Economic Reconstruction Agency Government of Jammu and Kashmir Project Management Consultants MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JAMMU & KASHMIR (ADB LOAN - 2151 – IND)

Upload: others

Post on 27-Feb-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Economic Reconstruction Agency Government of Jammu and Kashmir

Project Management Consultants

MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JAMMU & KASHMIR

(ADB LOAN - 2151 – IND)

Page 2: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 2 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

MONTHLY PROGRESS REPORT MARCH 10

TABLE OF CONTENTS CHAPTER 1 ...................................................................................................................................................... 3 

EXECUTIVE SUMMARY ........................................................................................................................... 3 OVERALL PROJECT COSTING SUMMARY (ALLOCATIONS) ........................................................... 3 OVERALL STATUS OF CONTRACT PACKAGES (IN MILLION Rs) .................................................. 4 ABSTRACT OF STATUS OF CONTRACT PACKAGES ......................................................................... 5 ABSTRACT OF STATUS OF CONTRACT PACKAGE ........................................................................... 6 OVERALL STATUS OF NOS. OF CONTRACT PACKAGES ................................................................. 7 SECTOR & REGION WISE STATUS OF NOS. OF CONTRACT PACKAGES ...................................... 8 LIST OF STATUS OF THE CONTRACT PACKAGES IN URBAN SECTOR JAMMU REGION ......... 9 LIST OF STATUS OF CONTRACT PACKAGES IN URBAN SECTOR KASHMIR REGION ........... 10 LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR ROADS JAMMU REGION ..................................................................................................................................................................... 11 LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR BRIDGES JAMMU REGION ...................................................................................................................................................... 12 LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR ROADS KASHMIR REGION ...................................................................................................................................................... 13 LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR BRIDGES KASHMIR REGION ...................................................................................................................................................... 14 LIST OF DROPPED / PROPOSED TO BE SHIFTED CONTRACT PACKAGES ................................. 15 SUMMARY OF EXPENDITURE UP TO ENDING MARCH 2010 (Million Rs.) .................................. 18 MONTH WISE EXPENDITURE GRAPH – ENDING MARCH 10 ........................................................ 19 

CHAPTER – 2 ................................................................................................................................................. 21 INTRODUCTION AND PROJECT OBJECTIVES ................................................................................... 21 

CHAPTER – 3 ................................................................................................................................................. 22 STATUS OF SHORT RESETTLEMENT PLANS (SRP) - JAMMU TRANSPORT ............................... 22 STATUS OF SHORT RESETTLEMENT PLANS (SRP) - KASHMIR TRANSPORT ........................... 23 

CHAPTER – 4 ................................................................................................................................................. 25 ENVIRONMENTAL PERFORMANCE REPORT JAMMU .................................................................... 25 

ENVIRONMENTAL PERFORMANCE REPORT KASHMIR .................................................................... 29 APPENDIX-I ............................................................................................................................................... 33 APPENDIX-II ............................................................................................................................................. 34 

CHAPTER – 5 ................................................................................................................................................. 35 ACTIVITIES DURING MARCH 10 .......................................................................................................... 35 

CHAPTER – 6 ................................................................................................................................................. 36 MEETINGS HELD DURING MARCH 10 ................................................................................................ 36 

CHAPTER 7 .................................................................................................................................................... 37 CONSULTANT STAFFING - MOBILISATION OF KEY PERSONNEL ............................................... 37 

CHAPTER 8 .................................................................................................................................................... 38 PROGRESS OF WORKS ........................................................................................................................... 38 ANNEXURE - IA URBAN JAMMU WATER SUPPLY & DRAINAGE ................................................ 38 ANNEXURE - I B URBAN KASHMIR WATER SUPPLY & DRAINAGE ........................................... 39 ANNEXURE - IIA TRANSPORT JAMMU ROADS ................................................................................ 40 ANNEXURE - IIB TRANSPORT JAMMU BRIDGES ............................................................................ 41 ANNEXURE - IIC TRANSPORT KASHMIR ROADS ............................................................................ 42 ANNEXURE - IID TRANSPORT KASHMIR BRIDGES ........................................................................ 43 ANNEXURE - II E CONSULTANCY ....................................................................................................... 44 ADDITIONAL INFORMATION ............................................................................................................... 45 

Page 3: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 3 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER 1 EXECUTIVE SUMMARY

OVERALL PROJECT COSTING SUMMARY (ALLOCATIONS)

PROJECT ALLOCATIONS (Revised) Allocation in million $ Equivalent amount in million Rs.

S. No Component Total ADB Govt Total ADB Govt

1 Civil Works- Component A - Urban 119.53 86.55 32.98 5509.5 3991.94 1517.56

2 Civil Works - component B- Transport 185.40 135.21 50.19 8689.50 6328.55 2360.95

3 Equipment and Material 8.91 8.04 0.87 419.08 377.17 41.91

4 Consulting Service and Training 13.76 13.76 0 630.60 630.60 0

5 Incremental Administration costs 7.00 6.44 0.56 315.00 278.34 36.66

Total Costs 334.60 250.00 84.60 15563.68 11606.60 3957.08

6 Interest During Construction and Commitment Charges

23.40 0.00 23.40 1053.00 0.00 1053.00

Total Project Costs 358.0 250.0 108.0 16616.68 11606.60 5010.08

1$=INR 45 for the disbursement claimed upto February 2009 and INR 47 for after February 2009

Page 4: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 4 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

OVERALL STATUS OF CONTRACT PACKAGES (IN MILLION Rs)

Status of Contract Packages Ending March 10 (In Million Rs.)

Sector

Contract Awarded

Original Cost (1)

Contract Tendered

Original Cost (2)

Contract yet to be Tendered Original Cost

(3)

Total Contracts To Be Committed

(4=[1+2+3])

Contracts Awarded (with

Approved Variation)

Likely Cost

Amount No Amount No Amount No Amount No Amount No Amount No

Jammu Water Supply 2273.15 19 2273.15 19 2438.79 19 2503.90 19

Jammu Drainage 620.99 4 620.99 4 729.32 4 784.20 4

Total Jammu Urban 2894.14 23 0.00 0 0.00 0 2894.14 23 3168.11 23 3288.10 23

Kashmir Water Supply 872.39 4 52.50 1 924.89 5 960.38 5 1047.50 5

Kashmir Drainage 1023.50 4 225.30 1 1248.80 5 1322.12 5 1464.30 5

Total Kashmir Urban 1895.89 8 277.80 2 0.00 0 2173.69 10 2282.50 10 2511.80 10

Jammu & Kashmir Urban Equipment

105.74 11 265.54 7 371.28 18 372.70 18 382.54 18

Total J & K Urban Equipment

105.74 11 265.54 7 0.00 0.00 371.28 18.00 372.70 18.00 382.54 18.00

Jammu Road 1735.75 8 230.00 1 1965.75 9 2229.00 9 2732.54 9

Jammu Bridges 70.60 3 70.60 3 106.66 3 113.25 3

Total Jammu Transport 1806.35 11 230.00 1 0.00 0 2036.35 12 2335.66 12 2845.79 12

Kashmir Road 3824.13 27 29.04 2 3853.17 29 4541.56 29 6375.64 29

Kashmir Bridges 562.24 22 562.24 22 578.03 22 765.46 22

Total Kashmir Transport 4386.37 49 29.04 2 0.00 0 4415.41 51 5119.59 51 7141.10 51

Total 11088.49 102.00 802.38 12.00 0.00 0.00 11890.87 114.00 13278.56 114.00 16169.33 114.00

Road Maintenance Equipment Jammu

Road Maintenance Equipment Srinagar

Total Road Maintenance Equipment Jammu & Srinagar

0.00 0 0.00 0

Page 5: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 5 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ABSTRACT OF STATUS OF CONTRACT PACKAGES (IN MILLION Rs.)

Sector Contract Awarded

Contract Tendered

Contracts to be

Tendered

Total Contracts To

Be Committed

1 2 3 4 5 Jammu & Kashmir Urban & Transport Sectors

11088.49 802.38 0.00 11890.87

Page 6: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 6 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ABSTRACT OF STATUS OF CONTRACT PACKAGE

Region Sector Sub-Sector No of Sub-Projects No of contracts

Contract Cost in Crores

Roads 21 29 Length 443.29 Kms 385.3

Bridges 18 22 Length 1033.6 Mtrs 56.2

3 3 Pipe Line 87.89 Kms 69.8

1 1 WTP 5 Nos 17.5

1 1 Sedimentation tanks 6 Nos 5.3

Public Toilet 1 1 No of Toilets 16 Nos 2.3

3 3 Length of Drains 54.58 Kms 100.0

1 1Replacement of worn out pumps 21 Nos. 22.5

Roads 9 9 Length 167 Kms 196.6

Bridges 3 3 Length 228 mtrs 7.1

Pipe Line 328.4 Kms 141.7

Tube wells 55 Nos 31.8

Re-Development of Tube wells 40 Nos. 0.8

Status OHT GLSRs

Completed 8 5Partly completed 1 1Finishing works in progress 13 9

Public Toilet 1 1 No of Toilets 25 Nos. 2.5

Drainage 3 3 Length of Drains 39 Kms 36.41 Km Completed 59.6

Water Tanker 9 Kl 24 Nos.

Water Tanker 4 Kl 11 Nos.

Front End Loader 7 Nos.

Bachoe Loader cum Excavator 4 Nos.

Skid Loader with attachments 4 Nos

Suction cum Jetting machine-7.5KL. 2 Nos

Suction cum jetting machine-4kl 2 Nos

Suction machine-7.5KL- 2 Nos

Suction machine-4-KL 2 Nos

Trolley Mounted Sewer Roading Equipment 2 Nos

Dumper Placer-4.5 cum 10 Nos

Garbage Container- 4.5cum 175 Nos

Garbage cover carrier Tipper -3.5 cum 6 Nos

Garbage cover carrier Tipper -8.0 cum 10 Nos

Procurement of Electrial equipments & goods

19.1

Electrical/ Mechanical Equipment for Pumping Station at Jammu 7.5

Equipments for Jammu & Srinagar

10.6

52.9

Drainage

Scope

1 no subproject at Bari Brahmana (6.5 Kms) completed68.93 Km Road Balck Topped (48 % Physical Progress Achieved)

Status of works

Urban

Transport

Kashmir

Transport

Jammu

Urban

Water Supply

271.91 Kms

Transformer-28Transmission line-112km

Suction cum Jetting machine-7.5KL Handed over

Suction cum Jetting machine- 4KL Handed over

238 Km road Black Topped(62 % Physical Progress Achieved)

9 Nos. bridges is through for traffic.(59 % Physical Progress Achieved)

80.27 Km completed

1 No. completed

3 Nos. functional and is open for public use

27 Nos. completed

17 Nos. completed and 2 Nos. finishing work in progrss

15 Tankers Handed Over

OHT & GSLR's43 OHT

& 17 GSLR's

Nos.

MultiSector Project for Infrastructure Rehabilitation in JK

Suction machine-7.5KL Handed over

6 Tankers Handed Over

25.435 Km completed

Bachoe Loader cum Excavator Handed over

Skid Loader with attachments Handed Over

Water Supply 1911

184

1 no bridge at Devak Nallah completed Except Protection work. 2 nos bridges substructure completed(72 % Physical Progress Achieved)

Front End Loader Handed Over

Suction machine- 4KL Handed over

Trolley Mounted Sewer Roading Equipment Handed Over

49 Nos.Functional

Page 7: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 7 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

OVERALL STATUS OF NOS. OF CONTRACT PACKAGES

URBAN & TRANSPORT SECTOR JAMMU & KASHMIR REGION Status Nos. No.Of Contracts Awarded 102 No.Of Contracts Tendered 12No Of Contracts Awarded & Tendered 114No Of Contracts to be Tendered 0 No. Of Contracts Dropped 2 No. Of Contracts Proposd to be Shifted to Subsequent Loan 54 Total Nos- Urban & Transport Sector Jammu & Kashmir Region

170

Page 8: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 8 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

SECTOR & REGION WISE STATUS OF NOS. OF CONTRACT PACKAGES Ending March 2010

URBAN SECTOR TRANSPORT SECTOR JAMMU & KASHMIR REGION JAMMU & KASHMIR REGION Status Nos. Status Nos. Contracts Awarded 42 Contracts Awarded & Signed 60 Contracts Tendered 9 Contracts Tendered 3 Contracts to be Tendered 0 Contracts to be Tendered 0 Contracts Dropped 0 Contracts Dropped 2 Contracts Shifted to Subsequent Loan 20 Contracts Shifted 34 Total Nos.- Urban Sector Jammu & Kashmir Region

71 Total Nos. of Contract Packages in Transport Sector Jammu & Kashmir

99

URBAN SECTOR TRANSPORT SECTOR JAMMU REGION ROADS & BRIDGES JAMMU REGION Status Nos. Status Nos. Contracts Awarded & Signed 34 Contracts Awarded & Signed 11 Contracts Tendered 7 Contracts Tendered 1 Contracts to be Tendered 0 Contracts to be Tendered 0 Contracts Dropped 0 Contracts Dropped 1 Contracts Proposd to be Shifted to Subsequent Loan 14 Contracts Proposd to be Shifted 14 Total Nos. of Contract Packages in Urban Sector Jammu Region

55 Total Nos. of Contract Packages in Transport Sector Jammu Roads & Bridges

27

URBAN SECTOR TRANSPORT SECTOR KASHMIR REGION ROADS & BRIDGES KASHMIR REGION Status Nos. Status Nos. Contracts Awarded & Signed 8 Contracts Awarded & Signed 49Contracts Tendered 2 Contracts Tendered 2Contracts to be Tendered 0 Contracts to be Tendered 0 Contracts Dropped 0 Contracts Dropped 1 Contracts Proposd to be Shifted to Subsequent Loan 6 Contracts Proposd to be Shifted 20 Total Nos. of Contract Packages in Urban Sector Kashmir Region

16 Total Nos. of Contract Packages in Transport Kashmir Roads & Bridges

72

Page 9: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 9 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF STATUS OF THE CONTRACT PACKAGES IN URBAN SECTOR JAMMU REGION

URBAN SECTOR JAMMU Contracts Awarded & Signed

1 Replacement of old and laying of new rising main (Phase I)

2 Replacement of old and laying of new rising main (Phase II) 3 Construction of 22 Tube wells on East of Jammu

4 Laying New Rising Mains in various Parts of Jammu West ( Phase - III) 5-7 Construction of intake well ,GLSR, OHT, Pumping Stn. in East of Jammu (LOT 1 & 2 & 3)

8-10 Construction of GLSR, OHT in WEST of Jammu (LOT 1, 2 & 3)

11-14 Construction of Tube Wells , Installation of Mechnical and Electrical Equipment and civil works under Jammu city water supply Rehabilitation programme. LOT- 1, 2, 3 & 4)

15 Replacement of Worn out Pipes in Jammu City, Phase I

16 Replacement of Worn out Pipes in Jammu City, Phase II

17 Re-Development of 38 tube wells

18 Construction of Tube Wells installation & commissioning of Mechanical / Electrical Equipment in Jammu Lot - 1

19 Construction of civils work of Tube Wells in Jammu – Lot-2

20 Supply and Delivery of Water Tankers of Capacity 4 KL - 6 Nos and 9 KL - 15

21 WaterTankers Lot-1 - Cap 9KL – 9 Nos.

22 WaterTankers Lot-2 - Cap 4KL – 5 Nos.

23-25 Equipment & vechicle for garbage cleaning (Group 1 - Lot 1 , Lot-2A & Lot 2B ) Front End Loader 7 No, Bachoe Loader cum Excavator 4 no. , (Skid Loader-4no).

26 Equipment & vechicle for garbage cleaning (Group 1 - Lot 3A) (Garbage cover carrier Tipper -3.5 cum -6no.)

27 Equipment & vechicle for garbage cleaning (Group 1 - Lot 3B) , (Garbage cover carrier Tipper - 8 cum -10 no.)

28- 29

Equipment & vechicle for garbage cleaning (Group 3- Lot 1 & 2) Suction cum Jetting machine-7.5KL-2no., Suction cum jetting machine-4kl-2no. Suction machine-7.5KL-2no., Suction machine-4-KL-2no. , Trolley Mounted Sewer Roading Equipment-2no.

30 GROUP-2 (Dumper Placer-4.5 cum-10 no., Garbage Container-4.5cum-175)

31 Rehabilitation of Primary drain and construction of deep drain at Talab Tillo area

32 Rehabilitation of Primary drain and construction of new secondary drain upstream Akhnoor Road

33 Rehabilitation and channelisation of Landoichoi primary drain

34 Public Toilets

Contracts Tendered 35-40 Providing 11KV dedicated feeder at PHE stations & augmentation of electrical substations Equipments

41 Electrical/ Mechanical Equipment for Pumping Station at Jammu Contracts to be Tendered

Note : Packages 'Water Tanker' and 'Garbage cleaning eqipment' are combined for Jammu and Srinagar

Page 10: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 10 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF STATUS OF CONTRACT PACKAGES IN URBAN SECTOR KASHMIR REGION

URBAN SECTOR KASHMIR Contracts Awarded

1 Rangil Water Supply-Tranmission Mains

2 Nishat Water Supply -Replacement /Realignment of Transmission Mains Nishat to Tale Manzil & Doodganga Water Supply - Improvement of transmission main

3 WTP & Pumping Stations - Renovation/revamping of Civil, Electro-mechanical units

4 Nishat Water Supply - Replacement of Dal bund transmission main (Nishat-Zinsha Masjid via NF Rd) 5 Public Toilets

6 Construction of Main drain and laterals along NH Byepass from Rawalpora to Tengpora Bridge

7 Construction of Main drain and laterals along NH Byepass from Pohru Chowk to Chanapora Bridge

8 Construction of Main drain and laterals along NH Byepass from Bemina Chowk to Parimpora Fruit Mandi Contracts Tendered

9 Construction of Sedimentation tanks, clear water sump and allied civil & Electro-Mechanical works for treatment of backwash water at water treatment plant lot A ,lot B , lot C

10 Replacement of worn out pumps, mechanical and electrical equipments for storm water pumping station . Contracts to be Tendered Nil

Page 11: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 11 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR ROADS JAMMU REGION

Jammu Roads Contracts Awarded & Signed 1 Imptt./UG.of Chenani-Sudh-Mahadev-Mantalai Road 2 Imptt./UG.of Udhampur-Ramnagar Road 3 Imptt./UG.of Sidhra-Surinsar-Mansar Road 4 Imptt./UG.of Bani-Dhagger road. 5 Double lanning of Bari Brahmana-Bishnah Road 6 Imptt/UG of Doda-Bharat road. 7 Imptt/UG.of Kalibari-Kathua-Hatli Morh road. 8 Imptt./UG. of Drabshalla-Bimalnag road. Contracts Tendered 9 Imptt./UG Sakhi Maidan-Kalai road. Contracts to be Tendered

Nil

Page 12: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 12 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR BRIDGES JAMMU REGION

Jammu Transport Bridges Contracts Awarded & Signed 1 Construction of 136.26m span multibarrel box culvert over Devak Nallah on Nagrota Motlian. 2 Construction of 45m span Steel Girder Bridge over Kooh Nallah on Udhampur /Ramnagar Road . 3 Construction of 47m span Steel Girder Bridge over Khagote Nallah on Udhampur /Ramnagar Road . Contracts to be Tendered Nil

Contracts Proposed to be Dropped

Nil

Page 13: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 13 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR ROADS KASHMIR REGION

Kashmir Transport Roads Contracts Awarded & Signed

1 Qazigund Kulgam Road 2 Lethpora-Penthachowk loop including Lethpora ladoo-Pampore Khrew road 3 Humhama-Budgam Raiton- Arizal road 4 Sangrama Sopore-Kulangam road 5 Batmaloo-Tengpora Road. Jehangir chowk to SKIMS6 Thajiwara Shangus Road including link road to Brakpora and Magreypora7 Natipora-Nowgam –Pulwama-Newa Road 8 Potkhah –Pachar Road 9 Sumbal Markundal-Hajin Madwan Road

10 Watergam-Behrampora Hib Dangerpora-Rebbon Road 11 Singhpora Kanihama Gundkhaja Qasim Road 12 Bijbehara Langanbal Road (MDR) 13 Wanpoh-Chawalgam Aharbal via Nehama 14 Kralgund Ashpora Qaziabad road in district Kupwara 15 Handwara Zachaldara Waddur Road 16 Town Roads Kargil - Lot1 (Circular road,Goma Kargil) 17 Town Roads Kargil - Lot2 (G.M Pora,Trespone link roads ) 18 Natipora - Chadoora Charie - Sharief Road 19 Sopore Bandipora Road 20 Town Roads Leh G1-Lot-01 (Leh Main, Shenam-Sheldon, Upper Tuckcha-Changespa) 21 Town Roads Leh G1-Lot-2 (Tukcha, Skampari Colony) 22 Town Roads Leh G2-Lot-1 (Tyari Rong- Jiva Tsal Road-RD0Km-RD3.6K) 23 Town Roads Leh G2-Lot-2 (Tyari Rong- Jiva Tsal Road RD3.60Km-RD7.20Km) 24 Town Roads Leh G4-Lot-01 B.M (Leh Main, Shenam-Sheldon, Upper Tuckcha-Changespa) 25 Town Roads Leh G4-Lot-02 B.M (Tyari Rong- Jiva Tsal Road) 26 Habdipora-Qadar- Qaimoh Road 27 Sharda- Kamal Kote Road

Contracts Tendered 28 Town Roads Kargil - G4-Lot2 B.M(Circular road, Goma Kargil) 29 Town Roads Kargil - G4-Lot1 B.M (G.M Pora,Trespone link Roads)

Contracts to be Tendered Nil

Page 14: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 14 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF STATUS OF CONTRACT PACKAGES IN TRANSPORT SECTOR BRIDGES KASHMIR REGION

Kashmir Transport Bridges Contracts Awarded & Signed

1 Bridge at Gundtal Dara 2 Bridge at Teilbal 3 Bridge at Laktipora 4 Steel Girder Bridge at Kani Kadal 5 Bridge near Town Hall Budgam 6 Bridge at Naraspora Budgam 7 Bridge at Yarbugh 8 Bridge at Sail Pulwama 9 Soaf Shali Bridge

10 Dachinpora Bridge 11 Popchan Bridge Baramulla 12 Wahibugh Bridge Pulwama 13 Sonawani Bridge 14 Bonchak Bridge Pulwama 15 Chanpora-Kunzer Bridge 16 Tokina Bridge Pulwama 17 Saidpura Bridge 18 Bridge at Padshahi Bagh 19 Tharmusa Pushkum Bridge at Kargil 20 Urbis Bridge at Leh 21 Bridge in Km 4th of Singhpora Kanihama Road via Gund Khwaja Qasim ” 22 Construction of 1*21 Mtr Span Bridge (Kirkadal) in Km 2nd at Bijbehara Langanbal Road Contracts Tendered

Nil Contracts to be Tendered

Nil

Page 15: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 15 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

LIST OF DROPPED / PROPOSED TO BE SHIFTED CONTRACT PACKAGES

URBAN SECTOR JAMMU Contracts Proposed to be Shifted to Subsequent Loan 1 Equipment & vechicle for garbage cleaning (Group 1 - Lot 4)

2 Rehabilitation of Primary drain and construction of new secondary drain between Panjtirthi, Chandnagar and Shivnagar

3 Rehabilitation of Primary drain and construction of new secondary drain in Digiana, Gangyal, Rampura, NaiBasti, Vikram chowk (LOT-1 & 2 )

4

Re-Development of 38 tube wells and Replacement of Electrical/Mechanical Equipment of tubewells under Jammu city Water Supply Rehabilitation programme.(Supply&installation of Elect. & Mech. Equipments and civil works in Jammu [ LOT-2]

5

Re-Development of 38 tube wells and Replacement of Electrical/Mechanical Equipment of tubewells under Jammu city Water Supply Rehabilitation programme.(Supply&installation of Elect. & Mech. Equipments and civil works in Jammu [ LOT-3]

6 Construction of GLSR, OHT, Pumping Stn. in East of Jammu (LOT-4)

7 Construction of GLSR, OHT, Pumping Stn. in WEST of Jammu (LOT 4) 8 Replacement of Worn out Pipes in Jammu City, Package III

9 Replacement of Worn out Pipes in Jammu City, Package IV (LOT-1 ) 10 Replacement of Worn out Pipes in Jammu City, Package V (LOT-1)

11 Renovation & replacement of wornout pumping machinery in CWPS and existing Tube Wells 12 Laying of pipes from Sitlee to Lohar and Sitlee to Manda 13 Supply of Mechanical and electrical equipment at Sitlee Pumping Stn. 14 Protection & diversion works and construction of weir at Sitlee

URBAN SECTOR KASHMIR Contracts Proposed to be Shifted to Subsequent Loan 1 Construction of Approach Road at Achhan Landfill Site. (Contract awarded Under ADB Loan No. 2331) 2 Construction of 20 tubewells and allied Pipeline works 3 Construction of Main drain and laterals along NH Byepass from Tengpora Bridge to Bemina Chowk. 4 Construction of Main drain and laterals along NH Byepass from Rawalpora to Chanapora Bridge 5 Construction of covered Lateral Drains wihin Project Area of Rawalpora-Tengpora Drainage Scheme 6 Completion of missing links under Rangil Water Supply & Distribution System

Page 16: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 16 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

Jammu Roads Contracts Proposed to be Dropped

1 Imptt./UG Drungli Bypass.

Contracts Proposed to be Shifted

1 Imptt./UG. of Mandli-Kough road.

2 Imptt./UG of Siot-Kalakote road.

3 Imptt/UG of Makerkote-Ukhral-Senabati road.

4 Imptt./UG of Malipeth Pushal 5 Imptt/UG Hiranagar Morh to Kattal Jandi via Hiranagar Town6 1mptt/UG Solki -.Arthamma - Sarooti road 7 Imptt./UG of Basohli-Dhar Mahanpur Road via Sananghat

8 Construction of Kahra-Bagdar Road

Jammu Equipment Contracts Proposed to be Shifted

1 Road Maintenance Management System Equipment for Public Works Department (PWD), Jammu

Jammu Transport Bridges Contracts Proposed to be Dropped Nil

Contracts Proposed to be Shifted 1 Construction of Fly over from Jewel Chowk to Canal Road 2 Construction of Flyover over Vikram Chowk 3 Construction of 42.0 span of multi-barrel box culvert over Mananu Nallaha on Samba-Mansar road.4 Construction of 45m span Steel Girder bridge in 5th Km on Chhatroo Singhpora Road. 5 Construction of 25m span Steel Girder bridge on Chhatroo Nallah on Gurinal Link Road. 6 Construction of 35m span vented causeway over Tridi Nallah on Parnallh Seri Mouni Road.

Kashmir Transport Roads Contracts Proposed to be Dropped

1 Baramula Babarishi Road ODR Contracts Proposed to be Shifted

1 Ujjar Kapran Khadar Road 2 Kupwara Hyhama Gulgam Road, 3 Gangbugh Anderhama Chandigam Road 4 Mushwad Gatipora Road 5 Awantipura Dadsara Tral Road 6 Bemina Bypass to Bemina Crossing, 7 Baghi-Ali Mardan Bota Kadal-Hazratbal Road 8 Khanyar-Zadibal-Pandach Road 9 Konkhan- Barbarshah- Habakadal- Karan Nagar- Tankipora Road

Kashmir Equipment Contracts Proposed to be Shifted 1 Road Maintenance Management System Equipment for Public Works Department (PWD), Jammu

Page 17: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 17 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

Kashmir Transport Bridges Contracts Proposed to be Dropped Nil Contracts Proposed to be Shifted

1 Exhibition to Haft Chinar Fly Over Srinagar 2 Bridge at Hugam 3 Meclayal Bridge at Karalpora 4 Bridge on Asthannad Road at Machil 5 Bridge at Machil on Machil-Pushwari Road . 6 Reconstruction of Barbarshah Bridge 7 Reconstruction of Tanki Pora Bridge 8 Mahjoor Bridge 9 Khumriyal/Shumriyal Bridge over Varnow Nallah

10 Kanthpura Bridge 11 Yaroo Bridge

Page 18: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 18 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

SUMMARY OF EXPENDITURE UP TO ENDING MARCH 2010 (Million Rs.)

SUMMARY OF EXPENDITURE DURING AND UPTO MARCH 10 (Million INR)

S.No Particulars

Financial Progress/ Disbursement

Upto Ending February 10

During March 10

Upto Ending March 10

1 Civil Works A Urban

A-1 i. Water Supply Jammu 1755.84 41.34 1797.17 A-2 ii.Water Supply Kashmir 734.27 31.85 766.11

Total Urban Water Supply 2490.10 73.18 2563.28 A-3 iii.Drainage Jammu 609.76 18.24 627.99 A-4 iv.Drainage Kashmir 532.90 6.63 539.53

Total Urban Drainage 1142.65 24.87 1167.52 A-5 v. Equipment 38.65 14.73 53.39

Total Equipment 38.65 14.73 53.39 Transport

B-1 i.Roads Jammu 1011.54 16.42 1027.96 B-2 ii.Roads Kashmir 3101.90 23.80 3125.69

Total Transport Roads 4113.44 40.21 4153.65 B-3 iii.Bridges Jammu 41.09 0.00 41.09 B-4 iv.Bridges Kashmir 356.54 12.64 369.18

Total Transport Bridges 397.63 12.64 410.27 2 Consultancy 459.55 4.41 463.97 3 Incremental & Administrative Cost 325.37 10.16 335.53 Total Consultancy , Incremental & Admin Cost 784.92 14.58 799.50

Total Expenditure (Million Rs.) 8967.39 180.21 9147.60Total Expenditure (Crores Rs.) 896.74 18.02 914.76

Page 19: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 19 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

MONTH WISE EXPENDITURE GRAPH – ENDING MARCH 10 Updated Disbursement

During January-December 07

During January-December 08

During January-December 09

During January- March10

Upto 2006 Cum upto Dec 06

542.00 542.00 In Million Rs

54.20 54.20 In Cr. Rs

Jan /07

Feb /07

Mar /07

Apr /07

May /07

June /07

July /07

Aug / 07

Sep /07

Oct /07

Nov /07

Dec/ 07

During 2007

Cum upto

Dec 07

25.13 23.63 90.40 127.36 23.37 39.91 56.49 157.17 122.72 98.87 350.39 95.13 1210.57 1752.58 In Mill.Rs

2.513 2.363 9.0398 12.736 2.3369 3.9911 5.649 15.717 12.272 9.8871 35.039 9.5131 121.057 175.23 In Cr. Rs

Jan /08

Feb /08

Mar /08

Apr /08

May /08

June /08

July /08

Aug / 08

Sep /08

Oct /08

Nov /08

Dec/ 08

During 2008

Cum upto

Dec 08

286.35 247.05 192.67 248.46 190.66 213.78 327.96 145.79 313.54 290.28 286.83 383.89 3129.44 4882.02 In Mill.Rs

28.64 24.71 19.27 24.85 19.07 21.38 32.80 14.58 31.35 29.03 28.68 38.39 312.94 488.20 In Cr. Rs

Jan /09

Feb /09

Mar /09

Apr /09

May /09

June /09

July /09

Aug / 09

Sep /09

Oct /09

Nov /09

Dec/ 09

During 2009

Cum upto

Dec 09

267.00 125.38 358.87 203.38 321.67 334.96 463.77 472.5 361.23 298.87 260.9 185.84 3654.26 8536.27 In Mill.Rs

26.70 12.54 35.89 20.33 32.12 33.50 46.38 47.25 36.12 29.89 26.09 18.58 365.43 853.63 In Cr. Rs

Jan /10

Feb /10

Mar /10

Cum upto March10

238.64 192.51 180.21 9147.64 In Mill.Rs

23.86 19.25 18.02 914.764 In Cr. Rs

Page 20: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 20 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

Page 21: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 21 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER – 2 INTRODUCTION AND PROJECT OBJECTIVES

1. INTRODUCTION

Overall project description The Government of Jammu and Kashmir has undertaken various schemes under “Multisector Infrastructure Rehabilitation Project" for rehabilitation and improvement of basic infrastructure in transport sector like roads, bridges, flyovers etc. and urban sector like drainage, water supply, pay and use toilets, etc. in J&K State with loan assistance from Asian Development Bank (ADB Loan No. 2151-IND). The Economic Reconstruction Agency (ERA), Government of Jammu and Kashmir is the Executing Agency for this infrastructure development project to carry out intensive upgradation and improvement of the existing state roads to provide connectivity to areas considered important from social, economic, and strategic points in transport sector and upgradation of drainage, sewerage and water supply in case of urban sector.

Project objectives

The project is primarily designed for the rehabilitation of essential infrastructure in the transport and urban sectors of J& K which have been deteriorated in quality and coverage over the past 15 years due to limited funding for rehabilitation and maintenance coupled with the security situation. The project will upgrade inherently sound facilities now in a poor state of repair. The objective is to increase their quality and life span.

The improved transport facility will give a boost to local economy by providing appropriate outlets for local farm and other produce. The overall assessment of transport sector subprojects envisages the following benefits:

• Improve socio-economic conditions of the inhabitants • Improve living conditions, quality of life and economic prospects • Reduce travel time and vehicle operating costs • Improve access to health, education and markets • Better connectivity to rural areas • Strengthening the weakly connected road stretches by means of construction of bridges

The urban sector sub-projects are aimed at improving the drainage, sanitation and water supply facilities in the urban areas of Jammu and Srinagar cities so as to cater to the demands and requirements of the increasing population. The urban sector subprojects envisage the following benefits:

• Improvement in health and hygiene conditions with rehabilitation of drainage system in the cities. • Maintaining an adequate potable water supply through rehabilitation as well as construction of new

OHTs, GLSRs and Tubewells and by providing additional backup facilities as water tankers to the line department.

• Improving upon the efficiency of infrastructure by replacement of worn out machinery and adequate power back up.

• Checking the losses in water supply through replacement of worn out and damaged pipelines. • Providing necessary public amenities in the form of Pay and Use Toilets.

Page 22: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 22 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER – 3 STATUS OF SHORT RESETTLEMENT PLANS (SRP) - JAMMU TRANSPORT

Transport Jammu Road Sub-projects in Jammu

S.No Name of the Sub Project Present Status of SRPs

1. Sidhra-Sruinsar-Mansar Road

SRP was approved by ADB dated 28th January 2008 with resettlements affects . But latter due to change in the technical design resettlement affects has been avoided and now no SRP is required

2. Chenani-Sudh Mahadev Road up to Mantalai. SRP not required as no land acquisition and road to be built within available ROW

3. Udhampur-Ramnagar Road Approved by ADB on 6th Feb 09

4. Double lanning of BariBrahmna-Bishna Road

SRP was approved by ADB dated 28th January 2008 with resettlements affects . But latter due to change in the technical design resettlement affects has been avoided and now no SRP is required

5. Bani-Dhagger Road Approved by ADB on 6th Feb 09

6. Sakhi Maidan-Kalai Road At Present, the final design does not imply any impact.

7. Doda-Bharth Road SRP not required as road to be built within available ROW

8. Drabshalla Bimalnag Road SRP under preparation

9. Kalibari-Kathua Hatli Morh Road SRP approved by ADB dated 31st Aug 07 with comments

Transport Jammu Bridges Sub-projects in Jammu

S.No Name of the Sub Project Present Status of SRPs

1 Multibox culvert over Devak Nallah on Nagrota Moutlian Bridge SRP under review with ERA

2 Kooh Nallah Bridge Approved by ADB on 5th March 09

Page 23: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 23 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

STATUS OF SHORT RESETTLEMENT PLANS (SRP) - KASHMIR TRANSPORT

Transport Kashmir Road Sub-projects in Kashmir S.No Name of the Sub Project Present Status of SRPs

1. Jahangir Chowk of SKIMS road Approved by ADB 31 October, 2007.

2. Bijbehara Langanbal Road (MDR) Approved by ADB 30 January,2008

3. Thajjiwara Shangus Road Approved by ADB on July,2009

4. Qazigund-Kulgam Road Approved by ADB on 23rd January,2008

5. Potkhah-pachhar Road Approved by ADB on 6th March 2009

6. Watergam Behrampora Hib Dangerpora Rebbon Road Approved by ADB on 3-Oct-07

7. Sumbal Markundal Hajin Madwan Road Approved by ADB on 3-Oct-07

8. Handwara – Zachaldara – Waddur Road Approved by ADB on 15th January,2008

9. Natipora-Nowgam –Pulwama-Newa Road Approved by ADB on 15th January,2008

10. Lethpora Penthachowk loop including Lethpora Ladoo-Pampora Khrew road Approved by ADB on 07th April, 2009.

11. Sangrama-Sopore-Kulangam Road Approved by ADB on 15th July 2008.

12. Sopore-Bandipora Road Approved by ADB 30 January, 2008.

13. Singhpora-Kanihama-Gundkhaja Qasim Road Approved by ADB 15 January, 2008.

14. Wanpoh-Chawalgam-Aharbal via Nehama Approved by ADB on 31Oct,2007

15. Kralgund Ashpora Qaziabad road Approved by ADB, 30 January 2008.

16. Natipora - Chadoora and Chadoora Charie-Sharief road Approved by ADB on. 3rd October, 07.

17. Sharda-Kamalkote Road Approved by ADB on 3-Oct-07.

18. Habdipora Kaddar Road Approved by ADB on Aug-09.

19. Humhama-Budgam Road Sub-project SRP Under Review with ERA

20. Town Roads Leh & Solar Colony Choglamsar Road & Urbis Bridge. Approved by ADB on 11th Dec 08

21. Roads in Kargil- Town Road Kargil Road & Tharumsa Pashkur Road Bridge Approved by ADB on 6th March 2009

Page 24: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 24 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

Bridges Sub Projects Kashmir

1. Soaf Shali Bridge (Major ) Approved by ADB on 15th Jan,2008

2. Sonwani Bridge (Major ) Approved by ADB on 15th July 2008..

3. Dachinpora Bridge (Major) Approved by ADB dt. on 3-Oct-2007

4. Popchan Bridge Approved by ADB, 20th January,2008.

5. Bonchak Bridge Approved by ADB,30 January,2008

6. Tokina Bridge Approved by ADB on 11th December 2008

7. Bridge at Gundtal Dara Approved by ADB on 3-Oct-07

8. Bridge at Teilbal Approved by ADB on 15 January, 2008

9. Bridge at Laktipora Approved by ADB on 3-Oct-2007.

10. Steel Girder Bridge at Kani Kadal Approved by ADB on 31-Oct-07.

11. Bridge at Sail Pulwama Approved by ADB on 15th January,2008

12. Bridge at Padshahi Bagh Approved by ADB on 15th July 2008.

13. Saidpora Bridge Approved by ADB on 15th July 2008. 14. Tharumsa Pashkum Bridge Approved by ADB on 15th March 2009

Urban Srinagar Bridges Sub-projects in Jammu

S.No Name of the Sub Project Present Status of SRPs

1 Rangil water Supply Approved by ADB on 7th April 2009.

Page 25: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 25 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER – 4

ENVIRONMENTAL PERFORMANCE REPORT JAMMU

The following work was carried out during the month of March 2010 in Transport and Urban sector subprojects in Jammu Province: 1. Transport Sector

EMP Implementation:

Special attention is required to be paid by contractor towards obtaining Environmental Clearances from SPCB and implementing measures regarding traffic safety, dust suppression, debris/construction waste disposal and worker camp management but there is no appreciable progress in this regard during the month. Further improvement is required in implementation of EMP on project roads where the work is in construction phase.

The Environmental Performance Fact Sheet for sub-projects in Jammu has been given as Appendix-I. Consents and Approvals:

a. Tree Cutting:

The current status of permissions for tree cutting on respective sub-projects is as under: Sidhra-Surinsar-Mansar Road Sub-project: Permission accorded for tree cutting upto Km 8.50. Udhampur-Ramnagar Road Sub-project: No forest land required. Permission accorded for cutting of

private trees upto Km 7.5. Chenani-Sudhmahadev-Mantalai Road Sub-project: No forest land required. Permission accorded for

cutting of private trees upto Km 3.00. Kalibari-Kathua-Hatli Morh Road Sub-project: Sanction accorded for cutting of 371 Social Forestry trees.

Tree cutting by State Forest Corporation has been completed. Bani-Dagger Road Sub-project: Govt. order issued for cutting of 60 trees. Tree cutting for the stretch

falling under forest, has been completed by forest department. Drabshala Bimalnag Road Sub-project: Permission accorded for cutting of private trees throughout the

stretch. Saki Maidan-Kalai Road Sub-project: Case lying pending with Forest Department. Doda-Bharat Road Sub-project: Case lying with PCCF. Joint inspection for verification lying pending.

Efforts are on to modify the plan to avoid tree cutting.

b. Other Statutory Approvals:

All the contractors have been repeatedly asked to provide complete details regarding the status of clearances/approvals/consents applied for/obtained for installation and operation of various plants and equipments (viz. crusher plant, batching plant, hot mix plant, Diesel Generator Set, etc.) and PUC for vehicles. Barring the contractors working on Sidhra-Surinsar-Mansar road, Doda- Bharat road, Udhampur- Ramnagar road and Chenani – Sudhmahadev – Mantalai road who have submitted some papers /details in this regard, however these were also incomplete, no other firm submitted any details regarding statutory compliance.

Environmental Safety Officers:

All the contractors working on road subprojects have nominated their Environmental Safeguard Officers and JKPCC, who is working on bridge subprojects, informed (verbally) to DSC-III that they have assigned this responsibility to their site incharge. The persons appointed as environmental safeguard officers by the contractor working on Sidhra-Surinsar-Mansar road is on long leave and the person who was assigned the responsibility has resigned therefore there is a need to nominate new person for this task.

Page 26: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 26 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

Environmental Reporting by Contractors:

The contractors are time and again reminded to pay attention to environmental issues and strictly adhere to the provisions of EMP and FIDIC conditions. Reporting formats were prepared and provided to contractors to keep record of various construction activities which are directly or indirectly related to Environmental and Social issues. Despite repeated reminders the submission of reporting formats is very poor. During the month of March 2010, Cube Construction (executing work on Doda – Bharath Road) submitted reporting formats for the month of November 2009 to February 2010 on 03.03.2010 and Khajuria Construction (executing work on Kalibari- Kathua- Hatli morh road) submitted the Environmental Reporting Formats from for the month of February 2010 and March 2010 on 9.03.2010 and 22.03.2010 respectively. However, the information filled in these formats is incomplete and require more interest from Contractors. Reporting formats from other subprojects are yet to be received.

Main Activities of the Month: Construction supervision of subprojects under execution. Discussion regarding implementation of EMP with Team Leader(DSC), Environment Expert ERA,

Environmental Expert PMC. Correspondence with Contractors on implementation of EMP and other Environmental and Safety issues. Addressed the comments received on Revised IEE from ADB.

2. Urban Sector

EMP Implementation:

Improvements are required in EMP implementation on all urban sector sub-projects under execution. Special attention is required to be paid to upgradation of living conditions in the workers camps, proper disposal of construction waste especially on the drainage sub-projects and implementation of proper worker’s safety measures at all the construction sites. The Environmental Performance Fact Sheet for sub-projects in Jammu has been given as Appendix-I.

Consents and Approvals:

The contractors have been asked to provide complete details regarding the status of environmental clearances/approvals/consents required/applied for/obtained for installation and operation of various plants and equipments (viz. crusher plant, hot mix plant, batching plant, diesel generator set etc.) and PUC certificates for vehicles.

In Jammu urban sector, out of 22 nos. packages, physical work in case of two packages is complete and contract is closed. Out of the rest twenty packages, two contracting firms have no vehicle for the packages allotted to them. Out of rest eighteen, it has been obtained in case of seventeen and in case of following one, it is to be obtained by the respective contracting firm and submit to the DSC.

• Construction of Tube wells, installation of mechanical and Electrical equipments and Civil Works under Jammu City water supply rehabilitation programme Lot 1 (6 nos tube wells)

Some of the PUC certificates had been found to be expired. The concerned contractors had again been asked to obtain the renewed certificates.

In Jammu urban sector out of the 15 nos. packages, in which stone aggregate is used, the copy of consent certificates for crushers for the thirteen sub-projects have been submitted by their respective contracting firms and in case of the following two packages it is still awaited:

1. Construction of 22 Tube Wells in Jammu (East) Water Supply Rehabilitation Programme. 2. Construction of Public Toilets in Jammu City.

Page 27: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 27 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

These respective contracting firms have again been reminded to obtain the approvals at the earliest. Some of the approvals and consents were found expired. The concerned contractors had again been asked to obtain the renewed certificates. Environmental Safety Officers:

All the contractors had been directed to nominate Environment and Social Safeguard Officers. Representatives for the nineteen sub-projects, out of twenty in which physical work is still going on, have been nominated by their respective Contracting Firms and in case of following one it is to be nominated:

• Construction of Tube wells, installation of mechanical and Electrical equipments and Civil Works under Jammu City water supply rehabilitation programme Lot 1 (6 nos tube wells)

Environmental Reporting by Contractors:

Contracting firms are reporting the status of EMP implementation through revised reporting format. In case of four packages i.e. Construction of 30 tube wells under Jammu (west) water Supply Rehabilitation Programme Lot – 1, 2, 3 and 4, no appreciable works has been carried out during this month as work is almost complete. Out of the rest, information pertaining to this month’s EMP status for the following twelve Packages has been submitted by their respective firms.

1. Rehabilitation and Channelization of Existing Primary Drains and Construction of New Deep Drains of Talab Tillo area.

2. Rehabilitation and Channelization of existing Primary Drains and construction of new secondary drains upstream of Akhnoor Road.

3. Rehabilitation and Channelization of LandoiChoi Primary Drain 4. Re-development of 38 tube wells and Replacement of Electrical/Mechanical Equipment of tube wells under

Jammu city water supply Rehabilitation programme Lot-1 5. Replacement of Rising Mains, laying new rising mains and gravity mains in various part of Jammu city

[strengthening of existing system (Phase – III)] 6. Replacement of worn out pipes and Strengthening of distribution network Phase-1 7. Replacement of worn out pipes and Strengthening of distribution Network Phase-II 8. Design and Construction of Over Head Tanks (OHT's) and Ground Level Service Reservoirs (GLSR's) and

other allied works at Jammu city West. Lot-1 (6 nos. OHT's, 3 GLSR'S) 9. Design and Construction of Over Head Tanks (OHT's) and Ground Level Service Reservoirs (GLSR's) and

other allied works at Jammu city West. Lot-2 (6 nos. OHT's, 3 GLSR'S) 10. Design, Construction , Supply , Installation, Testing, Commissioning, Trial run , Operation and maintenance

of Civil, Mechanical , Electrical equipment of Intake pumping near Boria and Design, Construction of Over Head Tanks (OHT'S) & Ground Level Service Reservoirs (GLSR'S) and other allied works at Jammu City East. Part - II (12 nos OHT’S, 4 GLSR'S)

11. Design, Construction , Supply , Installation, Testing, Commissioning, Trial run , Operation and maintenance of Civil, Mechanical , Electrical Equipment of Intake pumping near Boria and Design, Construction of Over Head Tanks (OHT'S) & Ground Level Service Reservoirs (GLSR'S) and other allied works at Jammu City East. Lot-1 (1.8 MGD Intake Structure)

12. Design, Construction, Supply, Installation, Testing, Commissioning, Trial run, Operation and maintenance of Civil, Mechanical , Electrical Equipment of Intake pumping near Boria and Design, Construction of Over Head Tanks (OHT'S) & Ground Level Service Reservoirs (GLSR'S) and other allied works at Jammu City East. Lot-2. (9 nos. OHT's, 4 GLSR'S)

Notice issued to all the contractors vide letter no: 11474-87 Dated 16.03.2010to submit the information on the time.

Main Activities of the Month:

• Site supervision of EMP implementation by DSC-I on the sub-projects where contractors have been mobilized and construction works are in progress.

Page 28: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 28 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

• Correspondence with Contractors on implementation of EMP and other environmental issues.

Site visits: Several separate and joint field visits by consultancies and EE ERA (J) were carried out during the month to ensure EMP compliance at the construction sites with regard to dust suppression, traffic and labours safety, safe disposal of debris/construction waste, maintenance of proper HSE at the labour camps etc. Constant reminders and instructions are being issued by DSCs, EE ERA and PMC from time to time to the contracting firms to ensure that all environmental safety measures are being taken up in accordance with EMP. 3. Key Issues

The Following are the key issues which require immediate necessary action / further improvement: Statutory clearances from various Govt. departments i.e. Forest, Wildlife, SPCB etc. Availability of temporary land for dumping waste from urban sector sub-projects especially in case of drainage

sub projects. Timely submission of filled up Environmental Reporting Formats by the respective Contracting Firms. Availability of undisputed ROW. Availability of land for dumping of debris/mulba. Progress of work beyond Km 18/500 on Sidhra-Surinsar-Mansar Road held up for want of clearance from

wildlife department and ADB. 4. Action Taken on non-compliance to Environmental Safeguards:

DSC-I, DSC-III and PMC are constantly perusing contractors to comply with statutory environmental regulations, implementation of EMP and submit the required information at earliest to the concerned DSCs. Necessary reminders were issued during the month to the contractors for compliance of the same. Most of the contracting firms have submitted the monthly reporting format for this month. Notice has been issued to others vide letter no: 11474-87 Dated 16.03.2010 to submit the monthly reporting format on time by DSC-I.

Page 29: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 29 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ENVIRONMENTAL PERFORMANCE REPORT KASHMIR

The following work was carried out during the month of March 2010 in Transport and Urban sector subprojects in Kashmir Province: 1. Transport Sector

EMP Implementation:

Construction work on Twenty seven (27) subprojects (excluding 9 Force Account Bridges executed through JKPCC) including four subproject Roads under PIUs supervision is in progress. Construction work of Padshahi Bridge has been started. However, generally there has been limited construction activities especially on Road subprojects since last half of October as macadamization process has been kept on hold due to start of cold weather conditions in Kashmir valley. Construction work on Soafshali Bridge has been completed and the bridge was officially inaugurated on 26.11.2009. The construction work on Saidpora Bridge has been stopped since September 2009 due to geo-technical holdup developed in both foundation wells. The construction work remains closed from November to March for the sub-projects of Leh, Kargil town Roads, Urbis and Tharumsa-Pashkum Bridges subprojects, construction work has been stopped due to extreme cold weather conditions. Construction work has been resumed on Sharda-Kamalkote road.

The overall EMP implementation on most of the subprojects, as reported by DSC IV , remained satisfactory during the month (Appendix II). In view of some discrepancies, suggestions/advice has been given to the contractors by DSC. Traffic safety measures were found to be satisfactory at most of the construction sites while as in several cases there is need of further improvement. There is improvement in labour safety measures at several subprojects and in overall they are satisfactory. The supervisory staff/nominated ESOs of the contractors and field/site engineers of DSC are required to be more proactive with regard to HSE implementation on all fronts of the under construction subprojects. Instructions were given to the erring contractors and their staff during site visits carried out in the current month by the environmental staff of consultancies and ERA. The conditions of the labour camps wherever provided by the contractors as per requirement were found to be in satisfactory conditions and the labourers inhabiting the camps were found satisfied with the available facilities/arrangements. Most of the labour camps have been established in rented houses/buildings by the contractors. Construction work of Sumbal-Markundal-Hajin-Madwan road and Potkah-Shrakwara-Pachar road subprojects has been completed by the contractor and in this context no labour camp is required. It has been ensured in all sub-projects that no child labour is engaged by the Contractors for construction activity. The contractors are generally procuring the material from borrow areas and stone quarries approved/owned by Geology and Mining Department on payment of royalty to the department. As such there is no issue of opening borrows areas in environmentally sensitive areas by the contractors. In some cases the contractors obtain soil for embankments from local land owners on agreed upon terms and conditions with permission from the engineer and satisfaction of the land owner. DSC has been asked to maintain record of such private agreements and ensure that no significant environmental issue arise out of private borrow areas. The environmental performance fact sheet is given in Appendix-II. Consents and Approvals:

Cutting of forest trees is not involved in any of the under construction subproject, therefore permission for tree cutting is not required. Some stretches of two under construction road subprojects namely Handwara Zachaldara Waddur road, Kralgund Ashpora Qaziabad Road and Humhama Budgam Raithon Arizol Road are located close or pass through forest areas. NOCs from the Forest Department for these subprojects have been obtained. The NOCs restrict the upgradation of the roads to available width only in order to avoid encroachment on forest land. In case of requirement of mulberry and walnut tree cutting, PIU takes permission from the concerned departments (Sericulture and Horticulture) from time to time as and when required. In case of Qazigund-Kulgam Road NOC has been obtained for cutting of 62 no. of Walnut trees from Horticulture Department. The DSC/PIU has to maintain record of permissions obtained from concerned

Page 30: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 30 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

departments. In case of Shardha Kamalkote Road subproject, there is Social Forestry fencing at three locations between km 10 to 14 but is sufficiently away from ROW. However, contractor has been directed not to disturb the fencing by any mean during execution of construction work. It is being constantly monitored and ensured that the contractors procure construction material (stone aggregate, bituminous materials) from approved plants. Most of the contractors have submitted the required consents/licenses for quarries, stone crusher plants, HMM and WMM Plants duly issued by the concerned regulatory authorities. The contractors of Natipora Newa Pulwama Road, Natipora Chadoora Chrar-i-Shrief, Hubdipora Kadder Qaimoh Road and Shardah Kamalkote Road subprojects have established their own Hot Mix Plant, Stone Crusher, Diesel Genset. Some of them have submitted the consent to establish from SPCB, while others have applied for the same to regulatory authority (SPCB). During this month the contracting firm of Hubdipora-Qadar-Qaimoh road has submitted the consent to operate fresh Wet Mix Macadam Plant vide Consent No: 351/RDK of 2010 Dated: 31/03/2010 issued by State Pollution Control Board (SPCB) vide Sr. No. SPCB/RoK/NOC/SC/Pul/98/1735-38 Dated: 31/03/2010. DSC-IV has been asked to initiate action against the erring contractor in view of prolonged non-compliance with agreed upon guidelines. In this context DSC has withheld 10% cost of the IPC submitted in the month of September by the contractor, M/s Bolasingh Jaiprakash Construction Ltd of Natipora Newa Pulwama Road subproject. DSC-IV contemplates similar action against other contractors if non-compliance is further prolonged. The requirement of approvals/consents for different plants and sites are being regularly monitored. The status of these approvals/consents is depicted in Appendix-II. Environmental safety officer:

At the end of the present month, twenty two (22) out of 23 contracting firms have had nominated the Environmental and Social Safeguard Officers. However, incase of Sharda-Kamalkote sub-project, the contracting firm is yet to nominate ESO as Contractor has already been directed. This figure does not include three ESOs nominated for Popchan Bridge, Dachnipora Bridge and Soafshali bridge subprojects as construction work on these bridges has been completed and there is no further environmental documentation required on part of the contractor. In case of the remaining subprojects, the contractors have been again directed to nominate the ESOs. Environmental Reporting Formats Contractors are submitting their monthly environmental reporting formats accordingly for ongoing sub-projects under execution and being supervised by DSC-IV. No reporting format is anticipated from the contracting firms of Leh Town Roads, Kargil Town Roads, Tharumsa-Pashkum Bridge as such construction work road remains closed due to the severe winter period in Ladakh region and road remains cut off for any vehicle movement from Srinagar to Ladakh national highway. 2. Urban Sector

EMP Implementation:

Construction work on seven (7) subprojects is in progress. However, there had been limited construction activities in case of Toilet Blocks and Nishat Zinshah via NFR Water supply Scheme during the present month as most of the construction work especially the water supply schemes is completed. The Rangil water supply scheme was inaugurated in this month on 15.03.2010 by Omer Abdullah, Chief Minister, J&K state. The supervision of subproject namely Approach Road to Achan Landfill has been assigned to the DHV/PSC, JKUSDIP (Loan II). Overall implementation of EMP was found partially satisfactory in most of the subprojects and in some cases there has been prolonged unsatisfactory EMP compliance. DSC has been asked to take action against the non-complying contracting firms. Attention is also needed to be paid towards the workers safety, dust suppression and debris disposal. Several site visits by consultancies and EE ERA were conducted to ensure the satisfactory implementation of EMP (Appendix II). The contractors of Pohru Chowk to Chanapora Bridge Drainage subproject has provided labour camps for the migratory labourers with satisfactory basic facilities. In addition to this, the contractor has also provided a makeshift accommodation to the limited number of labourers at the construction sites of WTPs.

Page 31: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 31 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

Consents and Approvals:

There are limited requirements of stone aggregate material in most of the urban sector subprojects. The contractors of Rawalpora to Tengpora Drainage has submitted the required consents. The contractor of Pohru chowk to Chanapora Drainage subproject has also submitted the consent for Stone Crusher.Consent to operate the 58 Dewatering Stations in Srinagar City has been obtained from SPCB vide No. 1529 0f 2007 dated 27.12.2007 (validity expired). SMC has been asked to get the renewal urgently from SPCB. DSC-II has been asked to ensure that remaining contracting firms are obtaining stone aggregate, GSB material from approved plants and borrow areas. Other necessary approvals/clearances have been obtained for under construction subprojects (Appendix II). Environmental Safety officer:

Out of seven (7) contracting firms, five (5) have nominated ESOs and for the remaining two (2) the nominated ESO resigned for which no replacement has been made so far. Environmental Reporting Formats:

As reported by DSC-II the following contracting firms have submitted/started submitting monthly environmental reporting documents:

• M/S Technofab Engineers in respect of Renovation of WTPs, • M/S SMS Paryavaran Ltd. in respect of Nishat Dal Bund WSS, • M/S Gousia Road Construction Company in respect of Approach Road to Achan Landfill Site. • M/S Sulabh International Social Service Org in respect of Construction of Public Toilet Blocks, • M/S Hassan Roads Construction Company has started submission of the reports in respect of NH Bypass

Drainage subproject. Rawalpora – Tengpora. • M / S M & Co has started submission of the reports in respect of NH Drainage subproject, Pohru –

Channapora. 4. Field visits / meetings

Several separate and joint field visits by consultancies and EE ERA (K) were carried out during the month to ensure EMP compliance at the construction sites with regard to dust suppression, traffic and labours safety, safe disposal of debris/construction waste, maintenance of proper HSE at the labour camps etc. Constant reminders and instructions are being issued by DSCs, EE ERA and PMC from time to time to the contracting firms to ensure that all environmental safety measures are being taken up in accordance with EMP. 5. Key issues:

The Following are the key issues which require immediate necessary action / further improvement: • It is a matter of grave concern in the subproject entitled WTP & Pumping Stations – Renovation /revamping of Civil,

Electro-mechanical units that the side wall on the eastern edge of the backwash tank is under possible threat of collapsing. The possible threat is due to the overlying HT- power line and the Pipeline laid alongside it. It is really a matter of concern and urgent action needs to be taken in order to ensure the safety of the workers as well as the low lying population.

• The supply of adequate numbers of Personal Protective Equipments (PPE) to workers. Use of PPEs by labourers. • Traffic, workers and public safety arrangements around the construction zones need improvement. • The Environmental, Health, Safety and traffic management measures at the workplaces need improved by the

contracting companies . • During the Bore Testing at Saidpora bridge, excavated earth material under protection was accidently spilled into

Nallah. Immediately Contractor was directed to comply and earth material was cleared and removed from the nallah as per Environmental Management Plan (EMP) under contractual obligations.

• Regular use of workers vests/jackets during construction activity in some of the subprojects which needs further improvement.

• Compliance of statutory requirements of NOC/ consents for some of the sub-projects under execution.

Page 32: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 32 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

• Compliance of renewal of consent to operate Stone Crusher plant and HMM Plant for some of sub-projects under

execution for which Contracting Firms has been directed submit copies of consents from SPCB.

6. Action Taken on non-compliance to Environmental Safeguards:

DSC-II, DSC-IV and PMC are constantly perusing contractor’s to comply with statutory environmental regulations, implementation of EMP and submit the required information at earliest to the concerned DSCs. Necessary reminders were issued during the month to the contractors for compliance of the same.

Page 33: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 33 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

APPENDIX-I

Page 34: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

By ERATree cutting Crusher Batching

PlantHot Mix

PlantWMM plant Diesel

Generator SetPollution Under Control (PUC) certificates for

Contractor's vehicles

1 Transport-Jammu/Jmu/Road/01/LCB-01Imptt./UG of Sidhra-Surinsar–Mansar road

Yes Yes Partially Satisfactory

Permission accorded for the forest stretches

falling between km 0.00 to km 8.5 and Km 22.500 to km 38.500

The persons appointed is on long leave and the person made incharge

has resigned. New yet to nominated.

Partially Satisfactory Partially satisfactory Partially Satisfactory Partially Satisfactory

2 Transport-Jammu/Udh/Road/02/LCB-01Imptt. /UG of Chenani-Sudh Mahadev-MantalaiRoad. Yes Yes Partially Satisfactory

No forest land required. Clearance granted for cutting of trees up to Km 3.00

Nominated Partially Satisfactory At present no labour camp Partially Satisfactory Partially Satisfactory

3 Transport-Jammu/Udh/Road/02/LCB-01Imptt./UG of Udhampur-Ramnagar Road.

Yes Yes Partially Satisfactory

No forest land required.Clearance

granted for cutting of trees up to Km 7.5

(conditional)

Nominated Below Satisfaction At present no labour camp Below Satisfaction Below Satisfaction

4 Transport-Jammu/Jmu/Road/03/LCB-02,03Double laning of Bari Brahmana-Bishnah Road.

Yes Yes

Partially satisfactory (because no documentary

evidence of Consents/clearance

submitted by contractor)

Not required

5 Transport-Jammu/Kathua/Road/04/LCB-03Imptt./UG of Bani-Dhagger Road

Yes Yes Partially Satisfactory Tree cutting in forest area completed Nominated Partially Satisfactory At present no labour

camp Below Satisfaction Satisfactory

6 Transport-Jammu/Poonch/Road/05/LCB-03Imptt./UG of Sakhi Maidan-Kalai Road.

Yes - The work is terminated.Govt. order issued for cutting of 15 trees and

use of Forest land

7 Transport-Jammu/Doda/Road/06/LCB-03Imptt. /UG of Doda-Bharth Road.

Yes Yes Partially Satisfactory Design has been changed to save trees Nominated Below Satisfaction At present no labour

camp Partially Satisfactory Partially Satisfactory

8 Transport-Jammu/Doda/Road/12/NCB-04Imptt./UG of Drabshalla-Bimalnag Road.

Yes Yes Below Satisfaction

Permission accorded for cutting of trees

throughout the stretch. (conditional)

Nominated Below Satisfaction At present no labour camp Below Satisfaction Partially Satisfactory

9 Transport-Jammu/Kathua/Road/08/NCB-04Imptt./UG of Kalibari-Kathua-Hatli Morh Road.

Yes Yes Partially satisfactory Tree cutting has been completed by SFC Nominated Partially satisfactory At present no labour

camp Partially Satisfactory Partially Satisfactory

1 Construction of Steel Girder Bridge over KoohNallah on Udhampur Ramnagar road . No Yes Partially Satisfactory Not required Not required Not

requiredNot

required Not required Site incharge assigned this responsibility Satisfactory Labour camp not

established Partially Satisfactory Satisfactory

2 Construction of Steel Girder Bridge over KaghoteNallah on Udhampur /Ramnagar road. No Yes Partially Satisfactory Not required Not required Not

requiredNot

required Not required Site incharge assigned this responsibility Satisfactory Labour camp not

established Partially Satisfactory Satisfactory

3 Construction of multibarrel box culvert over DevakNallah on Nagrota moutlian road.

No Yes Partially Satisfactory Not required Not required Not required

Not required Not required Site incharge assigned

this responsibility Satisfactory Labour camp not established Partially Satisfactory Satisfactory

The consent to establish and operate Hot Mix Plant & stone crusher plant submitted by Contractor but Consent to Operate for WMM, NOC for DG sets and PUC are yet to be submitted

ROAD WORK COMPLETED

Crusher Plant Installed and contractor submitted copy of letter to SPCB for granting NOC. PUCs are yet to be submitted.

Crusher plant and WMM plant installed. Copy of Consents/NOC from SPCB and PUC yet to be submitted by Contractor.

Traffic Safety Measures (Excellent/ Satisfactory/ Partially satisfactory/

Below Satisfaction)

Nomination of Environmental and Social

Safeguard Officers by Contractor (Nominated/

Yet to be Nominated)

Dust Control (Excellent/ Satisfactory/ Partially

satisfactory/ Below Satisfaction)

Labour Camp Management (Excellent/ Satisfactory/ Partially

satisfactory/ Below Satisfaction)

Contractor yet not established his crusher, batching plant, Hotmix plant, WMM plant. Contractor yet to be submit PUCs for vehicles engaged in construction .

Details yet to be submitted by Contractor

Road Packages

Some papers/ details submitted by Contractor but Consent to Operate HMP, WMM, Crusher Plant, DG sets and PUC are yet to be submitted

Consent to Establish and Consent to Operate for Stone crusher submitted by Contractor but NOC for DG sets and PUC are yet to be submitted.

THE CONTRACT TERMINATED ON 11/04/2009

ENVIRONMENTAL PERFORMANCE FACT SHEET FOR THE MONTH OF MARCH 2010

Overall status of EMP implementation (Excellent/

Satisfactory/ Partially satisfactory/ Below

Satisfaction)

S. No. Name of the Sub-Project EMP part of the Contract

Document (Yes/No)

EMP being implemented

(Yes/No)

Environmental Consents/Clearances to be obtained Workers Safety Measures (Excellent/ Satisfactory/ Partially satisfactory/

Below Satisfaction)

By Contractor

APPENDIX-I

Crusher plant and WMM plant installed. Copy of Consents/NOC from SPCB and PUC yet to be submitted by Contractor.

Bridge Packages

Details yet to be submitted by Contractor

Details yet to be submitted by Contractor

Details yet to be submitted by Contractor

A. Transport Sector

Page 35: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Tree Cutting

CrusherBatchin

gPlant

Hot MixPlant

ConcreteMixer

DieselGenerator

Set

Pollution Under Control

(PUC) Certificates for

Contractor's Vehicles

1

Rehabilitation and Channelization of ExistingPrimary Drains and Construction of NewDeep Drain of Talab Tillo area. No Yes Satisfactory N.R. Submitted N.R. N.R.

Information not

submitted by

contractor

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

2

Rehabilitation and Channelization of ExistingPrimary Drains and Construction of NewSecondary Drains upstream of AkhnoorRoad.

Yes Yes Satisfactory N.R. Submitted Applied to SPCB

N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

3

Rehabilitation and Channelization of Landoi Choi Primary Drain

Yes Yes Satisfactory N.R. Submitted N.R. N.R.

Information not

submitted by

contractor

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

1

Construction of 22 Tube wells underJammu (East) Water Supply Rehabilitation

No Yes Satisfactory N.R.Not

submitted N.R. N.R.

Information not

submitted by

contractor

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory N.R.

2

Construction of 30 tube wells underJammu (west) water Supply RehabilitationProgramme

Lot - 1Yes Yes Satisfactory N.R. N.R. N.R. N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory N.R.

3

Construction of 30 tube wells underJammu (west) water Supply RehabilitationProgramme

Lot - 2Yes Yes Satisfactory N.R. N.R. N.R. N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory N.R.

4

Construction of 30 tube wells underJammu (west) water Supply RehabilitationProgramme

Lot - 3Yes Yes Satisfactory N.R. N.R. N.R. N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory N.R.

5

Construction of 30 tube wells underJammu (west) water Supply RehabilitationProgramme

Lot - 4

Yes Yes Satisfactory N.R. Submitted N.R. N.R.Less than

5KVA N.R. Submitted Nominated Satisfactory Satisfactory Satisfactory N.R.

6

Re-development of 38 tube wells andReplacement of Electrical/MechanicalEquipment of tube wells under Jammu city

water supply Rehabilitation programme Lot-1

Yes Yes Satisfactory N.R. N.R. N.R. N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated N.R. Satisfactory Satisfactory N.R.

Construction of Tube wells, installation ofmechanical and Electrical equipments andCivil Works under Jammu City water supply

rehabilitation programme Lot 1 (6 nostube wells)

Yes Yes Satisfactory N.R. N.R. N.R. N.R. N.R.

Information not

submitted by

contractor

Not Submitted Not Nominated N.R. Satisfactory Satisfactory N.R.

1

Replacement of Rising Mains, laying newrising mains and gravity mains in variouspart of Jammu city (strengthening ofexisting system)

Phase - I

2

Replacement of Rising Mains, laying newrising mains and gravity mains in variouspart of Jammu city (strengthening ofexisting system)

Phase - II

Work completed and contract closed

Nomination of Environmental & Social Safeguard

Officer by Contractor

(Nominated / Yet to be Nominated)

Workers Safety Measures

(Excellent/ Satisfactory/Belo

w Satisfaction/Poor

Traffic Safety Measures

(Excellent/ Satisfactory/Belo

w Satisfaction/Poor

Environmental Consents / clearances RequiredB. Urban Sector

DRAINAGE SECTOR

TUBE WELL SECTOR

WATER SUPPLY SECTOR

S.No. Name of Sub Project

Work completed and contract closed

Dust Control

(Excellent/ Satisfactory/Belo

w Satisfaction/Poor

)

Labour Camp Management

(Excellent/ Satisfactory

/Below Satisfaction

EMP Part of

contract Documen

t

(Yes /

EMP being Implemente

d

(Yes / No)

Overall Status of EMP Implementation

(Excellent/Satisfactory/Below

Satisfaction/Poor)

Page 36: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

3

Replacement of Rising Mains, laying newrising mains and gravity mains in variouspart of Jammu city (strengthening ofexisting system)

Phase - III

Yes Yes Satisfactory N.R. Submitted N.R. N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

4

Replacement of worn out pipes andStrengthening of distribution network

Phase-1 Yes Yes Satisfactory N.R. Submitted N.R. N.R. N.R.

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

5

Replacement of worn out pipes andStrengthening of distribution network

Phase-IIYes Yes Satisfactory N.R. Submitted N.R. N.R. N.R.

No Generator set of more than 5 KVA deployed at

site

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

Design and Construction of Over Head Tanks(OHT's) and Ground Level ServiceReservoirs (GLSR's) and other allied worksat Jammu city

West.

1 Lot-1 (6 nos. OHT's, 3 GLSR'S) Yes Yes Satisfactory N.R. Submitted N.R. N.R.

No concrete mixers of

more than 5 KVA

deployed at site

No Generator set of more than 5 KVA deployed at

site

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

2 Lot-2 ( 6 nos. OHT's, 3 GLSR'S) Yes Yes Satisfactory N.R. Submitted N.R. N.R.

Information not

submitted by

contractor

Information not

submitted by

contractor

Contractor don't have any vehicle

Nominated Satisfactory Satisfactory Satisfactory Satisfactory

3 Lot-3 (10 nos OHT'S, 2 GLSR'S) Yes Yes Satisfactory N.R. Submitted N.R. N.R.

Information not

submitted by

contractor

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

Design, Construction , Supply , Installation,Testing, Commissioning, Trial run ,Operation and maintenance of Civil,Mechanical , Electrical Equipment of Intakepumping near Boria and Design,Construction of Over Head Tanks (OHT'S) &Ground Level Service Reservoirs (GLSR'S)and other allied works at Jammu City

East.

4 Lot-1 (1.8 MGD Intake Structure). Yes Yes Satisfactory N.R. Submitted N.R. N.R.

Electricity powered Concrete

Mixer used

No Generator set of more than 5 KVA deployed at

site

Submitted Nominated N.R. Satisfactory Satisfactory N.R.

5 Lot-2 (9 nos. OHT's, 4 GLSR'S) Yes Yes Satisfactory N.R. Submitted N.R. N.R.

No concrete mixers of

more than 5 KVA

deployed at site

No Generator set of more than 5 KVA deployed at

site

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

6 Part - II (12 nos OHT'S, 4 GLSR'S) Yes Yes Satisfactory N.R. Submitted N.R. N.R.

Information not

submitted by

contractor

Information not

submitted by

contractor

Submitted Nominated Satisfactory Satisfactory Satisfactory Satisfactory

1 Construction of Pay & Use Toilet No Yes Satisfactory N.R.Not

submitted N.R. N.R.

No concrete mixers of

more than 5 KVA

deployed at site

No Generator set of more than 5 KVA deployed at

site

Contractor don't have any vehicle

Nominated Satisfactory Satisfactory Satisfactory Satisfactory

PUBLIC TOILET SECTOR

OVER HEAD TANK & GLSR'S SECTOR

Page 37: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 34 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

APPENDIX-II

Page 38: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Permission for Tree Cutting Crusher (Consent to Establish)

Crusher (Consent to Operate)

Hot Mix Plant

Concrete Mixer

Diesel Generator Set

Pollution Under Control (PUC) Certificates for Contractors Vehicles)

1 Qazigund-Kulgam Road

EMP has been issued to the contractor vide No. SCPL/C-703/2552 Dated: 1-11-2007 Yes

Satisfactory 1.Construction work on road completed 2. Work in progress of Y.K Pora Bridge. 3.Work in progress of realigned portion (520 mtr)

Permission/ NOC obtained for cutting of 62 no of Walnut (Juglans regia ) from Horticulture Department.

PUC certificates stands submitted Nominated

Satisfactory Only required at Y.K Pora Section

Local Labourers engaged Satisfactory.

Satisfactory Contractor has already completed road furniture and Thermoplastic markings from Y.K Pora to Kulgam Stretch.

2Natipora-Nowgam – Newa-Pulwama Road

EMP has been issued to the contractor vide No. SCPL/C-703/2551 Dated: 1-11-2007 Yes Satisfactory.

●Required. ●PIU to take issue of permission from the concerned authorities.

PUC certificates stands submitted Nominated Satisfactory

(Labour Camp required for non-locals during BT work) Only local labourers engaged this month. Satisfactory Satisfactory

3Singhpora-Kanihama-Gundkhaja Qasim Road Yes Yes

Satisfactory Most of the work completed.

●Required ●PIU has to take issue of permission from the concerned authorities.

PUC certificates stands submitted Nominated Satisfactory ●Established Satisfactory Satisfactory

4 Soafshali Bridge Yes Yes

Sub-project under defect liability period Bridge officially

●Permission/NOC obtained for cutting of 4 Walnut (Juglans regia ) trees.

PUC certificates stands submitted Nominated Not Required

As per EMP labour camp/ site office will be dismantled Not Required Not Required

5Sumbal -Markundal-Hajin-Madwan Road Yes Yes

Satisfactory Main Construction work completed. Installation of road furniture to commence. .

. ●Not Required.

PUC certificates stands submitted Nominated

Not Required. As road has been macadamized. Not Required Not Required

Installation of Road Furniture and Thermoplastic Marking to commence.

6

Thajiwara-Shangus Road including link road to Brakpora and Magreypora

EMP has been issued to the contractor vide No. SCPL/C-703/2545 Dated: 1-11-2007 Yes

Satisfactory Most of the work completed.

●Required ●PIU has to take issue of permission for cutting of Walnut trees (Juglans regia ) from the concerned authorities.

PUC certificates stands submitted Nominated

Not required as road has been macadamized ●Established. Satisfactory Satisfactory

7Potkhah –Shrakwara-Pachar Road

EMP has been issued to the contractor vide No. SCPL/C-703/2542 Dated: 1-11-2007 Yes

Satisfactory . Main construction work completed. Installation of road furniture to commence

●Required . ●PIU to take issue of permission from the concerned authorities.

PUC certificates submitted Nominated

Not Required Road Surface already Macadamized. Not Required Not Required

Installation of Road Furniture and Thermoplastic Marking to commence.

A. Transport

● The contractor is procuring stone aggregates and bitumen concrete from approved stone crusher and hot mix plant respectively. ● Consents for Stone Crusher Plant, D.G Set & HMM stands submitted. ● Contractor has submitted the fresh copy of consent for HMM plant from procurring agency.

●Copy of consent for Stone Crusher Plant from SPCB already stands submitted.

●The contractor has been procuring stone aggregates and bitumen concrete from approved stone crusher and hot mix plant respectively. ●Consents for Stone Crusher-D.G Set and HMM Plants stands submitted by the contractor from SPCB.

●Copies of consents from SPCB already stands submitted.

APPENDIX-II

Dust Control Labour Camp Workers Safety

ENVIRONMENTAL PERFORMANCE FACT SHEET FOR THE MONTH OF MARCH 2010

Traffic SafetyNomination of Environmental & Social Safeguard Officer

Overall Status of EMP Implementation (Excellent/ Satisfactory/ Below Satisfactory/ Poor)

Environmental Consents/Clearances Required

● The contractor has established its own hot mix plant, Stone Crusher Plant, Batch Mix Plant (at Lasjan) and is in under process at SPCB level. ● Contractor has already applied for required NOC/ Consents and is in under process at SPCB level. ● Contractor has been procuring bituminous material from approved plant of M/s Tech Builders, Budgam and the contractor has submitted the required consent of that HMM plant to this office vide consent no: 527 of 2009, Dated: 10-01-2009. Penalty in the form of 10% cost of IPC bill stands withheld at ERA; w.e.f 17/09/2009 on the contracting firm M/s Bolasingh Jaiprakash Construction Ltd. after failed to comply to statutory requirements of above consents. ●The contractor is procuring stone aggregates and bitumen concrete from approved stone crusher and hot mix plant respectively. ● Copies of consents from SPCB already stands submitted.

● Copies of consents for Stone Crusher and HMM Plants from SPCB already stands submitted.

S. No. Name of Sub-project EMP Part of Contract Document

EMP being Implemented

Page 39: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Permission for Tree Cutting Crusher (Consent to Establish)

Crusher (Consent to Operate)

Hot Mix Plant

Concrete Mixer

Diesel Generator Set

Pollution Under Control (PUC) Certificates for Contractors Vehicles)

Dust Control Labour Camp Workers Safety Traffic SafetyNomination of Environmental & Social Safeguard Officer

Overall Status of EMP Implementation (Excellent/ Satisfactory/ Below Satisfactory/ Poor)

Environmental Consents/Clearances RequiredS. No. Name of Sub-project EMP Part of Contract Document

EMP being Implemented

8

Batamaloo-Tengpora & Jehangir chowk to SKIMS Road

EMP has been issued to the contractor vide No. SCPL/C-703/2544 Dated: 1-11-2007 Yes Satisfactory ●Not required.

PUC certificates stands submitted Nominated Satisfactory

Local Labourers engaged. (Non local workforce only engaged during macadamization work) Partially Satisfactory Satisfactory

9

Lethpora-Panthachowk loop including Lethpora ladoo-Pampore Khrew road

EMP has been issued to the contractor vide No. SCPL/C-703/2546 Dated: 1-11-2007

10Sangrama-Sopore-Kulangam Road

EMP has been issued to the contractor vide No. SCPL/C-703/2553 Dated: 1-11-2007 Yes Satisfactory.

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

Fresh PUC certificates submitted. Nominated Satisfactory ●Established. Partially Satisfactory Satisfactory

11Humhama-Budgam-Raithon-Arizal Road

EMP has been issued to the contractor vide No. SCPL/C-703/2547 Dated: 1-11-2007

12

Watergam-Behrampora-Hib Dangerpora-Chitlora-Rebban-Hadipora Road Yes Yes

Satisfactory Limited work Most of the Macadamized work completed ●Not required.

PUC certificates stands submitted Nominated

Satisfactory Most of the road surface has been macadamized ●Established. Partially Satisfactory

Partially Satisfactory

13 Road Yes

14 Bijbehara Langanbal Road Yes

15 Dachinpora Bridge Yes YesBridge completed. Nominated

Not Required

Labour camp being dismantled as specified in EMP Not Required

16 Papchan Bridge YesBridge completed. Nominated Not Required

Labour camp being dismantled as specified in EMP Not Required

Traffic Safety Measures Installed

17 Sonawani Bridge Yes Yes Satisfactory

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

PUC certificates stands submitted. Nominated Satisfactory

Local Labourers Engaged and Non Locals in case of concrete work. Satisfactory

Satisfactory. As no traffic movement is involved at the bridge site.

●The contractor is procuring stone aggregates and bitumen concrete from approved stone crusher and hot mix plant respectively. ●Consents for Stone Crusher, D.G Set and HMM Plants stands submitted by the contractor.

● The contractor is procuring stone aggregates and bitumen concrete from approved stone crusher and hot mix plant respectively. ● Consents for Stone Crusher Plant, D.G Set & HMM Plant stands submitted. ● Contractor has submitted the copy of consent for HMM plant from procurring agency.

●The contractor has establish its own Stone Crusher and Hot Mix Plants . ●Copies of consents from SPCB already stands submitted by the contractor. ● Fresh renewed copy of consent to operate Stone Crusher Plant submitted by the Contractor vide Consent No: 1035 of 2010 Dated: 09/03/2010.

● Contractor is procurring the aggregate material from approved Stone Crusher Plant. ●Contractor has submitted the required copy of consent of Stone Crusher Plant from SPCB.

SUB-PROJECT UNDER SUPERVISION OF PIU.

SUB-PROJECT UNDER SUPERVISION OF PIU.

SUB-PROJECT BEING SUPERVISED BY PIU.

● All the documents which were submitted by the contractor has been established in archives for records/ready reference.

● All the documents which were submitted by the contractor has been established in archives and for ready reference.

Page 40: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Permission for Tree Cutting Crusher (Consent to Establish)

Crusher (Consent to Operate)

Hot Mix Plant

Concrete Mixer

Diesel Generator Set

Pollution Under Control (PUC) Certificates for Contractors Vehicles)

Dust Control Labour Camp Workers Safety Traffic SafetyNomination of Environmental & Social Safeguard Officer

Overall Status of EMP Implementation (Excellent/ Satisfactory/ Below Satisfactory/ Poor)

Environmental Consents/Clearances RequiredS. No. Name of Sub-project EMP Part of Contract Document

EMP being Implemented

18

Handwara Zachaldara Waddur Road and Kralgund Ashpora Qazibad Road Yes Yes

Partially Satisfactory (Limited Work)

●Required. ●PIU has to take issue of permission from the concerned authorities.

PUC certificates stands submitted Nominated Satisfactory

●Kralgund-Ashpora-Qazibad Road (Established: Condition- Satisfactory) ● Handwara-Zachaldara-Waddur Road: (Established: Condition- Satisfactory) Partially Satisfactory Satisfactory

19 Wahibug Bridge Yes YesPartially Satisfactory

●Required . ●PIU to take issue of permission from the concerned authorities.

PUC certificates stands submitted Nominated.

Satisfactory As no traffic movement is involved at approaches hence only applied as per the intensity of construction vehicles. Established Below Satisfactory.

Satisfactory As no traffic is involved at or near bridge site

20 Kunzer Channapora Bridge Yes YesPartially Satisfactory

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

PUC certificates submitted Nominated Satisfactory Established Below Satisfactory

Barbed Wire & Boulder Baracading along main approach

21 Bonchak Bridge Yes YesPartially Satisfactory ●Not required.

PUC certificates stands submitted Nominated Satisfactory Established Below Satisfactory

Barbed Wire & Boulder Baracading

A. Town Roads Kargil Yes YesNo Work (Winter Period)

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

PUC certificates submitted Nominated No Work

Not Required. Local Laboures Engaged No Work No Work

B. Tharumsa-Pashkum Bridge Yes

No Work (Due to the Winter Period)

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

● Contractor has submitted a letter vide GICL/2009/059 dated: 19/12/2009 for timely compliance of above consent certificates in next working season of March 2010 Nominated

23 Tokina Bridge Yes Yes

Partially Satisfactory Limited work

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

PUC certificates submitted Nominated Satisfactory Established Partially Satisfactory

Satisfactory As no traffic is involved at or near bridge site

24Natipora-Chadora-Chrar e Shrief Road Yes Yes

Partially Satisfactory

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

PUC stands certificates submitted Nominated Satisfactory

Local labours engaged. Below Satisfactory

Partially Satisfactory

● Contractor is procuring Stone Aggregates from approved Stone Crusher Plant ●Copy of consent for Stone Crusher Plant from SPCB stands submitted.

No Work22

●Copy of consent to establish (Fresh) Stone Crusher and Wet Mix Macadam Plants already stands submitted by the contractor. ●Copy of consent to establish Hot Mix Macadem Plant already stands submitted by the contractor. ●Consents to operate above plants already stands submitted by the contractor.

● Contractor is procuring Stone Aggregates from approved Stone Crusher Plant ●Contractor has submitted the renewed copies of consents

● Contractor has submitted a letter vide GICL/2009/059 dated: 19/12/2009 for timely compliance of above consent certificates

in next working season of March 2010. ●Contractor is procuring stone aggregate from outsourcing

agency in Kargil .

● Contractor is procuring Stone Aggregates from approved Stone Crusher Plant ●Consents for Stone Crusher Plant and D.G Set already stands submitted by the contractor from SPCB.

● Contractor is procuring Stone Aggregates from approved Stone Crusher Plant ●Contractor has submitted the renewed copies of consents for Stone Crusher and Diesel Generator Set from SPCB.

pPlant, Hot Mix Plant, WMM Plant and Diesel Generator Sets. ● Contractor has already applied to SPCB for consents of above plants and the case is under process at SPCB level. ● Contractor has been procuring bituminous material from approved plant of M/s Tech Builders, Budgam and the contractor has submitted the required consent of that HMM

●The contractor is procuring stone aggregates from approved stone crusher plant. ● The Contractor has submitted the copies of consent for Stone Crusher Plant and D.G Set.

Page 41: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Permission for Tree Cutting Crusher (Consent to Establish)

Crusher (Consent to Operate)

Hot Mix Plant

Concrete Mixer

Diesel Generator Set

Pollution Under Control (PUC) Certificates for Contractors Vehicles)

Dust Control Labour Camp Workers Safety Traffic SafetyNomination of Environmental & Social Safeguard Officer

Overall Status of EMP Implementation (Excellent/ Satisfactory/ Below Satisfactory/ Poor)

Environmental Consents/Clearances RequiredS. No. Name of Sub-project EMP Part of Contract Document

EMP being Implemented

A. Leh Town Roads Yes

Work stopped due to the winter period

●Not required. ●PIU to take issue of permission from the district authorities if cutting of any Scheduled trees is involved.

PUC certificates submitted Nominated

Not Required. Local labourers available.

B. Urbis Bridge Yes

No Construction Work due to the technical reasons ●Not required.

26Hubdipora-Qaddar-Qaimoh Road Yes Yes Satisfactory

●Required. ●PIU to take issue of permission from the concerned authorities if cutting of any Scheduled trees is involved.

PUC certificates submitted Nominated Satisfactory

Established. At Qaimoh Partially Satisfactory Satisfactory

27 Sopore-Bandipora Road Yes Yes Satisfactory

●Required. ●PIU to take issue of permission from the concerned authorities.

PUC certificates submitted Nominated Satisfactory Established

Satisfactory Satisfactory

28 Saidpora Bridge Yes No Work

Construction work was due the Geo-technical fault in both wells. ●Not required.

PUC Certificates stands submitted. Nominated

Satisfactory. Complete Permanent Steel Barracading provided at approach 1 since minor traffic movement is involved at that side.

29 Sharda-Kamalkote road YesWork resumed by the Contractor.

●Required. ●PIU has to take issue of permission from the concerned authorities. Yet to submit Yet to nominate N.A

30 Padshahi Bagh Bridge Yes Yes Satisfactory Not Required

PUC certificates stands submitted Nominated Satisfactory Established. Satisfactory Satisfactory

●Contractor has already established its approved Stone Crusher Plant at Kunzer (Baramulla) and the contractor has submitted the required consent/ NOC for the above plant.

● Contractor is procuring Stone Aggregates from approved Stone Crusher Plant at Pulwama, Srinagar

which is being used for the Tokina and Soafshali subproject bridges.

●Contractor has submitted the same copy of consent for Stone Crusher from SPCB vide consent no: 368 of 2008

Dated: 18/09/2008.

● Contractor is procuring Stone Aggregate from outsourcing agency in Leh and is in process of acquiring the required

copies of consents from the agency.

●The contractor has establish its own Stone Crusher, Wet Mix Plant and Hot Mix Plants . ●Fresh Copies of consents from SPCB stands submitted by the contractor vide consent no's: 454 and 455 of 2009, Dated: 25/09/2009 for Hot Mix Plant, Wet Mix Plant and Stone Crusher Plant, respectively.

Crusher Plant at Gundi Achan, Pulwama for the sub-project under execution and details is given below ● Fresh copies of consent to establish Hot Mix Macadam Plant and Stone Crusher Plant submitted by the contractor vide consent no: 844 of 2010 & 845 of 2009/2010 Dated: 28/01/2010, respectively. ● Fresh consent to establish Wet Mix Macadam (WMM) Plant submitted by the

25

●Contractor has already applied to SPCB for aquiring of necessary consent to establish Stone Crusher Plant, HMM

and WMM Plants and is under process at SPCB level.

Page 42: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Permission for Tree Cutting Crusher (Consent to Establish)

Crusher (Consent to Operate)

Hot Mix Plant

Concrete Mixer

Diesel Generator Set

Pollution Under Control (PUC) Certificates for Contractors Vehicles)

Dust Control Labour Camp Workers Safety Traffic SafetyNomination of Environmental & Social Safeguard Officer

Overall Status of EMP Implementation (Excellent/ Satisfactory/ Below Satisfactory/ Poor)

Environmental Consents/Clearances RequiredS. No. Name of Sub-project EMP Part of Contract Document

EMP being Implemented

1 Providing, Laying, jointing, Testing, and commissioning of Water Supply pipelines under Rangil Water Supply Scheme

Below Satisfactory

Not Established Below Satisfactory Below Satisfactory

2 Nishat Water Supply –Replacement of Dal Bund Transmission Main by Nishat NFR Zindshah Masjid Transmission Mains.

Yes Yes Satisfactory/ construction work almost completed

●Cutting of forest trees and scheduled trees not involveded.

Submitted Nominated Satisfactory Not Established Below satisfactory Partially satisfactory

3 Improvement of Nishat and Doodhganga Water Supply Schemes by providing and laing of D.I pipe line Including Allied Works at Srinagar in the State of J&K.

Yes Yes Satisfactory ●Cutting of forest trees and scheduled trees not involveded.

Not Submitted Not Submitted

Not Submitted

NA Not Submitted Submitted (Validity expired)

Nominated Satisfactory Not Established Below Satisfactory Below Satisfactory

4 Construction of trunk drain, main drain, sub-mains along N.H. Bypass road including construction of pump house and other allied civil works from Pohru Chowk to Chanapora Bridge

Yes Yes Partially Satisfactory ●Cutting of forest trees and scheduled trees not involveded.

Submitted Submitted NA Electri run mixers in use

Contractor has applied for consent to SPCB

Submitted (validity expired)

Nominated Below Satisfactory

Established Partially Satisfactory Satisfactory

5 Construction of trunk drain, main drain, sub-mains along N.H. Bypass road including construction of pump house and other allied civil works Rawalpora Chowk to Tengpora Bridge

Yes Yes Satisfactory ●Cutting of forest trees and scheduled trees not involveded.

Not Submitted Submitted (validity expired)

NA Not submitted Not Submitted Submitted (Validity expired)

No Satisfactory Not Established Partially Satisfactory Satisfactory

6 Construction of trunk drain, main drain, sub-mains, laterals along N.H. Bypass road including construction of pump house and other allied civil works Bemina chowk to Parimpora Fruit Mandi

Yes Yes Partially Satisfactory ●Cutting of forest trees and scheduled trees not involveded.

Submited (validity expired)

No Satisfactory Not Established Below Satisfactory Partially Satisfactory

7 Construction of 16 Public Toilets Yes Yes Satisfactory/ Limited construction work

●Cutting of forest trees and scheduled trees not involveded.

NA Nominated

8 WTP & Pumping Stations - Renovation / Revamping of Civil-Electro-Mechanical units

Yes Yes Satisfactory ●Cutting of forest trees and scheduled trees not involveded.

Not Submitted Not Submitted

NA Not submitted Not Submitted Submitted Nominated NA Established (in the premises of line deptt. Office)

Partially Satisfactory NA

9 Construction of Approach Road to Achan Landfill site, Srinagar

No Construction work during the month

Limited Construction works

Not Submitted

NA

NA

As reported by DSC-II, the supervision of the sub-project is handed over to DHV/PSC, JKUSDIP in the month of February, 2010

Construction work completed, sub-project stands commissioned in the month of March (15h March 2010)B. Urban

Page 43: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 35 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER – 5

ACTIVITIES DURING MARCH 10

Name of the Contract Activity Date

Jammu

Urban

Construction of civils work of Tube Wells in Jammu Lot-2 Notification of Award 25-Mar-2010

Page 44: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 36 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER – 6

MEETINGS HELD DURING MARCH 10

S.No Purpose Date Chaired By

1 Variation cases of Jammu Urban 2/3/2010 CEO ERA J&K

2 To review the progress of Kashmir Urban drainage Packages 16/3/2010 Directors (U) J&K

ERA

3 Time Extension cases of Jammu and Kashmir Urban 20/3/2010 CEO ERA J&K

4 Variation cases of Jammu Transport 22/3/2010 Directors J&K ERA

Page 45: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 37 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER 7

CONSULTANT STAFFING - MOBILISATION OF KEY PERSONNEL

S.No Consultancy Scheduled No. of Key Experts

Key Experts Present during the Month for more

than 15 days.

Key Experts Present during the Month for less

than 15 days. 1. PMC 12 5 -

2. DSC I 11 3 -

3 DSC II 12 3 -

4 DSC III 19 11 1

5 DSC IV 24 9 2

Page 46: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 38 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

CHAPTER 8

PROGRESS OF WORKS

ANNEXURE - IA URBAN JAMMU WATER SUPPLY & DRAINAGE

Page 47: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 21 22 23

Contracts Awarded 1 UJ/WS/03 and

partof1/03/LCB/06

Replacement of Rising mains, laying new rising mains & gravity mains in various parts of Jammu city [Strengthening of existing system (Phase-I)

600-100 mm dia DI/MS Pipe LineLength - 60 km

Revised Scope-57.26

14-Sep-06 27-Mar-08 /31-Dec-08

232.48 200.21 201.10 100% 77% 0% 0% 100% 77% 214.97 0.00 214.97 M/S Electrosteel Casting Ltd.

PCSS No 0019.

2 UJ/WS/03andpartof1/03/PhII/LC

B/06

Replacement of Rising mains, laying new rising mains & gravity mains in various parts of Jammu city [Strengthening of existing system (Phase-II)]

250 - 100mm dia Pipe LIne.

Length 25.14 kmsRevised Scope-14.14

10-Feb-07 25-May-200831-March-09

70.50 76.53 49.50 100% 73% 0% 0% 100% 73% 45.97 0.00 45.97 M/S Electrosteel Casting Ltd.

PCSS No 0032

20 JAMMU WATER SUPPLY

RS.)

Contract fore closedLocation of work:-All tube well Sites in Jammu East and Company Bagh

Contract fore closed .

Location of work :-Gangyal , Kunjwani, Apna Vihar, KC Colony, Chak Bijjan, Jamwal Residency

3 UJ/WS/03/01/LCB/06

Construction of 22 Tube Wells under Jammu (East) Water Supply Rehabilitation

Tubewells 22

24-Jun-06 22-Jul-07 /22-Jan-08/30-June-0930-Sep-09

28- Feb -10

109.80 124.45 140.70 100% 99.29% 0% 0.00% 100% 99.29% 114.76 0.00 114.76 M/s Hanuman Tube Well Co.PCSS No 0014.

APNA VIHAR IN THE VICINITY Functional w.e.f 18.11.08. Handed over to P.H.E

SAINIK COLONY SECTOR C Functional w.e.f 08.01.08. Handed over to P.H.E

SAINIK COLONY SECTOR G Functional w.e.f 04.12.08. Handed over to P.H.E

ADARSH ENCLAVE Functional w.e.f 25.06.08. Handed over to P.H.E

SANJAY NAGAR Functional w.e.f 02.04.08. Handed over to P.H.E

KUNJWANI Functional w.e.f 12.12.08. Handed over to P.H.E

REHARI PARK Functional w.e.f 09.12.08. Handed over to P.H.ETRIKUTA NAGARSECTOR-5 Functional . Handed over to P.H.E

BALMIKI NAGAR Functional . Handed over to P.H.E

GANGYAL Functional w.e.f 13.11.08. Handed over to P.H.E

DEEP NAGAR Functional w.e.f 15.11.08. Handed over to P.H.E

DIGIANA Functional . Handed over to P.H.E

BABLIYANA Functional . Handed over to P.H.E

NARWAL NAKARIN Functional . Handed over to P.H.E

KC COLONY Functional . Handed over to P.H.E

JAMWAL RESIDENCY Functional . Handed over to P.H.E

NANAK NAGAR SEC-8 Functional . Handed over to P.H.E

CHHANNI -HIMMAT SEC 1A Functional .SEC-1A Functional .

PROCUREMENT NARWAL Functional .

Page 48: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

4 UJ/WS/02andpartof3/02/Phase-

III/NCB/07

Laying new rising mains in various parts of Jammu West Phase III.

100 - 250 mm dia DI pipe 300 - 450 mm dia

MS Pipe Length - 89 Km

27-Nov-07 6-Jun-0927-Jun-10

494.87 526.50 541.50 100% 83.16% 0% 2.87% 100% 86.03% 364.46 13.07 377.53 M/S Pratibha Industries

Ltd.PCSS No 0054.

Interconnection with PHE System

Line departments has been requested by ERA for granting permission .

5 UJ/WS/03/04/NCB/07

Design, construction, supply, Installation, Testing, Commissioning, Trial run, Operation and Maintenance of Civil, Mechincal, Electrical Equipments of intake pumping nar Boria EAST.[LOT-1]

1.8 MGD Intake Structure

19-Dec-07 30-Jun-0931-Mar-10

71.53 71.53 77.60 100% 69.08% 0% 0.44% 100% 69.52% 47.91 0.00 47.91 M/S SMS Prayawaran Ltd. PCSS No 0066.(Design as you

Built)

Scope: 89 km. Pipe Line Laid - 76.35 Kms.Pipe Line Tested - 63.31Kms.Pipe Line Commissioned - 38.37 Kms.Road restoration (WBM) - 47.25 Kms.Location of work:Keran, Roop Nagar, Trikuta Nagar, Muthi, Nagawala, DC Block, Balmiki

Out of 16 nos river piles, 16 nos piles completed at pile no. P1, P2, P3, P4, P5, P6, P7, P8, P9, P10, P11, P12, P13, P14, P15 & P16 Out of 10 nos. shore piles, 8 nos. shore pile completed, 1 nos in progressPipe : MS pipe 28.80m laidPump Room : Reinforcement of beam in progressB C ti f b b t SP4 & SP5 t l l

6 UJ/WS/03/04/NCB/07

Construction of Over Head Tanks (OHT's) & Ground Level Service reserviors (GLRS's) and other allied works in Jammu city EAST [LOT-2]

9 - OHT`s4 - GLSR`s

10-Dec-07 23-Jun-0923-Mar-1030-Nov-10

118.76 117.70 130.50 100% 82.52% 0% 4.18% 100% 86.70% 94.74 2.30 97.04 M/S Prabhu Dayal Kanojiya. PCSS No 0061.(Design as you

Built)

Interconnection with PHE System.

Line departments has been requested by ERA for granting permission

Rail Head Commissioned

D/C Block Balmiki Nagar Commissioned

Shastri Nagar Finishing Works in progress

Beam : Concreting of beam between SP4 & SP5 at level completed, Reinforcement in progressColumn : Concreting of beam at SPc9 & SPc10 at 306m level completed, Reinforcement in progressLocation of work:Intake At Boria

T/W -9 PHE Sub division Commissioned

Alternate location identified near Ravi Gas Agency Director (U) requested Divisional commissioner for allotment of land.

Shastri Nagar Finishing Works in progress

T/W -1 Finishing Works in progress

PHE Complex, Trikuta Nagar

Finishing Works in progress

Nanak Nagar, Sec -7 Finishing Works in progress

PHE Complex, Channi himmat

Finishing Works in progress

Gandhi Nagar Extn-II Design and Drawing approved

PHE Complex,Narwal Commissioned

Tube Well No.1 Finishing Works in progress

Boria Pumping Station Finishing Works in progress

Page 49: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

7 UJ/WS/03/04/NCB/07

Construction of Over Head Tanks (OHT's) & Ground Level Service reserviors (GLRS's) and other allied works in Jammu city[ EAST LOT-3]

12 - OHT`s5 - GLSR`s

15-Feb-08 21-Aug-0911-Jun-10

90.81 91.61 99.90 100% 67.00% 0% 1.02% 100% 68.02% 59.47 2.12 61.58 M/s Modern Constructions Pvt Ltd. PCSS

No 0074(Design as you

Built)

1.Interconnection with PHE System

Line departments has been requested by ERA for granting permission .

PHE Complex,Trikuta Nagar

Shaft wall in progress

* Design to be submitted by contractor

Dashmesh Nagar Shaft wall in progress

Sainik Colony,Sector- (D) Shaft wall in progress

Ajeet Nagar Shaft wall in progress

Sainik colony Sec-A Dome work in progress

Langer Shaft wall completed

Sainik colony Sec-C Shaft wall completed

Thanger Shaft wall in progress

Sainik Colony Sec F Shaft wall completed

Babliyana Dome work in progress

Apna Vihar Shaft wall in progress

8 UJ/WS/2/02/NCB/07

Desing and construction of Over Head Tanks (OHTs) & Ground Level Service Reserviors (GLSR's) and other allied works in Jammu city WEST (LOT-1)

6 - OHT`s3 - GLSR`s

10-Dec-07 23-Jun-0913-May-10

92.72 90.42 96.80 100% 63.47% 0% 2.25% 100% 65.72% 33.17 0.00 33.17 M/S Prabhu Dayal Kanojiya. PCSS No 0063.(Design as you Built)

Interconnection with PHE System.

Line departments has been requested by ERA for granting

Bandhu Rakh Design and Drawing approved

Dhodhi Gujjar Finishing work in progress

Sainik Colony,Sector F/G (F)

Finishing work in progress

Qasim Nagar Finishing work in progress

Uttam Nagar Design and Drawing approved

PHE Procurement Division (Narwal Jammu)

Partially commissioned

Nawabad near B.N College (Sunjwan)

Design and Drawing approved

* Design to be submitted by contractor

g gpermission .

Bakshi Nagar Finishing work in progress

Ram Mandir Gurha Bakshi Nagar

Finishing work in progress

Page 50: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

Parade Shaft wall in progress

Sarwal Design yet to be Submitted

Parade Dome work completed

Rehari/New Plot Finishing work in progress

* Design to be submitted by contractor

Amar Colony Shaft wall in progress

Id Gah Design yet to be Submitted

Company Bagh Completed

9 UJ/WS/2/02/NCB/07

Desing and construction of Over Head Tanks (OHTs) & Ground Level Service Reserviors (GLSR's) and other allied works in Jammu city WEST.(LOT-2)

6 - OHT`s3 - GLSR`s

29-Dec-07 6-Jul-099-Mar-10

76.8 76.80 82.30 100.0% 98.91% 0.0% 0.98% 100.0% 99.89% 68.76 0.00 68.76 M/S Maverick Dev. & Col. Pvt. Ltd. PCSS No 0067(Design as you Built)

Interconnection with PHE System

Line departments has beenrequested byERA forgranting permission .

Suryavanshi Vihar commissioned

Roop Nagar Stage-III commissioned

Ranjeetpura commissioned

Roop Nagar Stage-II commissioned

Rajpura commissioned

10 UJ/WS/2/02/NCB/07

Desing and construction of Over Head Tanks (OHTs) & Ground Level Service Reserviors (GLSR's) and other allied works in Jammu city WEST(LOT-3)

10- OHT`s2 - GLSR`s

21-Nov-07 4-Jun-0930-Jun-10

78.5 84.80 89.00 100.0% 91.17% 0.00% 2.65% 100.0% 93.82% 74.61 0.00 74.61 M/S Ch. Jagar Singh & Janak

Raj Gupta. PCSS No 0053. (Design as you

Built)

1. Interconnection with PHE System

1. PHE department requested for making interconnection.

Ranjeetpura commissioned

Indira Vihar Partially commissioned

* Design to be submitted by contractor

Relief Commissioner Finishing Works in progress

CPS Muthi commissioned

Roop Nagar Stage-II commissioned

CPS Bantalab commissioned

Page 51: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

Puran Nagar Finishing Works in progress

Dharmal Finishing Works in progress

Tomal Finishing Works in progress

Muthi village Finishing Works in progress

Resham ghar Finishing Works in progress

Muthi Tube well no.5 Finishing Works in progress

Janipur Stage IV Finishing Works in progress

Shifting of HT Electrical line

PDD yet to start work

11 UJ/WS/2/01/NCB/06

Construction of Tube Wells , Installation of Mechnical and Electrical Equipment and civil works under Jammu city water supply Rehabilitation programme. LOT- 1

10 Nos. Tube wells 4-Jan-08 10-Apr-0930-Nov-0928-Feb-10

45.55 61.75 63.20 100.0% 99.58% 0.00% 0.00% 100.0% 99.58% 63.24 5.32 68.56 M/s Gurnam Singh &

Co.PCSS No 0069.

Agriculture Complex Talab Tillo

Shaft wall in progress

Paloura Top Dome work in progress

Sitlee Finishing Works in progress

* Design to be submitted by contractor

Janipur Stage-IV Finishing Works in progress

Relief Commissioner Finishing Works in progress

Science College-I (Back side of main cricket ground)

Functional Handed over to P.H.E

Play Ground Medical Colege

Functional Handed over to P.H.E

PHE complex Barnai Functional Handed over to P.H.E

Rajinder Nagar Functional Handed over to P.H.E

Science College-II (left side of Hostel)

Functional Handed over to P.H.E

Science College-III (left corner of main cricket ground)

Functional Handed over to P.H.E

Durga Nagar Functional Handed over to P.H.E

Dental College Functional Handed over to P.H.E

Relief commissioner office Functional Handed over to P H ERelief commissioner office Functional Handed over to P.H.E

B.C Road kabir Colony Functional

Page 52: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

12 UJ/WS/2/01/NCB/06

Construction of Tube Wells , Installation of Mechnical and Electrical Equipment and civil works under Jammu city water supply Rehabilitation programme LOT-2

10 Nos. Tube wells 4-Jan-08 10-Apr-0930-Nov-0928-Feb-10

44.14 59.15 59.50 100% 99.52% 0% 0.00% 100% 99.52% 59.51 0.00 59.51 M/s Gurnam Singh & Co. PCSS No 0070

Indira vihar JDA Park Functional and handed over to PHE

Bua Dati Mandir Paloura Functional and handed over to PHE

Suryavanshi Nagar Functional and handed over to PHE

CPS Rajpura Mangotrian Functional and handed over to PHE

13 UJ/WS/2/01/NCB/06

Construction of Tube Wells , Installation of Mechnical and Electrical Equipment and civil works under Jammu city water supply Rehabilitation programme LOT-3

10 Nos. Tube wells 4-Jan-08 10-Apr-0930-Nov-0928-Feb-10

43.51 60.55 59.40 100% 99.51% 0% 0.00% 100% 99.51% 59.37 0.00 59.37 M/s Gurnam Singh & Co.PCSS No 0071.

Gole Gujral near B.H school

Functional and handed over to PHE

Agriculture Complex Functional and handed over to PHE

Near Shamshan Ghat Functional and handed over to PHE

Dharmal Functional and handed over to PHE

Poonch House (Bantalab) Functional and handed over to PHE

Himmat Colony Functional and handed over to PHE

14 UJ/WS/2/01/NCB/06

Construction of Tube Wells , Installation of Mechnical and Electrical Equipment and civil works under Jammu city water

l R h bilit ti

Civil works for 30 Nos Tube well

7-Jan-08 6-Jul-0915-Dec-0928-Feb-10

21.78 25.78 26.30 100% 100% 0% 0.00% 100% 100% 18.84 0.00 18.84 M/s Open Survey World.

PCSS No 0072.

CPS -Bantalab Functional and handed over to PHE

CPS Muthi Village Functional and handed over to PHE

Waziran Gali Bhori Talab Tillo

Functional and handed over to PHE

CPS Muthi Functional and handed over to PHE

Roop Nagar Stage-II Functional and handed over to PHE

Patoli brahmana Functional and handed over to PHE

Keran Functional and handed over to PHE

Lower Barnai(Shamshan Ghat)

Functional and handed over to PHE

Lower-Muthi-1(Lale-Da-Bagh)

Functional and handed over to PHE

Laxmi Narayan mandir Gandhi Nagar

Functional

Building work completed for all 31 nos. pump rooms

supply Rehabilitation programme LOT-4

Page 53: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

15 UJ/WS/4/1/NCB/07

Replacement of worn out pipes and Strengthening of distribution network Phase-1

80 - 250 mm dia DI Pipe

Length - 85 km

15-Feb-08 21 - Aug-0929-Aug -10

295.32 341.31 349.50 100% 69.32% 0% 2.80% 100% 72.12% 207.44 11.87 219.31 M/s Modern Constructions Pvt Ltd.PCSS No 0075.

1. Interconnection with PHE Systemand road cuttingpermission fromR&B deprtmentfor balance work.2. Inadequateresources deployed by thecontractor.3. Slow progressof work .

1. Linedepartments has beenrequested byERA forgranting permission.2. Contractorhas beenrequested several times todeploy adequate resources.3 Notice for

16 UJ/WS/4/2/NCB Replacement of worn out pipes 80 - 250 mm dia DI 25-Apr-08 08 - Nov-09 324.20 367.83 374.70 100% 76.14% 0% 0.00% 100% 76.14% 225.55 5.89 231.44 M/S SMS 1. 1. Line

Scope-85 KmPipe Line Laid - 61.50 Kms.Pipe Line Tested - 31.64 Kms.Pipe Line Commissioned - 5.83 Kms.Road restoration (WBM) - 48.58 Kms.Location:Gandhi Nagar,Chand Nagar, Shastri Nagar

Scope-83 Km16 UJ/WS/4/2/NCB/07

Replacement of worn out pipes and Strengthening of distribution network Phase-2

80 250 mm dia DI Pipe

Length - 83 km

25 Apr 08 08 Nov 0929-Aug -10

324.20 367.83 374.70 100% 76.14% 0% 0.00% 100% 76.14% 225.55 5.89 231.44 M/S SMS Prayawaran Ltd. PCSS No 0079

1. Interconnection with PHE Systemand road cuttingpermission fromR&B deprtmentfor balance work.

1. Linedepartments has beenrequested byERA forgranting permission .Matter beingpersued with

17 UJ/WS/5/01/NCB/07(Ph-I)

Re-Development of 38 tube wells and Replacement of Electrical/Mechanical Equipment of tubewells under Jammu city Water Supply Rehabilitation programme.(Redevelopment only) [LOT-1]

Tube Wells38

30-Jan-09 29-Oct-0931-May-10

8.37 8.37 7.40 100% 62.98% 0% 5.28% 100% 68.26% 3.08 0.78 3.86 M/s Shiv Drillers

PCSS No. 0096

18 UJ/WS/02/01A/ Construction of Tube Wells Tubewells 18-Jan-10 8-Feb-11 47.08 47.08 50.50 100% 0.5% 0% 0.0% 100% 0.5% 0.00 0.00 0.00 Hanuman Tube

Scope 83 KmPipe Line Laid - 62.66 Kms.Pipe Line Tested - 59.51 Kms.Pipe Line Commissioned - 11.29 KmsRoad restoration (WBM) - 38.08 Kms.Location:Greater Kailash, Sainik Colony

Work completed at 27 nos tube wells Gole (new), Sainik Colony sec-F, Tw No: 10 Cultural Academy, SICOP Ph-III Gangyal, Peerkho, Dodhi Gujjar, Kunjwani Bye Pass, Women College Gandhi Nagar, T/w no.II company bagh, Boria XI, Udheywala - IV, Udheywala - III, Channi Himmat (Old), Boria - 9, Col. Colony Talab Tillo,Barnai-II,Rail head, Samadiyan tw no-7, Samadiyan tw no. 11, Tube well no. 1, Tube well no. 9, RBI Tube well, Delli (New), Khadwala Trikuta Nagar, Sec 3 Trikuta Nagar, Company Bagh T/w No. 17 & T/w no. 8

Drilling in progress at DelliNCB/09 installation & commissioning of

Mechanical / Electrical Equipment in Jammu Lot-1

6 well Co.

19 UJ/WS/02/01A/NCB/09

Construction of civils work of Tube Wells in Jammu Lot-2

Tubewells 6

6.44 6.44 4.50 100% 0% 0% 0% 100% 0% 0.00 0.00 0.00 M/s Open Survey World. PCSS No

Contracts Awarded Jammu Urban Water Supply 2273.15 2438.79 2503.90 1755.84 41.34 1797.17

Total Urban Jammu Water Supply 2273.15 2438.79 2503.90 1755.84 41.34 1797.17

JAMMU EQUIPMENTContracts Awarded

20 ERA/URBAN/WS/01

Supply and Delivery of WaterTankers of Capacity 4 KL and 9KL, Mounted on Suitable CarrierVehicle including Pumps andDelivery Hoses etc. Complete

9 kl - 15 nos4 kl - 6 nos

13-Apr-06 12-Oct-06 19.98 19.98 19.90 100% 100% 0% 0% 100% 100% 17.24 0.00 17.24 M/S Eicher PCSS

No.0010A & 0010B

Final Bill to be finalised

Contract completed

21 Supply of Water Tankers LOT-1 9 Kl 9 Nos 24-Mar-09 14-Jul-0931 -Jan 10 8.61 8.606 8.60 100% 15% 0% 0% 100% 15% 0.00 0.00 0.00

M/S Ashoka Leyland PCSS

No.0097

g p g

Total 21 water Tankers (9KL=15 AND 4KL=6)received by J&K ERA and Handed over to PHED

.

Notification of Award issued on 25.03.2010

Equipments reached at Jammu

22 Supply of Water Tankers LOT-2 4 KL 5 No 24-Mar-09 14-Jul-0931 -Jan - 10 4.08 4.084 4.10 100% 15% 0% 0% 100% 15% 0.00 0.00 0.00

M/S Ashoka Leyland PCSS

No.0098

Page 54: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

Procurement of Equipment and vehicle for Garbage and Drain cleaning in Jammu & Srinagar GROUP-1

23 J&K/UJ&S/SWD/09/IS/06

LOT-1 Front End Loader 7 No

21-Nov-07 2-Apr-08 7.50 7.50 7.50 100% 100% 0% 0% 100% 100% 7.26 0.00 7.26 M/S ESCORTS Construction Equipments,

Faridabad PCSS No 60

Final Bill to be finalised

24

Lot-2A Bachoe Loader cum Excavator 4 no.

8.23 8.23 8.20

100% 100% 0% 0% 100% 100% 0.00 7.50 7.50M/S JCB India LimitedPCSS No. 0099

25 Lot- 2 B (Skid Loader-4no).

8.49 8.49 8.50

100% 100% 0% 0% 100% 100% 0.00 7.24 7.24M/S JCB India Limited

Delivery of equipment completed Final Bill to be finalised

Delievry of equipment completed

J&K/UJ&S/SWD/09/02/IS/08

28-Apr-09 17-Aug-0931-Jan-10

PCSS No. 0100

26 J&K/UJ&S/SWD/09/02/IS/09

Procurement of Equipment and vehicle for Garbage and Drain cleaning in Jammu & Srinagar GROUP-1 LOT-3A

(Garbage cover carrier Tipper -3.5 cum -6no.)

15-Jan-10 4-May-10 5.13 5.13 5.10 100% 15% 0% 0% 100% 15% 0.00 0.00 0.00

M/s Tata Motors

27 J&K/UJ&S/SWD/09/02/IS/09

Procurement of Equipment and vehicle for Garbage and Drain cleaning in Jammu & Srinagar GROUP-1 LOT-3B

(Garbage cover carrier Tipper - 8 cum -10 no.)

15-Jan-10 4-May-10 13.25 13.25 13.30 100% 15% 0% 0% 100% 15% 0.00 0.00 0.00

M/s Tata Motors

28

J&K/UJ&S/SWD/09/02/IS/09

Procurement of Equipment and vehicle for Garbage and Drain cleaning in Jammu & Srinagar GROUP-2

(Dumper Placer-4.5 cum-10 no.,Garbage Container-4.5cum-175)

19-Dec-09 8-Jul-10 16.31 16.31 14.60 100% 15% 0% 0% 100% 15% 0.78 0.00 0.78M/s Swaraj Motors

GROUP-329 LOT-1 (Suction cum Jetting

machine-7.5KL-2no., Suction cum jetting machine-4kl-2no.) (Suction machine-

17-Nov-07 30-Jun-0830-Jun-09

13.27 14.69 16.300 100% 100% 0% 0% 100% 100% 13.38 0.00 13.38

M/S TPS Manf & Const Pvt

Ltd. PCSS No

Final Bill to be finalised

Delivery awaited

Delievry of equipment completed

Delivery awaited .

Delivery awaited .

(7.5KL-2no., Suction machine-4-KL-2no.)

55

30 Lot-2- Trolley Mounted Sewer Roading Equipment-2no.)

20-Nov-07 27-Jun-08 0.90 0.90 0.90 100% 100% 0% 0% 100% 100% 0.00 0.00 0.00 M/S KAM - AVIDA. PCSS

No. 59.

Final Bill to be finalised

Contracts Awarded Jammu Equipment 105.74 107.16 107.00 38.65 14.73 53.39Total Urban Jammu Equipment 105.74 107.16 107.00 38.65 14.73 53.39

Delievry of equipment completed

Page 55: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

JAMMU DRAINAGE Contracts Awarded

211.30 238.60Work Scope in Km Completed in Km

Earth work 13.24 10.39

PCC M 7.5 5.82 4.19

PCC M 15 5.31 3.81

PCC/RCC For Bed 7.93 6.47

RCC walls 5.56 3.96

Brick Masonary 5.31 3.81

RCC covered slab 7 76 5 21

87.6% 0% 0.00% 100% 87.6% 154.3231 J&K/JU/SWD/12/01/LCB/06

Rehabilitation and Chanelization of Existing Primary Drains and Construction of New Deep Drains of Talab Tillo Area.

13.Km 18-Sep-06 28-Sep-0830-June-0928-Jan-1030-Nov-10

194.26 100% 0.00 154.32 M/S Prabhu Dayal Kanojia. PCSS No 0021.

1.H.T Electrical Poles (4-5 Nos) falling in between Janipur Nallah Alignment at Ch. 3200 - 4200 .2. Shifting of 200mm dia water supply pipe line at ch 3075 m.

1. PDD department has been requested by ERA for shifting of HT electrical poles .2. PHE department has been requested by ERA for shifting of pipe line estimate required from PHE .

RCC covered slab 7.76 5.21

RCC Box Culverts 7 7

297.71 314.30 Work Scope in Km Completed in Km

Earth work 23.15 21.23

PCC M 10 18.29 16.71

PCC M 15 4.29 3.68

PCC/RCC For Bed 18.84 17.22

RCC walls 15.58 13.85

Brick Masonary 4.07 3.49

Rehabilitation and Chanelisation of Existing Primary Drains and Construction of New Secondary Drains Upstream of Akhnoor Road

20 km 2-Mar-07 7-Mar-0930-June-0907-July-10

1. Durga Nagar ch 342- 382 m - Land dispute created by local public.2. Om Nagar Nallah ch 1091-1126m - court stay.

1. JDA authority has been requested by ERA for resolving land dispute2. Concerned land lord has agreed to withdraw court notice

100% 89.6% 253.93 7.88 261.81 M/S Valecha Multitech (JV). PCSS No 0034

228.20 100% 89.5% 0% 0.06%32 UJ/SWD/14&15/01/LCB/06

RCC covered slab 5.24 4.94

RCC Box Culverts 35 35

195.71 206.70 Work Scope in Km Completed in Km

Earth work 5.83 5.65

PCC M 10 5.83 5.63

RCC Bed 3.16 3.13

PCC Bed 5.43 5.23

RCC walls 3.16 3.13

RCC covered slab 0.075 0.075

RCC Box Culverts 9 7

33 UJ/SWD/Part-10/02/LCB/06

Rehabilitation and Chanelisation of Landoichai Primary Drain

6 Km 2-Mar-07 7-Sep-0830-June-0907-Jan-1030-June-10

173.93 96% 181.54 9.82 191.37 M/S Laxmi Narayan

Agarwal,Jaipur PCSS No 0033

100% 95% 0% 0.94% 100%

Page 56: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

34 UJ/PT/06/01/LCB/06

Construction of Public Toilets in Jammu City

25 nos 18-Sep-06 24.60 24.60 24.60 100% 80% 0% 3.16% 100% 83% 19.96 0.54 20.50 M/s Sulabh International PCSS No 0038.

24-Mar-07 24-Sep-0730-Jun-0931-Dec-0931-Sep-10 SANJAY NAGAR Functional

SAINIK COLONY Functional

DOGRA CHOWK, COMPANY BAGH

Functional

BUS STAND Functional

BAKSHI NAGAR OPP. POLICE STATION.

Functional

MOHINDER NAGAR Functional

GANGYAL Functional PLOURA Functional

OLD JANIPUR Functional

DC. OFFICE Functional

TRANSPORT NAGAR Functional

PLOURA Functional

PARKING AREA SUPER BAZAR.

Functional

DENTAL HOSPITAL WARD NO. 17

Functional

GOVT. MEDICAL COLLEGE, JAMMU FACING MAIN

Finishing work in progress

MOHALLA PAHARIAN Functional

CHABIL WALI GALI Functional

PARKING AREA PURANI MANDI

Functional

JALABI MORH SUBHASH NAGAR

Functional

work has been stopped as site is coming under proposed BC road flyoverwork has been stopped due to hindrance by pulic

HOSPITAL, CD HOSPITAL

GREEN BELT PARK, GANDHI NAGAR

Brick work in progress

REHARI CHOWK NEAR PASSANGER SHED.

Survey completed and Earth work in progress

GOVT. MEDICAL COLLEGE, JAMMU FACING TOWARDS MAIN ROAD

Finishing work in progress

CHANNI HIMMAT Brick work of parapit wall in progress

REHARI CHOWK NEAR DEVICHAND PARK

Survey completed

TRANSPORT NAGAR Work not started

WARD NO:63, BANTALAB.

Slab completed

Contracts Awarded Jammu Drianage 620.99 729.32 784.20 609.76 18.24 627.99

Total Jammu Urban Drainage 620.99 729.32 784.20 609.76 18.24 627.99

2999.88 3275.27 3395.10 2404.24 74.31 2478.55

TRANSPORT NAGAR YARD NO. 6

Work not started

Total Contracts Awarded Urban Jammu

Page 57: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March‐ 10 Annexure ‐ IAMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

sign

ruct

ion

sign

ruct

ion

sign

ruct

ion

Upto Ending Feb During Upto

Ending

RemarksSuggestions

Cumulative Progress upto

Mar 10

Expenditure (IN MILLION RS.)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress/

Contract Package Cost/

Engineers Estimate/Indicative

Cost (IN

MILLION RS )

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

S.No Contract Package No. Contract Package Description

Technical Specifications/ Scope

of work

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Likely Cost at Completion (In Million

Rs)

Des

Con

str

Des

Con

str

Des

Con

str Ending Feb

10 Mar 10 Ending Mar 10

RS.)

JAMMU EQUIPMENTContracts Tendered

Augmentation of 33/11 KV receiving station in Jammu east & Jammu west-besided creating 33 KV new lines & 11 KV independent Feeders for PHE/Tube well Procurement of Electrial equipments & goods in 6 Packages

190.54 190.54 190.54 100% 0% 0% 0% 100% 0% 0.00 0.00 0.00

41 Electrical/ Mechanical 75.00 75.00 85.00 0.00 0.00 0.00

Jammu Urban /EE/01-06

Transformer-28Transmission line-

112km

Bid Evaluation in progress for Package no. 5 Dead line for submission of Bids for packages 1 & 3 extended upto 21-04-10

35-40

Equipment for Pumping Station at Jammu

Total Contracts Tendered Equipments 265.54 265.54 275.54 0.00 0.00 0.00

Total Contracts Tendered Urban Jammu 265.54 265.54 275.54 0.00 0.00 0.00

3265.42 3540.81 3670.64 2404.24 74.31 2478.55Total Urban Jammu

IFB Issued on 25.03.10

Page 58: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 39 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ANNEXURE - I B URBAN KASHMIR WATER SUPPLY & DRAINAGE

Page 59: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IBMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

S.No Contract Package No.

Contract Package Description

Technical Specifications

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Package Cost/

Engineers Estimate/Indicative

Cost

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)Contract

Value/Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10 Likely Cost at

Completion (In Million

Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

C C C

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 21 22 23

Contracts Awarded

1 SU/WS/8/01/06 Rangil Water Supply - Transmission Main

700-150 diaOrignal Scope

47.45Resised Scope

51.63 Km

10-May-0601-Dec-07 /31-Aug-0930-Nov-09

271.5 281.051 314.00 100% 96.65% 0% 0.00% 100% 96.65% 277.61 14.50 292.11

M/s Pratibha Industries Ltd.

PCSS No 0013.

Completed

SU/WS/8/04&6/

Nishat Water Supply -Replacement/ Realignment of Tale Manzil Transmission

700 & 300 diaOrignal Scope

17-Oct-0819th August 2009 (For

D dhM/S Pratibha I d t i Ltd

In respect of Nishat – Talie Manzil package, underground utilities yet to be identified

MOU with R&B Department signed.

Doodhganga part completed and commissioined. Nishat - Talie Manzil part in

KASHMIR WATER SUPPLY

Physical Progress Pipe laid ---- 51.63 KM out of 51.63 KmPipe tested ----- 51.63 Km out of 51.63 KM

Total Pipe Line Laid = 16.12 Km out of 23.74 KmTotal Pipe Line Tested = 14.32 Km out of 23.74 Km

-

20

2 SU/WS/8/04&6/06 Mains & Doodganga

Water Supply - Improvement & extension of transmission main

g p24.97 Km

Revised Scope 23.74

9-Jul-07 Doodhganga line) and 30th June 2010 (For Nishat Talley

Manzil portion)

196.90 208.44 238.00 100% 38% 0% 0% 100% 38% 121.03 7.40 128.43 Industries Ltd. PCSS No

0046.

Manzil part in progress

3 SU/WS/8/07/06

WTP & Pumping Stations - Renovation / revamping of Civil, Electro-Mechanical units

5 extg WTPs 30-Oct-07

2-May-0915-Oct-0931-Jan-10

31-May -10174.62 184.47 204.00 90% 90% 0% 0.0% 90% 90% 147.40 9.95 157.35

M/S Technofab Engineering Ltd. PCSS No 0051.

Clarifloculator -Commissioned.

ALUSTENG

Two DG Sets -----INSTALLED. Cabling------COMPLETED. Back wash Tank---55% Completed. Alum Mixing, stabilizer and LT Panel---INSTALLED 1 No blower and second on in progress----Installed

DOODHGANGA

Backwash Tank--------- Completed. All Backwash pumps,DG Sets,,LT Panel,Sluice Value------Installed. Air Blowers (3 No's),Stabilizer ( 3 No),LT Panel (3no's) Alum Mixing and Flash Mixing----Commissioned.Chlorination Rooms-----75% Completed. 6) DG Sets commissioned.

NISHAT

Clarifloculator-----90% Completed. DG sets - 4Nos , Backwash Pumps--6Nos ,Alum Mixing (8 Nos)and Flash Mixing(2Nos),LT Panel( 4 No's), Air Blowers ( 3 No's )---INSTALLED. 1 Stablizer of 150KVA commissioned at 2.2 MGD, Stabilizer at 4 MGD Plant Installed, Stabilizers 3 Nos installed. Circular Backwash Tank---35% Completed. 6) Rectangular Backwash Tank-60% Completed. 7)Chlorination rooms---40% Completed.

Page 60: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IBMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

S.No Contract Package No.

Contract Package Description

Technical Specifications

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Package Cost/

Engineers Estimate/Indicative

Cost

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)Contract

Value/Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10 Likely Cost at

Completion (In Million

Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

C C C

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 21 22 23KASHMIR WATER SUPPLY

20

4 SU/WS/8/05/06

Nishat Water Supply -Replacement of Dal bund Transmission Main

750 & 400 diaOrignal Scope

12.70 KmRevised Scope

12 52 Km

22-Oct-076-March-0931-Aug-0930-Nov-09

229.37 233.92 239.00 100% 72% 0% 0.0% 100% 72% 188.22 0.00 188.22

M/S SMS Paryavaran Ltd. PCSS No 0052.

Completed

POKHRILBAL

LT PANEL ,STABLIZER AND DG SET------------Installed. Chlorination Rooms-----75% Completed.

RANGIL

SLUICE VALVE ------62 Nos Completed. Chlorination Rooms--15% Completed. D.G set of 320KVA of Rangil WTP installed at Nishat DalBund Site.

Physical Progress Pipe laid ---- 12.52 out of 12.52 KmPipe tested -----12.52 Km out of 12.52 Km

12.52 Km

Contracts Awarded Kashmir Urban Water Supply 872.39 907.88 995.00 734.27 31.85 766.11

Total Kashmir Urban Water Supply 872.39 907.88 995.00 734.27 31.85 766.11KASHMIR DRAINAGE Contracts Awarded

5 J&K/SU/PT/06/02/LCB/06

Construction of Public Toilet

16 nos Toilet Block 10-Apr-07

17-Jan-08 /30-June -09 31-Dec-0930-Nov-10

23.30 23.3 30.00 100% 78% 0% 0.0% 100% 78% 10.55 0.58 11.13

M/s Sulabh International.

PCSS No 0043.

HAZRATBAL-I The block has been made functional and is open for public use - Completed.

HAZRATBAL-III The block has been made functional and is open for public use - Completed.

HAZRATBAL-II Truss work CGI roofing painting sanitary / electric fittings in progress

SKIMS-I The block has been made functional and is open for public use - Completed.

ABI-GUZAR Concreting for 1st floor columns, sanitary and electrification is in progress

HAZRATBAL-II Truss work, CGI roofing, painting, sanitary / electric fittings in progress

EIDGAH Truss work, CGI roofing, tile work inner and outer, painting, sanitary / electric fittings, septic tank in progress

JENAB SAHIDSOURA Slab, 1st floor, truss work, CGI roofing, plastering, painting, sanitary / electric fittings, tile work inner and outer

SKIMS-II CGI roofing, painting, sanitary and electric fittings

SONWAR Painting work in progress

Regional Bus stand Panthachowk Site to be taken over by M/s Sulabh Internationals

Boat Man Colony Noorbagh Site to be taken over by M/s Sulabh Internationals

Metadar Stand Harvan Site to be taken over by M/s Sulabh Internationals

General Batamallo Bus stand Site to be taken over by M/s Sulabh Internationals

Dismantling of existing lavatory block has been completed and site clearance for work to be taken up for

Khir Bhawani. Sites yet to be Identified

Bohri Kadal Sites yet to be Identified

JVC Metadar Stand Bemina Dismantling of existing lavatory block has been completed and site clearance for work to be taken up for execution by M/s Sulabh Internationals

Page 61: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IBMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

S.No Contract Package No.

Contract Package Description

Technical Specifications

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Package Cost/

Engineers Estimate/Indicative

Cost

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)Contract

Value/Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10 Likely Cost at

Completion (In Million

Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

C C C

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 21 22 23KASHMIR WATER SUPPLY

20

6 J&K/SU/SWD/17/02/LCB/06

Construction of trunk drain, main drain, sub-mains along N.H. Bypass road including construction of pump house and other allied civil works Rawalpora chowk toTengpora Bridge

Orignal Scope24.97 Km

Revised Scope24.84

10-Aug-07 22-Feb-0930-Jun-10 329.40 402.72 470.00 100% 49.8% 0% 0.0% 100% 49.8% 239.91 6.05 245.95

M/S Hasan Road

Construction Ltd.

PCSS No 0050.

Electric poles on the alignment of trunk drain and main drain.

Being persued with the line department

Construction of trunk

11.470 Km of DRAINS ( Trunk Drain, Main Drain, Sub Mains Completed). out of 24.843 Km. Trunk Drain: 1.687 KMtrs. Completed out of 3.204 Km Main Drain: 0.483 Km. Completed out of 2.668 KmSub Main 9.3 Km. Completed out of 18.971 Km.

9.230 Km of DRAINS ( Trunk Drain, Main Drain, Sub Mains Completed) out of 16.945 Km.

7 J&K/US/SWD/17/01/LCB/06

drain, main drain, sub-mains along N.H. Bypass road including construction of pump house and other allied civil works from Pohru Chowk to Chanapora Bridge

Orignal Scope16.94 Km 26-Dec-07 06-Jul-09

30-Jun-10 417.00 417 450.00 100% 18.8% 0% 0.0% 100% 18.8% 197.49 0.00 197.49

M/S M & Company Srinagar. PCSS No

0064.

8 J&K/UU/SWD/17/05/NCB/06

Construction of trunk drain, main drain, sub-mains, laterals along N.H. Bypass road including construction of pump house and other allied civil works Bemina chowk to

Orignal Scope14 Km

Revised Scope12.80

29-Dec-07 11-Jul-0930-April-10 253.80 253.8 289.00 100% 14.5% 0% 0.3% 100% 14.7% 84.95 0.00 84.95

M/S Construction

Engineers Srinagar. PCSS No

0068.

4.735 Km of DRAINS ( Trunk Drain, Main Drain, Sub Mains Completed) out of 12.808 Km.Trunk Drain: 0.950 Km Completed out of 3.424 Km.Main Drain: 0 Mtrs. Completed out of 0.384 KmSub Main 3.785 Km. Completed out of 9.0 Km.

Trunk Drain: 0.745 Km. Completed out of 2.169 Km.Main Drain: 1.013 Km. Completed out of 1.543 KmSub main drain- 7.472 Km completed out of 13.233 Km.

.

Parimpora Fruit Mandi

Contracts Awarded Kashmir Urban Drainage 1023.50 1096.82 1239.00 532.90 6.63 539.53

Total Kashmir Urban Drainage 1023.50 1096.82 1239.00 532.90 6.63 539.53

1895.89 2004.70 2234.00 1267.16 38.48 1305.64

Contracts Tendered

9 J&K/US/WS/18/01/NCB/15

Construction of Sedimentation tanks, clear water sump and allied civil & Electro-Mechanical works for treatment of backwash water at water treatment plant lot A

Construction of 6 Nos sediment tank at Rangil, Alusteng, Pokhribal, Doodhganga and Nishat.

52.50 52.50 52.50 0% 0% 0% 0% 0% 0% 0.00 0.00 0.00

Total Contracts Awarded Urban Kashmir

.

IFB Issued 22.02.2010Bid Date recieved Extended

KASHMIR WATER SUPPLY

p,lot B , lot C

Total Contract Tendered Urban Kashmir Water Supply 52.50 52.50 52.50 0.00 0.00 0.00

Page 62: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IBMultisector Project for Infrastructure Rehabilitation in JK

Project Management Consultants

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

Physical & Financial Progress of Works - March 2010COMPONENT A: URBAN

S.No Contract Package No.

Contract Package Description

Technical Specifications

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Package Cost/

Engineers Estimate/Indicative

Cost

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)Contract

Value/Engineers Estimate/Indicative Cost (In

Million Rs)

Cumulative Progress upto Feb

10 Likely Cost at

Completion (In Million

Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

C C C

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 21 22 23KASHMIR WATER SUPPLY

20

Contracts Tendered

10 J&K/SU/SWD/18/01/LCB/06

Replacement of worn out pumps, mechanical and electrical equipments for storm water pumping station .

21 Nos. 225.30 225.3 225.3 0% 0% 0% 0% 0% 0% 0.00 0.00 0.00

Total Contract Tendered Urban Kashmir Drainage 225.30 225.30 225.30 0.00 0.00 0.00

Total Contract Tendered Urban Kashmir 277.80 277.80 225.30 0.00 0.00 0.00

Total Urban Kashmir 2173.69 2282.50 2511.80 1267.16 38.48 1305.64

KASHMIR DRAINAGE

IFB Issued on 02-July-09Technical Bid under evaluation

Page 63: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 40 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ANNEXURE - IIA TRANSPORT JAMMU ROADS

Page 64: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IIAMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010(In Million Rs)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24JAMMU ROADSContracts Awarded

1Transport-

Jammu/Jmu/Road/01/LCB/01

Imptt./UG. of Sidhra-Surinsar-

Mansar RoadJammu 38.50 18-Dec-06

17-Dec-08 31-Dec-09

30 -June -11399.00 489.62 625.20 85.0% 48.82% 0.0% 0.98% 85.0% 49.80% 278.21 16.42 294.63

M/s PBA Infrastructure Ltd. PCSS No

0027Design As you

Build

1.Wildlife Santuary Clearence from ch. 18.5 to 38.5 Km.

1. Follow up action for approval of ADB for 13.45 Km wild life santuary stretch in the light of NOC issued by Department of Wild Life protection vide letter no: FST/Land/49/2008 dated 15-01-092. Application for clearance from Supreme Court for 6.5 KM submitted.

2Transport-

Jammu/Jmu/Road/03/LCB/03

Double-laning Bari Brahmana -

Bishnah RoadJammu 6.50 12-Apr-07 11-April-08

31-Dec-08 64.34 75.44 78.87 100.0% 100.0% 0.0% 0.00% 100.0% 100.0% 71.86 0.00 71.86

M/S Harish Chandra, New Delhi. PCSS

No 0035.Design As you

Build

3Transport-

Jammu/Udh/Road/02/LCB/01

Imptt./UG. of Chenani-Sudh Mahadev Road up to Mantalai .

Udhampur 30.90 18-Dec-0617-Dec-08 17-Dec-09

31- Oct - 10236.62 269.19 320.44 85.0% 72.00% 0.0% 1.03% 85.0% 73.03% 163.19 0.00 163.19

M/s PBA Infrastructure Ltd. PCSS No

0028B.Design As you

Build.

1. Inadequate mobilisation of manpower & machinery by the contractor

1. Regular Review meetings with Contractor are being held at the level of Director.

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

COMPONENT B TRANSPORT

S.No Contract Package No

Contract Package

DescriptionDistrict Length

(Kms)

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Awarded Cost

/ Engineers Estimate/Indicative Cost (In

Million Rs)

Likely Cost at

Completion (In

Million Rs)

Critical Issues /Reasons for Slow Progress Suggestions Remarks

Earth Work - 36.00 Km nearly completedUpto Km 18.5Breast Wall - 8800 Rmts completed out of 8800 RM Retaining Walls - 2820 Rmts completed out of 2820 RMSlab Culverts - 30 Nos. completed out of 30 Hume Pipe culverts - 52 nos completed out of 53 Nos Drain -29100 Rm (Length Completed ) GSB - 18.5 Kms laid WMM - 18.5 Kms laid (in stretches)DBM - 17 Kms laid (in stretches)BM - 1.5 KmsBridge no.1 at Km 2.91: substructure completed except pier caps.Bridge no. 2 at Km 3.60 substructure completed except pier caps.Bridge no.3 at Km 4.75 substructure completed except abutment caps.Bridge no 4 at Km 6.40. substructure completed

Completed

Centre line marked & approved upto Km 26.70.Contractor asked to follow existing centre line beyond Km 26.70. Earthwork nearly completed 26.3 kms in stretchesBreast wall -6161 RM completed out of 6980 RMRetaining wall - 4776 RM completed out of 7150 RMSide drains - 11286 RM completed out of 7150 RMPipe Culverts- 58 Nos completed out of 60 Nos.GSB - 27.88 kms length completed.WMM - 26.80 kms length completed.DBM - 24.920 kms (length completed)SDBC- 5.6 Km (length completed)Parapet walls - 2582 Nos completed ( Parapet walls on Retaining wall - 1623 Nos. Completed . Parapet walls on Road side - 959 Nos. completed )laying of 53 Nos 300 mm dia pipes is completed.laying of 11 Nos 600 mm dia pipes is completed.laying of 119 Nos1000 mm dia pipes is completed.

21

Contract Value(Awarded + Approved

variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

Page 65: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IIAMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010(In Million Rs)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24JAMMU ROADS

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

COMPONENT B TRANSPORT

S.No Contract Package No

Contract Package

DescriptionDistrict Length

(Kms)

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Awarded Cost

/ Engineers Estimate/Indicative Cost (In

Million Rs)

Likely Cost at

Completion (In

Million Rs)

Critical Issues /Reasons for Slow Progress Suggestions Remarks

21

Contract Value(Awarded + Approved

variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

4Transport-

Jammu/Udu/Road/02/LCB/01

Imptt./UG of Udhampur -

Ramnagar road.Udhampur 27.73 18-Dec-06

17-Dec-08 17-Dec-09

31- Oct - 10374.76 412.49 414.84 80.0% 50.17% 0.0% 2.14% 80.0% 52.31% 201.59 0.00 201.59

M/s PBA Infrastructure

Ltd. PCSS No 0028A.

Design As you Build

1. Electric Poles to be shifteda. From ch. 16.400- 16.420 Km b. From ch. 20.20- 20.26 Km - c. From ch. 25.800-26.00 Km 2.PHE Line to be shifted a. Fom ch 26.5-27.38 Km

1. Removal of Poles is under Progress

2.Follow up action with Line department for removal of Poles & PHE Line

5Transport-

Jammu/Kathua/Road/04/LCB/03

Imptt./UG. of Bani-Dhagger

Road. Kathua 6.00 12-Apr-07

11-Oct-08/28- Feb -10

(Provisionaly approved)

86.10 86.10 119.52 60.0% 10.27% 0.0% 7.00% 60.0% 17.27% 9.52 0.00 9.52

M/S Harish Chandra, New Delhi. PCSS

No 0036.Design as you

Build

1 Structure to be removed a. Structure at ch 0.375-0.400 Kmb. Kacha Pacca house at Ch 0.440-.500 Km

1.Follow up action with Line department to resolve the issue.

6Transport-

Jammu/Doda/Road/06/NCB/05

Imptt./UG. of Doda-Bharat

road.Doda 20.50 16-Nov-07 15-Nov-09

14- Dec-2010 226.30 246.00 376.10 70.0% 64.65% 0.0% 2.26% 70.0% 66.91% 139.65 0.00 139.65

M/S Cube Constructions.

PCSS No 0057.

Design As you Build.

1. Land Acquisition From Ch. 11.650 to 13.650 Km From Ch. 15.700 to 20.500

1. Expedition of process for land acquisition with revenue department.

Earthwork - 26 kms completed in strechesBreast walls - 1852 RM completed out of 3100 RM Retaining wall 2850 RM completed out of 3700 RM Side drains 3420 RM completed out of 13000 RMHume pipe culverts - 35 Nos culverts completed out of 59 Nos Slab Culverts 4 nos. out of 16 Nos.GSB - 21.39 Km length completed WMM - 21.29 Km length completed.DBM -20.51 Km length completed.BM - 11.37 Km length completed.Parapet = 200 no completed.At Tawi Bridge, excavation of left side abutment 2 is in progress. At Riti Bridge, First & 2nd lift of Aburtment 2 is completed and third lift of Aburtment 2 is in Progress . Excavation of abutment no. 1 is completed.

L-section submitted by the contractor and returned with observations to contractor.Widening of road is completed upto km 2.0Earthwork in progress upto km 6.0. R/wall 216 RM length completed out of 800 RMB/wall 147 Rm length completed out of 800 RM.

Survey and investigations in progress by the contractor.Plan from Km 0/700 to 14/715 submitted by contractor & approved by DSC-III. L-section from 0/700-18/900 approved by DSC with modifications to be done by contractor.Centre line marked & approved from 0/700 to 14/700.Pavement design finalised and under review.Earthwork- completed upto Km 16 Retaining wall - 2644RM completed out of 3411 RMBreast wall -2327 RM completed out of 4029 RMGSB - 3.06 Kms length completed .

Page 66: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IIAMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010(In Million Rs)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 22 23 24JAMMU ROADS

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

COMPONENT B TRANSPORT

S.No Contract Package No

Contract Package

DescriptionDistrict Length

(Kms)

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Awarded Cost

/ Engineers Estimate/Indicative Cost (In

Million Rs)

Likely Cost at

Completion (In

Million Rs)

Critical Issues /Reasons for Slow Progress Suggestions Remarks

21

Contract Value(Awarded + Approved

variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Cumulative Progress upto Feb

10

Progress During Mar 10

7Transport-

Jammu/Doda/Road/12/NCB/04

Imptt./UG. of Drabshalla-

Bimalnag road.Kishtwar 8.36 12-Feb-08 11-Feb-10

13-Apr-10 120.03 126.42 145.30 100.0% 54.33% 0.0% 1.02% 100.0% 55.35% 23.77 0.00 23.77

M/s. Malik Construction

Co. Engineers

Design PCSS NO 0076

1. Land Acquisition FromCh. 0.185-0.225 Km Ch. 0.450-0.510 Km Ch.0.600 - 0.700 Km Ch. 2.700 - 2.800 Km Ch 6.025 - 6.075 Km Ch 7.610 - 7670 Km

1. Expedition of process for land acquisition with revenue department.2. Review meeting with contractor, asked to expedite the workn

8Transport-

Jammu/Kathua/Road/08/NCB/04

Imptt./UG. of Kalibari-Kathua-Hatli Morh road.

Kathua 6.57 9-Apr-08 6-May-10 228.61 293.74 389.87 100.0% 8.82% 0.0% 3.18% 100.0% 12.00% 102.99 0.00 102.99

M/s. Khajuria Construction, Kathua (JV).

Engineers Design

PCSS No . 0085

1.Shifting of PHE utilities FromCh. 0.850-0.920Ch. 2.30 -300 KmCh. 3.00-400 KmCh. 4.00-4.200 KmCh. 4.38, 4.42, 5.06,5.33 KmCh.6.100-6.450 km2. Shifting of PDD utilities From Ch. 0.850-0.9203.Electric Poles to be shifted:- 123 Nos.4.Transformer :- At Ch 2.49 km - 1 Nos.At Ch 3.075 - 1 Nos.5. Telephone Poles - 74 Nos.6. Structures to be removed :- From Ch. 0-1 Km - 6 Nos.From Ch 2-3 Km - 3 Nos.From Ch 3-4 Km - 3 Nos.From Ch. 4-5 Km - 3 Nos.From Ch. 5-6 km -6 Nos.

1.Follow up action with Line department to resolve the issue.

Total Contracts Awarded Transport Jammu -Roads 1735.75 1999.00 2470.14 990.77 16.42 1007.19Contracts To Be Tendered

9Transport-

Jammu/Poonch/Road/05/LCB/03

Imptt./UG.Sakhi Maidan-Kalai

road.Poonch 21.75 230.00 230.00 262.40 0.0% 0.00% 0.0% 0.00% 0.0% 0.00% 20.77 0.00 20.77

M/S Harish Chandra, New Delhi. PCSS

No 0037.Design As you

Build.

Original contract terminated, .

Total Contracts To be Tendered Transport Jammu Roads 230.00 230.00 262.40 20.77 0.00 20.77

1965.75 2229.00 2732.54 1011.54 16.42 1027.96Total Transport Jammu -Roads

Centre Line set out & approved upto Km 7.500Earthwork in cutting done from Km 0/300 to Km 7/500 except earthwork in hard rock.Retaining wall - 1184 RM length completed out of 2704 RM. Breast wall - 419 RM length completed out of 2204 GSB - 3.4 km length completed.widening of WMM is in progress and completed upto km 0.34Major Bridge under construction at RD 3/600.- Pier P2 & P3 :Substructure completed -Piers P1 : Substructure except Pier cap completed .- Abutment A2 : Raft is completed Utility shifting, tree cutting and structure removal under progress.Diversion of bridge at km 3/600 completed. Side Drain - 3730 RM length completed out of 11000 and 550 RM in progress.Widening of GSB (LHS) is completed upto 800 m Laying of WMM (LHS) is completed upto 700 m After changed requirement of irregation department , two canal bridges redesigned and handed over to contractor.

The contract is terminated.Fresh IFB issued on 27.01.2010.Date Reciept Tender to 12-04 -2010

Page 67: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 41 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ANNEXURE - IIB TRANSPORT JAMMU BRIDGES

Page 68: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IIBMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (In Million Rs)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 11 11 12 13 14 15 16 17 18 19 20 22 23 24

JAMMU BRIDGESContracts Awarded

1Transport-

Jammu/Jmu/Bridge/02

Const. of 136.26 mtr span multibarrel box culvert over Devak Nallah on Nagrota Moutlian road.

Jammu 136.26 28-Apr-0630-Nov-0731-Oct-0931-May-10

29.90 30.25 36.85 100% 85.03% 0% 0.00% 100% 85.03% 14.88 0.00 14.88JKPCC

Force Account PCSS No 0011

1.Inadequate resources deployed by JKPCC

1 Notice for slow progress issed to JKPCC

2Transport-

Jammu/Udh/Bridge/04

Const. of 45 m span steel girder bridge over Kooh Nallah on Udhampur - Ramnagar Road.

Udhampur 45.00 20-Feb-06

31-Mar -0831-Jan-1031-May-10

(Provisionally Approved)

20.80 40.09 40.09 100% 88.00% 0% 0.00% 100% 88.00% 17.92 0.00 17.92JKPCC

Force Account PCSS No 0023

1. Slow progress in the fabricaion of steel girders

1. Notice for Slow Progress issued JKPCC.

3Transport-

Jammu/Udh/Bridge/05

Const. of 47 m span steel girder bridge at Kaghote on Udhampur- Ramnagar road.

Udhampur 47.00 20-Feb-06

31-Mar-0828-Feb-1031- Aug-10

(Provisionally Approved)

19.90 36.31 36.31 70% 34.18% 0% 0.00% 70% 34.18% 7.35 0.00 7.35JKPCC

Force Account PCSS No 0022

1.Inadequate resources deployed by JKPCC

1. JKPCC persued to expedite the progress of work,

Total Contracts Awarded Transport Jammu Bridges 70.60 106.66 113.25 40.15 0.00 40.15

Total Transport Jammu Bridges 70.60 106.66 113.25 41.09 0.00 41.09

Cumulative Progress upto

Feb 10

S.NoContract Package

No

Contract Package

DescriptionDistrict Length

(Mts)

Date of Signing of Contract

Date of Completion as per Contract /Date of Time

Extension

Contract Package

Cost/Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value/

Engineers Estimate/Indicative Cost (In

Million Rs)

Likely Cost at

Completion (In Million

Rs)

Sub structure has been completed.Excavation of Hard rock is in progress for both side approaches.

Progress During Mar 10

Cumulative Progress upto

Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress Suggestions Remarks

21

The Bridge is through for Traffic moment.River protection works in progress.

Sub structure has been completed.Fabrication of superstructure steel girder is completed Approach wall on Udhampur side completed.Launching of steel girder is in progress.( Apprx. 75 % completed)Shifting of Steel Girder super structure from fabrication yard at Jammu to bridge site is completed.Bridge Roller cum rocker type bridge bearing arrived at site .

Critical Issues /Reasons for Slow

Progress

Expenditure of 0.94 for Mananu Nalla (Shifted to NABARD-PMGSY-CRF under State Plan) is included in Total

Page 69: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 42 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ANNEXURE - IIC TRANSPORT KASHMIR ROADS

Page 70: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Contracts Awarded

1Jehangir chowk -SKIMS road Srinagar 10.10 26-Dec-06

30-Jul-08 /30-June-09 /31-Dec-09 100.00 100.00 304.70 80.00% 58.42% 0.00% 0.00% 80.00% 58.42% 134.98 0.00 134.98

M/S Kamal Builders, PCSS No

0030Design as You Build

Test Pile at Darish Kadal cast. Restoration of Road in Km 4th – 5th by way of metalling & OGP completed. Restoration of Road to Bus Adda completed. Tengpora Batmaloo road E/w & GSB filling for 850 mtr completed on RHS & LHS. BM from Jehangir chowk to Sekidafer completed (3 kms). DBM from Jehangir chowk to Sekidafar Completed. Restoration from Idd Gah to SKIMS completed by way of metal patches and OGP. Work of WMM from Aali Masjid to SKIMS completed (LHS). DBM Ali Masjid to Buhluchpora completed (LHS). WMM: Batmaloo-Tengpora section completed 800mts. Covered RCC Drain 3+100 to 3+250 completed. R/wall 4+600 to 4+765 RHS completed. Footpath construction RD 4+200 to 5+300 completed LHS. BT Sekidafar to Bohlochora (Left Tube) & Bohluchpora to Soura Right Tube completed. Batmaloo-Tengpora Section: BT from RD 0+000 to 1+550 completed. Central Verge 0+000 to 0+700 completed. R/wall in Km 1st (LHS) 200m completed. Jehangir chowk-SKIMS section: WBM RD 3000 to 6200 completed RHS. WMM RD 3000 to 3+300 completed (RHS). BT RD 3000 to 3300 (RHS) completed. R/wall RD 4125 to 4140, RD 5820 to 5850 (LHS) completed. Footpath Concrete Block RD 3100 to 6800 90% completed LHS & 3100 to 7700 60% completed RHS. Central verge 3050 to 4100 in progress 20% completed. Surface drains LHS RD 3100 to 4100 in progress. Providing / Fixing / Redressing of Devri stone in progress.

land to be acquired = 5850 Sq.m.Structures to be removed:Sewerage Pumps, 5 Structures, 8 GodownsUtilities to be Shifted:Elec. Poles 21 nosTransformer 2 nos

Taken up with concerned quarters

2 Thajiwara-Shangus road Anantnag 13.53 26-Dec-06

22-Jul-08 /30-June-09 /30-Sep-0931-Jul-10

67.62 70.38 84.90 90.00% 68.49% 0.00% 1.20% 90.00% 69.69% 51.12 0.00 51.12

M/S Kamal Builders PCSS No

0029 Design as You Build

Thajiwara Shangus Road. Widening of Road from 1+800 to 4+150 by way of E/filling, GSB & Construction of R/walls completed. Laying of RCC pipes & raising done. Widening by way of E/w in km 5th, 6th, 8th & 9th completed including R/wall at Km 8+450 & laying of RCC pipes completed. Widening from 475 to 1800 completed Prov. & & Laying of GSB RD 5500 – 6200 & 7200 – 8500 completed. Providing & laying of G-II completed for 6.6 kms and G-III for 6.6 kms (1st layer) & G-III completed for 6.6 kms (2nd layer). Const. of culvert at RD 0+442 of span 4.5mt completed & opened to traffic. Const. of culvert at RD 5+500 of span 5.00mtr completed with slab. BM/ OGPC for 6 kms completed. Brakpora– Kanganhall Road Widening left side 400 to 2000 completed, widening right side completed. Laying of RCC pipes completed. Widening left side 2700 to 4000 completed. Construction of drain at 0 to 250 & 2325 to 2390 250completed, Const. of R/walls and B/walls completed. Const of Drain RD 7100 – 7200 & RD 4000 to 4100 completed. Providing & laying WBM G-II 1st layer for 4.0 Km completed & WBM G-II & III 2nd Layer completed for 4 kms. BM /OGPC for 4 kms completed

land to be acquired = 9222 Sq.m.Structures to be removedResidential/Commercial2 nos,Utilities to be Shifted:Elec. Poles 11 nosTransformer 3 nosWalnut trees 24 nos

Taken up with the concerned quarters

3 Qazigund-Kulgam Road Anantnag 16.50 27-Jun-06

24-July-08 /30-June-09 /30-Sep-0931-Aug-10

177.67 210.47 282.00 95.00% 68.97% 0.00% 2.47% 95.00% 71.44% 201.36 5.06 206.42

M/S Valecha Engineering

Ltd. PCSS No

0015 Design as you

build

Widening & overlay by way of GSB, WBM G -II & G-III completed 1+500 to 17+000. Const. of R/w in Km 3 to 17 Completed. Churat Bridge completed 100%. Y.K Pora Bridge- foundation of one Pier, abutment completed & sub-structure in progress including five lifts raised. Concreting of one Pier and one abutment including cap. Construction of approach walls in progress. Devsar Bridge ready for inauguration, opened to traffic. Cross drainage structures 94% completed. WBM G-II, G-III Completed 1+500 to 17+000. ■02 No’s 2 mt span culvert at Km 3rd completed. Const. of Breast walls completed. Const. of drains in progress (90% completed). Laying of BM and OGPC 15Km completed. R/wall in Re-aligned portion km 1st in progress. Extension of 2 No culvert at Devsar completed (10+325). Re-construction of one No. culvert in km 7th completed. Gabain structures in Km 14th completed & in km 7th in progress. Extension of 1 No culvert in Km 9th completed. Const. of drain in Km 13th completed. Const. of drain at Brazloo junction completed. Clearing & Grubbing in Km -2nd & at Re-aligned portion in progress. E/w in Re-aligned portion in progress. Construction of culvert at Re-aligned portion completed. Construction of culvert 2 mt span in Km 1st in progress. Reinforcement work of Y.K. Pora Bridge deck slab in progress.

land to be acquired 1047.5 Sq.m.Structures to be removedResidential/Commercial5 nos,Cow Sheds 1 nos1 No Rice StoreUtilities to be Shifted:52 Elec. Poles Transformer 3 nosWalnut trees 12 nos

Follow up action to be taken with line department to resolve the issues

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

Page 71: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

4Humhama-Budgam Raithion-Arizal Road

Budgam 37.60 27-Oct-06

24-Nov-08 /30-June-09 /31-Oct-0931-Aug-10

248.76 288.55 390.56 100.00% 88.50% 0.00% 0.29% 100.00% 88.79% 281.98 0.00 281.98

M/S BLA- Brahamputra

(JV) PCSS No

0026 Design as you

build

Humhama-Budgam sector (Km 1-6): Widening by way of GSB & WBM completed for aggregate length of 5.80 Km. Construction of approach roads to Town Hall bridge and Naraspora bridge completed. Humhama-Budgam sector (Km 1-6): Laying of Bituminous Macadam(BM)completed for aggregate length of 5.80Km. Laying of DBM completed fo an aggregate of 5.80Km and laying of SDBC completed for a lenght of 5.80kms Budgam-Raithan-Arizol sector (Km 7-37.6): Widening of road by earth-work completed for aggregate length of 25 Km including 8100 meters of retaining & 2202 mtrs of breast walls at various spots.Construction of side drain completed for an aggregate length of 20208 Mtrs from Km 0 to Km 37.6. Budgam-Raithan-Arizol sector (Km 7-23): Laying of GSB from Km.7 to 30 completed.Laying of WBM grade-II (Ist/ 2nd layer completed from km 7th to 21.5 and 1 layer completed upto 23rd Km. Laying of DBM/SDBC from km 7th to 19+850 completed.Raithan-Arizal sector (Km 24-37.30): Construction of 8 pipe-culverts in Km.26,27,28 completed. Laying of GSB from Km.24 to 30 completed. Laying of one coat of WBM from Km.24to28 completed for agg.length of 4.5 Km

Utility Shifting with PDD: 9 poles of 11000 KVA line to be shifted from Km 21 to Km 23rd at different spots. Utility Shifting With PHE: Leakage of Pipe line at Ichgam. Utility Shifting Others: Long Term Issues: Land Acquisition: Partly completed details with Collector Land Acquisition

Follow up action to be taken with line department to resolve the issues

5 Sangrama-Sopore-Kulangam Road

BaramulaKupwara 27.30 26-Oct-06

04-Dec-08 /30-June-09 /31 -Oct-0930-Sep-10

255.04 331.92 450.65 95.00% 61.3% 0.00% 0.14% 95.00% 61.4% 290.86 0.00 290.86

M/S ABCI (JV)

PCSS No 0024

Design as you build

Earthwork = 26.80 kms completed. GSB = 26.80 kms completed. WBM = 26.80 kms completed. B.T = 20.10 kms completed. R/walls 1320 RM completed Km 4, 7, 20, 22 & 23.B/walls = 163 RM completed in km 24. PCC Drain = 2500 mt completed in Kms 1, 2, 7, 11 & 25. Bridge at 16+350 – completed & Diversion at Km 13+400 completed. Pipe Culverts / Box Culverts = 37 No completed in kms 1, 7, 8 & 9, 13, 14, 15, 16, 17 & 20. Extension of 9.0 mt Minor Bridge at RD 11+380 in progress. Box type culverts at 0+300 completed.

1.Utility shifting PDD : 200 m, electric poles 14

Taken up with concerned quarters

6 Potkhah-Pachar Road Baramula 15.74 26-Dec-06

30-Jul-08 /30-June -09 /

30-Sep-0930-June-10

91.73 134.13 176.38 90.00% 91.57% 0.00% 0.00% 90.00% 91.57% 148.66 4.14 152.80

M/S Dinesh Chandra R Aggarwal

Infracon Ltd. PCSS No

0031 Design as you

build

Earthwork: 0+000 to 15+650 completed. GSB: (Shoulders) 0+000 to 15+600 90% completed. (Carriageway) 0+000 to 15+600 completed. WMM: 0+000 to 15+650 completed. BM: 0+000 to 15+350 completed. OGPC: 0+000 to 15+350 completed. R/walls: 1+475 to 15+653 in stretches LHS /RHS (Aggregate length 2150 RM) & 11+350 to 11+500 (100mt) Completed. B/walls 11+325 to 14+350 (aggregate length 780mts) at various locations completed. 10+970 to 15+560 (RHS) 100mt completed. Drains Covered /Open: RD 0+000 to 0+150 B/S, RD 2+913 to 3+025 RHS, RD 4+400 to 4+430 LHS, 5+443 to 5+985 LHS, 11+500 to 11+800 RHS and 9+280 to 9+400 completed. RCC Culverts: RD 3+010, 4+450, 5+900, 6+000 completed. Pipe Culverts: KM 1 to 5th (24 Nos) completed, Km 10th to 14th (06 Nos) in progress. M.S Pipe Culverts: 200mm dia Double row Km 1st completed.

land to be acquired = 730 Sq.m.Structures to be removedResidential/Commercial4 nos, Shops 4 nos,Walnut trees 3 nosHouses 2 Nos

Taken up with concerned quarters

7

Pampore-Ladhoo, Ladhoo-Khrew - Wuyn and lethpora-Ladhoo road sectors of Lethpora-Pantha chowk loop road

PulwamaSrinagar 37.80 13-Oct-06

10-Nov-08 /30-June-09 /31 -Oct-0931-Aug-10

250.00 286.95 376.03 100.0% 84.38% 0.00% 0.21% 100.00% 84.59% 310.77 0.00 310.77

M/S BLA-MK (JV). PCSS No

0025 Design as you

build

Widening by way of earth work completed for an aggregate length of 37.20 Kms.Laying of GSB for widening portion completed for an aggregate length of 37.20 Kms.Construction of drains 90% completed.Construction of 90% R/walls completed.Wet mix macadum(WMM)= 32.50 Km completed. Dense bitumionous Macadum(DBM)= 32 Km completed. Semi Dense bituminous concrete(SDBC)= 32 Km completed. Seal coat= 32Km completed.overall 32km Raod Bituminised.

Utility Shifting with PDD: 33KVA lines to be shifted. Work not taken up in hand yet for unknown reasons. some LT poles at Ladhoo village, Shar, Balhama not shifted yet. Transformers at Shar and Balhama not shifted yet

Follow up action to be taken with line department to resolve the issues

Page 72: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

8Natipora-Nowgam –Newa -Pulwama road

PulwamaBadgam 23.79 15-May-07 12-Jun-09

30-Sep-10 240.00 264.90 312.39 100.00% 70.65% 0.00% 0.00% 100.00% 70.65% 134.91 0.00 134.91M/s.BJCL PCSS No

0039

Widening by way of E/W, laying of GSB for 20 Kms completed. Const. of R/walls completed. Const. of Drains 90% completed. Pipe culverts 20 Nos in Km 4, 5, 7, 19, 20 & 21 completed Widening of Road completed 90% Providing & Laying of WMM 16.00Km completed. DBM 16.00 0Km completed & Hard shoulders in progress. Widening by way of E/w filling beyond 7.5mts from km 5th onwards in progress. Const. of two No. Box type culvert in Km 10th & 17th slab in Km 10th completed. Laying of BM from Natipora to Nowgam i.e. for 2.5 kms completed. Construction of 2 No Culverts in Km 14 & Km 18 completed.

land to be acquired = 345 Sq.m.Structures to be removedWalling 2 nos,Utilities to be Shifted:PDD line 22790 mElectric Poles 188 NosTransformer 9 nos

Taken up with concerned quarters

9

Watergam-Behrampora Hibdangerpora-Rebbon Road

Baramula 20.13 30-Jul-0723-Feb-0931-Oct-0931-Aug-10

139.50 139.50 192.49 100.00% 85.91% 0.00% 0.00% 100.00% 85.91% 91.89 0.00 91.89

M/S Dinesh Chandra A Aggarwal Infracon

Ltd.PCSS No 0048

EarthworkRD 0+000 to 4+925 4925 RM; 4+965 to 11+150 6185 RM; 14+975 to 20+000 5025 RMGSB Agg. Length Widening0+000 to 4+965 4975 RM; 4+965 to 11+930 9665 RM; 11+930 to 20+000 8070 RMWMM Agg. Length Widening0+000 to 4+965 2299 RM; 4+965 to 11+930 6797 RM; 11+930 to 20+000 6000 RMDBM / SDBC & Seal Coat: 0+000 to 4+965 Agg. Length 4925 RMBM / OGPC & Seal Coat: 4+965 to 11+930 Agg. Length 5500 RM; 11+930 to 20+000 Agg. Length 2700 RMR/B/E walls Agg. Length: 0+000 to 4+965 1242.00 RM; 4+965 to 11+930 2880.00 RM; 11+930 to 20+000 2122.83 RMConcrete Wall Length: 0+158 to 0+181 23 RMDrains Covered / Open (agg. Length): 0+000 to 4+965 1261.70 RM; 4+965 to 11+930 772.62 RM; 11+965 to 20+000 521.10 RMR.C.C Culverts: 0+181, 0+667 Completed ; 9+550 Pipe Culverts 300mm 450mm 600mm: 0+000 to 4+965 3 4 1; 4+965 to 11+930 13 3 11 Completed; 11+930 to 20+000 - 4 6M.SPipeCulverts (20mm)0+000 to 4+965 = 5 Nos Completed4+965 to 11+930 = 1 No Completed

Utilities to be Shifted:PHE Line 1830 m, PDD 3400 m, BSNL lines 750 m, Electric Poles & Transformers

Taken up with concerned quarters

10Sumbal - Markundal-Hajin Madwan Road

Bandipora 15.63 20-Jun-0717-Jan-0931-Oct-0931-Mar-10

76.60 91.40 142.70 100.00% 93.68% 0.00% 0.00% 100.00% 93.68% 101.97 0.00 101.97

M/S Dinesh Chandra R Aggarwal Infracon

Ltd.PCSS No 0045

Shoulder widening by way of E/W, loosening and compacting including filling from RD 5+175 to 10+000 and 11+000 to 15+823 , 1+650 to 5+175 completed. Construction of 2x5m box bridge RD 5+400 & 1 x 2.75mt span culvert RD 6+465 completed. Spreading and consolidation of G2 from km 11 to km 15+823 completed. G-II 1+650 to 10+000 completed (in shoulders), 10+950 to 15+822 (in carriageway) completed. G-III 0+000 to 5+150 completed (in shoulders) 5+000 to 10+000 completed (in carriageway & shoulders, 10+875 to 15+823 completed (in shoulders). G3, BM & OGPC 5+175 to 10+300 completed. BM 0+000 to 5+150 completed. OGPC 10+875 to 15+830 completed. Pipe culvert RD 2+500, 2+600, 2+950, 4+750, 4+900, 5+025 & 6+450 completed. R/wall RD 5+925 (50 mtr), R/walls 4+400, 8+240 (29m) , 0+000 to 0+042, 2+000 to 2+028, 15+836 to 15+870, PCC Edge wall Markundal junction RD 5+150 completed. Head walls for pipe culverts RD 6+450 completed & RD 5+979 completed. Granular Shoulder RD 10+875 to 13+000 RHS completed & Rd 10+875 to Rd 15+200 LHS completed. Granular shoulder 5+175 to 9+880 (4.5 Km) completed. GSB Rd 3+000 to 5+100 LHS & RHS completed. Shoulder widening on either sides RD 0+000 to 5+150 by way of GSB & G-II completed, and G-II from RD 0+000 to 0+550 completed. G-II RD 0+000 to 5+150 Both Sides completed. G-II 10+875 to 15+836 completed & G-II in Bus adda RD 15+823 completed.

Structures to be removedResidential/Commercial5 nos, Well 1 nos, Boundary Wall 1 nosUtilities to be Shifted:PDD 23 mElec. Poles 30 nosTransformer 6 nos

Taken up with concerned quarters

Page 73: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

11

Singhpora-Kanihama road via Gundkhaja Qasim

Baramula 6.63 20-Aug-0720-Mar-0930-Sep-0930-June-10

57.79 55.11 82.54 100.00% 85.43% 0.00% 0.94% 100.00% 86.37% 56.34 3.03 59.37

M/s Gousia Roads

Construction Ltd. PCSS No 0049

Const. of R/walls in Km 1st completed. Laying of Pipes at RD 0+109, 0+485, 0+616, 1+644, 1+952, 2+079,2+353, 2+837 laid with head walls 50% completed. Edge walls: RD 1+248 to 1+300, 1+600 to 1+630 LHS, 1+165 to 1+360 LHS & RHS, 3+175 to 3+325 (RHS), 3+647 to 3+678, 3+617.65 to 3+647, 4+300 to 4+317.6, 4+570, 5+275 (30m each) 5+200 to 5+450, 5+513 to 5+527, 5+640 to 5+659, 5+734 to 5+760, 6+168 to 6+266, 6+153 to 6+248 RHS completed. Toe walls: RD 1+184 to RD 1+230 (46 meters) completed. RD 6+168 to RD 6+196 (= 28 nos completed) RCC Walls: RD 0+098 to 0+297 completed. Slab Janked culvert in Km 1+300, 1+595 & 2+900 completed. 1 x 25m span Gund Khawaja Qasim bridge at RD 3+500. one test pile and One working pile casted. Widening of road by way of E/w in progress from km 0+000 to 2+900 completed & 3+600 to 4+250 in completed. Raising of road in km 2nd 1+300 to 1+165 completed. C.C Drain RD 2+920 to 3+400 both sides, 4+500 to 4+700 LHS, 4+700 to 5+400, 5+000 to 5+200, 5+764 to 5+848 LHS completed, RD 5+800 to 5+805 (RHS completed). Reconstruction of damaged R/wall from RD 0+016 to 0+042 completed. Widening of road by way of E/w in km 2nd completed & 3rd , 4th & 5th in progress. GSB 0+000 to 0+300 RD 2+278 to 2+778, 5+600 to 5+636 completed. G2 0+000 to 3+100 & 3+900 onwards upto 6+575 completed except 1.0 km. G-III RD 0+000 to 3+100, 3+600 to 4+250 completed. BM and OPGC (-) 0/019 to Km 2+800. BM 3+600 to 4+200. BM 2+907 to 3+340. 4+570 to 5+260, 5+587 to 5+787 completed. RCC culvert 1 x 2.90 mtr at RD 5+000 completed. Construction of 1 x 1.00mt R.C.C culvert RD 3+240 completed. Construction of drain from Rd 6+430 to 6+600 B/S in progress.

Utilities to be Shifted:Elec. Poles 6 nosPDD 5 mWalnut Trees 7 Nos

Taken up with concerned quarters

12Bijbehara-Langanbal road upto Avoora

Anantnag 29.00 5-Nov-07 30-Mar-10 264.50 364.77 480.06 90.00% 79.90% 0.00% 6.13% 90.00% 86.03% 307.14 5.92 313.06

M/s.R. G. Buildwell Engineers

Ltd. PCSS No

0056

Widening by way of Earthwork=28 Km completed & work is in progressGSB Filling: 27Km completed & work in progressWMM/WBM:- 22.5 Km completed DBM:- 22.5 Km completed BC/SDBC:-21 Km completed Bridges:-2 No of bridges completed with approaches.Cross Drainage:- out of 51 Nos culverts 35 no completed. & work in progressR/Wall,B/Wall:-(R/walls out of 2835mtr 2685mtr completed and B/walls out of 3500 mtr 3500 mtr completed.)Drains:- out of 5178 mtrs 5028 mtrs completed. & work is in progress

PDD:- 10925 Meter line affected.PHE : 5300 Meter Land Acquistion 160Sq.km/ 32 structures

Follow up action to be taken with line department to resolve the issues

13

Wanpoh-Chawalgam-Aharbal via Nehama

Kulgam 38.00 7-Jan-08 25-Nov-0931-Dec-10 268.10 419.00 538.94 100.00% 53.20% 0.00% 0.93% 100.00% 54.13% 284.97 0.00 284.97

M/S Hassan Road

Construction Co.Srinagar.

PCSS No 0073

Widening of road by way of executing GSB filling completed for 22 Km(in section 2nd)Widening of shoulders by way of nallah bed material filling completed for aggregate length of 7 Km completed10 Nos of construction of culverts,extension of culverts of different spans are completed.350rm of differtent dia's of R.C.C pipes laid,1700m of R.C.C drain completed,2169rm of R/walls,Breast walls completed.Hard shoulders by way of WBM GII,GIII completed for a length of 7Kms in section Ist completedSoft Shoulders completed by way of Earthwork for a length of 13.50 Kms in section 2nd.30Kms of road macamadized. Earthwork and Excavation is in progress, GSB filling is in progress, laying of WMM is in progress.

Utility shifting PDD : out of 504 poles 359 poles have been shifted and old one removed2.Utility shifting PHE : 90% completed and 70% charged. work in progress3. Structures to be aquired for construction of diversion to facilitate for const of 6 mtr span bridge at RD 1+630,and widening af bridge at RD 11+590.

Follow up action to be taken with line department to resolve the issues

Page 74: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

14Kralgund -Ashpora -Qaziabad Road

Kupwara 13.53 31-Mar-08 9-Nov-0930-Sep -10 133.37 198.93 244.08 100.00% 62.74% 0.00% 0.26% 100.00% 63.00% 90.71 5.65 96.37

M/s. Rash Builders Pvt. Ltd.PCSS No

0078

Earth Work 0 to 4+250 = 4.25km, 4+300 to 4+740 = 0.44km 5+000 to 5+360 = 0.36km, 5+625 to 7+000 = 1.470km, 7+000 to 13+400 = 6.40km Total 13.00 km completed in shoulder widening & re-grading. 03+100 to 3+500,5+200 to 6+000, 6+000 to 6+500 completed. Pipe Culverts 600mm dia = 8 No 450mm dia = 11 No 900mm dia = 10 No Total 25 No Completed R/Wall 0+350 to 3+125 = 681RM completed. Edge Wall 2+400 to 2+600 = 393m completed. Breast Wall 2+900 to 7+590 = 227m completed. GSB 0 to 4+250 = 4.25km, 4+300 to 4+740 = 0.44km, 5+000 to 5+300 = 0.30km, 5+625 to 6+695 = 1.07km, 7+00 to 10+000 = 3.00km. Total 9.06km completed. C.C Drains 0 to 0+250 = 500 RM, 0+500 to 0+600 = 100 RM, 0+800 to 0+950 = 150 RM, 1+000 to 1+400 = 400 RM, 4+700 to 5+000 = 300 RM, 6+300 to 6+350 7+300 to 8+400 = 1100 RM, 10+000 to 11+500 = 1500 RM , 3+175 to 3+300 = 100mt, 3+500 to 3+600 = 100Rm 3+400 = 150 RM Total 4400 RM Completed.PCC R/wall 0+700 to 6+700= 325 RM, 11+200 to 11+500 = 300m Total = 625 RM completed. B/walls 2+275 to 9+150 , 12+100 (30 RM) = 392 RM completed. WMM 0 to 3+400, 3+700 to 5+400 =5.20Km completed. BM 0 to 3+305, 3+700 to 5+400 = 5.00Km completed. RCC Box Culvert 1 No. Ch: 0+000 2x2m completed. 2 No 2m span ch: 2+700 & 3+200 (extension both sides) Completed 01 No 5+600 RHS in progress.. 1 No 2mx2m ch: 6+900 completed. 1 No Box culvert ch: 9+000 Completed. 01 No. Box Culvert 5+600 LHS Portion completed. 01 No. Box Culvert 10+500 RHS portion completed.

Structures to be removedResidential/Commercial1 nos,Shopps 3 nos

Taken up with concerned quarters

15Handwara -Zachaldara -Waddur Road

Kupwara 17.04 31-Mar-08 9-Nov-0930-Sep -10 199.86 267.33 329.31 100.00% 64.48% 0.00% 0.31% 100.00% 64.79% 145.19 0.00 145.19

M/s. Rash Builders Pvt. Ltd.PCSS No

0080

Earth Work 0+900 to 5+500 = 4.60km, 6+500 to 9+300 = 2.80km, 10+200 to 15+350 = 5.10km, 15+450 to 16+00 = 0.50km. Total 13.00 km completed in shoulder widening. GSB 0 to 0+600 = 0.60km, 0+900 to 6+000 = 4.60km, 6+500 to 9+300 = 2.80km, 10+200 to 15+350 = 5.00km, Total 13.50 km completed in shoulder widening. C.C Drains 0 to 0+400 = 400RM, 2+460 to 2+800 = 640RM, 4+200 to 4+800 = 1200 RM, 6+300 & 6+500 (250 RM) 8+550 to 8+650 = 100RM, 8+800 = 150RM., 8+800 to 9+350 = 550RM, 8+085 to 9+270 = 185 RM, 8+850 to 10+100 = 1250, 9+270 to 9+400 = 130RM Total 4900 RM completed. R/walls ( R.S Masonry / R.C.C Walls) 6+600 to 6+646 = 46RM, 7+980 to 7+990 = 10RM, 7+186 to 7+200 = 13RM, 6+965 to 6+980 = 15RM, 8+000 to 8+300 = 270 RM, 8+00 to 8+100 = 100 RM, 10+110 to 10+185 = 2x85 =170 RM, 10+185 to 10+230 = 45 RM Total 669 RM completed. R.C.C walls 2+000 to 2+069 = 130RM, 8+400 to 8+600 =200RM, 10+585 to 10+618 = 33 RM, 10+618 to 10+630 = 12RM, 10+825 to 10+870 = 80RM, 11+000 to 11+036 = 36RM, 11+090 to 11+109 = 19 RM, 13+830 to 13+845 = 15RM, 13+850 to 13+860 = 10 RM, 13+860 to 13+875 = 15 RM, 14+200 to 14+260 = 60 RM, 14+610 to 14+663 = 53 RM, 15+320 to 15+568 = 147 RM Total 810 RM completed. Pipe Culverts 1+300, 2+470, 3+100, 5+225, 7+200, 8+130 = 8 Nos (600 mm dia completed) 3+610, 3+915, 6+200, 6+405, 6+875, 8+030 = 9 Nos (900 mm dia completed) R.C.C Culverts 0+900, 01 No (4.5mt span) Box Culvert completed. 1+500, 01 No (2.8mt span) Box culvert completed. 0+600 & 0+700 = 2 No Extension both sides 3mt span each completed. 4+900 01 No 3mt Span culvert completed, 8+550 3mt Span culvert completed 01 No 10+900 RHS in progress. Minor Bridge 1+990 = 1 No 8.7m span completed, Km 12 , 01 No 5mt Span completed extension slab – 1 No 11+800 ((E/w mudmat). WMM 0+000 to 5+375, 6+320 to 7+300, 8+300 to 8+900, 9+00 to 9+100 = 7 Km completed. DBM 0+000 to 9+000 (except Km 587) = 7Km completed. PCC Wall Km 1st to 15+440 = 729 RM completed SDBC 1+000 to 4+500 = 3.50 Km completed.

Structures to be removedShopps 3 nosWalnut Trees 22 Nos

Taken up with concerned quarters

16

Town Roads Kargil - Lot1 (Circular road,Goma Kargil)

Kargil 5.00 2-May-0828-Feb-0915-Sep-0931-May-10

30.99 39.56 68.30 50.00% 84.77% 0.00% 0.00% 50.00% 84.77% 22.36 0.00 22.36

M/s Haji Ahmed

Hussain (JV)PCSS NO

0084.

E/w, Sub base and base course, cross drainage works, drainage and protective works in progress (80% completed). 2mt span culvert at RD 890 of Circular road completed. Parapets Goma Kargil Road completed Parapets on Circular Road RD 900 onwards in progress.

Land acquisition3967 sq m Structures to be removedResidential/Commercial8 nos,Utilities to be Shifted:Elec. Poles 26 nosNon Fruit Bearing Trees 456 nos

Taken up with concerned quarters

Page 75: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

17

Town Roads Kargil - Lot2 (G.M Pora,Trespone link roads )

Kargil 5.70 24-Apr-0821-Feb-0915-June-0930-June-10

14.39 41.38 46.98 100.00% 95.44% 0.00% 0.00% 100.00% 95.44% 22.79 0.00 22.79

M/s Mohammad

AliPCSS NO

0083.

E/w,Sub base and WBM Completed. Cross drainage works, drainage and protective works in progress.

18Natipora - Chadoora Charie -Sharief Road

Budgam 24.00 23-Jun-08 8-Aug-10 217.20 217.20 395.20 95.00% 64.71% 0.00% 1.67% 95.00% 66.38% 95.10 0.00 95.10

M/s Bola Singh Jai

Pralash const.PCSS NO

0087.

Const. of Retaining / Breast walls 98% completed. Widening by way of laying GSB 19Km completed. Const. of drains completed 90%. Widening by way of laying of WMM 2Km completed (out of 9.90kms) WMM (Carriageway) 2 km completed. DBM for 1.5Km completed. Const of 1x8mt Span Bridge at Kakaw Ring in progress. Restoration of damages in Km 1st Rd 0 - 800 by way of WBM / GSB completed.

land to be acquired = 5196.5 Sq.m.Utilities to be shifted:BSNL 1050 m, PDD 950 m, Poles 76 Nos Transformers 5 NosPHE Lines 5900 m

Taken up with concerned quarters

19 Sopore- Bandipora Road Baramula 30.87 22-Nov-08 19-Dec-10 347.31 347.31 493.18 60.00% 24.38% 0.00% 1.25% 60.00% 25.63% 115.54 0.00 115.54

M/s Shri Avantika

Contractors (JV)

PCSS NO 0093.

Confirmatory Survey upto Km 28 completed. E/w in shoulders KM 3+000 to 10+800 completed & Widening of road (hilly portion) 11+100 to 14+750, 15+000 to 18+580, 18+750 to 21+400, 21+800, 22+200 to 27+400 Both Sides. (Total 24.5 km) completed. GSB filling for above stretches 95% completed .Diversion over Madhumati Nallah completed. C.C Drain 6+700 to 6+900, 18+350 to 18+500, 19+550 to 19+625, 18+050 to 18+350 completed. R/walls & B/walls 1104 RM completed at various locations in hilly portion & 11+60 to 11+625 completed. Extension of culverts at RD 3+350, 11+325, 11+375, 11+425, 11+600, 11+800, 11+950, 12+050, 13+650 in progress (75% Completed).Pipe culverts (11 No completed) 19+100, 19+450, 19+600, 19+975, 20+375, 20+450, 23+290, 23+825, 23+900, 24+400 & 24+625 and 7+800, 8+025, 8+200, 8+225, 12+325, 12+650, 13+750, 14+500, 20+150, 22+650, 22+880, 23+875 in progress (65% completed). Delaunching of Bailey Bridges (2 Nos) completed and dismantling of abutments completed on Madhumati nallah. Shifting of Utilities by P.H.E Deptt. in progress.

Structures to be removedResidential/Commercial3 nos, Cowshed 1 Nos, Shopps 26 nosArea Encroached:Fencing of Forest Deptt.Utilities to be Shifted:PHE line 2200 mTransformer 2 nosPDD 100 mMulbery Trees 10 nos

Decision of taking up the construction of bridge taken by CEO

20

Town Roads Leh G1-Lot-01 (Leh Main, Shenam-Sheldon, Upper Tuckcha-Changespa)

Leh 3.20 10-Oct-08 7-Nov-0930-Sep-10 27.10 27.10 51.33 100.00% 69.43% 0.00% 0.00% 100.00% 69.43% 18.21 0.00 18.21

M/s Dorjey Tonyot

PCSS NO 0088.

E/W 90% completed. WBM 92% completed. R/walls 60% completed. C.C Drains 50% completed

21

Town Roads Leh G1-Lot-2 (Tukcha, Skampari Colony)

Leh 5.50 3-Nov-08 30-Nov-0930-Sep-10 29.20 29.20 53.85 100.00% 97.76% 0.00% 0.00% 100.00% 97.76% 20.85 0.00 20.85

Thupstan Rinchen

PCSS NO 0090.

E/W completed. WBM completed. E/walls in progress. Const. of C.C Drains in progress.

22

Town Roads Leh G2-Lot-1 (Tyari Rong- Jiva Tsal Road-RD0Km-RD3.6K)

Leh 3.60 3-Nov-08 30-Nov-09 21.50 21.50 29.04 100.00% 47.94% 0.00% 0.00% 100.00% 47.94% 9.99 0.00 9.99

Thupstan Rinchen

PCSS NO 0089.

WBM G–II in widened portion completed. Edge walls 15% completed. Culvert 5mt Span completed 90% (2+085). WBM 30% completed. E/walls 15% completed.

23

Town Roads Leh G2-Lot-2 (Tyari Rong- Jiva Tsal Road RD3.60Km-RD7.20Km)

Leh 3.60 20-Apr-09 17-May-10 23.55 23.55 24.24 100.00% 14.10% 0.00% 0.00% 100.00% 14.10% 3.84 0.00 3.84

Mohd. Sultan and Brothers

PCSS NO 0102

Earthwork in progress. Providing & Laying GSB in progress. 3 No Slab culverts 90% completed. 5 No Slab culverts in progress.

Page 76: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

24

Town Roads Leh G4-Lot-02 B.M (Tyari Rong- Jiva Tsal Road)

Leh 7.20 13-Aug-09 21-Dec-0930-Sep-10 27.66 27.66 27.65 0.0% 0.0% 0.00% 0.00% 0.0% 0.0% 5.53 0.00 5.53

Tsering AugchukPCSS NO

0103

Contract Awarded.

25 Habdipora-Qadar-Qaimoh Road

PulwamaAnantnag 24.00 8-Nov-08 5-Sep-10 299.74 299.74 492.80 100.00% 33.81% 0.00% 2.72% 100.00% 36.53% 117.29 0.00 117.29

Rash BuildersPCSS NO

0091.

Confirmatory survey in progress. Construction of Diversions at bridge sites (4 No’s) upto WBM level completed. Widening of road in km 1,2, 3, 4, 15 to 23 in progress. GSB 08 km completed (aggregate length) Tree cutting 80% completed. Const. of R/wall in Km 20,21, 13th, 14th, 18th & 19th completed (875 mt Length). 5th, 12th in progress. Const. of 76 pipe culverts Completed. Drain in 20+600 left side & right side & Km 19 completed & drain in Km 14+415 in progress (2500mt). Construction of 1 x 12mtr bridge abutments completed (Rd 20+773). Construction of Box culvert in 15+771 90% completed including approach walls in progress. RCC drains in Km 3+075 & 3+240 (Both sides) completed. Dismantling abutments of Qaimoh bridge completed & construction of A-2 & A-I in progress, Kadar Bridge dismantling 80% completed. Const. of B/wall in km 14 (150mt) completed. R/wall in Km 12, 100% completed. R/walls in km 9 in progress. Kadar Bridge A1 Abutt Laying Raft & lift one completed both sides. Raft of A2 laid including one lift of barrel. 1 x 2mt span culvert in Km 14 completed. Extension of culverts in km 23+170, 21+570 (2 Nos), RD 17+650, Rd 8+110 in progress. E/work filling RD 12+600 in progress.

land to be acquired = 14180 Sq.m.Structures to be removedResidential/Commercial4 nos, Utilities to be Shifted:PHE line 7650 m, PDD 465 mElec. Poles 66 nosWalnut Trees 38 nosMulbery Trees 24 nosFruit Bearing Trees 50 nos

Taken up with concerned quarters

26 Sharda- Kamal Kote Road Baramula 15.50 8-Apr-09 4-May-11 190.68 190.68 238.10 100.00% 2.78% 0.00% 0.81% 100.00% 3.59% 37.54 0.00 37.54

Rash BuildersPCSS NO

0101

Confirmatory survey / Demarcation of Road completed for 12.50 kms. Widening Km 1 – 12 in stretches by way of E/W excavation work in progress. Breast Walls at Km 3+920, 4060, 8+280 and 11+550 completed.

land to be acquired = 10000 Sq.m.Area Encroached:Fencing 2100 Sq.mUtilities to be Shifted:PHE Line 900 MeterElec. Poles 10 nosTransformer 1 nos7 Nos ShopsWalnut Trees 71 nosMulbery Trees 27 nosFruit Bearing Trees 39 nosNon Fruit Bearing 398 nos

After the visit for Director (T) major issues of land acquisition etc sorted out, survey work completed for 6 KM.

27

Town Roads Leh G4-Lot-01 B.M (Leh Main, Shenam-Sheldon, Upper Tuckcha-Changespa)

Leh 8.87 24.29 24.29 35.50 0.0% 0.0% 0.00% 0.00% 0.0% 0.0% 0.00 0.00 0.00M/s Dorjey

TonyotPCSS NO

Contract Awarded.Work not started yet

Total Contracts Awarded Transport Kashmir Roads 3824.13 4512.52 6343.90 3101.90 23.80 3125.69

Page 77: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐ 10 ANNEXURE ‐ IICMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT (IN Million Rs.)

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar 10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 KASHMIR ROADS

Date of Completion as per Contract /Date of Time

Extension

S.NoContract Package

DescriptionDistrict Length

(Km)

Date of Signing of Contract

Suggestions Remarks

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Critical Issues Reasons for Slow

Progress

Contract Awarded

Cost / Engineers Estimate/Indicative Cost (In

Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at

Completion (In Million

Rs)

Cumulative Progress upto Feb

10

Contracts Tendered

28

Town Roads Kargil - G4-Lot2 B.M(Circular road, Goma Kargil)

Kargil 3.60 18.04 18.04 18.04 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00 0.00 0.00

Fresh IFB issued on 22/02/10Fresh Tender received

29

Town Roads Kargil - G4-Lot1 B.M (G.M Pora,Trespone link Roads)

Kargil 3.60 11.00 11.00 13.70 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00 0.00 0.00

Fresh IFB issued on 22/02/10Fresh Tender received

Total Contracts To Be Tendered Transport Kashmir Roads 29.04 29.04 31.74 0.00 0.00 0.00

3853.17 4541.56 6375.64 3101.90 23.80 3125.69Total Transport Kashmir -Roads

Page 78: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 43 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ANNEXURE - IID TRANSPORT KASHMIR BRIDGES

Page 79: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐10 ANNEXURE ‐ IIDMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar

10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 KASHMIR BRIDGESContracts Awarded

1 Bridge at Gundtaldara Srinagar 1 X 18m 18 2-Feb-06 01-Feb-08 /

30-June-09 7.70 7.70 11.60 100% 97.80% 0% 0.00% 100% 97.80% 4.83 0.00 4.83

JKPCC.PCSS NO 0004Allotted Under Force Account

Bridge including approaches completed and opened to traffic.

No issue at present

2 Bridge at Laktipora Anantnag 1 X 18m 18 17-Feb-06 16-Feb-08 /

31-Dec-08 12.00 12.00 12.80 100% 99.97% 0% 0.00% 100% 99.97% 12.74 0.00 12.74JKPCC.

PCSS NO 0018. Force Account

Bridge including approaches completed and opened to traffic.

No issue at present

3 Bridge at Kani Kadal Srinagar 1 X 32m 32 2-Feb-06 01-Feb-08 /

31-Dec-08 15.40 15.40 15.40 100% 100.00% 0% 0.00% 100% 100.00% 12.74 0.00 12.74JKPCC.

PCSS NO 0007. Force Account

Bridge completed & opened to traffic.

No issue at present

4Bridge near Town Hall Budgam

Budgam 1 X 26m 26 17-Feb-06 16-Feb-08 /31-Mar-09 15.20 15.20 29.70 100% 95.50% 0% 0.00% 100% 95.50% 15.74 0.00 15.74

JKPCC. PCSS NO 0016. Force Account

Bridge completed with approaches, inaugurated & opened to traffic.

No issue at present

5 Dachinpora Bridge Baramula 2 x 25 m 50 21-Nov-07 17-Mar-09

31-Jul-09 19.60 22.45 24.67 100% 98.58% 0% 0.00% 100% 98.58% 24.22 0.00 24.22M/S Mohammad

Shahnawaz Beigh / PCSS No 0058

Bridge completed & opened to traffic.

No issue at present

6 Popchan Bridge Bandipora 2 x 26.285 m 52.6 4-Dec-07 7-Mar-0931-May-09 28.39 41.33 46.50 100% 95.35% 0% 0.00% 100% 95.35% 44.03 0.00 44.03

M/S Sofi & Company,Beehama-Ganderbal / PCSS No 0062

Bridge completed & opened to traffic.

No issue at present

7Bridge at Naraspora Budgam

Budgam 1 X 22m 22 17-Feb-06 16-Feb-08 /30-June-09 13.00 13.00 18.40 100% 74.64% 0% 0.00% 100% 74.64% 11.22 0.00 11.22

JKPCC. PCSS NO 0017. Force Account

Bridge completed. No issue at present

8 Bridge at Teilbal Srinagar 1 X 26m 26 2-Feb-06 01-Feb-08 /30-June-09 10.70 10.70 17.30 100% 93.10% 0% 0.00% 100% 93.10% 11.85 0.00 11.85

JKPCC. PCSS NO 0008. Force Account

Main Bridge & Approaches completed excluding B.T of approaches.

Land acquisition required forappraoches - 600 Sqm area

9 Soaf Shali Bridge Anantnag 4 x 30 m 120 31-Jul-07

13-Sep-08 /30-June-0930-Nov-09

42.10 42.10 55.90 100% 97.73% 0% 0.00% 100% 97.73% 45.49 0.00 45.49

M/S Tarmac Road and Roof Builders/ PCSS

No 0047

Bridge completed, inaugurated & opened to traffic.

Date of Signing of Contract S.No

Contract Package

DescriptionDistrict Span Length (Mts) Critical Issues Reasons for

Slow Progress Suggestions Remarks

Cumulative Progress upto Feb 10

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Date of Completion as per Contract /Date of Time

Extension

Contract Awarded Cost /

Engineers Estimate/

Indicative Cost (In Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at Completion (In

Million Rs)

Page 80: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐10 ANNEXURE ‐ IIDMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar

10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 KASHMIR BRIDGES

Date of Signing of Contract S.No

Contract Package

DescriptionDistrict Span Length (Mts) Critical Issues Reasons for

Slow Progress Suggestions Remarks

Cumulative Progress upto Feb 10

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Date of Completion as per Contract /Date of Time

Extension

Contract Awarded Cost /

Engineers Estimate/

Indicative Cost (In Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at Completion (In

Million Rs)

10 Bridge at Sail Pulwama Pulwama 1 X 22m 22 14-Jun-07 13-June-09

09-Jan-10 10.80 10.80 22.30 95% 89.93% 0% 0.00% 95% 89.93% 8.11 0.00 8.11JKPCC.

PCSS NO 0041. Force Account

Foot Bridge completed. Bridge completed & Slab laid including dirt walls & railing . proposals for approaches submitted to ERA.

Land acquisition required forappraoches - 1700 Sqm areaPHE line 50m Electric Poles -5 NosNon Fruit Bearing trees- 18 Nos required to be removed

JKPCC asked to submit the

estimate for approaches.

11 Bridge at Yarbugh village Baramula 1 X 37m 37 14-Jun-07 13-June-09

27-Oct-09 20.30 20.30 36.60 80% 57.22% 0% 0.00% 80% 57.22% 10.63 0.00 10.63JKPCC.

PCSS NO 0044. Force Account

Stagging for casting of bridge girders completed. 03 prestressed concrete Girder cast. Two Girders stressed

Inadequate man and machinery deployed by contractor.

Agency to arrange men &

machinery

12 Sonwani Bridge Kupwara 3 x 30 m 90 18-Dec-0722-April-0931-Dec-0931-July-10

49.80 49.80 64.76 90% 67.32% 0% 1.24% 90% 68.56% 36.72 2.42 39.14

M/S New Asian Construction

,Mumbai/PCSS No 0065

Substructure comprising of two abuts & Two Piers completed. Concreting of central span completed except prestressing.

Land acquisition 740 sqmStructures to be removed:Forest Check Post 1 NosUtilities to be shiftd:PDD 90 m, Electric poles 5 nosFruit bearing Trees 5 nos, Non Fruit Bearing Trees 84 nos

Taken up with the concerned quarters

13 Wahibugh Bridge Pulwama 2 x 30 +

1 x 35 95 15-Mar-08 9-Aug-09 26.53 26.53 38.50 100% 61.90% 0% 4.96% 100% 66.86% 16.13 1.98 18.10M/s Sohrab Iqbal

Goni (JV)PCSS NO 0077.

Foundation of both abuts & Piers laid. Substructure of both abuts & Piers completed upto cap level. Protection work of span A2 / P2 and Span P2 / P1 completed. Superstructure of span A2 / P2 in progress. Protection work of Span A1-P1 in progress

wall Nut Trees - 5 NosMulbery Trees - 2 nos

Taken up with the concerned quarters

14 Chanpora-Kunzer Bridge Baramula 1 x 40 m

1 x 14 m 54 9-Apr-08 23-Aug-0916-July-10 20.10 20.10 27.02 100% 21.62% 0% 0.02% 100% 21.64% 13.70 0.00 13.70

M/s Sohrab Iqbal Goni, Srinagar

PCSS NO 0081.

Substructure of both the spans completed. Stagging of 40mt span completed & Girder shuttering in progress. Reinforcement of 2 No Girders in progress. Beaings (6 Nos) fixed. Earth filling of approach on Chanapora side in progress.

Land acquisition 1300 sqmStructures to be removed:Commercial Buildings 4 Nos.Utilities to be shiftd:PHE 10 m, PDD 10 m, Electric poles 3 nosWalnut trees- 8 Nos

Taken up with the concerned quarters

15 Bonchak Bridge Pulwama 2 X 30 m 60 9-Apr-08 23-Aug-0930-Sep-10 21.10 21.10 32.80 50% 8.31% 0% 0.76% 50% 9.07% 6.50 0.00 6.50

M/s Sohrab Iqbal Goni, Srinagar

PCSS NO 0082.

Foundation of pier & abut A2 completed. Substructure of Abutt & pier 2 in progress. Protection work of Span A2-P2 in progress.

Land acquisition for approaches - 1037 sqm PHE line 30 M, BSNL 60mFruit Bearing Trees 143 nos

Follow up action to be taken with line department to resolve the issues

Page 81: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress Report March ‐10 ANNEXURE ‐ IIDMultisector Project for Infrastructure Rehabilitation in JK

Project  Management Consultants

Physical & Financial Progress of Works - March 2010COMPONENT B TRANSPORT

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Des

ign

Con

stru

ctio

n

Upto Ending Feb 10

During Mar 10

Upto Ending Mar

10

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 KASHMIR BRIDGES

Date of Signing of Contract S.No

Contract Package

DescriptionDistrict Span Length (Mts) Critical Issues Reasons for

Slow Progress Suggestions Remarks

Cumulative Progress upto Feb 10

Progress During Mar 10

Cumulative Progress upto Mar 10 Expenditure (In Million Rs)

Contractor / PCSS No Status/ Progress

Date of Completion as per Contract /Date of Time

Extension

Contract Awarded Cost /

Engineers Estimate/

Indicative Cost (In Million Rs)

Contract Value(Awarded

+ Approved variation) /Engineers Estimate/

Indicative Cost (In Million Rs)

Likely Cost at Completion (In

Million Rs)

16 Tokina bridge Pulwama 4 x 30 m 120 29-May-08 8-Feb-1031-Dec-10 90.60 90.60 99.84 100% 41.63% 0% 0.00% 100% 41.63% 50.18 0.00 50.18 Tarmac Builders

PCSS NO 0086.

Concreting A2 full 31.5 mtrs of well steining completed. P3 full 28.5 mtr of well steining completed. P1 28.5 mtrs of well steining completed. P2 - 26 mtrs of well steining completed.

Land acquisition for approaches - 2940 sqm Residential / Commercial - 5 Nos.Utilities to be shifted:PDD 20 mElecteric Poles 2 nos

Design issue sorted out, work resumed.

17 Urbis Bridge at Leh Leh 1 x 55 55 4-Dec-08 1-Jan-10

30-May-11 29.00 29.00 41.02 85.0% 0.26% 0% 0.00% 85.0% 0.26% 0.00 5.80 5.80M/s Granco Industries

PCSS NO 0095.

E/w in progress. Work Suspended for fresh Geotech Investigations

Design to be finalised By DSC

Geologist Report submitted, design being redone as per site requirement

18Tharmusa Pushkum Bridge at Kargil

Kargil 1x25 25 14-Oct-08 11-Nov-0930-Sep-10 17.15 17.15 29.42 100% 24.28% 0% 0.00% 100% 24.28% 5.28 0.00 5.28

M/s Granco Industries

PCSS NO 0094.

Concreting of Foundation of RHS abut. Laid. Shuttering for 3rd lift of LHS abutt in progress.

Land acquisition for approaches - 2793 sqm Non Fruit Bearing Trees 82 nos

Follow up action to be taken with revenue department to resolve the issues

19 Saidpura Bridge Srinagar 1 x 40m 40 6-Dec-08 2-Jan-1015-Dec-10 52.22 52.22 62.86 85% 21.20% 0% 0.00% 85% 21.20% 18.53 0.00 18.53 Tarmac Builders

PCSS NO 0092.

On Harwan side well Kerb along with 3 steining completed and on Ganderbal side 6 lifts with Kerb completed.

Land acquisition for Right side Abutment approaches - 150 sqm PHE Line -70 m 1 No boundary wall

Chemical treatment for rock cutting considered and chemicals being procured. Work will be resumed soon

20 Bridge at Padshahi Bagh Srinagar 1 X 26m 26 24-Aug-09 20-Sep-10 21.88 21.88 27.43 100% 22.47% 0% 0.56% 100% 23.03% 7.91 2.44 10.35

Riyaz Construction Co.PCSS NO 104

Role of JKPCC closed. 16 piles cast.

Land acquisition for approaches - 525 sqm Structures to be removed:1 no. irrigation & Flood Control Hut including Land

Follow up action to be taken with revenue department to resolve the issues

21

Bridge in Km 4th of Singhpora Kanihama Road via Gund Khwaja Qasim ”

Srinagar 1 X 24m 24 26-Feb-10 24-03-2011 18.67 18.67 19.64 100% 0.00% 0% 0.00% 100% 0.00% 0.00 0.00 0.00

Letter of commencement of work issued on 04-03-2010.Date of commencement 25-03-2010

22 Construction of 1*21 Mtr Span Bridge (Kirkadal) in Km 2nd Bijbehara Langanbal Road

Anantnag 1X21 21 20.00 20.00 31.00 100% 0.00% 0% 0.00% 100% 0.00% 0.00 0.00 0.00

Notification of Award issued on 22-02-2010.

Total Contracts Awarded Transport Kashmir Bridges562.24 578.03 765.46 356.54 12.64 369.18

562.24 578.03 765.46 356.54 12.64 369.18Total Transport Kashmir -Bridges

Page 82: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 44 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ANNEXURE - II E CONSULTANCY

Page 83: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Monthly Progress  Report March ‐ 10 Annexure ‐ II EMultisector Project for Infrastructure Rehablitaion in JK

Project Management Consultants

COMPONENT CONSULTANCY & INCREMENTAL COST

Upto Ending February 10 During March 10 Upto Ending March

101 2 3 4 5 6 7 8 9

1 Project Management Consultancy Services Scott Wilson India Pvt. Ltd with LBI 0001 27/Oct/05 221.35 144.88 0.00 144.88

2 Contract for Design and Supervision Consultancy -Jammu Urban (DSCI )

Stup Consultants Pvt. Ltd. Kolkatta 0002 27/Dec/05 103.28 84.27 1.49 85.77

3 Contract for Design and Supervision Consultancy Services for Srinagar Urban Package (DSC II)

Intercontinental Consultants & Technocrats Pvt Ltd. with Shah and Infra Pvt Ltd.

0003 26/Dec/05 84.90 62.58 0.00 62.58

4 Design and Supervision Consultancy for Jammu Transport DSC III

Intercontinental Consultants & Technocrats Pvt Ltd. 0006 20/Jan/06 76.80 64.93 0.00 64.93

5 Design and Supervision Consultanty (transport sector Component - Kashmir DSC IV)

Span Consultants Pvt. Ltd. 0005 20/Jan/06 130.16 102.89 2.92 105.81

Total Disbursement- Consultancy 459.55 4.41 463.97

1 Incremental and administrative expenditure J&K ERA 0009 Mar-06 163.00 325.37 10.16 335.53

Total Disbursement- Incremental Cost & Administrative Expenditure

325.37 10.16 335.53

Total Disbursement -Consultancy & Incremental & Administrative Cost 784.92 14.57 799.50

CONSULTANCY

INCREMENTAL & ADMINISTRATIVE EXPENDITURE

Financial Status of Consltancy & Incremental Cost - March 2010

S.No Contract Package Description Contractors Name PCSS NO Date of Signing of Contract

Contract Package Cost

Expenditure (In Million Rs)

Page 84: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Scottwilson India (P) Ltd Page 45 of 45 Louis Berger Group INC, USA

Project Management Consultants Monthly Progress Report –March 2010

MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND

ADDITIONAL INFORMATION

Page 85: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Point No. Jammu Urban

(i)List of contracts having major site clearance problems such as land acquisition, handing over of sites, shifting of utilities, environmental/forest clearance, cutting of trees etc. (which are affecting the progress and are not expected to be completed within 3 months)

Nil

(iI)List of contracts having minor site clearance problems such as land acquisition, handing over of sites, shifting of utilities, environmental/forest clearance, cutting of trees etc. (will be completed within 3 months or will take more than 3 months but will not affect the progress of work)

Nil

(III) List of contracts having specific design problems or generic design problems across the contracts, which is affecting implementation.

Nil

(iv) List of contracts affected by poor performance of contractors that require particular attention or action such as mobilization of additional resources

Nil

(vi) Chronic poor performance of contractors on multiple contracts

Nil

(vi) List of contracts for which contract variations are pending

Nil

(vii) List of contracts for which extension of time is pending.

Nil

(viii) List of contracts for which contract variation is to be provided to ADB (variations less than 15%)

Rehabilitation and Chanelisation of Existing Primary Drains and Construction of New Secondary Drains Upstream of Akhnoor Road

(ix) List of contracts for which contract variation is to be submitted for ADB approval (variations more than 15%)

Nil

(xi) List of contracts for which payment to the contractor has not been made for more than 2 months

Nil

Page 86: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Package No

Package Name PCSS No.Original Contract

Value

Completion cost for

the contract

Cost of price adjustment paid

or to be paid

Date of physical

completion

Date of taking over date of

handing over to line deparment

Reasons if not

handed over

Status of final bill prepared or not, if

pending with whom

Status of time

extenions approved or

not

UJ/WS/02 and part of 1/03/LCB/06

Replacement of Rising mains,laying new rising mains &gravity mains in various partsof Jammu city [Strengtheningof existing system. (Phase-I)]

0019 218.50 209.20 10.23 31.12.2008 - -Submitted to PIU, Jammu

Approved

UJ/WS/02 and part of 1/03/Ph-II /LCB/06

Replacement of Rising mains,laying new rising mains &gravity mains in various partsof Jammu city [Strengtheningof existing system. (Phase-II)]

0032 76.50 38.50 1.73 31.12.2008 - - Under preparation Approved

UJ/WS/03/01/LCB/06

Construction of 22 Tube Wells under Jammu (East) Water Supply Rehabilitation

0014 109.80 Under preparation

Construction of 30 nos. tube wells inwest of Jammu city and associatedworks in west of Jammu city.

Lot-1 0069 45.55 Under preparationLot-2 0070 44.14 Under preparationLot-3 0071 43.51 Under preparationLot-4 0072 21.78 Under preparation

UJ/WS/2/02/NCB/0

7

Design and Construction of Over Head Tanks (OHT'S) & Ground Level Service Reservoirs (GLSR'S) and other allied works at Jammu City West.Lot-2 ( 6 nos. OHTs, 3 GLSRS)

0067 76.80 Under preparation

Procurement of Equipment andVehicle for Garbage and Draincleaning in Jammu & Srinagar

Group 1 : Front End Loader 0060 7.50 7.30 22 / 30.12.200 - -Submitted to PIU, Jammu

List of completed contracts

UJ/WS/2/01/NCB/0

6

UJ&S/SWD/9/01/IS/06

Page 87: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Package No

Package Name PCSS No.Original Contract

Value

Completion cost for

the contract

Cost of price adjustment paid

or to be paid

Date of physical

completion

Date of taking over date of

handing over to line deparment

Reasons if not

handed over

Status of final bill prepared or not, if

pending with whom

Status of time

extenions approved or

not

List of completed contracts

Group 3 : Suction cum JettingMachine 4KL & 7.5KL

17.05.2008 - -Submitted to PIU, Jammu

Group 3 : Suction Machine 4KL& 7.5KL

17.05.2008 - -Submitted to PIU, Jammu

Supply & Delivery of WaterTanker 4KL & 9KL

0055 19.98 17.30 14.11.2006 - -Submitted to PIU, Jammu

Lot-2- 2A-(Backhoe Loader cumExcavator-4nos) 0099 8.23 8.33 31.01.2010

Submitted to PIU, Jammu

Lot-2- 2B- (Skid Loader withattachments-4nos). 0100 8.49 8.04 31.01.2010

Submitted to PIU, Jammu

0055 13.27 13.10UJ&S/SWD/9/01/IS/06

Page 88: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

S.No. Contract completion schedule Contracts brief title PCSS No.Likely

completion cost

Revised completion schedule if any

Revised completion costs if any

Reason for revision

1 Upto October 09 Construction of 19 tube wells 0014 140.71 Mar-10

Construction of 30 tube wells 0069 176.79 Nov-09

Redevelopment of 38 tube wells 0096 8.37 Jun-10

Construction of 30 pump houses 0072 26.28 Dec-09

Pocurement of Water Tanker 4KL & 9KL 12.70 Jan-10

Intake pump near Boria 0066 77.60 Jul-10

Construction of 9 OHT's and 4 GLSR's of Jammu (East)lot 2

0061 130.48 Aug-10

Construction of 6 OHT's and 3 GLSR's of Jammu(West) lot 2

0067 82.25 Mar-10

Construction of 8 OHT's and 2 GLSR's of Jammu(West) lot 3

0053 89.00 Jun-10

Pay and Use Toilets 0038 24.56 Mar-10

Landoichoi Primary Drain 0033 206.73 Jun-10

Primary drain in Talab Tillo Area 0021 238.62 Dec-10

Construction of 12 OHT's and 5 GLSR's of Jammu(East) lot 3

0074 99.88 Dec-10

Construction of 6 OHT's and 3 GLSR's of Jammu(West) lot 1

0063 96.79 Aug-10

Replacement of rising mains, laying new rising mains(Phase-III)

0054 541.52 Jun-10

(Garbage Carrier Container (Tipper) 3.5 cum 5.13 May-10

(Garbage Carrier Container (Tipper) 8.0 cum 13.75 May-10

Dumper placer suitable for Garbage container 4.5 cum10 nos & Garbage container 4.5 cum 175 nos(100 forJammu & 75 for Srinagar)

14.60 Jul-10

Replacment of worn out pipes in Jammu City, Package1

0075 349.54 Aug-10

Replacement of worn out pipes in Jammu City,Package II

0079 374.66 Aug-10

Rehabilitation and Channelization of existing primarydrain and construction of new drains u/s of Akhnoorroad

0034 314.33 Jul-10

3024.29

5 July 2010 to September 2010

Sub Total

2 October 2009 to December 2009

3 January 2010 to March 2010

4 April 2010 to June 2010

Page 89: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Point No. Jammu Transport

(i) Revised work plan from the contractors for remaining worka) Udhampur – Ramnagar and Chenani – Sudhmahadev – Mantalai roadb) Doda – Bharth roadc) Bani – Daggar roadd) Kalibari – Kathua – Hatlimorh roade) Darabshalla – Bimalnag roadf) Kooh Nallah Bridge by JKPCCg) Khagote Nallah Bridge by JKPCC.h) Moutlian Bridge by JKPCC(ii) List of Contracts for which revised work plan has not been submitted :a) Sidhra-Surinsar-Mansar Road

(iii)List of contracts having major site clearance problems such as land acquisition, handing over of sites, shifting of utilities, environmental/forest clearance, cutting of trees etc. (which are affecting the progress and are not expected to be completed within 3 months)

a) Kalibari – Kathua – Hatlimorh road (• BSNL Line Shifting • PDD Line • PHE Line)

b)Udhampur – Ramnagar road (• PDD poles at Km 16.4 - 16.42 & Km 25.800 )PHE Line Km 226.5

c)Sidhra – Surinsar – Mansar road (• Clearance from ADB for Wild Life Sanctuary KM 18.5 to KM 38.5.

(iv)List of contracts having minor site clearance problems such as land acquisition, handing over of sites, shifting of utilities, environmental/forest clearance, cutting of trees etc. (will be completed within 3 months or will take more than 3 months but will not affect the progress of work)

a) Doda – Bharth road ( Land Acquisation)

b) Darabshalla – Bimalnag road ( Land Acquisation)

c) Bani Dhgger road (Structure too be removed)

(v) List of contracts having specific design problems or generic design problems across the contracts, which is affecting implementation.

a) Bani – Dhaggar road (In-correct survey and hence revision of complete design.)

(vi) List of contracts affected by poor performance of contractors that require particular attention or action such as mobilization of additional resources

a) Bani – Dhaggar road ( M/s Harish Chandra (India) Ltd.)

b) Darabshalla – Bimalnag road (Malik Construction)

c) Doda Bharth road

(vii) Chronic poor performance of contractors on multiple contracts

a) Bani – Dhaggar road

b) Kooh Nalah JKPCC

c) Khaghote Nallah JKPCC

d) Devak Nallah

(viii) List of contracts for which contract variations are pending

a) Kalibari – Kathua – Hatlimorh road

(ix) List of contracts for which extension of time is pending.

a) Moutlian Bridge

Page 90: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Point No. Jammu Transport

(x) List of contracts for which contract variation is to be provided to ADB (variations less than 15%)

a) Doda – Bharth road

b) Darabshalla – Bimalnag road

c) Udhampur – Ramnagar & Chenani – Sudhmahadev road

(xi) List of contracts for which contract variation is to be submitted for ADB approval (variations more than 15%)

a) Sidhra -Surinsar - Mansar road

b) Bari Brahmana – Bishnah road

(xii) List of contracts for which payment to the contractor has not been made for more than 2 months

a) Bani – Daggar road (Bill yet submitted by contractor)

b) Darabshalla - Bimalnag road (Bill not submitted by contractor)

c) Moutlian bridge (No Bill submitted)

Page 91: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Package No. Package Name PCSS No.Original Contract

Value

Completion cost for the Contract

Cost of Price adjustment paid or

to be paid

Date of Physical

Completion

Date of taking over

Date of Handing over to line department

Reasons if not handed

over

Status of final prepared or not,if pending with

whom

Status of time Extension approved

or not

Transport/Jammu/Jmu/Road/03

Widening and Strenthening of Bari-Brahamna Bishnah Road

0035 Rs. 6.33 Crores Rs. 7,44,41,870.00 Rs. 4033610.00 30-Apr-09 1-May-09

ERA has been requested vide letter no.

ICT/446/ERA/TL/3989 Dated 25-09-2009 to

process the handing over.

In progressFinal bill yet to be submitted by the

contractor

First EOT approved upto 31-12-2008.

Second EOT under progress.

List of Completed Contracts

Page 92: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Schedule Cost

1 Upto December 09 Bari Brahmana Road 0035 78.87 Completed

2 January 2010 to March 2010Devak Nallah Bridge 0011 36.88 28.02.2010

Chenani - Sudhmahadev - Mantalai road

0028-B 320.44 30.06.2010

Kooh Nallah Bridge 0023 40.09 31.05.2010 As per revised scope

5 July 2010 to September 2010 Kaghote Nallah Bridge 0022 36.31 31.08.2010 As per revised scope

Udhampur - Ramnagar road 0028-A 414.84 31.10.2010 Revised completioon dateapproved by TAC on 26Jan. 2010

Drabshalla - Bimalnag road 0076 145.30 31.12.2010

Doda - Bharth road 0057 336.10 31.12.2010

Saki - Maidan - Kalai road (Contract terminated - Case Sub-judice)

0037 Revised cost will be givenbased on retendering cost.

Bani - Daggar road 0036 119.85 30.06.2011

Kalibari - Kathua - Hatlimorh road 0085 389.87 30.06.2011

Sidhra - Surinsar - Mansar road 0027 589.22 30.06.2011

2507.78

JAMMU (TRANSPORT)

April 2011 to June 20117

Sub - Total

4 April 2010 to June 2010

IFB Issued

QUARTERLY COMPLETION SCHEDULE - DSC - III JAMMU (TRANSPORT)

Contract completion schedule as per DSC-III

S.No. Revised Completion

schedule if any

Revised Completion costs if any (in million)

Reason for revisionAs per DSCsLikely completion

costs including variations, price

adjustment, utility shifting etc. under the contract but

excluding land cost (In million)

PCSS No.

Contracts brief title

Page 93: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Point No. Kashmir Transport(i) Revised work plan from the contractors for remaining work: Under Preparation -- Shall be submitted.

(ii) List of Contracts for which revised work plan has not been submitted :a) -b) -c) -

(iii)List of contracts having major site clearance problems such as land acquisition, handing over of sites, shifting of utilities, environmental/forest clearance, cutting of trees etc. (which are affecting the progress and are not expected to be completed within 3 months): 10

a) Jehangir Chowk -SKIMS Road

b) Qazigund - Kulgam Road

c) Sopore - Bandipora Roadd) Shadra - Kamalkote Roade) Hubdipora - Kadar Roadf) Thajiwara - Shangus Roadg) Circular Road and Goma Kargil Roadh) Natipora - Chadoora - Chrar-i-Sharief Roadi) Tokina BridgeJ) Bonchak Bridgek) Thramusa Pashkum Bridgel) Chanapora - Kunzer Bridgem) Sonawani Bridge

(iv)List of contracts having minor site clearance problems such as land acquisition, handing over of sites, shifting of utilities, environmental/forest clearance, cutting of trees etc. (will be completed within 3 months or will take more than 3 months but will not affect the progress of work): 02

a) Natipora - Nowgam - Newa Road

b) Kralgund - Ashpora Roadc) Handwara - Zachaldara Roadd) Saidpora Bridgee) Potkhah - Pachar Roadf) Padshahibagh Bridge

(v) List of contracts having specific design problems or generic design problems across the contracts, which is affecting implementation. 01

a) Bridge at Urbis ( During Excavation of Foundation Fissures were noticed in the bed rock which necessiated re-exploration of the strata. Steps have been taken for redesign of the foundation.

(vi) List of contracts affected by poor performance of contractors that require particular attention or action such as mobilization of additional resources

Nil(vii) Chronic poor performance of contractors on multiple contracts

Nil(viii) List of contracts for which contract variations are pending : 11

a) Natipora - Chadoora - Chrar-i-Sharief Road

b) Hubdipora - Kadar -Qaimoh Road

c) Sopore - Bandipora Road

d) Shadra - Kamalkote Road

e) Watergam - Behrampora Roadf) Tokina Bridge

g) Bonchak Bridge

Page 94: MULTI SECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN ... · MULTISECTOR PROJECT FOR INFRASTRUCTURE REHABILITATION IN JK ADB LOAN 2151 IND CHAPTER 1 EXECUTIVE SUMMARY OVERALL

Point No. Kashmir Transporth) Thramusa Pashkum Bridge

i) Chanapora - Kunzer Bridge

J) Sonawani Bridge

k) Wahibugh Bridge

(ix) List of contracts for which extension of time is pending: 11

a) Jehangir Chowk -SKIMS Road (2nd Extension)

b) Natipora - Chadoora - Chrar-i-Sharief Road

c) Hubdipora - Kadar -Qaimoh Road

d) Sopore - Bandipora Road

e) Shadra - Kamalkote Road

f) Tokina Bridge

g) Padshahibagh Bridge

h) Saidpora Bridge

i) Yarbugh Bridge

J) Sail Bridge

k) Leh Town Roads 33 Lot-2

(x) List of contracts for which contract variation is to be provided to ADB (variations less than 15%): 04a) Thajiwara - Shangus Roadb) Natipora - Nowgam - Newa Roadc) Singhpora - Kanihama Roadd) Dachinpora Bridge

(xi) List of contracts for which contract variation is to be submitted for ADB approval (variations more than 15%): 13

a) Sangrama -Sopore - Kulangam Road

b) Qazigund - Kulgam Road

c) Handwara - Zachaldara Road

d) Kralgund - Ashpora Road

e) Potkhah - Pachar Road

f) Sumbal - Markundal Road

g) Jehangir Chowk -SKIMS Road

h) Circular Road and Goma Kargil Road

i) G M Pora & Trespone Road

J) Leh Town Roads 32 Lot-1

k) Leh Town Roads 32 Lot-2

l) Leh Town Roads 33 Lot-2

m) Papchan Bridge

(xii) List of contracts for which payment to the contractor has not been made for more than 2 months

Nil