Page 1: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email address Date-Time-Group

19 September 2008

Fort Monroe ClosureEnvironmental

Planning

Page 2: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 2008

NEPAPA SECTION 106

Fort Monroe Transition to Closure

ContinuingInteraction

and Impacts

20052005 20112011

BRACDECISION

FMCLOSURE

REUSE

CONCEPT

TENANT RELOCATION

ENVIRONMENTAL REMEDIATION

Gov’t Rqmts Property Reuse

2

Page 3: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 20083

National Environmental Policy Act (NEPA)

• Army has determined an Environmental Impact Statement (EIS) is required based upon the Reuse Plan and the potential to exceed threshold levels for significant impacts.Notice of Intent in Federal Register – 19 Sep 08Public Scoping meeting – 28 Oct 08– Time: 7:00PM - 9:00 PM Place: Northampton Community Center– http://www.hampton.gov/parks/north_hampton_cc.html, 1435 Todds

Lane, Hampton, VA 23666

Page 4: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 2008

National Environmental Policy Act (NEPA)

Environmental Impact Statement (EIS)Major Milestones

• Notice of Intent in Federal Register -19 Sept 08• Public Scoping Meeting - 28 Oct 08• Description of Proposed Action and Alternatives - 29 Sep 08• Preliminary Draft EIS for Army Review - 08 Dec-05 Jan 09• Draft EIS 45-Day Public Review - 17 Apr-3 Jun 09• Public Meeting Draft EIS - 8 May 09• Final EIS Published - 9 Oct 09• Final EIS 30-Day Waiting Period - 20 Oct-19 Nov 09• Record of Decision Signed - 28 Dec 09

Page 5: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 20085

• Apr 06: Historical Records Review (HRR)

• Nov 06: Environmental Condition of Property (ECP) Report

• Aug - Oct 07: Initial sampling at potential Hazardous Toxic &

Radiological Waste (HTRW) Sites

• Jan 08: Draft Site Inspection Report for HTRW

• Mar – Apr 08: Updated Army Environmental Database - 16

Munitions Response Sites (MRS), 14 HTRW Sites and 3

Closure-related Compliance Sites

• Apr – Jun 08: Draft BRAC Installation Action Plan

Environmental Cleanup

Events to Date

Page 6: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 2008

Environmental CleanupWay Ahead

IRP :Contract awarded Aug 08 to conduct

Expanded Site Inspection work at 6 Sites:

anticipate award to conduct Remedial

Investigation at 8 sites by 3rd Qtr FY09

MMRP: Contract award pending to conduct

Remedial Investigation at 16 MR sites

Page 7: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 20087

• Established RAB 19 Sept 06

• Purpose – Citizens’ Advisory Board on environmental remediation; meet quarterly

• Completed Training - Environmental Cleanup Process (Feb 07) and Munitions (May 07)

• Visited HTRW sampling sites (open to the public), Aug 07

• Documents reviewed: • Historical Records Review • Environmental Condition of Property

• Documents provided for comment:• Draft Field Sampling Plan for HTRW, Jun - Jul 07• Draft Site Inspection Report for HTRW, Jan - Feb 08• Draft BRAC Installation Action Plan, May – Jun 08

• Meet quarterly – next meeting 6 Nov 08

Restoration Advisory Board (RAB)

Page 8: Name/Office Symbol/(703) XXX-XXX (DSN XXX) / email addressDate-Time-Group 19 September 2008 Fort Monroe Closure Environmental Planning

Robert Edwards/IMNE-MNR-RMO (757) 788-3571 (DSN 680) / [email protected] 1 July 20088

FY06 FY07 FY08 FY09 FY11FY10

NEPA

PA

Army Timeline for Fort Monroe

TRADOC HQ

NHPA Section 106 Compliance

IMCOM NE

NETCOM-N Region

ACA-N Region

JTFCS

Accessions Cmd

Cadet Command

Construction

Movement

Env Remediation

Implementation