nasa constellation confidence level estimate using aceit · ♦ perform a cost risk analysis on...

29
NASA Constellation Confidence Level Estimate Using ACEIT Kelley Cyr Constellation Program Cost Estimating Team Lead Jan. 16, 2008 2 nd Annual ACEIT User Conference

Upload: others

Post on 10-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

NASA Constellation Confidence Level Estimate Using ACEIT

Kelley CyrConstellation Program

Cost Estimating Team Lead

Jan. 16, 20082nd Annual ACEIT User Conference

Page 2: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

2Jan. 16, 2008

Topics

♦ Background• Why do a confidence assessment

• Cx Confidence assessment team

• Scope of Cx Confidence assessment

♦ Process • Process Overview

• Model Structure

• Challenges in integrating results

• Handling Discrete Risks

• Correlation

♦ Results♦ Future Work

Page 3: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

3Jan. 16, 2008

Purpose

♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate

♦ Fulfill Congressional/OMB request for Confidence Level Estimate of Constellation Program

♦ Fulfill Administrator’s requirement for 65% confidence level

♦ Support PMR Review with ESMD at NASA HQ

♦ Establish an automated cost model with integrated risk analysis for Constellation Program

♦ Complete an initial Schedule Risk Analysis on Constellation Program

♦ Provide direction to Management indicating individual cost threats

♦ Provide direction to Management regarding phasing of program funding

♦ Ultimately ensure the mission success of Constellation by…• Provide high quality analysis to Management for use in decision making

• Provide insight into cost and schedule of Constellation Projects

• Measure and Manage cost threats to Projects and Program

Page 4: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

4Jan. 16, 2008

Historical NASA Cost Growth

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

-40 -20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280

Cost Growth Percentage

Con

fiden

ce L

evel

/ C

umul

ativ

e Pr

obab

ility

Historical Data (1985-2005)Historical Data (1990-2005)Historical Data (Completed Only)

Apollo (64%) Mercury (92%) Gemini (143%)Space Station (86%)

Data Source: “ A Budgetary Analysis of NASA’s New Vision for Space Exploration,” Congressional Budget Office (CBO), Sept. 2004

Page 5: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

5Jan. 16, 2008

NASA Policy

♦ NASA Cost Estimating Handbook 2004• As a general rule, cost estimates at NASA should be presented at the

70% confidence level • As an entire portfolio of Projects, the budget should be presented at

the 80% confidence level♦ 7120.5D

• “The life-cycle cost estimate, includes reserves, along with the level of confidence estimate provided by the reserves based on a cost-risk analysis” (Ch. 4, page 22)

♦ Administrator/SMC Policy• Projects budget at the 70% confidence level

♦ Administrator’s Position• The confidence level is selectable by managers; we’ve chosen 70%

for agency projects in general, and I personally adjusted that to 65% for Cx.

Page 6: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

6Jan. 16, 2008

History of Constellation Cost Risk

♦ For ESAS, High Level Cost Risk Analysis Based on NASA History Used to Recommend Final Cost Reserve Levels • 65% confidence level for estimates through 2011 budget horizon

totaling $31.3B♦ For PMR 06, Cx Level II PP&C Office Conducted a Cost Risk

Assessment on the Major WBS Elements for each Project• Projects provided input, Level II team incorporated data into a Risk

model• Risk assessment focused on Cx program scope that was to support

ISS missions (6 missions through 2015)• Confidence level of budget estimated at 50%, as well as additional

funds required to achieve 65%♦ For PMR 07, Cx Level II PP&C Office Integrated Detailed Cost

Risk Analysis from Projects• Risk analysis conducted by projects and provided to Level II• Level II integrated cost risk assessments to assess overall program

cost risk• Risk assessment focused on ISS IOC; also evaluated Operations,

HLR and Lunar Operations

Page 7: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

7Jan. 16, 2008

PMR 07 Confidence Level Team

♦ Johnson Space Center• SCEA – Kelley Cyr, Vickie Gutierrez, Susan Bertsch, Steve Wilson• CEV – John Harrison, Susan Bertsch• EVA – Brian Johnson, Jen Nicholson• Program Integration – Keith Combs• Mission Ops – Brad Stewart

♦ Marshall Space Flight Center• CLV – Steve Creech, Charles Hunt, Barbara Stone-Towns

♦ Kennedy Space Center• Ground Ops – Glenn Rhodeside, Glenn Butts, Juan Gordon

♦ Aerospace Corp• Inki Min, Torrey Radcliffe, Marcus Lobbia, Dean Bucher

♦ Tecolote Research• Darren Elliott, Alf Smith, James Johnson, Mike Allen, Jeff McDowell,

Troy Miller♦ Vision Analytics (VAI)

• Jim Costello, Becca Marler, Stuart Spuler

Page 8: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

8Jan. 16, 2008

CxP Scope – 4 Phases

♦ ISS IOC• Through Initial Operations Capability

(IOC) mission (Orion 2, Sep. 2013)• Includes

− Development− Test hardware− Flight hardware for IOC mission− Fixed costs (infrastructure) thru IOC

year• Include ops costs thru IOC year

− If only one flight, include all ops cost in that year

− If more than one flight, prorate by fraction of launch year when IOC flight occurs

• Program Integration breakout determined by project

♦ ISS Operations• Everything non-Lunar not included in

ISS IOC thru 2020• Shared costs breakout as

determined by project• Includes flight hardware production

consistent w/ the assumptions above for IOC

• Program Integration breakout determined by project

♦ Human Lunar Return (HLR)• Through Human Lunar Return (HLR)

mission (LSAM 2, Jun. 2019)• Includes

− Development− Test hardware− Flight hardware for HLR mission− Fixed cost (infrastructure) Thru HLR

year • Includes all ops cost thru HLR year

− If only one flight, include all ops cost in that year

− If more than one flight, prorate by fraction of launch year when IOC flight occurs

• Program Integration breakout determined by project

♦ Lunar Operations• Everything non-ISS not included in

HLR thru 2020• Shared costs breakout determined

by project• Includes flight hardware production

consistent w/ the assumptions above for HLR

• Program Integration breakout determined by project

Page 9: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

9Jan. 16, 2008

General Methodology: Risk Assessment

♦ Obtain Cost Requirements from Projects• Phased results over time by major

WBS• Identification of costs into four program

phases (ISS IOC, ISS Operations, Lunar HLR, and Lunar Operations)

♦ Obtain Cost Risk Assessments from Projects• General approach • Risk results, correlation, and supporting

statistics

♦ Review Risk Results with Projects• Identify coverage of risk analysis (what

risks are covered)• Provide feedback on areas of concern

♦ Implement Correlation• Project Level (elements within a

project)• Program Level (project to project)

♦ Assess Project / Program Identified Threats• Project review of IRMA Threat List to

identify which are captured by project risk analysis

• Implementation of remainder into a probabilistic risk model

♦ Convolve Uncertainties (Project Cost Requirements plus Threats

♦ Identify where Cx Budget Values fall on Integrated Program S-Curve

$

$

$

P

P

P

Projects

CumulativeProbability

TOTAL Program

Cost

$

PThreats

Page 10: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

10Jan. 16, 2008

Uncertainty Definitions

Uncertainty in What You Are Estimating

• Input Uncertainty• Mass• MV Inputs

• Analogy Uncertainty• Level of Similarity

• Additional Uncertainties• Technical, RRW, etc.

Uncertainty Due to Unpredictable Scenarios• Project Re-Scope

• Major system change, etc.• Acts of Congress

• Change in direction• Funding loss, etc.

• Acts of God• Hurricanes, etc.

• Identified Threats• SSP Transition• Major Test Failures

All Estimate Uncertainties

NotIncluded

Uncertainty in the Model• CER Error• Database Coverage

Page 11: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

11Jan. 16, 2008

Integration Method

♦ Developed an Integrated Cost Model Framework in ACEIT• Structured to allow direct input from Projects for phased cost

requirements and risk statistics• Risk parameters and correlation applied to Project costs• Cost/Risk results bucketed into the four Cx Phases (ISS IOC, ISS

Ops, HLR, Lunar Ops)

♦ Second model developed to allow inter-project correlation and handling of threats (discrete risks from IRMA)• Top-level project results by phase exported to second model• Correlation of 0.40 applied to each project• Threats not contained within risk analysis are assessed and added as

a separate project

♦ Confidence Level Results Generated for:• General Total Program S-Curve• Budget Confidence over Time

Page 12: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

12Jan. 16, 2008

CLE Model Overview

♦ Model designed to support several activities• Detailed Integration and Allocation to Cx Phases for Project Risk

Estimates• Capability to correlate Project Results at total Cx Phase level• Incorporation of Discrete Risks into overall Cx Phase Risk Results• Integration of Cost and Schedule Risk Assessments• Identification of Confidence Level of Cx Budget

♦ CLE Model consists of four separate files• Detailed Project Risk Analysis ACE File• Program Level Integration ACE File• Cost and Schedule Integrated Risk ACE File• CLE Results Excel file

Page 13: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

13Jan. 16, 2008

High-Level CLE Model Architecture

Budget Section

Project Point Estimate Summary

Project Risk Results Over Time

Incorporation of Additional Risks

Risk Results by Phase(IOC, ISS Ops, HLR, Lunar Ops)

Project Estimates, Phasingand Risk Data

Project Model

General Inputs (Manifest, etc)

Budget Section

Program Phase Results(Project Correl and Discrete)

Program Risk Results Over Time

Cx Top-Level Project Risk Results(IOC, ISS Ops, HLR, Lunar Ops)

Discrete Risks(Impacts and Likelihood)

Discrete Risks by Cx Phase

Program Model

Cx Program SummaryResults by Phase

(Phased TY$M and Risk Distros)

Schedule Risk Assessment

Integrated Cost and Schedule

Cx Schedule Data

Cost and Schedule Results(Correlated)

CLE Results(S-Curves, Phased Results, Sand Charts,

Risk Over Time Charts, Cost/Sched Frontier Plots, etc)

Page 14: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

14Jan. 16, 2008

Challenges in Integrating Project Risk Data

♦ In many situations, the estimate for which a risk analysis was conducted was different than the phased estimate submitted for their PMR ’07 budget request

♦ Each project used different tools to conduct their risk analysis• NAFCOM• Crystal Ball• @Risk

♦ Projects had not structured their models to adequately bucket cost risk results into the four Cx program phases

Page 15: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

15Jan. 16, 2008

Three Approaches in Implementing Project Risks

♦ Method 1: Direct implementation of Risk Distributions on Project Estimates• Program Integration• Mission Operations

♦ Method 2: Application of Risk Distribution to Total Project Costs• Lander• SCIP

♦ Method 3: Project Risk Estimates Calibrated to Basis of Underlying Project Risk Analysis• EVA• Ground Operations• ARES I • ARES V• CEV

Page 16: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

16Jan. 16, 2008

Integration Review Placed Focus on What Risks were Encompassed by the Projects

♦ A Comprehensive Risk Analysis Usually Captures the Following:• Effort associated to conduct the activities• Labor rate changes• Weight Growth• SLOC Growth• Nominal Perturbations in Schedule

♦ A Typical Cost Risk Analysis Usually Does NOT Capture:• Major Requirement Changes• Major Design Changes (e.g., Engine change)• Manifest changes• Major Test Failures• Changes in Development/Production Plans (e.g., adding additional test

cycles, additional spares, etc)• Funding impacts to planned activities that cause delays

Page 17: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

17Jan. 16, 2008

However, Not All Risk Analysis are Equal

♦ Inputs-Based Approach with Parametric / Analogy Cost Estimating Methods• Capture wide range as historical programs constitute the data base

used for estimation• Distributions on estimate drivers capture impact of potential technical

parameter changes♦ Inputs-Based Approach with Grass Roots Estimating Methods

• Usually based on a particular plan / approach with estimating method based on “effort * rate” or “material * qty” methods

• Distributions placed on input parameters (effort, rate, etc) to equations• Overall risk captured is only as good as what was considered in

identifying the bounds (e.g., was the very worst case considered or was just in the identified effort what could be the potential range)

♦ Output-Based Approach around Cost Results• Distribution placed on resulting cost• Overall risk captured is only as good as what was considered in

identifying the bounds (e.g., was the very worst case considered or was just in the identified effort what could be the potential range)

Some Risk Analyses are More Comprehensive than Others

Page 18: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

18Jan. 16, 2008

Developing a Comprehensive Cost Risk Analysis for Cx Required Inclusion of IRMA Threats

♦ Review of Project Risk Results Identified that the Project Risk Assessments were not Equal• Some projects had a broad view of risk

− Used parametric models based on historical program− Thought through worst case and best case in establishing risk bounds

• Others focused on assessing the risk in the current plan, and not on the impact if the plan changes− Variability in Labor Rates− Range in effort required to complete planned work− Potential risks not considered in the plan were identified as threats in

IRMA

♦ In Order to Develop a Comprehensive Program Level Risk Analysis, the Project S-Curves Need to be Normalized to Same Risk Content Basis in Order to Assess Overall Cx Program Risk

♦ Need to Include IRMA Threats Not Captured by Project Risk Analysis into Overall Risk Analysis

Page 19: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

19Jan. 16, 2008

Summation Method for Including IRMA Threats into Cx CLE

Orion ~ costRisk S-Curve

CX ~ Comprehensive S-Curve

ΣProb(cost)

Cost Ares ~ costRisk S-Curve

All Projects ~ costRiskS-Curve

ΣProb(cost)

Cost

ΣProb(cost)

Cost

Orion ~ Threats S-Curve

ΣProb(cost)

Cost Ares ~ Threats S-Curve

All Projects ~ ThreatsS-Curve

ΣProb(cost)

Cost

ΣProb(cost)

Cost

Σ Prob(cost)

Cost

Page 20: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

20Jan. 16, 2008

Cx Discrete Risk Results by Program Phase

Cx ISS IOCIdentified Threats Risk Analysis

StatisticsCalculated with 3500 iterations

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$0,496 $0,703 $0,910 $1,116 $1,323 $1,530 $1,736 $1,943 $2,150 $2,356

TY $M

Con

fiden

ce L

evel

(CD

0%

1%

1%

2%

2%

3%

3%

4%

4%

5%

5%

Pro

babi

lity

(His

togr

a

Probability Histogram Confidence Level (CDF)

Cx ISS OpsIdentified Threats

StatisticsCalculated with 3500 iterations

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$85.89 $323.14 $560.39 $797.64 $1034.90$1272.15$1509.40$1746.65$1983.90$2221.16

TY $M

Con

fiden

ce L

evel

(CD

0%

5%

10%

15%

20%

25%

30%

Pro

babi

lity

(His

togr

a

Probability Histogram Confidence Level (CDF)

Cx Lunar HLRIdentified Threats

StatisticsCalculated with 3500 iterations

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$0,198 $0,286 $0,375 $0,463 $0,551 $0,640 $0,728 $0,817 $0,905 $0,993

TY $M

Con

fiden

ce L

evel

(CD

0%

1%

1%

2%

2%

3%

3%

4%

4%

5%

Pro

babi

lity

(His

togr

a

Probability Histogram Confidence Level (CDF)

Cx Lunar OpsIdentified Threats

StatisticsCalculated with 3500 iterations

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$34.26 $68.92 $103.58 $138.24 $172.90 $207.56 $242.22 $276.88 $311.54 $346.20

TY $M

Con

fiden

ce L

evel

(CD

0%

1%

2%

3%

4%

5%

6%

Pro

babi

lity

(His

togr

a

Probability Histogram Confidence Level (CDF)

Page 21: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

21Jan. 16, 2008

Impact on Program S-Curve by Adding Discrete IRMA Threats

Adding in Discrete Risks Shifts the S-Curve

M ultiple casesIntegrated Risk Program Estimate- ISS IOC Scope

(InterProject Correl)Statis tics

Calculated with 3500 iterationsUsing LatinHypercube

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$15,000 $17,000 $19,000 $21,000 $23,000 $25,000 $27,000 $29,000 $31,000 $33,000 $35,000

TY $M

Con

fiden

ce L

evel

(CD

Baseline Mean65% Confidence Level Cx Program without ThreatsMean (Cx Program without Threats)

Page 22: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

22Jan. 16, 2008

Correlation

♦ Correlation within Projects Determined by Projects• Range from 0.2 to 0.7 for component level correlation• Range from 0.2 to 0.5 for subsystem level correlation

♦ Correlation between Projects for Program Level Based on Minimum Error Assumption• Conducted sensitivity analysis for inter-project correlation

− Determined that maximum impact of correlation occurs in the 40-60% range

− Identified that 0.40 correlation provides minimum error from 0% to 100% correlation range

• 0.4 used to correlate projects to each other

♦ Comprehensive S-Curve captures correlation within projects and between projects

Page 23: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

23Jan. 16, 2008

Correlation Comparison Chart

Multiple case ComparisonTotal Program S-Curve

StatisticsCalculated with 3500 iterations

Using LatinHypercube

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$25,000 $30,000 $35,000 $40,000 $45,000 $50,000 $55,000

TY $M

Con

fiden

ce L

evel

(CD

Zero Parent Correl 100% Parent Correl 40% Parent Correl

Page 24: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

24Jan. 16, 2008

ISS IOC Confidence Level S-Curve

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$19.00 $21.00 $23.00 $25.00 $27.00 $29.00 $31.00

TY $B

Conf

iden

ce L

evel

PMR 07 Submit 65% Confidence Level

IOC Budget + IOC Allocated Reserves for Sept 2013 IOC Budget + IOC Reserves thru 2015

IOC Budget + All IOC Reserves thru 2013 IOC Budget + All Avail Reserves thru 2015

$26.40B

Page 25: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

25Jan. 16, 2008

Cx S-Curves by Phase

Confidence Level Estimate ~ Humar Lunar Return

Program Budget w/ Reserves

50%

65%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$35 $37 $39 $41 $43 $45 $47 $49 $51 $53 $55 $57 $59TY $B

Con

fiden

ce L

evel

65%Program

Budget w/ Reseves

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$19 $21 $23 $25 $27 $29 $31TY $B

Con

fiden

ce L

evel

Confidence Level Estimate - IOC Confidence Level Estimate - Station Operations

Program Budget w/ Reserves

50%

65%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$14 $16 $18 $20 $22 $24 $26TY $B

Con

fiden

ce L

evel

Confidence Level Estimate ~ Lunar Operations

Program Budget w/ Reserves

50%

65%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

$8 $9 $10 $11 $12 $13 $14 $15 $16TY $B

Con

fiden

ce L

evel

Page 26: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

26Jan. 16, 2008

Time Phased Risk

♦ Viewing Risk Results as Cumulative Result can be Misleading• Over entire effort, program may be under-funded, but large amount of reserves

thrown to program at the end.• Result is that reserves were not available when needed, effort that was

planned to get done was not done, schedule pressure has increased, and program may not be able to spend available dollars

♦ Level II Developed Methodology to View Risk Results over Time• Extract Risk Results for each year for the Cumulative Costs through that Period

in Time• Plot the Resulting 90% Confidence Band (5% to 95%) over Time• Plot the available budget• Identify the confidence level per year of the budget

♦ General Underlying Principles in Viewing the Results• First, assumption that the risk is evenly spread over the period, meaning that a

user cannot assign specific years to have higher or lower risk than specified in the overall risk bound.

• Second, underlying assumption that the estimate is phased appropriately over the time periods to capture the work that will be performed.

• There is an underlying assumption that when you look at a specific year that all the work planned to that point will have been accomplished. Or meaning in an EVM standpoint, CPI and SPI both equal "1".

Page 27: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

27Jan. 16, 2008

Time Phased Risk

♦ Cx Program is Underfunded in Early Years, thereby Placing Additional Pressure on Schedule

Confidence Band Over Time~ IOC

0

5

10

15

20

25

30

35

2007 2008 2009 2010 2011 2012 2013 2014Fiscal Years

$B

5-95% Bound

Available Budget

65% Target Level

Page 28: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

28Jan. 16, 2008

Integrating Cost and Schedule

♦ Cost And Schedule Risk Assessments give us Independent Perspectives of Confidence

♦ Key is to Link Cost And Schedule to Estimate Joint Probability• Ideally cost or schedule would be a driver for the other, but no

relationship for NASA manned programs could be determined• However, research in unmanned systems shows strong relationship

between cost and schedule growth

♦ Level II Implemented Method to Correlate Cost and Schedule S-Curves to Develop Joint Probability• Assumes 0.7 correlation (Strong) between cost and schedule• Further research needed to develop appropriate correlation values

Page 29: NASA Constellation Confidence Level Estimate Using ACEIT · ♦ Perform a Cost Risk Analysis on Constellation Program Cost Estimate ... Space Station (86%) Data Source: “ A Budgetary

29Jan. 16, 2008

Moving Forward Plan

♦ Build an Integrated Program Level Cost Model• Allow sensitivity to input changes (schedule slips, mission model)• Allow capability to model risk based on project methodologies• Phased rollout (NT = CLV and CEV)• Incorporate Periodic Estimate Updates targeted around major

program milestone activities (PMR, PPAR, Pre-NAR, IDACs, etc)♦ Update Risk Analysis to Account for Lunar Architecture Study

Results♦ Update Risk Analysis to Account for Lunar Lander Design

Study Results♦ Support Program Approval Process (PPAR)♦ Support Project Approval Process (Pre-NAR)♦ Support Program Planning, Budgeting, and Execution (PPBE)

Process