mswe rfi 9-01-11 (v2) - 2

Upload: brian-cummins

Post on 06-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    1/25

    CITYOFCLEVELAND,OHIO

    DEPARTMENTOFPUBLICUTILITIES

    CLEVELANDPUBLICPOWER

    REQUESTFORINFORMATION

    ANDQUALIFICATIONS

    FORA

    MUNICIPALSOLID

    WASTE

    TO

    ENERGY

    FACILITY

    September1,2011

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    2/25

    TableofContents

    Page

    SubmissionInstructions . . . . . . . . 3

    Definitions . . . . . . . . . . 4

    Introduction . . . . . . . . . . 7

    Background . . . . . . . . . . 8

    ScopeofInformationRequest . . . . . . . 9

    GeneralProjectInformation . . . . . . . . 10

    AirPermitApplication . . . . . . . . 11

    EconomicBenefits . . . . . . . . . 13

    RidgeRoadTransferStation . . . . . . . . 14

    CommerciallyAvailableConversionTechnology . . . . . 16

    ProjectDesignObjectives . . . . . . . . 17

    TradeSecrets . . . . . . . . . . 18

    RequestedForInformation . . . . . . . . 19

    EvaluationofResponses . . . . . . . . 21

    RequestForQualifications . . . . . . . . 23

    Attachments

    Attachment1 CityofClevelandWasteCompositionStudy

    Attachment2 CityofClevelandAirPermitApplication

    2

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    3/25

    SubmissionInstructions

    SubmissionRequirements:

    1. ResponsestothisRequestforInformation(RFI)shouldbeformattedin12pointTimesNewRomanfont,appropriateforprintingonsinglesided,singlespaced8.5by11inch

    paper,with1inchmargins.

    2. Provideaonepagecoversheetthatidentifiesthetitle,organization(s),respondent'stechnicalandadministrativepointsofcontact includingnames,addresses,phoneand

    faxnumbers,andemailaddressesofallcoauthors.

    3. Aonepageexecutivesummary.4. Pleaseprovidedetailedinformationregardingyourcompanysproductsorservicesthat

    mayassistthedevelopmentofthedescribedProject.

    SubmissionInstructions:

    All information submitted in response to this request must be submitted electronically to

    Lissett Capeles at [email protected] or Aliea McBooth at [email protected] by 5:00 pm

    EasternTimeonThursday,December1,2011.Allsubmissionsmustbe ineitherMSWordor

    PDFformat.

    ContactPerson:

    FormoreinformationonthisRFI,contactLissettCapeles,at2166643922#281orat

    [email protected]#[email protected].

    DISCLAIMER:

    ThisRFIisissuedasameansoftechnicaldiscoveryandinformationgathering.Itisforplanning

    purposesonlyandshouldnotbeconstruedasasolicitationoranobligationonthepartofthe

    Cityof

    Cleveland

    (City)

    to

    make

    any

    purchases

    or

    enter

    into

    any

    contracts.

    Participation

    in

    this

    RFIisvoluntaryandtheCitywillnotpayforthepreparationof: (1)anyinformationsubmitted

    byarespondent;or(2)theCitysuseofthatinformation.Respondentsdonotneedtoprepare

    detailedproposalsatthisstagebutshouldprovidebasicinformationregardingtheircapabilities

    andanindicationastohowtheywouldapproachworkingwiththeCityofClevelandtoachieve

    theProjectDesignObjectives.

    3

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    4/25

    Definitions

    Ash Residualsubstanceproducedduringtheburning,combustionoroxidationofwaste

    materials.

    Baghouse

    Air

    pollution

    control

    device

    that

    removes

    particulates

    out

    of

    air

    or

    gas

    released

    fromcommercialprocessesorcombustionforelectricitygeneration.

    BestAvailableTechnology(BAT)Referstothemoststringenttechnologyavailablefor

    controllingemissions.

    BoilerAnenclosedvesselinwhichwaterisheatedandcirculatedassuperheatedsteamfor

    thepurposeofheating,powering,and/orproducingelectricity.

    CarbonFootprintMeasureoftheimpactouractivitieshaveontheenvironment.

    CurbsideCollection

    A

    recycling

    program

    where

    recyclable

    materials

    are

    collected

    from

    homes

    orplacesofbusinessbymunicipalorprivatepartiesfortransfertoadesignatedcollectionsite

    orrecyclingfacility.

    Dioxins Dioxinsareaclassofchemicalcontaminantsthatareformedduringcombustion

    processessuchaswasteincineration.

    EnvironmentalProtectionAgency(EPA) AfederalagencyoftheU.S.governmentthatsets

    environmentalprotectionandenforcementstandards.

    Ferrousmetals

    Metals

    or

    metal

    alloys

    that

    contain

    the

    element

    iron.

    All

    ferrous

    metals

    are

    magneticandtypicallycontainsmallamountsofothermetalstoprovidespecificproperties.

    Gasification Athermochemicalprocessthatconvertscarboncontainingmaterialssuchas

    wasteorothermaterialsintoasynthesisgas(syngas).

    LandfillAlarge,outdoorsitefortheburialofsolidwaste.

    MaterialsRecoveryFacility(MRF)Afacilitythatsortsandprocessescollectedrecyclablesfor

    endusers.

    Metals:Chemical

    element

    or

    compound

    that

    is

    agood

    conductor

    of

    both

    electricity

    and

    heat

    andformsionicbondswithnonmetals.

    MunicipalSolidWaste(MSW)Awastetypeconsistingofeverydayitemsthatareconsumed

    anddiscardwhichpredominantlyincludesfoodwastes,yardwastes,containersandproduct

    packaging,andothermiscellaneousinorganicwastesfromresidentialandsomecommercial

    sources.

    4

    http://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/Waste_type
  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    5/25

    NitrogenOxide(NOx) GenerictermforthemonoNitrogenoxidesanddioxides.Theseare

    producedfromthereactionofNitrogenandOxygengasesintheairduringcombustion,

    especiallyathightemperatures.Inatmosphericchemistry,NOxreactswithmoistureandother

    chemicalstoformsmogandacidrain.NOxarealsocentraltotheformationoftroposphere

    ozone.

    ParticulateMatter(PM)Atermusedforthemixtureofsolidparticlesandliquiddroplets

    foundintheair.Someparticles,suchasdust,dirt,soot,orsmoke,arelargeordarkenoughto

    beseenwiththenakedeye.Othersaresosmalltheycanonlybedetectedusinganelectron

    microscope.Someformincomplicatedreactionsintheatmospherefromchemicalssuchas

    sulfurdioxidesandnitrogenoxidesthatareemittedfrompowerplants,industriesand

    automobiles.

    RecyclableProductsormaterialsthatcanbecollected,separatedandprocessedtobeusedas

    raw

    materials

    in

    the

    manufacture

    of

    new

    products.

    RefuseDerivedFuel(RDF) Aproductderivedfromthephysicaltransformationofwaste

    materialsbysegregating,crushingandmixinghighandlowvalueheatcontentorganicwaste

    materialandsolidifyingittoproducefuelpelletsorbriquettes.Theprocessenrichesthe

    organiccontentthroughremovalofinorganicmaterialsandmoisture.

    ResidentialWaste:Wastegeneratedbysingleormultifamilyhomeswhichincludesmaterials

    suchasnewspapers,clothing,foodpackaging,foodscrapsandyardtrimmings,bottlesand

    cans.

    SingleStreamRecycling Arecyclingprocessinwhichallrecyclablematerialsarecollected

    mingledtogetherwithoutseparation.

    SulfurDioxide Apungent,colorless,gasformedprimarilybythecombustionoffossilfuels.

    Syntheticgas(syngas) Agasconsistingprimarilyofhydrogenandcarbonmonoxidewithhalf

    theenergydensityofnaturalgas.Syngasiscombustibleandoftenusedasafuelorasan

    intermediatefortheproductionofotherchemicals.

    TransferStation Facilitywheresolidwasteistransferredfromcollectionvehiclestolarger

    trucksorrailcarsforlongerdistancetransport.

    TippingFeeThepriceindividuals,communitiesandtrashhaulerspaytodisposeofwasteata

    landfill.

    TippingFloor Theflatsurfaceonwhichthearrivingtrashtrucksdumptheirloadatawaste

    processingfacility.

    5

    http://en.wikipedia.org/wiki/Hydrogenhttp://en.wikipedia.org/wiki/Carbon_monoxidehttp://en.wikipedia.org/wiki/Carbon_monoxidehttp://en.wikipedia.org/wiki/Carbon_monoxidehttp://en.wikipedia.org/wiki/Carbon_monoxidehttp://en.wikipedia.org/wiki/Hydrogen
  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    6/25

    Turbine Adevicethatusessteamtodriveageneratorwhichthenproduceselectricity.WasteCollection Thecomponentofwastemanagementwhichresultsinthepassageofa

    wastematerialfromthesourceofproductiontoeitherthepointoftreatmentorfinaldisposal.

    WasteStream

    The

    total

    flow

    of

    solid

    waste

    from

    homes,

    businesses,

    institutions

    and

    manufacturingplantsandotherlocationsthatmustberecycled,gasifiedordisposedofin

    landfills.

    WasteToEnergyFacility Afacilitywhererecoveredwastematerialsareconvertedintoa

    usableformofenergy.

    6

    http://en.wikipedia.org/wiki/Waste_managementhttp://en.wikipedia.org/wiki/Waste_managementhttp://en.wikipedia.org/wiki/Waste_managementhttp://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/List_of_waste_treatment_technologieshttp://en.wikipedia.org/wiki/Landfillhttp://en.wikipedia.org/wiki/Landfillhttp://en.wikipedia.org/wiki/List_of_waste_treatment_technologieshttp://en.wikipedia.org/wiki/Waste_typehttp://en.wikipedia.org/wiki/Waste_management
  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    7/25

    Introduction

    TheDepartmentofPublicUtilities(DPU)operatestheDivisionofClevelandPublicPower(CPP)

    forthe

    purpose

    of

    supplying

    electric

    power

    to

    customers

    located

    in

    the

    City

    of

    Cleveland.

    Presently,CPPspurchasingnearly100%ofitselectricpowerneedsfromthemarket.This

    projectwillallowCPPtomeetthegoalofreducingCleveland'sdependencyonfossilfuelwhile

    alsoallowingCPPtheabilitytoinvestinlocalgenerationprojectsthatsatisfytheCityselectric

    generationportfoliodiversificationrequirements.,Tothatend,CPPhasappliedforanair

    permitforaMunicipalSolidWastetoEnergy(MSWE)Facility(theProject)attheCityof

    ClevelandsRidgeRoadTransferStation.CPPhasanelectricsubstationonthetransferstation

    propertywhichconnectstothegridat69KV.

    TheCityofClevelandDepartmentofPublicWorksoperatestheDivisionofWasteCollection

    andDisposal(DWC).TheDivisionprovidesweeklycollectionofwastefrom155,000Cleveland

    homes,theCityofClevelandsWestSideMarket,FireandPoliceStations,theJusticeCenter,

    CityHallandotherCitybuildingsandpublicareas.DWCoperatestheRidgeRoadTransfer

    Station,amunicipalsolidwastefacilitylocatedat3727RidgeRoad,Cleveland,Ohio44144..

    Municipalsolidwasteisbroughttothetransferstationviawastecollectionvehicles.Thewaste

    isgatheredandloadedintotransporttrucksandthentakentolandfills.

    TheproposedMSWEfacilityshallutilizethermalandphysicalconversiontechnologiesto

    processmunicipalsolidwaste(MSW)fromtheCityofClevelandandothercommunities. This

    processwillallowtheCityofClevelandtogenerateelectricityandwillproduceanumberof

    marketablebyproducts,suchasrecyclables,refusederivedfuel(RDF)pellets,steam,and

    possiblydecorative

    bricks.

    Ataminimum,thefacilityshallprocesstheMSWandrecyclablesasfollows:curbside

    collection;MSWhandlingandprocessingatanewMaterialRecoveryFacility;recycling;sorting

    andshredding;creationofRDFpellets;conversionofMSWtosyntheticgas;steamproduction,

    electricpowergenerationandtreatmentofemissionstomeetenvironmentalregulations.

    ThisfacilityshallenabletheCityofClevelandtoproduceelectricpowerlocally,utilizeMSWasa

    fuelsource,andalsoassistCPPinmeetingtheCityofClevelandsAdvancedEnergyPortfolio

    Standard(AEPS).TheAEPSrequiresCPPtopurchaseatleast15%ofitsbaseloadpowerfrom

    advanced

    and

    renewable

    sources

    by

    2015.

    ThroughtheissuanceofthisRFI,theCityinvitesinterestedpartiestoproviderelevant

    informationregardinghowtheCitymaybestdevelopawastetoenergyfacility.Inordertobe

    considered,informationprovidedmustbeconsistentwiththerequirementssetforthinthis

    RFI.

    7

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    8/25

    Background

    In2007,ClevelandPublicPower(CPP)createdaspecialprojectteamtoinvestigatethe

    productionofelectricpowerusingmunicipalsolidwasteasthefeedstock. Sincethattimethe

    Teamhasresearchedtheissues;attendedpresentations;hostedmeetingsontechnology

    options;visited

    waste

    to

    energy

    facilities,

    material

    recovery

    facilities,

    recycling

    facilities,

    and

    refusederivedfuelproductionfacilities;attendedwastetoenergyconferences;andmade

    recommendationsregardingthetechnologiesavailableforpowergeneration,suchas

    incinerationandgasification. Basedontheinformationgathered,gasificationappearedto

    presentCPPwitharenewableenergysourcethatwouldconvertMSWintoasyntheticgasfor

    powerproductionandhaveadditionalpositiveenvironmentalimpacts,suchasthe

    minimizationofmaterialssenttolandfillsandlowairemissionimpacts.

    InadditiontocreatingelectricpowerfromMSW,CPPisalsolookingintoreducingClevelands

    dependencyonelectricpowerpurchasesandtheelectrictransmissiongrid. CPPobtainedthe

    services

    of

    RNR

    Consulting,

    URS

    Corp.,

    DLZ

    Ohio

    Inc

    and

    Cloud

    &

    Associates

    to

    assess

    the

    feasibilityofaMunicipalSolidWasteFacilityattheClevelandsRidgeRoadTransferStation.

    TheConsultantassembledateamexperiencedintechnicalanalysesofgasification

    technologies,environmentalpermittingandregulations,trafficstudies,financialanalysisand

    communityassessments. TheConsultantalsoconductedduediligenceanddataoriented

    researchthroughdiscussionswithgasificationtechnologyfirmstoanalyzeexistingdata. The

    Consultantfoundthatgasificationandsteamcompressiontechnologieswerescientifically

    sound,presentnumerousopportunitiesforeconomicgrowthanddevelopment,and

    recommendedsiteinspectionstoseegasificationfacilitiesinoperation.

    In2009,theCitycreatedaMSWESteeringTeam. ThisTeamwascomprisedoflocalinterested

    partieswith

    related

    project

    experience

    and

    City

    employees.

    The

    Team

    was

    created

    to

    guide

    the

    developmentoftheCitysMSWEProjectandparticipatedindetailedbriefingonClevelands

    proposedsystemdesign,themanytypesofgasificationtechnologiesused,recycling,the

    feasibilitystudyfindings,economicdevelopmentregionalimpactsandmore.

    InAugustof2009,adelegationcomprisedofCityofficialsandMSWESteeringTeammembers

    visitedwastetoenergyfacilitiesinJapanandChina. Theobjectivesofthetripweretoobserve

    thetechnologiesinoperation,assessenvironmental/communityimpactsatoperatingfacilities

    andinterviewpersonnel. DuringtheirvisitstheyobservedKinseiSangyoCompany,a

    gasificationtechnologycompany,thathasbeeninoperationsince1967andhasover200

    gasificationplants

    in

    operation

    in

    Asia.

    The

    delegation

    visited

    Kinseis

    headquarters

    and

    demonstrationplantandalsotwolargecustomerinstallations. Bothcustomerfacilitieswere

    locatedinenvironmentallyandresidentiallysensitiveareas.

    8

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    9/25

    In2010,theCityofClevelandandPrincetonEnvironmentalGroupenteredintoapreliminary

    FacilityDesignAgreementfortheMSWEproject. TheClevelandPrincetonMSWEFacility

    DesignagreementprovidesthatPEGdevelopnonconstructiondesignsthatgenerallydescribe

    thedesiredfacility,andsubmitanairpermitapplicationforagasificationfacility. The

    preliminaryFacilityDesignalongwiththeresultsofthisRFIwillbeusedbytheCityasitselects

    consultantsand

    contractors

    to

    further

    develop

    and

    construct

    Clevelands

    MSWE

    facility.

    The

    CityiswaitingforOhioEPAsreviewofthepermitapplication,andexpectsPEGsfinalreportby

    theendofthisyear.

    Theprojectdefinedinthisdocumentshallbedesignedtomeetgovernmentaland

    environmentalregulationswhilemaintainingcapacity,efficiency,reliabilityandachievingsafety

    goals.

    ScopeofInformationRequest

    TheCityofClevelandrequestsinformationandqualificationsfromthermalconversion

    technologyproviders,wastehandlingequipmentsuppliers,projectdevelopers,consultantsand

    financialservicescompanies.RespondentsthatmeettheCitysminimumcriteria(see

    EvaluationofResponsesbelow)shallbeprequalifiedforfurtherparticipationinProject

    development.TheCitycannotassureanyRespondentthatitwillbedeemedqualifiedfor

    furtherparticipation,nordoestheCityguaranteethatitwillenterintoanycontractwithany

    respondentorserviceprovider.

    Asinglerespondentmayrecommendoneormoreprojectdevelopmentoptions.ThisRFIisnot

    a

    request

    for

    the

    proposal

    for

    services.

    It

    is

    intended

    to

    provide

    for

    disclosure

    of

    non

    proprietaryprojectinformationforpublicrelease.Thisincludesanytechnical,environmental,

    oreconomicinformationneededinordertopromotethedevelopmentoftheproject.Tothe

    extentthatanyrespondentprovidesconfidentialorproprietaryinformation,suchinformation

    mustbeclearlymarkedandwillbetheresponsibilityoftherespondenttodefendagainstany

    openrecordschallenges.(ForfurtherinstructionregardingproprietaryinformationseeTrade

    Secretsbelow.)

    9

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    10/25

    GeneralProjectInformation

    CurrentMSWCapacity

    TheCityofClevelandsRidgeRoadTransferStationhasadailyMSWcapacityof3,000tons(264

    daysofoperation).

    TheRidgeRoadTransferStationcollects230,000tonsperyearandhasaveragedailycollections

    ofMSW(includingrecyclables)duringSummerandWinterasfollows:

    Onpeak 991tonsdaily (MarchNovember) Offpeak 756tonsdaily(DecemberFebruary)

    RidgeRoadtotalcapacityis3,000tonsperdayandhasanunusedcapacityasfollows:

    Onpeak 2009tonsdaily Offpeak 2244tonsdaily

    WhyThisOptionforCleveland?

    Clevelandisuniqueinthatit:

    OwnstheMSW Ownsthegarbagetrucks Collectsitsownwaste HasahighvolumeandvarietyofMSW Ownsthetransferstation Hasitsownelectricsystemwithdirectaccesstotheelectricgrid Managesitsownwatersystem Purchases99.9%ofitspowerforCPP,itsmunicipalelectricutility,fromthepower

    marketvialongandshorttermcontracts

    ImposesonCPP,anAdvancedEnergyPortfolioStandard.ClevelandsTopPrioritiesfortheproject:

    ObtainelectricpowergenerationtoreduceCPPsmarketdependence ProduceelectricgenerationthathelpsmeettheCitysAEPSgoals Createanenvironmentallyconsciouswastetoenergyfacility MinimizeMSWsenttolandfill Reduceitswastemanagementdisposalcost AchieverecyclingonaCitywidebasis Achieveaselfsustainingsystem

    10

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    11/25

    GasificationSystemOperation

    BasedonthePreliminaryDesigncurrentlyunderdevelopmentbyPrincetonEnvironmental

    Group,Clevelandsfacilitywouldhavefourgasificationlineswithtwobatchgasifiersoperating

    intandemineachline.

    KinseiGasifierMaxOperation

    Schedule: 12hoursperdaypergasifier(365daysperyear) Feedstock:70tonsofMSW/batch. Cycle: OnebatchofMSWwillbeprocessedeachdayineachgasifier.

    AirPermitApplication

    TheCityofClevelandsubmittedanairpermitapplicationtoOhioEPAonMarch11,2011.The

    Applicationiscurrentlyunderagencyreview.Theairpermitapplicationisbasedonemissions

    using

    Kinsei

    Sangyo

    gasification

    technology.

    The

    City

    of

    Cleveland

    will

    bid

    out

    all

    aspects

    of

    the

    projectincludingthethermalcombustioncomponentoftheproject.IfKinseiwinsthebid,the

    CitywillproceedwiththeKinseigasifier.Ifnot,theCitywillusesomeotherthermalconversion

    technology.However,thewinningapplicantmustataminimumperformatthelevelofthe

    KinseitechnologyemissionsintheClevelandairpermit.

    TheBestAvailableTechnology(BAT)standardsapply.TheNationalSourcePerformance

    Standards(NSPS)subpartAAAAappliestosmallmunicipalwastecombustionunitsforwhich

    constructionoccurredafterAugust30,1999. TheNSPSsubpartEbappliestonewsource

    performance

    standards

    for

    large

    municipal

    waste

    combustors

    constructed

    after

    September

    20,

    1994.Clevelandsfacilityasproposedwillemitpollutantsatorbelowalloftheselevels.TheBATlimitsproposedfortheCPPprojectareequivalentto,ormorestringentthan,eachoftherelevantbenchmarks.(SeetheApplicationinAttachment2).AlthoughairqualitymodelingisnotrequiredpursuanttoOhioEPAEngineeringGuide#69for

    mercuryordioxin,CPPelectedtoincludemodelingforthosetwopollutantstodemonstrate

    thattheimpactfromtheproposedfacilityisfarlessthanlevelsthatunderOhioEPAAirToxic

    PolicyOptionA. Thisrequirementwillapplytoanythermalconversiontechnologythat

    replacestheoneidentifiedintheapplication.

    OhioEPArequiredthatanairqualitycomputermodelanalysisbeperformedontheproposed

    Clevelandfacility.ThemodelcompletedbyGTEnvironmentalpredictshowdifferentair

    pollutantstravelawayfromthesourceofpollution.Basedonthemodelinganalysis,the

    predictedmaximumoffsiteairqualityimpactforeachpollutantemittedbytheoperationof

    theproposedCPPfacilityiswellwithintheguidelinesestablishedbyOhioEPA. This

    11

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    12/25

    requirementwillalsoapplytoanythermalconversiontechnologythatreplacestheone

    identifiedintheapplication.

    TheCitywillworkwithOhioEPAsDivisionMaterialsandWasteManagement(DivisionofSolid

    &

    Infectious

    Waste

    Management)

    as

    necessary

    to

    ensure

    project

    compliance

    with

    all

    solid

    wastelaws.

    OtherEnvironmentalImpactsoftheProposedFacility:

    Odorcontrolsystemsthatremovemorethan95%ofairborneodor Primarilywatervaporemissions(noblack/graysmoke) Noincreasedorhighvolumenoise Mustberesidentialneighborhoodfriendly Thefacilitymustbeenclosedandwillhaveevenlessodorthanthecurrenttransfer

    station

    operation

    Atthecurrentlevel,approximately240varioustypesoftrucksgoinandoutoftheRidgeRoadTransferStationeachday. (Atfullcapacity,thefacilitycouldreceive3,000

    tonsperdayandwouldresultin550trucksperday.)

    MSWreceivedwillbeprocessedeachday.SustainabilityGoals

    UnderClevelandsAdvancedEnergyPortfolioStandard(AEPS),

    ClevelandPublicPowerwillproduceand/orpurchasegenerationfromAdvancedEnergy

    Sources,

    which

    include

    the

    MSWE

    Project,

    to

    meet

    the

    following

    goals

    and

    timelines:

    AEP TargetYear

    15% 2015

    20% 2020

    25% 2025

    AdvancedEnergy

    Portfolio

    Standards

    (AEPS)

    Fuel

    Sources

    TheCityofClevelandsAdvancedEnergyPortfolioStandardsencouragesthedevelopmentofdiverseandalternativeenergyresourcesandwillallowCPPtousethe

    followingsourcestomeettheabovegoals:

    Cogenerationusingcoaland/orRDF DistributedGeneration

    12

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    13/25

    FuelCells PelletsRefuseDerivedFuels Lowimpacthydropower WindPower Biomass SolarPower LandfillGas SolarPhotovoltaic SolarThermalResources

    ProjectRelatedRecyclingGoals

    TheProjectwillexpandtheCityscurvesiderecyclingprogramwhichcurrentlycovers1520%oftheCity.Oncefullyimplemented,allresidents

    willbeabletoextractrecyclablesfromtheirhouseholdwasteandbe

    allowedtocomingletheminadesignatedbin.TheadditionofaMaterial

    RecoveryFacilityandonsitesortingwillgreatlyincreasethematerial

    diversionrate.

    ThecurbsiderecyclingandautomatedpickupprogramwillsavetheCitymoneyandsignificantlyincreasingtherecyclingrate.

    EconomicBenefits

    EstimatedJobsperComponent

    The

    MSWE

    facility

    will

    operate

    24/7

    in

    3

    shifts.

    Full

    time

    staffing

    needs

    are

    as

    follows:

    CollectionProcess: N/A

    WasteSorting: 2436

    WasteProcessing: 1218

    RDFDevelopment: 1824

    GasificationOperation: 1824

    PowerPlantOperation: 1824

    TotalDirectJobs: 90126

    RegionalBenefits

    ParticipatingMunicipalitiesthatbringtheirMSWtotheRidgeRoadTransferStationwillenjoy

    thefollowingbenefits:

    Payaprocessingfeethatiscompetitiveandlowerthantheircurrenttippingfee ExperiencelowerMSWtransportationcostsincetheirMSWwillnotbetrucked miles

    awaytoalandfill

    13

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    14/25

    ReducedcarbonemissionscausedbytruckingMSWlongdistancestolandfills Lowercarbonfootprint

    RidgeRoadTransferStation

    TippingFloorView

    14

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    15/25

    ViewShowingOnSiteElectricSubstation

    RidgeRoadTransferStation(ExistingLayoutAerialView)

    15

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    16/25

    ConceptualLayout(everythingisenclosed)

    CommerciallyAvailableConversionTechnology

    Clevelandnarrowedtheselectionprocessforwastetoenergythermalconversiontechnologies

    basedonthefollowingcriteria: propertechnologyapplicationforitswastestream;proven

    reliability;abilitytoobtainanairpermit;andcommerciallyviabletechnology.

    (1)ApplicableTechnology

    SeveraltechnologiesthatcouldnotbedemonstratedasfeasibleoptionsfortheCity'sproject

    wereeliminatedfromconsideration. Forexample,althoughincinerationisrecognizedas

    technicallyfeasiblesamestillholdunfavorableviewsontheenvironmentalimpactsofthis

    technology.Anotherexampleincludesaerobicandanaerobicdigestion.Botharenotapplicable

    orwell suitedfortheMSWstreamreceivedbytheCity. CPPalsoeliminatedlandfillgas

    collectionandcombustionbecausetheCitydoesnotownoroperatethelandfillsthatreceive

    itsMSWandthelandfillsarenotlocatednearaCitygridconnection. Bothgasificationand

    pyrolysistechnologiesappearasapplicableoptions.Sincetheyappeartopresentfewer

    environmentalconcerns,havehigherpublicsupport,andwillworkwellwiththeCityswaste

    stream.

    16

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    17/25

    (2)ProvenReliability

    Clevelandisinterestedinwastetoenergytechnologythathasaproventrackrecordofsuccess

    onacommercialscale.Eligiblethermalconversiontechnologiesmustbeinoperationforat

    leastfiveyearsanddemonstrateatleastonesuccessfulcommercialoperation.Afurther

    requirement

    is

    that

    the

    technologies

    have

    at

    least

    a

    clear

    demonstration

    of

    a

    heterogeneous

    feedstock,suchasMSW,beingreliablyprocessedwiththetechnology.

    (3) AirPermiteligible

    Respondentsmustmeetthequalifyingcriteria,emissionlimitations,conditionsofoperation

    andrequirementsasstipulatedbytheairpermitapplicationsubmittedtotheOhioEPAon

    March11,2011,andanypermitthatOhioEPAissues. Theairpermitapplicationisbasedon

    emissionsusingKinseiSangyogasificationtechnology. However,thewinningapplicantmust

    performatleastaswellastheemissionsintheClevelandairpermitapplication.

    (4)CommerciallyViable

    Clevelandis

    interested

    in

    receiving

    information

    on

    waste

    management,

    materials

    recovery

    and

    wastetoenergytechnologiesthatarecommerciallyviable. Proposedtechnologiesmusthavea

    provencommercialtrackrecordandhistoryofsuccessfulinstallationsforaminimumoffive(5)

    years. Technologiesandprocessesmustbescalableandsuitablefortherangeofvolumeof

    MSWreceivedandprocessedbytheClevelandtransferstation.(SeeAttachment1Cityof

    ClevelandWasteCompositionStudy).

    ProjectDesignObjectives

    ProjectObjectives:

    Theprojectwillbebasedonaproformathatincludesrevenuestreamsfromthesaleofsorted,bundled,andpackagedrecycledgoods;electricity;wasteprocessingfees(to

    replacetippingfees);thesaleofrefusederivedfuelpellets;anduseoftheashby

    productthatremainsaftergasification.

    TheprojectwillbeacompleteMSWdisposaltechnologyfacility,includingequipmenttoreceive,sort,andprocessMSW,convertMSWintoarangeofmarketableproducts,such

    asfuels,electricity,chemicals,fertilizer,and/orcompost,andmarketablebyproducts

    suchasglass,metals,paper,ash,andslag.

    The

    project

    will

    include

    the

    production

    of

    an

    RDF

    pellet

    which

    will

    serve

    as

    the

    primary

    feedstockforthethermalconversiontechnologyselected.Excesspelletsmaybesoldto

    alocalcompanythatiscurrentlyusingcoalforsteamproduction.TheRDFpelletmust

    beenvironmentallyfriendly.

    OnlytheRDFpelletwillbefeedintotheconversiontechnologyofchoice. Theproposedprojectisdesignedtogasifytheequivalentof560tonsofMSWperday.

    Thewinningtechnologymustprocessthesameamountataminimum.

    17

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    18/25

    Theprojectistobemodularindesignwitheachcomponentbeingavailableforbidand/orsuppliedbydifferentvendors.

    TheprojectistointegratewiththeCitysRidgeRoadTransferStation. Theprojectistobecapableofdivertingatleast90%(byweight)ofthepostrecycled

    municipalsolidwastefromlandfillandproducefeedstockforthermalconversion.

    Theprojectmustbecapableofsustainedoperationatatippingfee/processingfeecompetitivewithlocalmarketconditions.

    Theprojectistobeastateoftheartfacilitymaximizingtheuseofsustainableconstructionandoperationpracticessuchasonsiterecycling/reuse,energy

    conservation,LEEDcertification,andothersimilarpractices.

    TradeSecrets

    TheCityissubjecttotheOhioPublicRecordsActfoundinOhioRevisedCodeSection149.43.

    Oneexceptiontothedefinitionofpublicrecordistradesecretinformation,asdefinedinOhio

    RevisedCode

    section

    1333.61.

    All

    information

    identified

    by

    the

    respondent

    as

    qualified

    for

    tradesecretstatusmustbeaccompaniedbyanexplanationofhowthatinformationqualifies

    asatradesecretunderthedefinitionfoundinOhiolaw. TheCitymaythenwithhold

    informationfromanythirdpartieswhorequestaccesstosuchinformation,absentacourt

    ordertoprovidesuchinformation. Bysubmittingitsinformation,respondentagreesto

    indemnifyanddefendanychallenge,claimorlawsuitagainsttheCitybaseduponorrelatedto

    theCitysrefusaltoprovideinformationtoathirdpartybecauseithasbeenidentifiedastrade

    secretprotectedbytherespondent. UponnotificationtorespondentthattheCityhasbeen

    namedinanyactiontoobtainaccesstorespondentsidentifiedtradesecrets;respondentshall

    enterits

    appearance

    in

    the

    action

    and

    assume

    the

    complete

    defense.

    Respondent

    shall

    hold

    harmlessandreleasetheCityfromanyandallliabilitywithrespecttoanycourtordered

    disclosureofinformationidentifiedbyrespondentastradesecretprotected.

    18

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    19/25

    RequestForInformationRespondentsmayrespondtoanyorallofthefollowingquestionsbutarenotrequiredto

    respondtoeachquestion.

    TheCityisrequestinginformationonthermalconversiontechnologieslimitedtogasification

    andpyrolysis

    as

    well

    as

    physical

    conversion

    technologies

    that

    convert

    MSW,

    after

    the

    removal

    ofrecyclablegoods,intofeedstockforthethermalconversionprocess.Theoutputofthe

    conversionprocessmustbetheproductionofsyntheticgasthatwillbeusedforelectric

    generationproduction.Theresidualsafterthethermalconversionprocessmustbeausable,

    marketablebyproduct.

    TheCitysubmittedanairpermitapplicationtotheOhioEPAbasedongasificationtechnology

    offeredbyKinseiSangyoofJapan.Kinseihasofferedgasificationtechnologythathasbeenin

    useformorethan30years. TheCitysairpermitapplicationisattachedasAttachment2.

    Q.1

    ThermalConversion

    Technology

    Discusswhetherthereareothergasificationorpyrolysistechnologiesthatcouldmeet

    theprojectsrequirementsandoperatewithintheemissionlimitsintheairpermit

    applicationor,uponissuance,theairpermit. TheOhioEPAand/orFederalguidelines

    mayfurtherclarifypermissibleprojectemissions.

    Q.2 RespondentProjectDevelopmentRecommendations

    Respondentsareaskedtodescribeacompleteprocess(i.e.,preprocessing,conversion,

    andpostprocessing/managementofproductsandresidue,refusederivedfuel

    productionandelectricenergygeneration)forafacilitythatisfullyintegratedwiththe

    Citys

    existing

    waste

    management

    infrastructure,

    the

    Ridge

    Road

    Transfer

    Station

    operations,andtheProjectObjectives.

    Q.3 DesignApproach

    Describe,innarrativeform,adesignapproachfortheproposedproject.Theapproach

    shoulddescribetheproposedtechnicalconceptfortheproject,includingadescription

    ofhowthefacilitywillworkfromreceiptofwastetoprocessingofwastethroughthe

    facilityandproductionofproducts.Thenarrativedescriptionshouldbeinsufficient

    detailtodemonstratethattheapproachwillsubstantiallycomplywiththeProject

    Objectives.

    19

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    20/25

    Q.4 GenericFacilityDesign

    a) Provideagenericfacilitysitelayout,equipmentgeneralarrangement,andschematicprocessflowdiagramfortheprojectattheRidgeRoadTransferStation.

    b) Provideageneraldescriptionofmajorsystemcomponentsforacommercialfacility,includinggascleanuptechnologiesandairpollutioncontroltechnologies,asapplicable.

    c) IdentifytheminimumnumberofacresrequiredfordevelopmentoftheprojectaswellasthepreferredacreageifdifferentfromtheacreageavailablefortheRidgeRoad

    TransferStation. TheRidgeRoadTransferStationsitsonan8acresite.

    Q.5 TippingFees

    Discussanytippingfeestabilizationorrampupconcerns. ProvideinformationtodemonstratetheProjectiscapableofsustainedoperationata

    marketcompetitivetipfee/processingfeeoverthetermofoperation.

    IfitisCityownedandoperated,discussthepossibilityoftheCitybeingabletoreduceitswasteprocessingfee(whichwillreplacethetippingfee)oncethefacilityisfully

    operational.

    Q.6 PublicorPrivateOwnership

    DiscusstradeoffsofprivateownershipversesCityownershipandoperationonanotforprofitselfsustaining,enterprisefundbasis.

    Q.7 ProjectFunding

    DiscusswhethertheProjectmaybebestfundedthroughprivateorpublicsources

    Debtfinancing:oCommerciallendingo

    Tax

    exempt

    bonds

    or

    taxable

    bonds

    oTaxincentivesforprivateinvestors Stateand/orFederalfinancingassistancesuchasgrantsorloanguarantees. Financingthroughtheprepaymentofelectricity. Identifyothercreativefinancingapproachesthathaveworkedonotherprojects.

    Q.10 TechnologyInformation

    Pleaseprovidethefollowinginformationfor(a)gasificationorpyrolysistechnology;(b)

    materialrecoveryfacilities;and(c)refusederivedfuelproductiontechnologyproviders:

    Providealistofoperatingfacilities,sizeofsuchfacilities,descriptionofwhethertheyarecommercialordemonstrationfacilities,dateplacedinoperation,andcurrentstatus.

    Ofthelist,identifythosefacilitiesthatareconsideredbytheRespondenttobe

    referencefacilities,inthattheymostcloselyrepresentthetechnologyrequestedforthe

    CitysProject.

    20

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    21/25

    Q.11 ReferenceTechnologiesForeachreferencefacilityandtechnologyidentifiedinresponsetoquestion10above,

    pleaseprovidethefollowingasapplicable:

    1. facilitynameandlocation;2. facilitydescription,includingprocessflowdiagram;3. facilityownerandoperator;4. developmentstatus(demonstrationorcommercialfacility);5. dates inoperation6. designcapacity(tpd);7. demonstratedoperatingcapacity(tpd);8. numberofunitsandunitcapacity(tpd);9. annualavailability;10.Output(designatetheunitsMW,Btu,tons/day,etc.);11.annualoperatinghours;12.typeandquantityofwasteprocessed;13.

    type

    of

    products

    energy,

    fuels,

    compost,

    etc.

    and

    marketability

    of

    same;

    14.environmentalperformance,permitcompliancehistory;15.usersatisfaction;16.otherrelevantinformationthatdemonstratesreadinessandreliabilityofthe

    technology;and

    17.photographsofthefacility/technologyinoperation.

    EvaluationofResponsesTheCitywillevaluateresponsesbasedonthefollowingcriteria:

    Clarityandcompletenessofsubmission GeneralreviewofRespondentexperience Experienceinworkingwithpublicagenciesintheanalysis,planningand/or

    implementationofinfrastructureprojects

    Ifaprovideroftechnology,respondentmustbetheownerofthetechnology,orotherwiseholdtheappropriatelicensesoragreementstomarket,develop,warranty,

    and(ifoperatingservicesareoffered)operateandmaintainthetechnologyfor

    longtermperiods(e.g.,10or20years)

    Thetechnologymustbereadyforimmediate,commercialdevelopment.TheRespondentshalldemonstratesuchreadinessbydocumentingwithitsRFIresponse

    thatthe

    technology

    has

    previously

    operated

    in

    either

    acommercial

    application

    and/or

    fordemonstrationpurposes,processingMSWcomparabletothecharacteristicsof

    MSWdescribedinAttachment1.

    Thetechnologymusthaveanexistingreferencefacility(demonstrationorcommercial)thatcanbevisitedtoobservethetechnologyinoperation.TheRFIresponsemust

    provideinformationonthatreferencefacility,includingitslocationandoperatingstatus.

    21

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    22/25

    Thetechnologymustprovideforbeneficialuseofwastethroughtheproductionoffuel

    and/orenergy,compost,andothermarketableproducts,asapplicable,evidencedbydefined

    marketsforallsuchproducts.

    Specificexperiencewithsolidwasteand/orrenewableenergyprojectfinancingsand/orprojectrelatedfinancialadvisoryengagements

    Familiaritywithandunderstandingofsolidwasteconversiontechnologiesandrenewableenergytechnologiesandprojectstructures(e.g.,inputandouttake

    contracts,securityandguaranteerequirements,riskallocation,etc.).

    ExperienceintheevaluationofState/Federalgrantand/orfinancialincentivesandsubsidyprogramsand/ortheinclusionofState/Federalgrantsand/orother

    subsidiesinfinancingstructures

    Forinvestmentbankersand/orlenders,whatpositions/roleshavetheyheldinpriortransactions

    22

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    23/25

    RequestForQualifications

    ThisRFQistoenabletheCitytobettergaugethemeritsoftheresponsessubmittedtotheRFI.

    Responsesmaybesubmittedbyawiderangeofinterestedparties(thermalconversion

    technologysuppliers,MRFdesignersandMRFequipmentsuppliers,recyclingequipment

    suppliers,system

    control

    suppliers,

    electric

    generation

    equipment

    suppliers,

    developers,

    projectfinancersandmore)andthosethatarefoundtobequalifiedwillbecontactedand

    prequalifiedastheCityproceedswithprojectdevelopment.TheCityreservestherighttoseek

    additionalinformation,beforequalifyingrespondentsandtherighttonotqualifyany

    respondent.

    (A) ForThermalconversiontechnologycompanies,pleaseprovidecompleteanswersto

    thefollowing:

    1: NameofFirm;Nameoftechnology;PrincipalContactPerson;Address;

    Telephone/Fax;andEmail.

    2: Pleaseprovidebackgroundinformationaboutyourcompany.Includecompany

    history,location(s),majoraccomplishmentsandbiosofyourkeypersonnel.

    3: Listanyreferencefacilitiesorprojects,includingforeach: a)Nameandlocation;

    b)Owner/Operator; c)Technology;d)Feedstock;e)CapitalandO&Mcost;f)Raw

    MSWandfeedstockthroughput; g)Types/quantitiesofproductsandbyproducts;

    h)Amountofresidualsenttolandfill; i)Historyofoperations;j)startupdate;k)

    timeinservice;andl)adiscussionofoperatingandmaintenancechallenges.

    4: Brieflydiscussthesignificantenvironmentalimpactsfromyourtechnologies,or

    issuesthat

    require

    permits

    of

    any

    type.

    Include,

    as

    appropriate,

    air

    emissions,

    wateremissions,solidwasteresidues,visualimpacts,andnuisance(odor,noise,

    traffic)impacts.

    5: Provideasummaryofthekeyadvantagesofferedbyyourtechnologyforthe

    Project.ComparethoseadvantageswiththekeychallengesyouforeseetheCity

    willencounter.

    6: ForthefacilityprovidedbytheRespondentfortheCity,theRespondentshould

    provide:

    6.1.

    Technical

    information,

    including

    narrative

    descriptions

    of

    the

    proposed

    facility.

    6.2. Adescriptionofthepreprocessingsystemrequiredtopreparethefeedstockfor

    processing.Includeequipmentusedtopresort,separate,shred,size,screen,

    dry,orotherwiseprocessthematerial.

    23

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    24/25

    6.2. Adescriptionoftheequipmentusedtofeedthethermalconversiontechnology,(e.g.screwfeedersorpresses.)

    6.3. Adescriptionofthegascleaningsystems,suchasscrubbers,baghouses,activatedcarbonfilters,etc.usedforcleaningthesyngasand/orwastegases.

    6.4. Whereapplicable,describethepowergenerationsystem,e.g.,reciprocatingengine,

    boiler,

    turbine,

    etc.,

    and

    associated

    environmental

    controls.

    6.5. Adescriptionoftheodorcontrolsystem/6.6. Heatandmaterialbalances.6.7. Listsofmajorpiecesofequipment,numberofunits,andcapacity6.8. Extentofprocessmodularizationandability/costtoincreasefuturecapacity.

    (B) Forcompaniesthatprovideanyofthefollowingorrelatedequipment,provide

    completeanswerstothequestionsbelow.

    WasteReceivingProcess WasteSeparationandRecoveryProcess RecyclablesHandlingProcess RecyclingEquipment WasteToEnergyFeedstockPreparationProcessIncludingBiomass(MSW) Drying,PelletizationandStorage SyngasFuelProcessing ResidualFlyAshProcessing AirEmissionsControlsandSystemControls

    Pleaseprovide

    detailed

    information

    regarding

    your

    companys

    products.

    Product

    informationshouldinclude,ifrelevant:

    1. FunctionsandOptions2. PerformanceCharacteristics3. Ratings4. MaterialsofConstruction5. InstallationConfigurationandFootprint6. PowerRequirements7. ControlScheme/ProprietarySoftware,Etc.8. Limitations,Exceptions9. MaintenanceRequirements10. AvailableWarranty11. ApproximateLeadTimeforDeliveryFromDayofOrder

    24

  • 8/3/2019 MSWE RFI 9-01-11 (v2) - 2

    25/25

    25

    (C) Forprofessionalservicescompanies,consultingfirms,developers,financersand

    relatedcompanies,pleaseprovidecompleteanswerstothefollowing:

    1. Provideabriefhistoryofyourcompany,emphasizingMunicipalSolidWasterelatedproject

    experience.

    2. Provide information that demonstrates that your company has furnishedequipment,systemsorservicestosimilarprojects.

    3. Number of similar projects under contract or pending award. Identify the dollarvalueandpercentcompleteforeachproject.