MS Project

Presented by Rolf Kuhnast, Pr Eng, B.Sc.Eng, MBL

Page 2: Ms project 2010 level 1&2

MS Project

✤ MS Project is a scheduling tool

✤ It becomes useful once the projects deliverables and activities have been defined, and the implementation strategy crafted by means of the Critical Path technique (Network diagram)

2

Page 3: Ms project 2010 level 1&2

3

A Word about Tools

✤ Many people assume that Project Management is about Management software

✤ That’s like saying that residential construction is all about hammers!

✤ Such tools will often make your work simpler and handle complex calculations with ease.

✤ Without a solid understanding of PM concepts, the tools often provide an illusion of project control that does not exist

✤ Learn the concepts, then the tools!

✤ Buying Accounting software does not make you an Accountant !

Page 4: Ms project 2010 level 1&2

4To use a Tool

✤ One has to understand the context in which it is applicable

✤ One has to understand its limitations

✤ MS Project can improve productivity in Scheduling and monitoring progress of a project by, maybe, 5-15%

Page 5: Ms project 2010 level 1&2

5

What does it do?

It helps to :

✤ Define Tasks /activities

✤ Assign resources to activities

✤ Allows the management of Resources and Activities

✤ Allows comparison of planned with actual progress

✤ Produce reports in various formats

Page 6: Ms project 2010 level 1&2

6

Lets recap: Some Definitions

✤ Tasks ?✤ Scope ?✤ Resources ?

Page 7: Ms project 2010 level 1&2

7

The Project Management Processes

Initiating

PlanningExecuting

Controlling

Terminating

Page 8: Ms project 2010 level 1&2

Lesson 1: Creating a new Project Plan, Setting the Scene

✤ The Default Screen✤ The Options Screen✤ Project attributes✤ The Calendar Screen✤ Views and the Organiser

8

Page 9: Ms project 2010 level 1&2

9

MS Project 2010 Default view: Gantt Chart

Gantt Pane

Page 10: Ms project 2010 level 1&2

1.1 Create a new Project File

✤ To create a new blank project in Project, click the File tab. Click New, and then click Blank Project.

✤ To create a new project from a template, click the File tab. Select a template from Templates (local), Office Online Templates (Web), or Project Server Templates.

10

Page 11: Ms project 2010 level 1&2

1.2 Set the Project start Date

✤ Click the File tab, and then click Info.

✤ On the right side of the Information page, select a date in the Start Date box.

11

Page 12: Ms project 2010 level 1&2

12

Project Information Box

Page 13: Ms project 2010 level 1&2

1.3 Define the Project Calendar

✤ Click the Project tab.

✤ In the Properties group, click Change Working Time.

✤ Identify working and non-working days and times for your project.

13

Page 14: Ms project 2010 level 1&2

14The Project Calendar

Page 15: Ms project 2010 level 1&2

The Organiser 15

Page 16: Ms project 2010 level 1&2

Lesson 2:Working with Tasks

✤ Planning tasks✤ Scheduling tasks✤ Entering tasks✤ Outlining tasks✤ Summary and Recurring

tasks✤ Entering durations✤ Linking tasks✤ Applying and removing

constraints 16

Page 17: Ms project 2010 level 1&2

2.1 Plan the Tasks

✤ In the planning stage, you devise a workable scheme to accomplish the project’s goals.

✤ To do this, you identify the project’s milestones, deliverables, and tasks.

✤ This plan can be your work breakdown structure (WBS).

✤ You develop and refine the schedule, and identify the resources required to implement the project.

17

Page 18: Ms project 2010 level 1&2

2.2.1Decide how you want to schedule tasks

✤ In Project 2010, you can now schedule tasks manually in addition to having Project automatically schedule them. Select the scheduling method after you enter a new task by clicking one of the following in the Task Mode column:

Manually scheduled With this method, Project won't move a task after it is created, even when resources are assigned to it, or tasks get linked to it, or if the Project calendar changes. New tasks are manually scheduled by default.

✤ Note New tasks are manually scheduled by default. To make new tasks automatically scheduled by default, click the Tasks tab. In the Schedule group, point to Task Mode, and in the list, click Auto Schedule.

18

Page 19: Ms project 2010 level 1&2

2.2.2 Decide how you want to schedule tasks

✤ Auto scheduled Use this method when you want Project to schedule the task based on dependencies, constraints, calendars, and other factors.

19

Page 20: Ms project 2010 level 1&2

20

Types of Tasks

✤ Summary tasks, contain subtasks and their properties

✤ Subtasks, are smaller tasks that are part of the summary task

✤ Recurring tasks, are tasks that occur at regular intervals

✤ Milestones, are tasks with zero durations and are like interim goals in the project

Page 21: Ms project 2010 level 1&2

2.3 Entering Tasks

✤ Click the View tab. In the Task Views group, click Gantt Chart.

✤ In the Task Name field, enter tasks.

✤ Tasks can also include summary tasks, milestones, and WBS items.

21

Page 22: Ms project 2010 level 1&2

2.4 Outline Tasks

✤ Createyourtaskhierarchy,includingtasksandmilestonesundersummarytasks,whichcanrepresentphasesorotherworkdivisions.ClicktheViewtab.IntheTaskViewsgroup,clickGan,Chart.Selectatask(orseveraltasks),andthenintheTasksgroup,clicktheIndentorOutdentbu>on.

✤ TipIfyoucreatedasummarytaskwithadura@on,startdate,orfinishdate,thenthetasksthatfallunderthesummarytaskwillnotberolleduptothissummarytask.They'llbeindependentofit.Thisisknownastop-downscheduling.

22

Page 23: Ms project 2010 level 1&2

23

Advantages of Outlining Tasks

✤ Creates multiple levels of subtasks that roll up into a summary task

✤ Collapse and expand summary tasks when necessary

✤ Apply a Work Breakdown Structure

✤ Move ,copy or delete entire groups of tasks (Scope Change)

Page 24: Ms project 2010 level 1&2

24

2.5 Summary tasks

✤ Summary tasks contain the broad concepts , phases or deliverables of projects.

✤ They are represented in the Gantt view by black bars with black triangular end points

✤ Schedule and cost information from tasks are accumulated at summary task level

✤ NOTE :Never link summary tasks!

Page 25: Ms project 2010 level 1&2

252.6 Recurring tasks

✤ To enter recurring tasks, such as progress meetings, in the “Task” tab, drop down the list under the Task button. Select “Recurring Task”

✤ Enter the required information

Page 26: Ms project 2010 level 1&2

26Recurring Task Screen

Page 27: Ms project 2010 level 1&2

2.7 Enter Durations

[email protected],youcanenterdura@onintwodifferentways,dependingontheschedulingmethodthatisbeingusedforthetask.

• ManuallyscheduledtaskEnterdura@onaseitheranumberorastext.Forexample,youcanenter"Some@meaOerJune,"or"TwodaysaOership."

[email protected],type4dtoindicate4days.Tospecifyamilestonewithoutdura@on,type0d.Toindicatethatadura@onisanes@mate,addaques@onmark;forexample,type6d?

• NoteWhenusingautoma@cscheduling,avoidenteringstartandfinishdatesfortasks.Instead,enterdura@onandletProject2010automa@callysetthesedates,whichmightchangeanywayasresourcesareassignedtotasks.

27

Page 28: Ms project 2010 level 1&2

28

Task Durations

Displays as:m, min, minute

h, hr, hour

d, dy, day

w, wk, week

emin, ehr, eday, ewk

Duration

✤ Minutes

✤ Hours

✤ Days

✤ Weeks

✤ Elapsed Duration

Page 29: Ms project 2010 level 1&2

Check your knowledge

Exercise 1.1

29

Page 30: Ms project 2010 level 1&2

30

2.8 Linking Tasks

✤ Tasks are usually scheduled to start as soon as possible

✤ The duration of tasks can be seen in the form of grey bars in the Gantt Chart

✤ Tasks that need to be completed before a task , are called predecessor tasks.

Page 31: Ms project 2010 level 1&2

31

Task Links

✤ Task dependencies should be determined by means of a network diagram completed manually together with the project team

✤ Once the task dependencies have been logically determined, taking strategic limitations and constraints into account, the tasks may be linked accordingly in MS Project Link tasks to show relationships

Page 32: Ms project 2010 level 1&2

Task Relationships32

Page 33: Ms project 2010 level 1&2

Task Relationships

Finish-Start

Start-start Finish-finish

Start-finish

Lead Lead

lag

33

Page 34: Ms project 2010 level 1&2

Float

Activity A

Activity B

Activity C

Activity D

ES EF=LF

LS

34

Page 35: Ms project 2010 level 1&2

Lead

Wideman Comparative Glossary of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March 2002.

Activity A

Activity B

35

In a network diagram, the minimum necessary lapse of time between the start of one activity and the start of an overlapping activity

Page 36: Ms project 2010 level 1&2

Lag

Wideman Comparative Glossary of Common Project Management Terms v3.1 is copyright by R. Max Wideman, March 2002.

Activity A Activity B

36

The amount of time after one task is started or finished before the next task can be started or finished.

Page 37: Ms project 2010 level 1&2

✤ Click the View tab. In the Task Views group, click Gantt Chart. Select the tasks that you want to link, and then click the Link Tasks button in the Tasks group. which is found under the Tasks tab. To change the default finish-to-start dependency type, double-click the line between the tasks that you want to change, and then select a task link from the Type list.

37

1. Link tasks to show relationships

Page 38: Ms project 2010 level 1&2

38

Task Information box

Page 39: Ms project 2010 level 1&2

39

To link Tasks in F-S Dependency

✤ Select tasks to be linked

Hold "Ctrl" while click tasks in order

✤ Click Ctrl+F2 , or click on the link icon in the schedule group

✤ NOTE: Summary tasks should never be linked; they should be left to float with the durations of their subtasks

✤ To unlink tasks , select the tasks and click the "Unlink Task" icon in the Schedule group

Ø Never remove a link by deleting a cell in the predecessor column, as this will delete the entire task!

Page 40: Ms project 2010 level 1&2

40

Delayed and Overlapping Links

✤ Tasks may be dependent on other factors causing delay time or overlapping, necessitating a lag or a lead time to be incorporated in a link

✤ Lag or lead times can be entered as units of time, or as a percentage of the duration of a predecessor. (See next)

Page 41: Ms project 2010 level 1&2

41

To enter Lag or Lead times

✤ Double-click a task to open the Task Information Dialog Box

✤ Click the Predecessors tab

✤ Select the lag/lead field

✤ Enter a number or a percentage in the cell

A negative number signifies a Lead time

A positive number is a Lag time

✤ click"OK"

Page 42: Ms project 2010 level 1&2

42Entering Leads/Lags

Page 43: Ms project 2010 level 1&2

Check your knowledge

Exercise 1.2

43

Page 44: Ms project 2010 level 1&2

442.9 Applying Constraints

✤ Intermediate deadlines need to be specified

✤ Certain tasks may need to be completed by a certain date

✤ But Note!: Constraints on a task can account for scheduling problems !

Page 45: Ms project 2010 level 1&2

45

There are 8 Types of Constraints

✤ Flexible constraints allow Project to calculate the schedule and make appropriate adjustments based on the constraint applied

✤ Inflexible constraints can cause conflict between successive and preceding tasks , and may require manual intervention to remove the constraint

Page 46: Ms project 2010 level 1&2

46Applying Constraints

Page 47: Ms project 2010 level 1&2

47To apply a Constraint

✤ Open the task information dialog box

✤ Click the “Advanced” tab and open the Constraint Type list by clicking on the Drop-down arrow

✤ Select the appropriate date for the constraint and click"OK"

Page 48: Ms project 2010 level 1&2

48

To remove a Constraint and apply ASAP/ALAP Constraint

✤ Select the tasks by holding Ctrl and clicking the tasks in order

✤ Click Task information Button and "Multiple Tasks" dialog opens

✤ Chose ASAP if the project has been scheduled from the start date, and ALAP if it has been scheduled from the finish date

✤ Click "OK"

Page 49: Ms project 2010 level 1&2

49Removing a Constraint

Page 50: Ms project 2010 level 1&2

Check your knowledge

Exercise 1.3

50

Page 51: Ms project 2010 level 1&2

Lesson 3: Working with Resources

✤ Assigning resources to tasks

✤ Task types & task tradeoffs

✤ Adding resources to the project

✤ Assigning resources to tasks

✤ Defining and controlling costs

51

Page 52: Ms project 2010 level 1&2

52

Questions to be answered

✤ What kind of resources are needed

✤ How many of each resource

✤ Where do these resources come from?

✤ How do you determine the cost of the project?

Page 53: Ms project 2010 level 1&2

3.1 Assigning Resources

✤ Assignments are the associations between specific tasks and the resources needed to complete them. You can assign more than one resource to a task. In addition to work resources (people), you can assign material resources (such as cement) and cost resources (such as travel) to tasks.

53

Page 54: Ms project 2010 level 1&2

3.2 Know your Task Type

✤ As soon as you assign resources to automatically scheduled tasks, Project 2010 determines how to schedule the task based on the task type. (Manually scheduled tasks don't use task types.) Durations might change as you assign resources to tasks.

54

Page 55: Ms project 2010 level 1&2

55

The Work, Duration and Units trade-off✤ Project takes the tasks duration and multiplies it by the specific

percentage or number of units to arrive at the hours of work that will be done

✤ Work is the amount of time or effort that a resource expends on a task

✤ Duration is the amount of clock time between the beginning and end of a task

✤ Work = Duration * Units (Number * Availability)

NOTE: Given the choice between duration, work and units, project will change duration. If Duration is fixed, then it will change work before it changes units

Page 56: Ms project 2010 level 1&2

How Task Types Work

In a... If you revise work...

If you revise duration...

If you revise units...

Fixed unit task

Duration changes

Work changes

Duration changes

Fixed work task

Duration changes Units change Duration

changes

Fixed duration task Units change Work

changesWork

changes

56

Page 57: Ms project 2010 level 1&2

How to change task types

✤ To set a default task type for the entire project, click the File tab, and then click Options. In the Default task type box, select Fixed Units (the default), Fixed Duration, or Fixed Work.

✤ To change the task type for an individual task, click the Task tab, and then in the Properties group, click the Task Information button . Click the Advanced tab, and then in the Task type box, click the task type that you want to create.

57

Page 58: Ms project 2010 level 1&2

3.3 Add Resources to your Project✤ Click the View tab. In the Resource Views group,

click Resource Sheet . In the Resource Name field, type the names of the resources you will use for this project.

✤ If you are using Project Professional, you can add resources from the enterprise resource pool. Click the Resources tab. In the Insert group, click Add Resources, and then click Build Team from Enterprise. This feature requires Project Professional 2010 that is connected to Project Server 2010.

58

Page 59: Ms project 2010 level 1&2

59

Entering Resource information in the Resource Sheet✤ Select a cell in the “name” column and type a resource

name. Press Enter.

✤ Enter the information, "work" for people, "material" for material, and “cost” for cost items

✤ Repeat the above until all the resources have been entered

✤ Enter all other relevant information, e.g. Hourly rate, Overtime rate etc as required

✤ Click 'OK.

Page 60: Ms project 2010 level 1&2

60

Resource Information Dialog box

✤ Double-clicking on a resource name in the Resource Sheet will display the Resource information Dialog Box

Page 61: Ms project 2010 level 1&2

3.4 Assign Resources to Tasks

✤ In the Gantt Chart view, select a task to which you want to assign a resource. On the Resources tab, in the Assignments group, click Assign Resources . Click the resource names, and then click Assign.

✤ Tip Use the new Team Planner to drag and drop tasks around easily from one person to another within your team, or back and forth in the schedule. Click the View tab. In the Resources group, click Team Planner. You can even create new tasks on the Team Planner, or remove tasks—by just dragging or dropping.

61

Page 62: Ms project 2010 level 1&2

Enter the Work Hours that Resources spend on Tasks

✤ When scheduling tasks, project managers sometimes prefer to enter the amount of work (or the amount of labor) needed to complete a task, rather than the duration for the task. Entering work reflects real-world scheduling.

✤ To enter work hours for resources assigned to tasks, add the Work column to the Gantt Chart view. Right click a column, and then click Insert Column. Type "Work", to select the Work column.

62

Page 63: Ms project 2010 level 1&2

Identify factors affecting task schedules✤ You can use Project 2010 to help you understand

how changes to one task can affect the rest of the project. Click the Task tab, and then in the Tasks group, click Inspect Task. A pane opens on the left showing the factors that affect the scheduling of the selected task.

✤ Tip You can also see task scheduling information (such as scheduling mode, duration, and start and stop times) quickly by hovering the mouse over the task's Gantt bar.

63

Page 64: Ms project 2010 level 1&2

64

Assigning a Base Calendar other than the Project Calendar to the Resource

✤ In the Resource Information dialog box click “ Change Working Time” to change the resource calendar

Page 65: Ms project 2010 level 1&2

Check your knowledge

Exercise 2.1 & 2.2

65

Page 66: Ms project 2010 level 1&2

66

3.5 Defining and Controlling Costs

✤ “Project” multiplies the number of hours a resource works and the hourly cost rate to give you the resource cost rate

✤ For multiple resources the individual resource costs are added

✤ The number of units used reflect material costs

✤ The “Standard Rate” or the “Rate of Pay” per time unit for regular working hours , or the cost per unit of a material resource and the Overtime Rate defined for overtime hours are the two rate values that have to be filled into the Resource Sheet view

✤ Fixed costs and the resource cost add up to the total cost

Page 67: Ms project 2010 level 1&2

67Accrual Methods

✤ Accrual methods describe the way in which Project calculates costs

✤ If payment for a resource has to be made before work starts , then the accrual method is "Start"

✤ Likewise, if payment is made after the work has been completed, then the accrual method is "End"

✤ For partially completed Tasks, estimated costs are prorated

✤ Accrual methods do not affect the final cost of the project

Page 68: Ms project 2010 level 1&2

68

Entering Cost for a Resource

✤ Open the resource information dialog box and click "cost' tab (In the resource sheet, double-click the resource name)

✤ Enter the effective date for the cost in the drop-down calendar✤ Enter the standard rate. The default is R/h, but this can be changed to R/y, R/m

as necessary✤ Materials use the Materials label assigned to the resource✤ Enter the overtime rate✤ Enter any additional 'per use cost' for a resource✤ If resources have different accrual methods, select from the Cost Accrual drop-

down list ✤ Project supports fixed and variable costs.✤ To enter a fixed cost, in the Gantt chart view, chose View>Table>Cost. Open

cost table. Select Fixed Cost for the task . Enter the amount

Page 69: Ms project 2010 level 1&2

69Entering Resource Costs

Page 70: Ms project 2010 level 1&2

70

Entering Cost Information

✤ On the Cost tab of the Resource Information Dialog Box, you can record up to 5 different rates for a selected resource that is assigned to 5 different tasks, by selecting one of 5 tabs.

✤ You can also enter separate rates such as Standard Rates, Overtime Rates and Per-Use rates

Page 71: Ms project 2010 level 1&2

Lesson 4: Fine-tuning the Plan

✤ Finding and resolving over-allocations

✤ Project contours✤ Working with filters✤ Viewing and grouping

information✤ Viewing costs✤ Reducing durations✤ Selecting views✤ Formatting text✤ Displaying statistics✤ Set the Project baseline

71

Page 72: Ms project 2010 level 1&2

72

4.1 Over-allocated Resources

✤ A Resource is over-allocated when the total of its time-phased work exceeds the resources maximum units

✤ In every Resource View, over-allocated resources are formatted in red

✤ In the Resource Sheet, Project displays a caution icon in the Indicator column of the over-allocated resource.

✤ Hover over this icon to view a tip to correct the over-allocation

Page 73: Ms project 2010 level 1&2

73Resolving over-allocations✤ In addition to levelling, you can eliminate some over-

allocations by using other methods. To resolve over-allocations:

✤ Reduce a task's duration.

✤ Delay a task.

✤ Split a task.

✤ Adjust the resources assigned to a task.

✤ Assign more resources to a task.

✤ Replace an over-allocated resource with an under-allocated one or remove a resource.

✤ Adjust or contour the amount of work assigned to a resource.

Page 74: Ms project 2010 level 1&2

74

Locating Over-allocations

✤ Choose View>Other views>More views>Resource Graph

✤ In the View tab, chose Split View, select Details ✤ Open Resource Graph ✤ Open Resource Form ✤ Right-Clicking on the graph will open the shortcut menu✤ Select Over-allocation ✤ Scroll through the resources with the horizontal scroll

bar in the Resource Graph to identify the times of over-allocation

Page 75: Ms project 2010 level 1&2

75Locating Over-allocations

Page 76: Ms project 2010 level 1&2

76

Applying Resource Levelling✤ Select any task

✤ In the Resource Tab, click on Leveling Options

✤ In the Resource leveling dialog box that opens, Select From/To option and use the drop-down calendar to select beginning and ending dates between which Project must search for over-allocations

✤ After it identifies over-allocations , it delays tasks based on the leveling order selected

✤ Tasks with constraints, and tasks which have begun, are left alone

Page 77: Ms project 2010 level 1&2

77

Resource Levelling dialogue box

Page 78: Ms project 2010 level 1&2

78

Three Levelling Orders

✤ I.D.: Higher ID tasks are delayed. Enter tasks in order of importance!

✤ Standard: This is the default levelling order

✤ Task priority can be set to any value between 0 and 1000 on the General Tab of the Task Information Form

Page 79: Ms project 2010 level 1&2

79

Standard Levelling Order

✤ Tasks without successors are delayed first

✤ Tasks that are not on the critical path are delayed first

✤ Tasks with later start dates are allowed to begin later

Page 80: Ms project 2010 level 1&2

80

Level Resources Manually

✤ In the View Tab, select More Views and select Resource Allocation

✤ Click in the Gantt Chart in the lower pane✤ Chose View>Table>More Tables, and the More Tables dialog box

opens✤ Select "Delay"✤ Click "Apply"✤ In the Resource Usage Table in the upper pane , right click on

"work" Column✤ Select “Insert Column”✤ Select “Assignment Delay” in the column definition dialog box✤ Click "O.K.“✤ You can now enter the required delays into this column

Page 81: Ms project 2010 level 1&2

81

Levelling Resources Manually

Page 82: Ms project 2010 level 1&2

82 Delaying a Task

Page 83: Ms project 2010 level 1&2

83

To Delay an Assignment

✤ Select the assignment that you want to delay in the Resource Usage Table

✤ Enter the duration of the delay in the Assignment Delay Field

Page 84: Ms project 2010 level 1&2

84

4.2 Contours

✤ A contour is the shape of the distribution of work within an assignment

✤ To Change the work contour for an assignment,in either the task Usage , or Resource Usage Views, double-click an assignment to open the Assignment Information Dialog box and chose a contour from the Work Contour drop-down list

Page 85: Ms project 2010 level 1&2

85

MS Project Contours

✤ Flat: The default contour with an even distribution of work

✤ Back-loaded: Peak activity happens at the end of the project

✤ Front-loaded: Peak activity is at the beginning of the project

✤ Double Peak: A Project has two major periods of peak activity

✤ Early Peak: The same as front-loaded, but with a ramp up to peak activity

✤ Late Peak: a back-loaded contour with a ramp

✤ Bell: A single peak in the middle of the project

✤ Turtle: A bell with a ramp up and a ramp down

Page 86: Ms project 2010 level 1&2

86

To change the Work Contour

✤ In either Task Usage View, or Resource Usage view, double click an assignment to open the Assignment Information Dialog box.

✤ Chose a contour from the Work Contour drop-down list

Page 87: Ms project 2010 level 1&2

87

Changing Work Contour

Page 88: Ms project 2010 level 1&2

Check your knowledge

Exercise 3.1& 3.2

88

Page 89: Ms project 2010 level 1&2

89

4.3 Using Filters

✤ Filtering allows you to Impose certain conditions on which you want to display your information at any time

✤ You can chose to hide information that you don't want to view, or highlight information that is important to you

Page 90: Ms project 2010 level 1&2

90

To Apply an Auto-filter

✤ In the View tab, drop down the list next to the Filter icon✤ Select the required heading✤ When the table is filtered, the column headings and filter drop-down arrow

turns blue✤ To include additional filter conditions use the drop-down list to select other

headings ✤ To turn off Auto Filter, select Display Auto Filter again in the Filter drop-

down list✤ You can use pre-defined filters in Project to filter tasks like milestones,

incomplete tasks , critical tasks and resource-specific tasks etc.

Page 91: Ms project 2010 level 1&2

91Custom Filters

✤ Select Auto-filter from View> Filter>Display Auto-filter.

✤ In the “Cost” column click on the dropdown list.

✤ Select “Custom” and enter the desired range

Page 92: Ms project 2010 level 1&2

92

4.4 Sorting and Grouping Information

✤ Data can be sorted by ascending order, cost, priority etc. Standard sorts are available for Name, I.D. and costs.

✤ In the View tab, drop down the list next to the Group By icon.

✤ Chose the method of grouping required

Page 93: Ms project 2010 level 1&2

934.5 Viewing Costs

✤ To view costs, display any List View

✤ Chose View>Table>Summary.

✤ Columns for Duration, Start, Finish, Cost, Work and % completion are displayed

Page 94: Ms project 2010 level 1&2

94

Viewing Costs

Page 95: Ms project 2010 level 1&2

95

4.6 Reducing Duration

✤ Since the project's duration is determined by the tasks on the critical path, reducing the critical path will reduce the duration.

✤ In the Views tab, drop down the Filter list. Select “Critical” from the list of filters. Drop down the Highlight list, and select Critical

✤ All critical tasks will appear in a different colour from the other tasks

Page 96: Ms project 2010 level 1&2

96

To Reduce the Duration of the Critical Path

✤ Overlap tasks (Fast Track)

✤ Schedule Overtime

✤ Break large tasks into smaller ones

✤ Identify and correct errors

✤ Reduce the scope of work

Page 97: Ms project 2010 level 1&2

Check your knowledge

Exercise 3.3

97

Page 98: Ms project 2010 level 1&2

4.7 Select a view✤ Project 2010 has some old views and some new views to help

you see project information and report it to others on your team or organization. Click the View tab. In either the Task Views group or the Resource Views group, select the view you want to use. There are many views, but the most useful ones include:

✤ Team planner view Move tasks easily from one person to another within your team, or back and forth in the schedule. You can create new tasks in the team planner or remove tasks—just by dragging them.

✤ Timeline view Place tasks, subtasks, or milestones onto a single timeline at the top of most views. You can copy the timeline into Word, PowerPoint, Excel, or Outlook. You can instantly create attractive project reports this way. Click the Timeline check box to see how the timeline works.

✤ Gantt Chart view View project tasks in a combination view, with columns on one side and bars along a timeline on the other side.

✤ Calendar view See project information in a familiar monthly or weekly calendar format that can be printed.

98

Page 99: Ms project 2010 level 1&2

Add a column

✤ Adding columns to a view is one of the easiest ways to create the view that meets your needs.

✤ Click the View tab. In either the Task Views group or the Resource Views group, select the view you want to use. Right click on a column header to the left of where you want to insert a new column, and then click Insert column. Type the name of the column you want to insert.

✤ Tip You can also insert a custom column as easily as a built-in column. For example, if you want a column called "Deliveries", type that name when you insert a new column. If you want the new column to contain only numbers (to specify the number of deliveries), then right click the column down-arrow, point to Data Type, and select the type of data that the column should contain.

99

Page 100: Ms project 2010 level 1&2

Customising Views

✤ Customizing views beyond adding columns has been made considerably easier in Project 2010. Whether it’s the Team Planner, Timeline, or classic Gantt Chart, all formatting options are available on the Format tab.

✤ Select the view you want to customize, and then on the Format tab click the type of view element you want to change, such as the bar styles on the Gantt Chart, callout text on the Timeline, or the gridlines and timescales of any views.

✤ Tip If you want to filter, sort, or group tasks prior to printing, Click the View tab, and then in the Data group, click the Sort, Filter, or

100

Page 101: Ms project 2010 level 1&2

Check your knowledge

Exercise 4.1

101

Page 102: Ms project 2010 level 1&2

102

4.8 Formatting Text

✤ Select the cell to be formatted✤ Chose Format, Text styles to display the Text

Styles dialog box✤ Assign a font to selected text✤ Select a new font type, and change the style,

colour and size required✤ click O.K.

Page 103: Ms project 2010 level 1&2

103

Formatting Gridlines

✤ Chose Format>Grid-lines to open the grid-line dialog box✤ Select the required line style from the list✤ In the Normal section of the dialog box, select the type

and pattern for the gridline✤ To delete an existing grid-line, select it from the list and

check the blank area in the Type drop-down list✤ Select an Interval, line type and colour✤ In the "At Interval section, chose “None” to display all

lines of the selected type, or chose an interval to display line only at that interval

Page 104: Ms project 2010 level 1&2

104

Changing Timescales

✤ The default timescale in the Gantt Chart View are weeks and days

✤ In the View tab, select the drop-down list under the Zoom icon will allow you to select the set of time units of your choice

✤ Alternately, right click with the cursor on the timescales in Gantt view and select the Timescales icon. Chose the required options

Page 105: Ms project 2010 level 1&2

105Changing Timescales

Page 106: Ms project 2010 level 1&2

106

4.9 Displaying a Summary of all Statistics✤ In the Project tab click on the Project information

icon>Statistics

✤ At the top of the box you will see the current start and finish dates

✤ If you saved a project Baseline when you first save your complete Project plan, and if you updated this baseline plan with actual progress and cost data, the statistics box will give you the variances between the baseline and the actual results

Page 107: Ms project 2010 level 1&2

107Displaying Statistics

Page 108: Ms project 2010 level 1&2

108To add a Hyperlink

✤ Open a view✤ Select a task, resource or assignment that you want to add a

Hyperlink to✤ Right Click on the task. In the drop-down menu that appears,

select Hyperlink ✤ In the Insert Hyperlink menu that appears, select the document

required, or type in a website URL, as required✤ Click O.K.

Page 109: Ms project 2010 level 1&2

Check your knowledge

Exercise 4.3

109

Page 110: Ms project 2010 level 1&2

110

Dividing a Project into Smaller Pieces✤ Open a large project that is to be sub-divided✤ Create a view that puts all the tasks that are to be moved into

consecutive order, or move the tasks so that they are in consecutive order

✤ Select these tasks and click the Cut Button, on the clipboard group✤ Select the File tab, and click the "New" button and create a new

project✤ Click the first cell of the Gantt Chart and press the Paste button✤ Save the new Project under an appropriate name✤ Repeat the above steps for all the Task Groups that are to be

moved

Page 111: Ms project 2010 level 1&2

111

Creating links between Tasks that cross Projects

✤ Open both projects and in the View tab, select the Arrange All icon to see both project in the same window

✤ Double-click the task that is to be the successor. This will open the Task information dialog box

✤ Click the predecessors' tab to establish the task as the predecessor

✤ Select the I.D. field and type the project name and ID# of the predecessor task, using the format: Project Name/Task ID #.

✤ Press Enter; Project adds External project to the Type and Lag fields.

✤ Click O.K.

Page 112: Ms project 2010 level 1&2

4.10 Set the Project Baseline

✤ Create a baseline or an interim plan so that later you can compare your up-to-date schedule to your baseline.

✤ Saving a baseline plan enables you to identify and solve discrepancies and plan more accurately for similar future projects.

112

Page 113: Ms project 2010 level 1&2

Save the Baseline Plan, and viewing the baseline data✤ After your project plan is solidly in place for the finish date, budget,

and scope, you can submit the plan for approval. Once it has been approved, save the baseline plan. Click the Project tab, in the Schedule group, click Set Baseline.

✤ Click the View tab, and then click the Gantt Chart button. Click the Format tab, and then in the Bar Styles group, click Baseline. The baseline information is shown as the lower of the two Gantt bars for each task.

✤ Click the View tab. In the Task Views group, click Gantt Chart (or any view that includes columns). Point to Tables, and then select Variance. This table includes fields for baseline and variance start and finish.

113

Page 114: Ms project 2010 level 1&2

Lesson 5: Tracking and updating the Project

✤ Managing changes✤ Updating progress✤ Tracking actual hours

and costs✤ Tracking actual dates

and durations

114

Page 115: Ms project 2010 level 1&2

5.1 Managing Changes

✤ Managing changes involves modifying durations, dates, dependencies, resource assignments, or tasks based on requested changes or new information.

✤ Keeping the current fields up to date and compare them to the baseline.

115

Page 116: Ms project 2010 level 1&2

5.2 Updating Progress

✤ Updating the progress of your project is the only way to make sure it stays on track as work is performed. The focus at this point is on managing changes, updating the schedule, tracking progress, and communicating project information.

✤ Note Project 2010 tracks three sets of dates: current, baseline, and actual. When you first set the baseline, current = baseline. When a task is 100% complete, current = actual. Baseline, current, and actual values exist for the start date, finish date, duration, cost, and work.

116

Page 117: Ms project 2010 level 1&2

117

Using the Update Task dialog box

✤ In the Task tab, click on the drop-down arrow of the Mark on Track button. Select the Update Task icon

✤ Enter the required information

Page 118: Ms project 2010 level 1&2

Track actual hours and costs

✤ If you want to enter actual and remaining work hours or costs, use the tracking table. Click the View tab. In the Data group, point Table, and then click Tracking. Enter progress data in the Act. Work or Act. Cost fields for the task.

✤ You can also use the tracking table to enter percent complete, actual start and finish dates, and actual and remaining duration.

118

Page 119: Ms project 2010 level 1&2

Track actual dates and durations✤ It’s best to decide on a single method for

tracking progress. You can enter percentage complete, actual start and finish dates, actual and remaining durations, or actual and remaining work.

✤ Click the Task tab, and select the task for which you want to enter actual progress. In the Schedule group, select the amount of progress done on the task .

119

Page 120: Ms project 2010 level 1&2

Check your knowledge

Exercise 5.1

120

Page 121: Ms project 2010 level 1&2

Lesson 6: Sharing and Publishing

✤ Workgroups✤ View or report information✤ Generate a report✤ Print or view a report✤ Create a new report✤ Create a final report✤ Save the project as a

template✤ Close the project

121

Page 122: Ms project 2010 level 1&2

Check your knowledge

Exercise 5.2

122

Page 123: Ms project 2010 level 1&2

123

6.1 Workgroups

✤ A Workgroup comprises people who are directly involved in the project- the manager and team in a project as well as external contractors and customers

✤ Project information can be communicated electronically by means of e-mail, Intranet or Internet.

✤ Team members do not require to have Project installed on their systems. Only the workgroup manager must have it installed

Page 124: Ms project 2010 level 1&2

124

To save as a different file and communicate with workgroups

✤ In the File tab, select Save as

✤ In the Save as window, select the file type in the save as type drop-down list

✤ Select the file type, and click Save

✤ Alternatively select Save and Send in the File tab

✤ Chose the option required , as above

Page 125: Ms project 2010 level 1&2

6.2 View or report information

✤ Keep stakeholders and team members up-to-date on project progress by providing them with access to online or printed views and reports.

✤ Project 2010 provides many ways to print and distribute both detailed and overview information project information quickly and efficiently.

125

Page 126: Ms project 2010 level 1&2

6.3 Generate a report

✤ Click the Project tab, and then in the Reports group, click one of the following:

✤ Visual Reports Use visual reports to see your project’s data as a PivotTable report in Excel 2010 or a PivotDiagram view in Visio Professional 2010.

✤ Reports Use basic reports to see your project's data in tabular reports that don't require Excel or Visio. These basic reports are collected in categories for easy selecting and printing.

✤ Compare Projects Use a compare projects report to view a report that displays changes in the current project compared to another project.

126

Page 127: Ms project 2010 level 1&2

127

Displaying a Gantt Chart Graphic in a Web Page (1)

■ In Gantt chart view, click the copy icon on the clipboard

■ Select to GIF Image File option■ In the Timescales section, select the dates range , or

select as shown on screen to capture the timescale that is currently displayed on the screen

■ Click O.K■ Open File> Save As>XML and select a filename and

location. Click save

Page 128: Ms project 2010 level 1&2

6.4 Print a view or report

✤ Set up the current view the way that you want it to look when printed. Click the File tab, and then click Print. A preview of the view will be printed appears on the right.

✤ Tip Click in the preview part of the view to see the actual size of the view as it will be printed.

128

Page 129: Ms project 2010 level 1&2

129

Printing Gantt Charts

✤ In the File tab, select Print

✤ Select the printer to be used, and the number of copies

✤ Under the Settings heading, use the drop-down lists to chose the desired settings

✤ The layout settings may be changed by selecting the required layout by clicking on the icons on the bottom right of the screen

Page 130: Ms project 2010 level 1&2

1306.5 Creating new Reports✤ In the Project tab, click the Reports icon

✤ In the Reports window, double-click the Custom icon

✤ The Custom Reports Dialog box gives a few options:

✤ New, for a completely new report:

✤ Copy, for a copy of a selected report:

✤ Organizer, shares reports with other projects

Page 131: Ms project 2010 level 1&2

6.6 Create a final report

✤ Click the Project tab. In the Reports group, click Visual Reports to see your project’s data as a PivotTable report in Excel 2010 or a PivotDiagram view in Visio Professional 2010.

✤ You can also view basic reports that don’t require Excel or Visio. Click the Project tab, and in the Reports group, click Reports. Double-click a report category, and then double-click the predefined report. Enter any requested information. A preview of the report appears. To print the report, click Print.

131

Page 132: Ms project 2010 level 1&2

6.7 Save a project as a template

✤ AOercomple@ngaproject,youshouldleveragewhatyou’velearnedintheprojectbymakingitatemplateforfutureprojects.ClicktheFiletab,clickSaveAs,andthenintheSaveAsTypebox,clickTemplate.

132

Page 133: Ms project 2010 level 1&2

6.8 Close the project✤ Justbecauseyourprojectisalmostfinisheddoesn’tmean

thatyourworkisdone.✤ Yous@llneedtoresolveanyfinalprojectdetailsandobtain

customeracceptanceoffinaldeliverables.✤ Conducta“lessonslearned”session,recording

informa@onaboutareasforimprovementandbestprac@ces.

✤ Makeanyfinalupdatestotheprojectplan.✤ Finally,archivetheprojectplanaccordingtoyour

organiza@on’sguidelines.

133

Page 134: Ms project 2010 level 1&2

Check your knowledge

Exercise 5.4

134

Page 135: Ms project 2010 level 1&2

135