance Commissioner.
COMMERCIAL DOCUMENTS
INVITATION TO BID
NATIONAL FERTILIZERS LTD
VIJAIPUR ESP-II PROJECT
9. The word “Monitor” word include both singular and plural.
Section 9: Pact Duration
This pact begins when both parties have legally signed it. It expires for the Contractor 12 months after the last payment under the contract, and for all other Bidder 6 months after the contract has been awarded. If any claim is made/lodged during this time, the same shall be binding and continue to be valid despite the lapse of this pact as specified above, unless it is discharged/determined by Chairman & Managing Director of NFL.
Section 10: Other Provisions
This agreement is subject to Indian Law. Place of performance andjurisdiction is the Registered Office of the Principal i.e. New Delhi.
Changes and supplements as well as termination notices need to bemade in writing. Side agreements have not been made.If the contractor is a partnership or a consortium, this agreementmust be signed by all partners or consortium members.
Should one or several provisions of this agreement turn out to beinvalid, the remainder of this agreement remains valid. In this case,the parties will strive to come to an agreement to their originalintentions.
(For & on behalf of the Principal) (For & on behalf of Bidder/Contractor) (Office Seal) (Office Seal) Place_________________ Date _________________ Witness 1: Witness 1: (Name & Address) (Name & Address) _____________________________ __________________________ _____________________________ __________________________ _____________________________ __________________________ Witness 2: Witness 2: (Name & Address) (Name & Address) _____________________________ __________________________ _____________________________ __________________________ _____________________________ __________________________