Form No: Statement Rev. No: 00 Date: 10/10/2004 Document No: QM No. of Pages 2 SCOPE: THIS METHOD STATEMENT WILL COVER ALL PLASTER WORKS FOR BUILDINGS BASED ON CONTRACT SPECIFICATIONS. PROCEDURE: 1) CIVILCO SHALL MAKE A MOCK UP SAMPLE FOR INTERNAL AND EXTERNAL PLASTER . THIS MOCK UP WALL IN CASE OF APPROVAL SHALL REMAIN AS A PART OF COMPLETED WORK. 2) CIVILCO SHALL USE PLASTER MIX . 3) MIXING WILL BE DONE MECHANICALY. 4) CIVILCO SALL ASSURE THAT ALL ARCHITECTURAL , MECHANICAL AND ELECTRICAL TRADES ON THE WALL ARE COMPLETED AND THE AREA TO BE PLASTERED IS NOT EXCESSIVELY MOIST 5) FIX METAL LATH FOR ALL JOINTS BETWEEN DIFFERENT SUBSTRATES AND ACROSS CHASES AS REQUIRED. 6) INSTALL PLASTER STOPS USING SQUARE NOSED BEADS BETWEEN THE VERTICAL PLASTERED SURFACES AND MARBLE SKIRTING(CONCEALED) METHOD STATEMENT FOR PLASTER WORKS

Upload: engr-muhammad-sohail

Post on 16-Sep-2015

217 views

Category:

Documents


3 download

DESCRIPTION

good

TRANSCRIPT

Form No: StatementRev. No: 00

Date: 10/10/2004Document No: QM

No. of Pages 2

SCOPE:

THIS METHOD STATEMENT WILL COVER ALL PLASTER WORKS FOR BUILDINGS BASED ON CONTRACT SPECIFICATIONS.

PROCEDURE:

1) CIVILCO SHALL MAKE A MOCK UP SAMPLE FOR INTERNAL AND EXTERNAL PLASTER . THIS MOCK UP WALL IN CASE OF APPROVAL SHALL REMAIN AS A PART OF COMPLETED WORK.2) CIVILCO SHALL USE PLASTER MIX .3) MIXING WILL BE DONE MECHANICALY.4) CIVILCO SALL ASSURE THAT ALL ARCHITECTURAL , MECHANICAL AND ELECTRICAL TRADES ON THE WALL ARE COMPLETED AND THE AREA TO BE PLASTERED IS NOT EXCESSIVELY MOIST

5) FIX METAL LATH FOR ALL JOINTS BETWEEN DIFFERENT SUBSTRATES AND ACROSS CHASES AS REQUIRED.6) INSTALL PLASTER STOPS USING SQUARE NOSED BEADS BETWEEN THE VERTICAL PLASTERED SURFACES AND MARBLE SKIRTING(CONCEALED)7) INSTALL CORNER BEADS TO VERTICAL ANGLES OF PLASTER.

8) CIVILCO SHALL MAKE INSPECTION FOR ALL PREPARATONS TO APPROVE THE APPLICATION OF THE FIRST COAT OF PLASTER.

9) APPLY FIRST COAT TO BASE MATERIAL WITH SUFFICIENT MATERIAL AND PRESSURE TO FORM COAT AT LEAST 9mm THICK.10) APPLY FIRST COAT WHICH WILL BE SCRATCHED HORIZONTALLY TO PROVIDE MECHANICAL KEY.11) IN CASE OF DELAYING THE SECOND COAT, THEN THE FIRST COAT SHALL BE KEPT MOIST FOR A MINIMUM OF 48HRS AFTER APPLICATION.12) THE FINISHING COAT WILL BE APPLIED AFTER THE FIRST COAT HAS SET UP .

13) START FILLING BETWEEN DAUBS TO BRING ALL TO A UNIFORM LEVEL OF 3mm FROM THE PROPOSED PLASTER FINISHED FACE .

14) SECOND COAT SHALL BE BROUGHT TO A TRUE, EVEN PLANE, THERE AFTER, MAKE-READY TO RECEIVE THE FINISH COAT BY SCRATCHING WIRE BRUSH .

15) SECOND COAT SHALL BE LEFT TO DRY FOR A MINIMUM OF 5 DAYS AFTER MOIST CURING OF 48HRS.

16) THE INTERNAL WALL PLASTER SHALL BE TROWELLED TO SMOOTH FINISH, FREE OF SURFACE BLEMISHES.

17) CIVILCO AND CONSULTANT SHALL MAKE FINAL JOINT INSPECTION FOR APPROVAL .

METHOD STATEMENT FOR PLASTER WORKS