municipal corporation of greater mumbai water sector initiatives
TRANSCRIPT
2
Water Supply- Key Issues
Issues pertaining to Quantity of water•Overall availability and equitable distribution
Issues pertaining to Quality of Water•Contamination due to aging network
Issues pertaining to Cost of Operations and tariff structure
Issues pertaining to hours of supply•Intermittent supply vs. 24X7 supply
Issues pertaining to “unaccounted for water”•Physical as well as revenue losses
Issues pertaining to Customers’ relationship management
4
Water Supply: 3350 Mld
Major Water Treatment Plants:
Bhandup: Rated capacity 1910 Mld, working at 2100 Mld Panjarapur: Rated capacity 1365 Mld, working at 1365 Mld Vehar + Tulsi : Rated capacity 90 Mld
Major Pumping stations: Pise Panjarapur Bhandup Raoli
Master Balancing Reservoirs : 2Yewai Bhandup
Service Reservoirs : 26
Length of water mains : 4000 Kms
No. of Distribution Zones : 109
No. of Leak-detection Zones : 615
No. of daily operated valves : 800
Mumbai Water Supply – At A Glance
5
Existing Water Supply Sources
Sr. No.
Name of the Source Year of Completion
Qty of Water Supply (MLD)
Total Qty of Water Supply
(MLD)(Cumulative)
1 Vihar Lake 1860 110 110
2 Tulsi Lake 1879 18 128
3 Tansa Lake 1892 to 1925 485 613
4 Lower & Upper Vaitarna 1957 1142 1755
Bhatsa
I Mumbai 1981 455 2210
II Mumbai 1989 455 2665
III Mumbai 1996 455 3120
6
III A MUMBAI 2007 350 3470 *
Inclusive of 120MLD En-Route Supply
6
Sources of Water Supply For Mumbai
Basin wise water
sources
Vaitarna
Upper Vaitarna
Lower Vaitarna
Middle Vaitarna
Pinjal
Gargai
Bhatsa
Ulhas
Kalu
Shai
MIDDLE VAITARNA
GARGAI
UPPER VAITARNA
LOWER VAITARNA
PINJAL
KALU
SHAI
BHATSA
TANSA
Mumbai Water Supply- Broad Features
• Mumbai’s Current Population : 13 million• Mumbai’s water supply : 3350 MLD• Non-revenue water : 20-25%• Domestic per capita water availability : 180 lpcd
(excluding 20% leakage & Ind./Com. Demand)• Avg. Hours of Supply : 2 to 4 hours
• The per capita water availability in some cities having 24X7 water supply:-• London : 150 lpcd• Singapore : 160 lpcd• Kuala Lumpur : 120 lpcd• Paris : 150 lpcd• Phnom-Penh : 45 lpcd
• Thus Mumbai has enough water to switch over from the present intermittent pattern to Continuous pattern of water supply provided:
1. Non revenue water is reduced significantly2. Customer Demand is managed (including wastage)3. Supply is augmented as per rising demand (new sources for future demand are created)
24X7 Water Supply- Myths & Realities
• 24X7 water supply is an achievable objective with proper technical & Managerial reforms.
• Myth:
The continuous water supply: Needs more water Expensive Is it necessary? Is it achievable?
• Truth:
The intermittent water supply Consumes more water. Requires huge capital investment & coping costs Associated with the water pollution & leakage management problems The system is never designed for intermittent supply Reduces the asset life
Intermittent System Consumes More Water
1. Consumer taps are usually kept open.
2. There is a tendency to store more water what is required.
3. The ‘STALE’ water is thrown to store ‘FRESH’ water.
4. High peak needs strong network and more capital investment.
5. Low pressures increases the coping cost of the consumer
6. Leak detection & management is difficult.
Benefits of 24 x 7 Water Supply
1. Improved public health through reduction of water pollution.
2. Better system: Demand management by efficient metering and rationalization of tariff
3. Better leak detection & control measures.4. Higher consumer satisfaction: willingness to pay more
and on time.5. Investments in the network can be optimised.6. Consumer can utilize his time more productively.7. Reduction in the coping cost on the consumers.8. The unregulated ground water exploitation and its
negative environmental impact prevented.9. Overall economic boost: Improved infrastructure attracts
Industry / Commerce.
11
Major Water Sector Initiatives
Source Augmentation
Demand-side Management
Supply-side Management
Transition from Intermittent to 24X7 Water Supply
12
Source Augmentation - Long Term Plan
In the year 1993, the Govt. of Maharashtra appointed an expert committee under the chairmanship of Dr M A Chitale (Ex-Secretary, Irrigation Dept) for advice on the long term planning for augmentation of water supply to Mumbai. The committee recommended development of following sources in phases
The GoM has accepted the Dr. Chitale Committee recommendations and has approved allotment of these sources. The MCGM has therefore taken up the Middle Vaitarna Project as an immediate additional source of water supply.Simultaneously feasibility of Gargai and Pinjal Projects is currently being studied and the report of the Consultants, M/s Mot Mcdonald & Co. in this regard is currently under scrutiny.
Sr. Source Basin YieldNo. [MLD]
1 Middle Vaitarna Vaitarna 455
2 Gargai Vaitarna 455
3 Pinjal Vaitarna 865
4 Kalu Ulhas 590
Demand Supply Scenario
2001
2011
2021
121.94 lakhs
152.99 lakhs
163.8 lakhs
Source: Dr. Chitale Committee Report
44502980
5300
38005010
5120
Demand in Mld
Supply in Mld
Present Supply 3350 Mld
14
Source AugmentationIII A Mumbai Water Supply Project
• Project based on Bhatsa Dam
• Original cost: Rs. 667 cr;
• Revised estimate: Rs.739 cr
• Earlier scheduled for completion in 2009, this project is fully commissioned in May 2007, giving 355 mld of additional water to Mumbai
• Present allocation of 355 mld water for the project has been renewed for 5 more yrs after 2007.
• Additional allocation of 300 mld okayed for Mumbai from Bhatsa Dam for five years till Middle Vaitarna Project is completed.
15
Project is based on a new dam to be constructed between Upper Vaitarna dam and Modak Sagar
Environmental Clearance along with permission for diversion of 634 ha of forest land received from the Ministry of Environment & Forest, Govt. of India
Detailed estimates of all the components of the scheme prepared through Consultants.
Tenders invited for most of the components of the Project Agency fixed for the Tunnel & Pipeline components
The work on the Project expected to start in Oct 2007. Rehabilitation Plan for the 43 Project Affected Persons
has been submitted to the District Rehabilitation Officer Thane for implementation after securing approval of the State Rehabilitation Authority
Approved Project Cost: Rs.1,329.50 crore
Proposal for financing under JNNURM cleared in February ’07 by the Government of India.1st installment of grant released.
Middle Vaitarna Water Supply Project
16
Middle Vaitarna Project Financing
MCGM share, (50%)
Rs.664.75 Crores,
Share of State Gov.(15%) Rs.199.43
Crores,
Share of GoI under
JNNURM (35%)
Rs.465.32 Crores
18
Demand/Supply Side Initiatives
Apart from source augmentation, the Corporation is also taking a number of
measures on both, the Demand side as well as the Supply side to ensure greater efficiency and consumer satisfaction.
19
Demand Side initiatives
• Universal metering is being introduced to enable the citizens pay as per their consumption
Expressions of Interest have been called for short-listing one or more agencies for supply, installation, operation/maintenance & reading of water meters throughout Mumbai. The agency will be appointed by the end of November 2007.
• Telescopic Rates to encourage conservation of water are proposed to be introduced after installation of meters on the connections to domestic consumers of planned buildings
• Proposed Tariff Structure is as under :• Upto 150 lpcd One time• 150 to 200 lpcd Two times• 200 to 250 lpcd Three times • 250 lpcd & above Four times• Proposal is under consideration at the level of the Group Leaders and the Standing
Committee.
• Prepaid water meters- water connections with prepaid meters are proposed to be given to the inhabitants of unauthorised slums & structures so as to avoid stealing of water & tampering of the watermains and thereby cut down the wasteful use of water.
20
Supply Side initiativesComprehensive Water Supply Distribution Improvement Programme is being taken up under the guidance of a reputed Consultant, broadly along the following lines -
Water Distribution Management & NRW Reduction: 1. Digital mapping of the utility on GIS compatible base maps.2. Hydraulic modeling of the entire network.3. Hydraulic model of DMA, each comprising about 1000
connections.4. 100% Consumer metering, Bulk metering and District
Metering set-up. 5. Water balance and estimation of NRW/UFW 6. Leakage detection, Repairs / Rehabilitation / Replacement
plan7. Water balance. If NRW within limits, implement 24X7
supply8. Introduce pressure regulating devices for equitable
distribution 9. Introduce / upgrade Distribution management tool ‘SCADA’
IMPROVEMENT IN PRIMARY NETWORK
• A massive programme for replacement of Tansa Water main is proposed to be undertaken from Gundavali to Tansa due to ageing of old pipes.
• Replacing Tansa and Vaitarna Mains between Gundavali and Bhandup Complex by 5500 mm dia. Tunnel for a length of 15 Kms.
• DPRs of these projects are under preparation and would be submitted to GoI for availing financial assistance under the JNNURM.
Improvement in Secondary Network
A major programme has been taken up for replacement of Trunk mains / Inlets / Outlets by Tunnels due to aging of pipe lines, and to avoid leakages -
(i) Replacing Tansa and Vaitarna Mains between Maroshi and Ruparel by 3000mm dia. Tunel for a length of 12 Kms.
(ii) Replacing of Outlets of Malbar Hill Reservoir between Malabar Hill and Cross Maidan by 2200mm dia. Tunnel for a length of 3.6 Kms.
(iii) Replacing of Outlets of Veravali Hill Reservoir between Veravali Hill and Yari Road by 2200mm dia. Tunnel for a length of 6.1 Kms.
30
Replacement and Rehabilitation of old pipelines
A major programme costing Rs. 356 Crore, to be implemented over two years, has been drawn up for replacement/rehabilitation of old pipelines to reduce leakages and possibility of contamination. DPR of Rs. 253.47 Crore is prepared and submitted to the GOI for availing financial assistance under the JNNURM.
Year
Pipelines
2006-07
length
2007-08
length
Total
length
Replacement 221 Km 103 Km 324 Km
Rehabilitation 196 Km 94 Km 290 Km
Total 417 Km 197 Km 614 Km
Expenditure (Rs. Crores)
150 206 356
Improvement in Secondary Network
Improvement in Tertiary Network
• In order to reduce leakages and consequent contamination, the tertiary network is being replaced / rehabilitated wherever necessary, under Expert guidance. Zonal contractors are being appointed for carrying out the work as suggested by the Consultant for which a proposal to appoint contractors in six zones of Mumbai has been submitted to the Standing Committee.
• Tender process for appointing a reputed Consultant for Comprehensive Water Supply Distribution Improvement Programme is currently going on.
32
Energy Audit
A reputed agency has been appointed for carrying out energy audit of the complete system and major pumping stations in water supply sector in order to identify areas where energy can be saved.The Audit Report is submitted in the month of February ’07 and the recommendations are being implemented
Supply Side Management:
Reduction of Operational Costs