nastt’s no-dig 2019 show we hope this helps you plan your...

16
Water/Wastewater Water Wastewater Electrical Gas Other Track # Track 1 (MM-T1-01-05) Track 2 (MM-T2-01-05) Track 3 (MM-T3-01-05) Track 4 (MM-T4-01-05) Track 5 (MM-T5-01-05) Track 6 (MM-T6-01-05) Track Leader Large Diameter Tunneling Robert Martin HDD Maureen Carlin Condition Assessment Paul Savard Pipe Bursting Babs Marquis CIPP Jason Schiro Wastewater Pipeline Rehabilitation George Kurz 9:30 AM Emerald Parkway Culvert Repair - Combining Multiple Trenchless Techniques to Repair Collapsed Culvert and Re-establish Safety A Study on the Design-Build Delivery of a 9,000-ft Intersect Horizontal Directional Drill Under the Barnegat Bay Late 20s, Early 30s - Riveted Steel Pipe Condition Assessment - City of Toronto's Cadillac Water Main City of Tampa's Courtney Campbell Causeway Project - Successful Pipe Bursting Under a Heavily Traveled Scenic Highway CIPP Longevity - Planning for Well Beyond the Standard 50 Years 3.6-Mile Sewer Force Main Repair and Rehabilitation 9:55 AM Design and Construction of the Magnolia Stormwater Project in El Paso, Texas Elimination of Two Pump Stations in Bloomington, Illinois Condition Assessment in the City of Champions - Brockton's Twin 24-in. CI Transmission Mains The City of Montrose Colorado Self Performs Pipe Replacement Program Proves Successful Rehabilitation of the 1917 NATS Trunk Sewer Calumet Intercepting Sewer 19F Rehabilitation 10:20 AM Corrosion Resistance Tunnel Shaft Lining Using Fiberglass Reinforced Polymer Mortar (FRPM) Pipes Alternative HDD Construction Method for Ocean Outfall Inspection, Condition Assessment and Rehabilitation Planning for the Primary Trunk Pipe Bursting Challenges and Emergency Rescue Shafts in Newport Beach, California - Orange County Sanitation District Toronto Water's Annual Sewer Rehabilitation Program Evaluation of Potential Release of Organic Chemicals in the Steam Exhaust during Pipe Rehabilitation Using CIPP 10:45 AM Corrugated City of Steam – University of Arizona Drama Tunnel Sensitivity of the Cavity Expansion Model to Variations in Input Parameters for Specific Soil Types Condition Assessment of Twin 30-in. Steel Force Mains What You Don't Know Can Hurt You When Pipe Bursting UV-Light Cured CIPP Lining for Pipeline Rehabilitation Nothing Rosy about a Failed Sewer Part 2: Lessons Learned During Construction 11:10 AM Mechanized Cross Passage Construction: Ideal for Soft Soils with High Groundwater Table Comparing Two Horizontal Directional Drilled Crossings With and Without a Surface Casing in Cache Creek, British Columbia Benefits of a Phased Approach to Force Main Assessment Redding, California, Successfully Uses Static Pipe Bursting for Over Three Miles of Gravity Sewer Mains and Laterals CIPP Pipe Renovation Under the Rideau Canal Using a Styren-Free Resin Engineered and Innovative - Taking the Trenchless Approach in Springfield, Massachusetts Schedule At-A-Glance: Monday AM Sessions NASTT’s NO-DIG SHOW 2019 March 17-21, 2019 | Chicago, Illinois 5 Plan your experience! Monday, March 18, 2019 Monday Events Attendee & Exhibitor Registration 7:00 AM – 5:00 PM - Lobby Kick-Off Breakfast 7:30 AM – 9:15 AM - Room 21-24 Exhibit Hall Ribbon Cutting Ceremony 11:40 AM – 11:45 AM - Foyer Hall A Exhibit Hall Open 11:45 AM – 3:45 PM - Hall A NASTT’s 18th Annual Educational Fund Auction & Reception 5:30 PM – 7:30 PM - Room 21-24 Direct Pipe Forum 3:45 PM MA-T3-01 and MA-T3-02 Track Leader: Jon Robison Room 1 This forum will provide a discussion of direct pipe driven by audience participation. AM Sessions Track 1: 9:30 AM – 11:35 AM - Room 14 Track 2: 9:30 AM – 11:35 AM - Room 12 Track 3: 9:30 AM – 11:35 AM - Room 1 Track 4: 9:30 AM – 11:35 AM - Room 2 Track 5: 9:30 AM – 11:35 AM - Room 3 Track 6: 9:30 AM – 11:10 AM - Room 4 PM Sessions Track 1: 3:45 PM – 5:25 PM - Room 14 Track 2: 3:45 PM – 5:25 PM - Room 12 Track 3: 3:45 PM – 5:25 PM - Room 1 Track 4: 3:45 PM – 5:25 PM - Room 2 Track 5: 3:45 PM – 5:25 PM - Room 3 Track 6: 3:45 PM – 5:25 PM - Room 4 Technical Paper Sessions Schedule As you delve into Conference Preview 1, you may notice it looks a bit different than in previous years. The new format shows the sessions by industry segment rather than by date/time. We hope this helps you plan your schedule at NASTT’s 2019 No-Dig Show!

Upload: ngobao

Post on 02-Feb-2019

214 views

Category:

Documents


0 download

TRANSCRIPT

Water/Wastewater Water Wastewater Electrical Gas Other

Track # Track 1 (MM-T1-01-05)

Track 2 (MM-T2-01-05)

Track 3 (MM-T3-01-05)

Track 4 (MM-T4-01-05)

Track 5 (MM-T5-01-05)

Track 6(MM-T6-01-05)

Track Leader Large Diameter Tunneling

Robert Martin

HDDMaureen Carlin

Condition AssessmentPaul Savard

Pipe BurstingBabs Marquis

CIPPJason Schiro

Wastewater Pipeline Rehabilitation

George Kurz

9:30 AM Emerald Parkway Culvert Repair - Combining Multiple Trenchless Techniques to Repair Collapsed Culvert and Re-establish Safety

A Study on the Design-Build Delivery of a 9,000-ft Intersect Horizontal Directional Drill Under the Barnegat Bay

Late 20s, Early 30s - Riveted Steel Pipe Condition Assessment - City of Toronto's Cadillac Water Main

City of Tampa's Courtney Campbell Causeway Project - Successful Pipe Bursting Under a Heavily Traveled Scenic Highway

CIPP Longevity - Planning for Well Beyond the Standard 50 Years

3.6-Mile Sewer Force Main Repair and Rehabilitation

9:55 AM Design and Construction of the Magnolia Stormwater Project in El Paso, Texas

Elimination of Two Pump Stations in Bloomington, Illinois

Condition Assessment in the City of Champions - Brockton's Twin 24-in. CI Transmission Mains

The City of Montrose Colorado Self Performs Pipe Replacement Program Proves Successful

Rehabilitation of the 1917 NATS Trunk Sewer

Calumet Intercepting Sewer 19F Rehabilitation

10:20 AM Corrosion Resistance Tunnel Shaft Lining Using Fiberglass Reinforced Polymer Mortar (FRPM) Pipes

Alternative HDD Construction Method for Ocean Outfall

Inspection, Condition Assessment and Rehabilitation Planning for the Primary Trunk

Pipe Bursting Challenges and Emergency Rescue Shafts in Newport Beach, California - Orange County Sanitation District

Toronto Water's Annual Sewer Rehabilitation Program

Evaluation of Potential Release of Organic Chemicals in the Steam Exhaust during Pipe Rehabilitation Using CIPP

10:45 AM Corrugated City of Steam – University of Arizona Drama Tunnel

Sensitivity of the Cavity Expansion Model to Variations in Input Parameters for Specific Soil Types

Condition Assessment of Twin 30-in. Steel Force Mains

What You Don't Know Can Hurt You When Pipe Bursting

UV-Light Cured CIPP Lining for Pipeline Rehabilitation

Nothing Rosy about a Failed Sewer Part 2: Lessons Learned During Construction

11:10 AM Mechanized Cross Passage Construction: Ideal for Soft Soils with High Groundwater Table

Comparing Two Horizontal Directional Drilled Crossings With and Without a Surface Casing in Cache Creek, British Columbia

Benefits of a Phased Approach to Force Main Assessment

Redding, California, Successfully Uses Static Pipe Bursting for Over Three Miles of Gravity Sewer Mains and Laterals

CIPP Pipe Renovation Under the Rideau Canal Using a Styren-Free Resin

Engineered and Innovative - Taking the Trenchless Approach in Springfield, Massachusetts

Schedule At-A-Glance: Monday AM Sessions

NASTT’s

NO-DIG SHOW 2

019

March 17-21, 2019 | Chicago, Illinois 5

Plan your experience!Monday, March 18, 2019

Monday EventsAttendee & Exhibitor Registration7:00 AM – 5:00 PM - Lobby

Kick-Off Breakfast 7:30 AM – 9:15 AM - Room 21-24

Exhibit Hall Ribbon Cutting Ceremony 11:40 AM – 11:45 AM - Foyer Hall A

Exhibit Hall Open 11:45 AM – 3:45 PM - Hall A

NASTT’s 18th Annual Educational Fund Auction & Reception5:30 PM – 7:30 PM - Room 21-24

Direct Pipe Forum3:45 PMMA-T3-01 and MA-T3-02 Track Leader: Jon Robison Room 1

This forum will provide a discussion of direct pipe driven by audience participation.

AM Sessions

Track 1: 9:30 AM – 11:35 AM - Room 14Track 2: 9:30 AM – 11:35 AM - Room 12Track 3: 9:30 AM – 11:35 AM - Room 1Track 4: 9:30 AM – 11:35 AM - Room 2Track 5: 9:30 AM – 11:35 AM - Room 3Track 6: 9:30 AM – 11:10 AM - Room 4

PM Sessions

Track 1: 3:45 PM – 5:25 PM - Room 14Track 2: 3:45 PM – 5:25 PM - Room 12Track 3: 3:45 PM – 5:25 PM - Room 1Track 4: 3:45 PM – 5:25 PM - Room 2Track 5: 3:45 PM – 5:25 PM - Room 3Track 6: 3:45 PM – 5:25 PM - Room 4

Technical Paper Sessions Schedule

As you delve into Conference Preview 1, you may notice it looks a bit different than in previous years. The new format shows the sessions by industry segment rather than by date/time.

We hope this helps you plan your schedule at NASTT’s 2019 No-Dig Show!

6

Track 1: Large Diameter TunnelingTrack Leader: Robert Martin

10:20 AM .....................................................MM-T1-03Corrosion Resistance Tunnel Shaft Lining Using Fiberglass Reinforced Polymer Mortar (FRPM) PipesBijan Khamanian, Hobas Pipe USAVery large diameter fiberglass (FRPM, GRP, FRP) pipes provide a unique solution as a finished liner for large tunnel shaft finish. The segments are faster to install than cast in place HDPE or PVC liner, which has been common in the years past.

Track 2: HDD Track Leader: Maureen Carlin

9:55 AM .......................................................MM-T2-02Elimination of Two Pump Stations in Bloomington, IllinoisLuke Thoele, City of Bloomington; Ryan Otto, City of Bloomington; Dan Good, Maurer-Stutz Inc; Don Colclasure, Stark Excavating; Mike Kaisner, Hoerr Construction; Eric Whiteside, Midwest MoleThe City of Bloomington, Illinois, was able to eliminate two sanitary sewer pump stations by using a creative combination of horizontal directional drilling, CIPP lining and repurposing an abandoned force main as a gravity flow sewer.

10:20 AM .....................................................MM-T2-03Alternative HDD Construction Method for Ocean OutfallCraig Camp, GHD; Sharron Lynn, City of Rehoboth Beach; Kelvin George, GHD; Nick Strater, Brierley AssociatesThe paper will focus on the lessons learned during construction of an offshore pipeline. Construction included 6,000 ft of outfall including diffuser. Horizontal directional drilling installed 3,800 ft of the offshore ocean outfall pipeline. The project required re-drilling 1,200 ft of pilot hole and intersecting the HDD alignment.

Track 3: Condition Assessment Track Leader: Paul Savard

10:20 AM .....................................................MM-T3-03Inspection, Condition Assessment and Rehabilitation Planning for the Primary TrunkJayne Harris, Jacobs; Justin Starr, Redzone Robotics; Ben Pressman, The Regional Municipality of York; Sam Cancilla, Redzone Robotics; Gordon Henrich, D.M Robichaud Ltd; Chris White, Redzone RoboticsEnhanced inspection and condition assessment of the primary trunk sanitary sewer to evaluate current condition and rate of change and to determine the optimum timeline for rehabilitation. 

10:45 AM .....................................................MM-T3-04Condition Assessment of Twin 30-in. Steel Force MainsWayne Gresh, Carollo Engineers; Susan Hildreth, King County Wastewater Treatment Division; Karl Hadler, Carollo Engineers; Alison Payauys, Carollo Engineers; Richard Pousard, HDRTrenchless condition assessment of approximately 25,000 lf of twin parallel 30-in. diameter steel force mains using soil corrosively, close interval potential survey, direct assessment, CCTV inspection and ultrasonic wall thickness measurements.

11:10 AM .....................................................MM-T3-05Benefits of a Phased Approach to Force Main Assessment Amy Bley, RJN Group Inc; Catherine Morley, RJN Group IncForce main inspections are inherently expensive.

This paper will explain the benefits of a phased approach in determining force main conditions and different inspection technologies available. By using specific case studies we will show how trenchless and traditional open cut techniques can be used together to save time, effort and money.

Track 4: Pipe Bursting Track Leader: Babs Marquis

10:20 AM .....................................................MM-T4-03Pipe Bursting Challenges and Emergency Rescue Shafts in Newport Beach, California - Orange County Sanitation DistrictRaul Cuellar, Orange County Sanitation District; Brad Moore, Orange County Sanitation District; Mark Hutchinson, Staheli Trenchless ConsultantsThis paper discusses the major challenges encountered during pipe bursting operations, the project installed 920 ft with three different pipe sizes within a busy traffic corridor in the City of Newport Beach. Two emergency rescue shafts were required to be constructed due to 2-in. thick redwood boards surrounding the existing sewer pipe.

10:45 AM .....................................................MM-T4-04What You Don’t Know Can Hurt You When Pipe BurstingMark Hutchinson, Staheli Trenchless Consultants; Daniel Tariku, City of Portland; Raul Cuellar, Orange County Sanitation DistrictThis paper provides examples from past projects of factors outside the pipe that affect pipe bursting and their result.  The paper provides a list of questions to ask during the predesign and design to better tailor the project to the site conditions you can’t see.

11:10 AM .....................................................MM-T4-05Redding, California, Successfully Uses Static Pipe Bursting for Over Three Miles of Gravity Sewer Mains and LateralsEdward Alan Ambler, AM Trenchless; Josh Vandiver, City of Redding; Corri Vandiver, City of Redding; George Mallakis, TT TechnologiesThe City of Redding in Northern California has constructed a static pipe bursting project replacing more than three miles of gravity sewer mainline and laterals. Redding design staff teamed with AM Trenchless and Cox and Cox Construction to perform the project to replace both existing VCP and AC pipelines.

Track 5: CIPP Track Leader: Jason Schiro

9:30 AM .......................................................MM-T5-01CIPP Longevity - Planning for Well Beyond the Standard 50 YearsRobert Lee, Murraysmith; Colleen Harold, City of PortlandMany municipalities utilize an asset management approach when deciding rehabilitation versus replacement. CIPP is traditionally thought to have a design life of 50 years. This paper presents the design rationale and case studies that present a case for a significantly longer and customized design life of CIPP.

9:55 AM .......................................................MM-T5-02Rehabilitation of the 1917 NATS Trunk SewerKevin Bainbridge, Robinson Consultants; Patrick Moskwa, Robinson Consultants; Roger Levesque, Halifax Water; David Ellis, Halifax WaterThe NATS Trunk Sewer was constructed in 1917 via tunneling and trench excavation along the Northwest Arm inlet. Inspections of the NATS identified the need for rehabilitation to remove debris, restore structural integrity, eliminate exfiltration and infiltration, establish a corrosion barrier and extend the life of the sewer.

10:20 AM .....................................................MM-T5-03Toronto Water’s Annual Sewer Rehabilitation ProgramChristopher Macey, AECOM; Bo Pajic, Toronto Water; Kevin Bainbridge, Robinson Consultants; Kristy Gibson, Toronto Water; Richard Sukut, AECOM

Water/Wastewater

Monday, March 18, 2019 - AM Sessions

Wastewater

Monday, March 18, 2019 - AM Sessions

Toronto Water manages an inventory of over 5,540 km of sewers that directly service a population of 2.8 million. Its annual rehab program is among the largest and most mature programs in North America with a focus on sustainability and minimizing the impact of delivering the program on the public.

Track 6: Wastewater Pipeline RehabilitationTrack Leader: George Kurz

9:30 AM .......................................................MM-T6-013.6-Mile Sewer Force Main Repair and RehabilitationScott Teschky, City of Fort Lauderdale; Jose Custodio, City of Fort Lauderdale; David Kinsella, Murphy Pipeline Contractors Inc 19,400 lf of failing DIP 30-in. force main was rehabilitated utilizing HDD, including a subaqueous crossing, swagelining and open cut. HDPE was used for the new pipe. Under an emergency purchase declaration, the city procured the project using the design-build delivery method to expedite execution of the work.

9:55 AM .......................................................MM-T6-02Calumet Intercepting Sewer 19F RehabilitationFrederick Wu, Metropolitan Water Reclamation District of Greater Chicago; Kevin Coburn, Insituform Technologies USAPaper and presentation surrounding the condition assessment, technology evaluation, and rehabilitation of 14,000 ft of 60-in. diameter wastewater pipeline (30 ft to 60 ft in depth) in the greater Chicago, Illinois, area.

10:20 AM .....................................................MM-T6-03Evaluation of Potential Release of Organic Chemicals in the Steam Exhaust during Pipe Rehabilitation Using CIPPVinayak Kaushal, Center for Underground Infrastructure Research and Education; Mohammad Najafi, Center for Underground Infrastructure Research and Education; Melanie Sattler, The University of Texas at Arlington; Kevin Schug, The University of Texas at ArlingtonThis paper is presents literature review results related to potential release of organic compounds during pipe renewal/rehabilitation using the steam-cured CIPP method.

10:45 AM .....................................................MM-T6-04Nothing Rosy about a Failed Sewer Part 2: Lessons Learned During ConstructionCasey Raines, GHD; Greg Watanabe, GHDThe Rose Canyon Trunk Sewer, a 60-in. plastic-lined reinforced concrete pipe, required rehabilitation due to failed weld strips at the joints. Internal mechanical pipe seals and new plastic liner strips were selected to repair the trunk sewer via manned entry. Part 2 outlines the lessons learned during construction.

11:10 AM .....................................................MM-T6-05 Engineered and Innovative - Taking the Trenchless Approach in Springfield, MassachusettsJonnas Jacques, KleinfelderThis presentation will focus on the trenchless rehabilitation methods used in the design and construction of the Main Interceptor Rehabilitation and CSO Improvements Project in Springfield, Massachusetts. The presentation will discuss some typical design challenges, the solutions to overcome them and considerations for future large diameter wastewater infrastructure rehabilitation.

Track 1: Large Diameter TunnelingTrack Leader: Robert Martin

9:30 AM .......................................................MM-T1-01Emerald Parkway Culvert Repair - Combining Multiple Trenchless Techniques to Repair Collapsed Culvert and Re-establish Safety

Water/Wastewater Water Wastewater Electrical Gas Other

Networking Event Kick-Off BreakfastMonday, March 18, 2019 - 7:30 AM – 9:15 AM - Room 21-24Full conference attendees are invited to rise and shine at NASTT’s No-Dig Show Kick-Off Breakfast! The morning will provide a fun mix of networking, good food, the much-anticipated NASTT and Trenchless Technology awards, as well as unforgettable entertainment.

This year’s esteemed awards will include NASTT’s 2018 Outstanding Papers in Rehabilitation and New Installation, as well as Trenchless Technology’s 2019 Person of the Year and 2018 Projects of the Year.

7

Anthony Vitale, Northeast Ohio Regional Sewer District; Ryan Butler, NTH Consultants Ltd; James Jones, Northeast Ohio Regional Sewer District; Brian Froehlich, Turn-Key Tunneling Inc; Karrthik Kirupakaran, NTH Consultants LtdThe Emerald Parkway Culvert Repair Project is a Design-Build Contract issued by the Northeast Ohio Regional Sewer District to address a 250-lf section of collapsed 11-ft diameter corrugated metal pipe culvert.  The collapse caused runoff from 625 acres of drainage area to submerge the inlet and upstream areas.

9:55 AM .......................................................MM-T1-02Design and Construction of the Magnolia Stormwater Project in El Paso, TexasAndrew Finney, Jacobs; Michael Ancell, Jacobs; Thomas Cieslik, El Paso WaterThis paper discusses the evaluation of appropriate tunneling technologies and presents construction observations related to tunneling through clean sand to construct a stormwater discharge to the Rio Grande for the Magnolia Stormwater Project.

Track 4: Pipe BurstingTrack Leader: Babs Marquis

9:55 AM .......................................................MM-T4-02The City of Montrose Colorado Self Performs Pipe Replacement Program Proves SuccessfulDave Holcomb, TT Technologies Inc; John Zarkis, City of MontroseRising costs associated with traditional open cut replacement pushed Montrose utilities division to look at trenchless pipe bursting. This paper will focus on the complete pipe replacement program, from aging pipe selection criteria through replacement pipe install. Including program challenges, lessons learned and overall cost savings.

Track 5: CIPPTrack Leader: Jason Schiro

10:45 AM .....................................................MM-T5-04UV-Light Cured CIPP Lining for Pipeline RehabilitationJeff Maier, C&L Water Solutions Inc.; Mark Hallett, Saertex Multicom LP; Steve Lamb, North Davis Sewer District A technical overview of the ultra-violet light cured, glass reinforced CIPP lining process (UV-CIPP) for trenchless rehabilitation of sewer, storm water and pressure pipelines is presented. Design and specification considerations, product selection, installation procedures, quality assurance/quality control measures and inspection will be covered. Case study examples will be provided. 11:10 AM .....................................................MM-T5-05CIPP Pipe Renovation Under the Rideau Canal Using a Styren-Free ResinHoussam Ghosn, Clean Water Works; Kyle Peori, Clean Water Works; Kaleel Rahaim, Interplastic Corporation; Derek Lougher-Goodey, Stantec; Jason Schiro, Interplastic CorporationAfter the successful completion of a styrene-free CIPP project for three sewer pipes installed under the Ottawa Rideau Canal a technical paper is prepared to describe the choice of a Styrene-Free resin application in lining the pipes, while presenting the challenges of setup and installation.

Track 1: Large Diameter TunnelingTrack Leader: Robert Martin

10:45 AM .....................................................MM-T1-04Corrugated City of Steam – University of Arizona Drama TunnelMo Ehsani, QuakeWrap Inc; Ryan Kelly, FRP Construction LLCThe paper describes the repair of over 130 ft of a 96-in. diameter corrugated metal pipe utility tunnel under a university campus. The tunnel houses several utility pipes.  Repairs using carbon FRP application were successfully completed on time with no disruption of service to the tunnel or campus traffic.  

11:10 AM .....................................................MM-T1-05Mechanized Cross Passage Construction: Ideal for Soft Soils with High Groundwater TableGerhard Lang, Herrenknecht AG; Peter Schmaeh, Herrenknecht AGCross passages are gaining importance in the construction of safe underground infrastructures such as traffic tunneling projects. This paper presents mechanized cross passage concepts to be used to link two traffic tunnels or tunnels with escape shafts in weak ground conditions with a high groundwater table.

Track 2: HDDTrack Leader: Maureen Carlin

10:45 AM .....................................................MM-T2-04Sensitivity of the Cavity Expansion Model to Variations in Input Parameters for Specific Soil TypesMary Neher, Bennett Trenchless Engineers; Dave Bennett, Bennett Trenchless EngineersA continuation of work by Staheli et al (2010), this paper addresses the sensitivity of the hydrofracture risk prediction for specific soil types. It discusses the results of the model when input parameters are varied over the range which is appropriate for soil types such as undrained clays.

Water

Monday, March 18, 2019 - AM Sessions

Track 3: Condition AssessmentTrack Leader: Paul Savard

9:30 AM .......................................................MM-T3-01Late 20s, Early 30s - Riveted Steel Pipe Condition Assessment - City of Toronto’s Cadillac Water MainPeter Peng, City of Toronto; Piero Salvo, GAME Trenchless ConsultantsThe City of Toronto has 500 km (300 mile) of trunk water mains, of which 16 km (10 miles) are 1920/1930s vintage Riveted Steel ‘Metrolinks’ pipe. These pipes are considered to be the Cadillac of water mains because of the way they were built. The city’s proactive Condition Assessment program will be presented.

9:55 AM .......................................................MM-T3-02Condition Assessment in the City of Champions - Brockton’s Twin 24-in. CI Transmission MainsIan Mead, Tighe & Bond; Lawrence Rowley, City of BrocktonThis paper and presentation include evaluation of options, planning, and implementation of an in-line leak detection and pipe location exercise for twin 24-in. cast iron water transmission mains for the City of Brockton, Massachusetts. A recent rupture

Track 2: HDDTrack Leader: Maureen Carlin

9:30 AM .......................................................MM-T2-01A Study on the Design-Build Delivery of a 9,000-ft Intersect Horizontal Directional Drill Under the Barnegat BayKerby Primm, Laney Directional Drilling; Mike Healy, Stantec; Marc Pannaccione, New Jersey Natural Gas; Maureen Carlin, Laney Directional DrillingThis case study discusses the recently constructed South Seaside Reinforcement Project for New Jersey Natural Gas. It included the 9,000-ft HDD installation of a 12-in. diameter pipeline under the Barnegat Bay. The drill geometry included multiple horizontal and vertical curves and the construction was executed using the intersect method.   11:10 AM .....................................................MM-T2-05Comparing Two Horizontal Directional Drilled Crossings With and Without a Surface Casing in Cache Creek, British ColumbiaMichelle van der Pouw Kraan, McMillen Jacobs Associates; Carrie Grant, FortisBC; Rachel Martin, McMillen Jacobs Associates; Norman Joyal, McMillen Jacobs AssociateThis paper compares the two crossings completed with and without a surface casing in the adverse ground present in the upper portions of the bore profile.

Gas

Monday, March 18, 2019 - AM Sessions

+ Other

Monday, March 18, 2019 - AM Sessions

and emergency response highlighted the need for condition assessment information and system redundancy.

Track 4: Pipe BurstingTrack Leader: Babs Marquis

9:30 AM .......................................................MM-T4-01City of Tampa’s Courtney Campbell Causeway Project - Successful Pipe Bursting Under a Heavily Traveled Scenic HighwayEdward Alan Ambler, AM Trenchless; Roy McKenzie, City of TampaThe City of Tampa successfully implemented a 1,700-lf 8-in. pipe bursting project under a scenic highway with an average daily traffic of 75,000 vehicles. Use of pipe bursting on this project clearly demonstrates the social savings trenchless provides to reduce the construction schedule and footprint on major roadways.

Water/Wastewater Water Wastewater Electrical Gas Other

8

Track 1: MicrotunnelingTrack Leader: Brenden Tippets

3:45 PM ........................................................ MA-T1-01 Kingsbury Run Culvert Repair: First Horizontal S-Curve & Double Vertical Curve in the United StatesBrian Daugherty, Northeast Ohio Regional Sewer District; Colin Irwin, Ward and Burke Tunneling Inc; James Jones, Northeast Ohio Regional Sewer District; Stephan Janosko, Northeast Ohio Regional Sewer District; Sven Wiberg, AECOM; Devonte Hopson, Northeast Ohio Regional Sewer DistrictThe Kingsbury Run Culvert Repair Project is an $9.8 million project constructed to address a failed/collapsed brick culvert section located in Cleveland, Ohio. The contractor performed a 2,700-lf horizontal S-Curve microtunnel run and a 900-lf microtunnel run with two vertical curves, a first in the United States.

Track 2: HDDTrack Leader: Dennis Doherty

4:35 PM ........................................................ MA-T2-03Beaufort Jasper Water & Sewer Authority Installs Multiple High-Risk HDDs with Proven Procurement MethodBrian Chemsak, Beaufort Jasper Water and Sewer Authority; Chris Burke, Hussey, Gay Bell, & DeYoungLocal utility Beaufort Jasper Water and Sewer Authority completed a 5,300-ft, 16-in. force main expansion, as well as a 4,200-ft, 24-in. reclaimed effluent pipeline installation using horizontal directional drilling (HDD), as well as the same team it had assembled in 2007 to complete its first high risk HDD project.

Track 4: Pipe RammingTrack Leader: Sam Brancheau

5:00 PM ........................................................ MA-T4-04Use of the Pipe Ramming Method to Finish Installations Begun by Other Trenchless MethodsAlan Goodman, HammerHead Trenchless; Pedro Montehano, Red Ant Boring Co

This case study describes a 24-in. casing installation job in Wisconsin begun with the auger boring technique. Auger boring operations stopped in saturated soil conditions of heavy, wet sand after progressing only 20 ft. The contractor used a 16-in. pneumatic ramming tool to install 90 ft of 36-in. steel-wall casing.

Track 5: CIPPTrack Leader: Bill Moore

3:45 PM ........................................................ MA-T5-01Not on My Watch - Using CIPP to Ensure Disaster Doesn’t StrikeJustin deMello, Woodard & Curran; Paul Costello, City of QuincyThis presentation will cover the ingenuity and construction process behind rehabilitating 1,600 lf of 12-in. Cured-in-place pipe and the cementitious coating of several manholes located down an embankment, on the beach, below the high tide line with manhole covers located 10 ft up in the air.

4:10 PM ........................................................ MA-T5-02East Central Regional Water Reclamation Facility (ECRWRF) Biosolids 30-in. RAS Twin Pipe RehabilitationJohn Tucker, Insituform; Ethan Heijn, Hazen and SawyerRehabilitating existing twin 500-ft long return activated sludge (RAS) pipes met with a number of challenges, including high ground water elevation and special pit placement due to aging infrastructure. This paper will review the project, solution selection, construction of the tri-axal glass fabric material and installation process.

4:35 PM ........................................................ MA-T5-03Success for Stamford in CIPPBradley Marin, GHD LtdThe Region of Niagara Falls is in the process of rehabilitating the Stamford Trunk Sanitary Sewer (STSS). The CIPP rehabilitation consists of approximately 3,015 ft of 42-in. and 4,577 ft of 48-in. concrete sewer and 23 manholes. By-pass pumping and material testing will play a key role in determining the success.

Track 6: Wastewater Pipeline RehabilitationTrack Leader: David Rosenberg

3:45 PM ........................................................ MA-T6-01 Emergency Force Main Trenchless Rehabilitation Michael Fleury, Carollo EngineersThis paper discusses an emergency design/build and construction services for the City of Riverside’s Trautwein and Alessandro Sewer Force Main Emergency Rehabilitation project. This fast-track emergency project was required after two sanitary sewer overflows (SSOs) occurred due to failures of the 16-in. diameter force main.

4:10 PM ........................................................ MA-T6-02Pipe Bursting Success in Developed NeighborhoodJeffrey Tarantino, Freyer & Laureta IncThe San Francisco Regional Water Quality Control Board issued Pacifica a Cease and Desist Order (CDO) to eliminate SSOs by January 2019. The San Pedro Point Neighborhood Sewer Rehabilitation Project replaced 16,000 ft of sewer main using pipe bursting as part of City multi-year CIP to successfully comply with the CDO.

4:35 PM ........................................................ MA-T6-03Life Cycle Cost Analysis for Decision Making in Collection System RehabilitationBevin Beaudet, Bevin A.Beaudet, P.E., LLC; Bruce Tobey, PLDOLife Cycle Cost (LCC) analysis facilitates good business case decisions that can stretch limited utility capital and operating budgets. This paper presents the LCC methodology as it pertains to collection system rehabilitation. A spreadsheet-based LLC case study of cured -in-place pipe (CIPP) lateral liners is presented and explained.

5:00 PM ........................................................ MA-T6-04Large Diameter Sewer Rehabilitation in the City of PortlandTodd Martinez, WSP USA Hamed Hakimelahi WSP USA; Kurt Robinson, City of Portland; Joe Hoffman, City of Portland; John Houle, City of PortlandA summary of the predesign phase of large diameter sewer rehabilitation in the City of Portland, Oregon, including condition assessment, strategies for project prioritization and selecting rehabilitation technologies to match observed defects.

Wastewater

Monday, March 18, 2019 - PM Sessions

Schedule At-A-Glance: Monday PM Sessions

Track # Track 1 (MA-T1-01-04)

Track 2 (MA-T2-01-04)

Track 3 (MA-T3-01-04)

Track 4 (MA-T4-01-04)

Track 5 (MA-T5-01-04)

Track 6(MA-T6-01-04)

Track Leader Microtunneling Brenden Tippets

HDDDennis Doherty

Direct PipeJon Robison

Pipe BurstingSam Brancheau

CIPPBill Moore

Wastewater Pipeline Rehabilitation

David Rosenberg

3:45 PM Kingsbury Run Culvert Repair: First Horizontal S-Curve & Double Vertical Curve in the United States

Design-Build Solution for Trenchless Installation of 9,500-ft Long HDD Crossing

Direct Pipe Forum

This forum will provide a discussion

of direct pipe driven by audience

participation.

Guided Pipe Ramming at O'Hare Airport Minimizes Disruption

Not on My Watch - Using CIPP to Ensure Disaster Doesn't Strike

Emergency Force Main Trenchless Rehabilitation

4:10 PM Proper Fluid Management for Successful Installations

Engineering Judgement in Maximum Bore Pressure Design

Overcoming Unanticipated Pipe-Ramming Obstructions in Sensitive Ground Conditions

East Central Regional Water Reclamation Facility (ECRWRF) Biosolids 30-in. RAS Twin Pipe Rehabilitation

Pipe Bursting Success in Developed Neighborhood

4:35 PM Globeville Ph. 3 Outfall Tunnel Project - Challenges and Solutions for Twin 8.5-ft Diameter Tunnels

Beaufort Jasper Water & Sewer Authority Installs Multiple High-Risk HDDs with Proven Procurement Method

A Case Study on the World-Record Direct Pipe® Method Installation Beneath the Gulf of Mexico

Use of the Pipe Crushing Technique Expedites Removal of 'Swallowed' Corrugated Metal Pipe (CMP)

Success for Stamford in CIPP

Life Cycle Cost Analysis for Decision Making in Collection System Rehabilitation

5:00 PM Randall's Island Microtunnel Crossing: Managing Risk while Microtunneling in a Dense Urban Environment

Outfall Replacement under San Elijo Lagoon Marine Reserve

42-in. Direct Pipe Through 227MPa Rock

Use of the Pipe Ramming Method to Finish Installations Begun by other Trenchless Methods

The Mechanical Property Testing and Evaluation for Reinforced CIPP Composite Materials using Glass, Carbon Fibers and Polyester Felt

Large Diameter Sewer Rehabilitation in the City of Portland

Water/Wastewater Water Wastewater Electrical Gas Other

Networking Event NASTT’s 18th Annual Educational Fund Auction & ReceptionMonday, March 18, 2019 - 5:30 PM – 7:30 PM - Room 21-24Join in the fun and excitement at NASTT’s fundraising social event of the year! Since 2002, NASTT has raised more than $1,000,000 to support educational initiatives, including being able to sponsor students’ attendance at the No-Dig Show, award scholarships and provide targeted training courses to the membership at large

This year’s Educational Fund Auction will feature a costume contest, Hawaiian vacation raffle and 50/50 raffle, and, of course, plenty of great items to bid on during the auction.

Track 1: MicrotunnelingTrack Leader: Brenden Tippets

4:35 PM ........................................................ MA-T1-03Globeville Ph. 3 Outfall Tunnel Project - Challenges and Solutions for Twin 8.5-ft Diameter TunnelsTodd Kilduff, Kilduff Underground Engineering; Lester Bradsha, Bradshaw Construction; Matthew Roberts, Kiewit Construction This paper is case history of a microtunneling project, twin 8.5-ft diameter tunnels, each 550 lf, under a very busy railyard and light transit rail operated by RTD in Denver, Colorado. The job had some unexpected challenges that required on-the-fly solutions.

Track 4: Pipe RammingTrack Leader: Sam Brancheau

4:35 PM ........................................................ MA-T4-03Use of the Pipe Crushing Technique Expedites Removal of ‘Swallowed’ Corrugated Metal Pipe (CMP)Alan Goodmank, HammerHead Trenchless; Jeff Rumer, UITThis presentation details the principles, tooling and technique of the pipe crushing method. It includes a case study in which a contractor uses the system while driving 60-in. steel-wall casings over 48-in. CMP culverts in wet sand.

+ Other

Monday, March 18, 2019 - PM Sessions

Track 2: HDDTrack Leader: Dennis Doherty

3:45 PM ........................................................ MA-T2-01Design-Build Solution for Trenchless Installation of 9,500-ft Long HDD CrossingJwala Sharma, Mears Group Inc; JB Brown, Mears Group Inc; Edward Weirsky, STVThis project describes the challenges during the design phase of a 9,500-ft long Hudson River crossing in New York, New York. The owner of the project has adopted design build approach to construct a bundle of HDPE pipes inside a 24-in. casing.

Track 4: Pipe RammingTrack Leader: Sam Brancheau

3:45 PM ........................................................ MA-T4-01Guided Pipe Ramming at O’Hare Airport Minimizes DisruptionRick Melvin, TT Technologies Inc; Brian Johnson, L.J. Keefe CoO’Hare International Airport is one of the world’s busiest airports, so construction delays must be minimized. The paper will focus on the use of a pilot tube GBM in conjunction with pipe ramming to install casings longer distances and on grade, the challenges encountered, planning and contingency plans required.

4:10 PM ........................................................ MA-T4-02Overcoming Unanticipated Pipe-Ramming Obstructions in Sensitive Ground ConditionsAlan Goodman, HammerHead Trenchless; Don Carter, Kinnan EngineeringThe presentation includes the case study of a 12-in. casing installation project to serve as a utilities conduit beneath a railway using pipe ramming. The operation stopped three times for undisclosed, impenetrable, buried objects. Several solutions were discussed with the project owner.

Track 1: MicrotunnelingTrack Leader: Brenden Tippets

4:10 PM ........................................................ MA-T1-02Proper Fluid Management for Successful InstallationsZachary Maassen, BOS SolutionsProper drilling and tunneling fluid management is crucial to the success of new pipe and shaft installations. With the proper solids control and mud programs in place, new installations can be achieved faster, more efficiently and cheaper than before. Case studies will be presented demonstrating these claims.

Track 2: HDDTrack Leader: Dennis Doherty

4:10 PM ........................................................ MA-T2-02Engineering Judgement in Maximum Bore Pressure DesignJake Andresen, Staheli Trenchless Consultants; Kimberlie Staheli, Staheli Trenchless ConsultantsThe intent of the paper is to serve as a guide for engineering judgment, which is based upon a thorough understanding of the hydrofracture mechanism and sound technical knowledge of hydrofracture prediction methods and their inherent limitations while referencing relevant case studies to that effect.

5:00 PM ........................................................ MA-T2-04Outfall Replacement under San Elijo Lagoon Marine ReserveSarah Williams, Kennedy Jenks Consultants; Mike Konicke, San Elijo Joint Powers AuthorityDesign and construction of a 2,600 lf, 36-in. (OD) HDD beneath an environmentally protected lagoon, railroad tracks and Highway 101 in north coastal San Diego county. Adding to project complexity, the new HDD pipeline connected to an existing ocean outfall pipeline, located 25 ft below the beach surface.

Track 5: CIPPTrack Leader: Bill Moore

5:00 PM ........................................................ MA-T5-04The Mechanical Property Testing and Evaluation for Reinforced CIPP Composite Materials using Glass, Carbon Fibers and Polyester FeltDan Koo, Indiana University - Purdue University; Hyun Wook Ji, Korea Institute of Civil Engineering and Building Technology; Sungsoo Yoo, Korea Institute of Civil Engineering and Building Technology; Jonghoon Kim, Oklahoma State UniversityThis paper presents a summary of mechanical test results and a comparison study of the various composite materials for CIPP rehabilitation.

Water/Wastewater

Monday, March 18, 2019 - PM Sessions

Electrical

Monday, March 18, 2019 - PM Sessions

Track 1: MicrotunnelingTrack Leader: Brenden Tippets

5:00 PM ........................................................ MA-T1-04Randall’s Island Microtunnel Crossing: Managing Risk while Microtunneling in a Dense Urban EnvironmentMaidie Erickson, McMillen Jacobs Associates; Ed Sturm, McMillen Jacobs Associates; Daniel Ebin, McMillen Jacobs Associates; Asif Dunga, McMillen Jacobs AssociatesThe Randall’s Island Microtunnel Crossing consists of two 60-in. diameter, 920 ft long tunnels. Unresolved easement issues, utility conflicts and difficult ground conditions presented challenges during excavation of launch and receiving shafts. This paper discusses lessons learned and focuses on risk mitigation during planning and construction to better alleviate these challenges.

Water

Monday, March 18, 2019 - PM Sessions

Gas

Monday, March 18, 2019 - PM Sessions

9

Track 3: Direct PipeTrack Leader: Jon Robison

4:35 PM ........................................................ MA-T3-03A Case Study on the World-Record Direct Pipe® Method Installation Beneath the Gulf of MexicoNick Michels, Laney Directional Drilling; Julien O’Connell, Herrenknecht AG; Maureen Carlin, Laney Directional DrillingIn December 2017, Laney Direction Drilling set a new world record in length at 5,000 ft for the Direct Pipe® Method. The Direct Pipe® method combines the advantages of microtunneling and HDD technology creating a single pass process that uses a steerable tunnel boring machine cutting head. 5:00 PM ........................................................ MA-T3-0442-in. Direct Pipe Through 227MPa RockKendall Matieshin, Innovative Pipeline Crossings Inc; Peter Hennig, Innovative Pipeline Crossings Inc42-in. Direct Pipe through hard rock, with numerous technical challenges due to significantly harder rock strength than what was anticipated in the geotechnical reports.

Water/Wastewater Water Wastewater Electrical Gas Other

Water/Wastewater Water Wastewater Electrical Gas Other

Track # Track 1 (TM1-T1-01-05)

Track 2 (TM1-T2-01-05)

Track 3 (TM1-T3-01-05)

Track 4 (TM1-T4-01-05)

Track 5 (TM1-T5-01-05)

Track 6(TM1-T6-01-05)

Track Leader Microtunneling Rory Ball

HDDJim Murphy

Condition AssessmentKalyan Piratla

Pipe JackingAlan Atalah

CIPPKaleel Rahaim

Asset Management Condition Assessment

Cathy Morley

8:00 AM Contact Grouting for Microtunneling Pipe: Is it Contact Grouting or Consolidation Grouting?

A New Perspective in Hydro Fracture Evaluation

Advanced Pressure Pipeline

Condition Assessment

ForumThis forum will

provide a discussion of advanced pressure

pipeline condition assessment driven by audience participation.

A Case Study in Corestones - Challenging Pipejack Beneath I-8 in San Diego

Hydraulic Study and Testing of CIPP Lined Water Main Internal Service Reinstatement and Impact on User Flowrate

Minimizing Water Main Digs with Inspection and Corrosion Control

8:25 AM The Expanding Capabilities of Microtunneling Demonstrated in Washington, D.C.

Comparison of Different Inadvertent Return Prediction Methods in Sand Profiles and Testing their Validity with Real World Examples

Removal of Large Concrete Obstruction on 96-in. Pipe Ram Crossing of Highway 61 in Neebing, Ontario

The City of Bend Plant Interceptor - Extending the Life of the City's Primary Means of Wastewater Conveyance

Great Hill Tunnel Rehabilitation: A Comparison of ROV and Manned Inspections of a 1927 Water Tunnel

8:50 AM Five Drives with 26 Curves Built in Zug, Switzerland; Lessons Learned

Mitigating Geologic Risk: Four Large Diameter HDDs Successfully Completed in Karst Terrain

City of Largo, Florida 20-in. Ductile Iron Reclaimed Pipe Inspection Using the LDS1000TM Tool Under a Hard to Reach Canal Crossing

Sioux Falls, South Dakota, I-229 Trenchless Crossing Obstacles Overcome through Teamwork and Perseverance: Or How Did We Miss That?

Carry Drive SE Sanitary Rehabilitation Phase 1 & 2 - CIPP Lining of H2S Damaged Sanitary Main

Binbrook Force Main Cleaning in City of Hamilton, Ontario

9:15 AM Microtunnel Planning for the Browns Valley Trunk in Napa, California

HDD under Pearl Harbor Provides Joint Base Pearl Harbor-Hickam with the New Water Supply Line

A Novel Statistical Approach to Detect Leakages in Water Pipeline Systems

Pipe Jacking in Hard Rock below a Highway Overpass in Montreal, Quebec

Addressing the Shortcomings of a Sampling Strategy in CIPP Quality Assurance Programs

Successful I/I Program Saves $20 Million in Treatment Expansion

9:40 AM Construction of 5,550 lf of 30 and 40-in. Relief Sewer Using Trenchless and Conventional Technologies in Connecticut

12-in. Water Line Horizontal Directional Drill across Hunting Bayou Using the Cartridge Method

Impossible Inspections

Unconventional Methods of Trenchless Pipeline Installation and Replacement Using Conventional Direct Pipe and HDD Equipment

Normandie Sewer - The UV Cured-in-Place Sewer Rehabilitation in the City of Los Angeles

Simple Tool for Operators to Quantify I/I, Detect Leaks & Measure Rehab Progress

Schedule At-A-Glance: Tuesday AM, 1st Session

Technical Paper Sessions Schedule AM Sessions - 1st Session Track 1: 8:00 AM – 10:05 AM - Room 14Track 2: 8:00 AM – 10:05 AM - Room 12Track 3: 8:00 AM – 10:05 AM - Room 1Track 4: 8:00 AM – 10:05 AM - Room 2Track 5: 8:00 AM – 10:05 AM - Room 3Track 6: 8:00 AM – 10:05 AM - Room 4

AM Sessions - 2nd SessionTrack 1: 10:20 AM – 12:00 PM - Room 14Track 2: 10:20 AM – 12:00 PM - Room 12Track 3: 10:20 AM – 12:00 PM - Room 1Track 4: 10:20 AM – 12:00 PM - Room 2Track 5: 10:20 AM – 12:00 PM - Room 3Track 6: 10:20 AM – 12:00 PM - Room 4

PM Sessions Track 1: 3:30 PM – 5:35 PM - Room 14Track 2: 3:30 PM – 5:35 PM - Room 12Track 3: 3:30 PM – 5:35 PM - Room 1Track 4: 3:30 PM – 5:35 PM - Room 2Track 5: 3:30 PM – 5:35 PM - Room 3Track 6: 3:30 PM – 5:35 PM - Room 4

10

Plan your experience!Tuesday, March 19, 2019

NASTT’s

NO-DIG SHOW2

019

March 17-21, 2019 | Chicago, Illinois

Advanced Pressure Pipeline Condition Assessment Forum8:00 AMTM1-T3-01 and TM1-T3-02 Track Leader: Joe Lane Room 5

This forum will provide a discussion of advanced pressure pipeline condition assessment driven by audience participation.

Innovative Products10:20 AMTM2-T3-01 and TM2-T3-02 Track Leader: Cindy Preuss Room 1

Join us for a showcase of innovative product releases in the trenchless industry. Companies presenting products are this year’s innovative product award finalists.

Tuesday EventsAttendee & Exhibitor Registration7:00 AM – 5:00 PM - Lobby

Exhibit Hall Open 12:00 AM – 3:30 PM - Hall A

Pre-Gala Awards Dinner Reception6:00 PM – 7:00 PM - Room 21-24

Gala Awards Dinner (a ticket event)7:00 PM – 10:00 PM - Room 21-24

11

Wastewater

Tuesday, March 19, 2019 - AM, 1st Session

Track 1: MicrotunnelingTrack Leader: Rory Ball

8:25 AM .......................................................TM1-T1-02The Expanding Capabilities of Microtunneling Demonstrated in Washington, D.C.Todd Brown, Bradshaw Construction CorporationThe Oregon Avenue NW Sewer Rehabilitation project in Washington, D.C., consisted of 4,300 ft of 24-in sewer to eliminate pipelines through Rock Creek Park. 2,700 ft of the new sewers were installed by microtunneling, include a single 1,860-ft long drive and a 430-ft long drive with a 625-ft radius S-Curve.

8:50 AM .......................................................TM1-T1-03Five Drives with 26 Curves Built in Zug, Switzerland; Lessons LearnedMarc Reinhard, Go Bau AGFive drives were built in the city of Zug, Switzerland, with eight vertical and 18 horizontal curves. This paper discusses the lessons learned through designing and executing. Risk management, rolling planning, ensuring the required quality, cost monitoring and cost forecast, time schedule and technical challenges are the main points.

9:15 AM .......................................................TM1-T1-04Microtunnel Planning for the Browns Valley Trunk in Napa, CaliforniaDru Nielson, McMillen Jacobs Associates; Justin Reeves, McMillen Jacobs Associates; Robin Gamble Holley, Napa Sanitation DistrictFindings from geotechnical research and exploration documents faults, high groundwater, variable ground conditions, potential obstructions (battered piles), and

Water/Wastewater Water Wastewater Electrical Gas Other

Track # Track 1 (TM2-T1-01-04)

Track 2 (TM2-T2-01-04)

Track 3 (TM2-T3-01-04)

Track 4 (TM2-T4-01-04)

Track 5 (TM2-T5-01-04)

Track 6(TM2-T6-01-04)

Track Leader Project Planning & Delivery

Dave Haug

HDD & Geotechnical Issues

Carrie Layhee

Innovative ProductsCindy Preuss

Project Planning & Delivery & Condition

AssessmentWill Craven

SlipliningDavid Crowder

Watermain Rehabilitation Joanne Carroll

10:20 AM Horizontal Bends in Horizontal Directional Drilling

Predicting the Saturated Hydraulic Conductivity of Natural Soil

Innovative Products

Join us for a show-case of innovative product releases in the trenchless

industry. Companies presenting products

are this year’s innova-tive product award

finalists.

What Happens After the Installation Is a Success?

Interceptor Lining in Lima, Ohio, Using SPR PE

30-in. Water Main Rehabilitation in Pringle Creek

10:45 AM Curved Microtunneling Alignments in the Design Toolbox

Assessment of Soil and Bedrock Abrasivity for Horizontal Directional Drilling Projects

Selection Process Challenges: Force Main Study Considers Variety of Trenchless Technologies and Corresponding Stakeholder Impacts

PS 30-31 Rehabilitation - Sliplining Sanitary Sewer Force Main

City of Taylor Embraces Pre-Chlorinated Pipe Bursting and Directional Drilling

11:10 AM Tunneling in the Shadow of Camden Yards

Horizontal Directional Drilling - Guidance Types, Accuracy and Safety

Non-Destructive Testing Options for Asbestos Cement Pipes

Sliplining of the Gaillard Water Treatment Plant Raw Water Pipeline

When Capital Improvement Plans Align: How Moorhead Public Service Collaborates with the City of Moorhead for Effective Water Main Replacement

11:35 AM Rationalization and Implementation of an Upgrading Approach for the Northeast Interceptor in Winnipeg, Manitoba

Westport's Pump Station No. 2 Force Main Replacement Project Using HDD

Assessment and Remediation of Gas Utility Tunnels in Chicago

Rehabilitation of Various Trunk Sewers in City of Toronto

Protecting a National Treasure: Rehabilitation of 20-in. Water Main Under a Bridge Feeding Fort William McHenry Baltimore, Maryland

Schedule At-A-Glance: Tuesday AM, 2nd Session

(66-in.) hard rock boring machine known as a Rockhead Gripper Shield to excavate the first-ever pipe jacking tunnel in rock below Montreal for the Contract A-335-4 Project, a wastewater pipeline.

Track 5: CIPPTrack Leader: Kaleel Rahaim

8:25 AM .......................................................TM1-T5-02The City of Bend Plant Interceptor - Extending the Life of the City’s Primary Means of Wastewater ConveyanceRobert Lee, Murraysmith; Jason Suhr, City of BendThis paper will focus on the condition assessment and rehabilitation of the City of Bend’s Plant Interceptor. Condition assessment of the 20,000 lf 36-in. and 42-in. pipe utilized digital scanning, sonar and laser. Rehabilitation utilized cured-in-place pipe, allowing both thermal and UV-curing methods. 

8:50 AM .......................................................TM1-T5-03Carry Drive SE Sanitary Rehabilitation Phase 1 & 2 - CIPP Lining of H2S Damaged Sanitary MainJordan Quick, ISL Engineering and Land Services Ltd; Garnet Dawes, ISL Engineering and Land Services Ltd; Kimberley Kimball, ISL Engineering and Land Services LtdFrom design to implementation, our presentation will focus on the challenges we faced and solutions we implemented throughout the project.

9:15 AM .......................................................TM1-T5-04Addressing the Shortcomings of a Sampling Strategy in CIPP Quality Assurance ProgramsTony Araujo, Paragon Systems TestingMany QA programs specify random sampling of field-installed CIPP samples to ensure that sewer rehabilitation installations comply with the owner’s specifications. This paper identifies the shortcomings of this approach and describes the experience of the City of Toronto in implementing a comprehensive quality control approach to CIPP installations.

historically filled and rerouted drainageways along a planned 15,600-ft trunk sewer to be designed and constructed in part by microtunneling under Caltrans State Route 29 and congested traffic corridors in Napa, California.

9:40 AM .......................................................TM1-T1-05Construction of 5,550 lf of 30 and 40-in. Relief Sewer Using Trenchless and Conventional Technologies in ConnecticutJohn Ososkie, Jacobs Engineering Group; Jason Waterbury, Metropolitan District Commission; Eric Muir, Jacobs Engineering GroupMDC and Jacobs prepared this paper to describe challenges overcome during sewer construction and the tunneling technologies implemented to achieve project success. The project includes various tunneling and open-cut excavation techniques, river crossings, permitting and traffic control considerations. Tunneling equipment selection significantly reduced construction risks throughout the project.

Track 4: Pipe JackingTrack Leader: Alan Atalah

8:50 AM .......................................................TM1-T4-03Sioux Falls, South Dakota, I-229 Trenchless Crossing Obstacles Overcome through Teamwork and Perseverance: Or How Did We Miss That?Michelle Carter, HDR; Dustin Posten, City of Sioux Falls; Dave Bennett, Bennett Trenchless EngineersDespite a thorough geotechnical investigation, unpleasant surprises were encountered. The City, South Dakota DOT, the design team and the contractor worked together to overcome difficulties and complete the project without litigation.

9:15 AM .......................................................TM1-T4-04Pipe Jacking in Hard Rock below a Highway Overpass in Montreal, QuebecTom Fuerst, The Robbins Company; Gill Tardif, Nella Drilling IncContractor Nella Drilling is utilizing a small diameter

1211:35 AM .....................................................TM2-T1-04Rationalization and Implementation of an Upgrading Approach for the Northeast Interceptor in Winnipeg, ManitobaAdam Braun, AECOM; Christopher Macey, AECOM; Kas Zurek, City of Winnipeg; Stacy Cournoyer, City of Winnipeg; Mike Gaudreau, AECOM The North End Water Pollution Control Centre (NEWPCC) handles more than 65 percent of the daily wastewater load for a city of 780,000. The Northeast Interceptor is one of three key Interceptors that service the NEWPCC and has a critical river crossing immediately upstream of the plant that needed to be upgraded.

Track 2: HDD & Geotechnical IssuesTrack Leader: Carrie Layhee

11:35 AM .....................................................TM2-T2-04Westport’s Pump Station No. 2 Force Main Replacement Project Using HDDBryan Thompson, Town of Westport; Abhinav Huli, Haley & Aldrich Inc; Lori Carriero, Tighe & BondThis presentation will discuss the challenges encountered when directional drilling a new force main underneath a tidal river in Westport, Connecticut. Technical challenges included accessing/evaluating subsurface conditions in a tidal river and designing a drill entirely in hard and abrasive work. Numerous permits were also required.

Track 4: Project Planning & Delivery & Condition AssessmentTrack Leader: Will Craven

10:45 AM .....................................................TM2-T4-02Selection Process Challenges: Force Main Study Considers Variety of Trenchless Technologies and Corresponding Stakeholder ImpactsWilliam Gibson, AECOM; Katherine Linares, Hampton Roads Sanitation District; Christopher Macey, AECOMThis paper will detail a case study in which the conditions were unusually opportunistic to evaluate a variety of trenchless technologies available to rehabilitate a critical 48-in., 1970s-era PCCP force main, or conversely, construct a parallel 42-in. HDD. The paper will detail the evaluation approach, findings, recommendations and selected alternative.

Track 5: SlipliningTrack Leader: David Crowder

11:35 AM .....................................................TM2-T5-04Rehabilitation of Various Trunk Sewers in City of TorontoPrapan Dave, City of Toronto; Laurel Murphy Jacobs, Joe Vera Southland; Renda Brian Ratchford, Capital Sewer ServicesThe City of Toronto is rehabilitation approximately 50 km of various trunk sewers in next 10 years. The City has successfully completed a few projects using sliplining and CIPP techniques. The paper will showcase successful projects, rehabilitation technique selection, challenges faced, successes and lessons learned.

Track 3: Condition AssessmentTrack Leader: Kalyan Piratla

8:50 AM .......................................................TM1-T3-03City of Largo, Florida 20-in. Ductile Iron Reclaimed Pipe Inspection Using the LDS1000TM Tool Under a Hard to Reach Canal CrossingEdward Alan Ambler, AM Trenchless; Piero Salvo, GAME Consultants; Weston Hagen, Reiss Engineering; David Black, City of LargoFlorida worked with Reiss Engineering, AM Trenchless and GAME Consultants to successfully inspect a 20-in. ductile iron reclaimed water main through five 45-degree bends under a hard to reach canal crossing. No evidence of leaks was observed and the City developed detailed protocol for future successful inspections.

Track 4: Pipe JackingTrack Leader: Alan Atalah

8:25 AM .......................................................TM1-T4-02Removal of Large Concrete Obstruction on 96-in. Pipe Ram Crossing of Highway 61 in Neebing, OntarioJames Carroll, MarshWagner; Travis Krag, LTL Drilling; Connor Beck, LTL Directional Drilling; Spencer Shand, Coogar Sales and ServiesThis paper will discuss the use of a non-detonating explosive to remove an abandoned bridge abutment encountered during a 96-in. pipe ramming under an active highway. Team work with the owner, contractor and engineer ensured safety of the traveling public and ability to complete ramming operations after weeks of delay.

Wastewater

Tuesday, March 19, 2019 - AM, 2nd Session Water/Wastewater

Tuesday, March 19, 2019 - AM, 1st Session

Water/Wastewater

Tuesday, March 19, 2019 - AM, 2nd Session

9:40 AM .......................................................TM1-T5-05Normandie Sewer - The UV Cured-in-Place Sewer Rehabilitation in the City of Los Angeles Sylvester Kueh, City of Los Angeles; Kent Welling, City of Los AngelesRehabilitation of a major sewer using an UV cured-in place liner technology. The 30-in. to 39-in. brick and concrete sewer was put in service in 1915 and had deteriorated, resulting in two sinkholes. Replacement and other methods of rehabilitation were considered but proved to be more expensive.

Track 6: Asset Management & Condition AssessmentTrack Leader: Cathy Morley

8:50 AM .......................................................TM1-T6-03Binbrook Force Main Cleaning in City of Hamilton, OntarioErika McEachran, Stantec Consulting Ltd; Gerald Bauer, Stantec Consulting Ltd; Dave Alberton, Hamilton Water; Donald Young, Hamilton Water Hamilton Water retained Stantec to develop a plan to clean the Binbrook Wastewater Pumping Station force main to meet development agreements. The mandate was to restore pumping capacity. Stantec created a flexible cleaning program utilizing available trenchless technology. This paper focuses on the lessons learned when instituting a force main maintenance program.

9:15 AM .......................................................TM1-T6-04Successful I/I Program Saves $20 Million in Treatment ExpansionRobert Lee, Murraysmith; Greg Springman, City of Sweet Home; Preston Van Meter, MurraysmithThe City of Sweet Home, Oregon, has embarked on a successful I/I abatement program that has reduced peak flows to its WWTP by more than 50 percent. This program has resulted in significant savings in conveyance upgrades and WWTP expansion, proving that I/I reduction can be the most cost-effective approach.

9:40 AM .......................................................TM1-T6-05Simple Tool for Operators to Quantify I/I, Detect Leaks & Measure Rehab ProgressGeorge Kurz, Sewer Capacity ManagementThis paper describes a simple, non-proprietary spreadsheet tool for measuring annual I/I and peak RDI/I using data already collected by wastewater treatment facility operators for EPA compliance. This system is more effective and has a broader application than the most recent method recommended by the US-EPA.

Track 1: Project Planning & DeliveryTrack Leader: Dave Haug

10:45 AM .....................................................TM2-T1-02Curved Microtunneling Alignments in the Design ToolboxDavid Mast, AECOM Technologies Inc; Patrick Dodds, AECOM Technologies Inc; Alison Schreiber, Northeast Ohio Regional Sewer District; Frederick Vincent, Northeast Ohio Regional Sewer District; Robin Dill, AECOM Technologies Inc; Paul Nicholas, AECOM Technologies IncNEORSD and AECOM successfully completed a complex combined sewer control design by taking full advantage of curved microtunneling alignments and providing flexibility to bidders. This paper will highlight the successful optimization of the project design and reasons for including the owner’s first designed curved microtunnel alignment in the bid documents.

Track 2: HDD & Geotechnical IssuesTrack Leader: Carrie Layhee

10:20 AM .....................................................TM2-T2-01Predicting the Saturated Hydraulic Conductivity of Natural SoilChi Hyun Park, McMillen Jacobs Associates; Charles Huse, Northeast Ohio Regional Sewer DistrictThe main goal of this paper is to present available methods in estimating hydraulic conductivity of saturated soils using geotechnical parameters in tunnel design and demonstrate their applicability to recent tunnel projects. This paper will examine the procedure and reliability of predicting the saturated hydraulic conductivity of natural soils. 

Track 4: Project Planning & Delivery & Condition AssessmentTrack Leader: Will Craven

11:10 AM .....................................................TM2-T4-03Non-Destructive Testing Options for Asbestos Cement PipesLisa Douglas, Ace Pipe Cleaning Inc; Mark Wade, Ace Pipe Cleaning Inc; Dallas McCready, Inversa Systems

Track 1: Project Planning & DeliveryTrack Leader: Dave Haug

11:10 AM .....................................................TM2-T1-03Tunneling in the Shadow of Camden YardsJoe Schrank, McMillian Jacobs Associates; Justin Kirk, Clark Construction; Todd Brown, Bradshaw Construction Company; Brandon Knapp, CSX Transportation; Matt Over, McMillen Jacobs Associates The design-build team perspective from the initial feasibility to project completion for the CSX Camden Street Storm Drain Replacement Project will be presented with a focus on the major project challenges and the development of a buildable solution that successfully managed the major risks for construction of three short tunnels.

Track 1: MicrotunnelingTrack Leader: Rory Ball

8:00 AM .......................................................TM1-T1-01Contact Grouting for Microtunneling Pipe: Is it Contact Grouting or Consolidation Grouting?Gregory Raines, Stantec; Nick Goodenow, Stantec; Adam Bedell, StantecThis paper is to address the issues with specified contact grouting of microtunneling pipe, which the authors believe to be misused in its need, application and payment.

Water/Wastewater Water Wastewater Electrical Gas Other

13Fifteen to 25 percent of water mains are asbestos cement (ACP). Asbestos was used until 1980s when it was eliminated due to health concerns. Utilities are faced with managing this aging infrastructure. Until now, there has not been reliable technologies for non-destructive testing for condition assessment. This presentation will present the non-destructive testing technology, Backscatter Computed Tomography (BCT).

Track 5: SlipliningTrack Leader: David Crowder

10:20 AM .....................................................TM2-T5-01Interceptor Lining in Lima, Ohio, Using SPR PEHugh Mickel, Contech Engineered Solutions LLCThis project involves lining more than 2,500 lf of varying diameter, combined sewers originally constructed with hand-laid tiles to form round pipes. Had open-cut construction methods been utilized, the detours would have been short, however, the frequency of traffic control changes was undesirable. Trenchless options provided significant benefits to the public.

10:45 AM .....................................................TM2-T5-02PS 30-31 Rehabilitation - Sliplining Sanitary Sewer Force MainJohn Rescober, Anchorage Water and Wastewater UtilityPS31 was upgraded since it is reaching the end of its useful life, including pumps, piping, electrical equipment, SCADA; sliplining 16,000 lf of HDPE pipe and PVC pipe within dual 16-in. DIP host pipes through wetlands, marshes and ADOT ROW to PS30 where successive sewer pumping is removed.

Track 6: Watermain RehabilitationTrack Leader: Joanne Carroll

11:35 AM .....................................................TM2-T6-04Protecting a National Treasure: Rehabilitation of 20-in. Water Main Under a Bridge Feeding Fort William McHenry Baltimore, Maryland John Moody Primus Line Inc.; Chris Billak Spiniello CoThis paper will discuss the rehabilitation of a 20-in. water main located on the underside of the East Forte Avenue bridge. A 650-ft long steel pipe was out of service because it was leaking onto the CSX railway tracks below. It needed to be replaced or renovated and 100 percent leak proof.

horizontal directional drilling methods. Because the pipe string could not be laid out without blocking a street intersection, the cartridge method was used with Certa-Lok(R) PVC pipe. The installation was successfully completed in May 2018.

Track 3: Condition AssessmentTrack Leader: Kalyan Piratla

9:15 AM .......................................................TM1-T3-04A Novel Statistical Approach to Detect Leakages in Water Pipeline SystemsHarshit Shukla, Clemson University; Kalyan Piratla, Clemson UniversityThis paper describes a novel statistical model to predict leak location and size in water pipeline systems using continuous pipeline vibration/acceleration data from multiple locations. This paper presents the model and demonstrates it using a small-scale pipeline test bed.

9:40 AM .......................................................TM1-T3-05Impossible InspectionsBill Sherwood, ASI GroupLong water conveyance tunnels, particularly wastewater systems, can be very difficult to inspect remotely due to restricted access, distance, bends and the presence of fouling material. Advances in robotics technologies have started to make possible what was formerly not so. These will be discussed in reference to specific inspection projects.

Track 4: Pipe JackingTrack Leader: Alan Atalah

8:00 AM .......................................................TM1-T4-01A Case Study in Corestones - Challenging Pipejack Beneath I-8 in San DiegoMatthew Wallin, Bennett Trenchless Engineers; Mark Niemiec, Padre Dam Municipal Water District; Michael Hindle, Padre Dam Municipal Water District; John Harris, Michael Baker InternationalThis paper discusses challenges faced on a new waterline installed beneath Interstate 8 near San Diego, California. The crossing was constructed in weak granodiorite rock that was known to contain much harder corestone material. The paper will focus on design features and construction challenges handled during pipejacking of the crossing.

Track 5: CIPPTrack Leader: Kaleel Rahaim

8:00 AM .......................................................TM1-T5-01Hydraulic Study and Testing of CIPP Lined Water Main Internal Service Reinstatement and Impact on User FlowrateJaasiel Villanueva, Corrpro; Richard Baxter, Insituform; George Bontus, AegionCIPP service connection hydraulic analysis of mechanical attachment in existing connection. Physical testing and FEA analysis performed to observe the effects on the flow to the customer. 

Track 6: Asset Management & Condition AssessmentTrack Leader: Cathy Morley

8:00 AM .......................................................TM1-T6-01Minimizing Water Main Digs with Inspection and Corrosion ControlRoy Brander, The City of Calgary; Joanna Line, The City of CalgaryCalgary, Canada, was able to reduce water main replacement by 75 percent, while simultaneously reducing water main breaks by 65 percent, over 20 years from 1998-2018. The strategy used electromagnetic inspections to precisely select replacement candidates and to target corrosion control with sacrificial anodes installed by vacuum excavation.

8:25 AM .......................................................TM1-T6-02Great Hill Tunnel Rehabilitation: A Comparison of ROV and Manned Inspections of a 1927 Water TunnelBrian Lakin, McMillen Jacobs Associates; Joe Schrank, McMillen

Water

Tuesday, March 19, 2019 - AM, 1st Session

Jacobs Associates; Daniel Ebin, McMillen Jacobs Associates; Lawrence Marcik, South Central Connecticut Regional Water AuthorityRegular inspection of water infrastructure, especially manned, is often challenging because of lack of redundancy, limited shutdown windows or aging infrastructure that could be compromised by dewatering. This paper compares differences in ROV vs. manned inspection results of the Great Hill Tunnel and how they are applied to tunnel rehabilitation.

Water

Tuesday, March 19, 2019 - AM, 2nd Session

Track 5: SlipliningTrack Leader: David Crowder

11:10 AM .....................................................TM2-T5-03Sliplining of the Gaillard Water Treatment Plant Raw Water PipelineNoel Guercio, Stantec Consulting Services Inc; Benjamin Baker, Stantec Consulting Services Inc; Erez Allouche, Stantec Consulting Services IncA 2,700-ft raw water tunnel and a 1,000-ft cast iron pipeline connect Lake Gaillard to Gaillard Water Treatment Plant. Recent inspections of the tunnel and pipeline revealed defects in the tunnel liner and pipeline. This paper focuses on the rehabilitation design and construction of the pipeline repair.

Track 5: Watermain RehabilitationTrack Leader: Joanne Carroll

10:20 AM .....................................................TM2-T6-0130-in. Water Main Rehabilitation in Pringle CreekBrendan O’Sullivan, Murraysmith; Micheal Linn, City of SalemThe City of Salem, Oregon, recently completed the rehabilitation and replacement of a critical water main. The approximately 560 ft section of 30-in. diameter welded steel 1947 pipe, with 200 ft located in Pringle Creek and under a 100-ft wide railroad bridge, was rehabilitated utilizing CIPP and the open-cut construction method.

10:45 AM .....................................................TM2-T6-02City of Taylor Embraces Pre-Chlorinated Pipe Bursting and Directional DrillingKelly McRobb-Ackland, Wade TrimThe intent of this paper is to highlight the proactive approach The City of Taylor, Michigan, used to address the aging water infrastructure through an efficient, minimally disruptive and cost-effective methodology.

11:10 AM .....................................................TM2-T6-03When Capital Improvement Plans Align: How Moorhead Public Service Collaborates with the City of Moorhead for Effective Water Main ReplacementKristofer Knutson, Moorhead Public Service; Jade Berube, Apex Engineering Group; June Baterina, Underground Solutions IncMoorhead Public Service (MPS) in Minnesota has employed various trenchless technologies as part of its water main asset management program. To reduce the cost of patching the disturbed portions of pavement associated with insertion pits, tie-ins and service connections, MPS uniquely coordinates with the City’s surface rehabilitation projects.

Track 2: HDDTrack Leader: Jim Murphy

9:15 AM .......................................................TM1-T2-04HDD under Pearl Harbor Provides Joint Base Pearl Harbor-Hickam with the New Water Supply LineDevin Nakayama Yogi, Kwong Engineers; Richard Botteicher, Underground Solutions; Andrew Amuro, Fukunaga & Associates Inc JBPHH needed a new water supply line across Pearl Harbor in order to meet its potable water and life safety requirements. The project included 3,500 ft of water line via steel encased HDD method from Ford Island to Landing C of JBPHH through extremely soft soil with structurally unstable sediments.

9:40 AM .......................................................TM1-T2-0512-in. Water Line Horizontal Directional Drill across Hunting Bayou Using the Cartridge MethodChristine Kirby, Lockwood, Andrews & Newnam Inc; Venus Price, City of Houston Public Works; Eric Hernandez Lockwood, Andrews & Newnam IncA 12-in. water line along IH-10 East Freeway in Houston was installed across Hunting Bayou using

Water/Wastewater Water Wastewater Electrical Gas Other

Networking EventGala Awards Dinner*Tuesday, March 19, 2019 - 7:00 PM – 10:00 PM - Room 21-24You are cordially invited to attend the trenchless industry’s premiere awards dinner! Join leaders and colleagues from across the industry while we honor those who have accomplished outstanding achieve-ments in their respective fields. NASTT will present and recognize its Hall of Fame Class of 2019, as well as the Chair’s Award for Outstand-ing Lifetime Service, the Ralston Award for Young Trenchless Achieve-ment and the Abbott Awards for Innovative Products & Services.

*NASTT’s 2019 No-Dig Show Gala Awards Dinner is a ticketed event.

14

Track 4: Project Planning & Delivery & Condition AssessmentTrack Leader: Will Craven

11:35 AM .....................................................TM2-T4-04Assessment and Remediation of Gas Utility Tunnels in ChicagoAswathy Sivaram, Black & Veatch; Chad Gailey, Black & Veatch; Cary Hirner, Black & VeatchTunnel and Pipeline Remediation Program - includes assessment, inspection and potential remediation of these tunnels and associated pipelines.

Gas

Tuesday, March 19, 2019 - AM, 2nd Session

Gas

Tuesday, March 19, 2019 - AM, 1st Session

Track 2: HDDTrack Leader: Jim Murphy

8:50 AM .......................................................TM1-T2-03Mitigating Geologic Risk: Four Large Diameter HDDs Successfully Completed in Karst TerrainGary Castleberry, GeoEngineers Inc; Paul Mitchell, Enbridge IncThis paper describes how four HDDs along a 36-in. pipeline route were completed in highly developed karst terrain. The paper will cover front-end engineering requirements, geotechnical and geophysical investigations and design recommendations, pipeline integrity studies and construction methodologies critical to the pipeline’s success and applicable to future projects.

+ Other

Tuesday, March 19, 2019 - AM, 1st Session

In this paper, realized annular pressure data during construction has been accumulated and reviewed to determine the accuracy of the fluid pressure prediction model in various case studies. Additionally, using the same data, pressure magnitude of actual hydraulic fracture occurrences have been recorded and compared with the prediction.

8:25 AM .......................................................TM1-T2-02Comparison of Different Inadvertent Return Prediction Methods in Sand Profiles and Testing their Validity with Real World ExamplesDavid Landing, Jacobs Engineering; Timothy Schnell, Jacobs EngineeringThis presentation presents results from various case studies for HDDs within sand geologic profiles. The case studies are compared to an assortment of HDD inadvertent return/frac-out prediction methods to give an in-depth account as to each methodologies validity in estimating confining pressures as compared to real world examples.

Track 4: Pipe JackingTrack Leader: Alan Atalah

9:40 AM .......................................................TM1-T4-05Unconventional Methods of Trenchless Pipeline Installation and Replacement Using Conventional Direct Pipe and HDD EquipmentJwala Sharma, Mears Group Inc; Jim Williams, Brierley Associates; JB Brown, Mears Group IncThis paper discusses how unique methodology of using conventional HDD and Direct Pipe thruster can be used to solve unique problems with some examples of successes and failures in projects over last couple of years. Additionally, some potential applications will be discussed.

best practices in borepath design and the effect on pullback forces when a horizontal bend is added to a crossing, particularly for larger diameter HDDs. 

Track 6: HDD & Geotechnical IssuesTrack Leader: Carrie Layhee

10:45 AM .....................................................TM2-T2-02Assessment of Soil and Bedrock Abrasivity for Horizontal Directional Drilling ProjectsNicholas Strater, Brierley Associates; Danny Crumpton, Inrock; Brian Dorwart, Brierley Associates; Jim Williams, Brierley AssociatesThe paper will summarize the impacts of abrasive ground conditions and typical soil and bedrock formations that may prove abrasive. An abrasivity scale will be presented for use in project planning, design and construction assessments.

11:10 AM .....................................................TM2-T2-03Horizontal Directional Drilling - Guidance Types, Accuracy and SafetyDave Dupuis, CCI; Justin Taylor, CCI; Don Chaddock, Horizontal TechnologyGuidance and tracking technology for horizontal directional drills has come a long way since the infancy of the industry. This paper will review the primary methods of guidance that have been developed over the past few decades, and highlight their differences, abilities and limitations.

Track 6: Project Planning & Delivery & Condition AssessmentTrack Leader: Will Craven

10:20 AM .....................................................TM2-T4-01What Happens After the Installation Is a Success?Brian Avon, Carollo Engineers; Josh Hampton, PG&EIn many cases, owners do not have a full understanding of trenchless technology and its application, whereas consultants may not understand the owner’s long term maintenance issues. This paper focuses on the aspects of a project and the installed assets owners and consultants must consider.

+ Other

Tuesday, March 19, 2019 - AM, 2nd Session

Track 2: HDDTrack Leader: Jim Murphy

8:00 AM .......................................................TM1-T2-01A New Perspective in Hydro Fracture EvaluationStefan Goerz, CCI Inc; Nicolas Boelhower, CCI Inc; Justin Taylor, CCI Inc

Track 6: Project Planning & DeliveryTrack Leader: Dave Haug

10:20 AM .....................................................TM2-T1-01Horizontal Bends in Horizontal Directional DrillingDiana Worthen, JacobsThis paper presents a discussion on horizontal bends in horizontal directional drilling installations. It addresses

Water/Wastewater Water Wastewater Electrical Gas Other

15

Water/Wastewater Water Wastewater Electrical Gas Other

Track # Track 1 (TA-T1-01-05)

Track 2 (TA-T2-01-05)

Track 3 (TA-T3-01-05)

Track 4 (TA-T4-01-05)

Track 5 (TA-T5-01-05)

Track 6(TA-T6-01-05)

Track Leader Pilot Tube Mohammad Najafi

HDDRachel Maupin

Condition Assessment & Asset Management

Jonathan Kunay

Research & Emerging Technologies

Brenda Kingsmill

SlipliningGeorge Regula

Wastewater Pipeline Re-habilitation: Geopolyner

Marc Lehmann

3:30 PM Unique Horizontal Drain Installation Under a Building Using Pilot Tube Guided Auger Bore Methods

The Environmentally Sensitive Boca Ciega Bay 4200-ft Force Main Replacement: Taming HDD Technology

Frontera Lift Station Force Main Condition Assessment

Conducting the ASTM D2992 - Challenges and Concerns

Emergency Repair and Lining of the PCI-12A Interceptor in Macomb County, Michigan

Fixing a 19th Century Sewer with a 21st Century Solution: A Case Study for Geopolymer Sanitary Sewer Rehabilitation

3:55 PM Guided Auger Boring Resolves Everyday Utility Installation Challenges at the O'Hare International Airport

Improved Magnetic Navigation for Horizontal Directional Drilling Using a Down-Hole Rotating Rare Earth Magnet Implementation.

Burnsville Minnesota Validates Estimates of Remaining Water Main Pipe Wall Thickness Gathered Using an Acoustic Velocity Testing Tool

Practical Criteria for Borehole Instability in Multi-Layer Soil Systems During Horizontal Directional Drilling

HDD...Wait, No...Slipline!

DC Water New Jersey B Street 10- to 18-Ft Diameter Trunk Sewer Rehabilitation During Live Dry Weather Flow

4:20 PM Trenchless Technologies Used in Flood Prevention Schemes Project in Doha, Qatar

Soil Mechanics and Calculating Hydraulic Fracture Risk

Cast Iron Pipe Condition Assessment - Service Measured by Centuries

Living Labs Validation of Trenchless Technical Solution in Real World Applications

Rehabilitation of the Barton Street Horseshoe-Shaped Combined Sewer in Hamilton, Ontario

Challenges Encountered During Rehabilitation of a Trunk Sewer Using Sprayed Geopolymer

4:45 PM Tunnel Design and Construction in Soft, Wet Ground

Pit-Launched HDD Proves Useful for WaterOne out of Lenexa Kansas

The Use of Innovative Inspection Technologies to Assess and Prioritize Rehabilitation for Water Pipeline Infrastructure

Demonstration of a Prototype System for the Automated Interpretation of Sewer CCTV Inspection Videos

Sliplining 120-In. RCP Wastewater in Dallas, Texas

Narragansett Bay Commission Rehabilitation of Large Diameter Brick Sewer with GeoSpray Geopolymer Mortar

5:10 PM Installation of New Culverts for Vermont Transportation Agency Using Two Pipe Ramming Methods

Multiple Trenchless Methods Allow for Water Supply Installation through Wyoming Terrain

Managing Linear Assets Beyond Their Original Design Life Case Study - City of DeSoto, Kansas Raw Water Transmission Main

Practical Application of a Sewer Pipe Rehabilitation Planning Framework

Denver Water Turns to Sliplining to Renew Century-Old Transmission Main

Urgent Storm Pipe Rehabilitation as a Result of Lingering Effects and Damage Caused By Hurricane Harvey

Schedule At-A-Glance: Tuesday PM Sessions

Track 1: Pilot TubeTrack Leader: Mohammad Najafi

4:45 PM ..........................................................TA-T1-04Tunnel Design and Construction in Soft, Wet GroundRyan Marsters, Lithos Engineering; John Beckos, BTrenchless IncThis paper will discuss a 375-ft tunnel that was built under four railroad tracks and highway I-15 consisting of 30-in. carrier pipe within 48-in. steel casing in Kaysville, Utah. Ground conditions were soft, wet clay, silt and sand deposited in a lake environment. Pilot tube auger boring with a hammer backup was the final installation method.

5:10 PM ..........................................................TA-T1-05Installation of New Culverts for Vermont Transportation Agency Using Two Pipe Ramming MethodsAlan Goodman, HammerHead Trenchless; Tom Loyer, Engineers Construction IncA contractor completed a design-build culvert project for Vermont Transportation Agency (VTrans), requiring three new 72-in. culverts to relieve ponding after large precipitation events along a section of railway bed. The contractor conducted a variety of ground stabilization and pipe installation techniques, including the pilot tube method.

Wastewater

Tuesday, March 19, 2019 - PM

Track 2: HDDTrack Leader: Rachel Maupin

3:30 PM ..........................................................TA-T2-01The Environmentally Sensitive Boca Ciega Bay 4200-ft Force Main Replacement: Taming HDD TechnologyFrancisco Bohorquez, AECOM; David Wilcox, AECOM; Mathew Francis, AECOM; Dennis Simpson, Pinellas County; Dinesh Kamath, Pinellas CountyThe 40-plus-year-old, 24-in. PCCP force main, direct buried across the protected and sensitive Boca Ciega Bay, conveyed wastewater from a high density beach area. Its aging condition posed an unacceptable risk to Pinellas County, which AECOM to evaluate alternatives, design and support construction of the replacement pipeline.

Track 3: Condition Assessment & Asset ManagementTrack Leader: Jonathan Kunay

3:30 PM ..........................................................TA-T3-01 Frontera Lift Station Force Main Condition AssessmentMarco Trujillo, Jacobs; Ivan Hernandez, El Paso Water UtilitiesCondition assessment of 3.5 miles of steel dual force mains that convey approximately 10 mgd and increase in size from 30-, 36- to 42-in. in diameter along its alignment.

Track 4: Research & Emerging TechnologiesTrack Leader: Brenda Kingsmill

4:45 PM ..........................................................TA-T4-04Demonstration of a Prototype System for the Automated Interpretation of Sewer CCTV Inspection Videos

Srinath Kumar, Purdue University; Dulcy Abraham, Purdue University; Tom Iseley, Trenchless Technology Center; Mohammad Jahanshahi, Purdue UniversityThis paper describes the development of a prototype system for the automated detection of defects (root intrusions and deposits) in sewer CCTV inspection videos.

5:10 PM ..........................................................TA-T4-05Practical Application of a Sewer Pipe Rehabilitation Planning FrameworkGreta Vladeanu, Trenchless Technology Center; John Matthews, Trenchless Technology Center This paper presents a practical application of a risk-based decision-making framework for wastewater pipe renewal planning and budgeting. Condition assessment data from a Louisiana wastewater utility was obtained to develop an integrated framework that determines the risk of failure of wastewater pipes.

Track 5: SlipliningTrack Leader: George Ragula

3:30 PM ..........................................................TA-T5-01Emergency Repair and Lining of the PCI-12A Interceptor in Macomb County, MichiganFritz Klingler, FK Engineering Associates; Joseph Alberts, FK Engineering Associates; Evans Bantios, Macomb County Public Works; Zachary Carr, FK Engineering Associates; Curtis Rozelle, Jay Dee Contractors IncThis paper is a case study of the emergency repair of the 11 ft PCI-12A Interceptor, following its collapse on Christmas Eve 2016. The paper will focus on the emergency efforts to stabilize the area, construct a 100 MGD pumping station and bypass and reline 3,700 ft of sewer.

16

3:55 PM ..........................................................TA-T5-02HDD...Wait, No...Slipline!Kerstin Kenty, Jacobs; Dinesh Kamath, Pinellas County Utilities; Dennis Simpson, Pinellas County UtilitiesThis paper will explore the decision points, challenges and opportunities experienced going from a HDD to slipline method during the installation of 3,100 ft of FPVC pipe as an emergency repair within a wastewater conveyance system.

4:20 PM ..........................................................TA-T5-03Rehabilitation of the Barton Street Horseshoe-Shaped Combined Sewer in Hamilton, OntarioDavid Crowder, R.V. Anderson Associates Limited; Tyler Lahti, R.V. Anderson Associates Limited; Harry Krinas, City of Hamilton; Julia Noble, Pipeflo Contracting CorpThis paper will provide an overview of the inspection, design and rehabilitation for this 275-m long, 1,200-mm by 1,350-mm diameter horseshoe shaped combine overflow sewer, located 7.5-m below Barton Street in the City of Hamilton.

4:45 PM ..........................................................TA-T5-04Sliplining 120-In. RCP Wastewater in Dallas, TexasMarty Paris, Kimley-Horn and Associates Inc; Kevin Cannon, Dallas Water Utilities; Ashlyn Morgan, Kimley-Horn and Associates IncThis paper will review a case study of the 120-in. Southside Interceptor Rehabilitation project in Dallas, Texas. The project involved evaluating rehabilitation alternatives for 15,000 lf of 120-in. RCP wastewater and 12,600 lf of parallel 72-in. RCP wastewater. The design included sliplining the 120-in. and point repairs on the 72-in.

Track 6: Wastewater Pipeline Rehabilitation: GeopolymerTrack Leader: Marc Lehmann

3:30 PM ..........................................................TA-T6-01Fixing a 19th Century Sewer with a 21st Century Solution: A Case Study for Geopolymer Sanitary Sewer RehabilitationAllison Swisher, City of Joliet; Joseph Sullivan, RJN Group IncIn 2016, sewer televising showed the structural integrity of Joliet’s limestone arch sewer was compromised. The sewer, which was constructed in the 1860s, was rehabilitated with a 1-in. thick geopolymer coating application. Overall, 2,200 lt of sewer were repaired in this high priority downtown business district.

3:55 PM ..........................................................TA-T6-02DC Water New Jersey B Street 10- to 18-Ft Diameter Trunk Sewer Rehabilitation During Live Dry Weather Flow Scott Naiva, Milliken Infrastructure; Steve Bian, DC WATER; Tim Bako, IPR NortheastIn 2018, DC Water started rehabilitation of its New Jersey B Street trunk line under live flow conditions. The project is 4,340 lf of 10- to 18-ft span pipe. This covers why geopolymer mortar was chosen, rehabilitation options considered, liner design/construction challenges and lessons learned.

4:20 PM ..........................................................TA-T6-03Challenges Encountered During Rehabilitation of a Trunk Sewer Using Sprayed GeopolymerPaul Headland, Aldea Services LLCThe 16th Avenue Sanitary Trunk Sewer Rehabilitation project comprises sprayed geopolymer relining of approximately 3-km of 2,642-mm diameter sewer tunnel at depths of up to 47-m below ground. This paper presents the results of the rehabilitation, as well as challenges encountered and lessons learned during the project.

4:45 PM ..........................................................TA-T6-04Narragansett Bay Commission Rehabilitation of Large Diameter Brick Sewer with GeoSpray Geopolymer MortarScott Naiva, Milliken Infrastructure Solutions; Meg Goulet, Narragansett Bay Commission; James Fleming, National Water Main CleaningThe summer 2018 Narraganset Bay Commission (NBC) in Providence, Rhode Island, had National Water Main Cleaning (NWMC) rehabilitate 2,200 lf of up to 60-in. brick pipe using Milliken’s GeoSpray geopolymer spray on mortar. This presentation is on trenchless options considered, construction challenges in the middle of a highway and lessons learned.

5:10 PM ..........................................................TA-T6-05Urgent Storm Pipe Rehabilitation as a Result of Lingering Effects and Damage Caused By Hurricane Harvey Steve Henning, Vortex CompaniesSeveral large diameter CMP stormwater pipes (84-in. to 96-in.) running beneath a multi-lane roadway in Houston, Texas, were failing as a result of damage and extreme flooding created by Hurricane Harvey. Full structural rehabilitation was achieved using a geopolymer lining system, thus avoiding total replacement.

Water/Wastewater

Tuesday, March 19, 2019 - PM

Track 1: Pilot TubeTrack Leader: Alan Atalah

3:55 PM ..........................................................TA-T1-02Guided Auger Boring Resolves Everyday Utility Installation Challenges at the O’Hare International AirportJason Holden, Akkerman Inc; Laura Anderson, Akkerman IncThis presentation is an overview of several recent utility casing installations that resolved design challenges at Chicago’s O’Hare International Airport using the pilot tube guided auger boring method.

4:20 PM ..........................................................TA-T1-03Trenchless Technologies Used in Flood Prevention Schemes Project in Doha, QatarMohammad Reza Jafari, CDM Smith; Francois Bernardeau, CDM SmithThis paper covers the application of a novel trenchless technique using axis laser guided boring (ALGB) method and HDD in drainage projects along with the comparison of this advance trenchless method with conventional techniques used for the Flood Prevention Scheme Project in Doha, Qatar.

Track 3: Condition Assessment & Asset ManagementTrack Leader: Jonathan Kunay

4:20 PM ..........................................................TA-T3-03Cast Iron Pipe Condition Assessment - Service Measured by CenturiesScott Williams, JacobsThe author will share Jacob’s experience with cast iron pipe condition assessment and remaining life projection. The presentation will include historical background on the early cast iron pipe industry, a discussion of progressive approaches to iron pipe inspection and a summary of findings from 10 years of field experience.

4:45 PM ..........................................................TA-T3-04The Use of Innovative Inspection Technologies to Assess and Prioritize Rehabilitation for Water Pipeline InfrastructureMark Wade, BlueWater Solutions Group IncThis paper will present a strategy that can be considered by a pipeline utility to evaluate and prioritize its buried water and wastewater assets using thoughtful and sensible inspection and assessment tools in a step-wise and progressive manner. Included will be tool descriptions and budget guidelines.

Track 4: Research & Emerging TechnologiesTrack Leader: Brenda Kingsmill

3:30 PM ..........................................................TA-T4-01Conducting the ASTM D2992 - Challenges and ConcernsShaurav Alam, Trenchless Technology Center; John Kraft, Trenchless Technology Center; John Matthews, Trenchless Technology Center; David Kozman, HammerHead Trenchless; Mark Chandler, Applied Felts Inc; Bill Donohu, Genedge Alliance Multiple obscurities in the ASTM D2992 hydrostatic design basis (HDB) or pressure design basis (PDB) procedure have potential to force the users towards a biased interpretation. This paper contains a detailed logical calculation of the standard to clarify the process for future investigators and thus help the trenchless community.

4:20 PM ..........................................................TA-T4-03Living Labs Validation of Trenchless Technical Solution in Real World ApplicationsTom Iseley, Trenchless Technology Center; Seyed Saleh, Behbahani Trenchless Technology Center; Shuai Han, Trenchless Technology CenterThis paper reviews the recent Trenchless Technology Center (TTC) project on the sewer lateral repair and the field evaluation test and installation process. Also, it discusses how the TTC Living Lab program allows the TTC Research Team to perform various procedures in a real-world scenario and monitor over time.

Track 2: HDDTrack Leader: Rachel Maupin

4:45 PM ..........................................................TA-T2-04Pit-Launched HDD Proves Useful for WaterOne out of Lenexa, Kansas Joe Abell, TT Technologies Inc; Matt Carter, WaterOneWaterOne out of Lenexa, Kansas, had to look outside its current equipment toolbox to a compact 13,500 lb pit launched HDD to solve a problem. This paper will focus on the challenges and restraints of the project, the cost and time savings over additional options and future uses. 

5:10 PM ..........................................................TA-T2-05Multiple Trenchless Methods Allow for Water Supply Installation through Wyoming TerrainRobert Hood, Sunrise EngineeringThe Jamestown-Rio Vista Water and Sewer District in Wyoming expanded its water supply system with over 25,000 ft of 8-in., 10-in., and 12-in. water lines installed via open trench, directional boring through rock conditions, pipe bursting and jack-and-bore.

Track 3: Condition Assessment & Asset ManagementTrack Leader: Jonathan Kunay

3:55 PM ..........................................................TA-T3-02Burnsville, Minnesota, Validates Estimates of Remaining Water Main Pipe Wall Thickness Gathered Using an Acoustic Velocity Testing ToolPaul Pasko, SEHTo assist making capital decisions about pipe rehabilitation during street reconstruction, the City estimates pipe wall thicknesses using Acoustic Velocity Testing. Pipe rehabilitation in its 2018 street project offered an opportunity to validate estimated thicknesses. Validation compares estimated thicknesses to physical measurements taken from salvaged pipe coupons.

5:10 PM ..........................................................TA-T3-05Managing Linear Assets Beyond Their Original Design Life Case Study - City of DeSoto, Kansas, Raw Water Transmission Main

Water

Tuesday, March 19, 2019 - PM

Water/Wastewater Water Wastewater Electrical Gas Other

17Lisa Douglas, Ace Pipe Cleaning Inc; Mark Wade, Blue Water Solutions GroupMany technologies maintain pipelines in a way that provides service beyond design life.  Without diagnostic and maintenance tools, it is a guessing game when to replace. There was a concern replacement would be necessary for the DeSoto, Kansas, transmission main. With tools to inspect (cctv/leak detection) and cleaning, replacement was canceled.

Track 5: SlipliningTrack Leader: George Ragula

5:10 PM ..........................................................TA-T5-05Denver Water Turns to Sliplining to Renew Century-Old Transmission MainMartin Garcia, Denver Water; Stephen Austin, Underground Solutions IncDenver Water used sliplining to rehabilitate a century-old 36-in. cast iron transmission main when its standard methods of cement mortar lining were no longer an option. This renewed pipeline is now the largest diameter PVC pressure pipe installed in Denver Water’s system.

Track 2: HDDTrack Leader: Rachel Maupin

4:20 PM ..........................................................TA-T2-03Soil Mechanics and Calculating Hydraulic Fracture Risk

Gas

Tuesday, March 19, 2019 - PM

+ Other

Tuesday, March 19, 2019 - PM

Track 1: Pilot TubeTrack Leader: Mohammad Najafi

3:30 PM ..........................................................TA-T1-01Unique Horizontal Drain Installation Under a Building Using Pilot Tube Guided Auger Bore MethodsMichelle Macauley, Macauley Trenchless; Steve Torgerson, Trenchless Construction ServicesDesign considerations and construction recap for installation of four 8-in. diameter horizontal drains under a critical building with no interior access. Key considerations included high water table in granular soils, limited work area around the building and coordination around and under a critical facility that never shuts down.

Wednesday, March 20, 2019 & Thursday, March 21, 2019

Plan to Attend a Post-Conference Course

NASTT’s Cured-In-Place Pipe (CIPP) Good Practices CourseWednesday, March 20, 2019 - 2:30 PM – 6:00 PMThursday, March 21, 2019 - 8:00 AM – 12:00 PMRoom 3The CIPP course provides an in-depth overview of water, wastewater mainline and sewer lateral pipe rehabilitation using CIPP from planning and design to job completion.

NASTT’s Sewer Laterals Good Practices CourseWednesday, March 20, 2019 - 2:30 PM – 5:30 PMThursday, March 21, 2019 - 8:30 AM – 12:00 PMRoom 2This course offers a clear understanding of the prob-lems and relevant issues unique to the private lateral portion of the collection system network, explains available options for inspection, evaluation and repair of sewer laterals and address the financial and legal issues that affect the means by which nec-essary work can be accomplished.

NASTT’s Horizontal Directional Drilling (HDD) Good Practices CourseWednesday, March 20, 2019 - 2:30 PM – 6:30 PMThursday, March 21, 2019 - 7:30 AM – 12:00 PMRoom 13/14The HDD Good Practices Guidelines course provides an in-depth overview of Horizontal Directional Drilling (HDD) and covers six topics: (1) operation and application; (2) equipment and materials; (3) planning, including surface and geological investiga-tions, utility surveys, bore planning, and regulations and permitting; (4) jobsite safety; (5) risk reduction, trouble shooting and mitigation; and (6) design.

NASTT’s Pipe Bursting Good Practices CourseWednesday, March 20, 2019 - 2:30 PM – 5:30 PMThursday, March 21, 2019 - 8:30 AM – 12:00 PMRoom 1The NASTT Pipe Bursting Good Practices Course pro-vides an in-depth overview of pipe bursting and cov-ers four topic areas: (1) the types, methods and application of pipe bursting; (2) planning and prelimi-nary design of a pipe bursting job; (3) design and construction considerations; and (4) troubleshooting and problem solving.

NASTT’s New Installation Methods Good Practices CourseWednesday, March 20, 2019 - 2:30 PM – 6:00 PMThursday, March 21, 2019 - 8:00 AM – 12:00 PMRoom 4The New Installation Good Practices Guidelines course provides an in-depth overview along with case studies covering many topics: (1) Trenchless methods used for grade and alignment control and guidance; (2) The limitations and advantages of each method discussed; (3) The steps you need to follow to know the underground; (4) How to establish the invert for a proper launch; (5) The history, sizes, equipment options and process of excavating through different ground types, pipe materials; (6) Ways to track where the pipe is located under-ground; and (7) Installation and jacking forces and ways to reduce these forces.

NASTT’s Gas Good Practices Course Cost to Attend: $200 Regular/$100 GovernmentThursday, March 21, 2019 - 8:00 am – 12:00 pmRoom 11/12This Gas Good Practices course will deliver a com-prehensive, consensus-based course outline that is non-commercial and academically oriented. Our instructors are experts and respected leaders in the gas industry.

Cost to Attend: $400 Regular/$250 Government unless otherwise noted. Includes attendance to the course, course handouts and a Continuing Education Unit certificate issued by Louisiana Tech University.

Continuing Education Units (CEUs) and Professional Development Hours (PDHs) - See page 20

Jonathan Robison, GeoEngineers Inc; Mark Miller, GeoEngineers IncThe results of inadvertent returns risk calculations are only as good as the input parameters. Recent engineering failures to use appropriate soil properties have resulted in permit violations and very large construction claims. This paper will review soil mechanics principles for proper calculations, using project examples to illustrate the concepts.

Track 2: HDDTrack Leader: Rachel Maupin

3:55 PM ..........................................................TA-T2-02Improved Magnetic Navigation for Horizontal Directional Drilling Using a Down-Hole Rotating Rare Earth Magnet Implementation.Clinton Moss, Scientific Drilling International; William Seaward, Scientific Drilling InternationalWe describe a novel approach to HDD navigation using a downhole rotating rare earth magnet sub on the bottom hole assembly. Downhole wires and surface coil wires are completely eliminated. With an operating depth of 150 m, the tool can save up to 70 percent of drilling time.

Track 4: Research & Emerging TechnologiesTrack Leader: Brenda Kingsmill

3:55 PM ..........................................................TA-T4-02Practical Criteria for Borehole Instability in Multi-Layer Soil Systems During Horizontal Directional DrillingHaitao Lan, Queen’s University; Ian Moore, Queen’s UniversityThis paper investigated horizontal borehole stability under excessive mud pressure experimentally and numerically during horizontal directional drilling in multi-layer soil systems, i.e. dense sand covered by different thickness of loose sand and dense sandy gravel.

Water/Wastewater Water Wastewater Electrical Gas Other

Water/Wastewater Water Wastewater Electrical Gas Other

Track # Track 1 (WM-T1-01-05)

Track 2 (WM-T2-01-05)

Track 3 (WM-T3-01-05)

Track 4 (WM-T4-01-05)

Track 5 (WM-T5-01-05)

Track 6(WM-T6-01-05)

Track Leader Microtunneling Jack Brown

HDDChris Schuler

Gas: Rehabilitation & HDDDennis Walsh

Pipe Bursting & HDD Construction Safety

Alan Ambler

Wastewater & Stormwater Pipeline Rehabilitation

Andrew Costa

Emerging Technologies Peter Oram

8:00 AMMicrotunneling

Installation of 24-in. (600-mm) Diameter Sanitary Sewer

Small Diameter HDD Downhole Pressure Control

World Record CIPL Renewal of a Natural Gas Main

Penn Township Sewage Authority: a Model of Consistency

Water Flows Uphill in Colorado: Rehabilitation of 54-in. Irrigation Siphon

Case Study of Large Diameter Sewer Rehabilitation using Centrifugally Cast Cementitious Pipe Liner

8:25 AMEngineering

Judgement Required to Use Empirical Tunneling Estimating Methods

Horizontal Directional Drilling Market in China

CO2 Pipeline in Mexico Uses New Connection Method with HDPE System

Do It Yourself Water Main Pipe Bursting

Sliplining Major Interceptor Sewers at the Littleton Englewood Wastewater Treatment Facility Saves Time and Money

Using Bore Planning Software to Complete Challenging Airport Fiber-Optic Project

8:50 AMAzimuth-Based

Navigation System for Extended Length and Curved Microtunneling

Water Agency in North Suburban Chicago Adds Six Communities to System Using Mix of Open Trench and Trenchless Construction

Plastic Gas Main and Service Splitting in Atlanta, Georgia

Sharing Perspective - How Bid Items Effect the Cost and Construction of a Pipe Bursting Project

Ice, Ice Baby: Ice Pigging of a Sanitary Sewer Force Main

Three Challenging Cases of Large Diameter Rehabilitation

9:15 AMReducing Risks of

Microtunneling from the Pipe's Perspective

Local Utilities Relocate Assets Via HDD Prior to FDOT Expansion

Service Abandonment Without Excavation

Reducing the Risk of Cross Bores

CCCP to the Rescue - Restoring a Buckling 84-in. CMP Storm Drain in Kaua'i

The Evolution of Carbon Fiber CIPP (CFCIPP) for Small Diameter Potable Water & Fire Suppression Systems

9:40 AMDesign Challenges of

the Parking Lot 6 Project in Cambridge, Massachusetts, Trenchless Connections and Shafts

Trenchless Technology Triumph in Tempe

Re-Defining Field Applied AROs

Removing Workers From Danger Zones During Exit-Side Horizontal Drilling (HDD) Operations

Use of Spray-Applied Pipe Linings as a Structural Renewal for Gravity Storm Water Conveyance Conduits

Optimized CFRP Design at Intermountain Power Results in a Successful Installation

Schedule At-A-Glance: Wednesday AM Sessions

Wastewater

Wednesday, March 20, 2019 - AM

Technical Paper Sessions Schedule AM Sessions

Track 1: 8:00 AM – 10:05 AM - Room 14Track 2: 8:00 AM – 10:05 AM - Room 12Track 3: 8:00 AM – 10:05 AM - Room 1Track 4: 8:00 AM – 10:05 AM - Room 2Track 5: 8:00 AM – 10:05 AM - Room 3Track 6: 8:00 AM – 10:05 AM - Room 4

18

Plan your experience!Wednesday, March 20, 2019

NASTT’s

NO-DIG SHOW2

019

March 17-21, 2019 | Chicago, Illinois

Wednesday EventsAttendee & Exhibitor Registration7:00 AM – 5:00 PM - Lobby

Exhibit Hall Open 9:00 AM – 12:30 PM - Hall A

Student Research Poster Competition10:30 AM – 12:30 PM - Hall A

Closing Luncheon12:30 PM – 2:00 PM - Room 21-24

Post-Event Course Registration Check-in 1:30 PM – 5:00 PM - Hall/Room 14

Track 4: Pipe Bursting & HDD Construction SafetyTrack Leader: Alan Ambler

8:00 AM .......................................................WM-T4-01Penn Township Sewage Authority: a Model of Consistency

Mike Schultz, TT Technologies Inc; Stan Caroline, Penn Township Sewage Authority Penn Township Sewage Authority will discuss the early days of its replacement program. What drove it to bring the work in-house? The lessons learned and how it ended up developing a 20-year replacement program focusing on pipe bursting and the cost saving to date.

Track 5: Wastewater & Stormwater Pipeline RehabilitationTrack Leader: Andrew Costa

8:25 AM .......................................................WM-T5-02Sliplining Major Interceptor Sewers at the Littleton Englewood Wastewater Treatment Facility Saves Time and Money Michael Middleton, Ingenium Engineers; Gunter Ritter, City of Englewood; Micheal Rocco, AUI Inc Sliplined 2,000 lf of RCP interceptors (66-in., 54-in. and 24-in.) with HOBAS pipe, spray applied epoxy

Track 1: MicrotunnelingTrack Leader: Jack Burnam

8:00 AM .......................................................WM-T1-01Microtunneling Installation of 24-in. (600-mm) Diameter Sanitary SewerPaolo Masaro, City of Vaughan; Jack Graziosi, City of VaughanThis paper will focus on the new microtunneling installation of approximately 850 ft (260m) of twin 24-in. (600mm) sanitary sewer to enable the construction of the first hospital in Vaughan.

8:25 AM .......................................................WM-T1-02Engineering Judgement Required to Use Empirical Tunneling Estimating MethodsBill Zietlow, Brierley Associates; Becky Brock, Brierley Associates; Ryan Crum, Denver Public Works The authors evaluate competing methods for estimating both tunneling-induced settlement and pipe jacking forces and compare to measured results from a recently completed microtunnel project. They find wide variation in predicted results and conclude that significant engineering judgement is required when selecting empirical methods and applying the estimated results.

8:50 AM .......................................................WM-T1-03Azimuth-Based Navigation System for Extended Length and Curved MicrotunnelingJason Holden, Akkerman; Laura Anderson, Akkerman Introduced in 2015, the AZ100 TGS tunneling navigation system has been used to successfully install thousands of lf on extended length and value engineered alignments with curves with minimal surveying downtime. This presentation highlights the AZ100 TGS capabilities on six case studies up to 1,890 lf and 86-in. diameter.

Track 2: HDDTrack Leader: Chris Schuler

8:25 AM .......................................................WM-T2-02Horizontal Directional Drilling Market in ChinaSamuel Ariaratnam, Arizona State UniversityThis paper examines the various markets and trends in the Chinese HDD industry, including discussion on several significant projects conducted over the past decade. Furthermore, discussion of unique

Water/Wastewater

Wednesday, March 20, 2019 - AM

rehabilitation of one concrete junction box and nine manholes all completed under live flow and without disruption to WWTP operations. 

8:50 AM .......................................................WM-T5-03Ice, Ice Baby: Ice Pigging of a Sanitary Sewer Force MainDavid Kerr, GHD IncThe paper will present a case study of utilizing a pipe cleaning technique that has, until recently, been applied to drink water distribution systems to sanitary force main. The cleaning technique will be compared to conventional cleaning methods. Hydraulic improvements will be presented.

Track 6: Emerging TechnologiesTrack Leader: Peter Oram

8:00 AM .......................................................WM-T6-01Case Study of Large Diameter Sewer Rehabilitation using Centrifugally Cast Cementitious Pipe LinerMarc Lehmann, CDM Smith; Jeff Bowra, Capital Region WaterWhat do you do when your oddly shaped sewer is in worse condition than anticipated? We will present a case study of the construction phase of rehabilitating 13,000 lf of large diameter cast in place concrete sewer using a specialized centrifugally cast cementitious pipe lining.

Water

Wednesday, March 20, 2019 - AM

Track 2: HDDTrack Leader: Chris Schuler

9:15 AM .......................................................WM-T2-04Local Utilities Relocate Assets Via HDD Prior to FDOT ExpansionJim Anderson, Baskerville Donovan Inc; James Brannon, Polyengineering IncWhen the Florida Department of Transportation initiated a series of projects to widen portions of US Highway 98, it required local utility owners to relocate their existing pipelines to new locations. Approximately 12 miles of 6 to 20-in. pipe were installed, one mile of which was via horizontal directional drilling.

Gas

Wednesday, March 20, 2019 - AM

Track 2: HDDTrack Leader: Chris Schuler

8:00 AM .......................................................WM-T2-01Small Diameter HDD Downhole Pressure ControlJake Andresen, Staheli Trenchless Consultants; Matthew Izzard, Tracto-Technik UK LTD; Mark Hutchinson, Staheli Trenchless Consultants Discussion of the design of small diameter HDD installations and recommended design criteria from the owner’s perspective. Special consideration is given to the extent of the contract documents and design when compared to large diameter HDD installations and the key contract elements that promote a successful project for an owner.

construction practices will be discussed that differ from conventional North American HDD practices.

8:50 AM .......................................................WM-T2-03Water Agency in North Suburban Chicago Adds Six Communities to System Using Mix of Open Trench and Trenchless ConstructionWilliam Soucie, Central Lake County Joint Action Water Agency; Amrou Atassi, CDM Smith; Jared Wendorf, CDM Smith; Marvin Lee, Underground SolutionsTrenchless construction using HDD was a key component of a larger overall project to expand the service area for Central Lake County Joint Action Water Agency in Lake County, Illinois. In total, the project included over 9,000 ft of transmission main piping installed via HDD with pipe sizes ranging from 10-in. to 24-in. in diameter.

Track 4: Pipe Bursting & HDD Construction SafetyTrack Leader: Alan Ambler

8:50 AM .......................................................WM-T4-03Sharing Perspective - How Bid Items Effect the Cost and Construction of a Pipe Bursting ProjectEdward Alan Ambler, AM Trenchless; Mike Woodcock, Portland Utilities Construction Company; Mark Hutchinson, Staheli Trenchless; Lawrence Pultz, CPH EngineersThis paper analyzes a wide variety of bid items for a pipe bursting project and how they affect the cost and construction of the project. Actual contracts will be used from all over North America sharing the perspective of owners, designers, contractors and construction inspectors.

Track 5: Wastewater & Stormwater Pipeline RehabilitationTrack Leader: Andrew Costa

9:15 AM .......................................................WM-T5-04CCCP to the Rescue - Restoring a Buckling 84-in. CMP Storm Drain in Kaua’iMichelle Beason, National Plant Services IncCentrifugally Cast Concrete Pipe (CCCP) is a fully structural liner that is applied via spincaster or nozzle to restore failing stormwater and wastewater pipelines. Case study and advantages of CCCP will be presented.

Track 6: Emerging TechnologiesTrack Leader: Peter Oram

8:50 AM .......................................................WM-T6-03Three Challenging Cases of Large Diameter RehabilitationKunihiro Kakui, PALTEM/Ashimori Industry; Takashi Ashimori, PALTEM/Ashimori IndustryCase examples of large diameter rehabilitation works are presented. Each case had site-specific challenges that involved holistic approaches from preliminary planning stage. The paper describes not only materials, but whole processes.

9:40 AM .......................................................WM-T2-05Trenchless Technology Triumph in TempeLevi Hawkins, PEC ; Steve Mortensen, PECA combined 10,000 lf of new HDD waterline split into two concurrent projects. The design phase considered sliplining, CIPP, HDD and even open-cut installation. Ultimately HDD was chosen and the paper will cover the decision-making process, considerations for each method and the factors that led to our decision.

Track 4: Pipe Bursting & HDD Construction SafetyTrack Leader: Alan Ambler

8:25 AM .......................................................WM-T4-02Do It Yourself Water Main Pipe BurstingRussell Colbath, City of MonroeA case study of how the City of Monroe, North Carolina, developed an internal water main pipe bursting program. As the only municipality in North Carolina to self-perform water main pipe bursting, the program has allowed Monroe to reach its replacement goals in an efficient, flexible and cost-effective way. 

Track 5: Wastewater & Stormwater Pipeline RehabilitationTrack Leader: Andrew Costa

8:00 AM .......................................................WM-T5-01Water Flows Uphill in Colorado: Rehabilitation of 54-in. Irrigation SiphonAdam Sedgeman, FRP Construction LLC; Max Schmidt, Orchard Mesa Irrigation District; Mo Ehsani, FRP Construction LLC; Marvin Murphy, FRP Construction LLC This project consisted of the rehabilitation of a 54-in. steel irrigation line in a remote location with steep terrain. In addition, the pipe had to be rehabilitated through the winter months in Colorado. The owner was very pleased with the fiber-reinforced polymer technology utilized on this project.

Track 6: Emerging TechnologiesTrack Leader: Peter Oram

9:15 AM .......................................................WM-T6-04The Evolution of Carbon Fiber CIPP (CFCIPP) for Small Diameter Potable Water & Fire Suppression SystemsIan Lancaster, Aegion; Medhi Zarghamee, Simpson Gumpertz & HegerIn 2013, engineers and material scientists from SGH and Aegion embarked on a development program for the Arizona Public Service Company. This development surrounded the use of carbon-fiber reinforced CIPP to rehabilitate and renew aging high pressure potable water/fire suppression system at a major facility in the southwestern United States.

19

Water/Wastewater Water Wastewater Electrical Gas Other

20

Track 1: MicrotunnelingTrack Leader: Jack Burnam

9:15 AM .......................................................WM-T1-04Reducing Risks of Microtunneling from the Pipe’s PerspectiveCyrill Althuser, Jackcontrol AGRisk analysis and mitigation are essential in microtunnel and pipe jacking applications. A microtunnel consists of many pipes being pushed through the ground, therefore, the pipe design requires special attention. This paper discusses the most important aspects to make the risk more bearable to all involved parties.

+ Other

Wednesday, March 20, 2019 - AM

9:40 AM .......................................................WM-T1-05Design Challenges of the Parking Lot 6 Project in Cambridge, Massachusetts, Trenchless Connections and ShaftsNick Goodenow, Stantec Consulting; Keith Gardner, Stantec Consulting; Dave VanHoven, Stantec Consulting; Jerry Friedman, City of CambridgeDesign challenges of a trenchless crossing roughly 200 ft located in poor geotechnical conditions including soft clays using a guided microtunneling or auger bore to cross between secant pile shafts, under the active MBTA Red Line, adjacent to a concurrently constructed six-story development in the urban environment of Cambridge, Massachusetts.

Track 4: Pipe Bursting & HDD Construction SafetyTrack Leader: Alan Ambler

9:15 AM .......................................................WM-T4-04Reducing the Risk of Cross BoresLee Schroeder, Vermeer; Jake Jeffords, McLaughlinProper upfront planning and taking preventive measures during an installation is the best way to avoid cross bores. Learn the steps every horizontal directional drilling crew should follow to avoid making a cross bore.

Track 5: Wastewater & Stormwater Pipeline RehabilitationTrack Leader: Andrew Costa

9:40 AM .......................................................WM-T5-05Use of Spray-Applied Pipe Linings as a Structural Renewal for Gravity Storm Water Conveyance ConduitsMohammad Najafi, Center for Underground Infrastructure Research and Education; Jeffrey Syar, ODOT Office of Hydraulic Engineering; Seyed Korky, Center for Underground Infrastructure Research & Education; Zahra Kohankar, Kouchesfehani Center for Underground Infrastructure Research and EducationThis paper outlines ongoing research and evaluation program conducted through NCHRP for seven U.S. DOTs (DelDOT, FDOT, MnDOT, NCDOT, NYSDOT, Ohio DOT, and PennDOT) to consider spray applied pipe linings (SAPLs) as a structural renewal for culverts and storm drains.

Track 6: Emerging TechnologiesTrack Leader: Peter Oram

8:25 AM .......................................................WM-T6-02Using Bore Planning Software to Complete Challenging Airport Fiber-Optic ProjectKipp Ulfrets, VermeerPinnacle Construction used bore planning software to map the bore ahead of time, GPR to confirm locations under runways, GPS to plot the course and on-the-rig software application to complete the bore successfully.

Track 3: Gas: Rehabilitation & HDDTrack Leader: Dennis Walsh

8:00 AM .......................................................WM-T3-01World Record CIPL Renewal of a Natural Gas MainGeorge Ragula, Public Service Electric & GasPaper will review the trenchless renewal of approximately 2,000 ft of leaking 36-in. diameter high pressure cast iron gas main in South Orange, New Jersey.

8:25 AM .......................................................WM-T3-02CO2 Pipeline in Mexico Uses New Connection Method with HDPE SystemSean Borris, Aegion; Alex Gutierrez, Miller PipelineA CO2 pipeline project in southern Mexico was in need of a corrosion protection solution. A thermoplastic lining system was selected to rehabilitate the system. The system also included a real-time condition assessment program and a fiber-reinforced polymer (FRP) system to act as the pipeline’s required CO2 crack arrestors.

8:50 AM .......................................................WM-T3-03Plastic Gas Main and Service Splitting in Atlanta, GeorgiaEddie Ward, TT Technologies IncPlastic gas main and service splitting replacement program in the Atlanta, Georgia, area. The focus for the paper will be on the observed best practices utilized by the typical gas splitting contractor, typical daily gas main and service projections, the usage of polymer during the splitting operation, pipe splitting equipment options and tracer wire install.

9:15 AM .......................................................WM-T3-04Service Abandonment Without ExcavationJulie Maupin, Peoples Gas; Jeff Mainzer, GTIPeoples Gas is using a bag-and-stop method to reduce excavations made for abandoning gas services that are being removed from service as part of the system modernization program. 

9:40 AM .......................................................WM-T3-05Re-Defining Field Applied AROsTammy Bomia, NRICoating inspections after HDD pipeline installation confirm that the borehole conditions cause coating damage. Field-applied AROs used for trenchless pipeline installation are historically robust anti-corrosion coatings. Fiber reinforced, field applied AROs have gained popularity over the past decade a reliable means to keep your corrosion coatings intact after pullback.

Track 6: Emerging TechnologiesTrack Leader: Peter Oram

9:40 AM .......................................................WM-T6-05Optimized CFRP Design at Intermountain Power Results in a Successful InstallationAmber Wagner, Aegion Corporation; Tomas Jimenez, Fyfe CoThis project was unique, not because this was the first time 12 segments of 102-in. pre-stressed concrete cylinder pipe (PCCP) required rehabilitation at this power plant, but because this was the first time a value-engineered alternative design utilizing the same carbon fiber-reinforced polymer (CFRP) system was presented to the owner.

Electrical

Wednesday, March 20, 2019 - AM

Track 4: Pipe Bursting & HDD Construction SafetyTrack Leader: Alan Ambler

9:40 AM .......................................................WM-T4-05Removing Workers From Danger Zones During Exit-Side Horizontal Drilling (HDD) OperationsJason LaValley, LaValley Industries; Jorge Prince, LaValley IndustriesThis paper focuses on the safety advantages of deploying new technology during horizontal directional drilling (HDD) exit-side operations with a particular focus on removing workers from danger zones. Additional focus on improving risk mitigation through precise torquieng of tool joints as tooling is added or removed from the tail string.

Continuing Education Units (CEUs) and Professional Development Hours (PDHs)NASTT, in conjunction with Louisiana Tech University, will award one CEU/10 PDHs for every 10 hours of six-track technical paper participation. CEUs/PDHs will also be awarded for the Introduction to Trenchless Technology – New Installation, Introduction to Trenchless Technology – Rehabilitation, Cured-In-Place Pipe (CIPP) Good Practices, Sewer Laterals Good Practices, Horizontal Directional Drilling Good Practices, Pipe Bursting Good Practices, New Installation Methods Good Practices and Gas Good Practices. To be eligible to receive CEUs you must:

(1) register to attend the No-Dig Conference sessions and/or register as a full conference exhibitor.(2) make sure your name badge is scanned upon entering and leaving each conference session(3) complete an evaluation form for each session attended

Water/Wastewater Water Wastewater Electrical Gas Other